Construction method for carrying out curtain grouting on adit of water conveyance tunnel
Through segmented drilling and segmented pressurized water pressure, combined with fine pulping process and material selection, the problems of slurry leakage and inaccurate data caused by different formation pressures in the existing technology are solved, and more efficient curtain notes are achieved Slurry effect and structural stability.
Patent Information
- Application Number
- CN202411250985.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-06
- Publication Date
- 2024-11-22
AI Technical Summary
The prior art causes poor slurry leakage and grouting quality in curtain grouting due to different formation pressures, and the grouting volume cannot be adjusted according to the depth. The pressurized water test data is inaccurate, resulting in poor grouting effect.
Using segmented drilling and segmented pressurized water pressure, combined with top-down and bottom-up segmented blocking grouting methods, set grouting pressures at different depths, and improve slurry through fine pulping processes and material selection. Performance, multiple data detection and rehydration processing are carried out.
The quality and structural stability of curtain grouting are improved, ensuring that each hole position has an appropriate grouting amount, reducing slurry leakage, improving data accuracy and engineering efficiency, and saving material costs.
Smart Images

Figure CN118997795A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of curtain grouting, in particular to a construction method for curtain grouting a branch hole of a water conveyance tunnel. Background Art
[0002] With the development of society, the construction of water tunnels is also being vigorously carried out. The construction of water tunnels is of great significance for improving water resource allocation, protecting the ecological environment, promoting economic development and maintaining national security. In order to improve the waterproof performance, structural stability and disaster resistance of water tunnels and ensure the safe operation of water pipelines, curtain grouting is usually carried out on tunnels and tunnel branches. In the existing technology, when curtain grouting is performed on the soil layer, the same pressure is usually used for grouting regardless of the depth of the hole position, which is prone to leakage due to different formation pressures. The overall grouting quality is poor, and the grouting amount cannot be adjusted according to actual needs, resulting in excessive waste of grouting materials; on the other hand, during the water pressure test, holes of different depths are not set for different pressure tests, resulting in the inability to collect water pressure conditions at different depths of the formation. The overall data is not accurate enough, resulting in poor subsequent grouting effects. Summary of the invention
[0003] The purpose of the present invention is to provide a construction method for curtain grouting of a branch tunnel of a water conveyance tunnel, so as to solve the problem of poor grouting effect in the prior art.
[0004] The present invention is implemented by the following technical scheme: A construction method for curtain grouting of a branch tunnel of a water conveyance tunnel comprises the following steps: Step 1: Carry out preliminary preparations; Step 2, slurry preparation; weigh the slurry materials, solid materials such as cement are measured by weight, and water for slurry is measured by volume; the centralized slurry preparation station prepares 0.5:1 or 1:1 ordinary pure cement slurry according to construction requirements and transports it to the working surface of each unit; at the same time, measure the slurry density and temperature, and keep records; Step 3, drilling construction: use XY-2 geological drilling rig to drill holes, and the holes are drilled in sections from top to bottom; one pilot hole is arranged for each unit of the overlapping curtain grouting; Step 4: Flushing the cracks; the flushing water pressure is 80% of the grouting pressure; Step 5: water pressure test: setting the corresponding segmented water pressure for the segmented rock penetration depth; Step 6, grouting; the grouting is constructed by top-down, segmented blocking, and in-hole circulation grouting method. The lower layer row and the middle layer row II sequence holes are constructed by bottom-up, segmented blocking, and in-hole circulation grouting method; the grouting is set in multiple sections, and different grouting pressures are set in different sections; Step 7: Data detection: 14 days after the completion of unit grouting, conduct visual inspection and core sampling inspection of the overlapping curtain grouting holes and the sealing quality of the inspection holes.
[0005] In order to better realize the present invention, further, the weighing error in step 2 is less than 5%; the slurry conveying flow rate is 1.4-2.0m / s; the pure cement slurry in step 2 uses a high-speed mixer, and the stirring time is not less than 30s; the slurry temperature should be maintained between 5-40°C, and the slurry exceeding this standard should be regarded as waste slurry; the slurry should be sieved before use, and the time from preparation to use up: ordinary pure cement slurry does not exceed 4h, and fine cement slurry does not exceed 2h.
[0006] In order to better realize the present invention, further, the cement used in step 2 is ordinary Portland cement with a strength grade not less than P.042.5; the cement fineness is preferably such that the residue passing through an 80 μm square hole sieve is not more than 5%; and an admixture is used, specifically natural river sand with a particle size not greater than 1.5 mm.
[0007] In order to better realize the present invention, further, in step 3, the grouting hole is 24m deep into the rock hole; the opening diameters of the pilot hole, the inspection hole and the lifting hole are not less than 89mm, and the final hole diameter is not less than 75mm; the hole position deviation is not more than 10cm; the maximum length of the core sample should be limited to 3m; for a drilling cycle of 1m or more, if the core sample collection rate is less than 80%, the next time should reduce the previous depth by 50%, and then reduce it by 50% successively until it reaches 50cm.
[0008] In order to better implement the present invention, further, after the drilling in step 4 is completed, a large flow of water is used to flush out the rock powder and slag in the hole, and pressurized water should be used to flush the fissures before grouting. The flushing time is until the return water is clean and shall not exceed 20 minutes.
[0009] In order to better realize the present invention, further, the water pressure test in step 5 specifically includes: selecting 10% of the holes in the lower row as pilot holes for single-point water pressure test, and the other grouting holes are combined with crack flushing for simple water pressure test; crack flushing must be performed separately before the single-point water pressure test.
[0010] In order to better realize the present invention, further, the pilot holes are drilled from top to bottom, cored, washed, flushed, and tested by single-point water pressure test, and then plugged from bottom to top after reaching the bottom of the hole; In order to better realize the present invention, further, in step 6, the overlapping curtain grouting is set with multiple water-cement ratio levels, and the operation is performed by changing the water-cement ratio according to the specific situation; under the maximum design pressure, when the injection rate is not more than 1L / min, the grouting is continued for 30 minutes to end; after the full hole grouting is completed, the hole is sealed.
[0011] In order to better realize the present invention, further, in step 7, the overlapping curtain water pressure inspection adopts a single-point water pressure test, the number of inspection holes is 5% of the total number of unit grouting holes, and at least one inspection hole is arranged in a unit project; the number of core sampling inspection holes is 2-3% of the number of sealed holes, and the inspection qualification standard is: the permeability is not greater than 1Lu, the qualified rate of the first section is 100%, and the qualified rate of the remaining sections is not less than 95%, the permeability value of the unqualified hole section does not exceed 3Lu, and the distribution is not concentrated, otherwise, supplementary irrigation should be carried out.
[0012] Compared with the prior art, the present invention has the following advantages and beneficial effects: (1) The present invention improves the pulping process and raw material requirements, so that the slurry has better performance after production, effectively improves the strength and stability of the engineering structure, and ensures the effect of curtain grouting; (2) The present invention can more accurately evaluate the water pressure conditions of formations at different depths by setting segmented processing of the depth of the borehole into the rock and then setting the corresponding segmented water pressure, so that the detection data of the water pressure test is more reasonable and the detection accuracy is improved; (3) The present invention can perform grouting at different pressures for boreholes of different depths by setting different sequence and segmented grouting pressures, thereby ensuring that each hole position receives an appropriate amount of grouting, thereby improving the overall grouting quality; at the same time, it can reduce grout leakage caused by different formation pressures; on the other hand, the grouting amount can also be adjusted according to actual needs to avoid excessive waste of grouting materials and save costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 Schematic diagram of hole arrangement.
[0014] Figure 2 Schematic diagram of the relationship between water pressure and drilling depth.
[0015] Figure 3 Schematic diagram of the relationship between grouting pressure and drilling depth.
[0016] Figure 4 Schematic diagram of the relationship between injection rate and pressure.
[0017] Figure 5 Schematic diagram of the relationship between inspection hole fissure flushing, water pressure and drilling depth. DETAILED DESCRIPTION
[0018] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0019] Embodiment 1: A construction method for curtain grouting of a branch tunnel of a water conveyance tunnel comprises the following steps: Step 1: Carry out preliminary preparations; Step 2, slurry preparation; weigh the slurry materials, solid materials such as cement are measured by weight, and water for slurry is measured by volume; the centralized slurry preparation station prepares 0.5:1 or 1:1 ordinary pure cement slurry according to construction requirements and transports it to the working surface of each unit; at the same time, measure the slurry density and temperature, and keep records; Step 3, drilling construction: use XY-2 geological drilling rig to drill holes, and the holes are drilled in sections from top to bottom; one pilot hole is arranged for each unit of the overlapping curtain grouting; Step 4: Flushing the cracks; the flushing water pressure is 80% of the grouting pressure; Step 5: water pressure test: setting the corresponding segmented water pressure for the segmented rock penetration depth; Step 6, grouting; the grouting is constructed by top-down, segmented blocking, and in-hole circulation grouting method. The lower layer row and the middle layer row II sequence holes are constructed by bottom-up, segmented blocking, and in-hole circulation grouting method; the grouting is set in multiple sections, and different grouting pressures are set in different sections; Step 7: Data detection: 14 days after the completion of unit grouting, conduct visual inspection and core sampling inspection of the overlapping curtain grouting holes and the sealing quality of the inspection holes.
[0020] Embodiment 2: Preliminary preparation work includes: cleaning and leveling the site to avoid water soaking; ensuring that human, machine and material resources are in place; and comprehensive cleaning, maintenance, commissioning, inspection and repair of all construction machinery.
[0021] The weighing error in step 2 is less than 5%; the slurry conveying flow rate is 1.4-2.0m / s; the pure cement slurry in step 2 uses a high-speed mixer, and the stirring time is not less than 30s; the slurry temperature should be maintained between 5-40°C, and those exceeding this standard should be regarded as waste slurry; the slurry should be sieved before use, and the time from preparation to use up: ordinary pure cement slurry does not exceed 4h, and fine cement slurry does not exceed 2h.
[0022] The cement used in step 2 is ordinary Portland cement with a strength grade not less than P.042.5; the cement fineness is preferably such that the residue passing through an 80 μm square hole sieve is not more than 5%; and the admixture used is specifically natural river sand with a particle size not greater than 1.5 mm.
[0023] In step 3, the grouting hole is 24m deep into the rock; the opening diameters of the pilot hole, inspection hole and lifting hole are not less than 89mm, and the final hole diameter is not less than 75mm; the hole position deviation is not more than 10cm; the maximum length of the core sample should be limited to within 3m; once the core sample is found to be stuck or worn, it should be taken out immediately; for a drilling cycle of 1m or more, if the core sample collection rate is less than 80%, the next time should reduce the previous depth by 50%, and then reduce it by 50% successively until 50cm. If the core sample collection rate is very low, the drilling equipment should be replaced or the drilling method should be improved.
[0024] After the drilling in step 4 is completed, a large flow of water is used to flush out the rock powder and slag in the hole. Before grouting, pressurized water should be used to flush the fissures. The flushing time is not more than 20 minutes until the return water is clean.
[0025] The water pressure test in step 5 specifically includes: selecting 10% of the holes in the lower row as pilot holes for single-point water pressure test, and performing simple water pressure test in combination with fissure flushing on the other grouting holes; fissure flushing must be performed separately before the single-point water pressure test.
[0026] The single-point water pressure test is to measure the pressure flow rate every 5 minutes under stable pressure. The difference between the maximum and minimum values in 4 consecutive readings is less than 10% of the final value, or the difference between the maximum and minimum values is less than 1L / min. The final reading is used as the calculated value of the rock permeability q. The simple water pressure test is to measure the water pressure flow rate every 5 minutes under stable pressure for 20 minutes. The final flow value is used as the calculated flow rate, and the result is expressed as permeability q. The water pressure is 80% of the grouting pressure and not more than 1.0MPa.
[0027] The pilot holes are drilled in sections from top to bottom, cored, washed, flushed in fractures, and tested with a single-point water pressure test, and then plugged in sections from bottom to top after reaching the bottom of the hole.
[0028] In step 6, the first section of the plugging position is generally at 0.5m into the rock, but in special cases such as large grouting, leakage of grout, etc., the plugging position can be appropriately moved down, but the blocking position shall not be greater than 1m into the rock at most; the plugging positions of other sections are all about 50cm above the section to be grouted; among them, the grouting segmentation method of the overlap curtain is 1.5m, 3m, and 5m, but in special cases such as rock formation fragmentation leading to hole collapse, drill jamming, and water loss, the segment length can be appropriately reduced, and different grouting pressures are set for different segments. Under normal circumstances, the grouting pressure should reach the design value as soon as possible, and the grouting pressure and injection rate should be adapted, but in the first section or the part with a large injection rate and prone to lifting, graded pressure-raising measures should be adopted for control; The overlapping curtain grouting uses 6 ratios, namely 5:1, 3:1, 2:1, 1:1, 0.8:1 and 0.5:1. The initial water-cement ratio of grouting is 5:1. If there is no pressure and no return when pressing water before grouting or leakage occurs during pressing water, the water-cement ratio can be adjusted to 3:1. When the grouting pressure remains unchanged and the injection rate continues to decrease, or when the injection rate remains unchanged and the pressure continues to increase, the water-cement ratio shall not be changed; when the injection volume of a certain ratio of slurry reaches more than 300L or the grouting time is more than 30min, and the grouting pressure and injection rate have not changed or have not changed significantly, the water-cement ratio should be thickened by one level; when the injection rate is greater than 30L / min, it can be thickened by leaps and bounds according to the specific situation.
[0029] At the maximum design pressure, when the injection rate is no more than 1L / min, continue grouting for 30 minutes to complete the grouting. After the full-hole grouting is completed, the residual slurry in the hole is replaced with a 0.5:1 thick slurry by the catheter grouting method, and the full-hole grouting is sealed with the maximum grouting pressure of the full hole, and the sealing time under pressure is not less than 60 minutes. The remaining part of the hole mouth is sealed with 0.8:1 cement mortar with a strength grade not less than M25 and pressed flush.
[0030] The quality inspection of overlapping curtain grouting is carried out 14 days after the grouting of the corresponding unit is completed. It is mainly based on the analysis of the water pressure results of the inspection hole, combined with the core sampling, panoramic images of the borehole, grouting records and test results for comprehensive evaluation. The inspection hole should collect rock cores and draw a borehole column chart. All rock cores should be photographed and retained for a long time. Among them, the overlapping curtain water pressure inspection adopts a single-point water pressure test. The hole position is designated by the supervision engineer. The number of inspection holes is 5% of the total number of unit grouting holes, and at least one inspection hole is arranged in a unit project; the inspection hole segmentation method is the same as the segmentation method of the overlapping curtain grouting hole in the corresponding unit. The sealing quality of the overlapping curtain grouting hole and the inspection hole should be inspected by the appearance inspection of the hole mouth and the sampling inspection of the core sampling. The number of core sampling inspection holes is 2-3% of the number of sealed holes. The location of the sampling inspection hole is determined based on the appearance inspection and the construction process data. The inspection pass standard is: the permeability is not greater than 1Lu, the pass rate of the first section is 100%, the pass rate of the remaining sections is not less than 95%, the permeability value of the unqualified hole section does not exceed 3Lu, and the distribution is not concentrated, otherwise, supplementary irrigation should be carried out.
[0031] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Any simple modification or equivalent change made to the above embodiment based on the technical essence of the present invention shall fall within the protection scope of the present invention.
Claims
1. A construction method for curtain grouting of a branch tunnel of a water conveyance tunnel, characterized in that: The following steps are involved: Step 1: Carry out preliminary preparations; Step 2, slurry preparation; weigh the slurry materials, solid materials such as cement are measured by weight, and water for slurry is measured by volume; the centralized slurry preparation station prepares 0.5:1 or 1:1 ordinary pure cement slurry according to construction requirements and transports it to the working surface of each unit; at the same time, measure the slurry density and temperature, and keep records; Step 3, drilling construction: use XY-2 geological drilling rig to drill holes, and the holes are drilled in sections from top to bottom; one pilot hole is arranged for each unit of the overlapping curtain grouting; Step 4: Flushing the cracks; the flushing water pressure is 80% of the grouting pressure; Step 5: water pressure test: setting the corresponding segmented water pressure for the segmented rock penetration depth; Step 6, grouting; the grouting is constructed by top-down, segmented blocking, and in-hole circulation grouting method. The lower layer row and the middle layer row II sequence holes are constructed by bottom-up, segmented blocking, and in-hole circulation grouting method; the grouting is set in multiple sections, and different grouting pressures are set in different sections; Step 7: Data detection: 14 days after the completion of unit grouting, conduct visual inspection and core sampling inspection of the overlapping curtain grouting holes and the sealing quality of the inspection holes.
2. A construction method for curtain grouting of a branch tunnel of a water conveyance tunnel according to claim 1, characterized in that: The weighing error in step 2 is less than 5%; the slurry conveying flow rate is 1.4-2.0m / s; the pure cement slurry in step 2 uses a high-speed mixer, and the stirring time is not less than 30s; the slurry temperature should be maintained between 5-40°C, and those exceeding this standard should be regarded as waste slurry; the slurry should be sieved before use, and the time from preparation to use up: ordinary pure cement slurry does not exceed 4h, and fine cement slurry does not exceed 2h.
3. A construction method for curtain grouting of a branch tunnel of a water conveyance tunnel according to claim 1, characterized in that: The cement used in step 2 is ordinary Portland cement with a strength grade not less than P.042.5; the cement fineness is preferably such that the residue passing through an 80 μm square hole sieve is not more than 5%; and the admixture used is specifically natural river sand with a particle size not greater than 1.5 mm.
4. A construction method for curtain grouting of a branch tunnel of a water conveyance tunnel according to claim 1, characterized in that: In step 3, the grouting hole is 24m deep into the rock hole; the opening diameters of the pilot hole, inspection hole and lifting hole are not less than 89mm, and the final hole diameter is not less than 75mm; the hole position deviation is not more than 10cm; the maximum length of the core sample should be limited to 3m; for a drilling cycle of 1m or more, if the core sample collection rate is less than 80%, the next time the depth should be reduced by 50% of the previous time, and then reduced by 50% successively until 50cm.
5. A construction method for curtain grouting of a branch tunnel of a water conveyance tunnel according to claim 1, characterized in that: After the drilling in step 4 is completed, a large flow of water is used to flush out the rock powder and slag in the hole. Before grouting, pressurized water should be used to flush the fissures. The flushing time is not more than 20 minutes until the return water is clean.
6. A construction method for curtain grouting of a branch tunnel of a water conveyance tunnel according to claim 5, characterized in that: The water pressure test in step 5 specifically includes: selecting 10% of the holes in the lower row as pilot holes for single-point water pressure test, and performing simple water pressure test in combination with fissure flushing on the other grouting holes; fissure flushing must be performed separately before the single-point water pressure test.
7. A construction method for curtain grouting of a branch tunnel of a water conveyance tunnel according to claim 6, characterized in that: The pilot holes are drilled in sections from top to bottom, cored, washed, flushed in fractures, and tested with a single-point water pressure test, and then plugged in sections from bottom to top after reaching the bottom of the hole.
8. A construction method for curtain grouting of a branch tunnel of a water conveyance tunnel according to claim 7, characterized in that: In step 6, multiple water-cement ratio levels are set for the overlapping curtain grouting, and the water-cement ratio is changed according to the specific situation to perform the operation; under the maximum design pressure, when the injection rate is not greater than 1L / min, the grouting is continued for 30 minutes to end; after the full-hole grouting is completed, the hole is sealed.
9. A construction method for curtain grouting of a branch tunnel of a water conveyance tunnel according to claim 8, characterized in that: In step 7, the water pressure test of the overlapping curtain is carried out by a single-point water pressure test, and the number of inspection holes is 5% of the total number of unit grouting holes, and at least one inspection hole is arranged in a unit project; the number of core sampling inspection holes is 2-3% of the number of sealed holes, and the inspection qualification standard is: the permeability is not greater than 1Lu, the qualified rate of the first section is 100%, and the qualified rate of the remaining sections is not less than 95%, the permeability value of the unqualified hole section does not exceed 3Lu, and the distribution is not concentrated, otherwise, supplementary irrigation should be carried out.