Large-span dome jig frame form switching construction method
Through the method of phase-by-stage adjustment and reverse engineering, the large-span dome tire frame shape switching is achieved, solving the problem of steel dome assembly and construction of large-scale span and height changes in the existing technology, improving construction efficiency and accuracy, and suitable for Assembly of the dome of the shell of the nuclear power plant.
Patent Information
- Application Number
- CN202411227041.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-03
- Publication Date
- 2024-11-26
AI Technical Summary
The existing technology cannot effectively realize the switching of the morphology of large-span steel dome frames, resulting in increased construction period and cost, and lack of targeted solutions to meet the assembly needs of the shell dome of nuclear power plants with large changes in spans and heights.
Through data confirmation, measurement and layout, positioning guide rails, adjusting the string beam and the lower triangle one by one, the reverse engineering method is used to achieve the shape switching of the tire frame, including the construction of the inner cylinder to top down in the center, the smooth movement of the lower triangle and the adjustment of the string beam one by one. , ensure the adaptability of the tire frame at different spans and elevations.
It realizes flexible switching of tire frame shape, suitable for steel dome assembly with different spans and elevations, shortens the installation process, improves construction efficiency and accuracy, and fills the gap in steel dome tire frame shape switching technology in the nuclear power construction industry.
Smart Images

Figure CN119021479A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of steel structure engineering construction, and in particular to a large-span dome cradle form switching construction method. Background Art
[0002] The Hualong One Nuclear Power Plant adopts a single-stack layout and double-layer containment design, that is, it has an inner and outer double dome. The assembly and construction process of its steel dome containment shell uses an arch membrane molding frame that is unique to the Zhangzhou Nuclear Power Project. It adapts to the dome's own spherical petal structure, provides a higher level of quality assurance for the assembly and construction of the dome in the Hualong One Nuclear Power Plant, and raises the assembly quality of the dome to a qualitative level.
[0003] During the construction of the outer shell dome of the Hualong One nuclear power plant, the diameter of its lower mouth increased by 12.3% compared with the lower diameter of the inner shell dome, and the height of the outer shell dome decreased by 45.41% compared with the height of the inner shell dome. The span of the steel dome increased, making it no longer suitable to use the original tire frame for construction.
[0004] The technical solution in the existing patent technology "CN 112609832 B-A construction method and construction frame for the double-shell dome arch membrane of a nuclear power plant nuclear island" is that S6 controls the overall height of the arch membrane frame by adjusting the top elevation of the center cylinder frame, which is suitable for dome forming with different curvatures, and controls the radius of the arch membrane frame by adjusting the radial spacing of the lower corner support points, which is suitable for dome forming with different spans. The patent solution has the following steps for adjusting the overall span and height of the frame: 1. Release the connection between the string beam and the upper corner support point, and lower the string beam to the corbel; 2. Adjust the installation elevation of the center cylinder frame; 3. Lift the string beam and connect it to the upper corner support point. In this technical solution, the beam string is lowered onto the corbel, and at this time the beam string makes a circular motion with the lower connection point as the center. The connection point of the upper corner and the connection point of the corbel are in the same arc trajectory of this circular motion, and the beam string is in a lying state. After a large height adjustment of the drum frame, when the beam string is lifted again to connect with the upper corner, the connection point of the upper corner is not in the same arc trajectory of the circular motion. Unless a large adjustment is made to the position of the lower beam string connection point, the connection action of the beam string and the upper corner fulcrum cannot be completed. The construction method for switching the frame shape in this patented technical solution is only applicable to a small range of elevation and span changes, and is not applicable to construction projects where the outer dome of the Hualong One nuclear power plant has a large change in span and height compared to the inner dome.
[0005] At present, in the nuclear power construction industry, there is no targeted solution for how to achieve the shape switching of the cradle first used for auxiliary steel dome assembly, and there are limited construction cases to refer to. For other similar large-span steel structures, the shape switching mainly adopts overall disassembly and assembly, which requires more construction site and repeats the disassembly and assembly process of the dome assembly cradle, resulting in a significant increase in construction period and cost. Summary of the invention
[0006] The present invention aims to solve the deficiencies of the prior art and aims to provide a construction method for switching the tyre frame shape of a large-span dome, so as to achieve the purpose of making the tyre frame suitable for construction projects with larger spans, shortening the tyre frame installation process, and ensuring installation accuracy.
[0007] The present invention is achieved through the following technical solutions:
[0008] A large-span dome frame form switching construction method comprises the following steps:
[0009] S1: Data confirmation, determine the tire frame usage requirements;
[0010] S2: Measure and lay out, locate the span radius and elevation of the tire frame, and set guide rails at each lower triangle position;
[0011] S3: Perform shape switching construction on the dome assembly frame;
[0012] The step S3 also includes the following specific steps:
[0013] S3-1: Release the upper end constraint of the beam string and lift the beam string so that the upper end of the beam string rotates around its lower end and lowers it to the bracket of the center inner tube;
[0014] S3-2: completing the lowering of the upper ends of the remaining beam string beams;
[0015] S3-3: Adjust the height of the center inner tube to reach the specified elevation;
[0016] S3-4: Release the constraints on both ends of the beam string and hoist the beam string so that the upper end of the beam string is connected to the upper triangle of the central inner tube and the lower end is placed on a temporary scaffold; then adjust the span of the beam string section by section;
[0017] S3-5: After all the beam string sections are adjusted, the entire circle of lower triangles are connected to the guide rails and moved to the positioned tire frame span radius position, and then the guide rails are removed;
[0018] S3-6: Connect the lower end of the beam string through the traction device, and drive the lower end of the beam string to rotate around its upper end, so that the lower end of the beam string is connected to the lower triangle, until the construction of all remaining beam strings is completed.
[0019] Compared with the prior art, the construction method for switching the shape of the frame is only applicable to the case where the elevation and span change within a small range, and is not applicable to the construction project where the span and height of the outer shell dome of the Hualong One nuclear power plant change greatly compared to the inner dome. In addition, in the nuclear power construction industry, there is no targeted solution for how to achieve the shape switching of the frame first used for auxiliary steel dome assembly. The present invention fills the gap in the steel structure installation technology of the assembly frame used for the steel outer dome in the nuclear power construction industry in the shape switching, and provides a practical, efficient, safe and convenient large-span dome frame shape switching construction method, so as to achieve the shape switching of the dome frame, so that it can meet the assembly of steel domes with different spans and elevations within a certain range, and also to achieve the assembly construction of the outer dome of the Hualong One nuclear power plant. In the specific scheme, the shape change installation construction of the lower triangle, the string beam and the central inner tube includes the following operations: S1, data confirmation, determination of the use requirements of the frame; S2, measurement and laying out, positioning of the span radius and elevation of the frame; S3, shape switching construction of the dome assembly frame. In the present invention, the central inner tube is constructed from top to bottom, the lower triangle is constructed in a smooth manner, and the string beam is constructed in a segment-by-segment adjustment manner. The requirements for the use of the cradle as described in S1 include the requirements for relatively large spans / small elevations and small spans / large elevations. Therefore, the construction method for switching the dome cradle shape shown in the present invention can adjust the large and small spans through reverse engineering, and adjust the shape of the cradle according to engineering requirements, which has high engineering adaptability.
[0020] Furthermore, the use requirements of the tire frame include engineering use requirements of large span / small elevation, and engineering use requirements of small span / large elevation.
[0021] As a method of measuring and locating the span radius and elevation after the tire frame shape is switched, and facilitating the movement and positioning of the lower triangle, the step S2 includes the following specific steps:
[0022] Position the elevation of the upper triangle of the inner tube truss ring beam at the center of the tire frame, and the overall layout radius of the lower triangle of the tire frame;
[0023] After the lower triangle is positioned at the radius of the overall layout, the lower triangle pier is circled in advance according to the newly positioned radius to mark the position of the new lower triangle group; the lower triangle includes a first diagonal brace and a second diagonal brace, the lower end of the first diagonal brace is provided with a pier, the lower end of the second diagonal brace is connected to the ground through a ground anchor, and the upper end of the first diagonal brace is used to connect the upper end of the second diagonal brace; a slide groove is reserved at the bottom of the pier;
[0024] The step of marking the position of the new lower triangle group also includes marking the positions of several new piers in the annular direction. When marking the positions of the new piers of the lower triangle, the guide rails are laid out at the same time; the guide rails are located between the new lower triangle group and the original lower triangle group, and are laid out along the radial direction of the tire frame. The guide rails are used to pass through the slide groove at the bottom of the pier, and the guide rails and the slide grooves are adapted and slidably connected.
[0025] To ensure the stability of the disassembly and assembly of the beam string, the step S3-2 further includes the following specific steps:
[0026] When a certain beam string is operated in step S3-1, the corresponding beam string at its radially symmetrical position is operated in step S3-1 at the same time, and the step S3-1 is completed in turn in a bidirectional counterclockwise or clockwise direction, so as to complete the lowering of the upper ends of all other beam string.
[0027] To sequentially complete the disassembly and assembly and elevation adjustment of the central inner tube, the central inner tube includes an inner tube and a truss ring beam, and the truss ring beam includes an outer ring beam and an inner ring beam;
[0028] The step S3-3 also includes the following specific steps:
[0029] 3-a: Release the connection between the inner ring beam and the outer ring beam in the truss ring beam, and lift the inner ring beam to the temporary storage area;
[0030] 3-b: Release the connection between the outer ring beam and the inner tube, and lift the outer ring beam to the temporary storage area;
[0031] 3-c: After the elevation of the cylindrical frame of the inner tube is adjusted, lift the outer ring beam and put it on the inner tube;
[0032] 3-d: After the outer ring beam forms a ring structure, the inner ring beam and the outer ring beam are hoisted to form an integral structure, and the elevation of the center inner tube is remeasured at the same time.
[0033] To ensure the stability of the disassembly and assembly of the beam string, when the S3-4 operation is completed for a certain beam string, the corresponding beam string at its radially symmetrical position is simultaneously subjected to the S3-4 operation, and the S3-4 operation is repeated in a bidirectional counterclockwise or clockwise direction until all the beam string sections are adjusted.
[0034] In order to facilitate moving all lower triangles from the original lower triangle group to the new triangle group, step S3-5 also includes the following specific steps:
[0035] 5-a: Release the connection between the second diagonal brace in the lower triangle and the ground anchor, and release the connection between the connecting rods and shear braces between the adjacent lower triangles;
[0036] 5-b: Connect the bottom pier of the first diagonal brace to the guide rail through the reserved slide groove, and connect the second diagonal brace to the corresponding guide rail, and connect the guide rail with the slide rail device to push the overall lower triangular upper guide rail;
[0037] 5-c: Push the lower triangle to move along the guide rail to the marked position;
[0038] 5-d: Repeat the above steps 5-a→5-b→5-c in a clockwise or counterclockwise direction until the entire lower triangle is pushed to the marked position;
[0039] 5-e: Pull out the guide rail, release the connection between the second diagonal brace and the slide rail device, reconnect the second diagonal brace to the ground with a ground anchor, and connect the adjacent lower triangular connecting rod and the shear brace;
[0040] 5-f: Repeat the above step 5-e in a clockwise or counterclockwise direction to connect the entire circle of lower triangles into a whole.
[0041] As a specific structural form of a slide rail device, the guide rail is an I-shaped guide rail, the lower flange of the I-shaped guide rail is connected to the ground, and the upper flange of the I-shaped guide rail is slidably connected to the slide rail device;
[0042] The slide rail device includes a sliding plate slidably clamped on both sides of the upper flange, the upper ends of the two sliding plates are extended upward, and a clamping gap is left between the two extended parts, and the lower end of the second diagonal brace is inserted into the clamping gap and bolted to the two extended parts respectively. The cross section of the sliding plate is similar to a "J" shape, and this shape setting can facilitate the adaptation of the inclination angle of the second diagonal brace when connecting the second diagonal brace.
[0043] In order to avoid occupying too large a construction site and to achieve rapid return of the beam string, the step S-6 also includes the following specific steps:
[0044] 6-a: A winch is arranged outside the lower triangle, and the winch is connected by a wire rope. The middle wire rope passes through the connection point at the top of the lower triangle, and the end of the wire rope is connected to the lower connection point of the string beam;
[0045] 6-b: Start the winch, drive the wire rope to pull the lower connection point of the beam string to make a circular motion with the upper connection point of the beam string as the center to the top connection point of the lower triangle, and connect the beam string with the lower triangle;
[0046] 6-c: Synchronously, the beam string at its radially symmetrical position performs step 6-b at the same time;
[0047] 6-d: The remaining beam string are installed symmetrically, and finally the adjacent annular members and shear braces 14 of the beam string are connected.
[0048] To ensure overall stability, in step S-6, the eight cross-orthogonal beam string beams are first symmetrically positioned, then the shear braces 14 between the eight beam string beams are connected, and finally the other beam string beams are positioned in turn in a bidirectional clockwise or counterclockwise direction.
[0049] Compared with the prior art, the present invention has the following advantages and beneficial effects:
[0050] 1. The present invention provides a large-span dome frame shape switching construction method, which can complete the dome assembly frame, freely switch the shape between the inner dome and outer dome assembly frames according to engineering requirements, realize frame integration, and fill the technical gap in the nuclear power construction industry in the shape switching of steel dome assembly frames;
[0051] 2. The invention provides a large-span dome frame shape switching construction method, which provides a new research direction and new construction case for the steel structure frame switching construction between large span / small elevation and small span / large elevation. BRIEF DESCRIPTION OF THE DRAWINGS
[0052] In order to more clearly illustrate the technical solutions of the exemplary embodiments of the present invention, the following briefly introduces the drawings required for use in the embodiments. It should be understood that the following drawings only illustrate certain embodiments of the present invention and should not be regarded as limiting the scope. For those of ordinary skill in the art, other relevant drawings can be obtained based on these drawings without creative work. In the drawings:
[0053] Figure 1 A schematic diagram of the process provided by the present invention;
[0054] Figure 2 A top view of the dome assembly frame guide rail arrangement provided by the present invention;
[0055] Figure 3 A schematic cross-sectional view of the beam string unloading construction provided by the present invention;
[0056] Figure 4 A schematic cross-sectional view of the span adjustment and repositioning construction of the beam string provided by the present invention;
[0057] Figure 5 A cross-sectional schematic diagram of a slide rail device provided by the present invention;
[0058] Figure 6 A top view of the triangular smoothing construction under the tire frame provided by the present invention;
[0059] Figure 7 This is a top view of the overall connection construction of the tire frame and the beam string provided by the present invention.
[0060] Marks and corresponding parts names in the attached drawings:
[0061] 1-new lower triangle group, 2-original lower triangle group, 3-guide rail, 4-pier mark position, 5-string beam, 6-corbel, 7-truck crane, 8-first diagonal brace, 9-second diagonal brace, 10-outer ring beam, 11-inner ring beam, 12-bolt, 13-sliding plate, 14-shear brace, 15-connecting rod, 16-winch, 17-wire rope, 18-temporary scaffolding. DETAILED DESCRIPTION
[0062] In order to make the objectives, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with embodiments and drawings. The exemplary embodiments of the present invention and their description are only used to explain the present invention and are not intended to limit the present invention.
[0063] Embodiment 1:
[0064] This embodiment 1 provides a large-span dome frame form switching construction method, such as Figure 1-Figure 7 As shown, the following steps are included:
[0065] S1: Data confirmation, determine the tire frame usage requirements;
[0066] S2: Measure and lay out, locate the span radius and elevation of the tire frame, and set guide rails at each lower triangle position;
[0067] S3: Perform shape switching construction on the dome assembly frame;
[0068] The step S3 also includes the following specific steps:
[0069] S3-1: release the constraint on the upper end of the beam string 5, and lift the beam string 5, so that the upper end of the beam string 5 rotates around its lower end and is lowered onto the bracket 6 of the central inner tube;
[0070] S3-2: completing the lowering of the upper ends of the remaining beam string 5;
[0071] S3-3: Adjust the height of the center inner tube to reach the specified elevation;
[0072] S3-4: release the constraints on both ends of the beam string 5, and hoist the beam string 5, so that the upper end of the beam string 5 is connected to the upper triangle of the central inner tube, and the lower end is placed on the temporary scaffolding 18; then adjust the span of the beam string 5 section by section;
[0073] S3-5: After all the beam string 5 are adjusted section by section, the entire circle of lower triangles is connected to the guide rail 3 and moved to the positioned tire frame span radius position, and then the guide rail 3 is removed;
[0074] S3-6: Connect the lower end of the beam string 5 through the traction device, and drive the lower end of the beam string 5 to rotate around its upper end, so that the lower end of the beam string 5 is connected to the lower triangle, until the construction of all remaining beam string 5 is completed.
[0075] Compared with the prior art, the construction method for switching the shape of the frame is only applicable to the case where the elevation and span change within a small range, and is not applicable to the construction project where the span and height of the outer shell dome of the Hualong One nuclear power plant change greatly compared to the inner dome. In addition, in the nuclear power construction industry, there is no targeted solution for how to achieve the shape switching of the frame first used for auxiliary steel dome assembly. The present invention fills the gap in the steel structure installation technology of the assembly frame used for the steel outer dome in the nuclear power construction industry in the shape switching, and provides a practical, efficient, safe and convenient large-span dome frame shape switching construction method, so as to achieve the shape switching of the dome frame, so that it can meet the assembly of steel domes with different spans and elevations within a certain range, and also to achieve the assembly construction of the outer dome of the Hualong One nuclear power plant. In the specific scheme, the shape change installation construction of the lower triangle, the string beam 5 and the central inner tube includes the following operations: S1, data confirmation, determination of the use requirements of the frame; S2, measurement and laying out, positioning the span radius and elevation of the frame; S3, shape switching construction of the dome assembly frame. In the present invention, the central inner tube is constructed from top to bottom, the lower triangle is constructed in a smooth manner, and the string beam 5 is constructed in a segment-by-segment adjustment manner. The requirements for the use of the cradle as determined in S1 include the requirements for relatively large spans / small elevations and small spans / large elevations. Therefore, the construction method for switching the dome cradle shape shown in the present invention can adjust the large and small spans through reverse engineering, and adjust the shape of the cradle according to the engineering requirements, which has high engineering adaptability.
[0076] Furthermore, the use requirements of the tire frame include engineering use requirements of large span / small elevation, and engineering use requirements of small span / large elevation.
[0077] As a method of measuring and locating the span radius and elevation after the tire frame shape is switched, and facilitating the movement and positioning of the lower triangle, the step S2 includes the following specific steps:
[0078] Position the elevation of the upper triangle of the inner tube truss ring beam at the center of the tire frame, and the overall layout radius of the lower triangle of the tire frame;
[0079] After the lower triangle is positioned at the radius of the overall layout, the lower triangle pier is circled in advance according to the newly positioned radius to mark the position of the new lower triangle group 1; the lower triangle includes a first diagonal brace rod 8 and a second diagonal brace rod 9, the lower end of the first diagonal brace rod 8 is provided with a pier, the lower end of the second diagonal brace rod 9 is connected to the ground through a ground anchor, and the upper end of the first diagonal brace rod 8 is used to connect the upper end of the second diagonal brace rod 9; a slide groove is reserved at the bottom of the pier;
[0080] The step of marking the position of the new lower triangle group 1 also includes marking the positions of several new piers in the circumferential direction. When marking the positions of the new piers of the lower triangle, the guide rail 3 is laid out at the same time; the guide rail 3 is located between the new lower triangle group 1 and the original lower triangle group 2, and is laid out along the radial direction of the tire frame. The guide rail 3 is used to pass through the slide groove at the bottom of the pier, and the guide rail 3 and the slide groove are adapted and slidably connected.
[0081] In order to ensure the stability of the assembly and disassembly of the beam string 5, the step S3-2 further includes the following specific steps:
[0082] When the step S3-1 operation is performed on a certain beam string 5, the corresponding beam string 5 at the radially symmetrical position thereof is simultaneously performed with the step S3-1 operation, and the step S3-1 operation is completed in turn in a bidirectional counterclockwise or clockwise direction, thereby completing the lowering of the upper ends of all the remaining beam string 5.
[0083] In order to sequentially complete the disassembly and assembly and elevation adjustment of the central inner tube, the central inner tube includes an inner tube and a truss ring beam, and the truss ring beam includes an outer ring beam 10 and an inner ring beam 11;
[0084] The step S3-3 also includes the following specific steps:
[0085] 3-a: Release the connection between the inner ring beam 11 and the outer ring beam 10 in the truss ring beam, and lift the inner ring beam 11 to the temporary storage area;
[0086] 3-b: Release the connection between the outer ring beam 10 and the inner tube, and lift the outer ring beam 10 to the temporary storage area;
[0087] 3-c: After the elevation of the cylindrical frame of the inner tube is adjusted, the outer ring beam 10 is lifted and mounted on the inner tube;
[0088] 3-d: After the outer ring beam 10 forms a ring structure, the inner ring beam 11 and the outer ring beam 10 are hoisted to form an integral structure, and the elevation of the center inner tube is remeasured at the same time.
[0089] To ensure the stability of the assembly and disassembly of the beam string 5, when a certain beam string 5 is operated in step S3-4, the corresponding beam string 5 at its radially symmetrical position is operated in step S3-4 at the same time, and the step S3-4 is repeated in a bidirectional counterclockwise or clockwise direction until all the beam string 5 are adjusted section by section.
[0090] In order to facilitate the movement of all lower triangles from the original lower triangle group 2 to the new triangle group, step S3-5 further includes the following specific steps:
[0091] 5-a: Release the connection between the second diagonal brace rod 9 in the lower triangle and the ground anchor, and release the connection between the connecting rod 15 and the shear brace 14 between the adjacent lower triangles;
[0092] 5-b: Connect the bottom support pier of the first diagonal brace 8 to the guide rail 3 through the reserved slide groove, and connect the second diagonal brace 9 to the corresponding guide rail 3, and connect them to the guide rail 3 through the slide rail device, so as to push the overall lower triangular upper guide rail 3;
[0093] 5-c: Push the lower triangle to move along the guide rail 3 to the marked position;
[0094] 5-d: Repeat the above steps 5-a→5-b→5-c in a clockwise or counterclockwise direction until the entire lower triangle is pushed to the marked position;
[0095] 5-e: Pull out the guide rail 3, release the connection between the second diagonal brace 9 and the slide rail device, reconnect the second diagonal brace 9 to the ground through a ground anchor, and connect the adjacent lower triangular connecting rod 15 and the shear brace 14;
[0096] 5-f: Repeat the above step 5-e in a clockwise or counterclockwise direction to connect the entire circle of lower triangles into a whole.
[0097] As a specific structural form of a slide rail device, the guide rail 3 is an I-shaped guide rail, the lower flange of the I-shaped guide rail is connected to the ground, and the upper flange of the I-shaped guide rail is slidably connected to the slide rail device;
[0098] The slide rail device includes a sliding plate 13 slidably clamped on both sides of the upper flange, the upper ends of the two sliding plates 13 are extended upward, and a clamping gap is left between the two extended parts, and the lower end of the second diagonal brace rod 9 is inserted into the clamping gap and respectively connected with the two extended parts by bolts 12. The cross section of the sliding plate 13 is similar to a "J" shape, and this shape setting can facilitate the adaptation of the inclination angle of the second diagonal brace rod 9 when connecting the second diagonal brace rod 9.
[0099] In order to avoid occupying too large a construction site and to achieve rapid return of the beam string 5, the step S-6 further includes the following specific steps:
[0100] 6-a: A winch 16 is arranged outside the lower triangle, and the winch 16 is connected by a steel wire rope 17. The middle steel wire rope 17 passes through the top connection point of the lower triangle, and the end of the steel wire rope 17 is connected to the lower connection point of the tension beam 5;
[0101] 6-b: Start the winch 16, drive the wire rope 17 to pull the lower connection point of the beam string 5 to make a circular motion with the upper connection point of the beam string 5 as the center to the top connection point of the lower triangle, and connect the beam string 5 with the lower triangle;
[0102] 6-c: synchronously, the beam string 5 at its radially symmetrical position simultaneously performs step 6-b;
[0103] 6-d: The remaining beam string 5 are installed symmetrically, and finally the adjacent annular members and shear braces 14 of the beam string 5 are connected.
[0104] To ensure overall stability, in step S-6, the eight cross-orthogonal beam string beams 5 are first symmetrically reset, then the shear braces 14 between the eight beam string beams 5 are connected, and finally the other beam string beams 5 are reset in turn in a bidirectional clockwise or counterclockwise direction.
[0105] Embodiment 2:
[0106] Based on Example 1, this Example 2 provides a specific implementation method for switching from the inner dome assembly cradle of the Hualong One nuclear power plant to the outer dome assembly cradle.
[0107] like Figure 1-Figure 7 As shown, this embodiment first introduces a high-altitude work platform vehicle into the interior of the dome frame, and uses a total station to locate and mark the elevation of the center inner cylinder of the frame and the lower triangle arrangement radius. When the dome assembly frame is switched, the string beam 5 is first laid flat on the inner cylinder bracket 6 in a symmetrical unloading manner through the car crane 7, and then the center inner cylinder is lowered from top to bottom. After the elevation of the center inner cylinder is adjusted to the specified position, the span of the string beam 5 is adjusted. During this period, the lower triangle is adjusted by laying the guide rail 3 and the slide rail device. After completion, the winch 16 can be used to return the string beam 5 to its original position.
[0108] The following specific implementation tasks are included:
[0109] S1. Confirm the data and determine the requirements for the tire frame;
[0110] In this embodiment, the central inner tube is constructed from top to bottom, the lower triangle is constructed in a smooth manner, and the string beam 5 is constructed in a segment-by-segment adjustment manner. Similarly, the construction method for switching the dome frame shape shown in the present invention can adjust the large and small spans through reverse engineering, and adjust the shape of the frame according to engineering requirements, which has high engineering adaptability.
[0111] In this embodiment, guide rails 3 are arranged radially on each frame to ensure that each frame moves to a specified position, making it more convenient to control the overall span of the tire frame.
[0112] In this embodiment, the tire frame usage requirements determined in S1 include engineering usage requirements of relatively large span / small elevation and relatively small span / large elevation.
[0113] S2. Measure and lay out, locate the span radius and elevation of the tire frame;
[0114] In the embodiment of the construction method of the present invention, the measurement and layout described in S2 uses a total station to locate the elevation at which the upper triangle of the ring beam of the inner tube truss of the tire frame center should be lowered, and locates the overall layout radius of the lower triangle of the tire frame. After the positioning of the layout radius of the lower triangle is completed, the lower triangle pier is circled in advance according to the newly located radius to mark the position of the new lower triangle group 1.
[0115] In this embodiment, when marking the new lower triangular pier, the I-beam guide rail is laid out at the same time, and the laying direction is radial.
[0116] In this embodiment, a slide groove through which an I-shaped guide rail passes is provided at the geometric center of the bottom of the pier below the first diagonal support rod 8 of the lower triangular tire frame.
[0117] In this embodiment, the newly marked lower triangular pier and the arranged I-beam guide rail, wherein the radial arrangement trajectory of the center position of each pier mark and the center position of the guide rail are in the same radial straight line as the original lower triangular pier.
[0118] S3. Perform shape switching construction on the dome assembly frame.
[0119] In the embodiment of the construction method of the present invention, the method of implementing the form switching construction of the dome assembly frame in step S3 includes the following steps:
[0120] S3-1. After the connection point between the upper part of the beam string 5 and the upper triangle is released from the constraint, the beam string 5 is lifted on the periphery of the tire frame by a truck crane 7, so that the beam string 5 moves in a circle with the connection point between the lower part and the lower triangle as the center, until the released connection point of the upper part of the beam string 5 is assembled with the connection point of the bracket 6 of the central inner tube, and a temporary bolt connection is performed to realize the flat lying of the beam string 5;
[0121] S3-2. When a certain string beam 5 is operated in step S3-1, the corresponding string beam 5 at its radially symmetrical position is operated in step S3-1 at the same time, and the step S3-1 is completed in a bidirectional counterclockwise or clockwise direction in sequence;
[0122] S3-3. Adjust the elevation of the central inner tube from top to bottom, that is, adjust the elevation of the cylindrical frame of the inner tube step by step, and monitor whether the elevation of the upper triangle reaches the specified elevation to ensure that the connection point with the string beam 5 is in the same section.
[0123] In the embodiment of the construction method of the present invention, before performing step S3-1, the connection between the adjacent annular members and the shear brace 14 of the beam string 5 is released.
[0124] In this embodiment, the central inner tube described in S3-3 is divided into an inner tube and a truss ring beam, and the truss ring beam is divided into an outer ring beam 10 and an inner ring beam 11. The cylindrical frame is adjusted step by step in terms of elevation, and the following steps are performed:
[0125] 3-a release truss ring beam inner ring beam 11 and outer ring beam 10 of the bolt connection, synchronous use of car crane 7 lifting the inner ring beam 11 to the temporary storage area;
[0126] 3-b. Release the connecting rod and bolt connection between the outer ring beam 10 and the inner tube, and simultaneously use the truck crane 7 to lift the outer ring beam 10 to the temporary storage area;
[0127] 3-c. After the elevation of the inner cylindrical frame is adjusted, first hoist the outer ring beam 10 to the inner cylinder using sleeve perforated bolts;
[0128] 3-d. After the outer ring beam 10 forms an annular structure, the inner ring beam 11 is hoisted to form an integral structure with the outer ring beam 10, and the elevation of the center inner tube is remeasured at the same time.
[0129] S3-4. Adjust the span of the horizontally lying beam string 5.
[0130] In the embodiment of the construction method of the present invention, the method of adjusting the span of the beam string 5 in step S3-4 comprises the following steps:
[0131] 4-a. Using a truck crane 7 to lift the beam string 5 outside the tire frame, while releasing the connection between the ends of the beam string 5 and the bracket 6 and the lower triangle;
[0132] 4-b. After the beam string 5 is disconnected, the upper part of the beam string 5 is connected to the triangle on the center inner tube and the bolts are initially tightened;
[0133] 4-c. The other end of the beam string 5 is placed on the scaffolding below to prevent the beam string 5 from shaking. At the same time, the span of the beam string 5 is adjusted section by section on the scaffolding platform.
[0134] In this embodiment, when step S3-4 is performed on a certain beam string 5, the corresponding beam string 5 at a radially symmetrical position thereof is simultaneously performed on step S3-4, and step S3-4 is repeated in a bidirectional counterclockwise or clockwise direction.
[0135] S3-5. Smooth the entire circle of the second type lower triangle to the position of the new lower triangle group 1 marked in step S2.
[0136] In an embodiment of the construction method of the present invention, the method of implementing the lower triangle smoothing to the marked position in step S3-5 comprises the following steps:
[0137] 5-a. Release the second diagonal brace rod 9 from the lower triangle and connect it to the ground anchor, and release the connecting rod 15 between the adjacent lower triangles and the shear brace 14;
[0138] 5-b push the overall lower triangle upper rail 3, first of all, the first diagonal strut 8 below the pier reserved for the chute, and then the second diagonal strut 9 connected to the rail device by bolts 12 access rail 3;
[0139] 5-c. Push the lower triangle in the direction of guide rail 3 to the marked position;
[0140] 5-d. Repeat the above steps 5-a→5-b→5-c in a clockwise or counterclockwise direction to push the lower triangle to the marked position;
[0141] 5-e pull out the rail 3, release the rail device and the second diagonal support rod 9 connection, the second diagonal support rod 9 and the ground anchor connection, the adjacent lower triangular link 15 and the shear support 14 are connected;
[0142] 5-f. Repeat the above step 5-e in a clockwise or counterclockwise direction to connect the entire circle of lower triangles into a whole.
[0143] In this embodiment, the above-mentioned slide rail device is composed of bolts 12 and a "J"-shaped plate. When installed, it is symmetrically installed on both sides below the second diagonal support rod 9 and wraps the I-shaped guide rail 3 at the same time.
[0144] In this embodiment, the connecting rods 15 connecting the adjacent lower triangles are replaced with connecting rods 15 suitable for the adjacent distance length.
[0145] S3-6. Return the beam string 5 to its original position, connecting the central inner tube and the lower triangle as a whole.
[0146] In the embodiment of the construction method of the present invention, the lower cam is provided with a winch 16 mechanical device, and the method for returning the string beam 5 to the original position in step S3-6 is performed by the following steps:
[0147] 6-a. The winch 16 arranged on the outside of the lower triangle is connected to the winch 16 by a wire rope 17, the middle wire rope 17 passes through the top connection point of the lower triangle, and the end of the wire rope 17 is connected to the lower connection point of the string beam 5;
[0148] 6-b. Start the winch 16, drive the wire rope 17 to pull the lower connection point of the beam string 5 to the upper connection point of the beam string 5 as the center of the circle to make a circular motion to the top connection point of the lower triangle, and connect the beam string 5 with the lower triangle;
[0149] 6-c synchronously, the beam string 5 in its radially symmetrical position simultaneously performs step 6-b;
[0150] 6-d. The remaining beam string 5 are installed symmetrically, and finally the adjacent annular members and shear braces 14 of the beam string 5 are connected.
[0151] In the embodiment of the construction method of the present invention, in the operation of step S3-6, the eight beam string beams 5 of the 4-5 axis, the 12-13 axis, the 20-21 axis, and the 28-29 axis are preferentially symmetrically reset, and then the shear braces 14 between the eight beam string beams 5 are connected to ensure the overall stability, and then the other beam string beams 5 are reset in turn in a bidirectional clockwise or counterclockwise direction.
[0152] The specific implementation methods described above further illustrate the objectives, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above description is only a specific implementation method of the present invention and is not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.
Claims
1. A large-span dome frame form switching construction method, characterized in that: The following steps are involved: S1: Data confirmation, determine the tire frame usage requirements; S2: measuring and laying out, positioning the span radius and elevation of the tire frame, and setting guide rails (3) at each lower triangle position; S3: Perform shape switching construction on the dome assembly frame; The step S3 also includes the following specific steps: S3-1: releasing the restraint on the upper end of the beam string (5), and lifting the beam string (5), so that the upper end of the beam string (5) rotates around its lower end and is lowered onto the bracket (6) of the central inner tube; S3-2: completing the lowering of the upper ends of the remaining beam string (5); S3-3: Adjust the height of the center inner tube to reach the specified elevation; S3-4: releasing the constraints on both ends of the beam string (5), and hoisting the beam string (5), so that the upper end of the beam string (5) is connected to the upper triangle of the central inner tube, and the lower end is placed on a temporary scaffold (18); then adjusting the span of the beam string (5) section by section; S3-5: After all the beam string (5) are adjusted section by section, the entire circle of lower triangles is connected to the guide rail (3) and moved to the positioned tire frame span radius position, and then the guide rail (3) is removed; S3-6: Connect the lower end of the beam string (5) through the traction device, and drive the lower end of the beam string (5) to rotate around its upper end, so that the lower end of the beam string (5) is connected to the lower triangle, until the construction of all the remaining beam strings (5) is completed.
2. A large-span dome frame form switching construction method according to claim 1, characterized in that: The requirements for the use of the tire frame include the requirements for projects with large spans and small elevations, and projects with small spans and large elevations.
3. A large-span dome frame form switching construction method according to claim 1, characterized in that: The step S2 comprises the following specific steps: Position the elevation of the upper triangle of the inner tube truss ring beam at the center of the tire frame, and the overall layout radius of the lower triangle of the tire frame; After the lower triangle is laid out and the radius positioning is completed, the lower triangle pier is circled in advance according to the newly positioned radius to mark the position of the new lower triangle group (1); the lower triangle includes a first diagonal support rod (8) and a second diagonal support rod (9), the lower end of the first diagonal support rod (8) is provided with a pier, the lower end of the second diagonal support rod (9) is connected to the ground through a ground anchor, and the upper end of the first diagonal support rod (8) is used to connect the upper end of the second diagonal support rod (9); a slide groove is reserved at the bottom of the pier; The step of marking the position of the new lower triangle group (1) also includes marking the positions of a plurality of new piers in the circumferential direction. When marking the positions of the new piers of the lower triangle, the guide rail (3) is laid out at the same time; the guide rail (3) is located between the new lower triangle group (1) and the original lower triangle group (2), and is laid out along the radial direction of the tire frame. The guide rail (3) is used to pass through the slide groove at the bottom of the pier, and the guide rail (3) and the slide groove are adapted and slidably connected.
4. A large-span dome frame form switching construction method according to claim 1, characterized in that: The step S3-2 also includes the following specific steps: When the step S3-1 operation is performed on a certain beam string (5), the corresponding beam string (5) at the radially symmetrical position thereof is simultaneously subjected to the step S3-1 operation, and the step S3-1 operation is sequentially completed in a bidirectional counterclockwise or clockwise direction, thereby completing the lowering of the upper ends of all the remaining beam string (5).
5. A large-span dome frame form switching construction method according to claim 1, characterized in that: The central inner tube comprises an inner tube and a truss ring beam, and the truss ring beam comprises an outer ring beam (10) and an inner ring beam (11); The step S3-3 also includes the following specific steps: 3-a: releasing the connection between the inner ring beam (11) and the outer ring beam (10) in the truss ring beam, and lifting the inner ring beam (11) to a temporary storage area; 3-b: releasing the connection between the outer ring beam (10) and the inner tube, and lifting the outer ring beam (10) to a temporary storage area; 3-c: After the elevation of the cylindrical frame of the inner tube is adjusted, the outer ring beam (10) is lifted and mounted on the inner tube; 3-d: After the outer ring beam (10) forms a ring structure, the inner ring beam (11) and the outer ring beam (10) are hoisted to form an integral structure, and at the same time, the elevation of the central inner tube is re-measured.
6. A large-span dome frame form switching construction method according to claim 1, characterized in that: When a certain beam string (5) is subjected to step S3-4, the corresponding beam string (5) at a radially symmetrical position thereof is subjected to step S3-4 at the same time, and step S3-4 is repeated in a bidirectional counterclockwise or clockwise direction until all beam string (5) are adjusted section by section.
7. A large-span dome frame form switching construction method according to claim 3, characterized in that: The step S3-5 also includes the following specific steps: 5-a: Release the connection between the second diagonal brace (9) in the lower triangle and the ground anchor, and release the connection between the connecting rod (15) and the shear brace (14) between the adjacent lower triangles; 5-b: Connect the bottom support pier of the first diagonal support rod (8) to the guide rail (3) through the reserved sliding groove, and connect the second diagonal support rod (9) to the corresponding guide rail (3), and connect the guide rail (3) through the sliding rail device, so as to push the overall lower triangular upper guide rail (3); 5-c: Push the lower triangle to move along the guide rail (3) to the marked position; 5-d: Repeat the above steps 5-a→5-b→5-c in a clockwise or counterclockwise direction until the entire lower triangle is pushed to the marked position; 5-e: Pull out the guide rail (3), release the connection between the second diagonal support rod (9) and the slide rail device, reconnect the second diagonal support rod (9) to the ground by ground anchoring, and connect the adjacent lower triangular connecting rod (15) and the shear support (14); 5-f: Repeat the above step 5-e in a clockwise or counterclockwise direction to connect the entire circle of lower triangles into a whole.
8. A large-span dome frame form switching construction method according to claim 7, characterized in that: The guide rail (3) is an I-shaped guide rail, the lower flange of the I-shaped guide rail is connected to the ground, and the upper flange of the I-shaped guide rail (3) is slidably connected to a slide rail device; The slide rail device comprises a sliding plate (13) slidably clamped on both sides of the upper flange, the upper ends of the two sliding plates (13) are extended upward, and a clamping gap is left between the two extended parts, and the lower end of the second diagonal support rod (9) is inserted into the clamping gap and is respectively connected to the two extended parts by bolts (12).
9. A large-span dome frame form switching construction method according to claim 1, characterized in that: The step S-6 also includes the following specific steps: 6-a: A winch (16) is arranged outside the lower triangle, and the winch (16) is connected via a steel wire rope (17). The middle steel wire rope (17) passes through the top connection point of the lower triangle, and the end of the steel wire rope (17) is connected to the lower connection point of the string beam (5); 6-b: Start the winch (16), drive the wire rope (17) to pull the lower connection point of the beam string (5) to make a circular motion with the upper connection point of the beam string (5) as the center to the top connection point of the lower triangle, and connect the beam string (5) with the lower triangle; 6-c: synchronously, the beam string (5) at its radially symmetrical position simultaneously performs the operation of step 6-b; 6-d: The remaining beam string (5) are installed symmetrically, and finally the adjacent annular members and shear braces 14 of the beam string (5) are connected.
10. A large-span dome frame form switching construction method according to claim 9, characterized in that: In the step S-6, the eight cross-orthogonal beam string beams (5) are first symmetrically reset, then the shear braces 14 between the eight beam string beams (5) are connected, and finally the other beam string beams (5) are reset in turn in a bidirectional clockwise or counterclockwise direction.