Beam section connecting structure for multiple space curve channel steel beams and trial assembly method

By using the connecting structure of inter-section support angle steel and node plate in the space curved trough steel beam of urban viaduct, combined with the trial assembly method of supporting tire frame and hydraulic jack, the problems of high-altitude operation difficulty and measurement accuracy in traditional technology are solved, and the problem of high-altitude operation is achieved. It has higher test assembly accuracy and structural stability, and improved construction efficiency and quality.

CN119061775APending Publication Date: 2024-12-03NANTONG ZHENHUA HEAVY EQUIP MFG +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411269012.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-11
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

In the construction of urban viaducts, the traditional continuous matching production method has difficulty in high altitude operations during the manufacturing and installation of space curve bridges, the measurement accuracy is affected by environmental factors, the accumulated deviation of the entire bridge is large, and the lack of effective support during the trial assembly of the beam section is insufficient. and adjustment methods lead to problems of poor structural stability and installation quality.

Method used

The connecting structure between the sections of the multi-space curved trough steel beams and beams is adopted. By setting up the support angle steel and node plates between the sections, a rigid structural frame is formed. It is precisely lifted and adjusted with the support tire frame and hydraulic jack, and trial assembly in sections and finely performed. Measurement and welding to ensure accurate position and connection accuracy of beam sections.

Benefits of technology

It reduces the difficulty and risks of high-altitude operations, improves the trial assembly accuracy and control of the connecting plate hole group state, ensures the overall linear and structural stability of the bridge, shortens the construction cycle and improves construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119061775A_ABST
    Figure CN119061775A_ABST
Patent Text Reader

Abstract

The invention discloses a multi-space curve channel steel beam inter-section connecting structure and a trial assembly method, and belongs to the technical field of channel steel beam trial assembly. According to the technical scheme, the method comprises the steps of manufacturing single sections, dividing trial assembly turns, arranging measuring points, erecting a jig frame, mounting a beam section on a jig and adjusting a beam, connecting and installing the sections, installing a support base plate, carrying out general measurement to analyze deviation, reserving the last beam section of the turn, and participating in trial assembly of the next turn. Compared with the prior art, the connecting structure and the trial assembly method have the beneficial effects that the connecting structure and the trial assembly method for the multiple space curve groove-shaped steel beam segments are provided, the trial assembly height is reduced, the construction safety is guaranteed, and the trial assembly efficiency is improved through round full-bridge trial assembly, single-round leveling, additional measurement point adding and data substituting into a model for data analysis. Meanwhile, the manufacturing precision is improved, the bridge site adjusting work is less, and the erecting speed is high.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of trial assembly of trough steel beams, and in particular to a connection structure between beam sections of multiple spatial curved trough steel beams and a trial assembly method. Background Art

[0002] With the continuous development of the manufacturing level of prefabricated steel structures, the proportion of steel bridges in bridge construction has continued to increase, especially in urban viaducts, which are increasingly widely used. In particular, urban viaducts, due to their complex shapes and short construction periods, have put forward higher requirements for the manufacturing and installation accuracy of steel structures. The trough beam structure has become the most typical structural form in urban steel viaducts due to its excellent bearing capacity and good bending resistance. In the traditional steel bridge manufacturing process, the manufacturer usually carries out continuous matching and production according to the linear dimensions of the finished bridge without trial installation. Although this method guarantees the continuity and integrity of the structure to a certain extent, it has many shortcomings in practical applications, especially in the manufacturing and installation of spatial curved bridges. For example, there are many high-altitude operations, the measurement accuracy is greatly affected by environmental factors, and the cumulative deviation of the whole bridge is large when the overall curve is trial-installed in rounds. These problems seriously affect the installation quality and construction efficiency of the bridge.

[0003] In the prior art, the manufacture and installation of steel bridges mainly rely on the traditional continuous matching production method. Although this method ensures the continuity of the structure to a certain extent, it has many shortcomings in actual operation. First, when encountering spatial curved bridges, the traditional manufacturing method requires continuous matching and trial assembly, which not only increases the difficulty of high-altitude operations, but also makes the measurement accuracy affected by factors such as ambient temperature. Secondly, due to the lack of an effective trial assembly and adjustment mechanism, the cumulative deviation of the entire bridge is often large, resulting in a lot of adjustment work that still needs to be completed at the bridge position. These problems not only increase the difficulty of construction, but also extend the construction period, seriously affecting the progress and quality of the project.

[0004] More importantly, the existing technology often lacks effective support and adjustment means during the trial installation of beam segments. The beam segments are prone to deformation during trial installation, affecting the stability and accuracy of the overall structure. In addition, during the connection and installation of beam segments, the hole group state of the connecting plate and the docking accuracy of the beam segments are difficult to control, resulting in unstable connection quality. The existence of these problems makes it difficult to ensure the overall linearity and structural stability of the bridge, which in turn affects the service life and safety of the bridge.

[0005] In the process of solving these problems, existing technologies face many challenges. For example, how to reduce the difficulty and risk of high-altitude operations while ensuring the accuracy of beam segment trial installation; how to improve construction efficiency and quality while ensuring the state of the connecting plate hole group and the accuracy of beam segment docking. The existence of these problems not only increases the complexity and difficulty of construction, but also puts higher requirements on the skills and experience of construction personnel. Therefore, existing technologies often fail to achieve ideal results when solving these problems, and a new technical solution is urgently needed to solve these problems. Summary of the invention

[0006] In order to solve the above problems, the present invention proposes a connection structure and assembly method between beam sections of multiple spatial curved trough steel beams, which solves the difficult problems of continuous matching and assembly when encountering spatial curves, the accuracy needs to be improved, there is still a lot of adjustment work at the bridge position, and the accumulated deviation of the entire bridge is large.

[0007] To achieve the above purpose, the technical solution adopted by the present invention is as follows:

[0008] A connection structure between beam sections of multiple spatial curved trough steel beams, including inter-segment support angle steels arranged between four beam sections between two adjacent sections, node plates fixedly arranged on the outer sides of the beam section webs, inter-segment support angle steels arranged between the node plates, and both ends of the inter-segment support angle steels connected to the node plates through connection plates.

[0009] One end of the inter-segment supporting angle steel is fixed to the top node plate by means of a punch and a bolt of the same diameter as shown in the drawing, and the other end is fixed by temporary welding, thereby forming a rigid structural frame between the beam segments to prevent the relative position of the beam segments from changing due to temperature changes.

[0010] A trial assembly method based on a connection structure between beam sections of multiple spatial curved channel steel beams includes the following steps:

[0011] S1: Single segment production

[0012] Assemble on the linear frame according to the drawing dimensions. Check and mark the vertical and horizontal reference lines of the bottom plate and web before the beam section is laid. The reference end is trimmed and cut before leaving the workshop. Figure 2 As shown;

[0013] The node plates outside the webs of the beam sections are all spot welded to fix the initial position;

[0014] S2: Trial assembly round division

[0015] Conduct trial assembly and matching of beam segments in batches according to the completed bridge alignment;

[0016] S3: Measurement point arrangement

[0017] According to the erection of the bridge beam section, the measuring point is set at the end of the beam section. The measuring point is set at the middle position of the thickness of the outer edge of the top and bottom plates and 50mm away from the end. Figure 3 , Figure 4 ;

[0018] S4: Support frame erection

[0019] Set up the supporting tire frame according to the tire frame data;

[0020] like Fig. 9 As shown, the tire support frame includes two brackets, which are connected by steel sections, and a guide plate is provided on the outer side of the top end of the bracket;

[0021] In order to prevent the deformation of the beam segment, the support frame is generally selected at the beam segment transverse diaphragm position during trial installation. The number of support frame points is selected according to the weight of the beam segment, generally 3 to 4 points, one transverse diaphragm point is selected at each end, and 1 to 2 points are selected in the middle as support. In order to prevent the frame from shifting when the beam segment ring is adjusted, the support frames at the near-end positions of the adjacent beam segments are connected and fixed, such as Figure 8 ; Steel plates with a thickness of more than 20mm must be laid on the support frame to prevent uneven ground force from causing ground subsidence. During the trial installation, observation records of the horizontal surface subsidence of the support frame must be made;

[0022] S5: Beam segment placement and beam adjustment

[0023] When the beam segment is put on the tire, the beam segment is hoisted between the guide plates, positioned according to the reference ground sample line combined with the test assembly drawing, and placed on the tire frame without loosening the hook. The hook can be removed only after the tire frame and beam segment position are checked to be qualified;

[0024] Use a jack to adjust the beam section so that the reference point of the beam section reference end coincides with the corresponding reference point of the ground sample, with an error of ±2mm. The allowable deviation of the beam section arch is ≤10mm. The support surface of the tire frame and the bottom plate of the beam section can be added with a pad to make the tire frame and the beam section close to each other to achieve accurate placement of the beam section.

[0025] After a single beam section is installed, the beam is adjusted. Each beam section is set with 4 jacking points. The support points are set according to the requirements of the test assembly drawing. The jacking points and support points are set at the intersection of the bottom plate, web plate and partition. The jacking points are set at the beam section near the ring partition, which can be adjusted according to the on-site position, such as Fig.11 ;

[0026] Place four three-way hydraulic jacks on the corresponding lifting points in advance, and prepare 20 shims of 4mm, 8mm, and 12mm in advance, with a size of 400*400mm.

[0027] To prevent the bottom plate from deformation, place a 30*400*400 lifting pad on the top of the three-way hydraulic jack, prepare 4 pieces in total; the lifting pad must not be in direct contact with the bottom plate, and a rubber pad is placed between the lifting pad and the bottom plate; to ensure that the bottom plate is not damaged, the lifting pad must not be in direct contact with the bottom plate, and a rubber pad is placed between them; check that the three-way jack is normal before use. Fig.12 , and regularly perform equipment maintenance and inspection; observe whether the box beam is deformed during the jacking process;

[0028] Lift the remaining beam sections onto the tires one by one and adjust the beams. Fig.13 ;

[0029] S6: Installation of connections between beam segments

[0030] The installation of the connection between beam segments includes the following steps:

[0031] a) According to the hole group status of the connecting plate, the connecting plates are divided into three categories;

[0032] Type 1: The hole groups of the factory-processed parts of a single node plate are made according to the drawings. The holes of a single node plate are made according to the drawings in the part state, and no matching holes are reserved;

[0033] Type 2: The single segment support angle steel is holed according to the drawing in the part state, and no matching holes are reserved; no matching holes are required in the pre-assembly state;

[0034] Type 3: The hole group drilled at the bridge position is not processed;

[0035] b) After the beam section is assembled and inspected in the workshop, the installation lines of each node plate are marked, and the node plate is initially positioned and assembled in the workshop or before trial installation. Welding is not completed at this time, and the hole spacing deviation of the upper and lower node plate holes of the beam section is controlled within ±3mm;

[0036] c) After the beam segments (4 beam segments) between two adjacent sections are adjusted to their relative positions, install the inter-segment support angle steels and check the coplanar alignment of the 4 node plates. If they are not on the same plane, adjust the node plate inclination angle;

[0037] d) After step c), the beam segments are fixed by supporting angle steels and bolts to form a rigid structural frame;

[0038] e) Complete the plate welding of the node; after welding, press Figure 21 to Figure 25 Measure hole deviation of all holes;

[0039] f) Substitute the hole group deviation data into the model for analysis;

[0040] Compare and analyze the measured values ​​and the model simulation values. If the deviation is controlled within ±4mm, no processing will be done. The bridge position can be adjusted by the deviation of the hole diameter and the bolt diameter.

[0041] S7: Installation of support plate

[0042] In order to ensure the accuracy of the bearing pad, the bearing pad is pre-processed to make the fitting surface between the pad and the beam bottom plate according to the line shape of the beam bottom plate in the trial installation state. After ensuring the fit with the bottom plate, it is welded to the bottom plate, and then the bottom surface is processed according to the data of the bearing bottom plate in the trial installation state.

[0043] S8: After a single round of trial assembly is completed, a general test is carried out, and the general test data is substituted into the model with the ends laid flat to analyze the deviation; at the same time, the data is transformed and brought into the bridge line model of the whole bridge for analysis;

[0044] S9: The last beam section of this round is reserved for the next round of trial installation to ensure that all connection ports are trial installed;

[0045] S10: The trial installation of the remaining beam sections is carried out according to the above steps.

[0046] The beam section reserves a 600mm main weld, which must be longer than the end connection plate to avoid extreme bending of the ring during adjustment, which prevents the connection plate from fitting tightly with the main structure. The main weld is not welded, and is used to adjust the misalignment of the ring during the later trial assembly of the beam section. Figure 1 Adjust the misalignment before welding to ensure the connection quality of the bolted surface.

[0047] In step S1, the margin line and the inspection line are drawn according to the precision control data, and the margin of the end is trimmed and polished according to the margin line using a creeping cutter, and the flatness of the end is controlled at 1 mm / m and does not exceed 3 mm overall;

[0048] When trimming the ends of the beam, because it is impossible to add temporary welds to the product, two 10*150mm bosses are reserved about 100mm outside the main weld L / 5 area. L is the length of the web, which is used for rigid connection when the rings are matched later. Figure 2 .

[0049] In step S2, the curvature of the beam section, the test assembly operation height, and the test assembly site are taken into consideration, and a test assembly round is generally divided into 5 to 6 sections.

[0050] In order to ensure the accuracy of the test assembly, additional measurement points need to be added, such as Figure 5 , 6 , 7, SM-*-* is the product measurement mark point number position, ASM-*-* is the additional measurement mark point number position;

[0051] The overall elevation difference of the beam segment is large. If the bridge position line is used for trial assembly, the cradle height is high, there are many high-altitude operations, and the trial assembly is difficult. In order to reduce the trial assembly height, the beam segment of each round of trial assembly needs to be rotated as a whole with the bottom plate of the end beam segment as the rotation point, so that the bottom plate endpoint of the first beam segment is at the same height as the endpoint of the last beam segment.

[0052] In step S4, the spacing is basically evenly divided. In addition to meeting the support load requirements, the number of tire frames can also effectively control the curve position of the beam section through the tire frame guide plate to achieve accurate placement of the beam section, such as Fig. 9 As shown, in order to increase the integrity of the support frame, the two brackets need to be connected with steel. In order to meet the requirements of machining the support pad at the bottom of the beam section, the height of the support frame is required to meet the lowest point of the beam section ≥1m;

[0053] When the upper part of the support frame is erected, the two data points at the end are determined according to the theoretical data, and then the wire is positioned, and then the support strips are installed. Fig.10 shown.

[0054] When adjusting the beams, avoid the influence of temperature and do it when there is no sunlight.

[0055] The reserved beam segments are used for positioning the beam segments in the next round of trial assembly. If the reserved beam segment data has deviations, the deviation of the first beam segment in this round must be consistent with the deviation of the last segment in the previous round, so as to facilitate the integration of the data of the two rounds in the model.

[0056] Through subsequent trial assembly of beam segments, uniform adjustment should be carried out, and adjustment should not be carried out in one beam segment to avoid extreme bending in the line shape of the finished bridge.

[0057] This scheme divides the entire bridge into multiple sections through segmented trial assembly, and each section is tested separately before being assembled as a whole, reducing the difficulty and cost of the trial assembly.

[0058] A tire frame support is set at the lower part of the beam section to prevent the beam section from deforming during the trial assembly, thereby improving the accuracy of the trial assembly.

[0059] During the trial installation process, the center line, elevation, camber, cross slope and other parameters of the beam section were measured and adjusted to ensure the installation accuracy of the beam section and improve the installation quality.

[0060] According to the hole group status of the connecting plate, the connecting plates are divided into three categories and processed separately to improve the connection efficiency.

[0061] In the trial installation state, the support pads are pre-processed and manufactured according to the linear shape of the bottom plate of the beam section, and then welded after ensuring that they fit well with the bottom plate, which improves the installation accuracy of the support pads.

[0062] The last beam section of this round is reserved for the next round of trial installation to ensure that all connection ports are trial installed and the installation accuracy of all connection ports is ensured.

[0063] A 600mm main weld is reserved at the end of the beam section for later adjustment of the misalignment of the ring mouth, thereby improving the connection quality of the ring mouth.

[0064] Use a crawling cutter to trim the end allowance according to the allowance line and polish it smooth to ensure the flatness of the beam section end.

[0065] Taking into account the curvature of the beam segment, the trial assembly height and the site, the beam segment for each round of trial assembly is rotated as a whole with the bottom plate of the end beam segment as the rotation point, which reduces the height and difficulty of the trial assembly.

[0066] In order to ensure the accuracy of the trial assembly, additional measuring points are added to improve the accuracy of the trial assembly.

[0067] The spacing between the tire frames is basically evenly distributed. In addition to meeting the support load requirements, the number of tire frames can also effectively control the curve position of the beam section through the tire frame guide plate, thereby improving the accuracy of beam section positioning.

[0068] When adjusting the beams, it is necessary to avoid the influence of temperature and do it when there is no sunlight, which improves the accuracy of the adjustment.

[0069] The reserved beam segments will be used in the positioning of the next round of trial installation. If there are deviations in the reserved beam segment data, the first beam segment of this round must be consistent with the deviation of the last segment of the previous round, so as to facilitate the blending of the data of the two rounds in the model and improve the smoothness of the overall line shape.

[0070] By subsequently participating in the trial assembly of beam segments, uniform alignment is performed and alignment is not allowed in one beam segment, thus avoiding extreme bends in the line shape of the finished bridge and improving the aesthetics of the overall line shape.

[0071] Compared with the prior art, the beneficial effects of the present invention are as follows: the present invention provides a connection structure and trial assembly method between beam sections of multiple spatial curved grooved steel beams, which reduces the difficulty and risk of high-altitude operations while ensuring the trial assembly accuracy of beam sections; improves the control capability of the state of the beam section connection plate hole group and the beam section docking accuracy; improves the construction efficiency and quality while ensuring the overall linearity and structural stability of the bridge, and has important practical application value and broad market demand;

[0072] Through rounds of full-bridge trial installation, single-round leveling, additional measurement points, and data analysis by entering the model, not only the trial installation height was reduced to ensure construction safety, but also the production accuracy was improved, the bridge position adjustment work was reduced, and the erection speed was fast;

[0073] The length of the weld reserved by the ring mouth is greater than the length of the connecting plate to avoid extreme bending of the ring seam while ensuring that the connecting plate fits tightly;

[0074] Through the trial installation in rounds, the occupancy of the trial installation site is reduced, the utilization rate of the site is improved, the trial installation cycle is shortened, and time is reserved for the production of a single segment;

[0075] By avoiding sunlight when adjusting the beams, the influence of temperature on manufacturing is effectively avoided and the manufacturing accuracy is improved. BRIEF DESCRIPTION OF THE DRAWINGS

[0076] The accompanying drawings are used to provide further understanding of the present invention and constitute a part of the specification. They are used to explain the present invention together with the embodiments of the present invention and do not constitute a limitation of the present invention.

[0077] Figure 1 Schematic diagram of the excess end weld of an embodiment of the present invention.

[0078] Figure 2 It is a schematic diagram of excess trimming according to an embodiment of the present invention.

[0079] Figure 3 This is a cross-sectional view of the measurement points of an embodiment of the present invention.

[0080] Figure 4 for Figure 3 A partial enlarged view of 1-1.

[0081] Figure 5 This is a top view of the arrangement of measurement points for a portion of a beam section according to an embodiment of the present invention.

[0082] Figure 6 This is a cross-sectional view of the position of the measurement marking points of the product according to the embodiment of the present invention.

[0083] Figure 7 This is a cross-sectional view of the position of additional measurement mark point numbers according to an embodiment of the present invention.

[0084] Figure 8 This is a vertical view of the arrangement of some beam segment cradles in an embodiment of the present invention.

[0085] Fig. 9 It is a cross-sectional view of a tire frame supporting an embodiment of the present invention.

[0086] Fig.10 This is a schematic diagram of positioning the support strips according to an embodiment of the present invention.

[0087] Fig.11 It is a schematic diagram of beam section adjustment according to an embodiment of the present invention.

[0088] Fig.12 for Fig.11 A partial enlarged view of location Ⅰ.

[0089] Fig.13 It is a schematic diagram of the beam section mounting method according to an embodiment of the present invention.

[0090] Fig.14 This is a schematic diagram of the initial positioning of the node plate of the beam segment according to an embodiment of the present invention.

[0091] Fig.15 This is a schematic diagram of the installation of the inter-segment support angle steel and the adjustment of the node plate corresponding to the first type of connecting plate in an embodiment of the present invention.

[0092] Fig.16 This is a schematic diagram of the installation of the inter-segment support angle steel and the adjustment of the node plate corresponding to the second type of connecting plate in an embodiment of the present invention.

[0093] Fig.17 This is a schematic diagram of the installation of the inter-segment support angle steel and the adjustment of the node plate corresponding to the third type of connecting plate in an embodiment of the present invention.

[0094] Fig.18 This is a schematic diagram of the positions of the punch pins used in the inter-segment support angle steel corresponding to the first type of connecting plate in an embodiment of the present invention.

[0095] Fig.19 This is a schematic diagram of the positions of the punch pins used in the inter-segment support angle steel corresponding to the second type of connecting plate in an embodiment of the present invention.

[0096] Fig. 20 This is a schematic diagram of the positions of the punch pins used in the inter-segment support angle steel corresponding to the third type of connecting plate in an embodiment of the present invention.

[0097] Fig.21 It is a schematic diagram of measuring the hole deviations of all holes after welding corresponding to the first type of connecting plate in an embodiment of the present invention.

[0098] Fig. 22 It is a schematic diagram of measuring the hole deviations of all holes after welding corresponding to the second type of connecting plate in an embodiment of the present invention.

[0099] Fig.23 It is a schematic diagram of measuring the hole deviations of all holes after welding corresponding to the third type of connecting plate in an embodiment of the present invention.

[0100] Fig.24 This is a schematic diagram of measuring the hole edge distance in an embodiment of the present invention in which the offset hole distance does not exceed the hole diameter.

[0101] Fig.25 This is a schematic diagram of the case where the offset hole distance exceeds the hole diameter when measuring the hole center distance in an embodiment of the present invention.

[0102] Among them, the accompanying drawings are marked as: 1. inter-segment support angle steel; 2. node plate; 3. connecting plate; 5. supporting tire frame; 501. bracket; 502. steel section; 503. guide plate; 6. jacking point; 7. three-way hydraulic jack; 8. jacking pad; 9. rubber pad. DETAILED DESCRIPTION

[0103] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present invention.

[0104] like Figures 1 to 25 As shown, the present invention provides a connection structure between beam sections of multiple spatial curved trough steel beams, including an inter-segment support angle steel 1 arranged between four beam sections between two adjacent sections, a node plate 2 is fixedly arranged on the outer side of the web of the beam section, the inter-segment support angle steel 1 is arranged between the node plates 2, and the two ends of the inter-segment support angle steel 1 are connected to the node plate 2 through a connecting plate 3.

[0105] One end of the inter-segment support angle steel 1 is fixed to the top node plate 2 with a punch and a bolt of the same diameter as shown in the drawing, and the other end is fixed by temporary welding, so as to form a rigid structural frame between the beam segments to prevent the relative position of the beam segments from changing due to temperature changes.

[0106] A trial assembly method based on a connection structure between beam sections of multiple spatial curved channel steel beams includes the following steps:

[0107] S1: Single segment production

[0108] Assemble on the linear frame according to the drawing dimensions. Check and mark the vertical and horizontal reference lines of the bottom plate and web before the beam section is laid. The reference end is trimmed and cut before leaving the workshop. Figure 2 As shown;

[0109] The node plates outside the webs of the beam sections are all spot welded to fix the initial position;

[0110] S2: Trial assembly round division

[0111] Conduct trial assembly and matching of beam segments in batches according to the completed bridge alignment;

[0112] S3: Measurement point arrangement

[0113] According to the erection of the bridge beam section, the measuring point is set at the end of the beam section. The measuring point is set at the middle position of the thickness of the outer edge of the top and bottom plates and 50mm away from the end. Figure 3 , Figure 4 ;

[0114] S4: Support frame erection

[0115] Set up a support frame 5 according to the frame data;

[0116] like Fig. 9 As shown, the tire support frame 5 includes two brackets 501, the two brackets 501 are connected by a steel section 502, and a guide plate 503 is provided on the outer side of the top end of the bracket 501;

[0117] In order to prevent the deformation of the beam segment, the support frame is generally selected at the beam segment transverse diaphragm position during trial installation. The number of support frame points is selected according to the weight of the beam segment, generally 3 to 4 points, one transverse diaphragm point is selected at each end, and 1 to 2 points are selected in the middle as support. In order to prevent the frame from shifting when the beam segment ring is adjusted, the support frames at the near-end positions of the adjacent beam segments are connected and fixed, such as Figure 8 ; Steel plates with a thickness of more than 20mm must be laid on the support frame to prevent uneven ground force from causing ground subsidence. During the trial installation, observation records of the horizontal surface subsidence of the support frame must be made;

[0118] S5: Beam segment placement and beam adjustment

[0119] When the beam segment is put on the tire, the beam segment is hoisted between the guide plates 503, positioned according to the reference ground sample line combined with the test assembly drawing, and placed on the tire frame without loosening the hook. The hook can be removed only after the tire frame and the beam segment position are checked to be qualified;

[0120] Use a jack to adjust the beam section so that the reference point of the beam section reference end coincides with the corresponding reference point of the ground sample, with an error of ±2mm. The allowable deviation of the beam section arch is ≤10mm. The support surface of the tire frame and the bottom plate of the beam section can be added with a pad to make the tire frame and the beam section close to each other to achieve accurate placement of the beam section.

[0121] After a single beam segment is installed, the beam is adjusted. Each beam segment is provided with 4 jacking points 6. The supporting points are provided according to the requirements of the test assembly drawing. The jacking points and supporting points are all provided at the intersection of the bottom plate, the web plate and the partition plate. The jacking points are all provided at the position of the beam segment close to the ring partition plate, which can be adjusted according to the on-site position, such as Fig.11 ;

[0122] Place four three-way hydraulic jacks 7 on the corresponding lifting points 6 in advance, and prepare 20 shims of 4mm, 8mm, and 12mm in advance, with a size of 400*400mm;

[0123] To prevent the bottom plate from deformation, a 30*400*400 lifting pad 8 is placed on the top of the three-way hydraulic jack 7, and a total of 4 pieces are prepared; the lifting pad 8 must not be in direct contact with the bottom plate, and a rubber pad 9 is placed between the lifting pad 8 and the bottom plate; to ensure that the bottom plate is not damaged, the lifting pad must not be in direct contact with the bottom plate, and a rubber pad is placed between them; before use, check that the three-way jack is normal, such as Fig.12, and regularly perform equipment maintenance and inspection; observe whether the box beam is deformed during the jacking process;

[0124] Lift the remaining beam sections onto the tires one by one and adjust the beams. Fig.13 ;

[0125] S6: Installation of connections between beam segments

[0126] The installation of the connection between beam segments includes the following steps:

[0127] a) According to the hole group status of the connecting plate, the connecting plates are divided into three categories;

[0128] Type 1: The hole groups of the factory-processed parts of a single node plate are made according to the drawings. The holes of a single node plate are made according to the drawings in the part state, and no matching holes are reserved;

[0129] Type 2: The single segment support angle steel is holed according to the drawing in the part state, and no matching holes are reserved; no matching holes are required in the pre-assembly state;

[0130] Type 3: The hole group drilled at the bridge position is not processed;

[0131] b) After the beam section is assembled and inspected in the workshop, the installation lines of each node plate are marked, and the node plate is initially positioned and assembled in the workshop or before trial installation. Welding is not completed at this time, and the hole spacing deviation of the upper and lower node plate holes of the beam section is controlled within ±3mm;

[0132] c) After the beam segments (4 beam segments) between two adjacent sections are adjusted to their relative positions, install the inter-segment support angle steels and check the coplanar alignment of the 4 node plates. If they are not on the same plane, adjust the node plate inclination angle;

[0133] d) After step c), the beam segments are fixed by supporting angle steels and bolts to form a rigid structural frame;

[0134] e) Complete the plate welding of the node; after welding, press Figure 21 to Figure 25 Measure hole deviation of all holes;

[0135] f) Substitute the hole group deviation data into the model for analysis;

[0136] Compare and analyze the measured values ​​and the model simulation values. If the deviation is controlled within ±4mm, no processing will be done. The bridge position can be adjusted by the deviation of the hole diameter and the bolt diameter.

[0137] S7: Installation of support plate

[0138] In order to ensure the accuracy of the bearing pad, the bearing pad is pre-processed to make the fitting surface between the pad and the beam bottom plate according to the line shape of the beam bottom plate in the trial installation state. After ensuring the fit with the bottom plate, it is welded to the bottom plate, and then the bottom surface is processed according to the data of the bearing bottom plate in the trial installation state.

[0139] S8: After a single round of trial assembly is completed, a general test is carried out, and the general test data is substituted into the model with the ends laid flat to analyze the deviation; at the same time, the data is transformed and brought into the bridge line model of the whole bridge for analysis;

[0140] S9: The last beam section of this round is reserved for the next round of trial installation to ensure that all connection ports are trial installed;

[0141] S10: The trial installation of the remaining beam sections is carried out according to the above steps.

[0142] The beam section reserves a 600mm main weld, which must be longer than the end connection plate to avoid extreme bending of the ring during adjustment, which prevents the connection plate from fitting tightly with the main structure. The main weld is not welded, and is used to adjust the misalignment of the ring during the later trial assembly of the beam section. Figure 1 Adjust the misalignment before welding to ensure the connection quality of the bolted surface.

[0143] In step S1, the margin line and the inspection line are drawn according to the precision control data, and the margin of the end is trimmed and polished according to the margin line using a creeping cutter, and the flatness of the end is controlled at 1 mm / m and does not exceed 3 mm overall;

[0144] When trimming the ends of the beam, because it is impossible to add temporary welds to the product, two 10*150mm bosses are reserved about 100mm outside the main weld L / 5 area. L is the length of the web, which is used for rigid connection when the rings are matched later. Figure 2 .

[0145] In step S2, the curvature of the beam section, the test assembly operation height, and the test assembly site are taken into consideration, and a test assembly round is generally divided into 5 to 6 sections.

[0146] In order to ensure the accuracy of the test assembly, additional measurement points need to be added, such as Figure 5 , 6 , 7, SM-*-* is the product measurement mark point number position, ASM-*-* is the additional measurement mark point number position;

[0147] The overall elevation difference of the beam segment is large. If the bridge position line is used for trial assembly, the cradle height is high, there are many high-altitude operations, and the trial assembly is difficult. In order to reduce the trial assembly height, the beam segment of each round of trial assembly needs to be rotated as a whole with the bottom plate of the end beam segment as the rotation point, so that the bottom plate endpoint of the first beam segment is at the same height as the endpoint of the last beam segment.

[0148] In step S4, the spacing is basically evenly divided. In addition to meeting the support load requirements, the number of tire frames can also effectively control the curve position of the beam section through the tire frame guide plate to achieve accurate placement of the beam section, such as Fig. 9 As shown, in order to increase the integrity of the support frame, the two brackets need to be connected with steel. In order to meet the requirements of machining the support pad at the bottom of the beam section, the height of the support frame is required to meet the lowest point of the beam section ≥1m;

[0149] When the upper part of the support frame is erected, the two data points at the end are determined according to the theoretical data, and then the wire is positioned, and then the support strips are installed. Fig.10 shown.

[0150] When adjusting the beams, avoid the influence of temperature and do it when there is no sunlight.

[0151] The reserved beam segments are used for positioning the beam segments in the next round of trial assembly. If the reserved beam segment data has deviations, the deviation of the first beam segment in this round must be consistent with the deviation of the last segment in the previous round, so as to facilitate the integration of the data of the two rounds in the model.

[0152] Through subsequent trial assembly of beam segments, uniform adjustment should be carried out, and adjustment should not be carried out in one beam segment to avoid extreme bending in the line shape of the finished bridge.

[0153] Example 2

[0154] In Example 2, the trial assembly method of the present invention further optimizes the trial assembly and adjustment process of the beam segment, especially in the connection and welding of the beam segment. The specific steps are as follows:

[0155] Single segment production: In the workshop, high-precision equipment is used to cut and weld the beam segments to ensure that the size and shape of each beam segment meets the design requirements.

[0156] Division of trial assembly rounds: The beam segments are matched and trial assembled in batches according to the line shape of the completed bridge, with each batch containing 6 beam segments.

[0157] Measurement point arrangement: additional measurement points are set at the ends of the beam sections to ensure the installation accuracy of each beam section and conduct real-time monitoring during the trial installation.

[0158] Erection of support frame: Use steel sections and guide plates to build support frame to ensure the stability of the beam section during the trial installation, and conduct real-time monitoring during the trial installation.

[0159] Beam segment installation and beam adjustment: Use three-way hydraulic jack to adjust the position of the beam segment to ensure that the reference end of the beam segment coincides with the corresponding reference point of the ground sample, and the error is controlled within ±1mm.

[0160] Connection and installation between beam segments: The beam segments are connected into a rigid structural frame through supporting angle steel and bolts, and the welding and hole group deviation are measured to ensure the stability and accuracy of the connection.

[0161] Installation of bearing pads: Under trial installation, the bearing pads are pre-processed and manufactured according to the linear shape of the bottom plate of the beam section, and welded to the bottom plate to ensure the fitting accuracy between the bearing pads and the bottom plate of the beam section.

[0162] By increasing the number of beam segments in the trial assembly rounds, the trial assembly rounds are reduced and the efficiency of the trial assembly is improved.

[0163] Through the optimized connection and adjustment process, the structural stability is enhanced, the connection between the beam segments is ensured to be more stable, and the structural problems caused by improper connection are reduced.

[0164] Through precise connection and adjustment, the construction quality of the overall structure is improved, ensuring the long-term performance of the bridge.

[0165] Example 3

[0166] In Example 3, the trial assembly method of the present invention further optimizes the trial assembly and adjustment process of the beam segment, especially in the connection and welding of the beam segment. The specific steps are as follows:

[0167] Single-segment production: Add a stress release step during the production process to reduce the deformation of the beam segment during subsequent construction.

[0168] Division of trial installation rounds: Flexibly arrange trial installation rounds according to construction progress and weather conditions to avoid the impact of adverse weather on construction.

[0169] Measurement point arrangement: Add strain sensors at key stress points of the beam section to monitor the stress changes of the beam section during the construction process in real time.

[0170] Support frame erection: Use high-strength composite materials instead of traditional steel to reduce the weight of the support frame and improve its durability.

[0171] Beam segment placement and beam adjustment: A temperature compensation mechanism is introduced during the beam adjustment process to automatically adjust the position of the beam segment according to changes in ambient temperature.

[0172] The stress release step effectively reduces the deformation of the beam section during construction and use.

[0173] The application of strain sensors makes the stress state of the beam section more controllable during the construction process, improving construction safety.

[0174] The use of a high-strength composite material to support the tire frame reduces weight while increasing durability and reducing maintenance costs.

[0175] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.

Claims

1. A connection structure between beam sections of multiple spatial curved trough steel beams, characterized in that: It comprises inter-segment support angle steels (1) arranged between four beam segments between two adjacent sections, node plates (2) are fixedly arranged on the outer sides of the beam segment webs, inter-segment support angle steels (1) are arranged between the node plates (2), and both ends of the inter-segment support angle steels (1) are connected to the node plates (2) via connection plates (3).

2. The connection structure between beam sections of multiple spatial curved channel steel beams according to claim 1 is characterized in that: One end of the inter-segment support angle steel (1) is fixed to the top node plate (2) by means of a punch and bolts of the same diameter as shown in the drawing, and the other end is fixed by temporary welding, thereby forming a rigid structural frame between the beam segments.

3. A trial assembly method for a connection structure between beam sections of multiple spatial curved channel steel beams according to claim 1, characterized in that: The following steps are involved: S1: Single segment production Assemble on the linear frame according to the drawing dimensions. Check and mark the vertical and horizontal reference lines of the bottom plate and web before the beam section is laid down. The reference end is trimmed and cut before leaving the workshop. The node plates outside the webs of the beam sections are all spot welded to fix the initial position; S2: Trial assembly round division Conduct trial assembly and matching of beam segments in batches according to the completed bridge alignment; S3: Measurement point arrangement According to the erection of the bridge beam section, a measuring point is set at the end of the beam section. The measuring point is set at the middle position of the thickness of the outer edge of the top and bottom plates and 50mm away from the end; S4: Support frame erection Setting up a supporting tire frame (5) according to the tire frame data; The tire support frame (5) comprises two brackets (501), the two brackets (501) are connected by a steel section (502), and a guide plate (503) is arranged on the outer side of the top end of the bracket (501); During the trial installation, the support frame is located at the cross diaphragm of the beam section. The number of support frame points is selected according to the weight of the beam section. One cross diaphragm point is selected at each end, and 1 to 2 points are selected in the middle as support. The support frames at the positions near the ends of adjacent beam sections are connected and fixed; a steel plate with a thickness of more than 20 mm must be laid on the support frame to prevent uneven ground force from causing ground settlement. During the trial installation, the horizontal settlement observation records of the support frame should be made; S5: Beam segment placement and beam adjustment When the beam segment is mounted on the tire, the beam segment is hoisted between the guide plates (503), positioned according to the reference ground sample line combined with the test assembly drawing, and placed on the tire frame without loosening the hook. The hook can be removed only after the tire frame and the beam segment position are checked to be qualified; Use a jack to adjust the beam section so that the reference point of the beam section reference end coincides with the corresponding reference point of the ground sample, with an error of ±2mm, and the allowable deviation of the beam section camber is ≤10mm; After a single beam segment is installed, the beam is adjusted. Four lifting points (6) are set for each beam segment. The supporting points are set according to the requirements of the test assembly drawing. The lifting points and supporting points are all set at the intersection of the bottom plate, the web plate and the partition plate. The lifting points are all set at the position of the beam segment close to the ring partition plate and can be adjusted according to the on-site position. Place four three-way hydraulic jacks (7) on the corresponding lifting points (6) in advance, and prepare 20 shims of 4 mm, 8 mm, and 12 mm in advance, with a size of 400*400 mm. A 30*400*400 lifting pad (8) is placed on the top of the three-way hydraulic jack (7), and a total of 4 pieces are prepared; the lifting pad (8) must not be in direct contact with the bottom plate, and a rubber pad (9) is placed between the lifting pad (8) and the bottom plate; Lift the remaining beam sections onto the tires one by one and adjust the beams; S6: Installation of connections between beam segments The installation of the connection between beam segments includes the following steps: a) According to the hole group status of the connecting plate, the connecting plates are divided into three categories; Type 1: The hole groups of the factory-processed parts of a single node plate are made according to the drawings. The holes of a single node plate are made according to the drawings in the part state, and no matching holes are reserved; Type 2: The single segment support angle steel is holed according to the drawing in the part state, and no matching holes are reserved; no matching holes are required in the pre-assembly state; Type 3: The hole group drilled at the bridge position is not processed; b) After the beam section is assembled and inspected in the workshop, the installation lines of each node plate are marked, and the node plate is initially positioned and assembled in the workshop or before trial installation. Welding is not completed at this time, and the hole spacing deviation of the upper and lower node plate holes of the beam section is controlled within ±3mm; c) After the beam segments (4 beam segments) between two adjacent sections are adjusted to their relative positions, install the inter-segment support angle steels and check the coplanar alignment of the 4 node plates. If they are not on the same plane, adjust the node plate inclination angle; d) After step c), the beam segments are fixed by supporting angle steels and bolts to form a rigid structural frame; e) Complete the plate welding of the node; measure the hole deviation of all holes after welding; f) Substitute the hole group deviation data into the model for analysis; Compare and analyze the measured values ​​and the model simulation values. If the deviation is controlled within ±4mm, no processing will be done. The bridge position can be adjusted by the deviation of the hole diameter and the bolt diameter. S7: Installation of support plate When the support pad is in the trial installation state, the pad is pre-processed to make the fitting surface between the pad and the beam bottom plate according to the line shape of the beam bottom plate. After ensuring that it fits the bottom plate, it is welded to the bottom plate, and then the bottom surface is processed according to the data of the support bottom plate in the trial installation state. S8: After a single round of trial assembly is completed, a general test is carried out, and the general test data is substituted into the model with the ends laid flat to analyze the deviation; at the same time, the data is transformed and brought into the bridge line model of the whole bridge for analysis; S9: The last beam section of this round is reserved for the next round of trial installation to ensure that all connection ports are trial installed; S10: The trial installation of the remaining beam sections is carried out according to the above steps.

4. The method for trial assembly of a connection structure between beam sections of multiple spatial curved channel steel beams according to claim 3, characterized in that: A 600mm main weld is reserved for the beam section.

5. The test assembly method of a connection structure between beam sections of multiple spatial curved channel steel beams according to claim 3 is characterized in that: In step S1, the margin line and the inspection line are drawn according to the precision control data, and the margin of the end is trimmed and polished according to the margin line using a creeping cutter, and the flatness of the end is controlled at 1 mm / m and does not exceed 3 mm overall; When trimming the excess at both ends of the beam section, reserve two 10*150mm bosses about 100mm outside the L / 5 area of ​​the main weld, where L is the length of the web.

6. The method for trial assembly of a connection structure between beam sections of multiple space curved channel steel beams according to claim 3, characterized in that: In step S2, a test assembly round is divided into 5 to 6 stages.

7. The test assembly method of a connection structure between beam sections of multiple spatial curved channel steel beams according to claim 3 is characterized in that: The beam segments in each round of trial assembly are rotated as a whole with the bottom plate of the end beam segment as the rotation point, so that the end point of the bottom plate of the first beam segment is at the same height as the end point of the last beam segment.

8. The method for trial assembly of a connection structure between beam sections of multiple spatial curved channel steel beams according to claim 3, characterized in that: In step S4, the height requirement for erecting the support frame is that the lowest point of the beam section bottom is ≥1m; When the upper part of the support frame is erected, the two data points at the end are determined according to theoretical data, and then the wire is pulled for positioning, and then the support strips are installed.

9. The trial assembly method of a connection structure between multiple space curved channel steel beams according to claim 3, characterized in that: When adjusting the beams, avoid the influence of temperature and do it when there is no sunlight.

10. The test assembly method of a connection structure between multiple space curved channel steel beam sections according to claim 3, characterized in that: The reserved beam segments will be used in the next round of trial assembly of beam segment positioning. If there are deviations in the reserved beam segment data, the first beam segment of this round must be consistent with the deviation of the last segment of the previous round to facilitate the reconciliation of the two rounds of data in the model.