Construction method of assembled mortar construction protective shed
The modular protective shed construction method solves the problems of difficult erection and low stability of traditional protective sheds, and realizes a fast, stable and safe construction environment, which is suitable for mortar construction protection on construction sites.
Patent Information
- Application Number
- CN202411186343.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-28
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2044-08-28
AI Technical Summary
Traditional methods of constructing protective sheds are difficult and time-consuming, and the sheds have low stability and cannot withstand severe weather.
The prefabricated protective canopy is constructed using a modular method, which includes steps such as reserving a safety margin, disassembly casting, frame installation, and sealing. Combined with cross-shaped connectors, shock-absorbing and anti-sway components, and a transparent roof design, it enhances structural stability and waterproof performance.
Reduce construction difficulty, shorten construction period, improve the stability and safety of protective sheds, prevent structural deformation and water accumulation, and provide a safe construction environment.
Smart Images

Figure CN118997478A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of mortar construction protection shed construction, and specifically relates to a method for constructing an assembled mortar construction protection shed. Background Art
[0002] With the development of the construction industry, standardized devices are used in more and more projects. These devices are usually used to ensure that parts or products in the production process can be accurately formed or processed under standard conditions, reduce manual intervention, and improve accuracy and repeatability. The main advantage of standardized devices is that they can standardize the production process, reduce production costs, shorten construction periods, and improve the overall quality of products. As an important equipment on construction sites, mortar tanks usually need to handle large amounts of mortar and other building materials. In order to ensure the safety of workers on the construction site, setting up standardized protective sheds can effectively isolate the construction area from the surrounding environment and prevent mortar splashes or equipment leakage from harming workers and passers-by.
[0003] The traditional way of erecting a shelter is difficult and usually requires complex engineering steps, including design, material preparation, on-site measurement, and building support structures. These processes are time-consuming, especially in large or complex construction projects, which may take days or even weeks to complete. Construction cannot be completed in a short period of time, affecting the progress of the construction site and civilized construction on site. In addition, traditional shelters are prone to collapse or damage in storms, blizzards, or heavy rains. Especially when there is heavy rainfall, water may accumulate on the roof, causing the structure to be compressed or even collapse. Summary of the invention
[0004] In view of this, the present invention provides a method for constructing an assembled mortar construction protective shed, which can solve the problems that the traditional protective shed erection method is difficult and time-consuming, and the protective shed has low stability and is difficult to withstand severe weather.
[0005] The present invention is achieved in that:
[0006] The present invention provides a method for constructing an assembled mortar construction protection shed, which comprises the following specific steps:
[0007] S10: Determine the size of the protective shed according to the size of the mortar tank and the drawings, and reserve a safety margin;
[0008] S20: After laying out the lines around the determined protection shed, fix the support base, and carry out concrete construction on the ground to cast the basic surface;
[0009] S30: Determine the structural dimensions of the protective shed according to the drawings and the actual on-site environment, and decompose and cast it;
[0010] S40: after the concrete solidifies, the cast protection shed frame is moved to the construction site in sequence, and is installed and fixed upward along the support base in sequence to perform protection shed frame construction;
[0011] S50: After the frame structure is installed, the frame sealing begins;
[0012] S60: Install warning signs on the assembled mortar construction protection shed to complete the construction of the mortar construction protection shed.
[0013] The technical effects of the method for constructing an assembled mortar construction protective shed provided by the present invention are as follows: reserving a safety margin can reduce the risk of accidents, while accommodating dimensional deviations or errors occurring during the construction of the protective shed to improve the stability of the overall structure and avoid damage or deformation of the protective shed due to overload.
[0014] Casting the base surface can provide a solid foundation to disperse the load and reduce local pressure, preventing the entire protective shed from structural displacement or settlement, thereby improving the safety and reliability of the entire construction.
[0015] By disassembling and casting the protective shed and then moving it to the construction site for splicing, it is easier to transport, carry, install and adjust the protective shed, which helps reduce the difficulty of construction and greatly shortens the construction period. At the same time, by breaking down the large structure into small parts for casting and assembly, the size and shape of each part can be more accurately controlled, thereby reducing the error of the overall structure of the protective shed.
[0016] Frame sealing can enhance the stability of the overall frame of the protective shed while reducing the possibility of structural movement or deformation; sealing can prevent unexpected objects from entering and causing unnecessary safety hazards, and can provide a safer construction environment.
[0017] On the basis of the above technical solution, the method for constructing an assembled mortar construction protection shed of the present invention can also be improved as follows:
[0018] Among them, the structure of the protective shed includes multiple sections of cross bars and vertical bars, and the adjacent cross bars and vertical bars are respectively installed inside the cross connector for fixing; the fixing member is arranged at the middle position of the cross bar and the vertical bar, and the fixing member is used to further support the stability of the connection between the cross bar and the vertical bar; the bottom of the vertical bar close to the ground is fixedly connected to the support base, and the side thereof is provided with the reinforcing assembly, and the reinforcing assembly is used to reinforce the safety and stability of the protective shed; the ceiling is arranged on the top of the structure composed of the cross bars and the vertical bars, and the ceiling is connected to the top of the structure composed of the cross bars and the vertical bars through a shock-absorbing and anti-swaying assembly, and a horizontal movement space of the ceiling is reserved in the structure composed of the cross bars and the vertical bars, so as to reduce the lateral force of the structure composed of the cross bars and the vertical bars in bad weather; the protective net is fixed on the side wall of the structure composed of the cross bars and the vertical bars, and the protective net is used to divide the internal and external spaces to stabilize the stability of the environment for mortar construction.
[0019] The beneficial effects of adopting the above improved solution are: by setting a cross connector, it can provide support in multiple directions, enhance the overall stability of the protective shed frame, and at the same time, the cross connector helps to evenly distribute the load to the horizontal bars and vertical bars connected thereto, reducing local stress concentration. By providing a strong and stable connection point, the firmness and durability of the structural frame are ensured.
[0020] By setting the fixing parts, it is possible to provide support for the horizontal bars and vertical bars in multiple directions, enhance the stability of the overall structure of the protective shed, and reduce local shaking or deformation.
[0021] The arched roof helps to drain water naturally, allowing rainwater to slide down the roof, reducing water accumulation and the risk of water leakage. The streamlined design of the arched roof can better resist wind force, reduce the impact of wind pressure on the structure, and improve overall stability.
[0022] By setting up shock-absorbing and anti-sway components, the lateral impact caused by wind can be absorbed and dispersed, reducing the direct impact on the ceiling and the structure below, and reducing potential damage caused by wind. Allowing the ceiling to have a certain displacement space under the action of wind can effectively prevent the ceiling and the structure below from shaking violently or becoming unstable due to excessive wind, thereby maintaining the stability of the overall structure. By absorbing the kinetic energy caused by wind and converting it into displacement, the shock-absorbing components can effectively prevent the ceiling and the structure below from being blown away or damaged due to excessive wind, thereby enhancing the safety of the structure.
[0023] Furthermore, the roof is a quasi-circular arch structure as a whole, and its cross-section along the vertical direction of the center point is a parabolic structure, which is formed by binding with steel bars, and an oily rainproof cloth is fixed on the top, and the oily rainproof cloth is a transparent structure, which is used to ensure the lighting inside the fireproof shed;
[0024] The oily rainproof cloth is fixed to the steel bars of the ceiling by a fixing clip to prevent the weight of rainwater from damaging the structure of the oily rainproof cloth; and the edge of the oily rainproof cloth is bent toward the inner wall of the ceiling so that the oily rainproof cloth is closely attached to the surface of the ceiling;
[0025] The fixing clip is a double-ring clip, including two clips, which are integrally arranged with an angle of 60° between them; one end of the double-ring clip is fixed to a position of the ceiling close to the inner wall of the oily rainproof cloth, and the other end is fixed to some positions of the oily rainproof cloth close to the ceiling, so as to tightly fix the ceiling and the oily rainproof cloth while ensuring the stability of the fixing clip.
[0026] The beneficial effects of adopting the above-mentioned improvement scheme are as follows: the round-arched transparent ceiling can provide more uniform natural light distribution, improve the lighting conditions of the working environment, and reduce shadow areas. At the same time, the round-arched ceiling has a modern and beautiful appearance, which can enhance the visual effect of the overall structure.
[0027] Fixing the oily tarpaulin from the inside of the ceiling with a fixing clip can make the tarpaulin fit more closely to the ceiling and prevent the fixing clip from being blown away by the wind or affected by the external environment and then corroded. When the tarpaulin needs to be inspected or replaced, the internal fixing design is usually more convenient and reduces interference with the external structure.
[0028] The 60° angle of the fixing clip helps to form a larger bearing surface, balance the load distribution, improve the overall stability of the clip, and reduce loosening or displacement caused by uneven force.
[0029] Furthermore, the shock-absorbing and anti-swaying assembly includes a fixing plate, a groove, a shock-absorbing member and a curling connector. The fixing plate includes two sections, namely a fixing section and a secondary installation section. The fixing section and the installation section are tightly fixed to the top of the structure composed of the cross bar and the vertical bar by bolts and steel bars in turn; the fixing plate is provided with the groove on one side, and the groove is a square structure; the shock-absorbing member is fixed on the inner wall of the groove; a connecting edge is welded at the bottom edge of the ceiling, and the connecting edge passes through the groove and is fixed to the inside of the fixing plate; the bottom of the ceiling is further fixed to the structure composed of the cross bar and the vertical bar by the curling connector; the curling connector is a steel core rope, and the steel core rope includes at least 3 turns;
[0030] Bolts are fixed to the fixing plate and the connecting edge in the vertical direction; the shock absorbing member includes a shock absorbing spring layer and a friction layer, the shock absorbing spring layer and the friction layer are fixed to the inner wall of the groove in sequence, and a friction stabilizer is arranged on the surface of the friction layer; a spring is fixed inside the shock absorbing spring layer, and the spring is used to absorb the force of the ceiling in the horizontal direction;
[0031] The height of the groove is the same as the height of the connecting edge of the ceiling, and a rubber layer is fixed at its opening position to further strengthen the connection between the ceiling and the structure composed of the cross bar and the vertical bar; the width of the groove is greater than the width of the connecting edge to reserve space for the ceiling to shake.
[0032] The beneficial effect of adopting the above-mentioned improvement scheme is that by setting the groove, a channel for lateral movement can be provided for the connecting edge of the ceiling, which facilitates the lateral displacement of the ceiling under the influence of wind, and the groove is perpendicular to the connecting edge of the ceiling.
[0033] The internal shock-absorbing spring layer can provide elastic buffering, reduce the impact and vibration of the connection edge, and protect the structure and connection parts from damage. The friction layer can increase the friction of the connection edge movement and convert the mechanical energy of the connection edge movement of the ceiling into heat energy for consumption.
[0034] The bolts penetrate the connection edge and the anti-vibration and shaking components at the same time. The reason why the connection edge can also move laterally in the groove is that during the construction process, there may be installation errors or slight asymmetry of the frame structure. Therefore, the connection edge and the bolt can move slightly relative to each other to effectively compensate for these errors and ensure that the final structural quality meets the design requirements. In addition, thermal expansion and contraction caused by temperature changes will also cause the connection edge and the bolt to move relative to each other, resulting in lateral displacement in the groove.
[0035] Furthermore, the protective net includes a double layer, which is mounted on both sides of the structure composed of the horizontal bar and the vertical bar. The outer protective net is fixedly connected to the structure composed of the horizontal bar and the vertical bar by fixing clips, and is respectively fixed on the cross connecting pieces connecting the horizontal bar and the vertical bar; the protective net is a grid structure, and the grid size of the outer layer is smaller than the grid size of the inner layer.
[0036] The beneficial effects of adopting the above-mentioned improvement scheme are as follows: the larger mesh on the outer layer can effectively intercept larger particles, impurities or objects, such as leaves, large dust particles, etc. The smaller mesh on the inner layer can further filter smaller particles and provide more refined protection. The double-layer mesh structure can effectively prevent small animals or insects from penetrating, improve the sanitary conditions of the shed environment, and reduce the risk of accidental intrusion of external objects.
[0037] Furthermore, the cross connector is a cross-shaped structure, with connecting grooves on its four corners, and the bottom width of the connecting groove is greater than the top width; the shape of the connecting groove is the same as the shape of the adjacent cross bar and the vertical bar; a spring clamping structure is provided at the bottom of the connecting groove, and a rubber protrusion is provided on the side wall of the connecting groove, and the rubber protrusion is perpendicular to the installation direction of the cross bar and the vertical bar, and is used to fix the cross bar and the vertical bar by the extrusion force of the rubber protrusion; the spring clamping structure includes a clamping plate and a spring member, and the clamping plate is an inclined structure, and the angle between the clamping plate and the side wall of the connecting groove gradually increases along the insertion direction of the cross bar and the vertical bar in the cross connector, and the spring member is fixed between the clamping plate and the side wall of the connecting groove, and is used to clamp and fix the cross bar and the vertical bar.
[0038] The beneficial effects of adopting the above-mentioned improvement scheme are as follows: the splint and the spring member can provide additional friction or fixing force to prevent the horizontal bar and the vertical bar from slipping during installation and handling, thereby enhancing the stability of the connection; by preventing the horizontal bar and the vertical bar from slipping, the deformation or displacement caused by loose connection when the structure is under load can be reduced, thereby maintaining the overall stability of the structure.
[0039] Furthermore, one end of the fixing member is fixed to the cross bar and the vertical bar, and its length is greater than the distance between the fixed cross bar and the vertical bar and the adjacent vertical bar and the cross bar; the fixing member is a memory metal, which curls when subjected to force, and one end away from the fixed cross bar and the vertical bar curls on the adjacent vertical bar and the cross bar; the curling directions of the adjacent fixing members are opposite, so as to balance the forces in multiple directions;
[0040] The reinforcement component includes a steel cable and a rivet, the rivet is welded and fixed to the embedded reinforcement inside the base surface, one end of the steel cable is fixed to the rivet, and the other end is fixed to the structure composed of the cross bar and the vertical bar; the reinforcement component includes multiple ones, which are symmetrically fixed on both sides of the structure fixed by the cross bar and the vertical bar.
[0041] The beneficial effects of adopting the above-mentioned improvement scheme are as follows: the fixing parts are arranged in the shape of the letter X, which can distribute the load more evenly, reduce concentrated stress, and improve the bearing capacity of the structure; at the same time, the X-shaped arrangement can effectively resist shear force, make the connection part stronger, and reduce loosening or falling off caused by shear force. The curling directions of adjacent fixing parts are opposite, which can prevent adjacent horizontal bars and vertical bars from falling off at the same time, reducing the occurrence of accidents.
[0042] The steel cables provide additional support, effectively dispersing the load, reducing the sway or tilt of the shelter under wind or other external forces, and improving overall stability. The tensioning effect of the steel cables enhances the wind resistance of the structure, allowing the shelter to remain stable in strong winds or bad weather conditions, reducing the risk of collapse. Rivets, as strong connectors, ensure that the fixed connection between the shelter and the foundation is firm and reliable, reducing the possibility of loosening and displacement.
[0043] Furthermore, after the frame structure is installed, the specific steps of starting the frame sealing are as follows:
[0044] A 14 mm thick template is used to be fixed from bottom to top along the inner wall of the protection shed in sequence, and the template and the fireproof shed are connected by self-tapping screws.
[0045] Furthermore, the mortar storage tank is arranged at the center of the fireproof shed.
[0046] Furthermore, the specific steps of installing the warning sign on the assembled mortar construction protection shed are:
[0047] A warning sign is fixed on the outer wall of the protection shed, and a circle of red LED lights surrounds the outer periphery of the warning sign to warn the mortar construction site.
[0048] Compared with the prior art, the beneficial effects of the method for constructing an assembled mortar construction protective shed provided by the present invention are: reserving a safety margin can reduce the risk of accidents, while accommodating dimensional deviations or errors occurring during the construction of the protective shed to improve the stability of the overall structure and avoid damage or deformation of the protective shed due to overload.
[0049] Casting the base surface can provide a solid foundation to disperse the load and reduce local pressure, preventing the entire protective shed from structural displacement or settlement, thereby improving the safety and reliability of the entire construction.
[0050] By disassembling and casting the protective shed and then moving it to the construction site for splicing, it is easier to transport, carry, install and adjust the protective shed, which helps reduce the difficulty of construction and greatly shortens the construction period. At the same time, by breaking down the large structure into small parts for casting and assembly, the size and shape of each part can be more accurately controlled, thereby reducing the error of the overall structure of the protective shed.
[0051] Frame sealing can enhance the stability of the overall frame of the protective shed while reducing the possibility of structural movement or deformation; sealing can prevent unexpected objects from entering and causing unnecessary safety hazards, and can provide a safer construction environment. BRIEF DESCRIPTION OF THE DRAWINGS
[0052] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings required for use in the description of the embodiments of the present invention will be briefly introduced below. Obviously, the accompanying drawings in the following description are only some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying creative labor.
[0053] Figure 1 It is a flow chart of a method for constructing an assembled mortar construction protection shed;
[0054] Figure 2 It is a front view of the assembled mortar construction protection shed;
[0055] Figure 3 This is a schematic diagram of the internal structure of the assembled mortar construction protection shed;
[0056] Figure 4 It is a partial cross-sectional view of a cross-connecting member of an assembled mortar construction protection shed;
[0057] Figure 5 It is a cross-sectional view of the shock-absorbing and anti-swaying components of the assembled mortar construction protection shed;
[0058] Figure 6 It is a schematic diagram of the structure of the fixing clamp of the assembled mortar construction protection shed;
[0059] Figure 7 It is a structural diagram of A;
[0060] In the accompanying drawings, the components represented by the reference numerals are listed as follows:
[0061] 10. Cross bar; 20. Vertical bar; 30. Cross connector; 31. Spring clamping structure; 311. Clamp; 312. Spring member; 40. Fixing member; 50. Reinforcement assembly; 60. Ceiling; 70. Protective net; 81. Fixing plate; 82. Groove; 83. Shock-absorbing member; 831. Shock-absorbing spring layer; 832. Friction layer; 84. Curled connector. DETAILED DESCRIPTION
[0062] In order to make the purpose, technical solution and advantages of the embodiments of the present invention more clear, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention.
[0063] like Figure 1 FIG. 1 is a flow chart of a method for constructing an assembled mortar construction protection shed provided by the present invention. In this embodiment, the method comprises the following specific steps:
[0064] S10: Determine the size of the protective shed according to the size of the mortar tank and the drawings, and reserve a safety margin;
[0065] S20: After laying out the lines around the determined protection shed, fix the support base, and carry out concrete construction on the ground to cast the basic surface;
[0066] S30: Determine the structural dimensions of the protective shed according to the drawings and the actual on-site environment, and decompose and cast it;
[0067] S40: after the concrete solidifies, the cast protection shed frames are moved to the construction site in sequence, and are installed and fixed upward along the support base in sequence to perform protection shed frame construction;
[0068] S50: After the frame structure is installed, the frame sealing begins;
[0069] S60: Install warning signs on the assembled mortar construction protection shed to complete the construction of the mortar construction protection shed.
[0070] like Figure 2-7 As shown, it is a structural schematic diagram of an assembled mortar construction protective shed provided by the present invention. In the above technical scheme, the structure of the protective shed includes multiple sections of cross bars 10 and vertical bars 20, and the adjacent cross bars 10 and vertical bars 20 are respectively installed inside the cross connector 30 for fixing; a fixing member 40 is arranged at the middle position of the cross bar 10 and the vertical bar 20, and the fixing member 40 is used to further support the stability of the connection between the cross bar 10 and the vertical bar 20; the bottom of the vertical bar 20 close to the ground is fixedly connected to the support base, and a reinforcing assembly 50 is arranged on its side, and the reinforcing assembly 50 is used to strengthen The safety and stability of the protection shed are ensured; a ceiling 60 is arranged on the top of the structure composed of the horizontal bars 10 and the vertical bars 20, and the ceiling 60 is connected to the top of the structure composed of the horizontal bars 10 and the vertical bars 20 through a shock-absorbing and anti-sway component, and a horizontal moving space for the ceiling 60 in the structure composed of the horizontal bars 10 and the vertical bars 20 is reserved to reduce the lateral force of the structure composed of the horizontal bars 10 and the vertical bars 20 due to bad weather; a protection net 70 is fixed on the side wall of the structure composed of the horizontal bars 10 and the vertical bars 20, and the protection net 70 is used to divide the internal and external spaces to stabilize the stability of the environment for mortar construction.
[0071] Furthermore, in the above technical solution, the ceiling 60 is a quasi-circular arch structure as a whole, and its cross-section along the vertical direction of the center point is a parabolic structure, which is formed by tying steel bars, and an oily rainproof cloth is fixed on the top, and the oily rainproof cloth is a transparent structure, which is used to ensure the lighting inside the fireproof shed;
[0072] The oily rainproof cloth is fixed to the steel bars of the ceiling 60 by a fixing clip to prevent the weight of rainwater from damaging the structure of the oily rainproof cloth; and the edge of the oily rainproof cloth is bent toward the inner wall of the ceiling 60 so that the oily rainproof cloth is closely attached to the surface of the ceiling 60;
[0073] The fixing clip is a double-ring clip, including two clips, which are integrally arranged with an angle of 60° between them; one end of the double-ring clip is fixed to a position of the ceiling 60 close to the inner wall of the oily rainproof cloth, and the other end is fixed to some positions of the oily rainproof cloth close to the ceiling 60, so as to tightly fix the ceiling 60 and the oily rainproof cloth while ensuring the stability of the fixing clip.
[0074] The ratio of the arch height to the span of the ceiling 60 is 1:5
[0075] Further, in the above technical solution, the shock-absorbing and anti-swaying assembly includes a fixing plate 81, a groove 82, a shock-absorbing member 83 and a curling connector 84. The fixing plate 81 includes two sections, namely a fixing section and a secondary installation section. The fixing section and the installation section are respectively tightly fixed to the top of the structure composed of the cross bar 10 and the vertical bar 20 by bolts and steel bars; a groove 82 is opened on one side of the fixing plate 81, and the groove 82 is a square structure; a shock-absorbing member 83 is fixed on the inner wall of the groove 82; a connecting edge is welded at the bottom edge of the ceiling 60, and the connecting edge passes through the groove 82 and is fixed inside the fixing plate 81; the bottom of the ceiling 60 is further fixed to the structure composed of the cross bar 10 and the vertical bar 20 by a curling connector 84; the curling connector 84 is a steel core rope, and the steel core rope includes at least 3 turns;
[0076] Bolts are fixed in the vertical direction of the fixing plate 81 and the connecting edge; the shock absorbing member 83 includes a shock absorbing spring layer 831 and a friction layer 832, which are fixed on the inner wall of the groove 82 in sequence, and a friction stabilizer is provided on the surface of the friction layer 832; a spring is fixed inside the shock absorbing spring layer 831, and the spring is used to absorb the force of the ceiling 60 in the horizontal direction;
[0077] The height of the groove 82 is the same as the height of the connecting edge of the ceiling 60, and a rubber layer is fixed at its opening position to further strengthen the connection between the ceiling 60 and the structure composed of the cross bar 10 and the vertical bar 20; the width of the groove 82 is greater than the width of the connecting edge to reserve space for the ceiling 60 to shake.
[0078] Furthermore, in the above technical solution, the protective net 70 includes a double layer, which is mounted on both sides of the structure composed of the horizontal bar 10 and the vertical bar 20. The outer protective net 70 is fixedly connected to the structure composed of the horizontal bar 10 and the vertical bar 20 by fixing clips, and is respectively fixed on the cross connecting pieces 30 connecting the horizontal bar 10 and the vertical bar 20; the protective net 70 is a grid structure, and the grid size of the outer layer is smaller than the grid size of the inner layer.
[0079] Furthermore, in the above technical solution, the cross connector 30 is a cross-shaped structure, and connecting grooves are provided on its four corners, and the bottom width of the connecting groove is greater than the top width; the shape of the connecting groove is the same as the shape of the adjacent cross bar 10 and vertical bar 20; a spring clamping structure 31 is provided at the bottom of the connecting groove, and a rubber protrusion is provided on the side wall of the connecting groove, and the rubber protrusion is perpendicular to the installation direction of the cross bar 10 and the vertical bar 20, and is used to fix the cross bar 10 and the vertical bar 20 by the extrusion force of the rubber protrusion; the spring clamping structure 31 includes a clamping plate 311 and a spring member 312, and the clamping plate 311 is an inclined structure, and the angle between the clamping plate 311 and the side wall of the connecting groove gradually increases along the insertion direction of the cross bar 10 and the vertical bar 20 in the cross connector 30, and a spring member 312 is fixed between the clamping plate 311 and the side wall of the connecting groove, which is used to clamp and fix the cross bar 10 and the vertical bar 20.
[0080] Further, in the above technical solution, one end of the fixing member 40 is fixed on the cross bar 10 and the vertical bar 20, and its length is greater than the distance between the fixed cross bar 10 and the vertical bar 20 and the adjacent vertical bar 20 and the cross bar 10; the fixing member 40 is a memory metal, which curls when subjected to force, and one end away from the fixed cross bar 10 and the vertical bar 20 curls on the adjacent vertical bar 20 and the cross bar 10; the curling directions of the adjacent fixing members 40 are opposite, which is used to balance the forces in multiple directions;
[0081] The reinforcement component 50 includes a steel cable and a rivet, which is welded and fixed to the embedded reinforcement inside the base surface. One end of the steel cable is fixed to the rivet, and the other end is fixed to the structure composed of the cross bar 10 and the vertical bar 20; the reinforcement component 50 includes multiple ones, which are symmetrically fixed on both sides of the structure fixed with the cross bar 10 and the vertical bar 20.
[0082] Furthermore, in the above technical solution, after the frame structure is installed, the specific steps of starting the frame sealing are:
[0083] Use 14mm thick formwork to fix it from bottom to top along the inner wall of the protective shed, and use self-tapping screws to connect the formwork and the fireproof shed.
[0084] Furthermore, in the above technical solution, the mortar storage tank is arranged at the center of the fireproof shed.
[0085] Furthermore, in the above technical solution, the specific steps of installing the warning sign on the assembled mortar construction protection shed are:
[0086] A warning sign is fixed on the outer wall of the protective shed, and a circle of red LED lights surrounds the warning sign to warn the mortar construction site.
[0087] Example:
[0088] First, determine the size of the protective shed according to the size of the mortar tank and the drawings. After the size is determined, the foundation of the protective shed is laid out, followed by concrete pouring. After the concrete pouring is completed, the steel pipes of the protective shed are erected. After the concrete solidifies, the skeleton of the mortar tank protective shed is constructed. The horizontal bar 10 and the vertical bar 20 are 50×50×3 (mm) models. The steel pipes are connected by a cross connector 30. The size of the protective shed skeleton is 5000×5000mm, the height is 2800mm, the side span skeleton spacing is 900mm, the middle spacing is 3200mm, the step distance is 1100mm, the top skeleton spacing is 600mm, and the side is reinforced with a reinforcement component 50. After the frame structure is installed, the mortar skeleton is sealed, and a 14mm thick template is used for sealing. The template skin and the skeleton are connected with self-tapping screws. After the template is sealed, the CI advertising cloth is hung to indicate the mortar tank and the safe operating procedures for the use of the mortar tank are clearly stated on the advertising cloth, so that the workers understand the use requirements and the construction is smoother.
[0089] Specifically, the principle of the present invention is: when in use, the size of the protective shed is determined according to the size of the mortar tank and the drawings, and a safety margin is reserved: after the line construction is carried out around the determined protective shed, the support base is fixed, and concrete construction is carried out on the ground to cast the basic surface: the structural dimensions of the protective shed are determined according to the drawings and the actual on-site environment, and it is decomposed and cast: after the concrete solidifies, the cast protective shed frame is moved to the construction site in turn, and installed and fixed upward along the support base in turn to carry out the protection shed frame construction; after the frame structure is installed, the frame sealing is started; warning signs are installed on the assembled mortar construction protective shed to complete the construction of the mortar construction protective shed.
Claims
1. A method for constructing an assembled mortar construction protection shed, characterized in that: The specific steps include: S10: Determine the size of the protective shed according to the size of the mortar tank and the drawings, and reserve a safety margin; S20: After laying out the lines around the determined protection shed, fix the support base, and carry out concrete construction on the ground to cast the basic surface; S30: Determine the structural dimensions of the protective shed according to the drawings and the actual on-site environment, and disassemble and cast it; S40: after the concrete solidifies, the cast protection shed frame is moved to the construction site in sequence, and is installed and fixed upward along the support base in sequence to perform protection shed frame construction; S50: After the frame structure is installed, the frame sealing begins; S60: Install warning signs on the assembled mortar construction protection shed to complete the construction of the mortar construction protection shed.
2. A method for constructing an assembled mortar construction protection shed according to claim 1, characterized in that: The structure of the protective shed comprises a plurality of sections of cross bars (10) and vertical bars (20), and the adjacent cross bars (10) and vertical bars (20) are respectively installed inside a cross connecting member (30) for fixing; the fixing member (40) is arranged at the middle position of the cross bars (10) and the vertical bars (20), and the fixing member (40) is used to further support the stability of the connection between the cross bars (10) and the vertical bars (20); the bottom of the vertical bar (20) close to the ground is fixedly connected to the support base, and the side of the vertical bar (20) is arranged with the reinforcing assembly (50), and the reinforcing assembly (50) is used to reinforce the safety and stability of the protective shed; the cross bars (10) and The top of the structure composed of the vertical bars (20) is provided with the ceiling (60), and the ceiling (60) is connected to the top of the structure composed of the horizontal bars (10) and the vertical bars (20) through a shock-absorbing and anti-swaying component, and a space for the ceiling (60) to move in the horizontal direction of the structure composed of the horizontal bars (10) and the vertical bars (20) is reserved, so as to reduce the lateral force of the structure composed of the horizontal bars (10) and the vertical bars (20) caused by bad weather; the protective net (70) is fixed on the side wall of the structure composed of the horizontal bars (10) and the vertical bars (20), and the protective net (70) is used to divide the internal and external spaces to stabilize the stability of the environment for mortar construction.
3. A method for constructing an assembled mortar construction protection shed according to claim 2, characterized in that: The ceiling (60) is a quasi-circular arch structure as a whole, and its cross-section along the vertical direction of the center point is a parabolic structure, which is formed by binding with steel bars, and an oily rainproof cloth is fixed on the top, and the oily rainproof cloth is a transparent structure, which is used to ensure the lighting inside the fireproof shed; The oily rainproof cloth is fixed to the steel bars of the ceiling (60) by a fixing clamp to prevent the weight of rainwater from damaging the structure of the oily rainproof cloth; and the edge of the oily rainproof cloth is bent toward the inner wall of the ceiling (60) so that the oily rainproof cloth is closely attached to the surface of the ceiling (60); The fixing clamp is a double-ring clamp, comprising two clamps, which are integrally arranged with an angle of 60° between them; one end of the double-ring clamp is fixed to a position of the ceiling (60) close to the inner wall of the oily rainproof cloth, and the other end is fixed to some positions of the oily rainproof cloth close to the ceiling (60), so as to tightly fix the ceiling (60) and the oily rainproof cloth while ensuring the stability of the fixing clamp.
4. A method for constructing an assembled mortar construction protection shed according to claim 3, characterized in that: The shock-absorbing and anti-swaying assembly comprises a fixing plate (81), a groove (82), a shock-absorbing member (83) and a curling connector (84); the fixing plate (81) comprises two sections, namely a fixing section and a secondary installation section; the fixing section and the installation section are respectively tightly fixed to the top of the structure composed of the cross bar (10) and the vertical bar (20) by bolts and steel bars; one side of the fixing plate (81) is provided with the groove (82), and the groove (82) is a square structure; the shock-absorbing member (83) is fixed on the inner wall of the groove (82); a connecting edge is welded at the bottom edge of the ceiling (60), and the connecting edge passes through the groove (82) and is fixed to the inside of the fixing plate (81); the bottom of the ceiling (60) and the structure composed of the cross bar (10) and the vertical bar (20) are further fixed by the curling connector (84); the curling connector (84) is a steel core rope, and the steel core rope includes at least 3 turns; Bolts are fixed in the vertical direction of the fixing plate (81) and the connecting edge; the shock absorbing member (83) comprises a shock absorbing spring layer (831) and a friction layer (832), the shock absorbing spring layer (831) and the friction layer (832) being fixed on the inner wall of the groove (82) in sequence, and a friction stabilizer is provided on the surface of the friction layer (832); a spring is fixed inside the shock absorbing spring layer (831), and the spring is used to absorb the force of the ceiling (60) in the horizontal direction; The height of the groove (82) is the same as the height of the connecting edge of the ceiling (60), and a rubber layer is fixed at its opening position to further reinforce the connection between the ceiling (60) and the structure composed of the cross bar (10) and the vertical bar (20); the width of the groove (82) is greater than the width of the connecting edge to reserve space for the ceiling (60) to shake.
5. The method for constructing an assembled mortar construction protection shed according to claim 4, characterized in that: The protective net (70) comprises a double layer, which is sleeved on both sides of the structure composed of the cross bar (10) and the vertical bar (20); the outer protective net (70) is fixedly connected to the structure composed of the cross bar (10) and the vertical bar (20) by a fixing clamp, and is respectively fixed on the cross connecting piece (30) connected to the cross bar (10) and the vertical bar (20); the protective net (70) is a grid structure, and the grid size of the outer layer is smaller than the grid size of the inner layer.
6. A method for constructing an assembled mortar construction protection shed according to claim 5, characterized in that: The cross connecting member (30) is a cross-shaped structure, and connection grooves are provided at the four corners thereof. The bottom width of the connection groove is greater than the top width. The shape of the connection groove is the same as the shape of the adjacent cross bar (10) and the vertical bar (20). A spring clamping structure (31) is provided at the bottom of the connection groove, and a rubber protrusion is provided on the side wall of the connection groove. The rubber protrusion is perpendicular to the installation direction of the cross bar (10) and the vertical bar (20) and is used to fix the cross bar (10) and the vertical bar (20) by the extrusion force of the rubber protrusion. 0) and the vertical rod (20); the spring clamping structure (31) comprises a clamping plate (311) and a spring member (312); the clamping plate (311) is an inclined structure, and the angle between the clamping plate (311) and the side wall of the connecting groove gradually increases along the insertion direction of the cross rod (10) and the vertical rod (20) in the cross connecting member (30); the spring member (312) is fixed between the clamping plate (311) and the side wall of the connecting groove, and is used to clamp and fix the cross rod (10) and the vertical rod (20).
7. A method for constructing an assembled mortar construction protection shed according to claim 6, characterized in that: One end of the fixing member (40) is fixed on the cross bar (10) and the vertical bar (20), and its length is greater than the distance between the fixed cross bar (10) and the vertical bar (20) and the adjacent vertical bar (20) and the cross bar (10); the fixing member (40) is a memory metal, which curls when subjected to force, and one end away from the fixed cross bar (10) and the vertical bar (20) curls on the adjacent vertical bar (20) and the cross bar (10); the curling directions of the adjacent fixing members (40) are opposite, so as to balance the forces in multiple directions; The reinforcing assembly (50) comprises a steel cable and a rivet, wherein the rivet is welded and fixed to the embedded reinforcement inside the base surface, one end of the steel cable is fixed to the rivet, and the other end is fixed to the structure composed of the cross bar (10) and the vertical bar (20); the reinforcing assembly (50) comprises a plurality of symmetrically fixed two by two on both sides of the structure to which the cross bar (10) and the vertical bar (20) are fixed.
8. The method for constructing an assembled mortar construction protection shed according to claim 7, characterized in that: After the frame structure is installed, the specific steps for starting the frame sealing are as follows: A 14 mm thick template is used to be fixed from bottom to top along the inner wall of the protection shed in sequence, and the template and the fireproof shed are connected by self-tapping screws.
9. The method for constructing an assembled mortar construction protection shed according to claim 8, characterized in that: The mortar storage tank is arranged at the center of the fireproof shed.
10. A method for constructing an assembled mortar construction protection shed according to claim 9, characterized in that: The specific steps of installing the warning sign on the assembled mortar construction protection shed are: A warning sign is fixed on the outer wall of the protection shed, and a circle of red LED lights surrounds the outer periphery of the warning sign to warn the mortar construction site.
Citation Information
Patent Citations
Windproof and heat insulation construction method for winter construction of pipe gallery
CN108532628A
Novel assembled distribution box protective shed
CN204060064U
Assembled concrete prefabricated part heat preservation shed
CN212241514U
Anti-smashing device for box-type substation of wind power plant
CN221239997U
Cited By