Roof heat preservation waterproof construction method and building structure thereof

By setting up waterproof layer, insulation layer, air collection channel and exhaust pipe on the upper part of the roof, combined with inverted and formal construction methods, the problems of waterproof layer aging and moisture evaporation of the insulation layer caused by plant root puncture are solved, and the roof waterproofing and Insulation performance.

CN118997403APending Publication Date: 2024-11-22XINGLUO CONSTR CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202411359174.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-27
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

During the construction process, the inverted construction method should not be used, which will cause the waterproof layer to be exposed to high temperature and ultraviolet light, and the aging will accelerate. The water storage property of the planting layer will cause the water evaporation inside the insulation layer, increasing the waterproof layer. Pressure, reduce the insulation effect.

Method used

The leveling layer is cast by a ground pump, the first waterproof layer is laid, the insulation layer is overlapped in the staggered joints, the air-collection channel and exhaust pipe are reserved, the exhaust mechanism is installed, the root-resistant puncture-resistant waterproof layer and protective layer are laid, combined with inverted and positive The advantages of a built-in roof are that air-collection channels are reserved through the hose core extraction, reducing construction difficulty and cost.

Benefits of technology

Effectively avoid root puncture, improve the service life and performance of waterproof and thermal insulation structures, reduce engineering costs, avoid pipe aging and damage, and improve overall waterproof performance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118997403A_ABST
    Figure CN118997403A_ABST
Patent Text Reader

Abstract

The invention discloses a roof heat-preservation waterproof construction method and a building structure thereof, and relates to the technical field of roof heat-preservation waterproof construction.The building structure comprises a roof body, a leveling layer is poured on the surface of the roof body through a ground pump, and a first waterproof layer is laid on the upper portion of the leveling layer. According to the roof structure, the root-puncture-resistant waterproof layer is installed on the lower portion of the protective layer, the root of a plant can be effectively prevented from penetrating downwards, the second waterproof layer is protected, and the roof body is subjected to two waterproof protections through the root-puncture-resistant waterproof layer and the second waterproof layer; meanwhile, an air collecting hole channel and an exhaust pipe which are installed in the heat preservation layer can discharge moisture absorbed in the heat preservation layer, the moisture in the heat preservation layer is prevented from damaging the waterproof layer, then the first waterproof layer is installed on the lower portion of the heat preservation layer, and the upper portion of the roof body is combined with the advantages of an inverted roof and an upright roof; therefore, the service life and the performance of the waterproof and heat-insulating structure of the roof main body are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of roof thermal insulation and waterproofing construction, in particular to a roof thermal insulation and waterproofing construction method and a building structure thereof. Background Art

[0002] Roof insulation and waterproofing is an important project in the construction process. It involves two main aspects: roof insulation and waterproofing. Roof insulation mainly uses thermal insulation materials to reduce the loss of indoor temperature, while waterproofing uses waterproof materials to prevent rainwater from penetrating into the room. These two tasks work together to significantly improve the energy efficiency of buildings and the comfort of the living environment.

[0003] For example, announcement number: CN113431270B discloses "a roof waterproof and heat-insulating structure and its construction method", which includes a main body, a sidewalk and a planting layer arranged on both sides of the sidewalk are laid on the main body, the sidewalk is provided with a drainage pipe, a water collection pipe is buried on the side of the planting layer close to the main body, and the water collection pipe is provided with a water inlet; a water retaining plate is inserted between the sidewalk and the planting layer, a drainage cavity is provided in the water retaining plate, and a drainage port connected to the drainage cavity is provided on the side of the water retaining plate close to the sidewalk; the drainage pipe is connected to the drainage cavity, a connecting pipe is provided in the sidewalk, one end of the connecting pipe is connected to the drainage cavity, and the other end is connected to the drainage pipe; the construction method comprises: laying a leveling layer, a waterproof layer, a slope layer, a thermal insulation layer and an isolation layer on the reinforced concrete roof panel; installing the drainage pipe and the water retaining plate; laying on the isolation layer; laying the planting layer.

[0004] However, in the prior art, roofs can be divided into walkable roofs and non-walkable roofs according to whether they are accessible to people, and can be divided into sloping roofs and flat roofs according to structural characteristics. As people have higher and higher requirements for quality of life and the pursuit of green buildings, many flat roof buildings for people to walk on will plant some green plants on the roofs. The building roofs planted with green plants are called planted roofs. Although planted roofs have the advantages of improving the quality of citizens' living and working environment, improving urban heat island effect, reducing urban drainage load, purifying the air, and improving the utilization rate of land resources, due to the piercing effect of plant roots, the roof should not be constructed using the inverted roof construction method, resulting in the need to construct the waterproof layer according to the construction method of the upright roof during the construction process. The method is installed on the upper part of the insulation layer, causing the waterproof layer to be exposed on the upper layer, which is easily affected by factors such as high temperature and ultraviolet rays, accelerating its aging and cracking, and affecting the waterproof effect. In addition, in the prior art, although the problem that the planting layer of the planting roof cannot drain quickly is solved, since the planting layer is mainly composed of a matrix layer, the matrix layer has a certain water storage capacity and water retention, causing the upper waterproof layer to be in a high-humidity environment for a long time, as time goes by, the insulation layer below the waterproof layer will also contain moisture. Under the action of high temperature, the moisture inside the insulation layer evaporates and cannot be discharged, which will cause the pressure on the lower part of the waterproof layer to increase, further accelerating the aging and cracking of the waterproof layer, and at the same time the overall thermal insulation effect of the water-containing insulation layer will decrease. Summary of the invention

[0005] The object of the present invention is to provide a roof insulation and waterproof construction method and its building structure, so as to solve the problem proposed in the above background technology that due to the piercing effect of plant roots, the roof should not adopt an inverted roof construction method, resulting in the need to install the waterproof layer on the upper part of the insulation layer according to the upright roof construction method during the construction process, causing the waterproof layer to be exposed to the upper layer, which is easily affected by factors such as high temperature and ultraviolet rays, accelerating its aging and cracking, and affecting the waterproof effect. In the prior art, since the planting layer is mainly composed of a matrix layer, the matrix layer has a certain water storage capacity and water retention, causing the upper waterproof layer to be in a high-humidity environment for a long time, the water inside the insulation layer evaporates and cannot be discharged, which will cause the pressure on the lower part of the waterproof layer to increase, further accelerating the aging and cracking of the waterproof layer, and at the same time the overall thermal insulation effect of the water-containing insulation layer will decrease.

[0006] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a roof insulation and waterproof building structure, comprising a roof body, a leveling layer cast on the surface of the roof body by a ground pump, a first waterproof layer paved on the top of the leveling layer, a thermal insulation layer paved on the top of the first waterproof layer by staggered overlap, a slope layer cast on the top of the thermal insulation layer, an air collecting duct reserved inside the slope layer, an exhaust pipe installed on the top of the air collecting duct, an exhaust mechanism fixedly connected to the top of the exhaust pipe, the exhaust mechanism being used to speed up the flow speed of air inside the air collecting duct, a second waterproof layer paved on the top of the slope layer, a root penetration resistant waterproof layer paved on the top of the second waterproof layer, a protective layer cast on the top of the root penetration resistant waterproof layer, a drainage duct paved on the top of the protective layer A filter layer is laid on the drainage layer, a planting layer is laid on the filter layer, a parapet is cast on the edge of the roof body, and an equipment room is built on the roof body. The first waterproof layer and the second waterproof layer are both provided with additional layers at the connection with the wall foot, parapet, air collecting duct and drain outlet of the equipment room. The additional layer of the first waterproof layer is bonded to the wall foot, parapet, exhaust pipe and air collecting duct installation position and the connection of the drain outlet of the equipment room. The additional layer of the second waterproof layer is bonded to the additional layer of the first waterproof layer. Pressing plates are installed at the side positions of the parapet and the wall foot of the equipment room. The pressing plates are respectively fixed to the parapet and the side of the wall foot of the equipment room by fixing anchor nails. The upper parts of the additional layers of the first waterproof layer and the second waterproof layer are bonded with sealant.

[0007] A roof insulation and waterproofing construction method comprises the following steps:

[0008] S1. Construction of the first waterproof structure: including roof treatment, the first roof water-tightness test, leveling layer construction, the first waterproof layer construction and the second roof water-tightness test;

[0009] The roof treatment includes cleaning and roughening the upper surface of the roof body, witnessing the sampling of waterproof materials and thermal insulation materials for waterproof and thermal insulation construction, retesting the sampled materials, registering and storing the materials that pass the retest, and registering and taking materials in the subsequent construction process;

[0010] The first roof water-tightness test: a water-tightness test is performed on the upper part of the roof body;

[0011] The leveling layer construction: pouring the leveling layer on the upper part of the roof body;

[0012] The first waterproof layer is constructed by laying the first waterproof layer on the top of the leveling layer;

[0013] The second roof water-tightness test: a water-tightness test is performed on the installed first waterproof layer;

[0014] S2. Insulation structure construction: including insulation layer construction, slope layer construction and exhaust pipe construction;

[0015] The insulation layer construction: laying the insulation layer on the first waterproof layer;

[0016] The slope layer construction: reserve gas collection ducts on the upper part of the insulation layer, and then pour the slope layer;

[0017] The construction of the reserved gas collection channel includes the following steps:

[0018] S21, firstly, a rubber hose is laid on the upper part of the insulation layer, then air is inflated into the rubber hose, and finally, a slope leveling layer is poured;

[0019] S22. After the strength of the slope layer reaches 0.4-0.8MPa, the hose is deflated and the hose is pulled out to form a gas collecting channel;

[0020] The exhaust pipe construction: exhaust pipes are installed at both ends of the gas collecting channel.

[0021] S3, Second waterproof structure construction: including the second waterproof layer construction, root penetration resistant waterproof layer construction and the third roof water-tightness test;

[0022] The second waterproof layer construction: installing the second waterproof layer on the top of the slope layer, the root penetration resistant waterproof layer construction and the protective layer construction;

[0023] The root puncture resistant waterproof layer is constructed by laying the root puncture resistant waterproof layer on the upper part of the second waterproof layer;

[0024] The third roof water-tightness test: a water-tightness test is performed on the installed second waterproof layer and the root penetration-resistant waterproof layer;

[0025] The protective layer construction includes pouring the protective layer on the upper part of the root penetration resistant waterproof layer;

[0026] S4. Planting structure construction: including drainage layer construction, filtration layer construction and planting layer construction;

[0027] The drainage layer construction: laying the drainage layer on the upper part of the protective layer;

[0028] The filter layer construction: laying the filter layer on the upper part of the drainage layer;

[0029] The planting layer construction: laying the planting layer on the top of the filtering layer.

[0030] Preferably, in step S1, the cleaning of the upper surface of the roof body comprises the following steps:

[0031] S11. Clean up the building materials and dust piled on the main part of the roof;

[0032] S12, chiseling away and cleaning the loose stones on the surface of the main roof;

[0033] S13. Clean the oil stains attached to the main surface of the roof;

[0034] S14, roughening the main surface of the roof.

[0035] Preferably, in step S12, the step of chiseling and cleaning the loose stones on the surface of the roof body comprises the following steps:

[0036] S121. Processing the quality defects on the surface of the main roof, wherein the quality defects include holes, honeycombs, and pockmarks with a diameter or side length greater than 0.5 mm, and cleaning the concrete at the location of the quality defects on the main roof by chiseling;

[0037] S122. Wet the chiseled and cleaned areas of the roof body and repair the chiseled areas with waterproof mortar or micro-expansion anti-seepage mortar.

[0038] Preferably, in step S1, the leveling layer is made of anti-seepage mortar, and the casting thickness of the leveling layer is 15-20 mm.

[0039] Preferably, in step S1, laying the first waterproof layer on the top of the leveling layer comprises the following steps:

[0040] S15, testing the moisture content of the leveling layer, when the first waterproof layer is installed, the moisture content of the leveling layer is less than 9%;

[0041] S16. Mark the upper part of the leveling layer: mark the edge line of the waterproof membrane and the edge line of the additional waterproof layer, and reserve an overlap edge greater than 100mm;

[0042] S17. First lay the additional waterproof layer, then spray the base treatment agent on the surface of the leveling layer, and then lay the waterproof membrane.

[0043] Preferably, in step S2, the insulation layer adopts one of EPS insulation board, XPS insulation board, polyurethane insulation board or rock wool insulation board.

[0044] Preferably, in step S2, pouring the slope layer on the upper part of the insulation layer comprises the following steps:

[0045] S21, determine the distance from the slope starting point to the drainage point, and perform the slope line laying operation;

[0046] S22. Carry out the first pouring according to the thickness of the thinnest part, and pour in layers and batches towards the highest point.

[0047] Preferably, in step S2, the construction of reserving gas collection channels on the upper part of the insulation layer includes the following steps:

[0048] S23, the horizontal and vertical spacings of the hoses arranged on the upper part of the insulation layer are not greater than 6m;

[0049] S24, the gas collecting channels are interconnected at the positions where the transverse and longitudinal intersections are located by using a three-way pipe or a four-way pipe;

[0050] S25. The gas collecting ducts form a gas collecting network on the upper part of the insulation layer. The four sides of the gas collecting network are 30-50 cm away from the side of the parapet. Exhaust pipes are installed on the upper part of the four sides of the gas collecting network, and an exhaust mechanism is installed on the upper part of the exhaust pipes.

[0051] Preferably, the exhaust mechanism adopts one of an unpowered roof fan or a ventilation fan.

[0052] Compared with the prior art, the present invention has the following beneficial effects:

[0053] 1. In the present invention, by installing a root-penetration-resistant waterproof layer under the protective layer, the roots of plants can be effectively prevented from penetrating downward, and the second waterproof layer can be protected. The root-penetration-resistant waterproof layer and the second waterproof layer provide two waterproof protections for the roof body. At the same time, the air collecting duct and the exhaust pipe installed inside the insulation layer can discharge the moisture absorbed inside the insulation layer, thereby preventing the moisture inside the insulation layer from damaging the waterproof layer. Then, the first waterproof layer is installed under the insulation layer, so that the upper part of the roof body combines the advantages of the inverted roof and the upright roof, thereby improving the service life and performance of the waterproof and thermal insulation structure of the roof body;

[0054] 2. In the present invention, by adopting the construction method of core pulling with a hose to reserve the air collection channel, it is possible to avoid grooving on the upper part of the slope layer, thereby improving the integrity and flatness of the slope layer, and thus reducing the construction difficulty of the upper process, so that the waterproof structure on the upper part of the slope layer can be better laid on the roof body, thereby improving the waterproof performance. By reserving the air collection channel by the construction method of core pulling with a hose, it is no longer necessary to lay pipelines, which can reduce the project cost, and at the same time, it can also avoid the problem of poor air flow caused by aging and damage of pipelines inside the slope layer;

[0055] 3. In the present invention, the first waterproof layer and the additional layer of the second waterproof layer are pressed and fixed by a pressing plate, and then the joints between the additional layer and the wall and the structure are sealed again by a sealant to improve the overall waterproof performance. The air flow speed in the exhaust pipe and the air collecting duct is accelerated by the exhaust mechanism, thereby increasing the exhaust distance of the air collecting duct and the exhaust pipe, so that it is not necessary to set an exhaust pipe in an area of ​​no more than 36 square meters on the upper part of the roof body as stipulated in the roof waterproofing and thermal insulation engineering design specifications. The exhaust pipes can all be set on the side of the parapet, reducing the interference of the exhaust pipe arrangement position on other structural positions of the roof, especially avoiding the exhaust pipe position from affecting the planting position of green plants on the upper part of the roof. BRIEF DESCRIPTION OF THE DRAWINGS

[0056] Figure 1 It is a process flow chart of a roof thermal insulation and waterproofing construction method of the present invention;

[0057] Figure 2 It is a cross-sectional structural schematic diagram of a roof thermal insulation and waterproofing construction method of the present invention;

[0058] Figure 3 for Figure 2 Enlarged structural diagram at A in the middle.

[0059] In the figure: 1. Roof body; 2. Leveling layer; 3. First waterproof layer; 4. Insulation layer; 5. Slope layer; 6. Second waterproof layer; 7. Root penetration resistant waterproof layer; 8. Protective layer; 9. Drainage layer; 10. Filter layer; 11. Planting layer; 12. Parapet; 13. Air collecting duct; 14. Exhaust pipe; 15. Exhaust mechanism; 16. Pressure plate; 17. Fixed anchor nails; 18. Sealant. DETAILED DESCRIPTION

[0060] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the implementation regulations described are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0061] Example 1: Reference Figure 1-Figure 3 As shown: A roof insulation and waterproofing construction method, comprising the following steps:

[0062] Step 1: Construction of the first waterproof structure: including roof treatment, the first roof water-tightness test, construction of the leveling layer 2, construction of the first waterproof layer 3 and the second roof water-tightness test;

[0063] Roof treatment: clean and roughen the upper surface of the roof main body 1, witness sampling of waterproof materials and thermal insulation materials for waterproof and thermal insulation construction, retest the sampled materials, register and store the materials with qualified retest quality, and register and take materials in the subsequent construction process; clean the upper surface of the roof main body 1, including cleaning the building materials and dust piled on the upper part of the roof main body 1, chiseling and cleaning the loose stones on the surface of the roof main body 1, cleaning the oil stains attached to the surface of the roof main body 1, and roughening the surface of the roof main body 1;

[0064] Chisel away and clean the loose stones on the surface of the roof body 1, including processing the quality defects on the surface of the roof body 1, the quality defects include holes, honeycombs, and pockmarks with a diameter or side length greater than 0.5 mm, chisel away and clean the concrete at the quality defect position of the roof body 1, wet the chiseled and cleaned position of the roof body 1, and use waterproof mortar or micro-expansion anti-seepage to repair the chiseled position, and use anti-seepage mortar for the leveling layer 2, and the pouring thickness of the leveling layer 2 is 15-20 mm;

[0065] The first roof water-tightness test: a water-tightness test is conducted on the upper part of the roof body 1. After confirming that the roof body 1 has no water leakage through the water-tightness test, the leveling layer 1 is constructed. The leveling layer 2 is poured on the upper part of the roof body 1 using a floor pump, and then the first waterproof layer 3 is constructed: the first waterproof layer 3 is paved and installed on the upper part of the leveling layer 2; the first waterproof layer 3 is paved on the upper part of the leveling layer 2, including testing the moisture content of the leveling layer 2. When installing the first waterproof layer 3, the moisture content of the leveling layer 2 is less than 9%. Line drawing is conducted on the upper part of the leveling layer 2: the laying edge line of the waterproof membrane and the edge line of the waterproof additional layer are drawn, and the overlapping edge line is reserved to be greater than 100mm. The waterproof additional layer is first laid, and then the base treatment agent is sprayed on the surface of the leveling layer 2, and then the waterproof membrane is laid;

[0066] Second roof water-tightness test: Carry out a water-tightness test on the installed first waterproof layer 3. After confirming through the water-tightness test that there is no water leakage in the construction link of the first waterproof layer 3, proceed to the next construction process.

[0067] Step 2: Insulation structure construction: including insulation layer 4 construction, slope layer 5 construction and exhaust pipe 14 construction;

[0068] Construction of thermal insulation layer 4: laying thermal insulation layer 4 on the top of first waterproof layer 3, construction of slope layer 5: construction of reserved gas collecting channel 13 on the top of thermal insulation layer 4, and then pouring slope layer 5, construction of reserved gas collecting channel 13 includes first laying out rubber hose on the top of thermal insulation layer 4, and then inflating inside of rubber hose, and finally pouring slope layer 5, after the strength of slope layer 5 reaches 0.4-0.8MPa, deflate the rubber hose, and pull out the rubber hose to form gas collecting channel 13, construction of reserved gas collecting channel 13 on the top of thermal insulation layer 4, including laying out rubber hose on the top of thermal insulation layer 4 with lateral and longitudinal spacing of no more than 6, gas collecting channel 13 is interconnected with tee or cross pipe at the position where lateral and longitudinal intersection is formed, pouring slope layer 5 on the top of thermal insulation layer 4, including determining the distance from the starting point of slope to the drainage point, laying out the slope line, pouring for the first time according to the thickness of the thinnest part, and pouring to the highest point in layers and stages;

[0069] Construction of exhaust pipe 14: exhaust pipe 14 is installed at both ends of the gas collecting duct 13, the insulation layer 4 adopts one of EPS insulation board, XPS insulation board, polyurethane insulation board or rock wool insulation board, and the gas collecting duct 13 forms a gas collecting network on the upper part of the insulation layer 4. The four sides of the gas collecting network are 30-50cm away from the side of the parapet 12, and exhaust pipes 14 are installed on the upper part of the four sides of the gas collecting network. An exhaust mechanism 15 is installed on the upper part of the exhaust pipe 14, and the exhaust mechanism 15 adopts one of a non-powered roof fan or a ventilation fan.

[0070] Step three, construction of the second waterproof structure: including construction of the second waterproof layer 6, construction of the root penetration resistant waterproof layer 7 and the third roof water-tightness test, construction of the second waterproof layer 6: installation of the second waterproof layer 6, construction of the root penetration resistant waterproof layer 7 and construction of the protective layer 8 on the upper part of the slope leveling layer 5, construction of the root penetration resistant waterproof layer 7: laying the root penetration resistant waterproof layer 7 on the upper part of the second waterproof layer 6, the third roof water-tightness test: conducting a water-tightness test on the installed second waterproof layer 6 and the root penetration resistant waterproof layer 7, and constructing the protective layer 8 after confirming through the water-tightness test that there is no water leakage in the second waterproof layer 6 and the root penetration resistant waterproof layer 7, construction of the protective layer 8: pouring the protective layer 8 on the upper part of the root penetration resistant waterproof layer 7.

[0071] Step 4, planting structure construction: including the construction of drainage layer 9, the construction of filtration layer 10 and the construction of planting layer 11; construction of drainage layer 9: laying drainage layer 9 on the top of protective layer 8, construction of filtration layer 10: laying filtration layer 10 on the top of drainage layer 9, construction of planting layer 11: laying planting layer 11 on the top of filtration layer 10.

[0072] The roof construction method of Example 1 and the traditional upright roof construction method were used to build proportionally reduced roof models for artificial climate accelerated aging tests, and the data of the number of leaks per square meter were compared:

[0073] Experimental principle: artificial methods are used to simulate and strengthen the environmental factors that the roof is exposed to in the natural climate, such as light, heat, oxygen, moisture, and rainfall, which are the main aging and damaging factors;

[0074] Experimental equipment: test chamber, xenon arc lamp with daylight filter, humidification equipment, spraying equipment, heating equipment, oxygen generator and oxygen controller.

[0075] The exposure environmental conditions are as follows:

[0076]

[0077] Table 1 Comparison of the number of leaks measured by closed water test after artificial climate accelerated aging test of roof models built by two construction methods

[0078]

[0079] Example 2: Reference Figure 1-Figure 3 As shown: A roof insulation and waterproofing construction method, comprising the following steps:

[0080] Step 1: Construction of the first waterproof structure: including roof treatment, the first roof water-tightness test, construction of the leveling layer 2, construction of the first waterproof layer 3 and the second roof water-tightness test;

[0081] Roof treatment: clean and roughen the upper surface of the roof main body 1, witness sampling of waterproof materials and thermal insulation materials for waterproof and thermal insulation construction, retest the sampled materials, register and store the materials with qualified retest quality, and register and take materials in the subsequent construction process; clean the upper surface of the roof main body 1, including cleaning the building materials and dust piled on the upper part of the roof main body 1, chiseling and cleaning the loose stones on the surface of the roof main body 1, cleaning the oil stains attached to the surface of the roof main body 1, and roughening the surface of the roof main body 1;

[0082] Chisel away and clean the loose stones on the surface of the roof body 1, including processing the quality defects on the surface of the roof body 1, the quality defects include holes, honeycombs, and pockmarks with a diameter or side length greater than 0.5 mm, chisel away and clean the concrete at the quality defect position of the roof body 1, wet the chiseled and cleaned position of the roof body 1, and use waterproof mortar or micro-expansion anti-seepage to repair the chiseled position, and use anti-seepage mortar for the leveling layer 2, and the pouring thickness of the leveling layer 2 is 15-20 mm;

[0083] The first roof water-tightness test: a water-tightness test is carried out on the upper part of the roof main body 1. After confirming that there is no water leakage in the roof main body 1 through the water-tightness test, the leveling layer 1 is constructed, and the leveling layer 2 is poured on the upper part of the roof main body 1 using a floor pump.

[0084] Step 2: Insulation structure construction: including insulation layer 4 construction, slope layer 5 construction and exhaust pipe 14 construction;

[0085] Construction of thermal insulation layer 4: laying thermal insulation layer 4 on the top of first waterproof layer 3, construction of slope layer 5: construction of reserved gas collecting channel 13 on the top of thermal insulation layer 4, and then pouring slope layer 5, construction of reserved gas collecting channel 13 includes first laying out rubber hose on the top of thermal insulation layer 4, and then inflating inside of rubber hose, and finally pouring slope layer 5, after the strength of slope layer 5 reaches 0.4-0.8MPa, deflate the rubber hose, and pull out the rubber hose to form gas collecting channel 13, construction of reserved gas collecting channel 13 on the top of thermal insulation layer 4, including laying out rubber hose on the top of thermal insulation layer 4 with lateral and longitudinal spacing of no more than 6, gas collecting channel 13 is interconnected with tee or cross pipe at the position where lateral and longitudinal intersection is formed, pouring slope layer 5 on the top of thermal insulation layer 4, including determining the distance from the starting point of slope to the drainage point, laying out the slope line, pouring for the first time according to the thickness of the thinnest part, and pouring to the highest point in layers and stages;

[0086] Construction of exhaust pipe 14: exhaust pipe 14 is installed at both ends of the gas collecting duct 13, the insulation layer 4 adopts one of EPS insulation board, XPS insulation board, polyurethane insulation board or rock wool insulation board, and the gas collecting duct 13 forms a gas collecting network on the upper part of the insulation layer 4. The four sides of the gas collecting network are 30-50cm away from the side of the parapet 12, and exhaust pipes 14 are installed on the upper part of the four sides of the gas collecting network. An exhaust mechanism 15 is installed on the upper part of the exhaust pipe 14, and the exhaust mechanism 15 adopts one of a non-powered roof fan or a ventilation fan.

[0087] Step three, construction of the second waterproof structure: including construction of the second waterproof layer 6, construction of the root penetration resistant waterproof layer 7 and the third roof water-tightness test, construction of the second waterproof layer 6: installation of the second waterproof layer 6, construction of the root penetration resistant waterproof layer 7 and construction of the protective layer 8 on the upper part of the slope leveling layer 5, construction of the root penetration resistant waterproof layer 7: laying the root penetration resistant waterproof layer 7 on the upper part of the second waterproof layer 6, the third roof water-tightness test: conducting a water-tightness test on the installed second waterproof layer 6 and the root penetration resistant waterproof layer 7, and constructing the protective layer 8 after confirming through the water-tightness test that there is no water leakage in the second waterproof layer 6 and the root penetration resistant waterproof layer 7, construction of the protective layer 8: pouring the protective layer 8 on the upper part of the root penetration resistant waterproof layer 7.

[0088] Step 4, planting structure construction: including the construction of drainage layer 9, the construction of filtration layer 10 and the construction of planting layer 11; construction of drainage layer 9: laying drainage layer 9 on the top of protective layer 8, construction of filtration layer 10: laying filtration layer 10 on the top of drainage layer 9, construction of planting layer 11: laying planting layer 11 on the top of filtration layer 10.

[0089] The roof construction method of Example 1 and the roof construction method of Example 2 were used to build proportionally reduced roof models for artificial climate accelerated aging tests, and the data of the number of leaking points per square meter were compared:

[0090] The experimental method and test parameters of the artificial climate accelerated aging test are the same as those in Example 1.

[0091] Table 2 Comparison of the number of leaks measured by closed water test after artificial climate accelerated aging test on roof models built by two construction methods

[0092]

[0093] Example 3: Reference Figure 1-Figure 3 As shown: A roof insulation and waterproofing construction method, comprising the following steps:

[0094] Step 1: Construction of the first waterproof structure: including roof treatment, the first roof water-tightness test, construction of the leveling layer 2, construction of the first waterproof layer 3 and the second roof water-tightness test;

[0095] Roof treatment: clean and roughen the upper surface of the roof main body 1, witness sampling of waterproof materials and thermal insulation materials for waterproof and thermal insulation construction, retest the sampled materials, register and store the materials with qualified retest quality, and register and take materials in the subsequent construction process; clean the upper surface of the roof main body 1, including cleaning the building materials and dust piled on the upper part of the roof main body 1, chiseling and cleaning the loose stones on the surface of the roof main body 1, cleaning the oil stains attached to the surface of the roof main body 1, and roughening the surface of the roof main body 1;

[0096] Chisel away and clean the loose stones on the surface of the roof body 1, including processing the quality defects on the surface of the roof body 1, the quality defects include holes, honeycombs, and pockmarks with a diameter or side length greater than 0.5 mm, chisel away and clean the concrete at the quality defect position of the roof body 1, wet the chiseled and cleaned position of the roof body 1, and use waterproof mortar or micro-expansion anti-seepage to repair the chiseled position, and use anti-seepage mortar for the leveling layer 2, and the pouring thickness of the leveling layer 2 is 15-20 mm;

[0097] The first roof water-tightness test: a water-tightness test is conducted on the upper part of the roof body 1. After confirming that the roof body 1 has no water leakage through the water-tightness test, the leveling layer 1 is constructed. The leveling layer 2 is poured on the upper part of the roof body 1 using a floor pump, and then the first waterproof layer 3 is constructed: the first waterproof layer 3 is paved and installed on the upper part of the leveling layer 2; the first waterproof layer 3 is paved on the upper part of the leveling layer 2, including testing the moisture content of the leveling layer 2. When installing the first waterproof layer 3, the moisture content of the leveling layer 2 is less than 9%. Line drawing is conducted on the upper part of the leveling layer 2: the laying edge line of the waterproof membrane and the edge line of the waterproof additional layer are drawn, and the overlapping edge line is reserved to be greater than 100mm. The waterproof additional layer is first laid, and then the base treatment agent is sprayed on the surface of the leveling layer 2, and then the waterproof membrane is laid;

[0098] Second roof water-tightness test: Carry out a water-tightness test on the installed first waterproof layer 3. After confirming through the water-tightness test that there is no water leakage in the construction link of the first waterproof layer 3, proceed to the next construction process.

[0099] Step 2: Insulation structure construction: including insulation layer 4 construction and slope leveling layer 5 construction;

[0100] Construction of thermal insulation layer 4: Lay thermal insulation layer 4 on the first waterproof layer 3, pour slope layer 5 on the thermal insulation layer 4, including determining the distance from the slope starting point to the drainage point, laying out the slope line, pouring the first time according to the thickness of the thinnest part, and pouring in layers and stages towards the highest point;

[0101] The thermal insulation layer 4 is made of one of EPS thermal insulation board, XPS thermal insulation board, polyurethane thermal insulation board or rock wool thermal insulation board.

[0102] Step three, construction of the second waterproof structure: including construction of the second waterproof layer 6, construction of the root penetration resistant waterproof layer 7 and the third roof water-tightness test, construction of the second waterproof layer 6: installation of the second waterproof layer 6, construction of the root penetration resistant waterproof layer 7 and construction of the protective layer 8 on the upper part of the slope leveling layer 5, construction of the root penetration resistant waterproof layer 7: laying the root penetration resistant waterproof layer 7 on the upper part of the second waterproof layer 6, the third roof water-tightness test: conducting a water-tightness test on the installed second waterproof layer 6 and the root penetration resistant waterproof layer 7, and constructing the protective layer 8 after confirming through the water-tightness test that there is no water leakage in the second waterproof layer 6 and the root penetration resistant waterproof layer 7, construction of the protective layer 8: pouring the protective layer 8 on the upper part of the root penetration resistant waterproof layer 7.

[0103] Step 4, planting structure construction: including the construction of drainage layer 9, the construction of filtration layer 10 and the construction of planting layer 11; construction of drainage layer 9: laying drainage layer 9 on the top of protective layer 8, construction of filtration layer 10: laying filtration layer 10 on the top of drainage layer 9, construction of planting layer 11: laying planting layer 11 on the top of filtration layer 10.

[0104] The roof construction method of Example 1 and the roof construction method of Example 3 were used to build proportionally reduced roof models for artificial climate accelerated aging tests, and the data of the number of leaking points per square meter were compared:

[0105] The experimental method and test parameters of the artificial climate accelerated aging test are the same as those in Example 1.

[0106] Table 3 Comparison of data on the number of leaks measured by two construction methods

[0107]

[0108]

[0109] Example 4: Reference Figure 1-Figure 3 As shown: A roof insulation and waterproofing construction method, comprising the following steps:

[0110] Step 1: Construction of the first waterproof structure: including roof treatment, the first roof water-tightness test, construction of the leveling layer 2, construction of the first waterproof layer 3 and the second roof water-tightness test;

[0111] Roof treatment: clean and roughen the upper surface of the roof main body 1, witness sampling of waterproof materials and thermal insulation materials for waterproof and thermal insulation construction, retest the sampled materials, register and store the materials with qualified retest quality, and register and take materials in the subsequent construction process; clean the upper surface of the roof main body 1, including cleaning the building materials and dust piled on the upper part of the roof main body 1, chiseling and cleaning the loose stones on the surface of the roof main body 1, cleaning the oil stains attached to the surface of the roof main body 1, and roughening the surface of the roof main body 1;

[0112] Chisel away and clean the loose stones on the surface of the roof body 1, including processing the quality defects on the surface of the roof body 1, the quality defects include holes, honeycombs, and pockmarks with a diameter or side length greater than 0.5 mm, chisel away and clean the concrete at the quality defect position of the roof body 1, wet the chiseled and cleaned position of the roof body 1, and use waterproof mortar or micro-expansion anti-seepage to repair the chiseled position, and use anti-seepage mortar for the leveling layer 2, and the pouring thickness of the leveling layer 2 is 15-20 mm;

[0113] The first roof water-tightness test: a water-tightness test is carried out on the upper part of the roof main body 1. After confirming that there is no water leakage in the roof main body 1 through the water-tightness test, the leveling layer 1 is constructed, and the leveling layer 2 is poured on the upper part of the roof main body 1 using a floor pump.

[0114] Step 2: Insulation structure construction: including insulation layer 4 construction and slope leveling layer 5 construction;

[0115] Construction of thermal insulation layer 4: Lay thermal insulation layer 4 on the first waterproof layer 3, pour slope layer 5 on the thermal insulation layer 4, including determining the distance from the slope starting point to the drainage point, laying out the slope line, pouring the first time according to the thickness of the thinnest part, and pouring in layers and stages towards the highest point;

[0116] The thermal insulation layer 4 is made of one of EPS thermal insulation board, XPS thermal insulation board, polyurethane thermal insulation board or rock wool thermal insulation board.

[0117] Step three, construction of the second waterproof structure: including construction of the second waterproof layer 6, construction of the root penetration resistant waterproof layer 7 and the third roof water-tightness test, construction of the second waterproof layer 6: installation of the second waterproof layer 6, construction of the root penetration resistant waterproof layer 7 and construction of the protective layer 8 on the upper part of the slope leveling layer 5, construction of the root penetration resistant waterproof layer 7: laying the root penetration resistant waterproof layer 7 on the upper part of the second waterproof layer 6, the third roof water-tightness test: conducting a water-tightness test on the installed second waterproof layer 6 and the root penetration resistant waterproof layer 7, and constructing the protective layer 8 after confirming through the water-tightness test that there is no water leakage in the second waterproof layer 6 and the root penetration resistant waterproof layer 7, construction of the protective layer 8: pouring the protective layer 8 on the upper part of the root penetration resistant waterproof layer 7.

[0118] Step 4, planting structure construction: including the construction of drainage layer 9, the construction of filtration layer 10 and the construction of planting layer 11; construction of drainage layer 9: laying drainage layer 9 on the top of protective layer 8, construction of filtration layer 10: laying filtration layer 10 on the top of drainage layer 9, construction of planting layer 11: laying planting layer 11 on the top of filtration layer 10.

[0119] The roof construction method of Example 1 and the roof construction method of Example 4 were used to build proportionally reduced roof models for artificial climate accelerated aging tests, and the data of the number of leaking points per square meter were compared:

[0120] The experimental method and test parameters of the artificial climate accelerated aging test are the same as those in Example 1.

[0121] Table 4 Comparison of data on the number of leaks measured using two construction methods

[0122]

[0123] In the construction scheme of the first embodiment, by respectively arranging the first waterproof layer 3, the thermal insulation layer 4, the air collecting duct 13 and the exhaust pipe 14, the second waterproof layer 6 and the root puncture resistant waterproof layer 7 on the upper part of the roof body 1, the upper part of the roof body 1 has a multiple waterproof structure of the first waterproof layer 3, the second waterproof layer 6 and the root puncture resistant waterproof layer 7, so that the upper part of the roof body 1 is fully waterproof protected;

[0124] In the construction scheme of the second embodiment, the construction steps of the first waterproof layer 3 are reduced compared with the construction scheme of the first embodiment. In the construction scheme of the third embodiment, the construction steps of installing the gas collecting duct 13 and the exhaust pipe 14 in the thermal insulation layer 4 are reduced compared with the construction scheme of the first embodiment. In the construction scheme of the fourth embodiment, the first waterproof layer 3 and the construction steps of installing the gas collecting duct 13 and the exhaust pipe 14 in the thermal insulation layer 4 are reduced compared with the construction scheme of the first embodiment. By analyzing the relevant data in the tables of the above-mentioned embodiments one to four, it can be known that the roof construction method of the first embodiment is adopted, and the first waterproof layer 3, the second waterproof layer 6 and the root puncture-resistant waterproof layer 7 are respectively installed on the upper part of the roof body 1 to waterproof the upper part of the roof body 1. The root puncture-resistant waterproof layer 7 is used to prevent the roots of the upper green plants from penetrating downward to cause damage to the lower structure of the root puncture-resistant waterproof layer 7. The first waterproof layer 3 and the second waterproof layer 6 are used to prevent the roots of the upper green plants from penetrating downward to cause damage to the lower structure of the root puncture-resistant waterproof layer 7. Layer 6 performs double-layer waterproof protection on the upper part of the roof body 1, and the air collecting duct 13 and the exhaust pipe 14 are installed in the insulation layer 4 to ventilate and dry the insulation layer 4, so that the roof body 1 still does not leak after four weeks of accelerated aging in the accelerated aging test. Compared with the roof construction method of Example 2, the construction steps of the first waterproof layer 3 are reduced. The situation where 1 leaks in the third week and 2 leaks in the fourth week is a better construction scheme. Similarly, compared with the roof construction methods of Examples 3 and 4, the number of leaks is used as a reference. Example 1 is the best construction method for waterproofing the roof body 1. In the construction scheme of Example 1, the roof body 1 does not leak, indicating that the insulation layer in the construction scheme of Example 1 is in a dry state, and further indicates that the thermal insulation performance in the construction scheme of Example 1 is better than the construction schemes in other embodiments.

[0125] By analyzing the relevant data in the tables of Example 1 and Example 3, it can be seen that in the construction method of Example 3, after reducing the construction steps of the air collecting duct 13 and the exhaust pipe 14, the roof body 1 leaked in the third week of use, indicating that if the moisture in the insulation layer 4 is not discharged in time, it will have an adverse effect on the first waterproof layer 3 and the second waterproof layer 6.

[0126] Embodiment 5: Figure 2 and Figure 3As shown, a roof insulation and waterproof building structure comprises a roof body 1, a leveling layer 2 is cast on the surface of the roof body 1 by using a ground pump, a first waterproof layer 3 is laid on the top of the leveling layer 2, a thermal insulation layer 4 is laid on the top of the first waterproof layer 3 by using a staggered overlap method, a slope layer 5 is cast on the top of the thermal insulation layer 4, an air collecting duct 13 is reserved inside the slope layer 5, an exhaust pipe 14 is installed on the top of the air collecting duct 13, an exhaust mechanism 15 is fixedly connected to the top of the exhaust pipe 14, and the exhaust mechanism 15 is used to speed up the flow speed of the air inside the air collecting duct 13, a second waterproof layer 6 is laid on the top of the slope layer 5, a root puncture-resistant waterproof layer 7 is laid on the top of the second waterproof layer 6, a protective layer 8 is cast on the top of the root puncture-resistant waterproof layer 7, a drainage layer 9 is laid on the top of the protective layer 8, and a filter layer 1 is laid on the top of the drainage layer 9 0, a planting layer 11 is laid on the top of the filter layer 10, a parapet 12 is cast on the edge of the roof body 1, and an equipment room is built on the top of the roof body 1, and the first waterproof layer 3 and the second waterproof layer 6 are provided with additional layers at the connection between the foot of the equipment room, the parapet 12, the installation position of the exhaust pipe 14 and the air collecting duct 13, and the drain outlet, the additional layer of the first waterproof layer 3 is bonded to the foot of the equipment room, the parapet 12, the air collecting duct 13, and the connection of the drain outlet, the additional layer of the second waterproof layer 6 is bonded to the additional layer of the first waterproof layer 3, and a pressure plate 16 is installed at the side of the parapet 12 and the foot of the equipment room. The pressure plate 16 is fixed to the parapet 12 and the side of the foot of the equipment room by fixing anchor nails 17, and the upper part of the additional layer of the first waterproof layer 3 and the second waterproof layer 6 is bonded with a sealant 18.

[0127] The process flow of this construction method is as follows: by processing the roof body 1, the leveling layer 2 can be tightly and firmly connected to the roof body 1 to avoid gaps at the joints, which will affect the overall strength and impermeability. At the same time, before pouring the leveling layer 2, the roof body 1 is subjected to the first roof water-tightness test to promptly handle the leaking points, so as to avoid the leaking points of the roof body 1 being covered after the first waterproof layer 3 is laid, resulting in quality defects that cannot be discovered;

[0128] After the first waterproof layer 3 is paved, the second roof water-tightness test is carried out, the first waterproof layer 3 is tested, and after confirming that there is no water leakage in the first waterproof layer 3, the thermal insulation layer 4, the slope layer 5, the air collection channel 13 and the exhaust pipe 14 are constructed respectively, and then the second waterproof layer 6 and the root puncture-resistant waterproof layer 7 are constructed. After the thermal insulation and waterproofing project is completed, the sub-project pre-acceptance is carried out, and the third roof water-tightness test is carried out after the pre-acceptance is qualified. After the third roof water-tightness test is qualified, the construction of the protective layer 8, the drainage layer 9, the filter layer 10 and the planting layer 11 is carried out, and finally the sub-project acceptance is carried out;

[0129] By adopting the construction method of core pulling with a hose to reserve the gas collection channel 13, it is no longer necessary to use pipelines, thereby reducing construction costs and preventing the exhaust pipeline from aging and damage during use.

[0130] Although the present invention has been described in detail with reference to the aforementioned embodiments, it is still possible for those skilled in the art to modify the technical solutions described in the aforementioned embodiments, or to make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A roof insulation and waterproof building structure, comprising a roof body (1), a leveling layer (2) is cast on the surface of the roof body (1) by a ground pump, a first waterproof layer (3) is paved on the upper part of the leveling layer (2), and the characteristics are: The first waterproof layer (3) is paved with a thermal insulation layer (4) in a staggered overlapping manner, the thermal insulation layer (4) is cast with a slope leveling layer (5), an air collecting channel (13) is reserved inside the slope leveling layer (5), an exhaust pipe (14) is installed on the air collecting channel (13), an exhaust mechanism (15) is fixedly connected to the upper part of the exhaust pipe (14), and the exhaust mechanism (15) is used to accelerate the flow speed of air inside the air collecting channel (13), the slope leveling layer (5) is paved with a second waterproof layer (6), the second waterproof layer (6) is paved with a root puncture resistant waterproof layer (7), the root puncture resistant waterproof layer (7) is cast with a protective layer (8), the protective layer (8) is paved with a drainage layer (9), the drainage layer (9) is paved with a filter layer (10), the filter layer (10) is paved with a planting layer (11), and the roof A parapet (12) is cast at the edge of the main body (1), and an equipment room is built on the upper part of the roof main body (1). The first waterproof layer (3) and the second waterproof layer (6) are both provided with additional layers at the connection points with the wall foot, the parapet (12), the installation position of the exhaust pipe (14) and the gas collecting duct (13), and the drain outlet of the equipment room. The additional layer of the first waterproof layer (3) is bonded to the connection points with the wall foot, the parapet (12), the gas collecting duct (13), and the drain outlet of the equipment room. The additional layer of the second waterproof layer (6) is bonded to the additional layer of the first waterproof layer (3). A pressing plate (16) is installed at the side of the parapet (12) and the wall foot of the equipment room. The pressing plate (16) is respectively fixed to the parapet (12) and the side of the wall foot of the equipment room by fixing anchor nails (17). The upper parts of the additional layers of the first waterproof layer (3) and the second waterproof layer (6) are both bonded with sealant (18).

2. A roof insulation and waterproofing construction method, characterized in that: A roof insulation and waterproof building structure using claim 1 comprises the following steps: S1, first waterproof structure construction: including roof treatment, first roof water-tightness test, leveling layer (2) construction, first waterproof layer (3) construction and second roof water-tightness test; Roof treatment: Clean and roughen the upper surface of the main roof (1), and witness the sampling of waterproof and thermal insulation materials for waterproof and thermal insulation construction, and retest the sampled materials. The materials that pass the retest will be registered and stored, and registered and taken in the subsequent construction process; First roof water-tightness test: Carry out a water-tightness test on the upper part of the roof body (1); Construction of the leveling layer (2): pouring the leveling layer (2) on the upper part of the roof body (1); Construction of the first waterproof layer (3): laying the first waterproof layer (3) on the upper part of the leveling layer (2); Second roof water-tightness test: Carry out a water-tightness test on the installed first waterproof layer (3). S2, thermal insulation structure construction: including thermal insulation layer (4), slope leveling layer (5) and exhaust pipe (14) construction; Construction of the thermal insulation layer (4): laying the thermal insulation layer (4) on the upper part of the first waterproof layer (3); Construction of the slope layer (5): a reserved gas collecting channel (13) is constructed on the upper part of the thermal insulation layer (4), and then the slope layer (5) is poured; The construction of the reserved gas collection channel (13) includes the following steps: S21, firstly, laying a rubber hose on the upper part of the thermal insulation layer (4), then inflating the inside of the rubber hose, and finally pouring the slope layer (5); S22, after the strength of the slope layer (5) reaches 0.4-0.8 MPa, the hose is deflated and the hose is pulled out to form a gas collecting channel (13); Exhaust pipe (14) construction: Install the exhaust pipe (14) at both ends of the gas collecting channel (13); S3, construction of the second waterproof structure: including the construction of the second waterproof layer (6), the construction of the root penetration resistant waterproof layer (7) and the third roof water-tightness test; Construction of the second waterproof layer (6): installing the second waterproof layer (6) on the upper part of the slope leveling layer (5), construction of the root puncture resistant waterproof layer (7) and construction of the protective layer (8); Construction of the root puncture resistant waterproof layer (7): laying the root puncture resistant waterproof layer (7) on the upper part of the second waterproof layer (6); The third roof water-tightness test: a water-tightness test is performed on the installed second waterproof layer (6) and the root penetration-resistant waterproof layer (7); Construction of the protective layer (8): pouring the protective layer (8) on the upper part of the root-penetration-resistant waterproof layer (7). S4, planting structure construction: including the construction of drainage layer (9), filtration layer (10) and planting layer (11); Construction of drainage layer (9): laying drainage layer (9) on the upper part of protective layer (8); Construction of the filter layer (10): laying the filter layer (10) on the upper part of the drainage layer (9); Construction of the planting layer (11): The planting layer (11) is laid on the upper part of the filtering layer (10).

3. A roof insulation and waterproofing construction method according to claim 2, characterized in that: In step S1, the upper surface of the roof body (1) is cleaned, comprising the following steps: S11, cleaning the building materials and dust piled on the upper part of the roof body (1); S12, removing and cleaning the loose stones on the surface of the roof body (1); S13, cleaning the oil stains attached to the surface of the roof body (1); S14, roughening the surface of the roof body (1).

4. A roof insulation and waterproofing construction method according to claim 2, characterized in that: In step S12, the loose stones on the surface of the roof body (1) are removed and cleaned, which includes the following steps: S121, treating the quality defects existing on the surface of the roof body (1), wherein the quality defects include holes, honeycombs, and rough surfaces with a diameter or side length greater than 0.5 mm, and cleaning the concrete at the locations of the quality defects of the roof body (1) by chiseling; S122, wetting the chiseled and cleaned parts of the roof main body (1), and repairing the chiseled parts with waterproof mortar or micro-expansion anti-seepage mortar.

5. A roof insulation and waterproofing construction method according to claim 2, characterized in that: In step S1, the leveling layer (2) is made of anti-seepage mortar, and the pouring thickness of the leveling layer (2) is 15-20 mm.

6. A roof insulation and waterproofing construction method according to claim 1, characterized in that: In step S1, laying the first waterproof layer (3) on the upper part of the leveling layer (2) comprises the following steps: S15, testing the moisture content of the leveling layer (2), and when the first waterproof layer (3) is installed, the moisture content of the leveling layer (2) is less than 9%; S16, marking lines on the upper part of the leveling layer (2): marking the edge line of the waterproof membrane and the edge line of the waterproof additional layer, and leaving an overlap edge line greater than 100 mm; S17, first lay the waterproof additional layer, then spray the base treatment agent on the surface of the leveling layer (2), and then lay the waterproof membrane.

7. A roof insulation and waterproofing construction method according to claim 2, characterized in that: In step S2, the insulation layer (4) is made of one of EPS insulation board, XPS insulation board, polyurethane insulation board or rock wool insulation board.

8. A roof insulation and waterproofing construction method according to claim 2, characterized in that: In step S2, pouring the slope layer (5) on the upper part of the thermal insulation layer (4) comprises the following steps: S21, determine the distance from the slope starting point to the drainage point, and perform the slope line laying operation; S22. Carry out the first pouring according to the thickness of the thinnest part, and pour in layers and batches towards the highest point.

9. A roof insulation and waterproofing construction method according to claim 2, characterized in that: In step S2, the construction of the reserved gas collection channel (13) on the upper part of the thermal insulation layer (4) comprises the following steps: S23, the horizontal and vertical spacings of the hoses arranged on the upper part of the insulation layer (4) are not greater than 6m; S24, the gas collecting channels (13) are interconnected at positions where the transverse and longitudinal intersections are located by using a three-way pipe or a four-way pipe; S25. The gas collecting duct (13) forms a gas collecting network on the upper part of the thermal insulation layer (4), and the four sides of the gas collecting network are 30-50 cm away from the side of the parapet (12), and exhaust pipes (14) are installed on the upper part of the four sides of the gas collecting network, and an exhaust mechanism (15) is installed on the upper part of the exhaust pipe (14).

10. A roof insulation and waterproofing construction method according to claim 2, characterized in that: The exhaust mechanism (15) adopts one of an unpowered roof fan or a ventilation fan.