Method for installing and constructing submarine cable between sea and land

Skipping and offshore boost stations are solved by installing floats and rollers on the submarine cable to reduce slip resistance and traction energy consumption, and using central fixtures and bending limiters on the offshore boost station side to prevent excessive bending of the submarine cables. The damage to the submarine cable caused by the bottom side erosion achieves efficient installation and extended service life of the submarine cable.

CN119050905AActive Publication Date: 2024-11-29GUANGDONG UNIV OF TECH +2

Patent Information

Application Number
CN202411224291.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-03
Publication Date
2024-11-29
Estimated Expiration
2044-09-03

AI Technical Summary

Technical Problem

During the installation and construction of submarine sea cables between the offshore booster station and the onshore switch station, the submarine cable slip resistance is large, which is easy to scratch the submarine cables. In addition, the bottom side of the offshore booster station is likely to form a erosion pit, causing the submarine cable to suspend and shake, which increases the number of Tension causes damage to the submarine cable.

Method used

After checking the site at sea, use a heat-shrink cap to seal the sea cable head, and lay a traction wire to connect the sea cable head at low tide. The floating ball is tied every 1-3m on the sea cable, and below the sea cable Set the rollers 3-4m apart to make the submarine cable float on the water surface, reducing slip resistance and traction energy consumption; install rollers and floats on land, and remove the floats and rollers after the submarine cable head is moved to the switch station tower; Install central fixtures and bending limiters on the offshore boost station side to prevent excessive bending of the submarine cable.

Benefits of technology

It effectively reduces the slip resistance and traction energy consumption of submarine cables, prevents scratches of submarine cables, and prevents excessive bending of submarine cables on the side of offshore booster stations, extending the service life of submarine cables.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119050905A_ABST
    Figure CN119050905A_ABST
Patent Text Reader

Abstract

The invention discloses a sea-land submarine cable installation construction method, which belongs to the technical field of submarine cable installation construction, comprises a submarine cable laying process of a starting end land switching station, and specifically comprises the following steps: step 1, checking a sea landing in-place point; 2, the ship is in place; step 3, packaging the submarine cable head; 4, laying a traction steel wire; 5, submarine cable head landing construction is conducted, specifically, a traction winch and an electric submarine cable disc on the construction ship are started, the submarine cable on the electric submarine cable disc is unwound while the traction winch draws, in the submarine cable unwinding and traction process, floating balls are bound on the submarine cable every 1-3 m, and idler wheels are arranged below the submarine cable every 3-4 m; 6, moving the submarine cable head to the switching station tower; and 7, moving the submarine cable head to the switching station tower and fixing the submarine cable. In the submarine cable laying process of the onshore switching station at the starting end, floating balls and rollers are arranged on the submarine cables, the submarine cable sections on the sea float on the sea surface to be prevented from making contact with the seabed, when the submarine cables move to the land, the rollers make contact with the land, sliding resistance is reduced, traction energy consumption is reduced, the submarine cables are protected, and the service life of the submarine cables is prolonged. And the submarine cable is prevented from being scratched in the sliding process.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of submarine cable installation and construction, in particular to a method for installing and constructing a submarine cable between sea and land. Background Art

[0002] At present, the following problems exist in the installation and construction of submarine cables between offshore booster stations and onshore switch stations: First, in the process of pulling the submarine cable head from the construction ship at sea to the land, since the submarine cable is very heavy, weighing about 125.7 kg per meter, the submarine cable will slide forward along the seabed and land, which not only has large resistance and large traction energy consumption, but also sometimes scratches the submarine cable during the sliding process. In the prior art, when the submarine cable head reaches the land, the submarine cable head is placed on the pulley. However, in the submerged area of ​​the sea surface, the submarine cable has already landed and slid along the bottom of the submerged area, and the seabed surface in the submerged area is even more It is easy to scratch the submarine cable, and the onshore switch station is still a long distance away from the sea water. If a section of the submarine cable on land is not in contact with the ground, multiple pulleys must be equipped on land. Since the submarine cable is very heavy, it takes a lot of manpower and labor to arrange multiple pulleys on the submarine cable. Secondly, the bottom side of the offshore booster station is impacted by sea water, and scour pits are easily formed near the pile foundation of the offshore booster station. The end of the J-tube is often washed out, causing the submarine cable at this location to be suspended in the air. Then, with the back-and-forth movement of the ocean current, the cable will shake, causing the tension of the submarine cable to increase, leading to damage to the submarine cable. Summary of the invention

[0003] The purpose of the present invention is to provide a method for installing and constructing a submarine cable between sea and land. In the process of laying the submarine cable at the onshore switch station at the starting end, the present invention not only reduces the sliding resistance and reduces the traction energy consumption, but also protects the submarine cable to avoid scratching the submarine cable during the sliding process.

[0004] In order to solve the above technical problems, the technical solution adopted by the present invention is: A method for installing and constructing a submarine cable between sea and land includes a submarine cable laying process at a starting land switch station, specifically comprising the following steps: Step 1: Check the landing site at sea: Check the landing site at sea to ensure that there are no sharp protrusions on the seabed surface at the landing site to ensure the safety of the submarine cable construction ship landing on the beach; Step 2: Ship positioning: Drive the construction ship carrying the submarine cable to the offshore landing position close to the beach, and make one side of the construction ship face the onshore switch station. With the assistance of the DGPS positioning system, accurately drop the positioning anchor to fix the construction ship. Step 3: Sealing the submarine cable head: Use a heat shrink cap to seal the submarine cable head and wrap it with waterproof tape; Step 4: Laying the traction wire: Connect the traction wire to the traction net on the cable head. At low tide, lay the other end of the traction wire from the ship's side to the shore landing point and connect it to the traction winch pre-installed on land. Step 5: Landing of the submarine cable head: Start the traction winch and the electric submarine cable drum on the construction ship. The submarine cable on the electric submarine cable drum is unwound while the traction winch is pulling. During the unwinding and pulling process of the submarine cable, a buoy is tied to the submarine cable every 1-3m, and rollers are set every 3-4m under the submarine cable. Under the action of the buoy, the submarine cable floats on the water surface, and the rollers touch the ground when the submarine cable lands; Step 6: The submarine cable head moves toward the switch station tower: When the submarine cable head moves, the buoy on the submarine cable is removed, and when it reaches the switch station tower, the roller on the submarine cable is removed; Step 7: Move the submarine cable head to the switch station tower and fix the submarine cable: After the submarine cable head passes through the protective casing, the staff sets up scaffolding around the tower. After the submarine cable head climbs up the switch station tower from the outer side of the switch station tower, a clamp is installed to fix the submarine cable to the switch station tower. The protective casing is located at the side bottom of the switch station tower.

[0005] Furthermore, in step 2, the diameter of the electric submarine cable drum on the construction vessel is 27 meters. The electric submarine cable drum is driven by 6 variable frequency motors distributed around the electric submarine cable drum. The electric submarine cable drum can carry 6,000 tons of submarine cable at a time, and the length of the submarine cable is 30-40 km.

[0006] Furthermore, before the submarine cable laying process at the starting onshore switch station, a transfer and cable connection process is also included, and the steps of the transfer and cable connection process are as follows: S1. Before the transfer and cable connection, the performance of the submarine cable is tested in the submarine cable factory; S2. The construction ship is moored at the submarine cable factory dock, and the ship position is adjusted and fixed so that the cable drum center of the construction ship is aligned with the cable transmission rack center of the submarine cable manufacturer; S3. The submarine cable is transported to the construction ship along the trestle, and the staff ties a steel rope net on the submarine cable head. After the submarine cable head passes through the cable transmission rack on the construction ship, it is towed into the electric submarine cable drum. Before winding, a 5m length of the submarine cable head is reserved in the electric submarine cable drum to facilitate the submarine cable testing; S4. The electric turntable is started, and the cable is collected by self-rotation. The transfer and cable connection speed is controlled within 600m / h; S5. After the transfer and cable connection is completed, the performance of the submarine cable is re-tested to confirm that various performance indicators meet the engineering design requirements.

[0007] Furthermore, after the submarine cable laying process of the onshore switch station at the starting end is completed, the submarine cable burying process and the submarine cable laying process of the terminal offshore booster station are carried out in sequence.

[0008] Furthermore, the process of laying a submarine cable includes the following steps: S100, placing a laying machine; S200, submarine cable laying construction: the anchor boat sets the traction anchor on the seabed in front of the construction ship according to the DGPS positioning in advance along the cable laying route, the construction ship is provided with a driving winch, one end of the traction wire rope on the driving winch is tied to the traction anchor in the sea, the driving winch is started, the traction wire drives the construction ship to move, the construction ship drives the laying machine to move, and the high-pressure water pump on the laying machine is started, the high-pressure water pump sucks seawater, and the water supply hose supplies water to the hydraulic plow of the laying machine The hydraulic plow cuts the seabed soil into grooves along the cable burying path through hydraulic jets, and places the submarine cable in the grooves. The sled at the rear of the burying machine smoothes the grooves to bury the submarine cable; S300, real-time detection of burying route trajectory: During the cable burying process, the construction ship command group monitors the real-time coordinates of the cable burying, the underwater posture of the burying machine and the burying depth of the cable through the cable burying navigation and positioning system and the burying depth monitoring system. The burial depth from the outer edge of the armored submarine cable to the seabed mud surface of this section is not less than 3 meters; S400, after the submarine cable burying process is completed, the burying machine is recovered.

[0009] Furthermore, in step S100, the process of launching the embedding machine is as follows: first, the submarine cable is passed through the cable guide cage and then placed into the abdominal cavity of the embedding machine, the embedding machine is lifted by a crane and suspended above the water surface, and the high-pressure water pump and the water supply hose of the embedding machine are connected; then, the embedding machine and the submarine cable are gently dropped into the water, while keeping the embedding machine level.

[0010] Furthermore, in step S300, the inclination sensor, attitude sensor, ground contact sensor and water depth sensor of the burying monitoring system are used to detect the current attitude of the burying machine on the seabed and the water depth at that time; the electronic compass and DGPS positioning system of the burying monitoring system are used to detect the current ship position and the position of the submarine cable on the seabed; after the receiver receives the information sent by the transmitter, it determines the relative position of the burying machine and the construction ship through computer system processing, and displays the actual laying route trajectory of the submarine cable on the screen.

[0011] Furthermore, in step S400, when the construction vessel is laying the cable near the booster station platform, the construction speed is slowed down, and attention is paid to the remaining length of the submarine cable in the electric turntable at all times. Preparation work before laying the submarine cable is performed, and DP positioning is changed to anchor positioning. Anchor boat is used to cooperate with the construction vessel to drop anchor and fix the ship's position, and the operation of recovering the burying machine is started.

[0012] Furthermore, the submarine cable laying process of the terminal offshore booster station includes the following steps: the cable laying machine on the construction ship pulls the submarine cable through the detent frame, and the submarine cable unwound from the electric cable drum is placed on the deck of the construction ship in an 8-shaped coil; when the unwound submarine cable reaches the laying length of the submarine cable terminal, the submarine cable is cut on the construction ship; the submarine cable head formed after cutting is sealed with a heat shrink cap and wrapped with waterproof tape, and a center clamp and a bending limiter are installed at a predetermined position of the submarine cable; a diver underwater checks the J-tube inlet on the offshore booster station. If the J-tube inlet has been silted up, an air sludge suction device is used to flush out enough space at the J-tube inlet position; the diver pulls the traction winch on the construction ship to the traction winch. One end of the steel wire is inserted from the lower end of the J-tube, and the traction steel wire is passed through the upper end of the J-tube and passes around the guide pulley on the gantry to connect with the submarine cable head on the construction ship; start the traction winch, and adjust the traction speed according to the on-site conditions until the submarine cable head passes through the J-tube and moves upward to the offshore booster station, leaving enough design margin for the submarine cable. At this time, the guide cone on one side of the center clamp is inserted and stuck in the lower end of the J-tube, and the lower section of the bend limiter is located on the seabed. The bend limiter is in a static free bending state, which can effectively protect the submarine cable and ensure its bending radius to avoid damage to the submarine cable caused by excessive bending; finally, fix the submarine cable on the bracket of the offshore booster station to complete the laying of the submarine cable terminal on the offshore booster station side.

[0013] Furthermore, in the submarine cable laying process of the terminal offshore booster station, the installation method of the center clamp and the bending limiter is as follows: 1) Determine the installation position of the center clamp on the submarine cable according to the position of the J-tube on the booster station side and the required submarine cable margin, and mark it on the submarine cable; 2) Install the middle clamp at the marked position. The middle clamp is a Haversian structure. Hold the two halves of the middle clamp around the submarine cable and align them. Tighten the bolts. The torque range of the bolts is 70-80N·m. 3) Install the tapered rings on both sides of the middle fixture, making sure the angles of the tapered rings are correct; 4) Install the guide cone on the side of the middle fixture that is closer to the cable head, and tighten the bolts. The torque range of the tightening bolts is 70-80N·m. Connect the guide cone and the middle fixture with screws; 5) Install the connecting shaft on the other side of the middle fixture, hold the submarine cable, and tighten the bolts; sacrificial anode cathodic protection blocks are provided on both sides of the middle fixture, and the sacrificial anode cathodic protection blocks are used to ensure that the central fixture will not be corroded for 25 years; 6) Install the bend limiter on the submarine cable. The bend limiter is a Haversian structure. Hold the two halves of the bend limiter around the submarine cable and align them. Tighten the bolts with a torque of 150-200 N·m and connect the bend limiter to the connecting shaft.

[0014] The beneficial effects of the present invention are: In the process of laying the submarine cable at the onshore switch station at the starting end, the present invention arranges buoys and rollers on the submarine cable during the process of pulling the submarine cable head to the land, so that the submarine cable section at sea floats on the sea surface to avoid contact with the seabed. When the submarine cable moves to the land, the rollers are in contact with the land, which not only reduces the sliding resistance and the traction energy consumption, but also protects the submarine cable to avoid scratching the submarine cable during the sliding process.

[0015] In particular, the present invention carries out roller installation on board. During the process of unwinding and pulling the submarine cable, the submarine cable is at a certain height from the deck of the ship. The roller is installed while the submarine cable is moving. This not only improves the installation efficiency, but also allows workers to install the submarine cable without lifting it, greatly reducing the workload. Moreover, before the submarine cable lands, it has already begun to slide along the seabed surface in the shallow water area of ​​the seaside using rollers, which can provide good protection for the submarine cable.

[0016] In the submarine cable laying process of the offshore booster station, the present invention installs a center clamp and a bend limiter on the submarine cable at the entrance of the J-tube to prevent the submarine cable from excessive bending, which can effectively avoid damage to the submarine cable. The bend limiter is made of polyurethane and other materials with high hardness, high strength and seawater corrosion resistance. The material density is small, which meets the requirement of no additional weight on the submarine cable underwater, and the tensile strength is not less than 40MPa. The bend limiter can withstand 8t lateral pressure, and the product service life is not less than 30 years. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a flow chart of the submarine cable laying process of the starting land switch station of the present invention; Figure 2 This is a state diagram of the submarine cable laying and installation of the terminal offshore booster station of the present invention; Figure 3 A state diagram of the central clamp and the bending limiter of the present invention after installation is completed; Figure 4 It is a schematic structural diagram of the roller, support frame and clamp of the present invention. DETAILED DESCRIPTION

[0018] In order to enable those skilled in the art to better understand the technical solution of the present invention, the present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments. It should be noted that the embodiments of the present application and the features therein can be combined with each other without conflict.

[0019] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper surface", "lower surface", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "forward", "reverse", "axial", "radial", "circumferential" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.

[0020] like Figure 1 As shown, a method for installing and constructing a submarine cable between sea and land includes a submarine cable laying process at a starting land switch station, specifically including the following steps: Step 1: Check the offshore landing site: Check the offshore landing site to ensure that there are no sharp protrusions on the seabed surface at the landing site to ensure the safety of the submarine cable construction ship landing on the beach.

[0021] Step 2, ship positioning: drive the construction ship carrying the submarine cable to the offshore landing position near the beach, and make one side of the construction ship face the onshore switch station, and accurately drop the positioning anchor with the assistance of the DGPS positioning system to fix the construction ship; the diameter of the electric submarine cable drum on the construction ship is 27 meters, and the electric submarine cable drum is driven by 6 variable frequency motors distributed around the electric submarine cable drum. The electric submarine cable drum can carry 6,000 tons of submarine cable at a time, and the length of the submarine cable is 30-40km.

[0022] Step 3: Sealing of submarine cable head: Use heat shrink cap to seal the submarine cable head and wrap it with waterproof tape.

[0023] Step 4: Laying the traction wire: Connect the traction wire to the traction net on the cable head. At low tide, lay the other end of the traction wire from the ship's side to the shore landing point and connect it to the traction winch pre-installed on land.

[0024] Step 5, submarine cable head landing construction: start the traction winch and the electric submarine cable drum on the construction ship. The submarine cable on the electric submarine cable drum is unwound while the traction winch is towing. During the unwinding and traction process of the submarine cable, a buoy is tied to the submarine cable every 1-3m, and rollers are set every 3-4m under the submarine cable. Under the action of the buoy, the submarine cable floats on the water surface, and the rollers touch the ground when the submarine cable lands.

[0025] like Figure 4As shown, specifically, the roller 14 is a universal roller, and two of them are installed at the bottom of the support frame 15. A clamp 16 is fixed on the top of the support frame 15. The clamp 16 is clamped and fixed on the submarine cable by screws 17. An elastic pad is provided between the clamp 16 and the submarine cable, which helps the clamp 16 to clamp the submarine cable.

[0026] On the deck of the construction ship, a translation conveyor belt is provided along the direction of the unwinding movement of the submarine cable. The moving speed of the translation conveyor belt is consistent with the moving speed of the submarine cable. The staff stands on the translation conveyor belt to install the universal roller and the floating ball. Multiple staff members take turns to install the rollers at various installation positions on the submarine cable. The present invention installs rollers on the ship. During the unwinding and traction process of the submarine cable, the submarine cable is at a certain height from the deck on the ship. The submarine cable is installed while the roller is moved, which not only improves the installation efficiency, but also the staff does not need to lift the submarine cable to install it, which greatly reduces the labor. In addition, before landing, the submarine cable has begun to slide along the seabed surface of the shallow water area by the sea using rollers, which can play a good protective role for the submarine cable.

[0027] Step 6: The submarine cable head moves toward the switch station tower: When the submarine cable head is moving, the buoy on the submarine cable is removed, and when it reaches the switch station tower, the roller on the submarine cable is removed.

[0028] Step 7: Move the submarine cable head to the switch station tower and fix the submarine cable: After the submarine cable head passes through the protective casing, the staff sets up scaffolding around the tower. After the submarine cable head climbs up the switch station tower from the outer side of the switch station tower, a clamp is installed to fix the submarine cable to the switch station tower. The protective casing is located at the side bottom of the switch station tower.

[0029] In the process of laying the submarine cable at the onshore switch station at the starting end, the present invention arranges buoys and rollers on the submarine cable during the process of pulling the submarine cable head to the land, so that the submarine cable section at sea floats on the sea surface to avoid contact with the seabed. When the submarine cable moves to the land, the rollers are in contact with the land, which not only reduces the sliding resistance and the traction energy consumption, but also protects the submarine cable to avoid scratching the submarine cable during the sliding process.

[0030] A method for installing and constructing a submarine cable between sea and land, which includes a transfer and cable splicing process before the submarine cable laying process at the starting land switch station, and the steps of the transfer and cable splicing process are as follows: S1, before the transfer and cable splicing, the performance of the submarine cable is tested in the submarine cable factory; S2, the construction ship is moored to the submarine cable factory dock, and the ship position is adjusted and fixed so that the cable drum center of the construction ship is aligned with the cable transmission rack center of the submarine cable manufacturer; S3, the submarine cable is transported to the construction ship along the trestle, and the staff ties a steel rope net on the submarine cable head, and after the submarine cable head passes through the cable transmission rack on the construction ship, it is towed into the electric submarine cable drum, and before winding, a 5m length of the submarine cable head is reserved in the electric submarine cable drum to facilitate the submarine cable testing; S4, the electric turntable is started, the cable is self-rotated and collected, and the transfer and cable splicing speed is controlled within 600m / h; S5, after the transfer and cable splicing is completed, the performance of the submarine cable is re-tested to confirm that various performance indicators meet the engineering design requirements.

[0031] After the submarine cable laying process of the onshore switch station at the starting end is completed, the submarine cable burying process and the submarine cable laying process of the terminal offshore booster station are carried out in sequence.

[0032] The process of laying the submarine cable comprises the following steps: S100. Launching the burying machine: The process of launching the burying machine is as follows: first, pass the submarine cable through the cable guide cage and place it into the abdominal cavity of the burying machine, use a crane to lift the burying machine and suspend it on the water surface, connect the high-pressure water pump and the water supply hose of the burying machine; then slowly put the burying machine together with the submarine cable into the water, keeping the burying machine level during the process.

[0033] S200, submarine cable laying construction: The anchor boat sets the traction anchor on the seabed in front of the construction ship according to the DGPS positioning along the cable laying route. The construction ship is equipped with a driving winch. One end of the traction wire rope on the driving winch is tied to the traction anchor in the sea. The driving winch is started, and the traction wire drives the construction ship to move. The construction ship drives the burying machine to move and starts the high-pressure water pump on the burying machine. The high-pressure water pump sucks seawater, and the water hose supplies water to the hydraulic plow of the burying machine. The hydraulic plow cuts the seabed soil into a groove along the submarine cable laying path through hydraulic jetting, and the submarine cable is placed in the groove. The sled at the rear of the burying machine smoothes the groove to lay the submarine cable.

[0034] The transmitter of the burial monitoring system is installed at the tail of the burial machine, the receiver is installed on the construction ship, four ground contact sensors are installed at the four ends of the burial machine sled, three pressure sensors are installed at the outlet of the submarine cable of the burial machine, and the information centralized processing box is installed on the upper part of the sled to avoid damage; the inclination sensor, attitude sensor, ground contact sensor and water depth sensor of the burial monitoring system are used to detect the current attitude of the burial machine on the seabed and the water depth at that time; the electronic compass and DGPS positioning system of the burial monitoring system are used to detect the current ship position and the position of the submarine cable on the seabed; after the receiver receives the information sent by the transmitter, it determines the relative position of the burial machine and the construction ship through computer system processing, and displays the actual laying route trajectory of the submarine cable on the screen; at the same time, the traction direction, burial depth and traction speed are determined according to the force of the three pressure sensors.

[0035] S300, real-time detection of laying route trajectory: During the cable laying process, the construction ship command team monitors the real-time coordinates of the cable laying, the underwater posture of the laying machine and the cable burial depth through the cable laying navigation and positioning system and the burial depth monitoring system. The burial depth from the outer edge of the submarine cable armor to the seabed mud surface of this section is not less than 3 meters.

[0036] S400, after the submarine cable laying process is completed, the laying machine is recovered. Specifically, when the construction ship is laying near the booster station platform, the construction speed is slowed down, and the remaining length of the submarine cable in the electric turntable is always paid attention to. Preparations before the submarine cable is laid are made, and DP positioning is changed to anchor positioning. Anchor boats are used to cooperate with the construction ship to anchor and fix the ship position, and the operation of recovering the laying machine is started.

[0037] In a method for installing and constructing a submarine cable between sea and land, the submarine cable laying process of the terminal offshore booster station includes the following steps: like Figure 2As shown, the cable laying machine on the construction ship 1 pulls the submarine cable through the untwisting frame, and the submarine cable unwound from the electric cable drum is placed on the deck of the construction ship in an 8-shaped coil; when the unwound submarine cable reaches the laying length of the submarine cable terminal, the submarine cable is cut on the construction ship; a heat shrink cap is used to seal the submarine cable head formed after cutting and a waterproof tape is wrapped around it, and a center clamp and a bending limiter are installed at a predetermined position of the submarine cable; a diver checks the inlet of the J-tube 3 on the offshore booster station 2 underwater, and if the inlet of the J-tube 3 has been silted up, an air sludge suction device is used to flush out enough space at the inlet position of the J-tube; the diver inserts one end of the traction wire 7 on the traction winch 6 on the construction ship through the lower mouth of the J-tube, and the traction winch 6 is pulled. The lead wire passes through the upper mouth of the J-tube and passes around the guide pulley 5 on the gantry 4 and is connected to the submarine cable head on the construction ship 1; the traction winch 6 is started, and the traction speed is adjusted according to the on-site conditions until the submarine cable head passes through the J-tube and moves upward to the offshore booster station 2, and sufficient design margin of the submarine cable is left. At this time, the guide cone 9 on one side of the center clamp 8 is inserted and stuck in the lower mouth of the J-tube 3, and the lower section of the bending limiter 10 is located on the seabed. The bending limiter 10 is in a static free bending state, which can effectively protect the submarine cable and ensure its bending radius to avoid damage to the submarine cable caused by excessive bending; finally, the submarine cable is fixed to the bracket of the offshore booster station to complete the laying of the submarine cable terminal on the offshore booster station side.

[0038] like Figure 3 As shown, in the submarine cable laying process of the terminal offshore booster station, the installation method of the center clamp and the bending limiter is as follows: 1) Determine the installation position of the center clamp on the submarine cable according to the position of the J-tube on the booster station side and the required submarine cable margin, and mark it on the submarine cable; 2) Install the middle clamp 8 at the marked position. The middle clamp 8 is a Haversian structure. After the two halves of the middle clamp are held around the submarine cable and aligned, tighten the bolts. The torque range of the bolts is 70-80 N·m. 3) Install the tapered rings 11 on both sides of the middle fixture 8, and make sure the angles of the tapered rings are correct; 4) Install the guide cone 9 on the side of the intermediate clamp 8 on the submarine cable that is closer to the submarine cable head, and tighten the bolts. The torque range of the tightening bolts is 70-80N·m, and connect the guide cone and the intermediate clamp with screws; 5) Install the connecting shaft 12 on the other side of the middle fixture 8, hold the submarine cable, and tighten the bolts; sacrificial anode cathodic protection blocks are provided on both sides of the middle fixture, and the sacrificial anode cathodic protection blocks are used to ensure that the central fixture will not be corroded for 25 years; 6) Install the bend limiter 10 on the submarine cable. The bend limiter is a Haversian structure. After the two halves of the bend limiter hug the submarine cable 13 and align them, tighten the bolts with a torque of 150-200N·m, and connect the bend limiter 10 to the connecting shaft 12. In the submarine cable laying process of the offshore booster station, the present invention installs a center clamp and a bend limiter on the submarine cable at the entrance of the J-tube to prevent excessive bending of the submarine cable, which can effectively avoid damage to the submarine cable. The bend limiter is made of materials such as polyurethane with high hardness, high strength, and seawater corrosion resistance. The material density is small, which meets the requirement of no additional weight on the submarine cable underwater, and the tensile strength is not less than 40MPa. The bend limiter can withstand 8t lateral pressure, and the product service life is not less than 30 years.

[0039] In addition, those skilled in the art may combine and combine the different embodiments or examples and the features of the different embodiments or examples described in this specification without contradiction. Although the embodiments of the present invention have been shown and described above, it is understood that the above embodiments are exemplary and cannot be understood as limiting the present invention. Those skilled in the art may change, modify, replace and modify the above embodiments within the scope of the present invention.

Claims

1. A method for installing and constructing a submarine cable between sea and land, comprising a submarine cable laying process at a starting land switch station, characterized in that: The specific steps include: Step 1: Check the landing site at sea: Check the landing site at sea to ensure that there are no sharp protrusions on the seabed surface at the landing site to ensure the safety of the submarine cable construction ship landing on the beach; Step 2: Ship positioning: Drive the construction ship carrying the submarine cable to the offshore landing position close to the beach, and make one side of the construction ship face the onshore switch station. With the assistance of the DGPS positioning system, accurately drop the positioning anchor to fix the construction ship. Step 3: Sealing the submarine cable head: Use a heat shrink cap to seal the submarine cable head and wrap it with waterproof tape; Step 4: Laying the traction wire: Connect the traction wire to the traction net on the cable head. At low tide, lay the other end of the traction wire from the ship's side to the shore landing point and connect it to the traction winch pre-installed on land. Step 5: Landing of the submarine cable head: Start the traction winch and the electric submarine cable drum on the construction ship. The submarine cable on the electric submarine cable drum is unwound while the traction winch is pulling. During the unwinding and pulling process of the submarine cable, a buoy is tied to the submarine cable every 1-3m, and rollers are set every 3-4m under the submarine cable. Under the action of the buoy, the submarine cable floats on the water surface, and the rollers touch the ground when the submarine cable lands; Step 6: The submarine cable head moves toward the switch station tower: When the submarine cable head moves, the buoy on the submarine cable is removed, and when it reaches the switch station tower, the roller on the submarine cable is removed; Step 7: Move the submarine cable head to the switch station tower and fix the submarine cable: After the submarine cable head passes through the protective casing, the staff sets up scaffolding around the tower. After the submarine cable head climbs up the switch station tower from the outer side of the switch station tower, a clamp is installed to fix the submarine cable to the switch station tower. The protective casing is located at the side bottom of the switch station tower.

2. The method for installing and constructing a sea-to-land submarine cable according to claim 1, characterized in that: In step 2, the diameter of the electric submarine cable drum on the construction ship is 27 meters. The electric submarine cable drum is driven by 6 variable frequency motors distributed around the electric submarine cable drum. The electric submarine cable drum can carry 6,000 tons of submarine cable at a time, and the length of the submarine cable is 30-40 km.

3. The method for installing and constructing a sea-land submarine cable according to claim 2, characterized in that: Before the submarine cable laying process at the onshore switch station at the starting end, a transfer and cable connection process is also included. The steps of the transfer and cable connection process are as follows: S1. Before transfer and cable connection, the performance of the submarine cable is tested in the submarine cable factory; S2. The construction ship is moored at the submarine cable factory dock, and the ship position is adjusted and fixed so that the center of the cable drum of the construction ship is aligned with the center of the cable transmission rack of the submarine cable manufacturer; S3. The submarine cable is transported to the construction ship along the trestle. The staff ties a steel rope net on the submarine cable head, and after the submarine cable head passes through the cable transmission rack on the construction ship, it is towed into the electric submarine cable drum. Before winding, a 5m length of the submarine cable head is reserved in the electric submarine cable drum to facilitate submarine cable testing; S4. The electric turntable is started, and the cable is collected by self-rotation. The transfer and cable connection speed is controlled within 600m / h; S5. After the transfer and cable connection is completed, the performance of the submarine cable is re-tested to confirm that various performance indicators meet the engineering design requirements.

4. The method for installing and constructing a sea-to-land submarine cable according to claim 3, characterized in that: After the submarine cable laying process of the onshore switch station at the starting end is completed, the submarine cable burying process and the submarine cable laying process of the terminal offshore booster station are carried out in sequence.

5. The method for installing and constructing a sea-to-land submarine cable according to claim 1, characterized in that: In the process of laying the submarine cable, The process comprises the following steps: S100, placing a laying machine; S200, submarine cable laying construction: the anchor boat sets the traction anchor on the seabed in front of the construction ship according to the DGPS positioning in advance along the cable laying route; the construction ship is provided with a driving winch, one end of the traction wire rope on the driving winch is tied to the traction anchor in the sea, the driving winch is started, the traction wire drives the construction ship to move, the construction ship drives the laying machine to move, and the high-pressure water pump on the laying machine is started, the high-pressure water pump sucks seawater, the water supply hose supplies water to the hydraulic plow of the laying machine, and the hydraulic plow moves along the sea The cable burying path is cut into a groove in the seabed soil by hydraulic jetting, and the submarine cable is placed in the groove. The sled at the rear of the burying machine smoothes the groove to bury the submarine cable; S300, real-time detection of the burying route trajectory: During the submarine cable burying process, the construction ship command group monitors the real-time coordinates of the submarine cable burying, the underwater posture of the burying machine and the burying depth of the submarine cable through the submarine cable burying navigation and positioning system and the burying depth monitoring system. The burial depth from the outer edge of the armored submarine cable to the seabed mud surface of this section is not less than 3 meters; S400, after the submarine cable burying process is completed, the burying machine is recovered.

6. The method for installing and constructing a sea-to-land submarine cable according to claim 1, characterized in that: In step S100, the process of launching the embedding machine is as follows: first, the submarine cable is passed through the cable guide cage and then placed in the abdominal cavity of the embedding machine, the embedding machine is lifted by a crane and suspended on the water surface, and the high-pressure water pump and the water supply hose of the embedding machine are connected; then the embedding machine and the submarine cable are gently put into the water, and the embedding machine is kept level during the process.

7. The method for installing and constructing a sea-land submarine cable according to claim 3, characterized in that: In step S300, the inclination sensor, attitude sensor, ground contact sensor and water depth sensor of the burial monitoring system are used to detect the current attitude of the burial machine on the seabed and the water depth at that time; the electronic compass and DGPS positioning system of the burial monitoring system are used to detect the current ship position and the position of the submarine cable on the seabed; after the receiver receives the information sent by the transmitter, it determines the relative position of the burial machine and the construction ship through computer system processing, and displays the actual laying route trajectory of the submarine cable on the screen.

8. The method for installing and constructing a sea-to-land submarine cable according to claim 1, characterized in that: In step S400, when the construction vessel is laying the cable near the booster station platform, the construction speed is slowed down, and the remaining length of the submarine cable in the electric turntable is always paid attention to. Preparations are made before the submarine cable is laid, and DP positioning is changed to anchor positioning. Anchor boats are used to cooperate with the construction vessel to drop anchor and fix the ship's position, and the operation of recovering the burying machine is started.

9. The method for installing and constructing a sea-to-land submarine cable according to claim 1, characterized in that: The submarine cable laying process of the terminal offshore booster station includes the following steps: the cable laying machine on the construction ship pulls the submarine cable through the untwisting frame, and the submarine cable unwound from the electric cable drum is placed on the deck of the construction ship in an 8-shaped coil; when the unwound submarine cable reaches the laying length of the submarine cable terminal, the submarine cable is cut on the construction ship; the submarine cable head formed after cutting is sealed with a heat shrink cap and wrapped with waterproof tape, and a center clamp and a bending limiter are installed at a predetermined position of the submarine cable; a diver underwater checks the J-tube inlet on the offshore booster station. If the J-tube inlet has been silted up, an air sludge suction device is used to flush out enough space at the J-tube inlet position; the diver pulls the traction wire on the traction winch on the construction ship to the bottom of the cable. One end of the cable is inserted from the lower end of the J-tube, and the traction wire is passed through the upper end of the J-tube and bypasses the guide pulley on the gantry to connect with the submarine cable head on the construction ship; start the traction winch, adjust the traction speed according to the on-site conditions, until the submarine cable head passes through the J-tube and moves upward to the offshore booster station, and leave enough design margin for the submarine cable. At this time, the guide cone on one side of the center clamp is inserted and stuck in the lower end of the J-tube, and the lower section of the bend limiter is located on the seabed. The bend limiter is in a static free bending state, which can effectively protect the submarine cable and ensure its bending radius to avoid damage to the submarine cable caused by excessive bending; finally, fix the submarine cable on the bracket of the offshore booster station to complete the laying of the submarine cable terminal on the offshore booster station side.

10. The method for installing and constructing a sea-to-land submarine cable according to claim 9, characterized in that: In the submarine cable laying process of the terminal offshore booster station, the installation method of the center clamp and the bending limiter is as follows: 1) Determine the installation position of the center clamp on the submarine cable according to the position of the J-tube on the booster station side and the required submarine cable margin, and mark it on the submarine cable; 2) Install the middle clamp at the marked position. The middle clamp is a Haversian structure. Hold the two halves of the middle clamp around the submarine cable and align them. Tighten the bolts. The torque range of the bolts is 70-80N·m. 3) Install the tapered rings on both sides of the middle fixture, making sure the angles of the tapered rings are correct; 4) Install the guide cone on the side of the middle fixture that is closer to the cable head, and tighten the bolts. The torque range of the tightening bolts is 70-80N·m. Connect the guide cone and the middle fixture with screws; 5) Install the connecting shaft on the other side of the middle fixture, hold the submarine cable, and tighten the bolts; sacrificial anode cathodic protection blocks are provided on both sides of the middle fixture, and the sacrificial anode cathodic protection blocks are used to ensure that the central fixture will not be corroded for 25 years; 6) Install the bend limiter on the submarine cable. The bend limiter is a Haversian structure. Hold the two halves of the bend limiter around the submarine cable and align them. Tighten the bolts with a torque of 150-200 N·m and connect the bend limiter to the connecting shaft.

Citation Information

Patent Citations

  • Long-distance intertidal zone landing construction process for submarine cable

    CN113964736A

  • Multi-ship abutting type submarine cable protection pipe embankment penetrating method in 360-degree rotating flow field

    CN116093836A

  • Submarine cable crossover processing method

    CN117559297A

  • Offshore Cable Laying Method

    US20140133919A1

  • Offshore Electrical Plant Installation Method and System

    US20140246232A1

Cited By

  • Offshore photovoltaic cluster submarine cable laying method

    CN119482189A

  • Submarine cable and submarine cable protection device integrated operation equipment and operation method

    CN120728459A