Method and structure for heightening pouring type asphalt concrete core wall in low-temperature environment

By adopting the method of heightening the cast asphalt concrete core wall in a low temperature environment, the construction problems of the early cast asphalt concrete core wall dam in a low temperature environment were solved, the anti-seepage effect and stability of the dam were improved, and the construction cycle was shortened. , saves costs and protects the natural environment.

CN119061846APending Publication Date: 2024-12-03CHINA WATER NORTHEASTERN INVESTIGATION DESIGN & RES
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411438572.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-15
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

Early cast asphalt concrete heart wall dams face construction problems in low temperature environments, difficulties in combining old heart walls with new and old heart walls, and problems in connecting waveproof walls.

Method used

The method of cast asphalt concrete core wall elevation under low temperature environments includes dismantling the original dam top structure, cleaning and leveling, wall elevation, softening asphalt, dam body stacking, protective layer installation, through infrared heating and polystyrene hard foam slab and other technologies ensure that the new and old asphalt concrete is combined, and the thickness of the sub-wall is increased layer by layer to evenly disperse the pressure of the wave-proof wall.

Benefits of technology

It improves the anti-seepage area and stability of the dam, shortens the construction cycle, saves construction costs, reduces interference to the natural environment, significantly improves construction quality and efficiency, and is suitable for dam construction in cold areas.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119061846A_ABST
    Figure CN119061846A_ABST
Patent Text Reader

Abstract

The invention discloses a pouring type asphalt concrete core wall heightening method and structure in a low-temperature environment. The asphalt concrete core wall heightening structure is formed through pouring according to the following steps that firstly, a newly-added core wall is prepared; 2, a cleaning and leveling stage; 3, heightening the wall body; 4, softening the asphalt; fifthly, the dam body is piled up; and sixthly, a protection layer is installed. By means of the steps, on the basis of the built pouring type asphalt concrete core wall dam, the core wall is heightened, the newly-poured core wall and the old core wall are fully combined into a whole, and the unique connection mode of the top of the core wall and the wave wall is beneficial to dispersing the pressure of the wave wall to protect the core wall; according to the method, an existing structure can be fully utilized, the investment for heightening the core wall is saved, construction is convenient, construction can be rapidly completed in a low-temperature environment, the anti-seepage area of the dam can be increased, the anti-seepage effect of the whole dam is improved, the dead weight of the dam is increased along with the increase of the height of the core wall, and the stability of the dam is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of water conservancy project water retaining building construction structure, and specifically relates to a method and structure for raising the cast asphalt concrete core wall in a low temperature environment. Background Art

[0002] Cast-in-place asphalt concrete core dam is mainly used in cold and extremely cold regions. It can be constructed in winter. The core wall does not require rolling tools and can be compacted by its own weight.

[0003] With the development of the times, my country's requirements for the functions of water conservancy projects are gradually increasing. The water conservancy projects built in the early days can no longer meet some functional needs at this stage. At the same time, the water conservancy projects built in the early days are also facing the problem of maintenance and reinforcement due to the increase in the operating years. In order to adapt to the needs of the development of water conservancy projects, extend the life of the original dam, improve its safety level, expand the reservoir capacity, etc., it is necessary to heighten and transform the original dam.

[0004] The anti-seepage walls of early cast-type asphalt concrete core wall dams were mostly built with asphalt mortar blocks or asphalt mortar concrete precast blocks into a groove, which was used as a template for pouring asphalt concrete for the core wall. The asphalt concrete was poured in the groove, and the core wall and the blocks on both sides together formed a main and auxiliary wall complex anti-seepage structure.

[0005] Heightening the early cast asphalt concrete core wall will face problems such as low temperature environment during construction, utilization of the old core wall, combination of the new and old core walls, and connection with the wave-breaking wall. Summary of the invention

[0006] The purpose of this section is to summarize some aspects of the embodiments of the present invention and briefly introduce some preferred embodiments. Some simplifications or omissions may be made in this section and the specification abstract and the invention title of this application to avoid blurring the purpose of this section, the specification abstract and the invention title, and such simplifications or omissions cannot be used to limit the scope of the present invention.

[0007] In order to solve the problems existing in the above-mentioned background technology, the present invention adopts the following technical solutions.

[0008] A method for raising the height of a poured asphalt concrete core wall in a low temperature environment comprises the following steps:

[0009] Step 1: In the preparation stage for the new core wall, the original asphalt core wall dam crest structure is dismantled, the filling materials on both sides of the auxiliary wall are excavated to the original dam body demolition elevation, the original core wall and auxiliary wall structure are retained, and a trench is pre-excavated on the top surface of the original core wall for placing the first layer of the new core wall;

[0010] Step 2: During the cleaning and leveling stage, the disturbed and damaged parts of the original asphalt concrete core wall and auxiliary wall during demolition are removed, and the undisturbed and undamaged parts are retained. The bottom of the groove is leveled to ensure the close connection between the contact surface of the new and old core walls;

[0011] Step 3: Raise the wall height by using precast concrete blocks and asphalt mortar to build auxiliary wall blocks on both sides of the core wall, which will serve as the template for pouring the asphalt core wall;

[0012] Step 4: Soften the asphalt. Use infrared heating equipment to heat and bake the entire section of the original asphalt core wall to melt the asphalt on the surface of the core wall, making it easier to remove the aging asphalt and enhance the bond between the new asphalt and the wall. The severely polluted interface between the new and old asphalt will be removed after the contaminated asphalt concrete is softened, and then the new asphalt concrete core wall will be poured to ensure that the new and old asphalt concrete core walls are combined into a whole.

[0013] Step 5: Dam body stacking. Fill the dam body with rocks layer by layer on both sides of the auxiliary wall until it is consistent with the casting elevation of the core wall. Reserve a space within one meter on both sides of the core wall and the auxiliary wall and do not fill it temporarily to avoid machine crushing and damaging the core wall.

[0014] Step 6: Install the protective layer. Use mortar to stick six-centimeter polystyrene rigid foam boards on both sides of the auxiliary wall. In the reserved space, use a combination of manual labor and small machines to fill the transition layer to avoid disturbing the core wall until it is consistent with the elevation of the stone pile on both sides.

[0015] Preferably, repeat steps three to six to raise the dam body layer by layer, and when the construction reaches the bottom elevation of the wave-breaking wall at 1.2 meters, increase the thickness of the auxiliary walls on both sides, so that the pressure of the wave-breaking wall on both sides of the core wall is more evenly distributed, thereby protecting the core wall; a copper sheet waterstop is set between the top of the core wall and the wave-breaking wall, and the gap between the auxiliary wall and the hard foam board is filled with mortar.

[0016] Preferably, in step 1, the height of the retained portion of the central wall and the auxiliary wall structure is 20 to 50 centimeters. This step retains the original central wall and the auxiliary wall structure that can work normally to the greatest extent.

[0017] Preferably, in step 4, dust and debris are removed from the bonding surface between the bonding layers of the new and old asphalt concrete core walls, and water washing is used to achieve the purpose of cleaning when necessary. The bonding surface is kept dry and clean, and the damaged areas are scraped and cleaned.

[0018] Preferably, the poured asphalt concrete construction adopts a construction method of horizontal layering and one-time paving of the entire axis. The paving thickness of the mixture is greater than the layer thickness by two centimeters. The asphalt concrete surface is cleaned before pouring and the material is evenly fed along the core wall. The pouring height of each layer is twenty to fifty centimeters. Vibration is performed simultaneously during pouring, and the pouring temperature is 150 to 160 degrees Celsius. Specifically: the lower limit is taken when the temperature is high, and the upper limit is taken when the temperature is low, so as to reduce transverse joints. Vibration is performed simultaneously during pouring, and the depth reaches the surface of the lower layer until no bubbles are removed and the surface is oily. The pouring temperature is 150 to 160 degrees Celsius.

[0019] Preferably, when not all axes are paved at one time, a formwork is erected at the empty end of the pouring section with a slope of one to three. When the upper and lower layers of asphalt concrete are poured in sections, the staggered distance at their joints should be greater than two meters.

[0020] Preferably, the concrete surface at the connection between the asphalt concrete and the concrete structure is coated with diluted asphalt. After the diluted asphalt dries, a layer of asphalt mastic is applied on its surface, or an asphalt mortar cushion layer about one to two centimeters thick is laid. The paving thickness of the asphalt concrete is reduced at the bank slope connection of the core wall, and small equipment is used to vibrate and compact it.

[0021] An asphalt concrete core wall heightening structure cast by using a casting asphalt concrete core wall heightening method in a low temperature environment, comprising a group of original precast concrete blocks laid in parallel, the original asphalt concrete core walls being filled between the original precast concrete blocks, newly built precast concrete blocks being added to the upper surfaces of the original precast concrete blocks, and the newly built precast concrete blocks being filled with the newly added asphalt concrete core walls, the outer surfaces of the original precast concrete blocks and the newly built precast concrete blocks being provided with filling mortar, and the original precast concrete blocks and the newly built precast concrete blocks being attached with polystyrene rigid foam boards through the filling mortar.

[0022] Preferably, dam body rockfill is piled on both sides of the asphalt concrete core wall, and a newly added gravel transition layer with a spacing of one meter is filled between the dam body rockfill and the newly added asphalt concrete core wall.

[0023] Compared with the prior art, the present invention has the following beneficial effects:

[0024] (1) The present invention aims to raise the height of the old dam wall, thereby increasing the anti-seepage area of ​​the dam and improving the anti-seepage effect of the entire dam, especially when the height of the original core wall is insufficient to meet the anti-seepage requirements. As the height of the core wall increases, the deadweight of the dam increases, which helps to improve the stability of the dam, especially in terms of resisting lateral sliding and overturning. Raising the core wall can better adapt to the terrain and geological conditions. Raising the core wall can reduce the disturbance to the surrounding environment. By raising the existing core wall instead of building a completely new dam, a large amount of construction costs can be saved, including land acquisition, material procurement and construction costs.

[0025] (2) The present invention raises the height of the original cast asphalt concrete core wall and utilizes the existing core wall structure to shorten the construction period. Because some infrastructure and construction preparation work have been completed, raising the existing core wall will cause less interference to the natural environment than building a completely new dam, which helps to protect the ecological balance. In summary, raising the height of the original cast asphalt concrete core wall is an economical, efficient and environmentally friendly engineering solution that can improve the overall performance and safety of the dam.

[0026] (3) The use of cast asphalt concrete core wall construction method does solve the problem of rolling asphalt concrete construction under low temperature conditions to a certain extent. Compared with rolling asphalt concrete, cast asphalt concrete usually has a higher asphalt content, which helps to improve the fluidity and workability of the mixture. Even at lower temperatures, it is easier to achieve uniform paving and dense molding. For low temperature environments, the present invention adopts the insulation measures of a self-made heating and insulation tank to ensure that the asphalt concrete after mixing always maintains the required pouring temperature in the tank, further ensuring the continuity and quality control of the pouring process.

[0027] (4) Due to the good working characteristics of the poured asphalt concrete of the present invention, a large-area paving operation can be completed in a relatively short time, thereby reducing the downtime caused by low temperatures during winter construction and improving the overall project progress. By selecting poured asphalt concrete technology and processes suitable for low-temperature environments, not only can the limitations of traditional rolled asphalt concrete under low-temperature conditions be overcome, but also the construction quality and efficiency can be significantly improved. It is suitable for dam construction and other civil engineering projects in cold regions. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1 It is a typical cross-sectional view after the original asphalt core wall dam top structure is demolished and the filling materials on both sides of the auxiliary wall are excavated to the proposed demolition elevation of the original dam body in the embodiment.

[0029] Figure 2 It is a typical cross-sectional view of the structure after the disturbed and damaged parts of the asphalt core wall are removed in the embodiment.

[0030] Figure 3 It is a typical cross-sectional view of the structure after the auxiliary wall is rebuilt and the core wall is cast to a certain elevation in the embodiment.

[0031] Figure 4 It is a typical cross-sectional view of the structure of the dam after the rockfill is filled to a certain elevation in the embodiment.

[0032] Figure 5 This is a typical cross-sectional view of the structure after the transition material is filled to a certain elevation in the embodiment.

[0033] Figure 6 It is a typical cross-sectional view of the structure after the central wall and the wave-breaking wall are connected in the embodiment.

[0034] The corresponding relationship between the illustrations and component names in the figure is as follows:

[0035] 1. Existing precast concrete blocks; 2. Existing asphalt concrete core wall; 3. Newly built precast concrete blocks; 4. Newly added asphalt concrete core wall; 5. Dam body rockfill; 6. Newly added gravel transition layer; 7. Polystyrene rigid foam board; 8. Filling mortar; 9. Copper sheet waterstop. DETAILED DESCRIPTION

[0036] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are described in detail below in conjunction with the accompanying drawings.

[0037] In the following description, many specific details are set forth to facilitate a full understanding of the present invention, but the present invention may also be implemented in other ways different from those described herein, and those skilled in the art may make similar generalizations without violating the connotation of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed below.

[0038] Secondly, the term "one embodiment" or "embodiment" as used herein refers to a specific feature, structure or characteristic that may be included in at least one implementation of the present invention. The term "in one embodiment" that appears in different places in this specification does not refer to the same embodiment, nor is it a separate or selective embodiment that is mutually exclusive with other embodiments. The present invention provides the following embodiments.

[0039] The following is combined with Figures 1 to 6 To further illustrate the present invention, this embodiment is a cast-type asphalt concrete core wall heightening structure under low temperature environment, including a group of original precast concrete blocks 1 laid in parallel, original asphalt concrete core walls 2 are filled between the original precast concrete blocks 1, new precast concrete blocks 3 are added to the upper surface of the original precast concrete blocks 1, and the new precast concrete blocks 3 are filled with newly added asphalt concrete core walls 4, the outer surfaces of the original precast concrete blocks 1 and the newly added precast concrete blocks 3 are provided with filling mortar 8, and the original precast concrete blocks 1 and the newly added precast concrete blocks 3 are affixed with polystyrene rigid foam boards 7 through the filling mortar 8, dam body rock piles 5 are piled on both sides of the asphalt concrete core wall, and a newly added gravel transition layer 6 with a spacing of one meter is filled between the dam body rock pile 5 and the newly added asphalt concrete core wall 4.

[0040] The structure in this embodiment is based on the existing cast-type asphalt concrete core wall dam, and the core wall is raised. The newly cast core wall and the old core wall are fully combined into a whole. The unique connection method between the top of the core wall and the wave-breaking wall is conducive to dispersing the pressure of the wave-breaking wall to protect the core wall. This method can make full use of the existing structure, save the investment in raising the core wall, and is easy to construct and can be completed quickly in a low temperature environment.

[0041] The construction method includes the following steps:

[0042] Step 1: In the preparation stage of adding a core wall, the original asphalt core wall dam top structure is demolished, the filling materials on both sides of the auxiliary wall are excavated to the original dam body demolition elevation, and the original asphalt concrete core wall 2 and the original masonry concrete prefabricated block 1 structure are retained. Figure 1 As shown; during the demolition process, excessive damage to the core wall and auxiliary wall structure should be avoided.

[0043] Step 2: During the cleaning and leveling stage, the original asphalt concrete core wall 2 and the original prefabricated concrete blocks 1 that were disturbed and damaged during the demolition of the wave-breaking wall are removed, and the parts that have not been disturbed and damaged are retained, such as Figure 2 shown.

[0044] Step 3: Raise the wall height. Use newly built precast concrete blocks 3 and asphalt mortar to build a precast concrete block auxiliary wall of a certain height on both sides of the original asphalt concrete core wall 2. The masonry height should not be greater than 10 cm of the asphalt concrete pouring layer thickness. It is used as a template for pouring the asphalt core wall. After pouring, a new asphalt concrete core wall 4 is formed. Figure 3 As shown; in step 3, the newly built prefabricated concrete block 3 should meet the following requirements:

[0045] a. The strength of the newly built precast concrete blocks 3 should meet the design requirements, and the masonry surface of the precast blocks and the contact surface with the asphalt concrete anti-seepage wall should be roughened and decontaminated.

[0046] b. Newly built precast concrete blocks 3 should be sprayed with diluted asphalt in a dry state and can only be used after the oil in the diluted asphalt has completely evaporated.

[0047] c. The auxiliary wall of precast concrete blocks should be built with asphalt mortar, and the asphalt mortar must be full; the joints on the contact surface with the transition layer gravel should be grouted with cement mortar.

[0048] d. The formwork of the concrete precast block auxiliary wall should be flat, firm, and avoid through-joints. The masonry height should not be greater than ten centimeters of the asphalt concrete pouring layer thickness.

[0049] Step 4: Soften the asphalt. Use infrared heating equipment to heat and bake the entire section of the original asphalt concrete core wall 2 to slightly melt the surface of the original asphalt concrete core wall 2. The severely polluted new and old asphalt bonding surfaces are removed after the polluted asphalt concrete softens. Then, pour the new asphalt concrete core wall 4 to ensure that the new and old asphalt concrete walls are combined into a whole. Figure 3 As shown; the pouring process of step 4 should meet the following requirements:

[0050] a. The pouring asphalt concrete construction should adopt the construction method of horizontal layering and one-time paving of the entire axis. The paving thickness of the mixture should be about two centimeters greater than the layer thickness. The asphalt concrete surface should be cleaned before pouring. The pouring should be evenly fed along the core wall. The pouring height of each layer should be 20 to 50 centimeters. While pouring, use a tamping rod to tamp the edge to a depth that reaches the surface of the lower layer until no bubbles are removed and the surface is oily. The material discharge height should not be greater than one meter, and the warehouse should be closed in time. If the asphalt mixture needs to be vibrated after the warehouse is closed, it should be vibrated until the surface is oily to prevent the asphalt mixture from segregating.

[0051] b. The pouring temperature can be between 150 and 160 degrees Celsius. The lower limit should be taken when the temperature is high, and the upper limit should be taken when the temperature is low. It is advisable to reduce transverse joints. If the entire axis cannot be paved at one time due to special reasons, a formwork should be erected at the empty end of the pouring section. The slope should be one to three. If the upper and lower layers of asphalt concrete are poured in sections, the staggered distance at the joints should be greater than two meters.

[0052] c. Before filling the transition layer, the surface of the asphalt concrete wall should be covered with canvas to prevent contamination of the wall surface.

[0053] d. After pouring asphalt concrete, the surface should be covered to prevent pollution, and it is strictly prohibited to bear external loads.

[0054] e. The concrete surface at the connection between asphalt concrete and concrete structure should be coated with diluted asphalt. After it dries, a layer of asphalt mastic should be applied, or an asphalt mortar cushion layer about one to two centimeters thick should be laid.

[0055] f. The paving thickness of asphalt concrete should be reduced at the bank slope connection part of the wall, and small equipment should be used to compact or vibrate it to make it dense.

[0056] Step 5: dam body stacking. On both sides of the original precast concrete blocks 1 and the newly built precast concrete blocks 3, fill the dam body with rocks 5 layer by layer until the elevation is consistent with the newly added asphalt concrete core wall 4. On both sides of the newly added asphalt concrete core wall 4 and the newly built precast concrete blocks 3, a space within about one meter is reserved for temporary filling to avoid damage to the wall by machine rolling. Figure 4 As shown;

[0057] Step 6: Installation of protective layer: Use mortar to paste 6 cm polystyrene rigid foam board 7 on both sides of the original precast concrete block 1 and the newly built precast concrete block 3; then fill the reserved space with a new gravel transition layer 6 by manual and mechanical methods to avoid disturbing the core wall until it is consistent with the elevation of the dam body rockfill 5 on both sides. Figure 5 As shown;

[0058] Further, repeat the above steps 3 to 6 to make the dam body rise stably and synchronously, wherein the new and old asphalt bonding surfaces in step 4 should be transformed into the interlayer bonding surfaces of the new asphalt concrete; when the construction reaches the bottom elevation of the wave-breaking wall at 1.2 meters, gradually increase the masonry thickness of the newly added asphalt concrete core wall 4 on both sides, such as Figure 6 As shown, the pressure of the wave-breaking wall on both sides of the core wall is more evenly distributed, thereby protecting the wall body; a copper sheet water stop 9 is arranged between the top of the wall body and the wave-breaking wall, and the gap between the newly built concrete prefabricated block 3 and the polystyrene rigid foam board 7 is filled with filling mortar 8.

[0059] The above content is a further detailed description of the present invention in combination with specific implementation methods. It cannot be determined that the specific implementation of the present invention is limited to these descriptions. For ordinary technicians in the technical field to which the present invention belongs, several simple deductions or substitutions can be made without departing from the concept of the present invention, which should be regarded as belonging to the scope of protection determined by the claims submitted for the present invention.

Claims

1. A method for raising the height of a cast asphalt concrete core wall in a low temperature environment, characterized in that: The following steps are included: Step 1: In the preparation stage for adding a new core wall, the original asphalt core wall dam crest structure is dismantled, the filling materials on both sides of the auxiliary wall are excavated to the original dam body demolition elevation, the original core wall and auxiliary wall structure are retained, and a trench is pre-excavated on the top surface of the original core wall; Step 2: During the cleaning and leveling stage, the disturbed and damaged parts of the original asphalt concrete core wall and auxiliary wall during demolition are removed, and the undisturbed and undamaged parts are retained, and the bottom of the trench is leveled; Step 3: Raise the wall, use precast concrete blocks and asphalt mortar to build auxiliary wall blocks on both sides of the core wall; Step 4: Soften the asphalt. Use infrared heating equipment to heat and bake the entire section of the original asphalt core wall to melt the asphalt on the core wall surface. Step 5: dam body stacking, fill the dam body rock layer by layer on both sides of the auxiliary wall until it is consistent with the core wall casting elevation, and reserve space within one meter on both sides of the core wall and the auxiliary wall without filling; Step 6: Install the protective layer. On both sides of the auxiliary wall, use mortar to stick six-centimeter polystyrene rigid foam boards; fill the transition layer in the reserved space until it is consistent with the elevation of the stone piles on both sides.

2. The method for raising the height of a poured asphalt concrete core wall in a low temperature environment according to claim 1, characterized in that: Repeat steps 3 to 6 to raise the dam layer by layer. When the construction reaches the bottom elevation of the wave-breaking wall at 1.2 meters, increase the thickness of the auxiliary walls on both sides so that the pressure of the wave-breaking wall on both sides of the core wall is more evenly distributed. A copper sheet waterstop is set between the top of the core wall and the wave-breaking wall, and the gap between the auxiliary wall and the hard foam board is filled with mortar.

3. The method for raising the height of a poured asphalt concrete core wall in a low temperature environment according to claim 1, characterized in that: Step 1: The height of the remaining part of the central wall and the auxiliary wall structure is 20 to 50 centimeters.

4. The method for raising the height of a poured asphalt concrete core wall in a low temperature environment according to claim 1, characterized in that: In the fourth step, dust and debris are removed from the bonding surface between the bonding layers of the new and old asphalt concrete core walls, and the purpose of cleaning is achieved by washing with water. The bonding surface is kept dry and clean, and the damaged areas are scraped and cleaned.

5. The method for raising the height of a poured asphalt concrete core wall in a low temperature environment according to claim 1, characterized in that: The poured asphalt concrete construction adopts a construction method of horizontal layering and one-time paving of the entire axis. The paving thickness of the mixture is two centimeters greater than the layer thickness. The pouring is evenly fed along the core wall. The pouring height of each layer is twenty to fifty centimeters. Vibration is performed simultaneously during pouring. The pouring temperature is one hundred and five degrees Celsius to one hundred and sixty degrees Celsius.

6. The method for raising the height of a poured asphalt concrete core wall in a low temperature environment according to claim 5, characterized in that: When the non-full axis is paved at one time, a formwork is set up at the empty end of the pouring section with a slope of one to three. When the upper and lower layers of asphalt concrete are poured in sections, the staggered distance at the joints should be greater than two meters.

7. The method for raising the height of a poured asphalt concrete core wall in a low temperature environment according to claim 5, characterized in that: The concrete surface at the connection between the asphalt concrete and the concrete structure is coated with diluted asphalt. After the diluted asphalt dries, a layer of asphalt mastic is coated on the surface. The paving thickness of the asphalt concrete is reduced at the bank slope connection of the core wall and vibrated to make it dense.

8. An asphalt concrete core wall heightening structure cast by using any of the cast asphalt concrete core wall heightening methods in a low temperature environment according to any one of claims 1 to 7, comprising a group of original prefabricated concrete blocks (1) laid in parallel, with original asphalt concrete core walls (2) filled between the original prefabricated concrete blocks (1), characterized in that: A newly built prefabricated concrete block (3) is added to the upper surface of the original prefabricated concrete block (1), and the newly built prefabricated concrete block (3) is filled with a newly added asphalt concrete core wall (4), and the outer surfaces of the original prefabricated concrete block (1) and the newly built prefabricated concrete block (3) are provided with filling mortar (8), and the original prefabricated concrete block (1) and the newly built prefabricated concrete block (3) are attached with a polystyrene hard foam board (7) through the filling mortar (8).

9. The pouring asphalt concrete core wall heightening structure in low temperature environment according to claim 8 is characterized in that: Dam body rockfill (5) is piled on both sides of the asphalt concrete core wall, and a newly added gravel transition layer (6) with a spacing of one meter is filled between the dam body rockfill (5) and the newly added asphalt concrete core wall (4).