Transport vehicle, bridge erecting device and bridge erecting machine transfer girder erecting method

By installing a load platform and transfer bracket on the transport vehicle, and using the frame body and mobile mechanism to support the arm, the problem of low stability of the bridge mounter during transportation and installation is solved, and construction safety and efficiency are improved.

CN119018033APending Publication Date: 2024-11-26CHINA RAILWAY SHISIJU GROUP CORP +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411206360.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-30
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

During the transportation and installation of existing bridge studs, the stability of the arm of the existing bridge studs is low, which affects construction safety, especially during the movement of the second column.

Method used

A transport vehicle is designed, including a load platform and a transfer bracket. The transfer bracket is slidably connected to the load platform along the longitudinal direction of the arm through the frame body and the moving mechanism. It can telescopicly support the arm, improve the stability of the arm, and be in the via hole. Provide continuous support in front of preparation and beam mount steps.

Benefits of technology

By lifting the stability of the arm, the safety and efficiency of the bridge erecting machine during transportation and installation are improved, ensuring the smooth progress of the bridge erecting operation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119018033A_ABST
    Figure CN119018033A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of construction mechanical equipment, and provides a transport vehicle, a bridge erecting device and a bridge erecting machine transfer girder erecting method. The transport vehicle comprises a load platform and a transfer support. The load platform extends in the longitudinal direction of the vehicle arm. The transfer support comprises a frame body and a moving mechanism. A moving mechanism is arranged at one end of the frame body, the other end of the frame body is used for abutting against the lower side of the arm, and the frame body is configured to be capable of stretching relative to the load platform to support the arm; the frame body is slidably connected with the load platform in the longitudinal direction of the arm through the moving mechanism. When the machine arm moves relative to the second supporting column for preparation before hole passing, the frame body can move along with the machine arm through the moving mechanism while supporting the machine arm, and the transfer support continuously supports the machine arm; and after the transport vehicle transports the beam pieces to the lower side of the machine arm, the transfer support extends to assist in supporting the machine arm, and the stability of the bridge girder erection machine during preparation and beam piece hoisting before hole passing is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of construction machinery and equipment, and in particular to a transport vehicle, a bridge erection device, and a method for transporting and erecting beams by a bridge erection machine. Background Art

[0002] The bridge erection machine is a common equipment for transporting beams and placing them on the preset bridge piers. The bridge erection machine includes a machine arm and multiple pillars, one of which is set in the middle of the machine arm as the second pillar, which can be extended and retracted relative to the machine arm, and the second pillar can slide relative to the machine arm. When the second pillar is supported on the bridge deck, the machine arm slides relative to the second pillar to adjust the distance between the front end of the machine arm and the second pillar. After the bridge erection machine moves and is erected through the hole, the second pillar can be supported on the bridge deck of the bridge head, and the front end of the machine arm can move to the bridge pier in the downstream direction of the bridge head.

[0003] Usually, a transport vehicle is used to transport the bridge erection machine. A transfer bracket is set on the platform of the transport vehicle. The transport vehicle is on the lower side of the machine arm, so that the transfer bracket supports the machine arm, so that the transport vehicle moves and drives the bridge erection machine to move. When the bridge erection machine is transferred from the transport vehicle to the bridge deck for preparation work before passing the hole, the second column of the machine arm will extend outside the platform of the transport vehicle to lift the machine arm, so that the machine arm is separated from the transfer bracket, and then the machine arm moves relative to the second column to adjust the distance between the front end of the machine arm and the second column to prepare for the subsequent passing hole operation; the second column has limited support for the machine arm, and the stability of the machine arm during the movement of the second column is low, which affects the safety of the bridge erection machine during construction. Summary of the invention

[0004] In order to solve the above technical problems or at least partially solve the above technical problems, the present disclosure provides a transport vehicle, a bridge erecting device and a bridge erecting machine transport and beam erecting method.

[0005] A first aspect of the present disclosure provides a transport vehicle for carrying the arm of a bridge erecting machine, comprising a load platform and a transfer bracket;

[0006] The load platform extends in the longitudinal direction of the machine arm;

[0007] The transport support comprises a frame body and a moving mechanism;

[0008] A moving mechanism is provided at one end of the frame body, and the other end is used to abut against the lower side of the machine arm, and the frame body is configured to be able to extend and retract relative to the load platform to support the machine arm;

[0009] The frame body is slidably connected to the load platform along the longitudinal direction of the machine arm through the moving mechanism.

[0010] Optionally, the moving mechanism includes a mechanism body, a driving member and a track;

[0011] The track is installed on the load platform and extends along the longitudinal direction of the arm. The mechanism body is connected to the frame body and is slidably connected to the track. The driving member is installed on the mechanism body and is transmission-connected to the track so that the driving member drives the mechanism body to slide relative to the track.

[0012] Optionally, the frame body includes a top beam, a telescopic drive member and a bottom beam assembly;

[0013] The bottom beam assembly is arranged opposite to the top beam, and the telescopic driving member is connected between the bottom beam assembly and the top beam, so that the telescopic driving member drives the bottom beam assembly and the top beam to move closer to and away from each other;

[0014] The top beam is in contact with the lower side of the machine arm, and the moving mechanism is installed on a side of the bottom beam assembly away from the top beam.

[0015] Optionally, the bottom beam assembly includes a lower cross beam, two guide columns and two movable beams;

[0016] The lower cross beam is arranged opposite to the top beam and extends in the lateral direction of the machine arm, and the moving mechanism is installed on a side of the lower cross beam facing away from the top beam;

[0017] The two guide posts are arranged at two ends of the lower cross beam, and the guide posts extend toward the top beam, and the top beam is slidably connected to the two guide posts;

[0018] Each guide column is detachably connected to a movable beam, and the movable beam is arranged between the top beam and the lower cross beam;

[0019] There are two telescopic driving members, and one telescopic driving member is connected between each of the moving beams and the top beam.

[0020] Optionally, the top beam includes an upper cross beam and a connecting joint, the upper cross beam and the bottom beam assembly are arranged opposite to each other and are slidably connected to each other, the telescopic driving member is connected to the upper cross beam, the connecting joint is connected to a side of the upper cross beam facing away from the bottom beam assembly, and the connecting joint is in sliding contact with the machine arm;

[0021] The connection joint is provided with a limiting structure, and when the connection joint abuts against the machine arm, the machine arm is limited in the limiting structure.

[0022] Optionally, the transfer bracket also includes two auxiliary brackets, which are respectively arranged on both sides of the frame body along the lateral direction of the arm, and the two ends of the auxiliary bracket are respectively detachably connected to the load platform and the frame body.

[0023] A second aspect of the present disclosure provides a bridge erection device, comprising a bridge erection machine and a transport vehicle as described in any one of the above items;

[0024] The bridge-building machine includes an arm and a second pillar, wherein the second pillar is installed on the lower side of the arm, the second pillar is configured to be telescopic relative to the arm, and the second pillar and the arm can slide relative to each other along the longitudinal direction of the arm.

[0025] Optionally, the bridge erecting machine further comprises a movable beam hoisting vehicle, which is slidably connected to the machine arm and is used for hoisting beam pieces.

[0026] A third aspect of the present disclosure provides a method for transporting and erecting beams using a bridge erecting machine, including a pre-hole preparation step, wherein the pre-hole preparation step includes:

[0027] The bridge erecting machine is transported to the bridge head by a transport vehicle, the front end of the machine arm and the second pillar are located outside the load platform, the transfer bracket is located at the end of the load platform away from the second pillar, the frame body is supported on the lower side of the machine arm, and the second pillar is in a retracted state and supported on the bridge deck;

[0028] Synchronously lifting the second support column and the frame body to lift the boom to a set height;

[0029] The arm is driven by the second support to move relative to the second support in a direction away from the transport vehicle, and the front end of the arm moves to a position with a set distance from the second support;

[0030] The frame body is controlled to retract to separate from the machine arm, and the transport vehicle is driven to withdraw from under the machine arm to complete the preparation before the through-hole.

[0031] Optionally, the bridge erecting machine further comprises a beam lifting movable vehicle, the beam lifting movable vehicle is slidably connected to the machine arm, and the beam lifting movable vehicle is used for lifting beam pieces;

[0032] The invention also includes a beam erection step, wherein the beam erection step includes:

[0033] The beam piece is placed on the load platform, and the transport vehicle carries the beam piece and moves it to the bottom of the machine arm;

[0034] The frame body is extended to support the machine arm;

[0035] The beam lifting mobile vehicle on the machine arm moves to the beam piece, controls the beam lifting mobile vehicle to lift the beam piece, and moves it to between the bridge pier at the edge of the bridge head and the bridge pier downstream of the bridge head, and lowers the beam piece onto the two bridge piers.

[0036] Compared with the prior art, the technical solution provided by the present invention has the following advantages:

[0037] The present invention provides a transport vehicle, a bridge-building device and a method for transporting and erecting beams for a bridge-building machine. The transport vehicle is used to carry the arm of the bridge-building machine, including a load platform and a transport bracket. The load platform extends along the longitudinal direction of the arm. The transport bracket includes a frame body and a moving mechanism. The moving mechanism is provided at one end of the frame body, and the other end is used to abut against the lower side of the arm. The frame body is configured to be able to extend and retract relative to the load platform to drive the arm to move in a direction close to and away from the load platform. When the second pillar lifts the arm to adjust the height of the arm, the frame body can synchronously lift the arm to improve the stability when adjusting the height of the arm. The frame body is connected to the load platform through a moving mechanism and is slidably connected along the longitudinal direction of the arm. When the arm moves relative to the second pillar and the relative position between the front end of the arm and the second pillar is adjusted, the frame body supports the arm and can move together with the arm through the moving mechanism, so that the transfer bracket continues to provide support for the arm when the arm moves relative to the second pillar. When the relative position between the second pillar and the arm is adjusted after the bridge erection machine is transferred from the transport vehicle to the bridge deck, the transfer bracket can improve the stability of the bridge erection machine; and after using the transport vehicle to transport the beam to the lower side of the arm, the transfer bracket can be extended to assist in supporting the arm, thereby improving the stability of the bridge erection machine when lifting the beam. BRIEF DESCRIPTION OF THE DRAWINGS

[0038] The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments consistent with the present disclosure and, together with the description, serve to explain the principles of the present disclosure.

[0039] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative labor.

[0040] Figure 1 This is one of the structural schematic diagrams of the transport bracket described in the embodiment of the present disclosure;

[0041] Figure 2 This is the second structural schematic diagram of the transport bracket according to the embodiment of the present disclosure;

[0042] Figure 3 A side view of the bridge erecting machine according to an embodiment of the present disclosure when placed on a transport vehicle;

[0043] Figure 4 A side view of the transfer bracket and the second support column when the machine arm is lifted according to the embodiment of the present disclosure;

[0044] Figure 5 A side view of the front end of the machine arm according to the embodiment of the present disclosure when there is a set distance between the front end and the second support column;

[0045] Figure 6 This is a side view of the transport support and the machine arm when the transport support is separated from the machine arm according to the embodiment of the present disclosure;

[0046] Figure 7 The present invention is a flow chart of the method for transporting and erecting beams by a bridge erecting machine according to an embodiment of the present disclosure.

[0047] Among them, 1. frame body; 11. top beam; 111. upper cross beam; 112. connecting joint; 113. limiting structure; 12. bottom beam assembly; 121. lower cross beam; 122. guide column; 123. moving beam; 13. telescopic drive member; 14. auxiliary bracket; 2. moving mechanism; 3. load platform; 4. machine arm; 5. second pillar; 6. lifting beam movable vehicle. DETAILED DESCRIPTION

[0048] In order to more clearly understand the above-mentioned objectives, features and advantages of the present disclosure, the scheme of the present disclosure will be further described below. It should be noted that the embodiments of the present disclosure and the features in the embodiments can be combined with each other without conflict.

[0049] In the following description, many specific details are set forth to facilitate a full understanding of the present disclosure, but the present disclosure may also be implemented in other ways different from those described herein; it is obvious that the embodiments in the specification are only part of the embodiments of the present disclosure, rather than all of the embodiments.

[0050] Reference Figures 1 to 7 As shown, the first aspect of the disclosed embodiment provides a transport vehicle for carrying the arm 4 of a bridge erecting machine, comprising a load platform 3 and a transfer bracket; the load platform 3 extends along the longitudinal direction of the arm 4; the transfer bracket comprises a frame body 1 and a moving mechanism 2; the moving mechanism 2 is provided at one end of the frame body 1, and the other end is used to abut against the lower side of the arm 4, and the frame body is configured to be able to extend and retract relative to the load platform 3 to support the arm 4; the frame body 1 is connected to the load platform 3 by a moving mechanism 2 along the longitudinal direction of the arm 4.

[0051] Specifically, the transport vehicle can be selected to have a load platform 3 and a front vehicle, wherein the load platform 3 is a platform structure with a wheel body, and the front vehicle is connected to the load platform 3 so that the front vehicle can drive the load platform 3 to move. Of course, it is also possible to select a plurality of moving wheels on the load platform 3, and an engine on the load platform 3, which can drive the moving wheels of the load platform 3 to roll, thereby enabling the load platform 3 to move on the bridge deck.

[0052] The above-mentioned arm 4 is usually kept parallel to the bridge deck when in use, the extension direction of the arm 4 is the longitudinal direction of the arm 4, and the direction perpendicular to the extension of the arm 4 in the horizontal direction is the lateral direction of the arm 4. A plurality of legs are arranged at intervals on the arm 4, usually the leg at the front end of the arm 4 is the first pillar, the rear leg at the rear end of the arm 4 is the third pillar, and a leg in the middle of the arm 4 is the second pillar 5. The second pillar 5 and the arm 4 can be selectively connected through a track along the longitudinal direction of the arm 4, so that the second pillar 5 can slide along the arm 4, and the second pillar 5 can be telescopic.

[0053] The above-mentioned frame body 1 can be selected to include mutually nested tubes or cylinders, and a driving cylinder is connected between the mutually nested tubes or cylinders, so that the driving cylinder drives the mutually nested tubes or cylinders to move closer or farther away from each other, so as to achieve the extension and shortening of the frame body 1.

[0054] The above-mentioned mobile mechanism 2 can be selected to include a mechanism body, a driving member and a track, the track is arranged on the load platform 3, the mechanism body is connected to the frame body 1, and is slidably connected to the track, the driving member is arranged on the mechanism body and is transmission-connected to the track, so that the driving member can drive the mechanism body to drive the frame body 1 to slide along the track; of course, the mobile mechanism 2 can also be selected to include a roller group formed by multiple wheel bodies, the wheel body is arranged at the end of the frame body 1, and the rotating axis of the wheel body is arranged along the transverse direction of the machine arm 4, the motor is connected to the rotating axis of the wheel body, and the motor can drive the wheel body to rotate after starting, and the roller group supports the frame body 1 on the load platform 3, so that the frame body 1 moves on the load platform 3 through the rotation of the roller group.

[0055] When the bridge-building machine is placed on a transport vehicle, part of the arm 4 is located outside the load platform 3. Due to the large size of the second pillar 5, the second pillar 5 needs to be set at the part of the arm 4 located outside the load platform 3. At this time, the second pillar 5 can only move on the part of the arm 4 located outside the load platform 3, and the relative movement distance between the second pillar 5 and the arm 4 is limited; when the bridge-building machine is transferred from the transport vehicle to the bridge deck, the second pillar 5 is extended and supported on the bridge deck. At this time, the second pillar 5 and the bridge deck remain relatively fixed, and the movement of the arm 4 relative to the second pillar 5 is not restricted by the transport vehicle. After the second pillar 5 and the arm 4 move relative to each other, the distance between the second pillar 5 and the front end of the arm 4 can meet the erection requirements of the bridge-building machine.

[0056] When the transport vehicle provided by the embodiment of the present disclosure is used, the bridge erection machine is transported to the bridge head by the transport vehicle, the front end of the arm 4 and the second pillar 5 are located on the outside of the load platform 3, the transfer bracket is located at the end of the load platform 3 away from the second pillar 5, the frame body 1 is supported on the lower side of the arm 4, and the second pillar 5 is in a retracted state and supported on the bridge deck; the second pillar 5 and the frame body 1 are synchronously lifted to lift the arm 4 to a set height; the arm 4 is driven by the second pillar 5 to move relative to the second pillar 5 in a direction away from the transport vehicle, and the front end of the arm 4 moves to a set distance between the second pillar 5; the transfer bracket is controlled to retract to disengage from the arm 4, and the transport vehicle is driven to exit from under the arm 4 to complete the preparation before the hole is crossed. After the bridge erection machine completes the preparation before the hole is crossed, the bridge erection machine is supported on the bridge deck, and the bridge erection machine can be driven to move on the bridge deck so that the bridge erection machine can be erected between the bridge deck of the bridge head and the bridge pier downstream of the bridge head for subsequent beam erection operations.

[0057] The transport vehicle provided by the embodiment of the present disclosure is used to carry the arm 4 of the bridge-building machine, and includes a load platform 3 and a transfer bracket; the load platform 3 extends along the longitudinal direction of the arm 4; the transfer bracket includes a frame body 1 and a moving mechanism 2; a moving mechanism 2 is provided at one end of the frame body 1, and the other end is used to abut against the lower side of the arm 4, and the frame body 1 is configured to be able to extend and retract relative to the load platform 3 to support the arm 4. When the second pillar 5 lifts the arm 4 to adjust the height of the arm 4, the frame body 1 can synchronously lift the arm 4 to improve the stability when adjusting the height of the arm 4; the frame body 1 is connected to the load platform 3 through the moving mechanism 2 along the longitudinal direction of the arm 4. When the arm 4 moves relative to the second pillar 5 and the relative position between the front end of the arm 4 and the second pillar 5 is adjusted, the frame body 1 supports the arm 4 and can move together with the arm 4 through the moving mechanism 2, so that the transfer bracket continues to provide support for the arm 4 when the arm 4 moves relative to the second pillar 5, thereby improving the stability of the bridge erection machine when adjusting the relative position between the second pillar 5 and the arm 4 after the bridge erection machine is transferred from the transport vehicle to the bridge deck; and after the beam is transported to the lower side of the arm 4 using the transport vehicle, the transfer bracket can be extended to assist in supporting the arm 4, thereby improving the stability of the bridge erection machine when lifting the beam.

[0058] Reference Figure 1 and Figure 2 As shown, in some embodiments, the mobile mechanism 2 includes a mechanism body, a driving member and a track; the track is installed on the load platform 3 and extends along the longitudinal direction of the machine arm 4, the mechanism body is connected to the frame body 1, and is slidably connected to the track, the driving member is installed on the mechanism body, and the driving member is transmission-connected to the track so that the driving member drives the mechanism body to slide relative to the track. In this way, the track guides the movement of the mechanism body, and the driving member provides power for the sliding of the mechanism body along the track, so that the mobile mechanism 2 drives the frame body 1 to move relative to the load platform 3, so that the transfer bracket can assist the movement of the machine arm 4.

[0059] Specifically, a groove can be formed on one side of the mechanism body facing the load platform 3, and the track can be inserted into the groove so that the mechanism body can slide relative to the track. The driving member can be selected as a motor, which is installed on the mechanism body, and a gear is installed on the output end of the motor. A rack is provided on the track along the longitudinal direction of the machine arm 4. The gear at the output end of the motor meshes with the rack on the track, and the output end of the motor drives the gear to rotate to drive the mechanism body to slide along the track. Of course, the driving member can also be selected as an annular chain and a motor extending longitudinally along the machine arm 4, the motor is connected to the annular chain, the annular chain is connected to the mechanism body, the motor is set on the track, and the motor drives the annular chain to rotate to make the mechanism body slide along the track.

[0060] Reference Figure 1 and Figure 2 As shown, in some embodiments, the frame body 1 includes a top beam 11, a telescopic drive member 13 and a bottom beam assembly 12; the bottom beam assembly 12 is arranged opposite to the top beam 11, and the telescopic drive member 13 is connected between the bottom beam assembly 12 and the top beam 11, so that the telescopic drive member 13 drives the bottom beam assembly 12 and the top beam 11 to move closer to or farther from each other; the top beam 11 abuts against the lower side of the machine arm 4, and the moving mechanism 2 is installed on the side of the bottom beam assembly 12 away from the top beam 11. In this arrangement, the telescopic drive member 13 drives the top beam 11 and the bottom beam assembly 12 to move closer to or farther from each other, so that the telescopic drive member 13 can provide power for the extension and shortening of the frame body 1, the top beam 11 abuts against the machine arm 4 and supports the machine arm 4 on the load platform 3, so that the top beam 11 moves in a direction away from the bottom beam assembly 12 to assist the second support 5 in jointly lifting the machine arm 4.

[0061] Specifically, the bottom beam assembly 12 may be selected as a frame or block structure, the bottom beam assembly 12 has a column structure extending toward the top beam 11, and the top beam 11 may be provided with a through hole, so that the column structure and the through hole are movably plugged, so that the top beam 11 is movably connected to the bottom beam assembly 12. Of course, the bottom beam assembly 12 may also be selected to be recessed on one side of the top beam 11 to form a movable groove, and the top beam 11 is provided with a column on one side of the bottom beam assembly 12, and the column is movably plugged into the movable groove, so that the top beam 11 is movably connected to the bottom beam assembly 12.

[0062] The above-mentioned telescopic driving member 13 can be selected as a telescopic cylinder, which is arranged along the direction of the top beam 11 toward the bottom beam assembly 12, so that the end of the telescopic cylinder moves in the direction of the top beam 11 toward the bottom beam assembly 12; after the telescopic cylinder is started, it can drive the bottom beam assembly 12 to move in the direction away from or close to the top beam 11, so as to extend and shorten the frame body 1; when the top beam 11 is supported on the lower side of the arm 4, the extension of the frame body 1 can raise the height of the arm 4, and when the second pillar 5 is extended to adjust the height of the arm 4, the frame body 1 can cooperate with the extension of the second pillar 5 to assist the second pillar 5 in adjusting the height of the arm 4.

[0063] Reference Figure 1 and Figure 2 As shown, in some embodiments, the bottom beam assembly 12 includes a lower cross beam 121, two guide columns 122 and two movable beams 123; the lower cross beam 121 is arranged opposite to the top beam 11 and extends along the lateral direction of the arm 4, and the movable mechanism 2 is installed on the side of the lower cross beam 121 facing away from the top beam 11; the two guide columns 122 are arranged at both ends of the lower cross beam 121, and the guide columns 122 extend toward the top beam 11, and the top beam 11 is slidably connected to the two guide columns 122; a movable beam 123 is detachably connected to each guide column 122, and the movable beam 123 is arranged between the top beam 11 and the lower cross beam 121; the number of the telescopic driving members 13 is two, and a telescopic driving member 13 is connected between each movable beam 123 and the top beam 11.

[0064] With such arrangement, the two guide posts 122 guide the relative movement between the top beam 11 and the lower cross beam 121, thereby improving the stability of the relative movement between the top beam 11 and the lower cross beam 121. The movable beam 123 is arranged between the top beam 11 and the lower cross beam 121, and the distance between the top beam 11 and the lower cross beam 121 is greater than the distance between the movable beam 123 and the top beam 11, that is, a smaller telescopic drive member 13 can be connected between the movable beam 123 and the top beam 11. The lower side of the arm 4 of the bridge erecting machine is usually provided with beam cranes and outriggers of different sizes. By adjusting the position of the movable beam 123 on the guide posts 122 and adjusting the distance between the top beam 11 and the load platform 3 when the telescopic drive member 13 is retracted, the collision between the beam crane and the outriggers and the load platform 3 is avoided when the arm 4 is supported on the transfer bracket.

[0065] Specifically, the lower cross beam 121 can be selected to extend laterally along the arm 4, and a guide column 122 is respectively set at both ends of the lower cross beam 121. The guide column 122 extends in a direction perpendicular to the load platform 3 in a direction away from the lower cross beam 121. Through holes can be selected to be set at both ends of the top beam 11, so that the two guide columns 122 can be movably inserted into the through holes at both ends of the top beam 11, so that the top beam 11 can move along the guide columns 122.

[0066] The above-mentioned moving beam 123 can be detachably connected to the guide column 122 by bolts. Of course, it is also possible to set a positioning hole on the guide column 122, and movably set a positioning pin on the moving beam 123, and the moving beam 123 can be detachably connected to the guide column 122 by plugging the positioning pin into the positioning hole. Two telescopic driving members 13 are respectively arranged on the side of the two moving beams 123 facing the top beam 11, and each telescopic driving member 13 is connected to the top beam 11; when the two telescopic driving members 13 are synchronously extended and shortened, the top beam 11 can be driven to move closer to or farther from the lower cross beam 121.

[0067] Of course, you can also choose to set a guide sleeve at each end of the top beam 11, the interior of the guide sleeve is hollow, and the two guide sleeves are plug-in connected to the two guide columns 122 in a one-to-one correspondence, so that the guide sleeve can move relative to the guide column 122, so that the top beam 11 can move relative to the lower cross beam 121 in the extension direction of the guide column 122.

[0068] The guide column 122 may selectively include two sub-columns, which are spaced apart longitudinally along the arm 4, a telescopic drive member 13 is disposed between the two sub-columns, and both ends of the telescopic drive member 13 are respectively connected to the moving beam 123 and the top beam 11.

[0069] Reference Figure 1 and Figure 2 As shown, in some embodiments, the top beam 11 includes an upper cross beam 111 and a connection joint 112, the upper cross beam 111 and the bottom beam assembly 12 are arranged opposite to each other and are slidably connected to each other, the telescopic driving member 13 is connected to the upper cross beam 111, the connection joint 112 is connected to the side of the upper cross beam 111 facing away from the bottom beam assembly 12, and the connection joint 112 is slidably abutted against the machine arm 4; a limiting structure 113 is provided on the connection joint 112, and when the connection joint 112 abuts against the machine arm 4, the machine arm 4 is limited in the limiting structure 113. In this way, the connection joint 112 is used to abut against the machine arm 4, and when the upper cross beam 111 moves in a direction away from the bottom beam assembly 12 to lift the machine arm 4, the limiting structure 113 can limit the machine arm 4, thereby improving the stability of the relative position between the machine arm 4 and the frame body 1.

[0070] Specifically, the upper crossbeam 111 can be selected to extend laterally along the arm 4, and through holes are set at both ends of the upper crossbeam 111, so that the two guide pillars 122 are movably connected with the through holes at both ends of the two upper crossbeams 111 respectively; of course, it is also possible to select guide sleeves to be set at both ends of the upper crossbeam 111, the interior of the guide sleeves is hollow, and the two guide sleeves are plug-in connected to the two guide pillars 122 in a one-to-one correspondence, so that the guide sleeves can move relative to the guide pillars 122, so that the top beam 11 can move relative to the lower crossbeam 121 in the extension direction of the guide pillars 122.

[0071] The above-mentioned connecting joint 112 can be selected as a block body, and two vertical plates can be selected to be set on the side surface of the connecting joint 112 away from the upper beam 111. The two vertical plates are arranged at intervals along the lateral direction of the machine arm 4, and the two vertical plates form a limiting structure 113. The machine arm 4 abuts against the connecting joint 112 between the two vertical plates, so that the two vertical plates limit the machine arm 4; of course, it is also possible to choose that the connecting joint 112 flies on the side surface facing away from the upper beam 111 to form a groove, and the groove penetrates the connecting joint 112 along the longitudinal direction of the machine arm 4. The groove on the connecting joint 112 is the limiting structure 113, and the machine arm 4 is placed in the groove of the connecting joint 112 and abuts against the bottom of the groove, so that the groove limits the machine arm 4.

[0072] Reference Figure 1 and Figure 2 As shown, in some embodiments, the transfer bracket further includes two auxiliary brackets 14, which are respectively arranged on both sides of the frame body 1 along the lateral direction of the machine arm 4, and the two ends of the auxiliary bracket 14 are respectively detachably connected to the load platform 3 and the frame body 1. In this way, the auxiliary bracket 14, the load platform 3 and the frame body 1 form a triangular structure, thereby improving the stability of the frame body 1 in the lateral direction of the machine arm 4; when the transfer bracket does not need to move relative to the load platform 3, the auxiliary bracket 14 is installed between the frame body 1 and the load platform 3, so that the frame body 1 can form a stable support for the bridge erection machine.

[0073] Specifically, the two ends of the auxiliary bracket 14 can be connected to the frame body 1 and the load platform 3 by bolt connection, and the auxiliary bracket 14 can be connected to the top beam 11. Of course, the auxiliary bracket 14 can also be connected to the bottom beam assembly 12; the two ends of the auxiliary bracket 14 are connected between the frame body 1 and the load platform 3, so that the auxiliary bracket 14, the load platform 3 and the frame body 1 form a triangular structure; the two auxiliary brackets 14 form a triangular structure on both sides of the horizontal direction of the arm 4 of the frame body 1, thereby improving the lateral stability of the frame body 1 in the arm 4.

[0074] The above-mentioned bridge erecting machine is placed on the load platform 3, so that when the transport vehicle transports the bridge erecting machine, the frame body 1 can be selected to be supported under the machine arm 4, and the frame body 1 is respectively connected to the auxiliary brackets 14 on both sides of the machine arm 4 in the lateral direction to prevent the frame body 1 from tipping over in the lateral direction of the machine arm 4 due to vibration during the transportation of the bridge erecting machine. When the second support 5 and the frame body 1 jointly lift the machine arm 4, the auxiliary bracket 14 can be selected as a telescopic rod, and the two ends of the telescopic rod are respectively rotatably connected to the frame body 1 and the load platform 3, so that when the frame body 1 is extended, the auxiliary bracket 14 is extended together with the frame body 1.

[0075] When the arm 4 moves relative to the second support 5 to adjust the distance between the front end of the arm 4 and the second support 5 , the auxiliary bracket 14 is separated from the frame body 1 , so that the frame body 1 can move relative to the load platform 3 under the action of the moving mechanism 2 .

[0076] Reference Figures 1 to 7As shown, the second aspect of the embodiment of the present disclosure provides a bridge erection device, including a bridge erection machine and the above-mentioned transport vehicle; the bridge erection machine includes an arm 4 and a second support column 5, the second support column 5 is installed on the lower side of the arm 4, the second support column 5 is configured to be able to extend and retract relative to the arm 4, and the second support column 5 and the arm 4 can slide relative to each other along the longitudinal direction of the arm 4. In this way, when the bridge erection machine is placed on the transport vehicle, the second support column 5 can be retracted to make the arm 4 close to the load platform 3, so as to facilitate the transport vehicle to transport the bridge erection machine; when the bridge erection machine is transferred from the transport vehicle to the bridge deck, the second support column 5 can be extended to adjust the height of the arm 4, so that the beam piece can enter under the arm 4 in the subsequent beam erection operation.

[0077] Specifically, when the bridge is erected, it has a plurality of piers arranged at intervals, beams are erected on two adjacent piers to form a bridge structure, and a plurality of beams are sequentially erected on two adjacent piers and connected to each other to finally complete the overall erection of the bridge, and the bridge head is on the side of the arrangement direction when the plurality of beams are sequentially erected as the downstream of the bridge head.

[0078] Bridge piers are provided at the edge of the bridge head for support. Among the multiple piers arranged at intervals, the adjacent piers downstream of the bridge head are the piers downstream of the bridge head. After the erection machine is erected between the piers at the edge of the bridge head and the piers downstream of the bridge head, the beam piece is transported between the two piers by the machine arm 4 to complete the installation operation of the beam piece.

[0079] The above-mentioned arm 4 is usually kept parallel to the bridge deck of the bridge head when in use, and the opposite ends of the arm 4 are the front end and the rear end respectively. A first pillar can be optionally provided on the front end of the arm 4, and the first pillar is used to support on a pier downstream of the bridge head. A second pillar 5 is provided in the middle of the arm 4, and the second pillar 5 is used to support on the bridge deck, so that part of the arm 4 is located between the pier at the edge of the bridge head and the pier downstream of the bridge head.

[0080] The above-mentioned arm 4 can be optionally provided with a track extending along the longitudinal direction of the arm 4, the second pillar 5 is connected to the track, and a motor is provided on the second pillar 5, a rack is provided on the track, and a gear is provided on the output end of the motor. After the motor is started, the second pillar 5 is driven to move relative to the arm 4 through the cooperation of the gear and the rack; of course, it is also possible to choose to provide a groove at the end of the second pillar 5 close to the arm 4, the arm 4 is slidably connected to the groove, a cylinder or a motor is provided on the second pillar 5, and the arm 4 is provided with a rack extending along the longitudinal direction of the arm 4, and a gear meshing with the rack of the arm 4 is provided on the output end of the cylinder or the motor, and the output end of the cylinder or the motor rotates to make the gear and the rack interact with each other to drive the second pillar 5 to move relative to the arm 4 along the longitudinal direction of the arm 4.

[0081] And the second pillar 5 can be selected to include mutually nested tubes or cylinders, and a telescopic cylinder is connected between the mutually nested tubes or cylinders. The telescopic cylinder is connected to one tube, and the telescopic end of the telescopic cylinder is connected to an adjacent tube, so that when the telescopic end of the telescopic cylinder is extended or retracted, the mutually nested tubes can approach and move away from each other, thereby realizing the extension and shortening of the second pillar 5; the second pillar 5 is arranged perpendicular to the arm 4, so that when the second pillar 5 is supported on the bridge deck, the height of the arm 4 on the bridge deck can be adjusted by extending and shortening the second pillar 5.

[0082] Reference Figures 3 to 6 As shown, in some embodiments, the bridge erecting machine further comprises a beam lifting mobile vehicle 6, which is slidably connected to the machine arm 4 and is used to lift the beam piece. In this way, the beam lifting mobile vehicle 6 can move on the machine arm 4 after lifting the beam piece to realize the operation of transporting the beam piece.

[0083] Specifically, the beam lifting movable vehicle 6 can be selected to include a traveling body, a hanger and a driving unit; the traveling body is slidably connected to the lower side of the arm 4, the driving unit is arranged on the traveling body and is transmission-connected to the arm 4, so that the driving unit drives the traveling body to slide relative to the arm along the longitudinal direction of the arm 4; the hanger is connected to the side of the traveling body away from the arm 4, and a single-line shoulder pole assembly and a double-line shoulder pole assembly are detachably connected to the hanger, and the single-line shoulder pole assembly or the double-line shoulder pole assembly is used to connect with the beam piece.

[0084] The number of the above-mentioned beam lifting mobile vehicles 6 is generally two, and the two beam lifting mobile vehicles 6 are spaced apart in the longitudinal direction of the boom 4 to provide two lifting points for the beam piece, and can also provide counterweight for the boom 4 during movement and erection. When the front end of the boom 4 extends out of the edge of the bridge head, the beam lifting mobile vehicle 6 can be selected at the rear end of the boom 4 to balance the counterweight of the boom 4, so that the boom 4 can stably extend out of the edge of the bridge head.

[0085] The above-mentioned traveling body is provided with an arm channel, and the arm 4 is inserted into the arm channel and is slidably connected with the traveling body. The arm channel can be selected as a groove formed by a depression on one side of the traveling body, and the groove runs through the traveling body. The arm 4 can be inserted into the groove to make the traveling body and the arm 4 slidably connected.

[0086] The above-mentioned driving part can be selected as a motor and a gear. The gear is installed at the output end of the motor. A rack extending along the longitudinal direction of the arm 4 is provided on the arm 4. The gear is meshed with the rack. When the output end of the motor rotates, the gear and the rack are cooperated to drive the traveling body to slide relative to the arm 4 along the longitudinal direction of the arm 4.

[0087] Reference Figures 1 to 7 As shown, the third aspect of the embodiment of the present disclosure provides a method for transporting and erecting beams by a bridge erecting machine, including a pre-hole preparation step, the pre-hole preparation step including:

[0088] Step S1, transport the bridge-building machine to the bridge head by a transport vehicle, the front end of the arm 4 and the second pillar 5 are located on the outside of the load platform 3, the transfer bracket is located at the end of the load platform 3 away from the second pillar 5, the frame body 1 is supported on the lower side of the arm 4, and the second pillar 5 is in a retracted state and supported on the bridge deck.

[0089] When the bridge erection machine is on the transport vehicle, the second support 5 can be selected to abut against the bridge deck, so that the transfer bracket and the second support 5 can share the weight of the machine arm 4. A running mechanism can be selected to be set at the bottom of the second support 5 so that the running mechanism is in contact with the bridge deck. When the bridge erection machine is transported by the transport vehicle, the running wheel group assists the bridge erection machine to move on the bridge deck. The state of the bridge erection machine when it is transported to the bridge head by the transport vehicle in step S1 is as follows: Figure 3 As shown, the rear end of the arm 4 is above the load platform 3, the second pillar 5 is on the outside of the load platform 3 and close to the edge of the load platform 3, the second pillar 5 is supported on the bridge deck, and the transfer bracket supports the arm 4 at the end of the load platform 3 away from the second pillar 5.

[0090] Step S2, synchronously lifting the second support column 5 and the frame body 1 to lift the arm 4 to a set height. Figure 4 The side view of the bridge erecting machine is when the second support 5 and the frame body 1 synchronously lift the arm 4 to the set height.

[0091] Specifically. The second pillar 5 is supported on the bridge deck and extended, the frame body 1 supports the arm 4 on the load platform 3 and extends, and the extension speed of the second pillar 5 is consistent with that of the frame body 1, so that the second pillar 5 and the frame body 1 can lift the arm 4 together. When the bridge-building machine is placed on the transport vehicle, the second pillar 5 is in a retracted state and the arm is close to the load platform 3. At this time, the height of the bridge-building machine is relatively low and it is convenient to pass through a tunnel with a smaller height or a space with obstructions in the air; before the bridge-building machine performs through-hole erection, the arm 4 needs to be raised so that after the bridge-building machine completes the through-hole erection, the transport vehicle can carry the beam piece into the lower side of the arm 4.

[0092] The above-mentioned set height is determined based on the height of the aerial obstructions in the environment where the bridge-building machine is constructed and the total height of the transport vehicle carrying the beams. When the distance between the arm 4 and the bridge deck enables the transport vehicle carrying the beams to enter under the arm 4, the distance between the arm 4 and the bridge deck is the set height.

[0093] Step S3 , driving the arm 4 to move relative to the second pillar 5 in a direction away from the transport vehicle via the second pillar 5 , and the front end of the arm 4 moves to a position with a set distance from the second pillar 5 . Figure 5 The side view of the bridge-building machine is when the arm 4 moves relative to the second support 5 so that a set distance exists between the front end of the arm 4 and the second support 5.

[0094] Specifically, the transfer bracket supports the arm 4 at the end of the load platform 3 away from the second pillar 5, and the second pillar 5 drives the arm 4 to move in the direction away from the transport vehicle. At this time, the second pillar 5 is supported on the bridge deck and remains relatively stationary with the load platform 3; the moving mechanism 2 drives the frame body 1 to move from the end of the load platform 3 away from the second pillar 5 toward the end close to the second pillar 5, so that the frame body 1 moves together with the arm 4, thereby maintaining support for the arm 4 during the process of moving the arm 4 relative to the second pillar 5.

[0095] A first pillar may be optionally provided at the front end of the above-mentioned arm 4. When the arm 4 moves relative to the second pillar 5, the first pillar moves together with the random arm 4. The first pillar moves along with the random arm 4 and changes the distance between it and the second pillar 5. When the distance between the first pillar and the second pillar 5 is greater than or equal to the distance between the edge of the bridgehead and the pier downstream of the bridgehead, the arm 4 stops relative movement with the second pillar 5. At this time, the distance between the front end of the arm 4 and the second pillar 5 is the set spacing. After the distance between the front end of the arm 4 and the second pillar 5 is adjusted to the set spacing, the bridge-building machine moves toward the downstream of the bridgehead, so that the front end of the arm 4 extends out of the edge of the bridgehead and moves to the pier downstream of the bridgehead, so that the first pillar at the front end of the arm 4 can be supported on the pier downstream of the bridgehead.

[0096] Step S4 controls the frame body 1 to retract to disengage from the arm 4, and drives the transport vehicle to exit from under the arm 4, completing the preparation for passing the hole. The arm 4 is supported on the bridge deck by the second pillar 5. At this time, the frame body 1 can be retracted to disengage from the arm 4, and the transport vehicle can move away from the second pillar 5 to disengage from under the arm 4, completing the preparation for passing the hole of the bridge erecting machine. The bridge erecting machine can perform subsequent passing hole operations, so that the bridge erecting machine is erected between the bridge deck and the bridge pier downstream of the bridge head. Figure 6 The side view of the bridge-building machine is when the frame body 1 is retracted to separate from the boom 4 and the transport vehicle exits from under the boom 4.

[0097] In some embodiments, the bridge erecting machine further comprises a beam-hanging movable vehicle 6, and when the beam-hanging movable vehicle 6 is slidably connected to the machine arm 4, it further comprises a beam erecting step, and the beam erecting step is after the through-hole preparation step, and the beam erecting step comprises:

[0098] Step S5, place the beam piece on the load platform 3, and the transport vehicle carries the beam piece to the bottom of the arm 4. The end of the load platform 3 facing the second pillar 5 can be selected as the front end of the load platform 3. After the beam piece is placed on the load platform 3, the frame body 1 is located on the side of the beam piece away from the front end of the load platform 3, and the transport vehicle carries the beam piece to enter the bottom of the arm 4.

[0099] Step S6, the frame body 1 is extended to support the arm 4. The frame body 1 may be optionally connected to an auxiliary bracket 14, and the frame body 1 is extended to be at a lower level with the lower side of the arm 4, so that the frame body 1 and the second support 5 jointly support the arm 4, thereby improving the stability of the arm 4.

[0100] In step S7, the beam lifting mobile vehicle 6 on the arm 4 moves to the beam piece, controls the beam lifting mobile vehicle 6 to lift the beam piece, and moves it to between the pier at the edge of the bridge head and the pier downstream of the bridge head, and lowers the beam piece onto the two piers.

[0101] Specifically, the beam lifting mobile vehicle 6 moves on the arm 4 toward the rear end of the arm 4, so that the beam lifting mobile vehicle 6 moves to the top of the beam piece. After the beam lifting mobile vehicle 6 is connected to the beam piece, it carries the beam piece relative to the arm 4 and moves toward the front end of the arm 4. The beam lifting mobile vehicle 6 moves the beam piece to between the pier at the edge of the bridge head and the pier downstream of the bridge head, and lowers the beam piece so that the beam piece is supported on the two piers, thereby completing the bridge erection operation.

[0102] When there are two beam lifting mobile carriages 6, two beam lifting mobile carriages 6 can be selected to move first to the end of the beam piece close to the second pillar 5, and a beam lifting mobile carriage 6 close to the front end of the arm 4 is connected to the end of the beam piece close to the second pillar 5; then a beam lifting mobile carriage 6 away from the front end of the arm 4 moves toward the rear end of the arm 4 to the end of the beam piece away from the second pillar 5, and the beam lifting mobile carriage 6 away from the front end of the arm 4 is connected to the end of the beam piece away from the second pillar 5; the two beam lifting mobile carriages 6 are respectively connected to the two ends of the beam piece to complete the operation of lifting the beam piece by the beam lifting mobile carriages 6; the two beam lifting mobile carriages 6 move synchronously relative to the arm 4 to move the beam piece to between the pier at the edge of the bridge head and the pier downstream of the bridge head, and the two beam lifting mobile carriages 6 synchronously lower the beam piece onto the two piers to complete the beam erection operation of the bridge erection machine.

[0103] It should be noted that, in this article, relational terms such as "first" and "second" are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.

[0104] The above description is only a specific embodiment of the present disclosure, so that those skilled in the art can understand or implement the present disclosure. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present disclosure. Therefore, the present disclosure will not be limited to the embodiments described herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. A transport vehicle for carrying an arm (4) of a bridge erecting machine, characterized in that: It includes a load platform (3) and a transport support; The load platform (3) extends in the longitudinal direction of the machine arm (4); The transport support comprises a frame body (1) and a moving mechanism (2); One end of the frame body (1) is provided with a moving mechanism (2), and the other end is used to abut against the lower side of the machine arm (4), and the frame body is configured to be able to extend and retract relative to the load platform (3) to support the machine arm (4); The frame body (1) is slidably connected to the load platform (3) along the longitudinal direction of the machine arm (4) via the moving mechanism (2).

2. The transport vehicle according to claim 1, characterized in that: The moving mechanism (2) comprises a mechanism body, a driving member and a track; The track is mounted on the load platform (3) and extends longitudinally along the arm (4); the mechanism body is connected to the frame body (1) and is slidably connected to the track; the driving member is mounted on the mechanism body and is in transmission connection with the track so that the driving member drives the mechanism body to slide relative to the track.

3. The transport vehicle according to claim 1, characterized in that: The frame body (1) comprises a top beam (11), a telescopic driving member (13) and a bottom beam assembly (12); The bottom beam assembly (12) and the top beam (11) are arranged opposite to each other, and the telescopic driving member (13) is connected between the bottom beam assembly (12) and the top beam (11), so that the telescopic driving member (13) drives the bottom beam assembly (12) and the top beam (11) to move closer to or farther from each other; The top beam (11) abuts against the lower side of the machine arm (4), and the moving mechanism (2) is installed on a side of the bottom beam assembly (12) away from the top beam (11).

4. The transport vehicle according to claim 3, characterized in that: The bottom beam assembly (12) comprises a lower cross beam (121), two guide columns (122) and two movable beams (123); The lower cross beam (121) is arranged opposite to the top beam (11) and extends in the transverse direction of the machine arm (4); the moving mechanism (2) is installed on a side of the lower cross beam (121) facing away from the top beam (11); The two guide columns (122) are arranged at two ends of the lower cross beam (121), and the guide columns (122) extend toward the top beam (11), and the top beam (11) is slidably connected to the two guide columns (122); Each guide column (122) is detachably connected to a movable beam (123), and the movable beam (123) is arranged between the top beam (11) and the lower cross beam (121); The number of the telescopic driving components (13) is two, and one telescopic driving component (13) is connected between each of the moving beams (123) and the top beam (11).

5. The transport vehicle according to claim 3, characterized in that: The top beam (11) comprises an upper cross beam (111) and a connection joint (112); the upper cross beam (111) and the bottom beam assembly (12) are arranged opposite to each other and are slidably connected to each other; the telescopic driving member (13) is connected to the upper cross beam (111); the connection joint (112) is connected to a side of the upper cross beam (111) facing away from the bottom beam assembly (12); and the connection joint (112) is in slidable contact with the machine arm (4); The connection joint (112) is provided with a limiting structure (113); when the connection joint (112) abuts against the machine arm (4), the machine arm (4) is limited within the limiting structure (113).

6. The transport vehicle according to claim 1, characterized in that: The transfer bracket also includes two auxiliary brackets (14), which are respectively arranged on both sides of the frame body (1) along the lateral direction of the machine arm (4), and the two ends of the auxiliary bracket (14) are respectively detachably connected to the load platform (3) and the frame body (1).

7. A bridging device, characterized in that: It comprises a bridge erecting machine and a transport vehicle as claimed in any one of claims 1 to 6; The bridge-building machine comprises an arm (4) and a second support column (5), wherein the second support column (5) is installed on the lower side of the arm (4), and the second support column (5) is configured to be able to extend and retract relative to the arm (4), and the second support column (5) and the arm (4) can slide relative to each other along the longitudinal direction of the arm (4).

8. The bridging device according to claim 7, characterized in that: The bridge erecting machine also includes a movable beam lifting vehicle (6), which is slidably connected to the machine arm (4) and is used for lifting beam pieces.

9. A method for transporting and erecting beams using a bridge erecting machine, characterized in that: The method comprises a pre-via preparation step, wherein the pre-via preparation step comprises: The bridge erecting machine is transported to the bridge head by a transport vehicle, the front end of the machine arm (4) and the second pillar (5) are located outside the load platform (3), the transfer bracket is located at the end of the load platform (3) away from the second pillar (5), the frame body (1) is supported on the lower side of the machine arm (4), and the second pillar (5) is in a retracted state and supported on the bridge deck; Synchronously lifting the second support column (5) and the frame body (1) to lift the machine arm (4) to a set height; The second support pillar (5) drives the arm (4) to move relative to the second support pillar (5) in a direction away from the transport vehicle, and the front end of the arm (4) moves to a position with a set distance from the second support pillar (5); The frame body (1) is controlled to retract to detach from the machine arm (4), and the transport vehicle is driven to withdraw from under the machine arm (4), thereby completing the preparation for through-hole drilling.

10. The method for transporting and erecting beams by a bridge erecting machine according to claim 9, characterized in that: The bridge erecting machine further comprises a beam lifting movable vehicle (6), the beam lifting movable vehicle (6) being slidably connected to the machine arm (4), and the beam lifting movable vehicle (6) being used for lifting beam pieces; The invention also includes a beam erection step, wherein the beam erection step includes: The beam piece is placed on the load platform (3), and the transport vehicle carries the beam piece and moves it to the bottom of the machine arm (4); The frame body (1) is extended to support the machine arm (4); The beam lifting mobile vehicle (6) on the machine arm (4) moves onto the beam piece, controls the beam lifting mobile vehicle (6) to lift the beam piece, and moves it between the pier at the edge of the bridge head and the pier downstream of the bridge head, and lowers the beam piece onto the two piers.