Modularized installation method and device for electromechanical integrated pipeline

Through BIM technology, the electromechanical pipeline model is integrated and modular design and construction simulation is carried out, the construction complexity caused by unreasonable design is solved, construction efficiency and management efficiency are improved, and the standardization and industrial construction of electromechanical pipelines are realized.

CN119004023APending Publication Date: 2024-11-22CHANGLU CONSTR ENG GRP CO LTD

Patent Information

Application Number
CN202411050690.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-01
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

There are conflicts such as pipeline crossing and collision caused by unreasonable design in existing mechanical and electrical pipeline design and construction. The construction is difficult and the management efficiency is low. Inappropriate coordination between design and construction leads to frequent rework and complex management.

Method used

BIM software is used to establish the integration of electromechanical pipeline models and structural models, and to perform collision detection and optimization. Through modular design and construction simulation, design and construction integration is realized. The model is displayed using Navisworks software, and equipment production and assembly is carried out in the prefabricated processing site. Finally, installation and functional testing are carried out at the construction site.

Benefits of technology

It improves the design accuracy, reduces problems in construction, realizes real-time sharing of information and data among multiple professions, reduces slow progress and stagnation of construction, strengthens the construction efficiency of engineering, and realizes standardized and industrialized construction of mechanical and electrical pipelines.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119004023A_ABST
    Figure CN119004023A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of electromechanical integrated pipeline installation, and particularly discloses a modular installation method and device for electromechanical integrated pipelines, and the method comprises the steps: 1, building each professional electromechanical pipeline model through BIM software, integrating each professional electromechanical pipeline model with a structure model in a unitized module manner, and carrying out the modular installation of the electromechanical integrated pipelines; performing collision detection on the BIM comprehensive model; step 2, extracting data through a split model to carry out collaborative deepening and corresponding limitation analysis, realizing a technical scheme of modular construction, and carrying out modular processing on the optimized BIM comprehensive model; 3, engineering information data are integrated through modular design, collaborative management among multiple specialties is facilitated, and a design and construction integrated sharing mode is formed; according to the method, modeling and collaborative deepening of electromechanical pipelines are carried out through the BIM technology, problems possibly occurring in construction are optimized in the design stage, and the design precision is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of electromechanical integrated pipeline installation, and in particular relates to a modular installation method and device for electromechanical integrated pipelines. Background Art

[0002] In recent years, the scale of my country's construction industry has been expanding with the continuous improvement of social science and technology. While people are constantly improving their living standards, they are also increasing their requirements for the aesthetics of space design and the full utilization of space. Correspondingly, the construction tasks and demand for electromechanical pipeline engineering are also increasing with the changes in the project environment. As a result, engineering problems arising from engineering technology or management appear to be more complex and diverse.

[0003] At present, the modular design and integrated application of complex electromechanical pipelines are relatively low. If the spatial layout of pipelines is not fully planned in the design stage, it will increase the difficulty of construction in the construction stage. For example, when laying water supply and drainage, HVAC, and cable trays, unreasonable layout may cause intersections or collisions between pipelines, frequent rework due to limited construction site space, improper coordination between design and construction professionals, frequent cross-processes, and high difficulty in site management, which takes up a lot of management time and energy of the management unit and makes management efficiency low.

[0004] Therefore, it is necessary to propose a modular installation method and device for electromechanical integrated pipelines to at least partially solve the problems existing in the prior art.

[0005] The above information disclosed in this background technology is only used to increase the understanding of the background technology of the present invention and therefore, it may include information that does not constitute the prior art known to ordinary technicians in this field. Summary of the invention

[0006] The purpose of the present invention is to provide a modular installation method and device for electromechanical integrated pipelines to solve the problems raised in the above-mentioned background technology.

[0007] To achieve the above object, the present invention provides the following technical solutions:

[0008] A modular installation method for electromechanical integrated pipelines, comprising:

[0009] Step 1: Use BIM software to build the electromechanical pipeline models of each discipline, integrate the electromechanical pipeline models of each discipline with the structural model in a unitized module, and then perform collision detection on the BIM comprehensive model;

[0010] Step 2: Extract data through splitting the model for collaborative deepening and corresponding restricted analysis, realize the technical solution of modular construction, and modularize the optimized BIM comprehensive model;

[0011] Step 3: Integrate engineering information data through modular design to facilitate collaborative management among multiple disciplines and form a shared model of integrated design and construction;

[0012] Step 4: Integrate the modules and perform collision detection. Then use the integrated model and information integration to simulate the module construction and display it in an intuitive way through Navisworks software.

[0013] Step 5: Combine the model in step 4 and produce and cut the equipment in the prefabrication processing plant according to the actual design requirements, and then transport it to the construction site for assembly;

[0014] Step 6: Perform functional tests on the assembled modules, then install them into the building structure and enter the installed module information into the integrated model to form an actual construction model.

[0015] Preferably, in step one, a three-dimensional model is established according to the degree of refinement required for the model, and after the model construction is completed, the model is integrated through Navisworks software, and a collision check is performed on the BIM integrated model in the Navisworks software.

[0016] Preferably, the collision check is usually divided into two steps: first, a comprehensive collision check is performed on the electromechanical pipelines, and then the collision between the pipelines and components is detected, a collision check report is generated, and the problems in the model are accurately found, and then pipeline avoidance is implemented in the BIM software, so as to make full use of the space, optimize the layout of the pipelines, and solve the problems that may arise in the construction phase in advance in the design phase.

[0017] Preferably, in step 2, all pipe bridge equipment in the electromechanical pipelines are split according to standard modules, and the same module is used for pipes of the same diameter to facilitate interoperability and compatibility of subsequent pipe fittings. The types of pipes are classified according to standard size information, which is conducive to subsequent prefabrication processing.

[0018] Preferably, in step 2, a support bracket model is established according to the design scheme of the support bracket, and is integrated into the BIM comprehensive model for collision detection. Thereafter, the force analysis software is used to perform force evaluation on the overall support bracket model, and the support bracket model is optimized and adjusted according to the evaluation results.

[0019] When designing supports and hangers, hole reservation design is carried out. First, the drawings are reviewed and the relevant hole burying plan is prepared. Secondly, according to the design requirements, the "three-level" measurement system is implemented to measure and lay out the construction site, and the positions of the layout are marked to ensure the accuracy of the position while meeting the design requirements.

[0020] Preferably, in step 2, the collaborative deepening includes the deepening of support and hanger deployment and the comprehensive collaborative deepening of electromechanical pipelines, wherein the support and hanger layout deepening adopts a comprehensive support and hanger solution with flexible combination and assembly, and uses BIM technology to realize the parameterization of supports and hangers, and the comprehensive collaborative deepening of electromechanical pipelines arranges the space reasonably under the standards that meet the design specifications, and assigns corresponding parameter values ​​to each professional electromechanical pipeline, so that it can express the model properties more accurately.

[0021] In step two, the electromechanical pipelines are integrated onto the same support and hanger (including pipeline bridge) according to the professional electromechanical pipeline models. Then, through precise hole reservation, the components are assembled using the structure as a carrier, and the overall structure is used as a standard unit module for subsequent prefabrication and on-site construction.

[0022] Preferably, in step three, in the process of standardized integration of the design and construction stages, an information technology integration involving the integration of participants and the intersection of professions in the operation is involved, ultimately achieving overall control management of cost, progress and quality.

[0023] Preferably, in step 4, the simulation process also involves BIM 5D simulation of time information and cost information, and Fabrication software is used to perform segmented optimization of each professional electromechanical pipeline; in step 5, before prefabrication, the design drawings are decomposed in detail, and then the decomposed contents are parametrically modeled using BIM software according to actual dimensions and processing procedures.

[0024] Preferably, in step six, the module installation process is integrated and coordinated with other systems, and after the installation is completed, a complete actual construction model and construction documents are delivered to the owner and maintenance team to facilitate future operations and maintenance.

[0025] During the installation process, connection work is carried out between modules, including pipe welding, threaded connection, electrical pipeline connection, etc., and functional tests include water pressure / water flow test, electrical performance test, etc. Other systems such as building automation system, fire protection system, etc., record the prefabricated production number information on the module during installation, and mark special situations to facilitate subsequent search and replacement.

[0026] A modular installation device for an electromechanical integrated pipeline, comprising at least one processor; and a memory communicatively connected to the at least one processor; wherein the memory stores a computer program executable by the at least one processor, and the computer program is executed by the at least one processor so that the at least one processor can execute a modular installation method for an electromechanical integrated pipeline as described in any one of the above.

[0027] Compared with the prior art, the present invention has the following beneficial effects:

[0028] The present invention uses BIM technology to model and collaboratively deepen the electromechanical pipelines, optimizes the problems that may arise in the construction during the design phase, improves the design accuracy, adopts modular design, integrates project data and combines the effects of construction simulation, enables all participants to share integrated information data in real time at various stages such as design and construction, reduces the phenomenon of slow progress and construction stagnation due to different professional levels, rationally arranges complex pipeline equipment, enhances the efficiency of engineering construction, and realizes the standardization and industrialization of prefabricated electromechanical pipeline construction under high-standard complex construction projects.

[0029] The above summary is for illustrative purposes only and is not intended to be limiting in any way. In addition to the illustrative aspects, embodiments and features described above, further aspects, embodiments and features of the present invention will be readily apparent by reference to the accompanying drawings and the following detailed description. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] Figure 1 It is a flow chart of the installation method of the present invention. DETAILED DESCRIPTION

[0031] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0032] Example:

[0033] See also Figure 1 As shown, a modular installation method for electromechanical integrated pipelines comprises:

[0034] Step 1: Use BIM software to build the electromechanical pipeline models of each discipline, integrate the electromechanical pipeline models of each discipline with the structural model in a unitized module, and then perform collision detection on the BIM comprehensive model;

[0035] Step 2: Extract data through splitting the model for collaborative deepening and corresponding restricted analysis, realize the technical solution of modular construction, and modularize the optimized BIM comprehensive model;

[0036] Step 3: Integrate engineering information data through modular design to facilitate collaborative management among multiple disciplines and form a shared model of integrated design and construction;

[0037] Step 4: Integrate the modules and perform collision detection. Then use the integrated model and information integration to simulate the module construction and display it in an intuitive way through Navisworks software.

[0038] Step 5: Combine the model in step 4 and produce and cut the equipment in the prefabrication processing plant according to the actual design requirements, and then transport it to the construction site for assembly;

[0039] Step 6: Perform functional tests on the assembled modules, then install them into the building structure and enter the installed module information into the integrated model to form an actual construction model.

[0040] In step one, a three-dimensional model is established according to the required level of refinement of the model. After the model is built, the model is integrated through Navisworks software, and a collision check is performed on the BIM integrated model in Navisworks software.

[0041] In step two, all pipe bridge equipment in the electromechanical pipelines are split according to standard modules, and the same module is used for pipes of the same diameter to facilitate interoperability of pipe fittings in the later stage. Pipe types are classified according to standard size information, which is conducive to the later prefabrication processing. A support and hanger model is established according to the design plan of the support and hanger, and it is integrated into the BIM comprehensive model for collision detection. After that, the force analysis software is used to evaluate the force of the overall support and hanger model, and the support and hanger model is optimized and adjusted according to the evaluation results.

[0042] In step 2, the split model is subjected to constraint analysis, including constraint analysis of each participant, pipe constraint analysis, working surface constraint analysis and machinery (transportation) constraint analysis. Constraint analysis of each participant: the owner unit makes project planning based on the performance requirements of the project, determines control indicators such as the complexity and cost of the project, and is responsible for the review of the entire project design plan; the design unit is mainly constrained by the degree of realization of the technical requirements of the engineering project in the design; the construction unit is mainly constrained by the collision and conflict caused by the design results of the designer during construction; pipe constraint analysis: the main constraint of the support and hanger is whether the design of the support and hanger meets the construction conditions; the main constraint of the pipeline bridge is the effective use of the equipment and materials of the pipeline bridge by the design unit in a limited space.

[0043] In step two, the coordinated deepening includes the deepening of support and hanger deployment and the comprehensive coordinated deepening of electromechanical pipelines. The support and hanger layout deepening adopts a comprehensive support and hanger solution with flexible combination and assembly, and uses BIM technology to realize the parameterization of supports and hangers. The comprehensive coordinated deepening of electromechanical pipelines arranges the space reasonably under the standards that meet the design specifications, and assigns corresponding parameter values ​​to each professional electromechanical pipeline, so that it can express the model properties more accurately.

[0044] In step three, during the standardized integration of the design and construction stages, an information technology integration involving the integration of participants and the intersection of disciplines in the operation is carried out to ultimately achieve overall control management of cost, schedule, and quality.

[0045] In step four, the simulation process also involves BIM 5D simulation of time information and cost information, and uses Fabrication software to optimize the segmented mechanical and electrical pipelines of various disciplines; in step five, before prefabrication, the design drawings are broken down in detail, and then BIM software is used to perform parametric modeling of the decomposed content based on the actual size and processing procedures.

[0046] Assume that a bolt with material A325 and D=19.5 is selected, a model is established and a section is selected on the section profile, and the attributes such as size and connection method are modified. At the same time, the CNC cutting machine is connected to the CNC intelligent machine to realize the process of numerical cutting, cutting and numbering, reduce the cost of manual cutting, and speed up the efficiency of material prefabrication and delivery.

[0047] In step six, the module installation process is integrated and coordinated with other systems, and after the installation is completed, a complete actual construction model and construction documents are delivered to the owner and maintenance team to facilitate future operations and maintenance.

[0048] A modular installation device for an electromechanical integrated pipeline, comprising at least one processor; a memory communicatively connected to the at least one processor; wherein the memory stores a computer program executable by the at least one processor, and the computer program is executed by the at least one processor so that the at least one processor can execute a modular installation method for an electromechanical integrated pipeline as any one of the above items.

[0049] As can be seen from the above, the present invention uses BIM technology to model and collaboratively deepen the electromechanical pipelines, optimizes the problems that may arise in the construction during the design stage, improves the design accuracy, adopts modular design, integrates project data and combines the effects of construction simulation, enables all participants to share integrated information data in real time at various stages such as design and construction, reduces the phenomenon of slow progress and construction stagnation due to different professional levels, reasonably arranges complex pipeline equipment, enhances the efficiency of engineering construction, and realizes the standardization and industrialization of prefabricated electromechanical pipeline construction under high-standard complex construction projects.

[0050] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "examples", "specific examples" or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine different embodiments or examples described in this specification and the features of different embodiments or examples, unless they are contradictory.

[0051] In the drawings of the embodiments disclosed in the present invention, only the structures involved in the embodiments disclosed in the present invention are involved, and other structures can refer to the general design. In the absence of conflict, the same embodiment and different embodiments of the present invention can be combined with each other.

[0052] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A modular installation method for electromechanical integrated pipelines, characterized in that: include: Step 1: Use BIM software to build the electromechanical pipeline models of each discipline, integrate the electromechanical pipeline models of each discipline with the structural model in a unitized module, and then perform collision detection on the BIM comprehensive model; Step 2: Extract data through splitting the model for collaborative deepening and corresponding restricted analysis, realize the technical solution of modular construction, and modularize the optimized BIM comprehensive model; Step 3: Integrate engineering information data through modular design to facilitate collaborative management among multiple disciplines and form a shared model of integrated design and construction; Step 4: Integrate the modules and perform collision detection. Then use the integrated model and information integration to simulate the module construction and display it in an intuitive way through Navisworks software. Step 5: Combine the model in step 4 and produce and cut the equipment in the prefabrication processing plant according to the actual design requirements, and then transport it to the construction site for assembly; Step 6: Perform functional tests on the assembled modules, then install them into the building structure and enter the installed module information into the integrated model to form an actual construction model.

2. A modular installation method for electromechanical integrated pipelines according to claim 1, characterized in that: In the step 1, a three-dimensional model is established according to the degree of refinement required for the model. After the model is built, the model is integrated through the Navisworks software, and a collision check is performed on the BIM integrated model in the Navisworks software.

3. A modular installation method for electromechanical integrated pipelines according to claim 2, characterized in that: In step 2, all pipe bridge equipment in the electromechanical pipeline is split according to the standard module, and the same module is used for pipes of the same diameter to facilitate interoperability and compatibility of pipe fittings in the later use. The types of pipes are classified according to standard size information, which is conducive to the later prefabrication processing.

4. The modular installation method of electromechanical integrated pipeline according to claim 3 is characterized by: In step 2, a support bracket model is established according to the design plan of the support bracket, and is integrated into the BIM comprehensive model for collision detection. Then, the force analysis software is used to evaluate the force of the overall support bracket model, and the support bracket model is optimized and adjusted according to the evaluation results.

5. The modular installation method of electromechanical integrated pipeline according to claim 4 is characterized by: In step 2, the collaborative deepening includes the deepening of support and hanger deployment and the comprehensive collaborative deepening of electromechanical pipelines. The support and hanger layout deepening adopts a comprehensive support and hanger solution with flexible combination and assembly, and uses BIM technology to realize the parameterization of supports and hangers. The comprehensive collaborative deepening of electromechanical pipelines arranges the space reasonably under the standards that meet the design specifications, and assigns corresponding parameter values ​​to each professional electromechanical pipeline, so that it can express the model attributes more accurately.

6. A modular installation method for electromechanical integrated pipelines according to claim 5, characterized in that: In step three, during the standardized integration of the design and construction stages, an information technology integration involving the integration of participants and the intersection of disciplines in the operation is involved, ultimately achieving overall control management of cost, schedule, and quality.

7. The modular installation method of electromechanical integrated pipeline according to claim 6 is characterized by: In step 4, the simulation process also involves BIM 5D simulation of time information and cost information, and Fabrication software is used to optimize the mechanical and electrical pipelines of each specialty in sections; In step five, before prefabrication, the design drawings are broken down in detail, and then the broken down contents are parametrically modeled using BIM software based on actual dimensions and processing procedures.

8. The modular installation method of electromechanical integrated pipeline according to claim 7 is characterized by: In step six, the module installation process is integrated and coordinated with other systems, and after the installation is completed, a complete actual construction model and construction documents are delivered to the owner and maintenance team to facilitate future operations and maintenance.

9. A modular installation device for electromechanical integrated pipelines, characterized in that: It includes at least one processor; a memory communicatively connected to the at least one processor; wherein the memory stores a computer program executable by the at least one processor, and the computer program is executed by the at least one processor so that the at least one processor can execute a modular installation method for an electromechanical integrated pipeline as described in any one of claims 1 to 8.

Citation Information

Patent Citations

  • Complex pipeline collision optimization method of subway electromechanical engineering

    CN103093061A

  • Method for solving problem of electromechanical integrated pipeline arrangement

    CN107066750A

  • Method for finely designing electromechanical pipeline based on BIM technology

    CN110110473A

  • Electromechanical full-assembly type three-dimensional forward design method based on BIM

    CN113761632A

Cited By

  • Pipeline construction data analysis method based on BIM

    CN119939837A

  • A BIM-based data analysis method for pipeline construction

    CN119939837B

  • Front support type grouting steel pipe positioning and arranging construction method in building support construction system based on BIM (Building Information Modeling) technology

    CN120354502A

  • Fabricated building design method based on BIM software

    CN121959722A