Railway millimeter wave ground base station deployment method, electronic equipment and storage medium
By calculating the station transmission capacity and docking time, evaluating the transmission matching degree and cost, and determining the optimal base station deployment plan, the problem of deploying millimeter-wave base stations in the large-capacity data transmission of passenger trains is solved, improving transmission efficiency and reducing costs.
Patent Information
- Application Number
- CN202411070442.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-06
- Publication Date
- 2024-11-26
AI Technical Summary
The existing technology cannot effectively solve the problem of deploying millimeter-wave base stations at stations during the transmission of large-capacity data in passenger trains, resulting in unreasonable transmission capacity and deployment costs.
By calculating the solution transmission matching degree, solution transmission capability and solution deployment cost, determine the base station deployment plan with the best comprehensive performance, determine the initial base station deployment plan based on the station's transmission capacity and docking time, and select the best base station deployment plan through comprehensive evaluation .
The reasonable selection of stations on railway lines has been achieved to deploy millimeter wave ground base stations, which improves transmission capacity and reduces deployment costs, and ensures timely transmission of train data.
Smart Images

Figure CN119031377A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of train data transmission, and in particular to a railway millimeter wave ground base station deployment method, electronic equipment and storage medium. Background Art
[0002] Massive amounts of data are generated during train operation, and these data need to be transmitted to the ground for viewing and analysis. For data with high real-time requirements, such as small-capacity data such as train control and operation data, real-time transmission is usually used. For data with less real-time requirements, such as large-capacity data such as video surveillance data, the traditional transmission solution is: the data is stored on the on-board mechanical hard disk during operation, and then manually copied when the train stops. However, the amount of large-capacity data is large, and the copying time required is long, which has a certain impact on train scheduling and operation efficiency. The millimeter wave communication rate is very fast, up to 1Gbps / s. By deploying several millimeter wave base stations along the railway line, the large-capacity data generated by the train can be transmitted in transit, avoiding the problem of long-term manual copying after the train stops.
[0003] There is a data transmission scheme for detection trains in the prior art. For the convenience of deployment, the millimeter wave base stations are directly selected to deploy. The specific scheme is: determine the total amount of detection data generated by the detection train and the dump capacity S of each station, and set the redundant dump capacity, and comprehensively determine the number of millimeter wave base stations m required. The prior art is aimed at the data dump problem of the detection train. Since the detection train does not stop at the station when running, the passing time of the detection train at each station is basically the same, and the millimeter wave communication rate will not fluctuate too much under normal circumstances. Therefore, the dump capacity S of each station is regarded as the same. Based on S, the required number of millimeter wave base stations is first determined, and then based on the required number of millimeter wave base stations, several base station planning schemes are generated for multi-objective optimization to obtain the optimal dump site planning scheme.
[0004] The existing technology is aimed at the application scenario of detecting whether a train passes a station without stopping, but it is not applicable to the passenger train operation scenario. Passenger trains need to stop at stations to pick up and drop off passengers, and the stop times at different stations are different, that is, the transmission capabilities of different stations are very different. In other words, different station selection schemes for deploying millimeter wave base stations result in different overall transmission capabilities. At the same time, the number of millimeter wave base stations that may need to be deployed may also be different, which in turn leads to different deployment costs. Regarding the deployment of millimeter wave base stations at stations for large-capacity data transmission in transit by passenger trains, a more reasonable station plan for deploying millimeter wave base stations can be determined by comprehensively considering factors such as the stop time of the train at the station and the cost of base station deployment. Summary of the invention
[0005] The purpose of the present invention is to solve the above-mentioned problems of the prior art and provide a method, device and storage medium for deploying railway millimeter wave ground base stations. The base station deployment scheme with the best comprehensive performance is determined by calculating the transmission matching degree of the scheme, the transmission capacity of the scheme and the deployment cost of the scheme, so as to reasonably select the stations on the railway line to deploy millimeter wave ground base stations.
[0006] In a first aspect, the present invention provides a method for deploying railway millimeter wave ground base stations, the method comprising: S1, determine the initial base station deployment plan based on the number of stations m on the railway line ; S2, calculate the transmission capacity and deployment cost of each initial base station deployment plan; the transmission capacity of the plan is based on the station variable W k and line transmission capacity S, the station variable W k and line transmission capacity S are both m-dimensional vectors W k ={w k (1),w k (2),……,w k (m)}, , S = {s(1), s(2), …, s(m)}, s(i) = v1t(i), which represents the transmission capacity of the i-th station on the railway line, which is determined by the millimeter wave train-to-ground communication rate v1 and the train's stop time t(i) at the station; the deployment cost of the scheme is based on the scheme station variable W k and the line deployment cost C, which is an m-dimensional vector, C={c(1),c(2),…,c(m)}, where c(i) represents the cost of deploying a millimeter-wave ground base station at the i-th station on the railway line; S3, obtaining the total amount of data generated when the train travels on the railway line, taking the total amount of data as the lower limit threshold of the transmission capacity of the scheme, and selecting an effective base station deployment scheme from the initial base station deployment schemes; S4, selecting the best base station deployment scheme from the valid base station deployment schemes based on the comprehensive scheme transmission capacity and scheme deployment cost.
[0007] Preferably, after selecting the effective base station deployment scheme in S3, the scheme transmission matching degree Q of the effective base station deployment scheme is calculated. k ;Q k =min{q k (i)|q k (i)≠0}, where q k (i) represents the effective base station deployment solution P k The transmission matching degree of the single station of the i-th station, the transmission matching degree of the scheme Q k Based on the effective base station deployment scheme P k The single-station transmission matching degree q of all base stations ink (i) The minimum value is determined; single-station transmission matching degree , where v2 represents the train data generation rate, T(i) represents the passing time of the train in the i-th section, which is determined by the sum of the running time of the train from the (i - 1)-th station to the i-th station and the stopping time of the train at the i-th station, j = max{w k (j) = 1 and j < i}, the j-th station is the previous station with a deployed base station before the i-th station, represents the amount of data generated from when the train departs from the j-th station to when it departs from the i-th station; In S4, the optimal base station deployment plan is selected from the effective base station deployment plans by combining the transmission matching degree of the plan, the transmission capacity of the plan, and the deployment cost of the plan.
[0008] Preferably, S4 includes: Perform dimensionless and normalization processing on the transmission matching degree of the effective base station deployment plan, the transmission capacity of the plan, and the deployment cost of the plan; Combine the set weights of the transmission matching degree of the plan, the transmission capacity of the plan, and the deployment cost of the plan, and calculate the comprehensive performance of each effective base station deployment plan; Select the optimal base station deployment plan based on the comprehensive performance of the effective base station deployment plan.
[0009] Preferably, when there are multiple effective base station deployment plans with the best comprehensive performance, perform the following operations: Select one of the transmission matching degree of the plan, the transmission capacity of the plan, and the deployment cost of the plan as the most priority parameter; For multiple effective base station deployment plans with the best comprehensive performance, extract the most priority parameter for comparison, and select the effective base station deployment plan corresponding to the optimal value of the most priority parameter as the optimal base station deployment plan.
[0010] Preferably, w k (1) = 0, w k (m) = 1, k ∈ (1, 2, ……, 2 m-2 ).
[0011] Preferably, in S3, set the redundant transmission amount, and use the sum of the total data amount and the redundant transmission amount as the lower threshold of the transmission capacity of the plan.
[0012] In a second aspect, the present invention provides an electronic device, including a memory, a computer program stored thereon, and a processor, and when the processor executes the computer program, it implements the above-mentioned method for deploying a railway millimeter-wave ground base station.
[0013] In a third aspect, the present invention provides a storage medium storing computer executable instructions. When the computer executable instructions are loaded and executed by a processor, the above-mentioned railway millimeter wave ground base station deployment method is implemented.
[0014] In summary, the present invention has the following beneficial effects: on the one hand, the transmission capacity of different stations on the railway line is determined based on the millimeter wave train-to-ground communication rate and the stop time of the train at the station, and the transmission capacity of the scheme is determined based on the scheme station variables and the transmission capacity of all stations on the railway line; at the same time, the scheme deployment cost is determined based on the scheme station variables and the cost of deploying base stations at stations on the railway line. On the other hand, the amount of data generated by the train in different sections on the railway line is determined based on the train data generation rate and the train's passing time in a section, and then the single-station transmission matching degree is determined by the difference between the transmission capacity of the station where the base station is deployed and the amount of data generated by the train within the section under the jurisdiction of the base station, that is, the effective and timely transmission capacity of a single base station, and then the scheme transmission matching degree is determined by the minimum value of the single-station transmission matching degree of all base stations to evaluate the overall effective and timely transmission capacity of all base stations in the base station deployment scheme. Finally, the base station deployment scheme with the best comprehensive performance is determined by the scheme transmission matching degree, the scheme transmission capacity and the scheme deployment cost, so as to reasonably select the millimeter wave ground base stations to be deployed at the stations on the railway line.
[0015] Additional aspects and advantages of the present invention will be given in part in the following description and in part will be obvious from the following description, or will be learned through practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] In order to more clearly illustrate the technical solutions and advantages in the embodiments of the present invention or the prior art, the drawings required for use in the embodiments or the prior art descriptions are briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0017] Figure 1 The figure is a schematic diagram of a method flow of a specific embodiment of the present invention.
[0018] Figure 2 The figure is a schematic diagram of a station on a railway line according to a specific embodiment of the present invention. DETAILED DESCRIPTION
[0019] In order to make the purpose, technical scheme and advantages disclosed in the embodiments of the present invention clearer, the embodiments of the present invention are further described in detail in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the embodiments of the present invention and are not intended to limit the embodiments of the present invention. Based on the embodiments in this application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of this application. Examples of the embodiments are shown in the accompanying drawings, where the same or similar reference numerals throughout represent the same or similar elements or elements with the same or similar functions.
[0020] It should be noted that the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions. For example, a process, method, system, product or server that includes a series of steps or units is not necessarily limited to those steps or units explicitly listed, but may include other steps or units that are not explicitly listed or inherent to these processes, methods, products or devices.
[0021] Passenger trains need to stop at stations to pick up and drop off passengers, and the stop times at different stations are different, that is, the transmission capacity of different stations is very different. In other words, different station selection schemes for deploying millimeter wave base stations will lead to different overall transmission capabilities, and the number of millimeter wave base stations that may need to be deployed may also be different, which in turn leads to different deployment costs. In order to deploy millimeter wave base stations at stations for large-capacity data transmission on the way by passenger trains, a comprehensive consideration of factors such as the stop time of trains at stations and the cost of base station deployment can more reasonably determine the station plan for deploying millimeter wave base stations.
[0022] Therefore, if Figure 1 As shown, the embodiment of the present application provides a railway millimeter wave ground base station deployment method, including S1, determining an initial base station deployment plan according to the number of stations m on the railway line In this step, the train departure stations and train parking lots at both ends of the railway line are regarded as stations to determine the number of stations m on the railway line. Each station can choose to deploy or not deploy a millimeter wave base station, so there are 2 initial base station deployment plans. m indivual.
[0023] The method of this embodiment further includes S2, calculating the transmission capacity and deployment cost of each initial base station deployment solution. The transmission capacity of the solution is based on the station variable W k and line transmission capacity S, the station variable W k and line transmission capacity S are both m-dimensional vectors W k ={w k (1),w k (2),……,w k (m)}, The line transmission capacity S = {s(1), s(2), ..., s(m)}, s(i) = v1t(i), which represents the transmission capacity of the i-th station on the railway line, is determined by the millimeter wave train-to-ground communication rate v1 and the train's stop time t(i) at the station.
[0024] In some embodiments of the present application, the stop time of the train at the exit station is regarded as 0, and it can be regarded that data is generated only after the train leaves the exit station, that is, no data needs to be transmitted at the train exit station, so w can be set k (1) = 0. The stop time of the train at the parking lot is set according to the actual situation of train scheduling. In addition, the data generated by the train between the last station and the parking lot can only be transmitted to the parking lot, so w can be set k (m)=1. Correspondingly, the number of initial base station deployment solutions is 2 m -2 .
[0025] The deployment cost of the scheme is based on the station variable W of the scheme k and the line deployment cost C, which is an m-dimensional vector, C={c(1),c(2),…,c(m)}, where c(i) represents the cost of deploying a millimeter-wave ground base station at the i-th station on the railway line.
[0026] The method of this embodiment also includes S3, obtaining the total amount of data generated when the train travels on the railway line, taking the total amount of data as the lower limit threshold of the scheme transmission capacity, and selecting an effective base station deployment scheme from the initial base station deployment schemes.
[0027] In the actual train-to-ground communication process, the communication rate may be slowed down due to weather or other factors. In order to ensure that the deployed millimeter wave base station can transmit the train data on the way, in some embodiments of the present application, the redundant transmission amount is set in S3, and the redundant transmission amount can be set as needed, such as 20% of the total data amount. The sum of the total data amount and the redundant transmission amount is used as the lower limit threshold of the transmission capacity of the scheme.
[0028] The method of this embodiment further includes S4, selecting the best base station deployment solution from the valid base station deployment solutions based on the transmission capability of the solution and the deployment cost of the solution.
[0029] In S3, the total data volume is used as the lower limit threshold of the scheme transmission capacity to select an effective base station deployment scheme from the initial base station deployment scheme. The scheme transmission capacity is the total transmission capacity of all stations with deployed base stations in the base station deployment scheme. However, when the total transmission capacity of the base station deployment scheme meets the standard, the matching degree between the single-station transmission capacity of the stations with deployed base stations and the train data volume of the station sections they管辖 is inconsistent. The range of the station section管辖 by a single base station is from the previous station with a deployed base station to the station where the base station is located. This base station transmits the data generated by the train in the station section it管辖. Therefore, the matching degree between the transmission capacity of each station with a deployed base station and the data volume generated by the trains in the station sections it管辖 should be as high as possible. To select a base station deployment scheme with a high transmission matching degree, in some embodiments of the present application, after selecting the effective base station deployment scheme in S3, calculate the scheme transmission matching degree Q of the effective base station deployment scheme. k ; Q k =min{q k (i)|q k (i)≠0}, where q k (i) represents the single-station transmission matching degree of the i-th station in the effective base station deployment scheme P k . The scheme transmission matching degree Q k is determined by the minimum value of the single-station transmission matching degrees q k of all base stations in the effective base station deployment scheme P k .
[0030] Single-station transmission matching degree , where v2 represents the train data generation rate, as shown in Figure 2 . T(i) represents the passing time of the train in the i-th station section, that is, the time from when the train leaves the (i - 1)-th station to before it leaves the i-th station, which is determined by the sum of the travel time of the train from the (i - 1)-th station to the i-th station and the stop time of the train at the i-th station. j = max{w k (j)=1 and j < i}, the j-th station is the previous station with a deployed base station before the i-th station, represents the data volume generated by the train from when it leaves the j-th station to before it leaves the i-th station.
[0031] In this embodiment, in S4, the optimal base station deployment scheme is selected from the effective base station deployment schemes by comprehensively considering the scheme transmission matching degree, the scheme transmission capacity, and the scheme deployment cost.
[0032] In some embodiments of the present application, the S4 includes: Perform dimensionless and normalization processing on the scheme transmission matching degree, the scheme transmission capacity, and the scheme deployment cost of the effective base station deployment scheme; The comprehensive performance of each effective base station deployment scheme is calculated by combining the set weights of the scheme transmission matching degree, scheme transmission capacity and scheme deployment cost; The optimal base station deployment scheme is selected based on the comprehensive performance of effective base station deployment schemes.
[0033] In some embodiments of the present application, the comprehensive performance of the effective base station deployment scheme in S4 is determined by summing the product of the scheme transmission matching degree, the scheme transmission capacity and the scheme deployment cost with their respective weights. It can be understood that when selecting a base station deployment strategy scheme, the higher the scheme transmission matching degree and the scheme transmission capacity, the better, and the lower the scheme deployment cost, the better, so the weights of the scheme transmission matching degree and the scheme transmission capacity are positive, and the weight of the scheme deployment cost is negative.
[0034] In some embodiments of the present application, when there are multiple effective base station deployment solutions with the best comprehensive performance, one of them can be randomly selected as the best. In some embodiments of the present application, when there are multiple effective base station deployment solutions with the best comprehensive performance, the following operations can be performed: Select one of the scheme transmission matching degree, scheme transmission capacity and scheme deployment cost as the most prioritized parameter; For multiple effective base station deployment plans with the best comprehensive performance, the most prioritized parameters are extracted for comparison, and the effective base station deployment plan corresponding to the optimal value of the most prioritized parameter is selected as the optimal base station deployment plan.
[0035] In some embodiments of the present application, different priorities can be set for the scheme transmission matching degree, scheme transmission capacity and scheme deployment cost. If there are multiple optimal values of the highest priority parameter, the second priority parameter is extracted for comparison, and the effective base station deployment scheme corresponding to the optimal values of the highest priority parameter and the second priority parameter is selected as the optimal base station deployment scheme.
[0036] On the one hand, the present application determines the transmission capacity of different stations on the railway line based on the millimeter wave train-to-ground communication rate and the train's stop time at the station, and determines the transmission capacity of the scheme based on the scheme station variables and the transmission capacity of all stations on the railway line; at the same time, the scheme deployment cost is determined based on the scheme station variables and the cost of deploying base stations at stations on the railway line. On the other hand, the amount of data generated by the train in different sections of the railway line is determined based on the train data generation rate and the train's passing time in a section, and then the single-station transmission matching degree, that is, the effective and timely transmission capacity of a single base station is determined by the difference between the transmission capacity of the station where the base station is deployed and the amount of data generated by the train within the section under the jurisdiction of the base station, and then the scheme transmission matching degree is determined by the minimum value of the single-station transmission matching degree of all base stations to evaluate the overall effective and timely transmission capacity of all base stations in the base station deployment scheme. Finally, the base station deployment scheme with the best comprehensive performance is determined by the scheme transmission matching degree, scheme transmission capacity and scheme deployment cost, so as to reasonably select the millimeter wave ground base stations to be deployed at the stations on the railway line.
[0037] The embodiment of the present application also provides an electronic device, including a memory and a processor, and the memory and the processor can be connected via a bus or other means. The memory can be used to store software programs, computer programs and modules, such as the program / module corresponding to the above-mentioned railway millimeter wave ground base station deployment method; the processor implements the above-mentioned railway millimeter wave ground base station deployment method by executing the computer program and module in the memory.
[0038] The processor may be a central processing unit, a digital signal processor, an application-specific integrated circuit, a field programmable gate array, etc., and the memory may be a high-speed random access memory, a non-volatile memory, etc.
[0039] The embodiment of the present application also provides a storage medium, in which computer executable instructions are stored, and when the computer executable instructions are loaded and executed by the processor, the above-mentioned railway millimeter wave ground base station deployment method is implemented. The storage medium can be a combination of one or more of a magnetic disk, an optical disk, a read-only storage memory, a random access storage memory, a flash memory, a hard disk, etc.
[0040] It should be noted that the sequence of the above embodiments of the present invention is for description only and does not represent the advantages and disadvantages of the embodiments. The above describes specific embodiments of this specification, and other embodiments are within the scope of the appended claims. In some cases, the actions or steps recorded in the claims can be performed in an order different from that in the embodiments and still achieve the desired results. In addition, the processes depicted in the drawings do not necessarily require the specific order or continuous order shown to achieve the desired results. In some embodiments, multitasking and parallel processing are also possible or may be advantageous.
[0041] The various embodiments in this specification are described in a progressive manner, and the same or similar parts between the various embodiments can be referenced to each other, and each embodiment focuses on the differences from other embodiments.
[0042] Those skilled in the art will appreciate that all or part of the steps of the above embodiments can be accomplished by hardware, or by programs instructing the relevant hardware to accomplish the steps. The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A method for deploying railway millimeter wave ground base stations, characterized in that: The method The following steps are involved: S1, determine the initial base station deployment plan based on the number of stations m on the railway line ; S2, calculate the transmission capacity and deployment cost of each initial base station deployment plan; the transmission capacity of the plan is based on the station variable W k and line transmission capacity S, the station variable W k and line transmission capacity S are both m-dimensional vectors W k ={w k (1),w k (2),……,w k (m)}, , S = {s(1), s(2), …, s(m)}, s(i) = v1t(i), which represents the transmission capacity of the i-th station on the railway line, which is determined by the millimeter wave train-to-ground communication rate v1 and the train's stop time t(i) at the station; the deployment cost of the scheme is based on the scheme station variable W k and the line deployment cost C, which is an m-dimensional vector, C={c(1),c(2),…,c(m)}, where c(i) represents the cost of deploying a millimeter-wave ground base station at the i-th station on the railway line; S3, obtaining the total amount of data generated when the train travels on the railway line, taking the total amount of data as the lower limit threshold of the transmission capacity of the scheme, and selecting an effective base station deployment scheme from the initial base station deployment schemes; S4, selecting the best base station deployment scheme from the valid base station deployment schemes based on the comprehensive scheme transmission capacity and scheme deployment cost.
2. A method for deploying railway millimeter wave ground base stations according to claim 1, characterized in that: After selecting an effective base station deployment plan in S3, calculate the plan transmission matching degree Q of the effective base station deployment plan k ; Q k =min{q k (i)|q k (i)≠0}, where q k (i) represents the single-station transmission matching degree of the i-th station in the effective base station deployment plan P k . The plan transmission matching degree Q k is determined by the minimum value of the single-station transmission matching degrees q k (i) of all base stations in the effective base station deployment plan P k ; The single-station transmission matching degree , where v2 represents the train data generation rate, and T(i) represents the passing time of the train in the i-th section, which is determined by the sum of the travel time of the train from the (i - 1)-th station to the i-th station and the stop time of the train at the i-th station. j = max{w k (j)=1 and j < i}, and the j-th station is the previous station with a deployed base station before the i-th station represents the amount of data generated from when the train leaves the j-th station to when it leaves the i-th station In S4, the optimal base station deployment scheme is selected from the valid base station deployment schemes by comprehensively considering the scheme transmission matching degree, scheme transmission capacity and scheme deployment cost.
3. A method for deploying railway millimeter wave ground base stations according to claim 2, characterized in that: The S4 includes: De-dimensionalize and normalize the transmission matching degree, transmission capacity and deployment cost of effective base station deployment solutions; The comprehensive performance of each effective base station deployment scheme is calculated by combining the set weights of the scheme transmission matching degree, scheme transmission capacity and scheme deployment cost; The optimal base station deployment scheme is selected based on the comprehensive performance of effective base station deployment schemes.
4. A method for deploying railway millimeter wave ground base stations according to claim 3, characterized in that: When there are multiple effective base station deployment solutions with the best overall performance, perform the following operations: Select one of the scheme transmission matching degree, scheme transmission capacity and scheme deployment cost as the most prioritized parameter; For multiple effective base station deployment plans with the best comprehensive performance, the most prioritized parameters are extracted for comparison, and the effective base station deployment plan corresponding to the optimal value of the most prioritized parameter is selected as the optimal base station deployment plan.
5. The method for deploying railway millimeter wave ground base stations according to claim 1, characterized in that: w k (1)=0,w k (m)=1,k∈(1,2,……,2 m-2 )。 6. A method for deploying railway millimeter wave ground base stations according to any one of claims 1 to 5, characterized in that: In S3, the redundant transmission amount is set, and the sum of the total data amount and the redundant transmission amount is used as the lower limit threshold of the transmission capacity of the scheme.
7. An electronic device comprising a memory and a computer program and a processor stored thereon, characterized in that: When the processor executes the computer program, it implements the railway millimeter wave ground base station deployment method as described in any one of claims 1-6.
8. A storage medium, characterized in that The storage medium stores computer executable instructions, and when the computer executable instructions are loaded and executed by the processor, the railway millimeter wave ground base station deployment method as described in any one of claims 1-6 is implemented.