Floor support plate construction technology

By reserving grooves and hook teeth on the steel frame bearing plate and using rebound ceramic washer, the problems of lateral slippage during laying of the bearing plate and inconvenient washing after welding are solved, and efficient Construction process.

CN119041705APending Publication Date: 2024-11-29CCCC SHEC DONGMENG ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411227055.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-03
Publication Date
2024-11-29

AI Technical Summary

Technical Problem

The steel frame bearing plates are prone to lateral slipping and misalignment when laying, and the fixed structure of the ceramic washer leads to inconvenience of recycling after welding.

Method used

Leave grooves and hook teeth on the hook edges of the steel frame bearing plates, and use a press-rebound ceramic washer for easy fixing and recycling during laying.

Benefits of technology

It avoids the lateral slippage of the steel frame bearing plate during assembly, saves adjustment time, facilitates efficient laying, and simplifies the recycling of ceramic washer after welding, and improves construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119041705A_ABST
    Figure CN119041705A_ABST
Patent Text Reader

Abstract

The invention discloses a floor support plate construction process which comprises the following steps: step 1, prefabricating a steel bar steel frame floor plate, preparing galvanized plate frames of a steel piece steel frame floor support plate in a factory workshop in advance before construction, and reserving a matching groove at a hook edge at one end of each galvanized plate frame, and hook teeth matched with the grooves are reserved at the hook edge on the other side of the galvanized plate frame. The reinforcing steel bar and steel frame floor support plate has the beneficial effects that the grooves and the hook teeth are reserved in the hook edges of each reinforcing steel bar and steel frame floor support plate, so that every two adjacent reinforcing steel bar and steel frame floor support plates can be limited in the lateral direction during mutual splicing, and the situation that every two adjacent reinforcing steel bar and steel frame floor support plates slide in a staggered mode in the lateral direction during splicing is avoided; the time consumed by repeatedly adjusting the two adjacent steel bar steel frame floor support plates is saved, efficient laying of the steel piece steel frame floor support plates is facilitated, and meanwhile through the design of the pressing springback type ceramic washers, the ceramic washers can be rapidly taken and recycled after studs on the steel bar steel frame floor support plates are welded.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of floor decking construction, and in particular to a floor decking construction process. Background Art

[0002] Floor decking is a supporting product for multi-story steel structures. It is used to replace traditional formwork as a permanent support. In the steel structure industry, it is also called floor slab, steel decking, galvanized floor decking, and combined floor slab. In the north, it is called corrugated steel plate or galvanized corrugated steel plate. With the continuous improvement of the construction progress, the application of reinforced steel frame floor decking is becoming more and more extensive.

[0003] At present, the general construction process of reinforced steel frame floor decking is: prefabrication of floor decking, transportation of floor decking, laying of floor slabs, binding of steel parts and installation of pipelines, construction of side formwork, and pouring of concrete. Although the convenient laying construction of steel frame floor decking can be realized under the above construction process, on the one hand, when laying the floor decking, the adjacent floor deckings are fixed by the hook edges reserved by themselves. Since the hook edges on each floor decking are long strip structures, it is easy for the adjacent two floor deckings to slide and dislocate relative to each other in the lateral direction during assembly, so that the two adjacent floor deckings need to be repeatedly adjusted after hooking, which is not convenient for efficient laying of the floor decking. Moreover, when welding the bolts after the floor decking is assembled, since the ceramic washers used in the above process are fixed structures, the ceramic washers and the floor deckings are closely fitted after welding, which is inconvenient to recycle. Summary of the invention

[0004] The purpose of the present invention is to provide a floor decking construction process in order to solve the above problems.

[0005] The present invention achieves the above-mentioned purpose through the following technical solutions: A floor deck construction process comprises the following steps: Step 1: Prefabrication of reinforced steel frame floor slabs. Before construction, prepare the galvanized sheet frames of the steel frame floor slabs in the factory workshop, and reserve a matching groove at the hook edge at one end of each galvanized sheet frame, and reserve a hook tooth matching the groove at the hook edge on the other side of the galvanized sheet frame; Step 2: Transportation of steel truss floor decking. According to the actual laying needs, the prefabricated steel frame floor decking is transported to the installation site, and the steel frame floor decking is hoisted and placed in the designated position; Step 3: Laying sequence planning. When laying the steel frame floor deck, the laying of each layer of steel truss formwork should be laid from the starting position to one direction, and the steel truss formwork of each layer should be laid according to the installation construction sequence of the main structure; Step 4: Cleaning before laying: Before laying, clean the debris on the upper side of the steel beam for installing the floor deck, and pre-fix the supporting angle steel on the steel beam at the suspended position where the floor deck is laid; Step 5: Laying of floor decking. When laying reinforced steel frame floor decking, align with the reference line, install the first board, and spot weld its supporting vertical reinforcement to the steel beam; then install other boards in sequence. During the laying process, each board should be marked and checked according to the diagram. If there is any deviation, it should be adjusted immediately; at the same time, when welding bolts between the floor decking and the supporting steel beam during the laying process, it is necessary to lay press-rebound ceramic washers in the reserved holes on the floor decking in advance to prevent welding damage in the reserved holes on the floor decking when fixing the floor decking; Step 6: Tie up the steel bars and install the pipelines. After laying a certain area, set the floor support connection bars, reinforcing bars and negative bars according to the design requirements. The connection bars should be tied up with the steel trusses, and the distribution steel bars should be tied up in time to prevent the lateral instability of the steel trusses. Step 7: During the construction of the side formwork, the side formwork should be straightened by pulling the wire. After proper adjustment, one end of the steel bar is spot welded to the stud and the other end is spot welded to the side formwork to fix the side formwork. The spot welding distance between the bottom of the side formwork and the upper flange of the steel beam is 300mm. Step 8: Concrete pouring. After the side formwork construction is accepted, you only need to pour concrete on the laid reinforced steel frame floor deck to complete the construction of the reinforced steel frame floor deck.

[0006] Furthermore, in the step 2, when transporting the reinforced steel frame floor decking, it is necessary to combine the engineering drawings with the actual situation of the construction site, consider the vehicle transportation length and the actual weight of each floor decking, and consider whether two workers can move the weight to layout, produce according to size, and package according to each area. The weight of each package should not exceed 3 tons. At the same time, when lifting the reinforced steel frame floor decking, the bearing capacity of the steel beam should be considered, and too much weight should not be piled on a certain steel beam. This design can effectively prevent the steel frame floor decking from damaging the supporting steel beam after transportation, thereby ensuring the structural strength of the supporting steel beam.

[0007] Furthermore, in step 5, when laying the steel frame floor decking, the floor decking connections are fastened in a snap-fitting manner, and the hook connections between the plates should be tight to ensure that there is no leakage when pouring concrete, and at the same time, attention should be paid to the consistent discharge direction; for the damaged edge tongues and grooves of the steel truss plates, correction tools should be used to correct them before installation to ensure a firm connection between the tongues and grooves.

[0008] Furthermore, in step 5, when laying the steel frame floor decking at the column corners and floor slab edges, when the entire slab cannot be placed, the truss slab can be cut, and the cutting size must be checked and verified before cutting; if the truss slab width is less than 600mm at the end of the span, the truss slab can be cut along the length of the truss, and there should be 1 or 2 steel trusses on the slab after cutting, and the steel trusses must not be cut off.

[0009] Furthermore, in the step 5, when the steel frame floor decking is laid, after the floor decking is in place, the vertical steel bars at its ends should be spot welded to the upper flange of the steel beam immediately, and the bottom formwork and the upper flange of the steel beam should be spot welded along the width of the plate by manual arc welding with a spacing of no more than 300 mm; the bolt welding points are welded at the position and spacing required by the design, and a special fusion welding machine is used for construction. The porcelain ring is kept dry and removed after welding. The weld feet should be uniform and full to ensure strength.

[0010] Furthermore, in step 5, when two adjacent steel floor decks are clamped and fixed, it is necessary to ensure that the grooves and hook teeth reserved on the steel floor deck are aligned.

[0011] Furthermore, the construction sequence during construction in step 6 is: tying of support connection steel bars - tying of reinforcement steel bars at the opening edge and column edge - tying of distribution steel bars.

[0012] Furthermore, in step 6, during construction, the floor support connecting bars and negative bars need to be placed according to the requirements of the design drawings, and the connecting bars should be firmly tied to the steel truss steel bars.

[0013] Furthermore, during the construction in step 6, it is necessary to set the openings and column side reinforcement steel bars according to the number, model and position of the design drawings.

[0014] Furthermore, in the step 6, when laying the distribution reinforcement perpendicular to the truss direction during construction, the lower layer of steel bars should be laid first, and the lower layer of distribution steel bars should be placed on the upper surface of the lower chord of the steel truss and tied firmly to the lower chord steel bars; after the lower layer of steel bars are laid, the pipelines should be laid and installed immediately. The pipelines laid in the plate should be made of materials with good flexibility, and multiple pipelines should be pre-buried as much as possible. Small-diameter pipelines should be pre-buried through holes as much as possible; the electrical junction box can be reserved and pre-buried, and it can be fixed on the galvanized plate in advance, and small holes below p30 should be drilled. The drilling should avoid deformation of the truss plate, affecting the appearance or causing leakage; after the pipeline installation is completed, the upper layer of distribution steel bars should be laid, and the upper layer of distribution steel bars should be placed on the lower surface of the upper chord of the steel truss and tied firmly to the upper chord steel bars; if it is difficult to place it under the upper chord in actual construction, the steel bars can be placed on the upper chord with the consent of the designer and the owner, but at the same time, the thickness of the steel slab and the thickness of the reinforced concrete protective layer must be guaranteed.

[0015] The beneficial effects of the present invention are: The present invention reserves grooves and hook teeth at the hook edges of each reinforced steel frame floor deck, so that two adjacent reinforced steel frame floor decks can be limited in the lateral direction when assembled with each other, thereby avoiding the lateral misalignment and slippage of the two adjacent reinforced steel frame floor decks during assembly, saving time consumed in repeatedly adjusting the two adjacent reinforced steel frame floor decks, and facilitating the efficient laying of the steel frame floor decks. At the same time, with the design of the press-rebound ceramic gasket, the ceramic gasket can be quickly taken out and recovered after the bolts on the reinforced steel frame floor deck are welded, thereby facilitating the efficient subsequent construction process of the reinforced steel frame floor deck. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 The present invention is a flow chart of a floor decking construction process. DETAILED DESCRIPTION

[0017] A floor deck construction process comprises the following steps: Step 1: Prefabrication of reinforced steel frame floor slabs. Before construction, prepare the galvanized sheet frames of the steel frame floor slabs in the factory workshop, and reserve a matching groove at the hook edge at one end of each galvanized sheet frame, and reserve a hook tooth matching the groove at the hook edge on the other side of the galvanized sheet frame; Step 2: Transportation of steel truss floor decking. According to the actual laying needs, the prefabricated steel frame floor decking is transported to the installation site, and the steel frame floor decking is hoisted and placed in the designated position; Step 3: Laying sequence planning. When laying the steel frame floor deck, the laying of each layer of steel truss formwork should be laid from the starting position to one direction, and the steel truss formwork of each layer should be laid according to the installation construction sequence of the main structure; Step 4: Cleaning before laying: Before laying, clean the debris on the upper side of the steel beam for installing the floor deck, and pre-fix the supporting angle steel on the steel beam at the suspended position where the floor deck is laid; Step 5: Laying of floor decking. When laying reinforced steel frame floor decking, align with the reference line, install the first board, and spot weld its supporting vertical reinforcement to the steel beam; then install other boards in sequence. During the laying process, each board should be marked and checked according to the diagram. If there is any deviation, it should be adjusted immediately; at the same time, when welding bolts between the floor decking and the supporting steel beam during the laying process, it is necessary to lay press-rebound ceramic washers in the reserved holes on the floor decking in advance to prevent welding damage in the reserved holes on the floor decking when fixing the floor decking; Step 6: Tie up the steel bars and install the pipelines. After laying a certain area, set the floor support connection bars, reinforcing bars and negative bars according to the design requirements. The connection bars should be tied up with the steel trusses, and the distribution steel bars should be tied up in time to prevent the lateral instability of the steel trusses. Step 7: During the construction of the side formwork, the side formwork should be straightened by pulling the wire. After proper adjustment, one end of the steel bar is spot welded to the stud and the other end is spot welded to the side formwork to fix the side formwork. The spot welding distance between the bottom of the side formwork and the upper flange of the steel beam is 300mm. Step 8: Concrete pouring. After the side formwork construction is accepted, you only need to pour concrete on the laid reinforced steel frame floor deck to complete the construction of the reinforced steel frame floor deck.

[0018] In this embodiment, in step 2, when transporting the reinforced steel frame floor decking, it is necessary to combine the engineering drawings with the actual situation of the construction site, consider the vehicle transportation length and the actual weight of each floor decking, and consider whether two workers can move the weight to layout, produce according to size, and package according to each area. The weight of each package should not exceed 3 tons. At the same time, when lifting the reinforced steel frame floor decking, the bearing capacity of the steel beam should be considered, and do not pile too much weight on a certain steel beam. This design can effectively prevent the steel frame floor decking from damaging the supporting steel beam after transportation, thereby ensuring the structural strength of the supporting steel beam.

[0019] In this embodiment, in step 5, when laying the steel frame floor decking, the floor decking is connected by snap-fitting, and the hook connection between the plates should be tight to ensure that there is no leakage when pouring concrete, and at the same time, pay attention to the consistent discharge direction; for the damaged edge tongue and groove of the steel truss plate, use correction tools to correct it before installation to ensure a firm connection between the tongue and groove.

[0020] In this embodiment, in step 5, when laying the steel frame floor decking at the column corners and the edges of the floor slabs, when the entire slab cannot be placed, the truss slab can be cut, and the cutting size must be checked and verified before cutting; at the end of the span, if the truss slab width is less than 600mm, the truss slab can be cut along the length direction of the truss, and after cutting, there should be 1 or 2 steel trusses on the slab, and the steel trusses must not be cut off.

[0021] In this embodiment, in the step 5, when the steel frame floor decking is laid, after the floor decking is in place, the vertical steel bars at its ends should be spot welded to the upper flange of the steel beam immediately and firmly, and the bottom formwork and the upper flange of the steel beam should be spot welded along the width of the plate by manual arc welding with a spacing of no more than 300 mm; the bolt welding points are welded at the position and spacing required by the design, and a special fusion welding machine is used for construction. The porcelain ring is kept dry and removed after welding. The weld feet should be uniform and full to ensure strength.

[0022] In this embodiment, when two adjacent steel floor decks are clamped and fixed in step 5, it is necessary to ensure that the grooves and hook teeth reserved on the steel floor deck are aligned.

[0023] In this embodiment, the construction sequence of step 6 during construction is: tying of support connection steel bars - tying of reinforcement steel bars at the opening edge and column edge - tying of distribution steel bars.

[0024] In this embodiment, in step 6, the floor support connecting bars and negative bars need to be placed according to the requirements of the design drawings during construction, and the connecting bars should be firmly tied to the steel truss steel bars.

[0025] In this embodiment, during the construction in step 6, it is also necessary to set the openings and column side reinforcing steel bars according to the number, model, and position of the design drawings.

[0026] In this embodiment, during the construction in step 6, the distribution reinforcement is laid perpendicular to the truss direction. The lower layer of steel bars should be laid first, and the lower layer of distribution reinforcement should be placed on the upper surface of the lower chord of the steel truss and tied firmly to the lower chord reinforcement. After the lower layer of reinforcement is laid, the pipeline should be laid and installed immediately. The pipeline laid in the plate should be made of materials with good flexibility, and multiple pipelines should be avoided from being pre-buried in a concentrated manner. Small-diameter pipelines should be used for dispersed perforation and pre-buried as much as possible. For the reservation and pre-buried of electrical junction boxes, they can be fixed on the galvanized plate in advance, and small holes below p30 should be drilled. The drilling should avoid deformation of the truss plate, which will affect the appearance or cause leakage. After the pipeline is installed, the upper layer of distribution reinforcement is laid, and the upper layer of distribution reinforcement should be placed on the lower surface of the upper chord of the steel truss and tied firmly to the upper chord reinforcement. If it is difficult to place it under the upper chord in actual construction, the reinforcement can be placed on the upper chord with the consent of the designer and the owner, but at the same time, the thickness of the reinforced floor slab and the thickness of the reinforced concrete protective layer must be guaranteed.

[0027] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A floor decking construction process, Features: It includes the following steps: Step 1: Prefabrication of reinforced steel frame floor slabs. Before construction, prepare the galvanized sheet frames of the steel frame floor slabs in the factory workshop, and reserve a matching groove at the hook edge at one end of each galvanized sheet frame, and reserve a hook tooth matching the groove at the hook edge on the other side of the galvanized sheet frame; Step 2: Transportation of steel truss floor decking. According to the actual laying needs, the prefabricated steel frame floor decking is transported to the installation site, and the steel frame floor decking is hoisted and placed in the designated position; Step 3: Laying sequence planning. When laying the steel frame floor deck, the laying of each layer of steel truss formwork should be laid from the starting position to one direction, and the steel truss formwork of each layer should be laid according to the installation construction sequence of the main structure; Step 4: Cleaning before laying: Before laying, clean the debris on the upper side of the steel beam for installing the floor deck, and pre-fix the supporting angle steel on the steel beam at the suspended position where the floor deck is laid; Step 5: Laying of floor decking. When laying reinforced steel frame floor decking, align with the reference line, install the first board, and spot weld its supporting vertical reinforcement to the steel beam; then install other boards in sequence. During the laying process, each board should be marked and checked according to the diagram. If there is any deviation, it should be adjusted immediately; at the same time, when welding bolts between the floor decking and the supporting steel beam during the laying process, it is necessary to lay press-rebound ceramic washers in the reserved holes on the floor decking in advance to avoid welding damage in the reserved holes on the floor decking when fixing the floor decking; Step 6: Tie up the steel bars and install the pipelines. After laying a certain area, set the floor support connection bars, reinforcing bars and negative bars according to the design requirements. The connection bars should be tied up with the steel trusses, and the distribution steel bars should be tied up in time to prevent the lateral instability of the steel trusses. Step 7: During the construction of the side formwork, the side formwork should be straightened by pulling the wire. After proper adjustment, one end of the steel bar is spot welded to the stud and the other end is spot welded to the side formwork to fix the side formwork. The spot welding distance between the bottom of the side formwork and the upper flange of the steel beam is 300mm. Step 8: Concrete pouring. After the side formwork construction is accepted, you only need to pour concrete on the laid reinforced steel frame floor deck to complete the construction of the reinforced steel frame floor deck.

2. A floor deck construction process according to claim 1, Features: In step 2, when transporting the reinforced steel frame floor decking, it is necessary to combine the engineering drawings with the actual situation of the construction site, consider the vehicle transportation length and the actual weight of each floor decking, and consider whether two workers can move the weight to layout, produce according to size, and package according to each area. The weight of each package should not exceed 3 tons. At the same time, when lifting the reinforced steel frame floor decking, the bearing capacity of the steel beam should be considered, and too much weight should not be piled on a certain steel beam.

3. A floor decking construction process according to claim 1, Features: In step 5, when laying the steel frame floor decking, the floor decking is connected by snap-fitting, and the hook connection between the plates should be tight to ensure that there is no leakage when pouring concrete, and at the same time, pay attention to the consistent discharge direction; for the damaged edge tongue and groove of the steel truss plate, use correction tools to correct it before installation to ensure that the connection between the tongue and groove is firm.

4. A floor decking construction process according to claim 1, Features: In the step 5, when laying the steel frame floor decking at the column corners and the floor edge (irregular shape), when the whole board cannot be placed, the truss board can be cut, and the cutting size must be checked and verified before cutting; at the end of the span, if the truss board width is less than 600mm, the truss board can be cut along the length direction of the truss. After cutting, there should be 1 or 2 steel trusses on the board, and the steel trusses must not be cut off.

5. A floor decking construction process according to claim 1, Features: In the step 5, when laying the steel frame floor deck, after the floor deck is in place, the vertical steel bars at its ends should be spot welded to the upper flange of the steel beam immediately, and the bottom formwork should be spot welded to the upper flange of the steel beam along the width of the plate by manual arc welding, with a spacing of no more than 300 mm.

6. A floor deck construction process according to claim 1, Features: In step 5, when two adjacent steel floor decks are clamped and fixed, it is necessary to ensure that the grooves and hook teeth reserved on the steel floor deck are aligned.

7. A floor deck construction process according to claim 1, Features: The construction sequence of step 6 during construction is: tying of support connection steel bars - tying of reinforcement steel bars at the opening edge and column edge - tying of distribution steel bars.

8. A floor deck construction process according to claim 1, Features: In step 6, during construction, the floor support connecting bars and negative bars need to be placed according to the requirements of the design drawings, and the connecting bars should be firmly tied to the steel truss steel bars.

9. A floor deck construction process according to claim 1, Features: During the construction in step 6, it is also necessary to set the openings and column side reinforcement steel bars according to the quantity, model and position of the design drawings.

10. A floor deck construction process according to claim 1, Features: During the construction of step 6, the distribution reinforcement perpendicular to the truss direction should be laid, and the lower layer of steel bars should be laid first, and the lower layer of distribution steel bars should be placed on the upper surface of the lower chord of the steel truss, and tied firmly to the lower chord steel bars; after the lower layer of steel bars are laid, the pipelines should be laid and installed immediately. The pipelines laid in the plate should be made of materials with good flexibility (it is recommended not to use materials such as galvanized steel pipes), and multiple pipelines should be avoided as much as possible. Small-diameter pipelines should be used for dispersed perforation and pre-embedding; the electrical junction box can be reserved and pre-embedded, and it can be fixed on the galvanized plate in advance, and small holes below p30 should be drilled. The drilling should avoid deformation of the truss plate, affecting the appearance or causing leakage; after the pipeline is installed, the upper layer of distribution steel bars should be laid, and the upper layer of distribution steel bars should be placed on the lower surface of the upper chord of the steel truss and tied firmly to the upper chord steel bars; if it is difficult to place it under the upper chord in actual construction, the steel bars can be placed on the upper chord with the consent of the designer and the owner, but at the same time, the thickness of the steel slab and the thickness of the reinforced concrete protective layer must be guaranteed.