Water conservancy pipeline laying equipment

By designing automated water conservancy pipeline laying equipment, including tunnel excavation, inner wall treatment and automatic pipe laying functions, the problems of many mechanical equipment and high labor intensity in the existing technology have been solved, and efficient and automated water conservancy pipeline laying has been achieved. It is applicable to in various geographical environments.

CN118998437AInactive Publication Date: 2024-11-22ZHENGYANG COUNTY WATER CONSERVANCY BUREAU
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411065463.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-05
Publication Date
2024-11-22
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing water conservancy pipeline laying method requires the use of a variety of machinery and equipment, and the staff has high labor intensity and low efficiency, which is particularly obvious in the irrigation process of farmland far away from the water source.

Method used

A water conservancy pipeline laying equipment was designed, including substrates, auxiliary wheels, tunnel excavation and conveying mechanisms, tunnel inner wall treatment mechanisms, tunnel automatic pipe laying mechanisms and surface finishing and soil covering mechanisms. Through these mechanisms, automated tunnel excavation and inner wall treatments are realized. Pipe laying and topsoil finishing reduce the use of manual operations and mechanical equipment.

Benefits of technology

It improves the efficiency of water conservancy pipeline laying and the practicality of equipment, reduces labor intensity, can effectively lay in locations where road conditions are poor or cannot be reached by machinery, reduces cost investment, and achieves efficient automated processing.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118998437A_ABST
    Figure CN118998437A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of pipeline laying equipment, and discloses water conservancy pipeline laying equipment which comprises a base plate which serves as a basic component of the whole equipment and is used for assembling and bearing all treatment mechanisms and subordinate lower structural parts of the treatment mechanisms. The auxiliary wheels are arranged at the positions, close to the edges, of the two sides of the base plate and used for assisting the whole equipment to move; and the tunnel excavation conveying mechanism is arranged on one side of the middle of the base plate and used for conducting tunnel excavation on the position where the water conservancy pipeline is laid and conveying soil materials generated in the tunnel excavation process. By adding and arranging the surface layer finishing and soil covering mechanism, after pipeline laying is completed, the tunnel excavation conveying mechanism conveys excavated soil to the rear portion, and then soil on the upper portion of the laid pipeline is treated through scraping, compacting and other treatment in sequence; and the problems of complexity, workload increase and the like caused by manual soil filling of subsequent workers are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of pipeline laying equipment, in particular to water conservancy pipeline laying equipment. Background Art

[0002] Water conservancy projects are projects built to control and allocate natural surface water and groundwater to achieve the purpose of eliminating harm and promoting benefits. They are also called water projects. Water is a valuable resource that is indispensable to human production and life, but its natural state does not fully meet human needs. Only by building water conservancy projects can we control water flow, prevent floods and waterlogging disasters, and regulate and distribute water to meet people's needs for water resources in life and production.

[0003] In some farmlands far away from water sources, crops need to be irrigated when the weather is hot or dry to ensure their normal growth. Since traditional canals will cause a lot of evaporation losses when transporting irrigation water, irrigation water is now generally transported through water conservancy pipes buried under the surface. However, the existing water conservancy pipe laying method uses excavators to dig trenches, and then manually lays pipes. After laying, the surface is covered with soil manually. This treatment method has low work efficiency, and more mechanical equipment is required during the laying process. In addition, the labor intensity of the staff is relatively high, and it is inconvenient to use. Therefore, technical personnel in this field have proposed a water conservancy pipe laying equipment to solve the above-mentioned technical problems. Summary of the invention

[0004] In view of the deficiencies in the prior art, the present invention provides a water conservancy pipeline laying device, which solves the problem that a large amount of mechanical equipment is needed in the prior art water conservancy pipeline laying process and the labor intensity of the workers is high.

[0005] To achieve the above objectives, the present invention is implemented through the following technical solutions: a water conservancy pipeline laying equipment, comprising

[0006] The base plate is the basic component of the whole equipment and is used to assemble and carry each processing mechanism and its subordinate structural parts;

[0007] Auxiliary wheels are arranged on both sides of the base plate near the edge to assist the movement of the whole device;

[0008] The tunnel excavation and conveying mechanism is arranged on one side of the middle part of the base plate, and is used to excavate the tunnel at the location where the water conservancy pipeline is laid, and to convey the soil materials generated during the tunnel excavation process;

[0009] The tunnel inner wall processing mechanism is arranged on both sides of the bottom of the base plate and is used to process both sides of the inner wall of the tunnel excavated by the tunnel excavation and conveying mechanism for burying the pipeline;

[0010] The tunnel automatic pipe laying mechanism is arranged on the other side of the middle part of the base plate and is used to automatically lay the conveying pipeline in the tunnel after the tunnel inner wall processing mechanism has processed it;

[0011] The surface preparation and covering mechanism is arranged at the rear side of the base plate and is used for covering the tunnel after the pipeline is laid and for preparing the surface soil.

[0012] Preferably, the tunnel excavation and conveying mechanism includes an opening, an opening is provided on one side of the middle part of the base plate, an inclined mounting seat is provided in the opening, a transmission chain belt is provided on the outer wall of the inclined mounting seat, and a plurality of bucket seats are equidistantly provided in the middle part of the outer wall of the transmission chain belt.

[0013] Preferably, the tunnel excavation and conveying mechanism also includes a side mounting plate, a side mounting plate is fixedly connected to the side of the top of the base plate away from the opening, a discharge guide plate is fixedly connected to the inner side of the side mounting plate away from the inclined mounting seat, the side mounting plate is rotatably connected to a mounting rod 1 on the inner side close to the inclined mounting seat, strong torsion springs are provided at both ends of the middle part of the mounting rod 1, and a flip adjustment plate is fixedly connected to the middle part of the mounting rod 1.

[0014] Preferably, the tunnel inner wall processing mechanism includes an open-wall seat, and the open-wall seat is fixedly connected to both sides of the bottom end of the substrate near the opening, and the front side surface of the open-wall seat is provided with an inclined flow surface. Two mounting rods are obliquely arranged on both sides of the middle part of the bottom end of the substrate near the edge, and compaction rollers are rotatably connected to the two mounting rods.

[0015] Preferably, the automatic tunnel pipe laying mechanism includes a storage box, which is fixedly connected to one side of the middle part of the top of the base plate, a pipe placement cavity is provided inside the storage box, a hollow cavity is opened in the middle part of the bottom end of the storage box, and a triangular inclined wall is provided in the upper and middle part of the inner side of the pipe placement cavity.

[0016] Preferably, the automatic tunnel pipe laying mechanism also includes a pipe discharge port, and pipe discharge ports are provided at the bottom of both sides of the inner wall of the hollow cavity, and the pipe discharge ports are connected to the interior of the pipe placement cavity, and a pipe outlet is provided on one side of the middle part of the substrate, and both sides of the inner wall of the pipe outlet are inclined, and a guide box is fixedly connected to the pipe outlet, and the inner wall of the guide box is covered with a rubber friction layer.

[0017] Preferably, the surface finishing and covering mechanism includes a connecting frame, which is fixedly connected to the middle part of one side of the base plate, and the other end of the connecting frame is fixedly connected to a finishing seat, and the bottom of both sides of the finishing seat away from the base plate are fixedly connected to extension seats, and the middle and lower parts between the extension seats are rotatably connected to a leveling roller, and the material of the leveling roller is concrete material.

[0018] Preferably, a traction seat is fixedly connected to the middle part of the side of the base plate away from the leveling roller, and a connecting pin is provided on the traction seat.

[0019] Working principle: When irrigating some planting areas that are far away from the water source, it is necessary to lay deep underground water conservancy pipes around the planting areas to drain the water source. Before starting the operation, the staff first moves the equipment through the auxiliary movement of the auxiliary wheels, and at the same time moves the traction equipment to the position where the pipe needs to be laid, and then connects the equipment to the traction equipment through the cooperation of the traction seat and the connecting pin on the base plate, so as to complete the preparation work before starting the operation. After the preparation work is completed, the tunnel excavation and conveying mechanism is started. As the traction equipment moves, the traction equipment drives the equipment to move synchronously while moving, so the base plate drives the transmission chain belt in the opening to move synchronously while moving, and the inclined mounting seat on the transmission chain belt is started. When the inclined mounting seat is started, it drives the bucket seat on it to move synchronously. Multiple bucket seats shovel a tunnel on the soil surface where pipes can be laid while moving, thereby digging out a prototype of a tunnel where pipes can be laid, thereby completing the tunnel. During the excavation operation, after the bucket seat on the transmission chain belt shovels the soil in the bottom soil into the bucket seat, with the continuous driving of the transmission chain belt on the inclined mounting seat, when the bucket seat is driven by the transmission chain belt into the hollow cavity of the storage box, the soil shoveled in the bucket seat rotates continuously with the angle, so that the soil discharged from the bucket seat is discharged to the tail of the base plate in sequence through the flip adjustment plate and the discharge guide plate on the side mounting plate. After the soil in the bucket seat is dumped, with the continuous driving of the transmission chain belt on the bucket seat The bucket seat keeps moving, and presses one end of the flip adjustment plate, so that one end of the flip adjustment plate is pressed by the bucket seat and drives the mounting rod 1 inside to rotate. The mounting rod 1 tightens the strong torsion spring on it while rotating. After the transmission chain drives the bucket seat on it to rotate to the bottom of the flip adjustment plate, the pressure on the flip adjustment plate disappears, and then the strong torsion spring on the mounting rod 1 drives the flip adjustment plate to reset, thereby facilitating the subsequent soil discharge operation, thereby completing the transportation operation of the tunnel soil;While the whole equipment is moving, the tunnel inner wall processing mechanism is started, and while the traction device pulls the whole equipment to move, it drives the base plate to move synchronously. While the base plate moves, it drives the wall opening seat at the bottom to move synchronously. While the wall opening seats on both sides of the bottom of the base plate move, an inclined surface is opened on both sides of the inner wall of the tunnel prototype excavated by the tunnel excavation and conveying mechanism, and while the wall opening seat moves, the scraped loose soil is guided to the rear side of the wall opening seat through the inclined flow surface thereon, and at the same time, the inclined surfaces on both sides of the tunnel are preliminarily leveled through the inclined flow surface on the wall opening seat, so as to prevent the soil on the inclined surface of the tunnel from flowing into the bottom of the tunnel and affecting the subsequent pipeline laying operation. At the same time, as the base plate keeps moving, the base plate moves its bottom while moving. The installation rod 2 drives the synchronous movement, and the installation rod 2 drives the compaction roller on it to move synchronously while moving. The surface of the compaction roller contacts the surfaces on both sides of the tunnel. While the compaction roller rolls and moves, the inner walls on both sides of the tunnel are leveled and compacted, thereby preventing the soil on the side walls of the tunnel from flowing into the bottom of the tunnel and affecting the subsequent pipeline laying operations, thereby completing the leveling and compaction of the inner wall of the tunnel; at the same time, the automatic pipe-laying mechanism of the tunnel is started, and the base plate is driven to move synchronously while the overall equipment is synchronously moved by the traction equipment, and the base plate drives the storage box on it to move synchronously while moving, and the storage box drives the pipe in its pipe placement cavity to move synchronously while moving. When the tunnel excavation and conveying mechanism and the inner wall of the tunnel are After the management mechanism has processed the tunnel to be used, the triangular inclined wall in the pipe placement cavity diverts the pipes inside to the two sides for overlapping and stacking. Then, as the overall equipment moves, the pipes on both sides of the pipe placement cavity pass through the pipe discharge port at the bottom of the storage box and the inclined surface in the side mounting plate into the guide box in turn, and are guided by the inclined surface when entering the guide box. After that, the pipes entering the guide box increase the friction between them and the pipes through the rubber friction layer on its inner wall, slowing down the falling speed of the pipes inside, thereby preventing the pipes in the guide box from being continuously discharged, causing the pipes in the tunnel to accumulate and the pipes to get stuck and the equipment cannot move, thereby completing the automatic pipe laying process in the tunnel. After the road is paved, the surface finishing and covering mechanism is started, and the traction equipment pulls the whole equipment to move simultaneously. The whole equipment moves while driving the base plate to move synchronously. The base plate moves while driving the connecting frame on it to move synchronously. The connecting frame moves synchronously while driving the finishing seat on it to move synchronously. The finishing seat scrapes and flattens the soil discharged from the discharge guide plate while moving, and drives the extension seat on it to move continuously while scraping and flattening the finishing seat. The extension seat drives the leveling roller inside it to roll continuously during the movement, so as to compact the surface soil on the top of the pipeline after the finishing seat has been leveled, thereby completing the finishing and covering of the surface soil after the pipeline is laid. ;

[0020] The present invention provides a water conservancy pipeline laying device, which has the following beneficial effects:

[0021] 1. The present invention increases and sets up a tunnel excavation and conveying mechanism. When laying water conservancy pipelines, on the one hand, the tunnel where the water conservancy pipeline is to be laid can be excavated, thereby avoiding the cost and work efficiency problems caused by using other excavating machines. On the other hand, the practicability and adaptability of the overall equipment can be improved, so that it can be used in some locations with bad road conditions that cannot be reached by excavators.

[0022] 2. The present invention increases and sets up a tunnel inner wall processing mechanism. After the tunnel is excavated into a tunnel prototype by the tunnel excavation and conveying mechanism, an inclined surface is then opened on the inner walls on both sides of the tunnel by a wall opening seat, thereby preventing the soil on both sides of the tunnel prototype from flowing into the bottom of the tunnel and affecting the subsequent normal laying of pipelines. After the processing is completed, the soil on the tunnel side wall is compacted again by roller compaction, thereby improving the flatness and compaction of the tunnel side wall and ensuring the normal progress of the subsequent pipeline laying operation.

[0023] 3. The present invention increases and sets up an automatic pipe-laying mechanism for the tunnel. After the tunnel is excavated and shaped, the pipeline is laid in an automatic and continuous manner. This not only avoids the problems of high labor intensity and low work efficiency caused by manual pipe laying by workers, but also has a high degree of automation. At the same time, the laying efficiency is much faster than manual laying. Moreover, this laying method does not require the assistance of other mechanical equipment during use, and is more convenient to lay.

[0024] 4. The present invention adds and sets a surface finishing and covering mechanism. After the pipeline is laid, the tunnel excavation and transportation mechanism transports the excavated soil to the rear, and then processes the upper soil of the laid pipeline by scraping, compacting, etc., thereby avoiding the tediousness and increased workload caused by manual filling of soil by subsequent staff.

[0025] 5. When laying pipelines, the present invention sequentially carries out continuous process processing methods such as tunnel excavation, inner wall treatment, automatic pipe laying and surface covering. Not only is the laying efficiency high, but also the integrated processing and forming are avoided, thus avoiding the use of other machines and the investment of a large amount of manpower costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 It is a schematic diagram of the front right side structure of the present invention;

[0027] Figure 2 It is a schematic diagram of the front left side structure of the present invention;

[0028] Figure 3It is a schematic diagram of the rear structure of the present invention;

[0029] Figure 4 It is a schematic diagram of the internal structure of the storage box of the present invention;

[0030] Figure 5 It is a schematic diagram of the partial structure of the side mounting plate of the present invention;

[0031] Figure 6 It is a schematic diagram of the partial structure of the flip adjustment plate of the present invention;

[0032] Figure 7 It is a schematic diagram of the bottom structure of the substrate of the present invention;

[0033] Figure 8 It is a schematic diagram of the rear structure of the storage box of the present invention;

[0034] Fig. 9 It is a schematic diagram of the front structure of the storage box of the present invention;

[0035] Fig.10 It is a schematic cross-sectional view of the internal structure of the guide box of the present invention.

[0036] Among them, 1. base plate; 2. inclined mounting seat; 3. bucket seat; 4. transmission chain belt; 5. pipe placement cavity; 6. storage box; 7. connecting frame; 8. extension seat; 9. sorting seat; 10. compaction roller; 11. auxiliary wheel; 12. opening; 13. traction seat; 14. connecting pin; 15. leveling roller; 16. hollow cavity; 17. side mounting plate; 18. discharge guide plate; 19. flip adjustment plate; 20. mounting rod one; 21. inclined surface; 22. strong torsion spring; 23. guide box; 24. mounting rod two; 25. open wall seat; 26. oblique flow surface; 27. pipe outlet; 28. triangular inclined wall; 29. ​​pipe outlet; 30. rubber friction layer. DETAILED DESCRIPTION

[0037] The following will be combined with the drawings of the specification of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0038] Please see attached Figure 1 - Attachment Figure 3 The embodiment of the present invention provides a water conservancy pipeline laying device, comprising

[0039] The base plate 1 is used as the basic component of the whole device and is used to assemble and carry each processing mechanism and its subordinate structural parts; the auxiliary wheels 11 are arranged near the edges of both sides of the base plate 1 and are used to assist the whole device to move;

[0040] A traction seat 13 is fixedly connected to the middle of the side of the base plate 1 away from the leveling roller 15 , and a connecting pin 14 is provided on the traction seat 13 .

[0041] Before starting the operation, the staff first moves the equipment with the assistance of the auxiliary wheel 11, and at the same time moves the traction device to the position where the pipeline needs to be laid, and then connects the equipment with the traction device through the cooperation of the traction seat 13 and the connecting pin 14 on the base plate 1, thereby completing the preparation work before starting the operation.

[0042] Please see attached Figure 4 - Attachment Figure 6 , a tunnel excavation and conveying mechanism, which is arranged on one side of the middle part of the base plate 1, and is used to excavate a tunnel at the location where the water conservancy pipeline is laid, and to convey the soil materials generated during the tunnel excavation process;

[0043] The tunnel excavation and conveying mechanism includes an opening 12. An opening 12 is provided on one side of the middle of the base plate 1. An inclined mounting seat 2 is provided in the opening 12. A transmission chain belt 4 is provided on the outer wall of the inclined mounting seat 2. A plurality of bucket seats 3 are equidistantly provided in the middle of the outer wall of the transmission chain belt 4.

[0044] When the tunnel excavation conveying mechanism is started, as the traction equipment moves, the traction equipment drives the equipment to move synchronously while moving, so the base plate 1 drives the transmission chain belt 4 in the opening 12 to move synchronously while moving, and at the same time, the inclined mounting seat 2 on the transmission chain belt 4 is started, and the inclined mounting seat 2 drives the bucket seat 3 thereon to move synchronously while starting, and multiple bucket seats 3 shovel out a tunnel on the soil surface for laying pipes while moving, thereby digging out a prototype of a tunnel for laying pipes, thereby completing the tunnel excavation operation.

[0045] The tunnel excavation and conveying mechanism also includes a side mounting plate 17, to which the side mounting plate 17 is fixedly connected on the side of the top of the base plate 1 away from the opening 12, to which a discharge guide plate 18 is fixedly connected on the side of the side mounting plate 17 away from the inside of the inclined mounting seat 2, to which a mounting rod 20 is rotatably connected on the side of the side mounting plate 17 close to the inside of the inclined mounting seat 2, to which strong torsion springs 22 are arranged at both ends of the middle part of the mounting rod 20, and to which a flip adjustment plate 19 is fixedly connected in the middle part of the mounting rod 20.

[0046] After the bucket seat 3 on the transmission chain belt 4 shovels the soil in the bottom soil into the bucket seat 3, with the continuous driving of the transmission chain belt 4 on the inclined mounting seat 2, when the bucket seat 3 enters the hollow cavity 16 of the storage box 6 along with the driving of the transmission chain belt 4, the soil shoveled in the bucket seat 3 rotates continuously with the angle, so that the soil discharged from the bucket seat 3 is discharged to the tail end of the base plate 1 in sequence through the flip adjustment plate 19 and the discharge guide plate 18 on the side mounting plate 17.

[0047] After the soil in the bucket seat 3 is dumped, as the bucket seat 3 on the transmission chain 4 continues to move, the bucket seat 3 presses against one end of the flip adjustment plate 19, so that one end of the flip adjustment plate 19 is pressed by the bucket seat 3 and drives the mounting rod 20 therein to rotate. While the mounting rod 20 rotates, the strong torsion spring 22 thereon is tightened. After the transmission chain 4 drives the bucket seat 3 thereon to rotate to the bottom of the flip adjustment plate 19, the pressing force on the flip adjustment plate 19 disappears, and then the strong torsion spring 22 on the mounting rod 20 drives the flip adjustment plate 19 to reset, thereby facilitating the subsequent soil discharge operation, thereby completing the transportation operation of the tunnel soil.

[0048] Please see attached Figure 7 , a tunnel inner wall processing mechanism, which is arranged on both sides of the bottom of the base plate 1, and is used to process both sides of the inner wall of the tunnel excavated by the tunnel excavation and conveying mechanism for burying the pipeline;

[0049] The tunnel inner wall processing mechanism includes a wall opening seat 25, and the wall opening seat 25 is fixedly connected to both sides of the bottom end of the substrate 1 near the opening 12, and the front side surface of the wall opening seat 25 is provided with an inclined flow surface 26. The middle of the bottom end of the substrate 1 is inclinedly provided with a mounting rod 24 near the edge on both sides, and the mounting rod 24 is rotatably connected to the compaction roller 10.

[0050] When the tunnel inner wall processing mechanism is started, the traction device pulls the entire equipment to move and drives the base plate 1 to move synchronously. The base plate 1 drives the wall opening seat 25 at the bottom to move synchronously while moving. When the wall opening seats 25 on both sides of the bottom of the base plate 1 move, an inclined surface is opened on both sides of the inner wall of the tunnel prototype excavated by the tunnel excavation and conveying mechanism. When the wall opening seat 25 moves, the scraped loose soil is guided to the rear side of the wall opening seat 25 through the inclined flow surface 26 thereon. At the same time, the inclined surfaces on both sides of the tunnel are preliminarily leveled through the inclined flow surface 26 on the wall opening seat 25, thereby preventing the soil on the inclined surface of the tunnel from flowing into the bottom of the tunnel and affecting the subsequent pipeline laying operations.

[0051] At the same time, as the base plate 1 keeps moving, the base plate 1 drives the mounting rod 24 at its bottom to move synchronously while moving. The mounting rod 24 drives the compaction roller 10 thereon to move synchronously while moving. The surface of the compaction roller 10 contacts the surfaces on both sides of the tunnel. While the compaction roller 10 rolls, the inner walls on both sides of the tunnel are leveled and compacted, thereby preventing the soil on the side walls of the tunnel from flowing into the bottom of the tunnel and affecting the subsequent pipeline laying operations, thereby completing the leveling and compaction of the inner walls of the tunnel.

[0052] Please see attached Figure 8 - Attachment Fig.10 , a tunnel automatic pipe laying mechanism, which is arranged on the other side of the middle of the base plate 1, and is used to automatically lay a conveying pipeline in the tunnel after the tunnel inner wall processing mechanism has processed it;

[0053] The automatic tunnel pipe laying mechanism includes a storage box 6, which is fixedly connected to one side of the middle of the top of the base plate 1, and a pipe placement cavity 5 is arranged inside the storage box 6. A hollow cavity 16 is opened in the middle of the bottom end of the storage box 6, and a triangular inclined wall 28 is arranged in the middle and upper part of the inner side of the pipe placement cavity 5.

[0054] The automatic pipe-laying mechanism of the tunnel is started, and while the whole equipment is moved synchronously by the traction equipment, it drives the base plate 1 to move synchronously, and while the base plate 1 moves, it drives the storage box 6 thereon to move synchronously, and while the storage box 6 moves, it drives the pipes in its pipe placement cavity 5 to move synchronously. When the tunnel excavation and conveying mechanism and the tunnel inner wall processing mechanism have completed processing the tunnel to be used, the triangular inclined wall 28 in the pipe placement cavity 5 will divert the pipes inside to both sides for overlapping stacking.

[0055] The automatic tunnel pipe laying mechanism also includes a pipe discharge port 29. The bottom of both sides of the inner wall of the hollow cavity 16 are provided with a pipe discharge port 29, and the pipe discharge port 29 is connected to the interior of the pipeline placement cavity 5. A pipe outlet 27 is provided on one side of the middle part of the base plate 1. Both sides of the inner wall of the pipe outlet 27 are arranged with inclined surfaces 21. A guide box 23 is fixedly connected to the pipe outlet 27, and the inner wall of the guide box 23 is covered with a rubber friction layer 30.

[0056] Then, as the entire equipment moves, the pipes on both sides of the pipe placement cavity 5 enter the guide box 23 through the pipe discharge port 29 at the bottom of the storage box 6 and the inclined surface 21 in the side mounting plate 17 in turn, and are guided by the inclined surface 21 when entering the guide box 23. Thereafter, the pipes entering the guide box 23 increase the friction between the pipes and the pipes through the rubber friction layer 30 on its inner wall, slowing down the falling speed of the pipes inside, thereby preventing the pipes in the guide box 23 from being continuously discharged, causing the pipes in the tunnel to accumulate and the pipes to get stuck and the equipment cannot move, thereby completing the automatic pipe laying process in the tunnel.

[0057] Please see attached Figure 1 - Attachment Figure 3 The surface finishing and covering mechanism is arranged at the rear side of the base plate 1 and is used for covering the tunnel after the pipeline is laid and finishing the surface soil.

[0058] The surface finishing and covering mechanism includes a connecting frame 7, which is fixedly connected to the middle part of one side of the base plate 1, and the other end of the connecting frame 7 is fixedly connected to a finishing seat 9, and the bottoms of the finishing seats 9 on both sides away from the base plate 1 are fixedly connected to extension seats 8, and the middle and lower parts between the extension seats 8 are rotatably connected to a leveling roller 15, and the material of the leveling roller 15 is concrete material.

[0059] When the surface finishing and covering mechanism is started, the traction equipment pulls the entire equipment to move simultaneously, and the movement of the entire equipment drives the base plate 1 to move synchronously, and the movement of the base plate 1 drives the connecting frame 7 thereon to move synchronously, and the connecting frame 7 drives the finishing seat 9 thereon to move synchronously, and the finishing seat 9 will scrape and level the soil discharged from the discharge guide plate 18 while moving, and drive the extension seat 8 thereon to move continuously while scraping and leveling the finishing seat 9, and the extension seat 8 drives the leveling roller 15 therein to roll continuously during the movement, so as to compact the surface soil on the upper part of the pipeline after the leveling treatment by the finishing seat 9, thereby completing the finishing and covering of the surface soil after the pipeline is laid.

[0060] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A water conservancy pipeline laying equipment, characterized in that: include A base plate (1), which is a basic component of the overall device and is used to assemble and carry various processing mechanisms and their subordinate structural components; Auxiliary wheels (11), which are arranged on both sides of the base plate (1) near the edge and are used to assist the overall device in moving; A tunnel excavation and conveying mechanism is arranged on one side of the middle part of the base plate (1) and is used to excavate a tunnel at the location where the water conservancy pipeline is laid, and to convey soil materials generated during the tunnel excavation process; A tunnel inner wall processing mechanism, which is arranged on both sides of the bottom of the base plate (1) and is used to process both sides of the inner wall of the tunnel excavated by the tunnel excavation and conveying mechanism for burying the pipeline; An automatic tunnel pipe laying mechanism, which is arranged on the other side of the middle part of the base plate (1) and is used to automatically lay a conveying pipeline in the tunnel after the tunnel inner wall processing mechanism has processed the tunnel inner wall; The surface finishing and covering mechanism is arranged on the rear side of the base plate (1) and is used to cover the tunnel after the pipeline is laid and to finish the surface soil.

2. A water conservancy pipeline laying equipment according to claim 1, characterized in that: The tunnel excavation and conveying mechanism comprises an opening (12), wherein the opening (12) is provided on one side of the middle of the base plate (1), an inclined mounting seat (2) is provided in the opening (12), a transmission chain belt (4) is provided on the outer wall of the inclined mounting seat (2), and a plurality of bucket seats (3) are equidistantly provided in the middle of the outer wall of the transmission chain belt (4).

3. A water conservancy pipeline laying equipment according to claim 2, characterized in that: The tunnel excavation and conveying mechanism also includes a side mounting plate (17), a side of the top of the base plate (1) away from the opening (12) is fixedly connected to the side mounting plate (17), a side of the side mounting plate (17) away from the inside of the inclined mounting seat (2) is fixedly connected to a discharge guide plate (18), a side of the side mounting plate (17) close to the inside of the inclined mounting seat (2) is rotatably connected to a mounting rod (20), strong torsion springs (22) are provided at both ends of the middle of the mounting rod (20), and a flip adjustment plate (19) is fixedly connected to the middle of the mounting rod (20).

4. The water conservancy pipeline laying equipment according to claim 1, characterized in that: The tunnel inner wall processing mechanism comprises a wall opening seat (25), and the wall opening seat (25) is fixedly connected to both sides of the bottom end of the base plate (1) near the opening (12), and the front side surface of the wall opening seat (25) is provided with an oblique flow surface (26), and the middle of the bottom end of the base plate (1) is inclinedly provided with a second mounting rod (24) near the edge on both sides, and the second mounting rod (24) is rotatably connected to a compaction roller (10).

5. The water conservancy pipeline laying equipment according to claim 1, characterized in that: The tunnel automatic pipe laying mechanism comprises a storage box (6), a storage box (6) is fixedly connected to one side of the middle part of the top end of the base plate (1), a pipe placement cavity (5) is arranged inside the storage box (6), a hollow cavity (16) is opened in the middle part of the bottom end of the storage box (6), and a triangular inclined wall (28) is arranged in the middle and upper part of the inner side of the pipe placement cavity (5).

6. The water conservancy pipeline laying equipment according to claim 5, characterized in that: The tunnel automatic pipe laying mechanism also includes a pipe discharge port (29), the bottom of both sides of the inner wall of the hollow cavity (16) are provided with a pipe discharge port (29), and the pipe discharge port (29) is communicated with the interior of the pipe placement cavity (5), a pipe outlet (27) is provided on one side of the middle part of the base plate (1), both sides of the inner wall of the pipe outlet (27) are arranged in the form of inclined surfaces (21), a guide box (23) is fixedly connected inside the pipe outlet (27), and the inner wall of the guide box (23) is covered with a rubber friction layer (30).

7. The water conservancy pipeline laying equipment according to claim 1, characterized in that: The surface finishing and covering mechanism comprises a connecting frame (7), the connecting frame (7) is fixedly connected to the middle of one side of the base plate (1), the other end of the connecting frame (7) is fixedly connected to a finishing seat (9), the bottoms of both sides of the finishing seat (9) away from the base plate (1) are fixedly connected to extension seats (8), and the middle and lower parts between the extension seats (8) are rotatably connected to a leveling roller (15), and the material of the leveling roller (15) is concrete material.

8. The water conservancy pipeline laying equipment according to claim 1, characterized in that: It also comprises a traction seat (13), the traction seat (13) being fixedly connected to the middle of one side of the base plate (1) away from the leveling roller (15), and a connecting pin (14) being arranged on the traction seat (13).