Foundation treatment device and hole guiding and vibroflotation integrated equipment thereof
Through the design of the integrated equipment for lead-hole vibrating and impulse, the integration of the lead-hole device and impulse device is realized, which solves the problems of frequent movement and pollution of equipment in existing construction, improves construction efficiency and safety, and ensures the quality of foundation treatment and stability.
Patent Information
- Application Number
- CN202411361135.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-27
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2044-09-27
AI Technical Summary
In the construction of existing vibration impulse methods, the separation of the hole lead device and the vibration impulse device causes the equipment to move frequently, which easily leads to collapse and environmental pollution, and is costly.
Design a kind of integrated equipment for guide hole vibration and impulse, through the integration of guide hole device and vibration device, the removable connecting pipe fittings and open-closing retainers can be used to achieve flexible installation and operation of guide rods, avoid equipment displacement, and adopt dual guide rails The system integrates the lead hole and vibration impulse method.
The single pile lead hole and vibration impulse machine are not displaced, which improves construction efficiency and safety, reduces pollution and costs, and ensures the quality and stability of foundation treatment.
Smart Images

Figure CN119021186A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of foundation treatment technology, and more specifically, to a hole-guiding and vibrating integrated device. In addition, the present invention also relates to a foundation treatment device including the hole-guiding and vibrating integrated device. Background Art
[0002] Vibroflotation is a method of foundation treatment: it generally involves lifting a vibrator with a guide rod by a crane or drilling rig, and vibrating the soft foundation soil layer to compact it under the action of the exciting force generated by the vibrator, or vibrating holes in the foundation soil layer, filling the holes with crushed stone, etc., and vibrating and compacting the crushed stone section by section to form vibroflotated stone piles, which form a composite foundation with the surrounding foundation soil, thereby achieving the foundation treatment purpose of improving the foundation bearing capacity, increasing the foundation stability, and improving the foundation's ability to resist earthquake liquefaction.
[0003] In recent years, with the development of urban infrastructure, the application of vibroflotation construction has become more and more extensive, but it has also brought new difficulties and challenges to the construction, mainly reflected in the difficulty of vibroflotation drilling in mixed geology and poor construction quality control. For some complex geology, at present, the conventional construction plan is to first drill with a long spiral or rotary drilling rig, and then use a vibrator. Due to the coordinated work of multiple devices, the equipment needs to be moved frequently, which is easy to cause hole collapse. For this reason, it is necessary to use a mud wall protection method, which causes environmental pollution. Although the above scheme can greatly improve the construction efficiency, the use of multiple devices is costly and will cause certain pollution.
[0004] In summary, how to realize the integration of the hole-guiding device and the vibro-impacting device is a problem that needs to be solved urgently by those skilled in the art. Summary of the invention
[0005] In view of this, an object of the present invention is to provide a hole-drawing and vibratory-impacting integrated device, which can realize the integration of a hole-drawing device and a vibratory-impacting device.
[0006] Another object of the present invention is to provide a foundation treatment device including the above-mentioned integrated hole-guiding and vibro-impacting equipment.
[0007] In order to achieve the above object, the present invention provides the following technical solutions:
[0008] A hole-guiding and vibrating integrated device, comprising:
[0009] A hole-guiding device, comprising a power head, a spiral drill rod connected to the power head and used for drilling holes, and an openable hole-guiding retainer;
[0010] A vibratory device, comprising a guide rod, a vibrator disposed at the bottom of the guide rod and used for vibrating soil, an openable upper retainer and an openable lower retainer;
[0011] A pile frame, which is provided with vertically distributed columns, on which a first guide rail and a second guide rail are vertically provided with intervals, the fixing portion of the upper retainer and the fixing portion of the lower retainer are both used to slide along the first guide rail, the opening and closing portion of the upper retainer and the opening and closing portion of the lower retainer are sleeved on the outer periphery of the guide rod to selectively clamp or pass through the guide rod, the fixing portions of the power head and the guide hole retainer are both used to slide along the second guide rail, and the opening and closing portion of the guide hole retainer is sleeved on the outer periphery of the auger rod to limit the position of the auger rod;
[0012] A plurality of winches are arranged on the pile frame, and a goose head is arranged on the top of the column. The steel wire rope of one winch drops through the goose head to be connected with the upper retainer, and the steel wire rope of another winch drops through the goose head to be connected with the power head.
[0013] In one embodiment, the lower retainer includes a lower retaining movable part, a lower retaining fixed part, and a lower connecting pin shaft for connecting the lower retaining movable part and the lower retaining fixed part, and the lower retaining fixed part is provided with a lower claw for sliding along the first guide rail;
[0014] The lower retaining movable part and the lower retaining fixed part are cooperated to form a lower through hole for passing the guide rod, the inner wall of the lower through hole is provided with at least two lower key strips along the circumferential direction, a lower latch mechanism is provided between two adjacent lower key strips, the guide rod is provided with a lower key groove engaged with the lower key strip, and the lower latch mechanism is telescopically movable along the radial direction of the lower through hole to selectively clamp or pass the guide rod.
[0015] In one embodiment, the lower latch mechanism is connected to a lower safety device to prevent the guide rod from falling due to accidental contact with the lower latch mechanism.
[0016] In one embodiment, the lower latch mechanism comprises a lower holding oil cylinder and a lower holding latch connected to the lower holding oil cylinder, and the lower holding latch is arranged along the radial direction of the lower through hole;
[0017] The lower safety device includes a lower retaining limit shaft, a lower sleeve sleeved on the outer periphery of the lower retaining limit shaft, and a lower retaining reset spring embedded in the lower sleeve. One end of the lower retaining limit shaft is vertically inserted into the lower retaining pin, and the other end of the lower retaining limit shaft is used to be connected to a rope for manual control by an operator. The lower retaining reset spring is used to drive the lower retaining limit shaft to reset.
[0018] In one embodiment, the upper retainer includes an upper retaining movable part, an upper retaining fixed part, and an upper connecting pin shaft for connecting the upper retaining movable part and the upper retaining fixed part, an upper claw for sliding along the first guide rail is provided on one side of the upper retaining fixed part, and an upper pulley block is provided on the top of the upper retaining fixed part, and the upper pulley block is used to wind the wire rope;
[0019] The upper retaining movable part and the upper retaining fixed part are cooperated to form an upper through hole for passing the guide rod, the inner wall of the upper through hole is provided with at least two upper key strips along the circumferential direction, an upper latch mechanism is provided between two adjacent upper key strips, the guide rod is provided with an upper key groove for engaging with the upper key strips, and the upper latch mechanism is used to telescopically move along the upper through hole to selectively clamp or pass the guide rod.
[0020] In one embodiment, two relatively distributed, semicircular clamping plates are provided at the bottom of the upper retainer, and the clamping plates are clamped in the clamping grooves of the guide rod to be suspended and clamped in place when the guide rod is installed as a whole.
[0021] In one embodiment, the upper latch mechanism is connected to an upper safety device to prevent the guide rod from falling due to accidental contact with the upper latch mechanism.
[0022] In one embodiment, the upper latch mechanism comprises an upper retaining cylinder and an upper retaining latch connected to the upper retaining cylinder, and the upper retaining latch is arranged along the radial direction of the upper through hole;
[0023] The upper safety device includes an upper retaining limit shaft, an upper sleeve sleeved on the outer periphery of the upper retaining limit shaft, and an upper retaining reset spring embedded in the upper sleeve. One end of the upper retaining limit shaft is vertically inserted into the upper retaining pin, and the other end of the upper retaining limit shaft is used to be connected to a rope for manual control by an operator. The upper retaining reset spring is used to drive the upper retaining limit shaft to reset.
[0024] In one embodiment, the guide rod includes multiple sections of detachably connected pipes, a top plate is provided on the top of the topmost pipe, cables and water and gas pipes are provided inside the guide rod, and the top plate is provided with a pipe guide to constrain the length of the cables and water and gas pipes inside the guide rod.
[0025] A foundation treatment device comprises the integrated hole-guiding and vibro-impacting equipment as described in any one of the above items.
[0026] When using the integrated hole-guiding and vibrating device provided by the present invention, first, the upper retainer can be opened (i.e., the hinge between the opening and closing part and the fixed part of the upper retainer is opened), and its opening and closing part can be installed to the corresponding position of the guide rod, and the bottom clamping plate (i.e., the clamping plate) of the upper retainer can be clamped to the corresponding position of the guide rod. Then, the wire rope hoisted on the pile frame is connected to the upper retainer through the pulley block extending from the goose head, and the fixed part of the upper retainer and the fixed part of the lower retainer are slidably arranged on the first guide rod and the second guide rail on the side of the column, and the opening and closing part of the upper retainer and the opening and closing part of the lower retainer are controlled to retract so that the guide rod can pass through the upper retainer and the lower retainer. Afterwards, the guide rod can be lifted to the bottom of the upper retainer using relevant auxiliary equipment, and the hinge between the fixed part and the opening and closing part of the upper retainer can be connected using a pin shaft.
[0027] Then, the upper retainer is lifted by a winch, and the related auxiliary equipment continues to suspend the guide rod to prevent the guide rod from touching the bottom and damaging the water and gas pipes and cables. When the guide rod reaches a nearly vertical state, another winch is used to lift the lower retainer, so that the guide rod passes through the lower retainer, and the opening and closing part of the lower retainer is controlled to extend to clamp the guide rod, and the hinge between the fixed part and the opening and closing part of the lower retainer is connected by a pin. Then, the vibrator and the buffer device are installed, that is, the buffer device is first installed at the bottom of the guide rod, and then the vibrator is installed directly below the buffer device, and the cable of the vibrator and the water and gas pipes are connected.
[0028] Afterwards, the opening and closing part of the lower retainer is controlled to retract to pass through the guide rod, and the upper retainer clamps the guide rod to perform a falling operation under the action of gravity. When the upper retainer falls and approaches the lower retainer, the opening and closing part of the lower retainer is controlled to extend to clamp the column guide rod. In addition, the bottom clamping plate of the upper retainer can be removed, and the opening and closing part of the upper retainer is controlled to retract to pass through the guide rod. At this time, the upper retainer and the lower retainer are close, and the upper retainer can move relative to the guide rod. Under the pulling action of the hoisting wire rope, the upper retainer is driven to move upward along the guide rod. When the upper retainer reaches the top of the guide rod, the opening and closing part of the upper retainer is controlled to extend to clamp the column guide rod, and the lower retainer and the guide rod are separated (that is, the opening and closing part of the lower retainer is controlled to retract to pass through the guide rod), so that the upper retainer and the guide rod are pulled up and down by the wire rope to avoid the guide rod being much higher than the upper retainer, so that the guide rod higher than the whole machine can be put into the hole to ensure that the vibration hole can reach the required depth.
[0029] Finally, the pulley group extending from the power head through the winch can be installed as a whole on the second guide rail of the column, and then the auger rod can be connected to the power head, and the fixed part of the hole guide holder can be installed on the second guide rail of the column, and the opening and closing part of the hole guide holder can be sleeved on the outer periphery of the auger rod to limit the position of the auger rod and avoid large deviation when the auger rod is drilling.
[0030] After the device is assembled, different geological development operations can be performed in different ways according to different geological development reports. For example, the vibratory impact device can be used directly for the vibration hole operation, or the hole guide device can be used for the hole guide operation first, and then the vibratory impact device can be used for the vibration hole operation. During use, the upper retainer (the upper retainer at this time clamps the guide rod) or the power head can be lifted only by hoisting, thereby realizing the lifting operation of the guide rod or the spiral drill rod. This device is equipped with double guide rails on the column, and the hole guide device and the vibratory impact device run along different guide rails respectively, integrating the hole guide and the vibratory impact method, realizing the purpose of single pile hole guide and vibration impact machine not shifting, avoiding the collapse of the hole, and making the vibration hole operation and hole guide operation of the device efficient and easy to replace.
[0031] In summary, the integrated hole-drawing and vibro-impacting equipment provided by the present invention can realize the integration of the hole-drawing device and the vibro-impacting device.
[0032] In addition, the present invention also provides a foundation treatment device including the above-mentioned integrated hole-guiding and vibro-impacting equipment. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying creative work.
[0034] Figure 1 This is a front view of the integrated hole-guiding and vibrating device provided by the present invention;
[0035] Figure 2 It is a side view of the integrated hole-guiding and vibrating equipment;
[0036] Figure 3 It is a top view of the integrated hole-guiding and vibrating equipment;
[0037] Figure 4 It is a schematic diagram of the local structure of the hole-guiding and vibrating integrated equipment;
[0038] Figure 5 It is a top view of the column;
[0039] Figure 6 is a schematic diagram of the structure of the lower retainer;
[0040] Figure 7 is a side view of the lower retainer;
[0041] Figure 8 is a top view of the lower retainer;
[0042] Fig. 9is a cross-sectional view of the lower safety device;
[0043] Fig.10 is a schematic diagram of the structure of the upper retainer;
[0044] Fig.11 is a side view of the upper retainer;
[0045] Fig.12 is a top view of the upper retainer;
[0046] Fig.13 It is a schematic diagram of the structure when the upper retaining movable part and the upper retaining fixed part are relatively flipped;
[0047] Fig.14 is a schematic diagram of the structure of the guide rod;
[0048] Fig.15 for Fig.14 A partial enlarged view of the middle part;
[0049] Fig.16 for Fig.14 A partial enlarged view of point B in the middle;
[0050] Fig.17 This is the first step installation diagram of the drilling and vibrating integrated equipment;
[0051] Fig.18 It is a structural schematic diagram of the pallet;
[0052] Fig.19 This is a schematic diagram of the second step installation of the hole-guiding and vibrating integrated equipment;
[0053] Fig. 20 This is the third step installation diagram of the hole-guiding and vibrating integrated equipment;
[0054] Fig.21 This is a partial schematic diagram of the third step when it is installed in place;
[0055] Fig. 22 This is the fourth step installation diagram of the hole-guiding and vibrating integrated equipment;
[0056] Fig.23 This is the fifth step installation diagram of the hole-guiding and vibrating integrated equipment;
[0057] Fig.24 This is the sixth step installation diagram of the hole-guiding and vibrating integrated equipment;
[0058] Fig.25 This is a schematic diagram of the use of the spiral drill rod and vibrator after the integrated hole-guiding and vibrating equipment is installed in place.
[0059] Reference numerals:
[0060] 1-goose head, 2-power head, 3-column, 3.1-first guide rail, 3.2-second guide rail, 3.3-ladder, 4-upper retainer, 4.1-upper retaining movable part, 4.2-upper latch mechanism, 4.3-upper key bar, 4.4-upper pulley block, 4.5-upper connecting pin shaft, 4.6-upper safety device, 4.7-upper claw, 4.8-fastener, 4.9-card, 4.10-upper retaining fixture, 5-diagonal brace assembly, 6-mast erection mechanism, 7-hydraulic pump station, 8-hydraulic oil tank, 9-auxiliary winch, 10-cab, 11-short boat assembly, 12-1# main winch, 13-2# main winch, 14-3# main winch, 1 5-fuselage assembly, 16-counterweight assembly, 17-long boat assembly, 18-lifting mechanism, 19-retainer, 20-vibrator, 21-lower retainer, 21.1-lower retaining movable part, 21.2-lower latch mechanism, 21.2.1-lower retaining cylinder, 21.2.2-lower retaining latch, 21.2.3-lower retaining limit shaft, 21.2.4-lower retaining return spring, 21.3-lower key bar, 21.4-lower retaining fixing part, 21.5-lower claw, 21.6-lower safety device, 21.7-lower connecting pin, 22-guide rod, 23-auger rod, 24-hole guiding device, 25-vibrator, 26-pile frame. DETAILED DESCRIPTION
[0061] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0062] The core of the present invention is to provide a hole-guiding and vibrating integrated device, which can realize the integration of a hole-guiding device and a vibrating device. Another core of the present invention is to provide a foundation treatment device including the hole-guiding and vibrating integrated device.
[0063] Please refer to Figures 1 to 25 .
[0064] This specific embodiment provides a hole-guiding and vibrating integrated device, including:
[0065] The drilling device 24 includes a power head 2, a spiral drill rod 23 connected to the power head 2 and used for drilling holes, and an openable drilling retainer 19;
[0066] A vibrating device 25, comprising a guide rod 22, a vibrator 20 disposed at the bottom of the guide rod 22 and used for vibrating the soil, an openable upper retainer 4 and an openable lower retainer 21;
[0067] The pile frame 26 is provided with vertically distributed columns 3, on which the first guide rail 3.1 and the second guide rail 3.2 are vertically provided with intervals, the fixing portion of the upper retainer 4 and the fixing portion of the lower retainer 21 are both used to slide along the first guide rail 3.1, the opening and closing portion of the upper retainer 4 and the opening and closing portion of the lower retainer 21 are sleeved on the outer periphery of the guide rod 22 to selectively clamp or pass through the guide rod 22, the fixing portions of the power head 2 and the guide hole retainer 19 are both used to slide along the second guide rail 3.2, and the opening and closing portion of the guide hole retainer 19 is sleeved on the outer periphery of the auger rod 23 to limit the position of the auger rod 23;
[0068] A plurality of winches are provided on the pile frame 26 , and a goose head 1 is provided on the top of the column 3 , a steel wire rope of one winch is dropped through the goose head 1 to be connected with the upper retainer 4 , and a steel wire rope of another winch is dropped through the goose head 1 to be connected with the power head 2 .
[0069] It should be noted that if Figure 5 As shown, the first guide rail 3.1 and the second guide rail 3.2 arranged on the column 3 are arranged at intervals, which may refer to the relative distribution of the first guide rail 3.1 and the second guide rail 3.2 or the distribution at a certain angle, so as to facilitate the assembly of different working devices respectively, so that the hole-drawing device 24 and the vibro-impacting device 25 work in coordination. In addition, a ladder 3.3 may be arranged on the column 3 so that the staff can inspect or operate the device accordingly. In addition, during use, the vibro-impacting device 25 needs to be installed first and then the hole-drawing device 24 is installed. Because the guide rod 22 is long, it needs to be changed from a horizontal state to a vertical state, and the required space is large. If the vibro-impacting device 25 and the hole-drawing device 24 are installed at the same time, the space required for the vibro-impacting device 25 will be occupied, resulting in the inability to smoothly install the vibro-impacting device 25. After the vibro-impacting device 25 and the hole-drawing device 24 are installed, the vibro-impacting device 25 or the hole-drawing device 24 can be selected as needed during use to perform the corresponding operation. This device integrates the hole-drawing operation and the vibro-impacting operation, and has the characteristics of good pile body quality, controllable vertical precision, high construction efficiency, and good safety and stability of the whole machine.
[0070] In addition, it should be noted that a goose head 1 is provided on the top of the column 3, and many pulley groups are provided on the goose head 1 to change the direction of rotation. The power head 2 and the upper retainer 4 can move up and down relative to the guide rail of the column 3. The upper retainer 4 and the lower retainer 21 not only guide the guide rod 22, but also prevent the guide rod 22 from rotating. The hole retainer 19 mainly guides the auger rod 23 and will not limit the rotation of the auger rod 23.
[0071] It should also be noted that the pile frame 26 is also provided with a diagonal brace assembly 5 (which is arranged on opposite sides of the column 3 so that the column 3 is distributed vertically), a mast mechanism 6 (which is used to connect the diagonal brace assembly 5 and the column 3), a hydraulic pump station 7 (the device is fully hydraulically driven, the hydraulic pump station 7 is driven by a motor, and the motor is externally connected to a power supply), a hydraulic oil tank 8 (that is, all hydraulic oil in the device is provided by the hydraulic oil tank 8), an auxiliary winch 9 (which is the smallest winch and serves as a backup for subsequent lifting of some small components), a cab 10 (that is, all automatic control operations of the device are completed in the cab 10, and the cab 10 is provided with a display screen and an operating lever, etc.), a short boat assembly 11 ( It is used to realize the forward and backward movement of the device), 1# main winch 12 (one in use and one in reserve), 2# main winch 13 (for example, it can be connected to the power head 2 to realize the lifting operation of the power head 2), 3# main winch 14 (for example, it can be connected to the upper retainer 4 to realize the lifting operation of the upper retainer 4), counterweight assembly 16 (which is used to lower the center of gravity of the whole machine and improve the safety of the whole vehicle), long boat assembly 17 (which is used to realize the left and right movement of the device), lifting mechanism 18 (for example, it includes multiple vertical cylinders, the cylinders are fixed on the fuselage, and the lifting ends of the cylinders are respectively connected to the bottom of the long boat assembly 17 and the short boat assembly 11, so as to realize the spatial movement operation of the whole machine).
[0072] In one embodiment, Figures 6 to 9 As shown, the lower retainer 21 includes a lower retaining movable member 21.1, a lower retaining fixed member 21.4, and a lower connecting pin 21.7 for connecting the lower retaining movable member 21.1 and the lower retaining fixed member 21.4, and the lower retaining fixed member 21.4 is provided with a lower claw 21.5 for sliding along the first guide rail 3.1;
[0073] The lower retaining movable member 21.1 and the lower retaining fixed member 21.4 cooperate to form a lower through hole for passing the guide rod 22, and the inner wall of the lower through hole is provided with at least two lower key strips 21.3 (such as Figure 8 As shown, three lower key bars 21.3 are arranged at equal intervals along the circumferential direction. A lower latch mechanism 21.2 is provided between two adjacent lower key bars 21.3. The guide rod 22 is provided with a lower key groove engaged with the lower key bar 21.3. The lower latch mechanism 21.2 moves radially along the lower through hole to selectively latch or pass through the guide rod 22.
[0074] It should be noted that the lower retainer 21 adopts an open-and-close design to facilitate the installation of the guide rod 22. The inner wall of the lower through hole is provided with three raised lower key strips 21.3. The lower key strips 21.3 are used to prevent the vibrator 20 and the guide rod 22 from rotating. Moreover, a lower latch mechanism 21.2 is provided between two adjacent lower key strips 21.3, which refers to the position of the lower latch mechanism 21.2 in a top-down perspective (i.e., the circumferential position of the lower latch mechanism 21.2). In fact, the lower latch mechanism 21.2 is installed on the top of the lower retainer 21 (i.e., the axial position of the lower latch mechanism 21.2). For example, a cylinder control is adopted to drive the latch member of the lower latch mechanism 21.2 to extend and retract laterally, thereby clamping the guide rod 22 for fixation, or separating from the guide rod 22 through the guide rod 22.
[0075] In one embodiment, the lower latch mechanism 21.2 is connected to the lower safety device 21.6 to prevent the guide rod 22 from falling due to accidental contact with the lower latch mechanism 21.2, thereby preventing the lower latch mechanism 21.2 from failing to be in place during operation, causing the guide rod 22 to fall off and causing a dangerous accident.
[0076] In one embodiment, Fig. 9 As shown, the lower latch mechanism 21.2 includes a lower holding cylinder 21.2.1 and a lower holding latch 21.2.2 connected to the lower holding cylinder 21.2.1, and the lower holding latch 21.2.2 is arranged along the radial direction of the lower through hole; the lower safety device 21.6 includes a lower holding limit shaft 21.2.3, a lower sleeve sleeved on the outer periphery of the lower holding limit shaft 21.2.3 and a lower holding reset spring 21.2.4 embedded in the lower sleeve, one end of the lower holding limit shaft 21.2.3 is vertically inserted into the lower holding latch 21.2.2, and the other end of the lower holding limit shaft 21.2.3 is used to be connected to a rope for manual control by an operator, and the lower holding reset spring 21.2.4 is used to drive the lower holding limit shaft 21.2.3 to reset.
[0077] It should be noted that one or more of the three groups of lower latch mechanisms 21.2 are equipped with a lower safety device 21.6. Before the lower retaining latch 21.2.2 is retracted, the lower retaining limit shaft 21.2.3 needs to be pulled down and the lower retaining latch 21.2.2 needs to be pulled out (the lower retaining reset spring 21.2.4 can be automatically reset), and then the lower retaining cylinder 21.2.1 can be actuated to prevent the lower latch mechanism 21.2 from being out of place during operation, causing the guide rod 22 to fall off.
[0078] In one embodiment, the upper retainer 4 includes an upper retaining movable part 4.1, an upper retaining fixed part 4.10, and an upper connecting pin 4.5 for connecting the upper retaining movable part 4.1 and the upper retaining fixed part 4.10. An upper claw 4.7 for sliding along the first guide rail 3.1 is provided on one side of the upper retaining fixed part 4.10. An upper pulley block 4.4 is provided on the top of the upper retaining fixed part 4.10. The upper pulley block 4.4 is used for winding a wire rope. Therefore, the upper pulley block 4.4 and the upper retainer 4 can be driven to move up and down by controlling the winch operation.
[0079] The upper retaining movable part 4.1 and the upper retaining fixed part 4.10 are cooperated to form an upper through hole for passing the guide rod 22, and at least two upper key strips 4.3 are circumferentially provided on the inner wall of the upper through hole (for example, three upper key strips 4.3 are circumferentially arranged at equal intervals along the inner wall of the upper through hole), and an upper latch mechanism 4.2 is provided between two adjacent upper key strips 4.3, and the guide rod 22 is provided with an upper key groove for clamping with the upper key strip 4.3, and the upper latch mechanism 4.2 is used to telescopically move along the radial direction of the upper through hole to selectively clamp or pass the guide rod 22.
[0080] It should be noted that the upper retainer 4 adopts an open-and-close design to facilitate the installation of the guide rod 22. The inner wall of the lower through hole is provided with three raised upper key strips 4.3. The upper key strips 4.3 are used to prevent the vibrator 20 and the guide rod 22 from rotating. Moreover, an upper latch mechanism 4.2 is provided between two adjacent upper key strips 4.3 here, which refers to the position of the upper latch mechanism 4.2 in a top-down perspective (i.e., indicating the circumferential position of the upper latch mechanism 4.2). In fact, the upper latch mechanism 4.2 is installed on the top of the upper retainer 4 (i.e., indicating the axial position of the upper latch mechanism 4.2). For example, an oil cylinder control is used to drive the latch member of the upper latch mechanism 4.2 to extend and retract laterally, thereby clamping the guide rod 22 for fixing, or separating from the guide rod 22 through the guide rod 22. Furthermore, the slot on the guide rod 22 for clamping with the upper retainer 4 can be set as an inverted U-shaped slot, such as Fig.16 As shown, the two are locked and fixed when the upper retainer 4 moves along the guide rod 22, preventing the upper retainer 4 from being separated from the top of the guide rod 22.
[0081] In one embodiment, Fig.18 As shown, two relatively distributed, semicircular clamping plates 4.9 are provided at the bottom of the upper retainer 4, and the clamping plates 4.9 are clamped in the clamping grooves of the guide rod 22 to be suspended and clamped when the guide rod 22 is installed as a whole. For example, the clamping plates 4.9 can be installed at the bottom of the upper retainer 4 through fasteners 4.8, and protrusions can be provided on the clamping plates 4.9, and clamping grooves can be provided at corresponding positions of the guide rod 22 to achieve clamping and fixing of the clamping plates 4.9 and the guide rod 22, which is used for the suspension clamping of the guide rod 22 when the guide rod 22 is installed as a whole.
[0082] In one embodiment, the upper latch mechanism 4.2 is connected to the upper safety device 4.6 to prevent the upper latch mechanism 4.2 from accidentally touching and causing the guide rod 22 to fall off, thereby preventing the upper latch mechanism 4.2 from being out of place during operation and causing the guide rod 22 to fall off and cause a dangerous accident.
[0083] In one embodiment, the upper latch mechanism 4.2 includes an upper retaining cylinder and an upper retaining latch connected to the upper retaining cylinder, and the upper retaining latch is arranged along the radial direction of the upper through hole; the upper safety device 4.6 includes an upper retaining limit shaft, an upper sleeve sleeved on the outer periphery of the upper retaining limit shaft, and an upper retaining reset spring embedded in the upper sleeve, one end of the upper retaining limit shaft is vertically inserted into the upper retaining latch, and the other end of the upper retaining limit shaft is used to be connected to a rope for the operator to manually pull and control, and the upper retaining reset spring is used to drive the upper retaining limit shaft to reset.
[0084] It should be noted that the upper retainer 4 is connected to the pulley block through the goose head 1 hoisting wire rope for lifting and lowering operations. Since the upper retainer 4 also adopts an open-and-close design, it is used for lifting the guide rod 22 when it is installed as a whole. The inner wall of the upper through hole of the upper retainer 4 is provided with three raised upper key strips 4.3, which are used to prevent the vibrator 20 and the guide rod 22 from rotating. Three groups of upper latch mechanisms 4.2 are installed on the top of the upper retainer 4, which are controlled by the upper holding cylinder to drive the upper holding latch to extend and retract, thereby clamping the guide rod 22 and driving the guide rod 22 to lift and lower. One group of upper latch mechanisms 4.2 is equipped with an upper safety device 4.6 of the same design as the lower retainer. Before the upper holding latch is retracted, the operator needs to pull down the upper holding limit shaft through the rope and pull the upper holding limit shaft out of the upper holding latch (the upper holding reset spring can automatically reset), and then the upper holding cylinder can be operated to prevent the upper latch mechanism 4.2 from not being in place during the working process, causing the guide rod 22 to fall off.
[0085] In one embodiment, the guide rod 22 includes multiple sections of detachably connected pipes, a top plate is provided on the top of the topmost pipe, cables and water and gas pipes are provided inside the guide rod 22, and a pipe guide is provided on the top plate to constrain the length of the cables and water and gas pipes inside the guide rod 22. That is, the guide rod 22 is connected to the vibrator 20, the main body of the guide rod 22 is designed with pipes, cables, water and gas pipes, etc. are arranged inside the guide rod 22, and the guide rod 22 is mainly formed by connecting pipes of different standard lengths through flange bolts. The top plate is provided with a pipe guide to constrain the length of the cables, water and gas pipes, etc. inside the guide rod 22. Moreover, the outer periphery of the guide rod 22 is provided with a card slot to cooperate with the latch mechanism of the upper retainer 4 and the lower retainer 21 for relative fixation.
[0086] In order to further illustrate the installation sequence and use method of the integrated hole-guiding and vibrating equipment provided by the present invention, an example is given below, in which the guide rod 22 of the device is about 60 meters long and consists of 6 pipe structures with a length of 10 meters, which are bolted in sequence.
[0087] 1. Place the upper retaining element 4.1 as Fig.17 As shown, it is installed to the corresponding position of the second guide rod 22, and then the clamping plate 4.9 at the bottom of the retainer 4 is installed to clamp the corresponding clamping groove of the guide rod 22 with the clamping plate 4.9.
[0088] 2. Connect the pulley block extending from the winch through the goose head 1 to the upper retainer 4, and connect the upper retainer 4 and the lower retainer 21 to the first guide rail 3.1 of the column 3 through the claw structure, and connect the latch cylinder oil circuits of the upper retainer 4 and the lower retainer 21, open the latch mechanism of the upper retainer 4 and the lower retainer 21, and retract the latch. Use related auxiliary equipment to lift the guide rod 22 to the bottom of the upper retainer 4, and use the upper connecting pin 4.5 to connect the upper retaining movable part 4.1 and the upper retaining fixed part 4.10 to achieve Fig.10 state.
[0089] 3. Remove the hanging point of the second guide rod 22, use the winch to lift the upper retainer 4, and use related auxiliary equipment to continue to suspend the fifth guide rod 22 to prevent the guide rod 22 from touching the bottom and damaging the water and gas pipes and cables. When the guide rod 22 reaches a nearly vertical state, use the auxiliary winch 9 to lift the lower retainer 21, so that the guide rod 22 passes through the lower retainer 21, and the latch mechanism of the lower retainer 21 is closed, that is, the latch of the lower retainer 21 extends out to clamp the guide rod 22, and the state is as follows: Fig. 20 Status shown.
[0090] 4. Install the vibrator and the buffer device. First connect the buffer device, then place the vibrator directly below, and connect the cable and water and air pipe of the vibrator 20 to achieve the following: Fig. 22 Status shown.
[0091] 5. Open the lower latch mechanism 21.2 of the lower retainer 21, so that the latch of the lower retainer 21 is retracted, and the upper retainer 4 clamps the guide rod 22 to fall. When the upper retainer 4 falls close to the lower retainer 21, close the lower latch mechanism 21.2 of the lower retainer 21, so that the lower retaining latch 21.2.2 extends out and is locked in the corresponding position of the second guide rod, so as to achieve the following Fig.23The state shown. Remove the card plate 4.9 of the upper retainer 4, and connect the upper retaining movable part 4.1 and the upper retaining fixed part 4.10. At this time, the two retainers are close, and the upper retainer 4 can be separated relative to the guide rod 22. The wire rope pulls the upper retainer 4 to move along the guide rod 22. When the upper retainer 4 moves to the top of the guide rod 22, the upper retainer 4 and the guide rod 22 are fixed, and the lower retainer 21 and the guide rod 22 are separated, so that the guide rod 22 can be pulled up and down by the wire rope to prevent the guide rod 22 from extending out of the upper retainer 4 by a lot of positions, so that the guide rod 22 that is higher than the position of the whole machine can be put into the hole to reach the required depth. Among them, the upper retainer 4 and the lower retainer 21 each have a set of latch devices with safety devices. Before opening the latch mechanism of the retainer each time, the operator needs to pull the lower retaining limit shaft 21.2.3 or the upper retaining limit shaft to disengage it from the hole on the latch, and the corresponding latch can be retracted.
[0092] 6. Install the pulley block extending from the power head 2 through the winch onto the second guide rail 3.2 of the column 3 as a whole, and then connect the auger rod 23 to the power head 2 to achieve the following Fig.24 In addition, a suitable number of standard sections of auger rods can be installed according to the actual construction depth, and corresponding guide hole retainers 19 can be installed to avoid a large deviation in the trajectory of the auger rod when it is used.
[0093] The column 3 of the device is provided with double guide rails, which can integrate the hole-guiding and vibratory methods. The device has high operating efficiency, can realize the hole-guiding of a single pile, and can vibratory flushing without displacement of the whole machine, thus avoiding the occurrence of collapsed holes. Moreover, the unique opening and closing structure of the upper retainer 4 is used to realize the lifting and installation of the entire guide rod 22. In addition, the upper retainer 4 and the lower retainer 21 both adopt an opening and closing design, and the two are used in combination to facilitate the installation and use of the guide rod 22, and can ensure the verticality of the guide rod 22, and then the drilling accuracy of the vibratory flushing device 20. Furthermore, the device can be used with a large platform walking chassis, with a large platform space (so that the diagonal brace assembly 5, hydraulic pump station 7, cab 10 and lifting mechanism 18, etc. can be set on the pile frame 26), multiple working systems can be integrated, and a walking walking chassis is adopted, and the whole machine has high safety and stability.
[0094] In addition to the above-mentioned integrated hole-guiding and vibrating equipment, the present invention also provides a foundation treatment device including the integrated hole-guiding and vibrating equipment disclosed in the above-mentioned embodiment. For the structures of other parts of the foundation treatment device, please refer to the prior art and will not be described in detail herein.
[0095] It should be noted that, in the first guide rail 3.1 and the second guide rail 3.2 mentioned in the present invention, the first and the second are only used to distinguish the different positions, and there is no order of precedence.
[0096] In addition, it should be noted that the directions or positional relationships indicated by "up and down", "vertical" and "horizontal" in the present invention are based on the directions or positional relationships shown in the accompanying drawings and are only for the purpose of simplifying the description and facilitating understanding. They do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction. Therefore, they should not be understood as limitations on the present invention.
[0097] In this specification, each embodiment is described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the embodiments can be referred to each other. Any combination of all embodiments provided by the present invention is within the protection scope of this invention and will not be described in detail here.
[0098] The foundation treatment device and the integrated hole-guiding and vibrating equipment provided by the present invention are introduced in detail above. Specific examples are used herein to illustrate the principles and implementation methods of the present invention. The description of the above embodiments is only used to help understand the method of the present invention and its core idea. It should be pointed out that for ordinary technicians in this technical field, without departing from the principles of the present invention, several improvements and modifications can be made to the present invention, and these improvements and modifications also fall within the scope of protection of the claims of the present invention.
Claims
1. A hole-guiding and vibrating integrated device, characterized in that: include: A hole-guiding device (24), comprising a power head (2), a spiral drill rod (23) connected to the power head (2) and used for drilling holes, and an openable hole-guiding retainer (19); A vibratory device (25) comprising a guide rod (22), a vibrator (20) disposed at the bottom of the guide rod (22) and used for vibrating soil, an openable upper retainer (4), and an openable lower retainer (21); A pile frame (26) is provided with vertically arranged columns (3), wherein the columns (3) are vertically provided with a first guide rail (3.1) and a second guide rail (3.2) which are spaced apart from each other, the fixing portion of the upper retainer (4) and the fixing portion of the lower retainer (21) are both used to slide along the first guide rail (3.1), the opening and closing portion of the upper retainer (4) and the opening and closing portion of the lower retainer (21) are sleeved on the outer periphery of the guide rod (22) to selectively clamp or pass through the guide rod (22), the fixing portions of the power head (2) and the guide hole retainer (19) are both used to slide along the second guide rail (3.2), and the opening and closing portion of the guide hole retainer (19) is sleeved on the outer periphery of the auger rod (23) to limit the position of the auger rod (23); A plurality of winches are provided on the pile frame (26), a goose head (1) is provided on the top of the column (3), a steel wire rope of one winch is dropped through the goose head (1) to be connected to the upper retainer (4), and a steel wire rope of another winch is dropped through the goose head (1) to be connected to the power head (2).
2. The hole-guiding and vibrating integrated equipment according to claim 1, characterized in that: The lower retainer (21) comprises a lower retaining movable part (21.1), a lower retaining fixed part (21.4), and a lower connecting pin (21.7) for connecting the lower retaining movable part (21.1) and the lower retaining fixed part (21.4); the lower retaining fixed part (21.4) is provided with a lower claw (21.5) for sliding along the first guide rail (3.1); The lower retaining movable part (21.1) and the lower retaining fixed part (21.4) cooperate to form a lower through hole for passing the guide rod (22); the inner wall of the lower through hole is provided with at least two lower key strips (21.3) along the circumferential direction; a lower latch mechanism (21.2) is provided between two adjacent lower key strips (21.3); the guide rod (22) is provided with a lower key groove engaged with the lower key strips (21.3); the lower latch mechanism (21.2) moves radially along the lower through hole to selectively latch or pass through the guide rod (22).
3. The hole-drawing and vibrating integrated equipment according to claim 2, characterized in that: The lower latch mechanism (21.2) is connected to the lower safety device (21.6) to prevent the guide rod (22) from falling due to accidental contact with the lower latch mechanism (21.2).
4. The hole-drawing and vibrating integrated equipment according to claim 3, characterized in that: The lower latch mechanism (21.2) comprises a lower retaining oil cylinder (21.2.1) and a lower retaining latch (21.2.2) connected to the lower retaining oil cylinder (21.2.1), and the lower retaining latch (21.2.2) is arranged along the radial direction of the lower through hole; The lower safety device (21.6) comprises a lower retaining limit shaft (21.2.3), a lower sleeve sleeved on the outer periphery of the lower retaining limit shaft (21.2.3), and a lower retaining reset spring (21.2.4) embedded in the lower sleeve, one end of the lower retaining limit shaft (21.2.3) is vertically inserted into the lower retaining latch (21.2.2), the other end of the lower retaining limit shaft (21.2.3) is used to be connected to a rope for manual control by an operator, and the lower retaining reset spring (21.2.4) is used to drive the lower retaining limit shaft (21.2.3) to reset.
5. The hole-guiding and vibrating integrated equipment according to any one of claims 1 to 4, characterized in that: The upper retainer (4) comprises an upper retaining movable part (4.1), an upper retaining fixed part (4.10), and an upper connecting pin (4.5) for connecting the upper retaining movable part (4.1) and the upper retaining fixed part (4.10); an upper claw (4.7) for sliding along the first guide rail (3.1) is provided on one side of the upper retaining fixed part (4.10); an upper pulley block (4.4) is provided on the top of the upper retaining fixed part (4.10); and the upper pulley block (4.4) is used for winding the steel wire rope; The upper retaining movable part (4.1) and the upper retaining fixed part (4.10) are cooperatively provided with an upper through hole for passing the guide rod (22); at least two upper key strips (4.3) are circumferentially provided on the inner wall of the upper through hole; an upper latch mechanism (4.2) is provided between two adjacent upper key strips (4.3); the guide rod (22) is provided with an upper key groove for engaging with the upper key strips (4.3); and the upper latch mechanism (4.2) is used to telescopically move along the radial direction of the upper through hole so as to selectively latch or pass through the guide rod (22).
6. The hole-drawing and vibrating integrated equipment according to claim 5, characterized in that: The bottom of the upper retainer (4) is provided with two relatively distributed, semicircular clamping plates (4.9), and the clamping plates (4.9) are clamped in the clamping grooves of the guide rod (22) to be suspended and clamped when the guide rod (22) is installed as a whole.
7. The hole-drawing and vibrating integrated equipment according to claim 5, characterized in that: The upper latch mechanism (4.2) is connected to the upper safety device (4.6) to prevent the guide rod (22) from falling due to accidental contact with the upper latch mechanism (4.2).
8. The hole-guiding and vibrating integrated equipment according to claim 7, characterized in that: The upper latch mechanism (4.2) comprises an upper retaining oil cylinder and an upper retaining latch connected to the upper retaining oil cylinder, wherein the upper retaining latch is arranged along the radial direction of the upper through hole; The upper safety device (4.6) comprises an upper retaining limit shaft, an upper sleeve sleeved on the outer periphery of the upper retaining limit shaft, and an upper retaining reset spring embedded in the upper sleeve, one end of the upper retaining limit shaft is vertically inserted into the upper retaining latch, the other end of the upper retaining limit shaft is used to be connected to a rope for manual control by an operator, and the upper retaining reset spring is used to drive the upper retaining limit shaft to reset.
9. The integrated hole-guiding and vibrating device according to any one of claims 1 to 4, characterized in that: The guide rod (22) comprises a plurality of detachably connected pipes, a top plate being provided on the top of the topmost pipe, a cable and a water and gas pipe being provided inside the guide rod (22), and a pipe guide being provided on the top plate to restrict the length of the cable and the water and gas pipe inside the guide rod (22).
10. A ground treatment device, characterized in that: The invention comprises the integrated hole-guiding and vibro-impacting equipment as described in any one of claims 1 to 9 above.
Citation Information
Patent Citations
Hydraulic lifting and locking apparatus for anti-slide pile
CN101387108A
Full-stroke hole-leading hydraulic static pile driver
CN103669351A
Pile embracing system
CN109989402A
Method for controlling construction perpendicularity of vibro-replacement stone column machine
CN115704211A
Ultra-deep vibro-replacement gravel pile drilling machine and construction method thereof
CN116927665A
Cited By
Vibroflotation equipment
CN120945876A
A vibroflotation device
CN120945876B