Laying cushion structure for slope protection and construction method thereof

By flexible laying the structure of the foundation pad and concrete block splicing, combined with the zipper connection and reinforcement structure, the problems of low slope protection construction efficiency and repair difficulties are solved, rapid laying and flexible disassembly are achieved, and construction efficiency and maintenance convenience are improved.

CN119021150AInactive Publication Date: 2024-11-26TIANYUAN CONSTR GROUP +2
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202411030570.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-30
Publication Date
2024-11-26
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing slope protection construction process is complicated, time is long and difficult to repair, resulting in low construction efficiency and high cost, and inconvenient subsequent maintenance.

Method used

The flexible laying base pad and concrete block splicing structure are adopted, combined with zipper connection and reinforcement structure, to achieve rapid laying and flexible disassembly, simplify construction processes, improve efficiency and reduce costs.

Benefits of technology

It achieves efficient and fast slope laying, shortens construction period, reduces construction costs, improves the convenience of subsequent maintenance, and enhances the stability and safety of the laying structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021150A_ABST
    Figure CN119021150A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of buildings, and discloses a laying cushion structure for slope protection, which comprises a laying base cushion, concrete blocks and holes. The laying base pads are made of flexible materials, the multiple laying base pads are of the same structure, and the multiple laying base pads are sequentially spliced to form a laying pad structure; the multiple concrete blocks are evenly arranged on one side face of the laying base pad, and a set distance is formed between every two adjacent concrete blocks; the multiple holes are evenly formed in the laying base pad, and the multiple holes and the multiple concrete blocks are alternately arranged on the same side face of the laying base pad. According to the method, the laying construction efficiency is improved, the construction period is greatly shortened, the construction cost is effectively reduced, and the convenience of follow-up overhauling of the side slope is improved. The invention further discloses a construction method of the laying cushion structure for slope protection.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of construction technology, for example, to a laying mat structure for slope protection and a construction method thereof. Background Art

[0002] Revetment is a protective structure installed on embankments of rivers, lakes and coasts to resist waves and currents. Revetment is widely used due to its regular shape, uniform size, high construction efficiency, easy control of engineering quality, and little impact of weather on construction.

[0003] At present, many new types of ecological slope protection and ecological retaining wall blocks have appeared in water conservancy projects, such as articulated slope protection, stepped slope protection and flat slope protection. The above slope protection forms are all composed of a group of prefabricated concrete blocks of consistent size, shape and weight connected to each other by a series of ropes to form an interlocking matrix. However, the use of concrete blocks for slope protection construction is relatively complicated and takes a long time to complete the laying construction. When the slope protection needs to be repaired, the damaged concrete blocks need to be found and replaced one by one, which makes subsequent repairs more difficult.

[0004] Therefore, how to efficiently and quickly complete the paving of the slope, shorten the construction period, reduce the construction cost, and improve the convenience of subsequent maintenance of the slope is a technical problem that needs to be urgently solved by technical personnel in this field.

[0005] It should be noted that the information disclosed in the above background technology section is only used to enhance the understanding of the background of the present application, and therefore may include information that does not constitute the prior art known to ordinary technicians in the field. Summary of the invention

[0006] In order to provide a basic understanding of some aspects of the disclosed embodiments, a brief summary is given below. The summary is not an extensive review, nor is it intended to identify key / critical components or delineate the scope of protection of these embodiments, but rather serves as a prelude to the detailed description that follows.

[0007] The disclosed embodiments provide a paving mat structure for slope protection and a construction method thereof, which can not only efficiently and quickly complete the paving construction on the slope, simplify the construction process, reduce the construction time, improve the efficiency of the paving construction, greatly shorten the construction period, and effectively reduce the construction cost, but also a plurality of paving base mats are laid on the slope in a spliced ​​form, which can make the connection between the paving base mats more flexible, and facilitate the disassembly, repair or replacement of the damaged paving base mats separately when the paving base mats are damaged, thereby reducing the tediousness of subsequent repair or replacement construction and improving the convenience of subsequent maintenance of the slope.

[0008] In some embodiments, a paving mat structure for slope protection includes: a paving base mat, concrete blocks and holes. The paving base mat is made of a flexible material and has multiple paving base mats, the structures of the multiple paving base mats are the same, and the multiple paving base mats are sequentially spliced ​​to form a paving mat structure; there are multiple concrete blocks, and the multiple concrete blocks are evenly arranged on one side of the paving base mat, wherein there is a set spacing between two adjacent concrete blocks; there are multiple holes, and the multiple holes are evenly opened on the paving base mat, and the multiple holes and the multiple concrete blocks are alternately arranged on the same side of the paving base mat.

[0009] Optionally, two adjacent laying base mats are spliced ​​by a zipper connection structure, and the zipper connection structure includes: a buckle chain and a sliding connection member. The buckle chain is arranged on two opposite sides of the laying base mat; one side wall of the sliding connection member is connected to the buckle chain on one side of the laying base mat, and the other side wall is connected to the buckle chain on the other side of the laying base mat, and the sliding connection member is used to slide and mesh the corresponding buckle chains of the two adjacent laying base mats.

[0010] Optionally, the sliding connectors are arranged in pairs, the paired sliding connectors are respectively located on two opposite sides of the laying base mat, and the paired sliding connectors slide towards each other along the same side of the laying base mat.

[0011] Optionally, the buckle chain is made of plastic.

[0012] Optionally, the paving mat structure for slope protection further includes: a reinforcement structure. There are multiple reinforcement structures, each side of the paving base mat is provided with a reinforcement structure, and the reinforcement structure is used to fix the paving base mat on the slope.

[0013] Optionally, the reinforcement structure includes: a reinforcement plate and U-shaped soil nails. The reinforcement plate is a long rectangular structure; there are a plurality of U-shaped soil nails, which are evenly arranged on one side of the reinforcement plate.

[0014] Optionally, the concrete block has a hemispherical structure, a truncated cone structure or a conical structure.

[0015] In some embodiments, a construction method for laying a mat structure for slope protection includes:

[0016] Measure the total length of the slope to determine the number of base mats to be used;

[0017] Place a corresponding number of roll-shaped laying base mats side by side at the top of the slope;

[0018] Roll down one end of each paving base mat in turn to make the paving base mat flat on the surface of the slope;

[0019] Splicing two adjacent laying base mats in sequence;

[0020] Dig a pit at the location of the hole on the slope, and plant green plants in the pit on the slope at the location of the hole.

[0021] Optionally, sequentially splicing two adjacent laying base mats includes: connecting the two adjacent laying base mats using a zipper connection structure.

[0022] Optionally, after sequentially splicing two adjacent laying base mats, the method further includes: fixing each side of the laying base mats by using a reinforcement structure.

[0023] The paving mat structure for slope protection and the construction method thereof provided in the embodiments of the present disclosure can achieve the following technical effects:

[0024] The laying base mat is made of flexible material, which makes it have better elastic deformation ability. Before laying, the laying base mat can be rolled into a roll shape, and then one end of the laying base mat can be rolled down to make the laying base mat flat on the surface of the slope. Among them, the multiple concrete blocks evenly arranged on the laying base mat can make up for the shortcomings of the laying base mat in strength and hardness, and ensure that the overall structural strength and hardness are enhanced without affecting the curling up into bundles for storage, thereby improving the stability of the laying base mat after laying. Green plants buried in the slope are planted in the holes, and there is no need to reinforce the laying base mat laid on the slope, which makes the laying of the laying base mat on the slope more stable. This prevents the paving base from slipping and ensures the safety of paving. Therefore, when paving the slope, it can not only complete the paving construction on the slope efficiently and quickly, but also simplify the construction process, reduce the construction time, improve the efficiency of the paving construction, greatly shorten the construction period, and effectively reduce the construction cost. In addition, multiple paving bases are laid on the slope in the form of splicing, which makes the connection between the paving bases more flexible. In the event that the paving bases are damaged, the damaged paving bases can be disassembled, repaired or replaced separately, which reduces the tediousness of subsequent repair or replacement construction and improves the convenience of subsequent maintenance of the slope.

[0025] The above general description and the following description are exemplary and explanatory only and are not intended to limit the present application. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] One or more embodiments are exemplarily described by corresponding drawings, which do not limit the embodiments. Elements with the same reference numerals in the drawings are shown as similar elements, and the drawings do not constitute a scale limitation, and wherein:

[0027] Figure 1 is a structural schematic diagram of a paving mat structure for slope protection provided by an embodiment of the present disclosure;

[0028] Figure 2is a schematic diagram of the structure of the reinforcement nail provided by the embodiment of the present disclosure;

[0029] Figure 3 is a structural schematic diagram of a zipper connection structure provided by an embodiment of the present disclosure;

[0030] Figure 4 is a structural schematic diagram of another zipper connection structure provided by an embodiment of the present disclosure;

[0031] Figure 5 is a schematic structural diagram of a reinforced pad body provided in an embodiment of the present disclosure;

[0032] Figure 6 is a structural schematic diagram of a reinforcement structure provided by an embodiment of the present disclosure;

[0033] Figure 7 is a schematic structural diagram of a strip concrete block provided by an embodiment of the present disclosure;

[0034] Figure 8 is a schematic diagram of a construction method for laying a mat structure for slope protection provided by an embodiment of the present disclosure;

[0035] Fig. 9 It is a schematic diagram of another construction method for laying a mat structure for slope protection provided by an embodiment of the present disclosure.

[0036] Reference numerals:

[0037] 100. Laying base pad; 101. Fiber fabric; 102. Cement powder; 103. Reinforcement nails; 200. Concrete block; 300. Holes; 400. Zipper connection structure; 401. Buckle chain; 402. Sliding connector; 500. Reinforcement structure; 501. Reinforcement plate; 502. U-shaped soil nails; 600. Reinforcement pad; 700. Strip concrete block. DETAILED DESCRIPTION

[0038] In order to be able to understand the features and technical contents of the embodiments of the present disclosure in more detail, the implementation of the embodiments of the present disclosure is described in detail below in conjunction with the accompanying drawings. The attached drawings are for reference only and are not used to limit the embodiments of the present disclosure. In the following technical description, for the convenience of explanation, a full understanding of the disclosed embodiments is provided through multiple details. However, one or more embodiments can still be implemented without these details. In other cases, to simplify the drawings, well-known structures and devices can be simplified for display.

[0039] The terms "first", "second", etc. in the specification and claims of the embodiments of the present disclosure and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the terms used in this way can be interchanged where appropriate, so that the embodiments of the embodiments of the present disclosure described herein. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions.

[0040] In the embodiments of the present disclosure, the terms "upper", "lower", "inside", "middle", "outside", "front", "back" and the like indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings. These terms are mainly intended to better describe the embodiments of the present disclosure and their embodiments, and are not intended to limit the indicated devices, elements or components to have a specific direction, or to be constructed and operated in a specific direction. Moreover, in addition to being used to indicate directions or positional relationships, some of the above terms may also be used to indicate other meanings. For example, the term "upper" may also be used to indicate a certain dependency or connection relationship in certain circumstances. For those of ordinary skill in the art, the specific meanings of these terms in the embodiments of the present disclosure can be understood according to specific circumstances.

[0041] In addition, the terms "disposed", "connected", and "fixed" should be understood in a broad sense. For example, "connected" can be a fixed connection, a detachable connection, or an integral structure; it can be a mechanical connection, or an electrical connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be an internal connection between two devices, elements, or components. For those of ordinary skill in the art, the specific meanings of the above terms in the embodiments of the present disclosure can be understood according to specific circumstances.

[0042] Unless otherwise stated, the term "plurality" means two or more.

[0043] In the embodiment of the present disclosure, the character " / " indicates that the preceding and following objects are in an "or" relationship. For example, A / B indicates: A or B.

[0044] The term "and / or" is a description of the association relationship between objects, indicating that three relationships can exist. For example, A and / or B means: A or B, or, A and B.

[0045] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present disclosure may be combined with each other.

[0046] Combination Figure 1-2As shown, the embodiment of the present disclosure provides a paving mat structure for slope protection, including: a paving base mat 100, a concrete block 200 and a hole 300. The paving base mat 100 is made of a flexible material and has a plurality of paving base mats 100, the structures of the plurality of paving base mats 100 are the same, and the plurality of paving base mats 100 are sequentially spliced ​​to form a paving mat structure; there are a plurality of concrete blocks 200, and the plurality of concrete blocks 200 are evenly arranged on one side of the paving base mat 100, wherein a set spacing is provided between two adjacent concrete blocks 200; there are a plurality of holes 300, and the plurality of holes 300 are evenly opened on the paving base mat 100, and the plurality of holes 300 and the plurality of concrete blocks 200 are alternately arranged on the same side of the paving base mat 100.

[0047] The paving mat structure for slope protection provided by the embodiment of the present disclosure is adopted. The paving base mat 100 is made of flexible material, so that it has better elastic deformation ability. Before paving, the paving base mat 100 can be curled into a roll shape, and then one end of the paving base mat 100 is rolled downward to make the paving base mat 100 flat on the surface of the slope. Among them, the multiple concrete blocks 200 evenly arranged on the paving base mat 100 can make up for the shortcomings of the paving base mat 100 in strength and hardness, and ensure that the overall structural strength and hardness are enhanced while not affecting the curling up into bundles for storage, thereby improving the stability of the paving base mat 100 after paving. Green plants buried in the slope are planted in the holes 300, and there is no need to reinforce the paving base mat 100 laid on the slope. , making the laying of the laying base mat 100 on the slope more stable, avoiding the slipping of the laying base mat 100, and ensuring the safety of paving. Therefore, when paving the slope, not only can the paving construction on the slope be completed efficiently and quickly, but also the construction process can be simplified, the construction time can be reduced, the efficiency of the paving construction can be improved, the construction period can be greatly shortened, and the construction cost can be effectively reduced. Moreover, multiple paving base mats 100 are laid on the slope in the form of splicing, which can make the connection between the paving base mats 100 more flexible, and it is convenient to disassemble, repair or replace the damaged paving base mat 100 separately when the paving base mat 100 is damaged, thereby reducing the cumbersomeness of subsequent repair or replacement construction and improving the convenience of subsequent maintenance of the slope.

[0048] Optionally, the laying base mat 100 is a three-layer structure, wherein the upper and lower layers are both fiber fabrics 101, and the middle layer is uniformly provided with cement powder 102 that hardens in water. In this way, it can have good elasticity when not in use, and is convenient for storage, and it is convenient to quickly lay on the slope during the laying construction. At the same time, after the laying of the laying base mat 100, the cement powder 102 in it hardens in water, which can make the laying base mat 100 have higher structural strength and hardness, thereby improving the stability of the laying base mat 100 after laying.

[0049] Optionally, a plurality of reinforcing nails 103 are evenly arranged on the other side of the paving base mat 100, and each reinforcing nail 103 corresponds to a concrete block 200. In this way, when the paving base mat 100 is laid on the slope, the reinforcing nails 103 can be inserted into the slope soil layer to improve the paving stability of the paving base mat 100, and effectively prevent the paving base mat 100 from shifting under the impact of water flow.

[0050] Optionally, the length of the laying base mat 100 is greater than or equal to 1 meter and less than or equal to 3 meters, and the width of the laying base mat 100 is adapted to the width of the slope. In this way, the length and width of the laying base mat 100 are both within a reasonable range, which can avoid the situation where the construction is difficult due to the long length, and the situation where the laying time is wasted due to the short length, which is conducive to completing the paving construction of the slope efficiently and quickly, and ensures the paving effect.

[0051] Optionally, multiple concrete blocks 200 and multiple holes 300 are arranged in a crisscross pattern on the paving base mat 100, and an avoidance design is adopted between the holes 300 and the concrete blocks 200. In this way, the multiple concrete blocks 200 and multiple holes 300 can be arranged more evenly on the paving base mat 100, enhancing the visual effect after the slope is paved, and the multiple concrete blocks 200 can make up for the shortcomings of the paving base mat 100 in strength and hardness, ensuring that the overall structural strength and hardness are enhanced without affecting the curling up and bundling of the paving base mat 100, thereby improving the stability of the paving base mat 100 after paving, and planting green plants buried in the slope in the holes 300, without the need to reinforce the paving base mat 100 laid on the slope, making the paving of the paving base mat 100 on the slope more stable, and avoiding the paving base mat 100 from slipping. The safety of paving is ensured. By planting plants in the holes 300, the release of nutrients in the bottom sediment can be effectively controlled, excess nutrients in the water body can be absorbed, and the growth of phytoplankton can be inhibited. At the same time, the plants grown in the holes 300 act as a filtering barrier, which can prevent soil erosion on the top of the slope, and garbage and harmful water bodies from directly entering the river and stream under the action of surface runoff. It plays a certain purification role and reduces the pollution of the river water. The holes 300 can make the paving base 100 have good water permeability, and the water that penetrates into the filter layer can be discharged quickly, reducing the hydrostatic pressure under the surface layer, thereby avoiding excessive buoyancy to ensure the stability of the paving.

[0052] like Figure 3-4As shown, optionally, two adjacent laying base mats 100 are spliced ​​by a zipper connection structure 400, and the zipper connection structure 400 includes: a buckle chain 401 and a sliding connection member 402. The buckle chain 401 is arranged on two opposite sides of the laying base mat 100; one side wall of the sliding connection member 402 is connected to the buckle chain 401 on the side of one of the laying base mats 100, and the other side wall is connected to the buckle chain 401 on the side of the other laying base mat 100, and the sliding connection member 402 is used to slide and mesh the corresponding buckle chains 401 of the two adjacent laying base mats 100. In this way, after the paving of the paving base mat 100 is completed, the corresponding snap-fit ​​chains 401 of two adjacent paving base mats 100 are meshed and connected by using the sliding connector 402, so that the multiple paving base mats 100 form an integral structure, and the correlation between the multiple paving base mats 100 is enhanced, which not only ensures the paving quality and improves the stability of the slope paving, but also ensures the paving safety, avoids the paving base mat 100 from shifting under the impact of water flow, and simplifies the splicing method, improves the convenience of connection, and helps to complete the assembly efficiently and quickly.

[0053] It can be understood that the zipper connection structure 400 is a zipper, and the zipper is a prior art, and its specific structure and usage are not described in detail here.

[0054] Optionally, the position of the zipper connection structure 400 corresponds to the upper and lower layers of the fiber fabric 101 of the laying base mat 100. In this way, the influence of the cement layer in the middle of the laying base mat 100 on the zipper connection structure 400 is reduced, the setting position of the zipper connection structure 400 is more reasonable, and it is ensured that the zipper connection structure 400 can be used to connect two adjacent laying base mats 100 relatively smoothly.

[0055] Optionally, the sliding connectors 402 are arranged in pairs, and the paired sliding connectors 402 are respectively located on two opposite sides of the laying base mat 100 , and the paired sliding connectors 402 slide toward each other along the same side of the laying base mat 100 . In this way, two adjacent paving base mats 100 are connected by using two sliding connectors 402 that slide toward each other. After the two adjacent paving base mats 100 are connected, the sliding connector 402 can be located in a local part of the paving pad structure, reducing the impact of external factors on the sliding connector 402 and ensuring the stability and safety of the connection. For example, if a single sliding connector 402 is installed, after the sliding connector 402 connects the two adjacent paving base mats 100, the sliding connector 402 will move to the top or bottom of the slope. When it is located at the top, the sliding connector 402 is easily damaged or moved by human beings, causing it to shift and causing the two connected paving base mats 100 to separate. When it is located at the bottom, the sliding connector 402 is easily affected by the impact of water flow and shifted, which still affects the stability of the connection between the paving base mats 100.

[0056] Optionally, when two adjacent laying base mats 100 are spliced, the paired sliding connectors 402 are buckled and connected. In this way, the correlation between the two sliding connectors 402 is enhanced, and the influence of the external environment on the sliding connectors 402 is further reduced. After the paired sliding connectors 402 connect the two adjacent laying base mats 100, the paired sliding connectors 402 will not separate, ensuring the stability of the sliding connectors 402, thereby improving the stability of the splicing between the laying base mats 100.

[0057] Optionally, one of the sliding connectors 402 is provided with a snap-fitting groove, and the other sliding connector 402 is rotatably provided with a snap-fitting block, and the snap-fitting block is in an L-shaped structure. When the sliding connectors 402 are in contact, one end of the snap-fitting block can be adaptively snapped into the snap-fitting groove. In this way, after the paired sliding connectors 402 connect two adjacent laying base mats 100, the snap-fitting block on one of the sliding connectors 402 is connected to the snap-fitting groove on the other sliding connector 402, so that the two sliding connectors 402 are tightly connected together, avoiding the situation where the connection stability between the laying base mats 100 is affected by the separation of the two sliding connectors 402, and the connection method is simplified, which improves the convenience of connection.

[0058] Optionally, the buckle chain 401 is made of plastic material. In this way, the plastic material is relatively soft and easy to deform elastically, so that the buckle chain 401 connected to the side of the laying base mat 100 will not affect the overall elasticity of the laying base mat 100, so that the laying base mat 100 can still be rolled up into a roll shape, which is convenient for storing the laying base mat 100 and moving it and laying it on the slope in a rolling form.

[0059] like Figure 5-6 As shown, optionally, the paving mat structure for slope protection further includes: a reinforcing pad body 600. The reinforcing pad body 600 is made of a flexible material and has a porous mesh structure. The reinforcing pad body 600 is attached to the paving base mat 100 and has a portion located inside the concrete block 200, or covers the concrete block 200. In this way, the tightness of the connection between the concrete block 200 and the paving base mat 100 is enhanced. The reinforced pad body 600 can be used to make the concrete block 200 more stably attached to the paving base mat 100, thereby ensuring the stability of the concrete block 200. Thus, the concrete block 200 can effectively make up for the shortcomings of the paving base mat 100 in strength and hardness, ensuring that the overall structural strength and hardness are enhanced without affecting the curling and bundling of the paving base mat 100, thereby improving the stability of the paving base mat 100 after paving.

[0060] Optionally, the reinforcement pad body 600 has meshes corresponding to the holes 300. In this way, the influence of the reinforcement pad body 600 on the planting of vegetation is reduced, and it is ensured that after the reinforcement pad body 600 is installed, the reinforcement pad body 600 will not block the holes 300 on the laying base pad 100, thereby ensuring the stability of the concrete block and facilitating the planting of green plants.

[0061] Optionally, the material of the reinforcement pad body 600 is epoxy adhesive. In this way, the epoxy adhesive can absorb the concrete block 200, so that the concrete block 200 is more firmly arranged on the laying base pad 100.

[0062] Optionally, the laying mat structure for slope protection further includes: a reinforcement structure 500. There are multiple reinforcement structures 500, and each side of the laying base mat 100 is provided with a reinforcement structure 500, and the reinforcement structure 500 is used to fix the laying base mat 100 on the slope. In this way, after the laying base mat 100 is laid flat on the slope, the side of the laying base mat 100 is fixed by using the reinforcement structure 500, so that the laying base mat 100 can be laid more firmly on the slope, avoiding the displacement of the laying base mat 100 due to the impact of water flow for a long time, ensuring the stability of the paving, and improving the ability of the laying base mat 100 to resist the impact of water flow.

[0063] Optionally, after two adjacent laying base mats 100 are spliced, the spliced ​​sides of the two share a reinforcing structure 500. In this way, the arrangement of the reinforcing structure 500 is more reasonable, and the reinforcing structure 500 can be used to reinforce the part of the laying mat structure formed by sequentially splicing multiple laying base mats 100, that is, the connection position of the laying base mats 100, which can further enhance the paving stability of the laying base mats 100.

[0064] Optionally, the reinforcement structure 500 covers the zipper connection structure 400. In this way, the zipper connection structure 400 can be installed in a hidden manner using the reinforcement structure 500, which can not only make the paving base mat 100 smoother after paving and enhance the paving effect, but also protect the zipper connection structure 400, reduce the damage to the zipper connection structure 400 caused by the external environment or human factors, and ensure the stability of the connection of the paving base mat 100.

[0065] Optionally, the reinforcement structure 500 includes: a reinforcement plate 501 and U-shaped soil nails 502. The reinforcement plate 501 is a long rectangular structure; there are multiple U-shaped soil nails 502, and the multiple U-shaped soil nails 502 are evenly arranged on one side of the reinforcement plate 501. In this way, the multiple U-shaped soil nails 502 can better fix the paving base mat 100, so that it can be paved on the slope more stably, avoiding the situation of position movement under the influence of external force, and the reinforcement plate 501 ensures the flatness and neatness after connection, improves the appearance, and simplifies the reinforcement method, which improves the convenience of processing and construction.

[0066] Optionally, the thickness of the reinforcement plate 501 is greater than or equal to 4 cm and less than or equal to 6 cm. In this way, the thickness of the reinforcement plate 501 is within a reasonable range, and after installation, the height of the reinforcement plate 501 protruding from the paving base mat 100 can be reduced, so that it can be in the same plane as the paving base mat 100, thereby improving the flatness of the overall paving.

[0067] It can be understood that the length and width of the reinforcement structure 500 correspond to the length and width of the laying base pad 100, that is, the length of the reinforcement structure 500 is the same as the length of the laying base pad 100, and the width of the reinforcement structure 500 is the same as the width of the laying base pad 100. There is no need to use a large number of reinforcement structures 500, which can facilitate construction and ensure the neatness of the appearance. Secondly, the U-shaped soil nails 502 can be fully inserted into the laying base pad 100 and then extend downward to the slope, or one of the nails can be directly inserted into the slope, and the other can be inserted into the laying base pad 100 and then extend downward to the slope. I will not go into details here.

[0068] Optionally, the concrete block 200 is in a hemispherical structure, a truncated cone structure or a conical structure. In this way, the side wall of the concrete block 200 can be relatively smooth, thereby effectively reducing the influence of the concrete block 200 on the flow of water on the laying base mat 100, and allowing the water to flow back to the river again after impacting the laying base mat 100, thereby preventing the concrete block 200 from hindering the downward flow of water, ensuring that the water can flow smoothly to the river, thereby preventing the laying base mat 100 from being eroded by the water being stored on the laying base mat 100 for a long time, enhancing the protection of the laying base mat 100, and extending the service life of the laying base mat 100.

[0069] like Figure 7 As shown, optionally, the paving mat structure for slope protection also includes: strip concrete blocks 700. The strip concrete blocks 700 are arranged in pairs, and the paired strip concrete blocks 700 are respectively located on one side of the paving base mat 100 corresponding to the top of the slope and one side of the paving base mat 100 corresponding to the bottom of the slope. In this way, the strip concrete blocks 700 located at the top of the slope can enhance the stability of the paving base mat 100 after paving, and avoid the paving base mat 100 from sliding, while the strip concrete blocks 700 located at the bottom of the slope can resist the impact of water flow on the slope, improve the ability of the paving base mat 100 to resist the impact of water flow, and better protect the slope from soil erosion.

[0070] Optionally, there is a set spacing between the side of the strip concrete block 700 and the side of the paving base mat 100, and the set spacing is the same as the width of the reinforcement plate 501. In this way, the impact on the installation of the reinforcement plate 501 can be reduced, and the reinforcement construction of the paved paving base mat 100 is convenient.

[0071] Optionally, the strip concrete block 700 is in a semi-cylindrical structure or a trapezoidal structure. In this way, it can be better rolled into a roll shape and can be smoothly rolled during paving, thereby ensuring the smoothness and stability of paving.

[0072] Optionally, the length of the strip concrete block 700 is the same as the spacing between the two zipper connection structures 400 on both sides of the paving base mat 100. In this way, the influence of the strip concrete block 700 on the assembly process of two adjacent paving base mats 100 is reduced, and the convenience of assembly is improved.

[0073] Optionally, the volume of the strip concrete block 700 located at the top of the slope is greater than the volume of the strip concrete block 700 located at the bottom of the slope. In this way, the stability of the paving base mat 100 after paving can be enhanced to prevent the paving base mat 100 from slipping.

[0074] In other embodiments, the volume of the strip concrete block 700 at the top of the slope is optionally smaller than the volume of the strip concrete block 700 at the bottom of the slope. In this way, the weight of one end of the rolling paving mat 100 can be larger, thereby providing a downward pulling force for the paving mat 100 during paving, making the paving mat 100 flatter after paving and avoiding wrinkles, so that there is no need to adjust the flatness again after paving, which ensures the paving effect while simplifying the construction process and improving the paving efficiency.

[0075] It is understandable that in order to ensure the coordination and neatness of the overall structure, the volume of the strip concrete block 700 located at the top of the slope can also be the same as the volume of the strip concrete block 700 located at the bottom of the slope, which will not be repeated here.

[0076] Combination Figure 8 As shown, the embodiment of the present disclosure provides a construction method for laying a mat structure for slope protection, comprising:

[0077] S01, measure the total length of the slope and determine the number of base mats to be laid;

[0078] S02, placing a corresponding number of roll-shaped laying base mats in parallel at the top of the slope;

[0079] S03, rolling down one end of each paving base mat in turn, so that the paving base mat is laid flat on the surface of the slope;

[0080] S04, sequentially splicing two adjacent laid base mats;

[0081] S05, digging a soil pit at a position of the slope corresponding to the hole, and planting green plants in the soil pit of the slope at the position of the hole.

[0082] By adopting the construction method of the paving pad structure for slope protection provided by the embodiment of the present disclosure, when paving the slope, not only can the paving construction of the slope be completed efficiently and quickly, the construction process is simplified, the construction time is reduced, the efficiency of the paving construction is improved, the construction period is greatly shortened, and the construction cost is effectively reduced. In addition, multiple paving base pads are laid on the slope in a splicing form, which can make the connection between the paving base pads more flexible, and it is convenient to disassemble, repair or replace the damaged paving base pads separately when the paving base pads are damaged, thereby reducing the tediousness of subsequent repair or replacement construction and improving the convenience of subsequent maintenance of the slope.

[0083] Optionally, after rolling down one end of each paving base mat in turn to lay the paving base mat flat on the surface of the slope, the process further includes: checking the flatness and neatness of the paving base mat. In this way, the flatness and neatness of the paving base mat can be effectively ensured, reducing the impact on subsequent construction.

[0084] Optionally, checking the flatness of the paving of the base mat includes: observing whether there is a wrinkled part of the paving base mat. In this way, by observing whether there is a wrinkled part of the paving base mat, the flatness of the paving of the base mat can be quickly and accurately determined.

[0085] Optionally, checking the neatness of the laying of the base mat includes: using an infrared laser light or a marking line to check whether the laying of the base mat is offset. In this way, the neatness of the laying of the base mat can be accurately checked by using the infrared laser light and the marking line to ensure the accuracy of the inspection.

[0086] Optionally, before measuring the total length of the slope and determining the number of base mats to be laid, the following steps are performed: weeds, garbage, etc. on the slope surface are removed, and if there are pits on the slope surface, backfill and compact them with backfill soil, and if there are raised soil piles on the slope surface, the raised soil piles are flattened. In this way, the slope surface is flattened and meets the design slope gradient requirements, and the slope surface can be made neater and smoother, which is convenient for subsequent construction.

[0087] Optionally, before measuring the total length of the slope and determining the number of base mats to be laid, the method further includes: laying a gravel cushion layer on the slope surface, the thickness of which is 4-6 cm. In this way, the slope surface is more neat and stable, which is helpful for better paving of the base mat thereon.

[0088] Optionally, before measuring the total length of the slope and determining the number of base mats to be laid, the method further includes: laying anti-filtration geotextile on the sand and gravel cushion layer, thereby enhancing the anti-seepage effect.

[0089] Optionally, splicing two adjacent paving mats in sequence includes: connecting the two adjacent paving mats using a zipper connection structure. In this way, after the paving of the paving mats is completed, the corresponding buckle chains of the two adjacent paving mats are meshed and connected using a sliding connection piece, so that the multiple paving mats form an integral structure, and the correlation between the multiple paving mats is enhanced, which not only ensures the paving quality and improves the stability of the slope paving, but also ensures the safety of the paving, and avoids the displacement of the paving mats under the impact of water flow. The splicing method is simplified, the convenience of connection is improved, and it is helpful to complete the assembly efficiently and quickly.

[0090] Optionally, connecting two adjacent paving pads by using a zipper connection structure includes: aligning the buckle chains of the corresponding sides of the two adjacent paving pads, sliding two sliding connectors toward each other, and engaging the buckle chains of the two adjacent paving pads. In this way, by connecting the two adjacent paving pads by using two sliding connectors sliding toward each other, after the two adjacent paving pads are connected, the sliding connector can be located in a local part of the paving pad structure, reducing the influence of external factors on the sliding connector, and ensuring the stability and safety of the connection. For example, if a single sliding connector is installed, after the sliding connector connects the two adjacent paving pads, the sliding connector will move to the top or bottom of the slope. In the case of being located at the top, the sliding connector is easily damaged or moved by human beings, causing it to shift and cause the two connected paving pads to separate. In the case of being located at the bottom, the sliding connector is easily affected by the impact of water flow and shifted, which still affects the stability of the connection between the paving pads.

[0091] like Fig. 9 As shown, optionally, after the two adjacent paving mats are spliced ​​in sequence, the method further includes: S06, fixing each side of the paving mat with a reinforcement structure. In this way, after the paving mat is laid flat on the slope, the side of the paving mat is fixed with a reinforcement structure, so that the paving mat can be laid more firmly on the slope, avoiding displacement of the paving mat due to long-term impact of water flow, ensuring the stability of paving, and improving the ability of the paving mat to resist water flow impact.

[0092] Optionally, using a reinforcement structure to fix each side of the paving base mat includes: taking a reinforcement plate body of the same length as the side to be reinforced, making the side with the U-shaped soil nails face the slope, and pressing down the reinforcement plate body to fix it on the slope. In this way, the paving base mat can be better fixed by using multiple U-shaped soil nails, so that it can be laid on the slope more stably, avoiding the situation of position movement under the influence of external forces, and the reinforcement plate body ensures the flatness and neatness after connection, improves the appearance, and simplifies the reinforcement method, which improves the convenience of processing and construction.

[0093] The above description and the accompanying drawings sufficiently illustrate the embodiments of the present disclosure to enable those skilled in the art to practice them. Other embodiments may include structural and other changes. The embodiments represent only possible variations. Unless explicitly required, individual components and functions are optional, and the order of operations may vary. Portions and features of some embodiments may be included in or replace portions and features of other embodiments. The embodiments of the present disclosure are not limited to the structures described above and shown in the accompanying drawings, and various modifications and changes may be made without departing from the scope thereof. The scope of the present disclosure is limited only by the appended claims.

Claims

1. A paving mat structure for slope protection, characterized in that: include: The laying base mat (100) is made of a flexible material and has a plurality of them. The plurality of laying base mats (100) have the same structure, and the plurality of laying base mats (100) are sequentially spliced ​​to form a laying mat structure; There are a plurality of concrete blocks (200), wherein the plurality of concrete blocks (200) are evenly arranged on one side of the paving base mat (100), wherein a set distance is provided between two adjacent concrete blocks (200); The holes (300) are multiple, and the multiple holes (300) are evenly opened on the paving base mat (100), and the multiple holes (300) and the multiple concrete blocks (200) are alternately arranged on the same side of the paving base mat (100).

2. The paving mat structure for slope protection according to claim 1, characterized in that: Two adjacent laying base mats (100) are spliced ​​together via a zipper connection structure (400), and the zipper connection structure (400) comprises: The buckle chain (401) is arranged on two opposite sides of the laying base mat (100); A sliding connection member (402) has one side wall connected to a buckle chain (401) on the side of one of the laying base mats (100), and the other side wall connected to a buckle chain (401) on the side of another laying base mat (100). The sliding connection member (402) is used to slide and mesh the corresponding buckle chains (401) of two adjacent laying base mats (100).

3. The paving mat structure for slope protection according to claim 2, characterized in that: The sliding connectors (402) are arranged in pairs. The paired sliding connectors (402) are respectively located on two opposite sides of the laying base mat (100), and the paired sliding connectors (402) slide towards each other along the same side of the laying base mat (100).

4. The paving mat structure for slope protection according to claim 2, characterized in that: The buckle chain (401) is made of plastic.

5. The paving mat structure for slope protection according to claim 1, characterized in that: Also includes: The reinforcement structure (500) has a plurality of reinforcement structures, and each side edge of the paving base mat (100) is provided with a reinforcement structure (500). The reinforcement structure (500) is used to fix the paving base mat (100) on the slope.

6. The paving mat structure for slope protection according to claim 5, characterized in that: The reinforcement structure (500) comprises: The reinforcement plate (501) is a long rectangular structure; There are multiple U-shaped soil nails (502), and the multiple U-shaped soil nails (502) are evenly arranged on one side of the reinforcement plate body (501).

7. The paving mat structure for slope protection according to any one of claims 1 to 6, characterized in that: The concrete block (200) is in a hemispherical structure, a truncated cone structure or a conical structure.

8. A construction method for laying a mat structure for slope protection, characterized in that: include: Measure the total length of the slope to determine the number of base mats to be used; Place a corresponding number of roll-shaped laying base mats side by side at the top of the slope; Roll down one end of each paving base mat in turn to make the paving base mat flat on the surface of the slope; Splicing two adjacent laying base mats in sequence; Dig a pit at the location of the hole on the slope, and plant green plants in the pit on the slope at the location of the hole.

9. The construction method for laying a mat structure for slope protection according to claim 8, characterized in that: The steps of splicing two adjacent laying base mats in sequence include: Two adjacent laying base mats are connected by using a zipper connection structure.

10. The construction method for laying a mat structure for slope protection according to claim 8, characterized in that: After the two adjacent laying base mats are spliced ​​in sequence, the method further includes: Use reinforcement structures to secure each side of the laid base mat.

Citation Information

Patent Citations

  • Sludge fence capable of extending horizontally

    CN114929970A

  • Concrete body interlocking block soft mattress

    CN202745013U

  • Hardening slope protection cement blanket with holes

    CN220246968U

  • Geogrid

    US20020069605A1