Combined transshipment port conveyor
By combining the design of the port conveyor with concrete foundations and pressure-bearing positioning mechanisms, a fast and enclosed bulk material transport between large cargo ships and ports is realized, solving the turnover difficulties and scattering problems in existing technologies, and improving loading efficiency and flexibility.
Patent Information
- Application Number
- CN202411416962.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-11
- Publication Date
- 2024-11-26
AI Technical Summary
Existing port conveyors suffer from problems such as difficulty in handling bulk materials from large cargo ships when transporting them at high elevations, scattering of powder, and unsuitability for conveying large volumes of materials at multiple workstations.
The combined transfer port conveyor system includes a concrete foundation fixed to the top of underwater piles, a support base, and a pressure control mechanism. It utilizes a pneumatic conveying pump and a control transfer assembly to achieve rapid transfer and enclosed conveying of bulk materials. The pressure control mechanism controls the unit spacing and height.
It enables rapid transshipment between large cargo ships and ports, avoids powder scattering, improves loading efficiency and flexibility, and adapts to the needs of multi-station conveying.
Smart Images

Figure CN119018656A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of conveyors, in particular to a combined transfer port conveyor. Background Art
[0002] Port conveyor is a kind of mechanical equipment used for loading and unloading and handling of cargo in ports. It is widely used in the loading, transshipment and stacking operations of bulk cargo such as coal and ore. Port conveyor is one of the core equipment in modern port logistics system.
[0003] After searching, there are many types of port conveyor structures in the prior art. For example, in the patent document with patent application number CN201910717856.3, a port high-drop vertical lifting and conveying device is disclosed, and its main structure includes a plant, a telescopic cover, a slide bar, a guide bar, a U-shaped hook, a first belt conveyor, a second belt conveyor, a stand, a self-tensioning device, a tensioning roller, a movable roller, a door frame, a locking mechanism, a ratchet rack, a ratchet rod, an oil cylinder, a counterweight, a first winch, a second winch, a bracket, a material trough, a guide rail, a hopper, a laser ranging sensor, and a reflector; when working, the first belt conveyor and the second belt conveyor cooperate with the winch to complete the material control lifting.
[0004] However, the above-mentioned conveyor has the following problems when used in working conditions with high drop conveying such as loading and unloading of bulk cargo (such as coal and sand) at ports:
[0005] First, the inclined conveyor belt method has problems with turnover and transportation when dealing with large cargo ships that are far from the shore.
[0006] Second, when the open conveying structure transports bulk cargo on both sides of the ship and the shore at the port coast, the powder is easy to float under wind load.
[0007] Third, the belt lifting conveyor device in the prior art is not suitable for handling large conveying volumes and multi-station conveying.
[0008] Based on this, the present invention optimizes and improves the problems existing in the prior art, and hereby proposes a combined transfer port conveyor that can be suitable for complex port loading conditions to better solve the problems existing in the prior art. Summary of the invention
[0009] The present invention is to solve one of the above technical problems, and the technical solution adopted is: a combined transfer port conveyor, including a concrete foundation fixed on the top of an underwater foundation pile, the right sea surface of the concrete foundation is used for docking cargo ships, a safety distance is set between the left side of the concrete foundation and the shore, a support base is installed above the concrete foundation, a pressure-bearing position control mechanism is installed on the top of the support base, and a first loading unit and a second transfer unit are respectively arranged on the front and rear sides of the pressure-bearing position control mechanism with respect to the central vertical surface thereof. The first loading unit and the second transfer unit are both used for transferring and conveying bulk materials between the cargo ship end and the port end. In the working state, both end portions of the first loading unit and the second transfer unit are used in conjunction with pneumatic conveying pumps installed at corresponding external positions.
[0010] In any of the above schemes, it is preferred that the pressure-bearing position control mechanism is used to complete the control of the center height position of the first loading unit and the second transfer unit, and is also used to complete the control of the spacing distance between the first loading unit and the second transfer unit.
[0011] In any of the above schemes, it is preferred that the pressure-bearing control mechanism includes a central positioning seat horizontally arranged above the supporting base, two central lifting cylinders are fixedly installed at the bottom of the central positioning seat, and the bottoms of the two central lifting cylinders are fixedly installed on the top of the supporting base; end positioning seats are symmetrically arranged on the front and rear sides of the central positioning seat, two end lifting cylinders are fixedly installed at the bottom of each end positioning seat, and the bottom of each end lifting cylinder is fixedly installed on the top of the supporting base; each of the central lifting cylinders and each of the end lifting cylinders are in a synchronous motion state in the working state; a central lead screw is movably installed in the center hole of the central positioning seat The threads on the outer walls on the front and rear sides of the center screw have opposite rotation directions, and the front and rear ends of the center screw respectively pass through the outside of the end positioning seat and are plugged into the outer end connecting seat at the corresponding position. Guide shafts are respectively arranged at intervals on the left and right sides of the center screw, and the two ends of each guide shaft are respectively movably passed through the corresponding end positioning seat and the center positioning seat and are fixedly connected to the outer end connecting seat at the corresponding position. A movable slide is respectively screwed and installed on the center screw between each end positioning seat and the center positioning seat, and the bottom of each movable slide is respectively fixedly connected to the top of the first loading unit or the top of the second transfer unit at its corresponding position.
[0012] In any of the above schemes, it is preferred that the first loading unit and the second transfer unit both adopt a control transfer component with the same structure, the middle height of the control transfer component can be raised and lowered, and the height and inclination angle of the left and right sides of the control transfer component can be adjusted, one end of the control transfer component is the bulk material feed end, and the other end is the bulk material discharge end.
[0013] In any of the above schemes, it is preferred that the regulating and transferring component includes a central frame fixedly installed at the bottom of the movable slide of the pressure-bearing position control mechanism, and end bearings are symmetrically fixedly installed at both ends inside the central frame, and a transition transfer mechanism is arranged in the space between the two end bearings, and the two ends of the transition transfer mechanism are movably passed through the end bearings and are movably sealed and connected with the corresponding ends of the left end conveying component and the right end conveying component at the corresponding positions on the left and right sides thereof, and the two are internally connected.
[0014] In any of the above schemes, it is preferred that each of the left-end conveying components and each of the right-end conveying components are equipped with a pneumatic conveying pump for pneumatically conveying bulk materials at their ends in the working state.
[0015] In any of the above schemes, it is preferred that a plurality of synchronous lifting cylinders are arranged between the support base and the concrete foundation, the bottom of each synchronous lifting cylinder is fixed to the top of the concrete foundation, and the top of the piston rod of each synchronous lifting cylinder is fixedly installed on the bottom of the support base.
[0016] In any of the above schemes, it is preferred that the right end of the left-end conveying assembly can swing around the left end of the transition transfer mechanism; a first upper winch is fixedly installed on the top of the movable slide arranged opposite to the left-end conveying assembly, and the end of the upper left steel wire rope wound on the first upper winch is fixedly connected to the top of the middle section of the left-end conveying assembly.
[0017] In any of the above schemes, it is preferred that the left end of the right-end conveying assembly can swing around the right end of the transition transfer mechanism; a second upper winch is fixedly installed on the top of the movable slide seat arranged opposite to the right-end conveying assembly, and the end of the upper right steel wire rope wound on the second upper winch is fixedly connected to the top of the middle section of the right-end conveying assembly.
[0018] In any of the above schemes, it is preferred that the transition transfer mechanism includes a driving outer cylinder installed inside the central frame, two ends of the driving outer cylinder are respectively movably inserted through corresponding end bearings, and two-way material pipes are respectively sealed and inserted in the inner holes at both ends of the driving outer cylinder, the interior of the two-way material pipe is connected with the interior of the driving outer cylinder, a driven gear is fixedly installed on the outer side wall of the driving outer cylinder, a driving gear is meshed on one side of the driven gear, the driving gear is fixedly connected to the motor shaft of a central driving motor fixedly arranged on its left side, a central real shaft is coaxially arranged in the inner cavity of the driving gear, a spiral feeding channel is fixedly installed in the annular cavity between the central real shaft and the inner side wall of the driving outer cylinder, and the feed port and the discharge port at the left and right ends of the spiral feeding channel are respectively connected with the interior of the two-way material pipe at the corresponding positions.
[0019] In any of the above schemes, preferably, telescopic pistons are installed at even intervals along the circumference between the end flange of the driving outer cylinder and the connecting disk fixedly connected to the outer side wall of the bidirectional material tube, and one end of each telescopic piston is installed on the end flange and the other end is installed on the connecting disk.
[0020] In any of the above schemes, it is preferred that a hollow external spherical segment body is integrally formed at the outer end of the bidirectional material pipe, a hollow internal spherical segment body is sealingly installed inside the external spherical segment body, the interior of the internal spherical segment body is connected to the interior of the external spherical segment body, and a left end conveying component or a right end conveying component is integrally formed on the outer side wall of the internal spherical segment body.
[0021] In any of the above schemes, it is preferred that the left-end conveying assembly includes a left-side pneumatic conveying pipe, the right end of which is fixedly connected to the outer wall of the built-in spherical segment body and the two are internally connected; the right-end conveying assembly includes a right-side pneumatic conveying pipe, the left end of which is fixedly connected to the outer wall of the built-in spherical segment body and the two are internally connected.
[0022] In any of the above schemes, preferably, ears for connecting corresponding steel wire ropes are welded to the top and bottom of the middle section of each left-side pneumatic conveying pipe and the top and bottom of the middle section of each right-side pneumatic conveying pipe, respectively.
[0023] In any of the above schemes, preferably, a material-pickup shaft is horizontally arranged in the cavity of the built-in spherical segment body, and the front and rear ends of the material-pickup shaft are movably passed through the mounting holes on the external spherical segment body, and a plurality of material-pickup teeth are evenly spaced along the circumference of the material-pickup shaft in the cavity of the built-in spherical segment body, and a driving motor is fixedly mounted on the outer side wall of the external spherical segment body, and the output shaft of the driving motor is fixedly connected to the end of the material-pickup shaft and is used to drive the material-pickup shaft to rotate.
[0024] Compared with the prior art, the present invention has the following beneficial effects:
[0025] 1. The combined transfer port conveyor of the present invention adopts a concrete foundation as support, which can avoid the problem of difficulty in transition of large cargo ships to the shore, effectively realize the rapid transfer and transportation of bulk cargo between large cargo ships and port terminals, and reduce the difficulty of transportation.
[0026] 2. The combined transfer port conveyor of the present invention adopts pneumatic conveying when completing the transfer and transportation of bulk cargo. The entire conveying route adopts an internal blocking method, which can effectively deal with the problem of random scattering of materials caused by wind during the transportation process and improve the quality of the working environment.
[0027] 3. The present invention relies on a pressure-bearing position control mechanism to complete the position control of the first loading unit and the second transfer unit on both sides, and can complete the transportation of bulk materials for a single cargo ship as needed, thereby improving the loading efficiency; at the same time, the interval distance between the first loading unit and the second transfer unit can be adjusted to complete the bulk material transfer and transportation for two cargo ships at the same time.
[0028] 4. The first loading unit and the second transfer unit are independent of each other in working state, and the conveying directions of the first loading unit and the second transfer unit can be the same or different, which effectively improves the flexibility and operability of the transfer and conveying work.
[0029] 5. In the present invention, both ends of the first loading unit and the second transfer unit are used in conjunction with pneumatic conveying pumps installed at corresponding external positions in the working state. The matching pneumatic conveying pumps can be selected and installed according to the bulk material conveying volume, effectively combining the conveying time to quickly complete the conveying and transfer operations. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] In order to more clearly illustrate the specific embodiments of the present invention or the technical solutions in the prior art, the following is a brief introduction to the drawings required for the specific embodiments or the description of the prior art. In all the drawings, similar elements or components are generally identified by similar reference numerals. In the drawings, the elements or components are not necessarily drawn according to the actual scale.
[0031] Figure 1 It is a schematic structural diagram of the combined transfer port conveyor of the present invention in a first use state.
[0032] Figure 2 It is a schematic structural diagram of the combined transfer port conveyor of the present invention in a second use state.
[0033] Figure 3 It is a schematic structural diagram of the combined transfer port conveyor of the present invention in a third use state.
[0034] Figure 4 It is a schematic diagram of the main structure of the first loading unit of the present invention.
[0035] Figure 5 It is a schematic diagram of the three-dimensional structure of the first loading unit and the second loading unit of the present invention in an installed state.
[0036] Figure 6 for Figure 5 Schematic diagram of the top view structure.
[0037] Figure 7 For the present invention Figure 4 Schematic diagram of the partial cross-section structure.
[0038] Figure 8 It is a schematic diagram of the partial internal cross-sectional structure of the transition transfer mechanism of the present invention.
[0039] In the figure, 1, concrete foundation; 2, sea surface; 3, support base; 4, center positioning seat; 5, center lifting cylinder; 6, end positioning seat; 7, end lifting cylinder; 8, center lead screw; 9, outer end connecting seat; 10, guide shaft; 11, moving slide; 12, center frame; 13, end bearing; 14, synchronous lifting cylinder; 15, first upper winch; 16, upper left wire rope; 17, second upper winch; 18, upper right wire rope; 19, first lower winch; 20, lower left wire rope; 21, left pneumatic conveying pipe; 22, right Side pneumatic conveying pipe; 23, second lower winch; 24, lower right wire rope; 25, driving outer cylinder; 26, two-way material pipe; 27, driven gear; 28, driving gear; 29, central real shaft; 30, spiral feeding channel; 31, end flange; 32, connecting plate; 33, telescopic piston; 34, external ball segment; 35, internal ball segment; 36, ear seat; 37, material discharging shaft; 38, material discharging tooth; 39, driving motor; A, first loading unit; B, second loading unit; wherein, the arrow indicates the direction of bulk material conveying 40, central driving motor. DETAILED DESCRIPTION
[0040] The following is a detailed description of the embodiments of the technical solution of the present invention in conjunction with the accompanying drawings. The following embodiments are only used to more clearly illustrate the technical solution of the present invention, and are therefore only used as examples, and cannot be used to limit the scope of protection of the present invention. Figure 1-Figure 8 as shown in .
[0041] Embodiment 1: A combined transfer port conveyor comprises a concrete foundation 1 fixed on the top of an underwater foundation pile, a sea surface 2 on the right side of the concrete foundation 1 is used for docking cargo ships, a safety distance is set between the left side of the concrete foundation 1 and the shore, a support base 3 is installed above the concrete foundation 1, a pressure-bearing position control mechanism is installed on the top of the support base 3, and a first loading unit A and a second transfer unit B are respectively arranged on the front and rear sides of the pressure-bearing position control mechanism, which are spaced apart about the central vertical surface thereof. The first loading unit A and the second transfer unit B are both used for transferring and conveying bulk materials between the cargo ship end and the port end 3, and both ends of the first loading unit A and the second transfer unit B are used in conjunction with pneumatic conveying pumps installed at corresponding external positions in the working state.
[0042] The entire combined transfer port conveyor is installed in the port area, and its functions include but are not limited to: providing a connecting link for the transportation between large cargo ships that cannot dock at close range and the port shore, effectively ensuring the convenience of loading and unloading of bulk cargo such as granular particles between the port and the cargo ship, and when working, the corresponding pneumatic conveying pumps are installed at the ends of each first loading unit A and each second loading unit, thereby completing the power installation of the entire conveyor; when bulk cargo needs to be transported from the cargo ship to the shore, the cargo ship end is used as the feed end and the shore is used as the discharge end, and the working angle and state of the first loading unit A and the second transfer unit B are adjusted according to the actual transfer and transportation needs. During the adjustment process, the pressure-bearing control mechanism can control the interval between the first loading unit A and the second transfer unit B, so as to meet the pneumatic transfer and transportation of bulk materials for a single cargo ship or two cargo ships at the same time.
[0043] In any of the above schemes, it is preferred that the pressure-bearing position control mechanism is used to complete the control of the center height position of the first loading unit A and the second transfer unit B, and is also used to complete the control of the spacing distance between the first loading unit A and the second transfer unit B.
[0044] It should be noted that when the pressure-bearing position control mechanism is used to lift and lower the middle parts of the first loading unit A and the second transfer unit B, the state of the entire conveying route can be indirectly adjusted, effectively ensuring the smoothness of the conveying.
[0045] In any of the above schemes, it is preferred that the pressure-bearing control mechanism includes a central positioning seat 4 horizontally arranged above the supporting base 3, two central lifting cylinders 5 are fixedly installed at the bottom of the central positioning seat 4, and the bottoms of the two central lifting cylinders 5 are fixedly installed on the top of the supporting base 3; end positioning seats 6 are symmetrically arranged on the front and rear sides of the central positioning seat 4, two end lifting cylinders 7 are fixedly installed at the bottom of each end positioning seat 6, and the bottom of each end lifting cylinder 7 is fixedly installed on the top of the supporting base 3; each of the central lifting cylinders 5 and each of the end lifting cylinders 7 are in a synchronous motion state under working conditions; a central lead screw 8 is movably installed in the center hole of the central positioning seat 4, and the central lead screw 8 is movably installed in the center hole of the central lead screw 8. The threads on the outer walls on the front and rear sides of the core screw 8 have opposite rotation directions, and the front and rear ends of the center screw 8 respectively pass through the outside of the end positioning seat 6 and are plugged into the outer end connecting seat 9 at the corresponding position. Guide shafts 10 are respectively arranged at intervals on the left and right sides of the center screw 8, and the two ends of each guide shaft 10 are respectively movably passed through the corresponding end positioning seat 6 and the center positioning seat 4 and are fixedly connected to the outer end connecting seat 9 at the corresponding position. A movable slide 11 is respectively screwed and installed on the center screw 8 between each end positioning seat 6 and the center positioning seat 4, and the bottom of each movable slide 11 is respectively fixedly connected to the top of the first loading unit A or the top of the second transfer unit B at its corresponding position.
[0046] It should be noted that: when adjusting the pressure-bearing control mechanism, the center screw 8 is connected to the external servo motor, and the operation of the servo motor can drive the rotation of the entire center screw 8. Since the threads on the outer walls on the front and rear sides of the center screw 8 have opposite rotation directions, the two movable slides 11 thereon will approach or move away from each other when the center screw rotates, thereby achieving the purpose of quickly controlling the spacing distance between the first loading unit A and the second loading unit.
[0047] When the central lead screw 8 drives the corresponding movable slide 11 to translate, the guide shafts 10 on both sides can play a guiding role.
[0048] In any of the above schemes, it is preferred that the first loading unit A and the second transfer unit B both adopt a control transfer component with the same structure, the middle height of the control transfer component can be raised and lowered, and the height and inclination angle of the left and right sides of the control transfer component can be adjusted, one end of the control transfer component is the bulk material feed end, and the other end is the bulk material discharge end.
[0049] When the transition transfer mechanism located in the center of the regulating transfer component is raised or lowered, the height and inclination angle of the left-end conveying component and the right-end conveying component hinged at both ends can be adjusted accordingly, thereby achieving the purpose of following linkage of the entire loading and conveying route.
[0050] In any of the above schemes, it is preferred that the regulating and transferring component includes a central frame 12 fixedly installed at the bottom of the movable slide 11 of the pressure-bearing position control mechanism, and end bearings 13 are symmetrically fixedly installed at both ends inside the central frame 12, and a transition transfer mechanism is arranged in the space between the two end bearings 13, and the two ends of the transition transfer mechanism are movably passed through the end bearings 13 and are movably sealed and connected with the corresponding ends of the left end conveying component and the right end conveying component at the corresponding positions on the left and right sides thereof, and the two are internally connected.
[0051] The entire structure of the regulating and transferring assembly is connected to the movable slide 11 by the central frame 12 to ensure the stability of the entire structure; at the same time, the transition transfer mechanism located in the internal space can rely on the end bearings 13 at both ends to provide stable support to ensure its stability during fixed-axis rotation.
[0052] In any of the above solutions, preferably, each of the left-end conveying components and each of the right-end conveying components is equipped with a pneumatic conveying pump for pneumatically conveying bulk materials at its end in the working state. The pneumatic conveying pump can be made of existing technology.
[0053] In any of the above schemes, it is preferred that a plurality of synchronous lifting cylinders 14 are arranged between the support base 3 and the concrete foundation 1, the bottom of each synchronous lifting cylinder 14 is fixed to the top of the concrete foundation 1, and the top of the piston rod of each synchronous lifting cylinder 14 is fixedly installed on the bottom of the support base 3.
[0054] Taking into account the control range of the lifting height of the entire structure, the lifting of the entire structure is initially controlled by relying on the lifting of each of the synchronous lifting cylinders 14.
[0055] In any of the above schemes, it is preferred that the right end of the left-end conveying assembly can swing around the left end of the transition transfer mechanism; a first upper winch 15 is fixedly installed on the top of the movable slide 11 arranged opposite to the left-end conveying assembly, and the end of the upper left steel wire rope 16 wound on the first upper winch 15 is fixedly connected to the ear seat 36 at the top of the middle section of the left pneumatic conveying pipe 21 of the left-end conveying assembly.
[0056] In any of the above schemes, it is preferred that the left end of the right-end conveying assembly can swing around the right end of the transition transfer mechanism; a second upper winch 17 is fixedly installed on the top of the movable slide 11 arranged opposite to the right-end conveying assembly, and the end of the upper right steel wire rope 18 wound on the second upper winch 17 is fixedly connected to the ear seat 36 at the top of the middle section of the right-side pneumatic conveying pipe 22 of the right-end conveying assembly.
[0057] In any of the above schemes, it is preferred that a first lower winch 19 is fixedly installed on the concrete foundation 1 below the middle section of the left pneumatic conveying pipe 21 of the left end conveying assembly, and the end of the lower left steel wire rope 20 wound on the first lower winch 19 is fixedly connected to the ear seat 36 at the bottom of the middle section of the left pneumatic conveying pipe 21.
[0058] In any of the above schemes, it is preferred that a second lower winch 23 is fixedly installed on the concrete foundation 1 below the middle section of the right-side pneumatic conveying pipe 22 of the right-end conveying assembly, and the end of the right lower steel wire rope 24 wound on the second lower winch 23 is fixedly connected to the ear seat 36 at the bottom of the middle section of the right-side pneumatic conveying pipe 22.
[0059] It should be noted that separate winches are respectively arranged at the upper and lower parts of the left-end conveying assembly and the right-end conveying assembly corresponding to the left and right sides, which can cooperate with the tightening of the upper and lower wire ropes to achieve effective positioning, thereby ensuring the stability of the entire left-end conveying assembly and the right-end conveying assembly when they are in an inclined state to complete loading and conveying bulk materials; at the same time, the outer ends of the left-end conveying assembly and the right-end conveying assembly need to be positioned as needed during installation.
[0060] Embodiment 2: Compared with Embodiment 1, this embodiment is different in that it also includes the following technical features:
[0061] The transition transfer mechanism includes a driving outer cylinder 25 installed inside the central frame 12, and the two ends of the driving outer cylinder 25 are movably inserted through the corresponding end bearings 13, and two-way material pipes 26 are sealed and inserted in the inner holes at the two ends of the driving outer cylinder 25, and the interior of the two-way material pipe 26 is connected with the interior of the driving outer cylinder 25. A driven gear 27 is fixedly installed on the outer wall of the driving outer cylinder 25, and a driving gear 28 is meshed with one side of the driven gear 27. The driving gear 28 is fixedly connected to the motor shaft of the central driving motor 40 fixedly arranged on the left side thereof, and a central real shaft 29 is coaxially arranged in the inner cavity of the driving gear 28. A spiral feeding channel 30 is fixedly installed in the annular cavity between the central real shaft 29 and the inner wall of the driving outer cylinder 25, and the left and right ends of the spiral feeding channel 30 are respectively connected with the interior of the two-way material pipe 26 at the corresponding positions.
[0062] It should be noted that the transition transfer mechanism is mainly used to connect the left-end conveying component with the internal part of the right-end conveying component, so as to ensure that the smoothness of material transportation can be better guaranteed when the bulk material transportation of particles is completed at the cargo ship end and the port shore end. During the transportation process, the driving gear 28 and the driven gear 27 are driven to rotate through the rotation of the central driving motor, so as to effectively drive the rotation of the entire driving outer cylinder 25. During the rotation of the driving outer cylinder 25, due to the presence of a spiral hollow spiral conveying channel 30 inside, the bulk material entering from the feed port at the end or during the rotation of the spiral conveying channel 30 is gradually conveyed downstream along the spiral conveying channel 30. The spiral conveying channel 30 arranged here can serve the purpose of spiral conveying materials and temporarily storing materials for long-distance transportation.
[0063] In addition, in the pneumatic conveying state, part of the airflow enters the spiral conveying channel 30, which can also cooperate with the spiral conveying to achieve the purpose of efficiently blowing the material.
[0064] In any of the above schemes, it is preferred that telescopic pistons 33 are installed at even intervals along the circumference between the end flange 31 of the driving outer cylinder 25 and the connecting disk 32 fixedly connected to the outer side wall of the two-way material tube 26, and one end of each telescopic piston 33 is installed on the end flange 31 and the other end is installed on the connecting disk 32.
[0065] Taking into account that the angle of the intersection will change during the process of driving the central frame 12 to rise and fall, a telescopic piston 33 is provided to adjust the relative distance between the driving outer cylinder 25 and the corresponding two-way material pipe 26, so as to better match the length to the current adjustment needs and avoid the occurrence of movement dead points and movement interference; when the telescopic pistons 33 are controlled to extend and retract synchronously, the corresponding two-way material pipes 26 can be driven to change the insertion amplitude of the two-way material pipes 26.
[0066] In any of the above schemes, it is preferred that a hollow external spherical segment body 34 is integrally formed at the outer end of the bidirectional material tube 26, a hollow internal spherical segment body 35 is sealingly installed inside the external spherical segment body 34, the interior of the internal spherical segment body 35 is connected to the interior of the external spherical segment body 34, and a left end conveying component or a right end conveying component is integrally formed on the outer side wall of the internal spherical segment body 35.
[0067] Since the outer end of the bidirectional material pipe 26 is at a certain angle to the left and right conveying components and is connected internally, an external spherical segment 34 is matched with an internal spherical segment 35 and the matching parts are sealed to effectively ensure the smoothness and durability during relative rotation, while ensuring the sealing of the surrounding connection parts and controlling the leakage problem.
[0068] In any of the above schemes, it is preferred that the left-end conveying assembly includes a left-side pneumatic conveying pipe 21, the right end of which is fixedly connected to the outer wall of the built-in spherical segment body 35 and the two are internally connected; the right-end conveying assembly includes a right-side pneumatic conveying pipe 22, the left end of which is fixedly connected to the outer wall of the built-in spherical segment body 35 and the two are internally connected.
[0069] It should be noted that the left pneumatic conveying pipe 21 and the right pneumatic conveying pipe 22 are respectively inclined to realize the conveying of materials within the height difference range. At the same time, since the ends are hinged and the coordination control is achieved through the spherical segment body, the stability and sealing of the entire hinged part during rotation can be effectively guaranteed, and the effect of angle adjustment can be effectively guaranteed.
[0070] In any of the above schemes, preferably, ears 36 for connecting corresponding steel wire ropes are welded to the top and bottom of the middle section of each left-side pneumatic conveying pipe 21 and the top and bottom of the middle section of each right-side pneumatic conveying pipe 22, respectively.
[0071] In any of the above schemes, it is preferred that a material-pickup shaft 37 is horizontally arranged in the cavity of the built-in spherical segment body 35, and the front and rear ends of the material-pickup shaft 37 are movably passed through the mounting holes on the external spherical segment body 34, and a plurality of material-pickup teeth 38 are evenly spaced along the circumference of the material-pickup shaft 37 in the cavity of the built-in spherical segment body 35, and a driving motor 39 is fixedly mounted on the outer side wall of the external spherical segment body 34, and the output shaft of the driving motor 39 is fixedly connected to the end of the material-pickup shaft 37 and is used to drive the material-pickup shaft 37 to rotate.
[0072] Taking into account the possibility of accumulation of materials inside the spherical segment during bulk material conveying, the driving motor 39 is used to drive the corresponding material-discharging shaft 37 and material-discharging teeth 38 to rotate to achieve rapid control of the materials entering the spherical segment to complete the purpose of discharging and pushing the materials, thereby improving the smoothness of material conveying in this area.
[0073] Specific working principle: The entire combined transfer port conveyor designed in the present invention is installed in the port to provide a connecting link between large cargo ships that cannot dock at close range and the port shore, effectively ensuring the convenience of loading and unloading of bulk cargo such as granular materials between the port and the cargo ship.
[0074] Specifically, during operation, corresponding pneumatic conveying pumps are respectively installed at the ends of each first loading unit A and each second loading unit, thereby completing the power installation of the entire conveyor.
[0075] When bulk cargo needs to be transported from a cargo ship to the shore, the cargo ship end is used as the feed end and the shore is used as the discharge end, and the working angles and states of the first loading unit A and the second transfer unit B are adjusted according to actual transfer and transportation needs.
[0076] During the adjustment process, the pressure-bearing position control mechanism can control the spacing distance between the first loading unit A and the second transfer unit B, so as to meet the requirements of pneumatic transfer and transportation of bulk materials for a single cargo ship or two cargo ships at the same time.
[0077] Among them, the transition transfer mechanism of the regulating transfer assembly is mainly used to connect the left-end conveying assembly with the internal part of the right-end conveying assembly, so as to ensure that the smoothness of material transportation can be better guaranteed when the bulk material transportation of particles is completed at the cargo ship end and the port shore end. During the transportation process, the driving gear 28 and the driven gear 27 are driven to rotate through the rotation of the central driving motor, so as to effectively drive the rotation of the entire driving outer cylinder 25. During the rotation of the driving outer cylinder 25, due to the presence of a spiral hollow spiral feeding channel 30 inside, the bulk material entering from the feed port at the end or during the rotation of the spiral feeding channel 30 is gradually transported downstream along the spiral feeding channel 30. The spiral feeding channel 30 can serve the purpose of spirally conveying materials and temporarily storing materials for long-distance transportation.
[0078] From the above, it can be seen that the combined transfer port conveyor in the present invention adopts the concrete foundation 1 as support, which can avoid the problem of difficulty in transition of large cargo ships to dock, effectively realize the rapid transfer and transportation of bulk cargo between large cargo ships and port terminals, and reduce the difficulty of transportation; the combined transfer port conveyor adopts pneumatic conveying when completing the transfer and transportation of bulk cargo, and the entire conveying route adopts internal blocking, which can effectively deal with the problem of random dispersion of materials caused by wind during transportation, and improve the quality of the working environment.
[0079] In the present invention, the position control of the first loading unit A and the second transfer unit B on both sides is completed by relying on a pressure-bearing position control mechanism, so that the bulk material transportation of a single cargo ship can be completed as needed, thereby improving the loading efficiency; at the same time, the interval distance between the first loading unit A and the second transfer unit B can be adjusted, so that the bulk material transfer and transportation for the two cargo ships can be completed at the same time; the first loading unit A and the second transfer unit B are independent of each other in the working state, and the conveying directions of the first loading unit A and the second transfer unit B can be the same or different, which effectively improves the flexibility and operability of the transfer and transportation work; the first loading unit A and the second transfer unit B have both end portions in the working state that are used in conjunction with the pneumatic conveying pumps installed at the corresponding external positions, and the matching pneumatic conveying pumps can be selected and installed according to the bulk material conveying amount, so as to effectively combine the conveying time to quickly complete the conveying and transfer operations.
[0080] The above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit the same. Although the present invention has been described in detail with reference to the above embodiments, those skilled in the art should understand that the technical solutions described in the above embodiments can still be modified, or some or all of the technical features can be replaced by equivalents. These modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the present invention. For those skilled in the art, any replacement improvements or changes made to the implementation methods of the present invention fall within the protection scope of the present invention.
[0081] The matters not described in detail in the present invention are all known technologies to those skilled in the art.
Claims
1. A combined transfer port conveyor, comprising a concrete foundation fixed on the top of an underwater foundation pile, wherein the right sea surface of the concrete foundation is used for docking cargo ships, and is characterized in that: A safety distance is set between the left side of the concrete foundation and the shore, a support base is installed above the concrete foundation, a pressure-bearing position control mechanism is installed on the top of the support base, and a first loading unit and a second transfer unit are respectively arranged on the front and rear sides of the pressure-bearing position control mechanism with respect to the central vertical plane. The first loading unit and the second transfer unit are both used to transfer and transport bulk materials between the cargo ship end and the port end. In the working state, both end portions of the first loading unit and the second transfer unit are used in conjunction with pneumatic conveying pumps installed at corresponding external positions.
2. A combined transfer port conveyor according to claim 1, characterized in that: The pressure-bearing position control mechanism is used to complete the control of the center height position of the first loading unit and the second transfer unit, and is also used to complete the control of the spacing distance between the first loading unit and the second transfer unit.
3. A combined transfer port conveyor according to claim 2, characterized in that: The pressure-bearing position control mechanism includes a central positioning seat horizontally arranged above the supporting base, two central lifting cylinders are fixedly installed at the bottom of the central positioning seat, and the bottoms of the two central lifting cylinders are fixedly installed on the top of the supporting base; end positioning seats are symmetrically arranged on the front and rear sides of the central positioning seat, two end lifting cylinders are fixedly installed at the bottom of each end positioning seat, and the bottom of each end lifting cylinder is fixedly installed on the top of the supporting base; each central lifting cylinder and each end lifting cylinder are in a synchronous motion state under working conditions; a central lead screw is movably installed in the central hole of the central positioning seat, and the central lead screw The threads on the outer walls on the front and rear sides have opposite rotation directions, and the front and rear ends of the center screw respectively pass through the outside of the end positioning seat and are plugged into the outer end connecting seat at the corresponding position. Guide shafts are respectively arranged at intervals on the left and right sides of the center screw, and the two ends of each guide shaft are respectively movably passed through the corresponding end positioning seat and the center positioning seat and are fixedly connected to the outer end connecting seat at the corresponding position. A movable slide is respectively screwed and installed on the center screw between each end positioning seat and the center positioning seat, and the bottom of each movable slide is respectively fixedly connected to the top of the first loading unit or the top of the second transfer unit at its corresponding position.
4. A combined transfer port conveyor according to claim 3, characterized in that: The first loading unit and the second transfer unit both use a control transfer component with the same structure. The middle height of the control transfer component can be raised and lowered, and the height and inclination angle of the left and right sides of the control transfer component can be adjusted. One end of the control transfer component is the bulk material feed end, and the other end is the bulk material discharge end.
5. A combined transfer port conveyor according to claim 4, characterized in that: The regulating and transferring component includes a central frame fixedly installed at the bottom of the movable slide seat of the pressure-bearing and positioning control mechanism, and end bearings are symmetrically fixedly installed at the two ends of the center frame. A transition transfer mechanism is arranged in the space between the two end bearings, and the two ends of the transition transfer mechanism are movably passed through the end bearings and are movably sealed and connected with the corresponding ends of the left end conveying component and the right end conveying component at the corresponding positions on the left and right sides thereof, and the two are internally connected.
6. A combined transfer port conveyor according to claim 5, characterized in that: In the working state, the ends of each of the left-end conveying components and each of the right-end conveying components are equipped with pneumatic conveying pumps for pneumatically conveying bulk materials.
7. A combined transfer port conveyor according to claim 6, characterized in that: A plurality of synchronous lifting cylinders are arranged between the support base and the concrete foundation, the bottom of each synchronous lifting cylinder is fixed to the top of the concrete foundation, and the top of the piston rod of each synchronous lifting cylinder is fixedly installed on the bottom of the support base.
8. The combined transfer port conveyor according to claim 7, characterized in that: The right end of the left-end conveying assembly can swing around the left end of the transition transfer mechanism; a first upper winch is fixedly installed on the top of the movable slide seat arranged opposite to the left-end conveying assembly, and the end of the upper left steel wire rope wound on the first upper winch is fixedly connected to the top of the middle section of the left-end conveying assembly.
9. A combined transfer port conveyor according to claim 8, characterized in that: The left end of the right-end conveying assembly can swing around the right end of the transition transfer mechanism; a second upper winch is fixedly installed on the top of the movable slide seat arranged opposite to the right-end conveying assembly, and the end of the upper right steel wire rope wound on the second upper winch is fixedly connected to the top of the middle section of the right-end conveying assembly.