Dam anti-seepage and reinforcement construction method

By combining steel-concrete composite piles with reinforced concrete cap beams on the dam, a seepage prevention, reinforcement, and anti-sliding pile structure is formed, solving the problems of difficult construction quality control and high cost in existing dam reinforcement methods, and achieving a fast and economical dam reinforcement effect.

CN119021148APending Publication Date: 2024-11-26CHINA RAILWAY SHANGHAI DESIGN INST GRP CO LTD

Patent Information

Application Number
CN202411415315.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-11
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

Among existing dam reinforcement methods, flexible reinforcement measures are difficult to control in terms of construction quality, while rigid reinforcement measures are costly and cause significant damage to the dam during construction. It is difficult to effectively improve the reinforcement effect while ensuring economy and ease of construction.

Method used

A seepage prevention and reinforcement structure combining steel-concrete composite piles and reinforced concrete capping beams is adopted. The seepage prevention and reinforcement structure is formed by setting interlocking steel-concrete composite piles on the top of the dam and connecting them with reinforced concrete capping beams. A portal anti-sliding pile structure is set at the slope position, and the soil is cut by the mixing head and grouting is used to form cement-soil piles.

Benefits of technology

It achieves improved seepage prevention and anti-sliding capabilities of dikes while maintaining economic efficiency, with rapid and simple construction, reduced disturbance to existing dikes, and enhanced overall rigidity and stability of dikes.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021148A_ABST
    Figure CN119021148A_ABST
Patent Text Reader

Abstract

The invention relates to an anti-seepage and reinforcement construction method for a dam, which is characterized in that two or more rows of mutually engaged concrete-filled steel tube mixing composite piles are arranged at the top of the dam, and the two rows of concrete-filled steel tube mixing composite piles are connected and fixed by arranging a reinforced concrete top beam at the top to form an anti-seepage and reinforcement structure; two rows of concrete-filled steel tube mixing composite piles arranged in parallel are arranged at the landslide position of a dam, and the two rows of concrete-filled steel tube mixing composite piles are connected and fixed by arranging a reinforced concrete top beam at the top to form a gate-type anti-sliding row pile structure; when the concrete-filled steel tube mixing composite pile is constructed, the steel tube is rotated to sink, the mixing head arranged at the bottom of the steel tube cuts a soil body, and cement paste is sprayed to the mixing head through the grouting steel tube synchronously, so that a mixing pile is formed. The method has the advantages that the characteristics of a rigid pile and a flexible pile are combined, the reinforcing effect can be effectively improved under the condition that the economical efficiency is guaranteed, meanwhile, construction is easy, machines and tools are short, small and flexible, and construction is fast.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of pile foundation engineering, in particular to a dam anti-seepage and reinforcement construction method. Background Art

[0002] With the increase in the use time of dams on the banks of reservoirs, lakes, rivers and other water bodies in my country and the increase in the frequency of disaster weather, the diseases of dam projects are increasing day by day. The main diseases are dam seepage, deformation, cracking, instability and even collapse. At present, the reinforcement methods of dams mainly include flexible reinforcement measures such as mixing piles, rotary jet piles, cement soil walls, grouting, and rigid reinforcement measures such as bored piles, steel sheet piles, and concrete walls. However, the construction quality of flexible reinforcement measures is difficult to control, and the reinforcement body is a flexible body, so its reinforcement effect is limited. Rigid reinforcement measures are expensive and cause great damage to the dam during the construction process. Summary of the invention

[0003] The purpose of the present invention is to provide a dam anti-seepage and reinforcement construction method based on the above-mentioned deficiencies of the prior art, which combines the characteristics of rigid piles and flexible piles and can effectively improve the reinforcement effect while ensuring economy. At the same time, its construction is simple, the equipment is short and flexible, and the construction is fast, which is convenient for reinforcing existing dams in the field.

[0004] The purpose of the present invention is achieved by the following technical solutions: A dam anti-seepage and reinforcement construction method, characterized in that the construction method comprises the following steps: Two or more rows of mutually interlocking steel tube concrete mixing composite piles are arranged at the top of the dam, and the two rows of steel tube concrete mixing composite piles are connected and fixed by a reinforced concrete crown beam arranged on the top to form an anti-seepage reinforcement structure; Two rows of parallel steel tube concrete mixing composite piles are arranged at the landslide position of the dam, and the two rows of steel tube concrete mixing composite piles are connected and fixed by arranging reinforced concrete crown beams on the top to form a gate-type anti-sliding pile row structure; During the construction of the steel tube concrete mixing composite pile, the steel tube is rotated and sunk, so that the mixing head arranged at the bottom of the steel tube cuts the soil and cement slurry is simultaneously sprayed to the mixing head through the grouting steel pipe to form a mixing pile.

[0005] The gate-type anti-sliding pile row structure is arranged at the slope foot position or the slope middle position of the dam.

[0006] Two rows of mutually interlocking steel tube concrete mixing composite piles refer to that the cement soil of adjacent steel tube concrete mixing piles in the same row interlock with each other, and the cement soil of corresponding steel tube concrete mixing piles in different rows interlock with each other.

[0007] A connecting steel cage is arranged on the top of the steel pipe, and the connecting steel cage is connected to the steel cage in the reinforced concrete cap beam.

[0008] The advantages of the present invention are: 1) When steel tube concrete mixing composite interlocking piles are used as anti-seepage and reinforcement piles, due to the presence of rigid core piles, their anti-seepage ability is greatly enhanced. Under the action of water pressure, cement soil adheres to the steel tube concrete structure and is not easy to be destroyed. At the same time, since the steel tube concrete + crown beam forms an overall rigid pile structure with high overall rigidity, the leakage point is not easy to expand and cause the overall collapse of the dam; 2) When reinforced concrete mixing composite piles are used as anti-slide piles, the reinforced concrete cap beams cast on the double-row piles are rigidly connected to the composite piles to form a gate-type anti-slide row pile structure, which has a strong ability to resist landslide thrust; 3) The construction machinery of steel tube concrete mixing composite piles is short, has low site requirements, strong adaptability, causes little disturbance to existing embankments, and is fast and convenient to construct. BRIEF DESCRIPTION OF THE DRAWINGS

[0009] Figure 1 A schematic diagram of the structure of the anti-seepage reinforcement structure provided by the present invention; Figure 2 for Figure 1 Pile location plan in the Figure 3 A schematic diagram of the first structure of the gate-type anti-sliding pile structure provided by the present invention; Figure 4 for Figure 2 Pile location plan in the Figure 5 A schematic diagram of a second structure of the gate-type anti-sliding pile structure provided by the present invention; Figure 6 The construction steps of the present invention Figure Ⅰ ; Figure 7 The construction steps of the present invention Figure II ; Figure 8 The construction steps of the present invention Figure III . DETAILED DESCRIPTION

[0010] The features of the present invention and other related features are further described in detail below through embodiments in conjunction with the accompanying drawings to facilitate understanding by those skilled in the art: like Figure 1-8 As shown, the marks 1-10 in the figure respectively represent: steel tube concrete mixing composite pile 1, reinforced concrete crown beam 2, dam 3, cement slurry pump 4, grouting hose 5, mixing head 6, steel pipe 7, grouting steel pipe 8, rotary power head 9, and frame 10.

[0011] Example: Figure 1 As shown, the steel tube concrete mixing composite piles for anti-seepage and reinforcement of the dam in this embodiment are used to play an anti-seepage and reinforcement role for the dam, thereby improving the structural performance and safety of the dam.

[0012] Specifically, if Figure 1 and Figure 2 As shown, when the dam 3 has leakage or there is a risk of leakage, two or more rows of interlocking steel tube concrete mixing composite piles 1 can be set on the dam top. The steel tube concrete mixing composite piles 1 include cement soil and steel pipes set in the cement soil, and concrete is poured inside the steel pipes; reinforced concrete cap beams 2 are cast on the two rows of steel tube concrete mixing composite piles 1 and rigidly connected to the composite piles to form an anti-seepage reinforcement structure. When in use, the cement soil applied by the mixing process is used to stop leakage. At the same time, due to the presence of steel pipes set inside, the rigidity of the dam is increased, the stability of the dam is improved, and the expansion of the leakage point can also be effectively prevented.

[0013] In this embodiment, if Figure 2 As shown, the two rows of mutually interlocking steel tube concrete mixing composite piles 1 refer to that the cement soil of the adjacent steel tube concrete mixing piles in the same row interlock with each other, and the cement soil of the corresponding steel tube concrete mixing piles in different rows interlock with each other, thereby ensuring the anti-seepage and plugging effect of the cement soil.

[0014] like Figures 3 to 5 As shown, when a landslide occurs on the slope of the dam 3, two rows of steel tube concrete mixing composite piles 1 can be quickly constructed at the foot of the slope or the middle of the slope. The two rows of steel tube concrete mixing composite piles 1 are arranged in parallel and spaced at a certain distance. A reinforced concrete cap beam 2 is poured on the two rows of steel tube concrete mixing composite piles 1 and rigidly connected to the composite piles to form a gate-type anti-sliding pile row structure. When in use, the gate-type anti-sliding pile row structure resists the thrust of the landslide.

[0015] In the specific implementation of this embodiment: a connecting steel cage is arranged on the top of the steel tube of the steel tube concrete mixing composite pile 1, and the connecting steel cage is connected to the steel cage in the reinforced concrete crown beam 2 to improve the connection performance and integrity between the steel tube concrete mixing composite pile 1 and the reinforced concrete crown beam 2.

[0016] like Figures 5 to 8 As shown, this embodiment includes the following construction method: 1) The rotary power head 9 holds the steel pipe 7 and rotates, driving the bottom mixing head 6 to rotate. The mixing head 6 cuts the soil. At the same time, the cement slurry pump 4 sprays cement slurry to the mixing head 6 through the grouting hose 5 and the grouting steel pipe 8. The pile head soil is fully mixed with the cement slurry under the stirring of the mixing head 6 to form a large cement soil pile. At the same time, the frame 10 drives the steel pipe 7 and the mixing head 6 to sink while stirring in the soil. If repeated stirring is required, the frame can also drive the steel pipe and the mixing head to stir up and down to complete the repeated stirring.

[0017] 2) When constructing a portal anti-sliding pile structure, two rows of parallel steel tube concrete mixing composite piles 1 are constructed at a certain interval according to the first step, concrete is poured into the two rows of steel tube piles, and a connecting steel cage is set on the top of the piles.

[0018] When constructing the anti-seepage reinforcement structure, two rows of mutually interlocking steel tube concrete mixing composite piles 1 are constructed in the first step in a way that cement soil interlocks with each other. At the same time, concrete is poured into the two rows of steel tube piles, and a connecting steel cage is set on the pile top.

[0019] 3) Cast a reinforced concrete crown beam structure on the top of the pile to form a portal anti-sliding pile structure or an anti-seepage reinforcement structure.

[0020] Although the above embodiments have described the concepts and embodiments of the present invention in detail with reference to the accompanying drawings, ordinary technicians in this field can recognize that various improvements and changes can still be made to the present invention without departing from the scope of the claims, so they are not described here one by one.

Claims

1. A dam anti-seepage and reinforcement construction method, Features: The construction method comprises the following steps: Two or more rows of mutually interlocking steel tube concrete mixing composite piles are arranged at the top of the dam, and the two rows of steel tube concrete mixing composite piles are connected and fixed by a reinforced concrete crown beam arranged on the top to form an anti-seepage reinforcement structure; Two rows of parallel steel tube concrete mixing composite piles are arranged at the landslide position of the dam, and the two rows of steel tube concrete mixing composite piles are connected and fixed by arranging reinforced concrete crown beams on the top to form a gate-type anti-sliding pile row structure; During the construction of the steel tube concrete mixing composite pile, the steel tube is rotated and sunk, so that the mixing head arranged at the bottom of the steel tube cuts the soil and cement slurry is simultaneously sprayed to the mixing head through the grouting steel pipe to form a mixing pile.

2. A dam anti-seepage and reinforcement construction method according to claim 1, Features: The gate-type anti-sliding pile row structure is arranged at the slope foot position or the slope middle position of the dam.

3. A dam anti-seepage and reinforcement construction method according to claim 1, Features: Two rows of mutually interlocking steel tube concrete mixing composite piles refer to that the cement soil of adjacent steel tube concrete mixing piles in the same row interlock with each other, and the cement soil of corresponding steel tube concrete mixing piles in different rows interlock with each other.

4. A dam anti-seepage and reinforcement construction method according to claim 1, Features: A connecting steel cage is arranged on the top of the steel pipe, and the connecting steel cage is connected to the steel cage in the reinforced concrete cap beam.

Citation Information

Patent Citations

  • Soil slope support structure with miniature steel pipe piles with pile end concrete expansion heads, and construction method of soil slope support structure

    CN110004944A

  • Novel steel pipe stiff composite pile construction device and construction method thereof

    CN116397631A

  • Stiff mixing pile supporting structure

    CN209227542U

  • Vertical enclosure wall structure