Foundation pit earth excavation method
By adopting the island excavation method combining multi-layer horizontal support beams and steel sheet piles in deep foundation pits, the problems of unstable and low efficiency of support structures in traditional deep foundation pits are solved, and safer and more efficient Earth excavation simplifies construction technology and reduces costs.
Patent Information
- Application Number
- CN202411428805.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-14
- Publication Date
- 2024-11-29
AI Technical Summary
The traditional deep foundation pit earth excavation method has problems such as unstable support structure, low excavation efficiency and great impact on the surrounding environment.
The combination of multi-layer horizontal support beams and inner and outer steel sheet piles is adopted, and the excavation of the earth is layer by layer through island excavation method and fan-shaped division. The hydraulic cylinder and annular track are used to achieve flexible positioning and fixing of the support beams, reducing the impact on the surrounding environment.
It improves the safety and efficiency of deep foundation pit excavation, reduces costs, simplifies construction technology, and achieves rapid and orderly earth excavation.
Smart Images

Figure CN119041443A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of foundation pit excavation, in particular to an earth excavation method for deep foundation pit engineering, which improves the safety and efficiency of deep foundation pit excavation through innovative support structure and excavation sequence. Background Art
[0002] With the acceleration of urbanization, the demand for deep foundation pit engineering for high-rise buildings and subway projects is growing. Although traditional deep foundation pit support methods, such as slope excavation, soil nail wall, steel sheet pile, cast-in-place pile, etc., can meet engineering needs to a certain extent, there are many problems in traditional deep foundation pit earthwork excavation, such as unstable support structure, low excavation efficiency, and great impact on the surrounding environment. In order to solve these problems, the present invention provides a new excavation method. Summary of the invention
[0003] The present invention provides a foundation pit excavation method, which is implemented by the following technical solutions:
[0004] A foundation pit excavation method comprises the following steps:
[0005] Step 1: After the deep foundation pit is laid out and measured, N layers of horizontal support beams are designed from top to bottom in the deep foundation pit according to the deep foundation pit engineering conditions, and the foundation pit earthwork is excavated layer by layer using the island excavation method, 1≤N≤20;
[0006] Step 2: Drive the outer steel sheet piles downward along the outer wall of the deep foundation pit;
[0007] Step 3: Drive inner steel sheet piles in the center of the deep foundation pit. The inner steel sheet piles form a circle with a diameter of D, 1m≤D≤3m. The inner steel sheet piles and the core earthwork form a middle island;
[0008] Step 4: Excavate the soil between the outer steel sheet piles and the inner steel sheet piles to the bottom elevation of the first horizontal support beam. When excavating to the bottom of the first horizontal support beam, weld the first outer support frame beam at the position of the outer steel sheet pile corresponding to the first horizontal support beam, and weld the first inner support frame beam at the position of the inner steel sheet pile corresponding to the first horizontal support beam. The first inner support frame beam is provided with a circular track.
[0009] Step 5: Slidingly connect one end of the first-layer horizontal support beam to the inner support frame beam, and position and fix it, and temporarily fix the other end of the first-layer horizontal support beam to the first-layer outer support frame beam;
[0010] Step 6: excavate the soil above the bottom of the second-layer horizontal support beam, and divide it into n sector-shaped excavation areas, where n is an even number, and excavate the soil above the bottom of the second-layer horizontal support beam in the first sector-shaped excavation area corresponding to the first-layer horizontal support beam;
[0011] Step Seven: After excavating the first sector area, set the fixed horizontal support beam at the position of the first-layer horizontal support beam. Weld the two ends of the fixed horizontal support beam to the internal support frame beam and the first-layer external support frame beam respectively. After completing the setting of the fixed horizontal support beam, disassemble the temporary fixation of the first-layer horizontal support beam and move it to the central axis of the second sector excavation area. Position and fix one end of the first-layer horizontal support beam to the internal support frame beam, and temporarily fix the other end of the first-layer horizontal support beam to the first-layer external support frame beam;
[0012] Step Eight: Repeat Steps Six to Seven until the soil above the bottom of the second-layer horizontal support beam is completely excavated. Weld the second-layer external support frame beam at the position of the second-layer horizontal support beam corresponding to the outer steel sheet pile, and weld the second-layer internal support frame beam at the position of the second-layer horizontal support beam corresponding to the inner steel sheet pile. The second-layer internal support frame beam is provided with a circular track;
[0013] Step Nine: Repeat Steps Five to Eight until all the soil above the Nth-layer horizontal support steel plate is completely excavated, and the deep foundation pit soil excavation is completed.
[0014] Further, a plurality of threaded positioning holes are arranged at intervals on the back plate of the circular track in Step Four. There are two rows of threaded positioning holes.
[0015] Further, the horizontal support beam in Step Five includes a fixed section and a telescopic section. The fixed section and the telescopic section are sleeved. A hydraulic cylinder is fixed at one end of the fixed section close to the telescopic section, and the free end of the hydraulic cylinder is fixedly connected to the telescopic section.
[0016] Further, a positioning plate is arranged at one end of the fixed section. The positioning plate is provided with rollers that are in close contact with the back plate. Two limit nuts are arranged at the positions corresponding to the threaded positioning holes on the positioning plate. Two limit screws are arranged in cooperation with the two limit nuts, and the limit screws can be screwed into the threaded positioning holes for positioning.
[0017] Further, the length of the horizontal support beam in Step Six is R, and the outer arc length L of the sector should meet L < n×π×R / 180°, where n is the central angle.
[0018] Further, two horizontal support beams are provided in Step Five. The two horizontal support beams are symmetrically arranged around the center of the middle island. The soil excavation of the first sector excavation area and the (1 + n / 2)th sector excavation area is carried out simultaneously in Steps Six to Seven.
[0019] After adopting the above technical solutions, the beneficial effects of the present invention are:
[0020] 1. The construction method of the present invention improves the safety of deep foundation pit excavation, and enhances the stability of the foundation pit by combining the use of multi-layer horizontal support beams and internal and external steel sheet piles;
[0021] 2. The construction method of the present invention improves excavation efficiency and realizes rapid and orderly earth excavation through island excavation method and sector division;
[0022] 3. The construction method of the present invention is simple and easy to implement, does not require a trestle, effectively speeds up the construction period, reduces the cost of deep foundation pit excavation, and is a safe and reliable deep foundation pit excavation method. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] In order to more clearly illustrate the technical solutions in the implementation modes of the present application, the drawings required for use in the description of the implementation modes will be briefly introduced below. Obviously, the drawings described below are only some implementation modes of the present application. For those skilled in the art, other drawings can be obtained based on these drawings without creative work.
[0024] Figure 1 This is a schematic diagram of an embodiment of the foundation pit excavation method.
[0025] Figure 2 This is a schematic diagram of the installation of the first layer of horizontal support beams for this foundation pit excavation method.
[0026] Figure 3 This is the schematic diagram of the excavation of the first fan-shaped excavation area of this foundation pit excavation method.
[0027] Figure 4 This is a schematic diagram of the circular track for this foundation pit excavation method.
[0028] Figure 5 This is a schematic diagram of the positioning plate for this foundation pit excavation method.
[0029] Figure 6 This is a schematic diagram of Example 2 of the foundation pit excavation method.
[0030] Description of reference numerals:
[0031] 100-outer steel sheet piles, 200-inner steel sheet piles, 300-core earthwork, 400-horizontal support beam, 401-fixed section, 4011-positioning plate, 4012-roller, 4013-limiting nut, 4014-limiting screw, 402-telescopic section, 403-hydraulic cylinder, 500-outer support frame beam, 600-inner support frame beam, 601-annular track, 602-threaded positioning hole, 700-fixed horizontal support beam. DETAILED DESCRIPTION
[0032] The following description of the embodiments will help the public better understand the present invention, but the specific embodiments given by the applicant cannot and should not be regarded as limitations on the technical solutions of the present invention. Any changes to the definitions of components or technical features, or formal rather than substantive changes to the overall structure should be regarded as the scope of protection defined by the technical solutions of the present invention.
[0033] In this application, unless otherwise clearly specified or limited, the terms "installation", "connection", "fixation" and the like should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be internal communication between two elements, or it can be only surface contact, or surface contact connection through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0034] The present invention is implemented by the following technical solutions:
[0035] Embodiment 1:
[0036] A foundation pit excavation method comprises the following steps:
[0037] Step 1: After the deep foundation pit is laid out and measured, N layers of horizontal support beams 400 are designed from top to bottom in the deep foundation pit according to the deep foundation pit engineering conditions, and the foundation pit earthwork is excavated layer by layer using the island excavation method, 1≤N≤20;
[0038] Step 2: driving outer steel sheet piles 100 downward along the outer wall of the deep foundation pit;
[0039] Step 3: Inner steel sheet piles 200 are driven into the center of the deep foundation pit. The inner steel sheet piles 200 form a circle with a diameter of D, 1m≤D≤3m. The combination of the inner steel sheet piles 200 and the core earthwork 300 is similar to the structure of steel pipe piles to form a middle island, which ensures the core strength of the middle island while reducing the footprint of the middle island;
[0040] Step 4: excavate the soil between the outer steel sheet pile 100 and the inner steel sheet pile 200 to the bottom elevation of the first horizontal support beam 400. When excavating to the bottom position of the first horizontal support beam 400, weld the first outer support frame beam 500 at the position of the outer steel sheet pile 100 corresponding to the first horizontal support beam 400, and weld the first inner support frame beam 600 at the position of the inner steel sheet pile 200 corresponding to the first horizontal support beam 400. The first inner support frame beam 600 is provided with an annular track 601. A plurality of threaded positioning holes 602 are arranged at intervals on the back plate of the annular track 601, and the threaded positioning holes 602 are arranged in two rows.
[0041] Step Five: Slide one end of the first-layer horizontal support beam 400 onto the inner support frame beam 600 and position and fix it. Temporarily fix the other end of the first-layer horizontal support beam 400 to the first-layer outer support frame beam 500. The horizontal support beam 400 includes a fixed section 401 and a telescopic section 402. The fixed section 401 and the telescopic section 402 are sleeved together. A hydraulic cylinder 403 is fixed at one end of the fixed section 401 close to the telescopic section 402. The free end of the hydraulic cylinder 403 is fixedly connected to the telescopic section 402. A positioning plate 4011 is provided at one end of the fixed section 401. The positioning plate 4011 is provided with rollers 4012. The rollers 4012 are in contact with the back plate. Two limit nuts 4013 are provided at positions corresponding to the threaded positioning holes 602 on the positioning plate 4011. Two limit screws 4014 are provided in cooperation with the two limit nuts 4013. The limit screws 4014 can be screwed into the threaded positioning holes 602 for positioning. When the first-layer horizontal support beam 400 needs to be moved to the target position, its telescopic section 402 contracts through the hydraulic cylinder 403, and the rollers 4012 of the positioning plate 4011 slide within the annular track 601. When the target position is reached, rotate the limit screws 4014 on the positioning plate 4011 to screw the limit screws 4014 into the threaded positioning holes 602 to fix the positioning plate 4011. Then, extend the telescopic section 402 through the hydraulic cylinder 403 until the free end of the telescopic section 402 abuts against the outer support frame beam 500, and temporarily fix the free end of the telescopic section 402 to the outer support frame beam 500;
[0042] Step Six: Excavate the soil above the bottom of the second-layer horizontal support beam 400 and divide it into n fan-shaped excavation areas. Here, n is an even number. Excavate the soil above the bottom of the second-layer horizontal support beam 400 in the first fan-shaped excavation area corresponding to the first-layer horizontal support beam 400. The length of the horizontal support beam 400 is R, and the outer arc length L of the fan should meet L < n×π×R / 180°, where n is the central angle, to ensure the stable support of the horizontal support beam 400 for this fan-shaped excavation area and ensure the safety of the foundation pit construction;
[0043] Step Seven: After excavating the first fan-shaped area, set up the fixed horizontal support beam 700 at the position of the first-layer horizontal support beam 400. Weld and fix both ends of the fixed horizontal support beam 700 to the inner support frame beam 600 and the first-layer outer support frame beam 500 respectively. After completing the setting of the fixed horizontal support beam 700, disassemble the temporary fixation of the first-layer horizontal support beam 400 and move it to the axis of the second fan-shaped excavation area. Position and fix one end of the first-layer horizontal support beam 400 to the inner support frame beam 600, and temporarily fix the other end of the first-layer horizontal support beam 400 to the first-layer outer support frame beam 500, which can timely provide support for the horizontal support beam 400 and ensure the stability of the entire support structure;
[0044] Step 8: Repeat steps 6 to 7 until the soil above the bottom of the second-layer horizontal support beam 400 is completely excavated, and the second-layer outer support frame beam 500 is welded at the position where the outer steel sheet pile 100 corresponds to the second-layer horizontal support beam 400, and the inner second-layer support frame beam is welded at the position where the inner steel sheet pile 200 corresponds to the second-layer horizontal support beam 400, and the second-layer inner support frame beam 600 is provided with a circular track 601;
[0045] Step 9: Repeat steps 5 to 8 until all the earthwork above the Nth layer of horizontal support steel plates is excavated and the deep foundation pit excavation is completed.
[0046] Embodiment 2:
[0047] What is different from the first embodiment is that in the step five, two horizontal support beams 400 are provided, and the two horizontal support beams 400 are arranged symmetrically about the center of the middle island. In the steps six to seven, the soil excavation of the first fan-shaped excavation area and the 1+n / 2 fan-shaped excavation area is carried out simultaneously. Since n is an even number, the symmetrically arranged horizontal support beams 400 can always maintain the force balance of the middle island, and can simultaneously construct multiple working surfaces of the foundation pit, further improving the construction efficiency.
[0048] Those skilled in the art should understand that those skilled in the art can implement variations by combining the prior art and the above embodiments, which will not be described in detail here. Such variations do not affect the essential content of the present invention, and will not be described in detail here.
[0049] The above describes the preferred embodiments of the present invention. It should be understood that the present invention is not limited to the above-mentioned specific embodiments, and the devices and structures that are not described in detail should be understood to be implemented in a common manner in the art; any technician familiar with the art can use the above-disclosed methods and technical contents to make many possible changes and modifications to the technical solutions of the present invention without departing from the scope of the technical solutions of the present invention, or modify them into equivalent embodiments of equivalent changes, which does not affect the essential content of the present invention. Therefore, any simple modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solutions of the present invention are still within the scope of protection of the technical solutions of the present invention.
Claims
1. A foundation pit excavation method, characterized in that: The following steps are involved: Step 1: After the deep foundation pit is laid out and measured, N layers of horizontal support beams (400) are designed from top to bottom in the deep foundation pit according to the deep foundation pit engineering conditions, and the foundation pit earthwork is excavated layer by layer using the island excavation method, 1≤N≤20; Step 2: driving outer steel sheet piles (100) downward along the outer wall of the deep foundation pit; Step 3: driving inner steel sheet piles (200) at the center of the deep foundation pit, the inner steel sheet piles (200) form a circle with a diameter of D, 1m≤D≤3m, and the inner steel sheet piles (200) and the core earthwork (300) form a middle island; Step 4: excavate the soil between the outer steel sheet pile (100) and the inner steel sheet pile (200) to the bottom elevation of the first horizontal support beam (400). When the excavation reaches the bottom position of the first horizontal support beam (400), weld the first outer support frame beam (500) at the position of the outer steel sheet pile (100) corresponding to the first horizontal support beam (400), and weld the first inner support frame beam (600) at the position of the inner steel sheet pile (200) corresponding to the first horizontal support beam (400). The first inner support frame beam (600) is provided with a circular track (601); Step 5: Slidingly connect one end of the first-layer horizontal support beam (400) to the inner support frame beam (600), and position and fix it, and temporarily fix the other end of the first-layer horizontal support beam (400) to the first-layer outer support frame beam (500); Step 6: excavate the soil above the bottom of the second-layer horizontal support beam (400), and divide it into n sector-shaped excavation areas, where n is an even number, and excavate the soil above the bottom of the second-layer horizontal support beam (400) in the first sector-shaped excavation area corresponding to the first-layer horizontal support beam (400); Step 7: After excavating the first sector-shaped area, a fixed horizontal support beam (700) is set at the position of the first horizontal support beam (400), and the two ends of the fixed horizontal support beam (700) are respectively welded to the inner support frame beam (600) and the first outer support frame beam (500). After the fixed horizontal support beam (700) is set, the temporary fixation of the first horizontal support beam (400) is disassembled and moved to the axis of the second sector-shaped excavation area, and one end of the first horizontal support beam (400) is positioned and fixed to the inner support frame beam (600), and the other end of the first horizontal support beam (400) is temporarily fixed to the first outer support frame beam (500); Step 8: Repeat steps 6 to 7 until the soil above the bottom of the second-layer horizontal support beam (400) is completely excavated, and the second-layer outer support frame beam (500) is welded at the position of the outer steel sheet pile (100) corresponding to the second-layer horizontal support beam (400), and the inner second-layer support frame beam is welded at the position of the inner steel sheet pile (200) corresponding to the second-layer horizontal support beam (400), and the second-layer inner support frame beam (600) is provided with a circular track (601); Step 9: Repeat steps 5 to 8 until all the earthwork above the Nth layer of horizontal support steel plates is excavated and the deep foundation pit excavation is completed.
2. A foundation pit excavation method according to claim 1, characterized in that: On the back plate of the annular track (601) in the fourth step, a plurality of threaded positioning holes (602) are arranged at intervals, and there are two rows of threaded positioning holes (602).
3. A foundation pit excavation method according to claim 2, characterized in that: The horizontal support beam (400) in the fifth step includes a fixed section (401) and a telescopic section (402). The fixed section (401) and the telescopic section (402) are sleeved. A hydraulic cylinder (403) is fixed at one end of the fixed section (401) close to the telescopic section (402), and the free end of the hydraulic cylinder (403) is fixedly connected to the telescopic section (402).
4. A foundation pit excavation method according to claim 3, characterized in that: One end of the fixed section (401) is provided with a positioning plate (4011). The positioning plate (4011) is provided with rollers (4012). The rollers (4012) are in close contact with the back plate. Two limit nuts (4013) are arranged at positions corresponding to the threaded positioning holes (602) on the positioning plate (4011). Two limit screws (4014) are arranged in cooperation with the two limit nuts (4013), and the limit screws (4014) can be screwed into the threaded positioning holes (602) for positioning.
5. A foundation pit excavation method according to claim 4, characterized in that: In the sixth step, the length of the horizontal support beam (400) is R, and the outer arc length L of the sector should meet L < n×π×R / 180°, where n is the central angle.
6. A foundation pit excavation method according to claim 5, characterized in that: Two horizontal support beams (400) are provided in the fifth step. The two horizontal support beams (400) are arranged symmetrically about the center of the middle island. In the sixth to seventh steps, the soil excavation of the first sector excavation area and the (1 + n / 2)-th sector excavation area is carried out simultaneously.