High-voltage line lower station accessory structure and shallow soil covering tunnel side crossing interactive construction method
By using shield assembly and debugging, enclosing pile structure and glass fiber piles in the interactive construction of the high-voltage offline station attachment structure and shallow-covered soil tunnel, the ultra-close distance between the high-voltage offline station attachment structure and shallow-covered soil large-diameter tunnel is solved. The difficulty and safety risks of side-pass construction achieve controllability and construction safety of ground settlement, shorten the construction period and reduce costs.
Patent Information
- Application Number
- CN202411213392.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-30
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2044-08-30
AI Technical Summary
In the construction of the 220KV high-voltage offline station attachment structure and the ultra-close-diameter tunnel with shallow-covered soil, there are problems such as high construction difficulty, high safety risks and tight construction periods, especially in the case of poor soil burial depth and soil quality. Technology is difficult to effectively control ground settlement and reduce the impact on high-voltage lines.
Adopting the interactive construction method of the auxiliary structure of the high-voltage offline station and the side-passing of shallow-covered soil tunnel, through shield assembly and debugging, enclosing pile structure, glass fiber piles, embedded steel plates and steel support, shield pipe sheets are formed at one time and multiple compensation notes Technical means such as slurry and side wall pressure box stress monitoring to control ground settlement and ensure construction safety, and avoid high-voltage lines relocation or renovation.
The controllability and construction safety of ground settlement at ultra-close distance are achieved, the construction period is reduced, the overall safety and stability of the tunnel structure is improved, the impact on high-voltage lines is avoided, and the project cost is reduced.
Smart Images

Figure CN119021702A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of tunnel side-penetration construction methods, and in particular to a method for interactive side-penetration construction of an auxiliary structure of a station under a high-voltage line and a shallow covered tunnel. Background Art
[0002] As urban rail transit networks become more and more developed, more and more shield tunnels are being used to cross stations. When constructing subway station ancillary projects under overhead high-voltage lines, there are many residents, hospitals, and industrial plants near the high-voltage lines. The cost of relocation or tower upgrading is very high, and the approval process is very long. It is impossible to relocate or transform the high-voltage lines, so the construction method of the project itself needs to be changed in a targeted manner.
[0003] At present, there is a lot of experience and research on the construction of underground tunneling under existing stations, but there is little research on the construction of large-diameter shield tunneling at a very close distance (195mm) to the side of the existing station auxiliary structure. In particular, the requirements for the inclination measurement of the existing station auxiliary piles and the control of the shallow overburden ground settlement are so strict, which is rare in domestic subway construction. The construction difficulty and safety risks of this project are extremely high, and the construction period is relatively tight, so it is listed as an oversized dangerous project.
[0004] In actual construction scenarios, when the subway tunnel is close to the existing station auxiliary level and the covering soil is only 9.7m deep, the soil is the station excavation backfill soil, and the soil quality is extremely poor. If the tunnel is constructed by dark excavation, the construction process is cumbersome, the construction requirements are high, and the risk is relatively high. The slightest carelessness may cause deformation of the initial support and unfavorable control of ground settlement. At the same time, in terms of construction period, due to the overlap of construction periods, the conventional plan is to carry out shield tunneling after the entrance and exit construction is completed and the backfill is completed, and the construction period is tight. Therefore, the present invention has developed a method for interactive construction of station auxiliary structures under high-voltage lines and shallow covering tunnels to solve the problems existing in the prior art. Summary of the invention
[0005] The purpose of the present invention is to provide a method for the interactive side-through construction of station auxiliary structures under high-voltage lines and shallow covered tunnels, so as to solve the problem of limited ultra-close side-through construction between station auxiliary structures under 220KV high-voltage lines and shallow covered large-diameter tunnels in the prior art.
[0006] The technical solution of the present invention is: a method for interactive construction of a station auxiliary structure under a high-voltage line and a shallow covered tunnel sideways, comprising:
[0007] a. Determine the construction site and configure the construction equipment; at the construction site, mainly carry out the entrance and exit construction and the tunnel side crossing construction; then simultaneously determine the horizontal clearance between the entrance and exit contour line and the tunnel contour line;
[0008] b. Determine the construction period, where the entrance and exit are divided into two phases of construction, the shield machine assembly and commissioning for tunnel side-crossing construction and the first phase of the entrance and exit structure are cross-constructed; after the first phase of the entrance and exit structure is capped, the shield machine starts to penetrate the tunnel side structure, and then the second phase of the entrance and exit construction is carried out;
[0009] c. Construction of the first phase of the entrance and exit structure: a retaining pile structure is set up at the entrance and exit construction site. A high-voltage line is crossed above the local area surrounded by the retaining pile structure. Then the main foundation pit is excavated until the structure is capped. During the construction of the retaining pile structure, glass fiber piles are constructed within the upper and lower rated ranges of the shield center side-passing area. During the process, the shield machine is assembled and debugged, and the shield starting section is reinforced simultaneously;
[0010] d. The shield machine begins to excavate and pass through the entrance and exit sideways. During the excavation process, one-time formed shield segments are used and multiple compensatory grouting is carried out.
[0011] Preferably, in step a, the construction equipment mainly includes a crawler crane, a shield machine, a grouting machine, and a slurry mixing machine; insulation measures are added to the crawler crane before assembly, and grounding devices are added to the crane and the roadbed.
[0012] Preferably, in step c, the shield starting section is reinforced, mainly including using pipe shed and ground sleeve valve pipe grouting reinforcement to cover the vault range;
[0013] The pipe shed is arranged within the range of 110°-130° of the arch, the opening of the pipe shed is arranged at the position of 240-265mm of the excavation contour line of the shield arch, and cement slurry is used for grouting;
[0014] The reinforcement range of the ground sleeve valve pipe is 4.05-4.35m outside the shield contour line, 14.5-15.6m longitudinally, and the depth is 0.9-1.2m below the tunnel arch bottom.
[0015] Preferably, in step c, the main foundation pit formed by the entrance and exit, including at least the side wall on the side biased towards the shield side penetration, is supported by embedded steel plates and steel supports.
[0016] Preferably, in step c, during the construction of the entrance and exit, a side wall pressure box stress monitoring instrument is synchronously embedded to measure the inclination of the retaining pile structure, the supporting axial force and the side wall stress monitoring within the side penetration range during the tunnel side penetration construction.
[0017] Preferably, in step c, before the construction of the first phase structure of the entrance and exit, the overhead line height limit frame is constructed to define the minimum vertical distance and minimum horizontal distance between the high-voltage line and the building.
[0018] Preferably, in step d, the tunneling speed of the shield machine is controlled at 30-45 mm / min, the horizontal posture is controlled at ±20°, and the single-ring deviation correction is controlled at ±5 mm.
[0019] Preferably, during the tunneling process of the shield machine, the gap between the shield segment and the surrounding rock is filled and compacted by controlling the grouting amount and grouting pressure;
[0020] The grouting volume shall not be less than 7.5m 3 During the grouting process, ensure that the pipelines are grouted at the same time, the upper grouting pressure is not greater than 0.3Mpa, and the lower grouting pressure is not greater than 0.34Mpa.
[0021] Preferably, the soil pressure is controlled at about 0.8 bar during excavation, and the pressure is maintained at about 1.0 bar when stopped;
[0022] The thrust of the shield machine is controlled at 11000-18000KN, the torque is controlled at 1300KN·m-2000KN·m, and the cutter head speed is controlled at 1.9-2.0rpm.
[0023] Preferably, the soil improvement is strengthened during the excavation process, and the amount of foaming agent per ring is 3.8-4.2m 3 , add mud 22-28m 3 The slag discharge volume is controlled at 7-8 buckets, and the slag discharge volume of a single ring is not more than 145m 3 , weight not more than 255T.
[0024] Compared with the prior art, the advantages of the present invention are:
[0025] (1) When the horizontal clearance between the entrance and exit contours and the tunnel contours is close, shield construction technology is used to achieve controllable ground settlement through reinforcement of the shield starting section, one-time forming of the shield segments, and multiple compensatory grouting.
[0026] (2) Before assembling the crawler crane, insulation measures are added and grounding devices are added to the crane and roadbed to ensure that risks are controllable and that a safe distance is maintained between the crawler crane boom and the high-voltage transmission line. At the same time, there is no need to relocate or modify the high-voltage line, and there is no impact on nearby buildings.
[0027] (3) By constructing fiberglass piles, embedded steel plates and steel supports, reinforcing the starting section of the shield machine, and performing alternating construction, the overall safety and stability of the tunnel and structure were enhanced, with a short construction period and high safety.
[0028] (4) Pre-buried side wall pressure box stress monitoring instrument is used to measure the inclination of the retaining pile structure, support axial force and side wall stress within the side penetration range during tunnel side penetration construction, so as to facilitate timely adjustment of excavation parameters and ensure construction efficiency.
[0029] (5) By rationally controlling the tunneling parameters and grouting parameters of the shield machine, the disturbance to the entrance and exit structure when the shield machine passes through the entrance and exit sideways can be reduced, and over-excavation and disturbance of the soil can be avoided; by strengthening the improvement of the slag, the continuity and plasticity of the slag can be maintained. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] The present invention will be further described below in conjunction with the accompanying drawings and embodiments:
[0031] Figure 1 It is a process flow chart of the interactive construction method of the auxiliary structure of the station under the high-voltage line and the side-through of the shallow covered tunnel according to the present invention;
[0032] Figure 2 It is a schematic cross-sectional diagram of the entrance and exit and the tunnel excavation surface of the present invention;
[0033] Figure 3 It is a layout diagram of stress monitoring points at the entrance and exit of the present invention and a distribution diagram of shield segments.
[0034] Among them: 1. Entrance and exit;
[0035] 11. Entrance and exit contour lines, 12. Retaining pile structure, 13. Fiberglass piles, 14. Stress monitoring points;
[0036] 2. Tunnel;
[0037] 21. Tunnel outline, 22. Shield segments. DETAILED DESCRIPTION
[0038] The present invention is further described in detail below in conjunction with specific embodiments:
[0039] For ease of understanding, the application scenario of this application is first explained. A 220KV high-voltage line crosses partially above the B2 port (entrance and exit) of a certain station. The right line of the shield tunnel section in the middle ventilation shaft starts from the station's B2 port at an ultra-close distance. The horizontal clearance between the shield tunnel excavation contour line and the B2 port retaining structure is only 195mm. Considering the construction deviation, the construction risk is high. Therefore, this application has formed a set of ultra-close-distance interactive construction technology for side-crossing between the station's auxiliary structure under the high-voltage line and the shallow-covered large-diameter tunnel.
[0040] like Figure 1 , Figure 2 As shown, a method for interactive construction of a station auxiliary structure under a high-voltage line and a shallow covered tunnel sideways includes the following:
[0041] (1) Determine the construction site and surrounding scenes;
[0042] At the construction site, the construction of the entrance and exit 1 and the side-through construction of the tunnel 2 are mainly carried out; then the horizontal clearance between the entrance and exit contour line 11 and the tunnel contour line 21 is simultaneously determined; this application can be applied to the ultra-close horizontal clearance, which is generally set to a distance less than 500mm; Figure 2 As shown, taking a certain site as an actual application example, the horizontal clearance (distance s) between the entrance and exit contour line 11 and the tunnel contour line 21 is 195 mm, the covering soil depth is shallow, only 9.7 m, and there is a high-voltage line crossing over part of the construction site.
[0043] (2) Construction preparation and configuration of construction equipment;
[0044] The construction equipment mainly includes crawler crane (25t), shield machine, grouting machine (Gz5), slurry mixer (200L); it also includes anchor spraying equipment, backup diesel generator, etc.
[0045] As the construction site is under high-voltage lines, insulation measures are added before assembling the crawler crane, and grounding devices are added to the crane and roadbed to ensure that risks are controllable and a safe distance is maintained between the crawler crane boom and the high-voltage transmission lines. At the same time, there is no need to relocate or modify the high-voltage lines, and there is no impact on nearby buildings.
[0046] At the same time, relevant construction materials are prepared, mainly including steel plates (10mm), steel supports (φ609, wall thickness 16mm), cement (PO42.5), load-bearing ropes, warning materials (light strips, colorful flags, warning signs, etc.), insulating nets, etc.
[0047] (3) Figure 1 As shown, the construction period and process are determined, wherein the entrance and exit are divided into two phases of construction, the assembly and commissioning of the shield machine used for tunnel side penetration construction and the cross-construction of the first phase structure of the entrance and exit; after the first phase structure of the entrance and exit is capped, the shield machine starts the tunnel side penetration structure, and then the second phase construction of the entrance and exit is carried out.
[0048] (4) Overhead line height limit construction;
[0049] According to Article 4.1.22 of the "Technical Regulations for Safety in the Use of Construction Machinery", the minimum vertical safety distance of 220KV high-voltage lines is 6m, and the minimum horizontal safety distance is 6m. According to Article 13.0.4 of the "110KV~750KV Overhead Transmission Line Design Specifications", the minimum vertical distance of 110KV conductors from buildings should be 5m, and the minimum horizontal distance should be 4m.
[0050] The construction process of overhead line height limit frame is mainly as follows:
[0051] a. Measure and lay out to determine the buried position of the pole;
[0052] b. The buried depth of the pole is 3m, and the slope is excavated to the bottom elevation of the foundation. The slope around is 1:1, and a 15cm C30 concrete cushion is applied;
[0053] c. Fix the steel strand and red light strip on the top of the pole, and set colored flags every 50cm on the steel strand. The installation height must be guaranteed to be more than 0.3m away from the communication line;
[0054] d. The pole body is buried using a 25t crawler crane in conjunction with manual installation. After the C30 concrete is poured, the guy rope is tightened to ensure the pole body is vertical before the crane hook is removed;
[0055] e. After the concrete strength reaches 100%, the guy rope can be removed and the steel strand can be tensioned.
[0056] (5) Construction of the first phase structure of entrance and exit 1. A retaining pile structure 12 is set up at the entrance and exit construction site. A high-voltage line crosses the local area surrounded by the retaining pile structure 12. The main foundation pit is then excavated until the structure is capped. During the construction of the retaining pile structure 12, glass fiber piles 13 are constructed within the upper and lower rated range of the shield center side penetration area. During the process, the shield machine is assembled and debugged, and the shield starting section is reinforced simultaneously.
[0057] Specifically, the main foundation pit formed by the entrance and exit 1 at least includes the side wall biased towards the side of the shield tunneling, which is supported by embedded steel plates and steel supports to further enhance the strength and stability of the entrance and exit structure when the shield tunneling is side-passing.
[0058] During the construction of entrance and exit 1, Figure 3 As shown, a synchronously embedded side wall pressure box stress monitoring instrument is installed at a stress monitoring point 14 and is used to measure the inclination, support axial force and side wall stress of the retaining pile structure 12 within the side penetration range during tunnel side penetration construction.
[0059] Regarding fiberglass piles 13, Figure 2 As shown in the figure, the fiberglass piles are arranged within the rated range of 1m above and below the side penetration area biased towards the center of the shield machine. That is to say, the fiberglass piles are arranged for a total of 2m, that is, the distance L shown in the figure. The fiberglass piles, as a reinforcing material, enhance the overall safety and stability of the entrance and exit structure and reduce the impact of subsequent side penetration of the shield machine on the entrance and exit structure.
[0060] The entrance and exit structures are constructed with early-strength concrete to ensure structural strength. Once the strength reaches 35MPa, the subsequent shield tunneling can be started.
[0061] The starting section of the shield tunnel was reinforced simultaneously with the first-phase structure of the entrance and exit, mainly including the use of pipe sheds and ground sleeve valve pipe grouting reinforcement for the soil covering the arch range; the pipe shed was arranged within the range of 110°-130° of the arch, the pipe shed opening was arranged at a position of 240-265mm on the excavation contour line of the shield arch, and cement slurry was used for grouting; the ground sleeve valve pipe reinforcement range was 4.05-4.35m outside the shield contour line, 14.5-15.6m longitudinally, and the depth was 0.9-1.2m below the tunnel arch bottom.
[0062] In the actual construction scenario, the pipe shed is arranged within 120° of the arch, the pipe shed opening is arranged at 250mm from the excavation contour line of the shield arch, and cement slurry is used for grouting; the ground sleeve valve pipe reinforcement range is 4.15m outside the shield contour line, 15m longitudinally, and 1m deep below the tunnel arch bottom. After the reinforcement is completed, core sampling is carried out for testing.
[0063] (6) The shield machine begins to excavate and pass through the entrance and exit sideways. During the excavation process, the shield segment 22 formed in one step is used, and multiple compensatory grouting is performed. At the same time, ground monitoring points are arranged.
[0064] Specifically, the shield machine uses an earth pressure balance shield machine with a cutterhead excavation surface of φ8610mm. Since there are many factors that affect the structure of the shield side-penetrating entrance and exit construction, mainly the influence of construction parameters such as soil bin pressure, advancement speed, total thrust, excavation volume, cutterhead speed, grouting volume and grouting pressure, the construction excavation parameters must be optimized.
[0065] First, the excavation surface is stabilized by controlling the amount of slag discharged, and the pressure in the soil bin is kept constant by adding air to maintain pressure, and its fluctuation is controlled as small as possible. The amount of excavation discharged should be strictly controlled during the process, and the amount of slag discharged should not exceed 145m 3 .
[0066] Second, strengthen the improvement of slag soil, adjust the proportion of foam stock solution from 2% to 2.5%, adjust the gas: mixed liquid ratio to 12:1, and adjust the foam injection rate to 50%-60%. During the excavation process, ensure that the foam pipeline is fully open, control the water addition in the soil bin according to the improvement of slag soil, pay special attention to the improvement effect of slag soil in the center area of the cutter head, and maintain the continuity and fluidity of the slag soil.
[0067] Third, control the excavation speed, and make the shield machine pass through the entrance and exit sideways to avoid large speed fluctuations, prevent problems such as increased soil bin pressure and incomplete grouting caused by excessive speed. Too slow excavation speed prolongs the disturbance time of the stratum, so the excavation speed is planned to be maintained at 30-45mm / min to ensure that the shield machine passes through the B2 entrance at an even speed and minimize the disturbance to the structure.
[0068] Fourth, strict linear control and attitude control should be carried out on shield tunneling. Attitude adjustment should not be too large or too frequent to reduce deviation correction. The horizontal attitude is planned to be excavated at around ±20°, and the single-loop deviation correction is controlled within the range of ±5mm to avoid over-excavation and disturbance of the soil.
[0069] Fifth, set a reasonable grouting volume and grouting pressure to ensure that the gap between the shield segment 22 and the surrounding rock can be filled and compacted in time; based on the protection of the entrance and exit structure and the prevention of ground subsidence, the grouting volume shall not be less than 7.5m 3 During the grouting process, ensure that the pipeline is grouted at the same time, the upper grouting pressure is not more than 0.3Mpa, and the lower grouting pressure is not more than 0.34Mpa. In the actual construction process, the grouting parameters are adjusted in time according to the data fed back by the stress monitoring points and the ground monitoring points. During shield construction, the synchronous grouting ratio is adjusted to: 300kg cement, 240kg fly ash, 370kg water, 80kg bentonite, 750kg sand, and the initial setting time is 6-8h.
[0070] Sixth, excavation parameter control;
[0071] Soil pressure control: Based on the geological conditions and burial depth, the soil pressure is controlled at around 0.8 bar, and the shutdown pressure is maintained at around 1.0 bar.
[0072] Thrust control: The thrust is controlled at 11000-18000KN, which is related to the excavation speed. The torque is controlled at 1300KN·m-2000KN·m to ensure the shield excavation at a uniform speed. In order to reduce the disturbance to the soil layer, the cutter head speed is controlled between 1.9-2.0rpm. During the process, strict attention is paid to the surface and structure monitoring data, and appropriate parameter adjustments are made according to the monitoring data.
[0073] h: Slag volume control: Strengthen the improvement of slag during excavation, and use 4m3 of foaming agent per ring 3 About, add mud 25m 3 The slag discharge volume is controlled at about 7.5 buckets to ensure uniform slag discharge. The slag discharge volume of a single ring is less than or equal to 145m 3 , weight ≤255T.
[0074] In summary, the main construction scenarios of this application include:
[0075] First, the horizontal clearance s between the entrance and exit contour line and the tunnel contour line 21 is 195 mm;
[0076] Second, the cover soil is shallow, only 9.7m deep;
[0077] Third, there are high-voltage lines crossing over part of the construction site.
[0078] For the above three extreme scenarios, this application adopts the following measures to overcome them:
[0079] First, interactive construction is carried out to avoid overlapping of construction periods, which may cause conflicts between the shield excavation contour and some retaining pile structures, and to avoid partial pile grinding during side penetration, so as to ensure construction safety and structural safety; at the same time, the excavation speed and posture of the shield machine are strictly controlled;
[0080] Second, the shield starting section is reinforced, the shield segments are formed in one step, and multiple compensation grouting is performed;
[0081] Third, the construction of overhead line height limit frames ensures construction safety. At the same time, insulation measures are added before assembling the crawler crane, and grounding devices are added to the crane and roadbed to ensure that risks are controllable and a safe distance is maintained between the crawler crane boom and the high-voltage transmission line.
[0082] The implementation of the above measures has further brought about the advantages of shortening the construction period and saving project costs. The main reason is that the interactive construction has greatly shortened the construction period, reduced the impact of tunnel construction on entrance and exit construction, effectively improved the quality and safety of the formed tunnel, and greatly saved the construction period and emergency rescue costs.
[0083] The above embodiments are only for illustrating the technical concept and features of the present invention, and their purpose is to enable people familiar with this technology to understand the content of the present invention and implement it accordingly, and they cannot be used to limit the scope of protection of the present invention. For those skilled in the art, it is obvious that the present invention is not limited to the details of the above exemplary embodiments, and the present invention can be implemented in other specific forms without departing from the spirit or basic features of the present invention. Therefore, no matter from which point of view, the embodiments should be regarded as exemplary and non-restrictive. The scope of the present invention is limited by the attached claims rather than the above description, and it is intended to include all changes within the meaning and scope of the equivalent elements of the claims in the present invention.
Claims
1. A method for the alternating construction of the auxiliary structure of a station under a high-voltage line and a shallow covered tunnel sideways. It is characterized in that include: a. Determine the construction site and configure the construction equipment; at the construction site, mainly carry out the entrance and exit construction and the tunnel side crossing construction; then simultaneously determine the horizontal clearance between the entrance and exit contour line and the tunnel contour line; b. Determine the construction period, where the entrance and exit are divided into two phases of construction, the shield machine assembly and commissioning for tunnel side-crossing construction and the first phase of the entrance and exit structure are cross-constructed; after the first phase of the entrance and exit structure is capped, the shield machine starts to penetrate the tunnel side structure, and then the second phase of the entrance and exit construction is carried out; c. Construction of the first phase of the entrance and exit structure: a retaining pile structure is set up at the entrance and exit construction site. A high-voltage line is crossed above the local area surrounded by the retaining pile structure. Then the main foundation pit is excavated until the structure is capped. During the construction of the retaining pile structure, glass fiber piles are constructed within the upper and lower rated ranges of the shield center side-passing area. During the process, the shield machine is assembled and debugged, and the shield starting section is reinforced simultaneously; d. The shield machine begins to excavate and pass through the entrance and exit sideways. During the excavation process, one-time formed shield segments are used and multiple compensatory grouting is carried out.
2. The method for alternately constructing the auxiliary structure of the station under the high-voltage line and the side-through of the shallow covered tunnel according to claim 1, Features: In step a, the construction equipment mainly includes a crawler crane, a shield machine, a grouting machine, and a slurry mixing machine; insulation measures are added to the crawler crane before assembly, and grounding devices are added to the crane and the roadbed.
3. The method for alternately constructing the auxiliary structure of the station under the high-voltage line and the side-through of the shallow covered tunnel according to claim 2, Features: In step c, the starting section of the shield is reinforced, mainly including using pipe sheds and ground sleeve valve pipe grouting to reinforce the soil covering the vault range; The pipe shed is arranged within the range of 110°-130° of the arch, the opening of the pipe shed is arranged at the position of 240-265mm of the excavation contour line of the shield arch, and cement slurry is used for grouting; The reinforcement range of the ground sleeve valve pipe is 4.05-4.35m outside the shield contour line, 14.5-15.6m longitudinally, and the depth is 0.9-1.2m below the tunnel arch bottom.
4. The method for alternately constructing the auxiliary structure of the station under the high-voltage line and the side-through of the shallow covered tunnel according to claim 3, Features: In step c, the main foundation pit formed by the entrance and exit, including at least the side wall on the side of the shield side penetration, is supported by embedded steel plates and steel supports.
5. The method for alternately constructing the auxiliary structure of the station under the high-voltage line and the side-through of the shallow covered tunnel according to claim 1, Features: In step c, during the construction of the entrance and exit, a side wall pressure box stress monitoring instrument is synchronously embedded to measure the inclination of the retaining pile structure, the supporting axial force and the side wall stress monitoring within the side penetration range during the tunnel side penetration construction.
6. The method for alternately constructing the auxiliary structure of the station under the high-voltage line and the side-through of the shallow covered tunnel according to claim 1, Features: In step c, before the construction of the first phase structure of the entrance and exit, the overhead line height limit frame is constructed to limit the minimum vertical distance and minimum horizontal distance between the high-voltage line and the building.
7. The method for alternately constructing the auxiliary structure of the station under the high-voltage line and the side-through of the shallow covered tunnel according to claim 1, Features: In step d, the tunneling speed of the shield machine is controlled at 30-45 mm / min, the horizontal posture is controlled at ±20°, and the single-loop deviation correction is controlled at ±5 mm.
8. The method for alternately constructing the auxiliary structure of the station under the high-voltage line and the side-through of the shallow covered tunnel according to claim 7, Features: During the tunneling process of the shield machine, the gap between the shield segment and the surrounding rock is filled and compacted by controlling the grouting amount and grouting pressure; The grouting volume shall not be less than 7.5m 3 During the grouting process, ensure that the pipelines are grouted at the same time, the upper grouting pressure is not greater than 0.3Mpa, and the lower grouting pressure is not greater than 0.34Mpa.
9. The method for alternately constructing the auxiliary structure of the station under the high-voltage line and the side-through of the shallow covered tunnel according to claim 8, Features: The soil pressure is controlled at about 0.8 bar during excavation, and maintained at about 1.0 bar when stopped; The thrust of the shield machine is controlled at 11000-18000KN, the torque is controlled at 1300KN·m-2000KN·m, and the cutter head speed is controlled at 1.9-2.0rpm.
10. The method for alternately constructing the auxiliary structure of the station under the high-voltage line and the side-through of the shallow earth-covered tunnel according to claim 9, Features: Strengthen soil improvement during excavation, and use 3.8-4.2m3 of foam agent per ring. 3 , add mud 22-28m 3 The slag discharge volume is controlled at 7-8 buckets, and the slag discharge volume of a single ring is not more than 145m 3 , weight not more than 255T.
Citation Information
Patent Citations
Shield tunneling construction method in overlapped tunnel in water-rich silt stratum
CN106499399A
Upper-lower overlapping cross parallel tunnel shield construction method
CN109458185A
Construction method for crossing civil air defense roadway of metro shield tunnel
CN113818889A
Construction method for making water-rich sand layer shield over cross existing line and underneath cross sewage push pipe at close range
US20210301660A1
Construction method for shield tunnels passing underneath viaduct in multi-interval, small-clear-distance and overlapping manner
WO2020224233A1