Pre-embedded grouting pipe and shield tunnel karst cave treatment method under high-rise building under construction
The cave grouting is carried out on the ground construction platform by embedding the grouting pipe to reinforce the untreated shield tunnel cave, which solves the problems of construction safety and deformation control of shield tunnels under high-rise buildings under construction, and achieves efficient cave reinforcement and Improved construction safety.
Patent Information
- Application Number
- CN202410957716.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-17
- Publication Date
- 2024-12-03
AI Technical Summary
The treatment of shield tunnel caves under high-rise buildings under construction is difficult to ensure the safety of shield tunnel construction and the deformation control requirements of adjacent buildings. The existing technology has limited grouting reinforcement range and poor results.
Pre-embedded grouting pipes, including steel pipes, top, middle and bottom waterproof structures, are used to grout caves on the ground construction platform to reinforce untreated caves to ensure construction safety and reduce the impact on high-rise buildings.
It effectively improves the construction safety of shield tunnels, reduces the impact on high-rise buildings, ensures the quality of cave reinforcement treatment, and solves the problems of limited ground construction conditions and limited treatment range in the cave.
Smart Images

Figure CN119061895A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of shield tunnel construction, and in particular relates to a pre-buried grouting pipe and a method for treating a karst cave in a shield tunnel under a high-rise building under construction. Background Art
[0002] At present, with the continuous improvement of my country's urbanization level and the rapid development of urban rail transit, subway tunnels inevitably pass under a large number of existing or under-construction buildings and structures, and face huge challenges in excavation risk control under complex geological conditions. Among them, karst, as a common geological phenomenon in southern my country, has a great impact on the safety of shield construction, and is prone to quality and safety accidents such as shield machine head drop, shield segment damage, water leakage, karst roof collapse, etc. In severe cases, it causes large ground settlement, endangering the safety of ground buildings.
[0003] The treatment of karst caves in shield tunnels mainly adopts the method of ground grouting reinforcement, which determines the boundary of the karst cave by drilling holes on the ground and uses the holes for grouting filling. However, for the treatment of karst caves under the high-rise buildings under construction that are under the subway tunnel and before the shield construction, since the scope of karst cave treatment during the foundation construction of the high-rise building cannot meet the risk control requirements of shield tunnel construction, the unreinforced karst caves should be further treated before the shield tunneling passes under the high-rise building. At this time, due to the lack of conditions for karst cave treatment on the ground high-rise building structure, the method of grouting in the cave through the shield advance detection hole is generally used on site to reinforce the karst cave. However, due to the limitations of the site conditions in the cave and the grouting process, the scope of grouting reinforcement in the cave is limited and the grouting reinforcement effect is poor, which makes it difficult to ensure the safety of shield tunnel construction and the internal force and deformation control requirements of adjacent buildings.
[0004] Therefore, a new technology is needed to solve the problem in the prior art that the karst cave treatment of the shield tunnel under the high-rise building under construction is difficult to ensure the safety of the shield tunnel construction and the deformation control requirements of the adjacent buildings. Summary of the invention
[0005] In order to solve the above-mentioned problems in the prior art, the present invention provides a pre-buried grouting pipe and a method for treating the karst cave of a shield tunnel under a high-rise building under construction, which has the characteristics of providing ground construction conditions for the karst cave treatment of the shield tunnel at the bottom plate of the high-rise building under construction, and can achieve the effect of maximally ensuring the safety of shield tunnel construction and reducing the impact on high-rise structures.
[0006] The present invention adopts the following technical solutions:
[0007] A pre-buried grouting pipe comprises a steel pipe and a top sealing structure, a middle waterproof structure and a bottom waterproof structure connected to the steel pipe in sequence from top to bottom, wherein the bottom of the steel pipe is filled with concrete;
[0008] The top sealing structure includes a cover plate, which is detachably mounted on the upper end of the steel pipe and is used to seal the upper end of the steel pipe;
[0009] The middle waterproof structure includes a water-stop flange, which is sleeved on the outside of the steel pipe and tightly connected to the outer surface of the steel pipe;
[0010] The bottom waterproof structure includes a waterproof reinforcement layer with a structure approximately in the shape of a funnel. The waterproof reinforcement layer is sleeved on the outer periphery of the steel pipe and is tightly connected to the outer surface of the steel pipe. The maximum size of the lower end of the waterproof reinforcement layer is greater than the maximum size of the upper end.
[0011] As a further improvement of the technical solution of the present invention, the top sealing structure also includes a mounting flange fixed to the outside of the steel pipe, the upper end surface of the mounting flange is flush with the upper end surface of the steel pipe, and the cover plate is located above the mounting flange and is detachably fixedly connected to the mounting flange.
[0012] As a further improvement of the technical solution of the present invention, the middle waterproof structure includes a waterstop flange and a waterstop strip. The waterstop flange is mounted on the outside of the steel pipe and is tightly connected to the steel pipe. The waterstop strip is annular. The upper surface of the waterstop strip is tightly connected to the lower surface of the waterstop flange, and the inner side of the waterstop strip is tightly connected to the outer surface of the steel pipe.
[0013] As a further improvement of the technical solution of the present invention, the longitudinal section of the waterproof reinforcement layer is approximately L-shaped, and the waterproof reinforcement layer includes a cylindrical body and an annular plate fixedly connected in sequence from top to bottom, the lower end of the cylindrical body is tightly connected to the inner circle of the annular plate, and the inner surface of the cylindrical body is tightly connected to the outer surface of the steel pipe;
[0014] The bottom waterproof structure also includes a metal hoop, which is fastened to the outside of the cylindrical body to tightly connect the cylindrical body and the steel pipe;
[0015] The cylindrical body and the annular plate are tightly connected via an annular chamfered structure, and sealant is filled between the chamfered structure and the outer surface of the steel pipe.
[0016] A method for treating a karst cave in a shield tunnel under a high-rise building under construction, using the pre-buried grouting pipe as described above, comprises the following steps:
[0017] S1. Pre-buried grouting pipes: After the concrete cushion layer and waterproof layer of the main structure bottom plate of the high-rise building under construction above the tunnel are completed, when the structural steel bars are tied, several grouting pipes are pre-buried at intervals within the karst treatment range of the shield tunnel, and each pre-buried grouting pipe is fixedly connected to the structural steel bars;
[0018] S2. Karst cave exploration: When the previous exploration points within the shield tunnel karst cave treatment range reveal the presence of karst caves, and the ground has not been treated during the construction of the high-rise building foundation, the exploration points revealing the presence of karst caves are taken as the center, and karst cave exploration drilling is carried out in several pre-buried grouting pipes near each exploration point to determine the horizontal and vertical ranges of the karst caves;
[0019] S3. Grouting and filling of caves: Select some pre-buried grouting pipe holes as grouting holes in the karst cave treatment plane, and select some pre-buried grouting pipe holes as exhaust holes. Use the main structure floor of the high-rise building as a construction platform, and grout the caves through the grouting holes on the main structure floor platform of the high-rise building;
[0020] S4. Grouting effect detection: Use the secondary grouting method to check the cave grouting filling rate, and use the standard penetration method to determine the cave grouting filling density;
[0021] S5. After the grouting filling of the cave is completed, double liquid slurry is used to seal the bottom of the pre-buried grouting pipe of each completed hole to prevent water from bubbling up from below the hole to damage the waterproof layer of the main structure of the building;
[0022] S6. Backfill the micro-expansion waterproof concrete into each pre-buried grouting pipe, and then seal the pipe openings of each pre-buried grouting pipe. After the sealing is completed, restore the base plate structure of the main building structure.
[0023] As a further improvement of the technical solution of the present invention, in step S1, the shield tunnel karst cave treatment range is centered on the tunnel structure outline, extending 3m to the left and right sides and the bottom, and the upper treatment range extends upward to the ground surface. The horizontal cross-section of the treatment range is rectangular.
[0024] As a further improvement of the technical solution of the present invention, in step S2, the process is terminated until the cave detection drilling fails to reveal the cave or reaches the horizontal boundary range of the cave processing to determine the boundary and size of the cave.
[0025] As a further improvement of the technical solution of the present invention, in step S3, some of the cave edge drilling holes or grouting holes also serve as exhaust holes, and the exhaust hole drilling holes are arranged at the top of the cave.
[0026] As a further improvement of the technical solution of the present invention, in step S3, during the grouting filling process of the cave, when the cave is a fully filled cave, a standard penetration test is performed on the filling material, and when the standard penetration number is greater than 10 blows, no filling treatment can be selected, and when the standard penetration number is less than 10 blows, the cave needs to be grouting treated; when the cave is an unfilled cave or a semi-filled cave with a height of less than 3m, cement slurry is used for compaction grouting; when the cave is an unfilled cave or a semi-filled cave with a height greater than or equal to 3m, cement mortar is first used for filling, and then cement slurry is used for compaction grouting.
[0027] As a further improvement of the technical solution of the present invention, in step S3, if the boundary of the cave exceeds the cave treatment range, before grouting the cave, double liquid slurry is first used to seal the boundary of the cave treatment range to form a water-stopping and grout-stopping curtain, and then cement slurry is used for compaction grouting inward.
[0028] Compared with the prior art, the present invention has the following beneficial effects:
[0029] The pre-buried grouting pipe provides ground construction conditions for the treatment of the karst caves in the shield tunnels under high-rise buildings, ensures the quality of the karst cave reinforcement treatment, greatly reduces the risk of shield construction, and ensures that the construction work will not pose a safety threat to the adjacent high-rise buildings. It solves the problem of no ground construction conditions for the treatment of the karst caves in the shield tunnels under the high-rise buildings under construction before the shield construction, and the limited treatment range and poor treatment quality in the cave. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] The technology of the present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments:
[0031] Figure 1 It is a cross-sectional schematic diagram of the pre-buried grouting pipe of the present invention;
[0032] Figure 2 It is a schematic diagram of the treatment scope of the shield tunnel cave under the high-rise building under construction and the layout of the pre-buried grouting pipe on the horizontal plane of the present invention;
[0033] Figure 3 It is a schematic diagram of the cover structure on the pre-buried grouting pipe;
[0034] Figure 4 It is a schematic diagram of the connection structure between the mounting flange and the steel pipe;
[0035] Figure 5 It is a schematic diagram of the connection structure between the water stop flange and the steel pipe;
[0036] Figure 6 It is a schematic diagram of the structure of a metal hoop.
[0037] Reference numerals:
[0038] 1- Tunnel cave treatment scope;
[0039] 2-Shield tunnel structure outline;
[0040] 3-Cave edge;
[0041] 4- grouting pipe; 41- steel pipe; 42- top sealing structure; 421- cover plate; 422- mounting flange; 43- middle waterproof structure; 431- water stop flange; 432- water stop strip; 44- bottom waterproof structure; 441- waterproof reinforcement layer; 4411- cylindrical body; 4412- chamfered structure; 44133- annular plate; 442- sealant; 443- metal hoop; 4431- clamp; 4432- connection part; 45- concrete filling;
[0042] 5-Preliminary exploration points;
[0043] 6- Sealing structure;
[0044] 7- Waterproof layer;
[0045] 8- Bottom plate. DETAILED DESCRIPTION
[0046] The following will be combined with the embodiments and drawings to clearly and completely describe the concept, specific structure and technical effects of the present invention, so as to fully understand the purpose, scheme and effect of the present invention. It should be noted that the embodiments in this application and the features in the embodiments can be combined with each other without conflict. The same reference numerals used throughout the drawings indicate the same or similar parts.
[0047] It should be noted that, unless otherwise specified, when a feature is referred to as being "fixed" or "connected" to another feature, it may be directly fixed or connected to the other feature, or it may be indirectly fixed or connected to the other feature. In addition, the descriptions of up, down, left, right, etc. used in the present invention are only relative to the relative positional relationship of the components of the present invention in the drawings.
[0048] Reference Figures 1 to 6 A grouting pipe comprises a steel pipe 41 and a top sealing structure 42, a middle waterproof structure 43, and a bottom waterproof structure 44 which are connected to the steel pipe in sequence from top to bottom. The top sealing structure 42, the middle waterproof structure 43, and the bottom waterproof structure 44 are arranged at intervals in the vertical direction and have a good waterproof effect. The height of the steel pipe 41 is equal to the thickness of the bottom plate 8 of the main structure of the high-rise building under construction, and the bottom of the steel pipe 41 is provided with a concrete filling 45. The top sealing structure 42 comprises a cover plate 421, which is detachably mounted on the upper end of the steel pipe and is used to seal the upper end of the steel pipe. The middle waterproof structure 43 comprises a water stop flange 431, which is mounted on the outside of the steel pipe and is tightly connected to the outer surface of the steel pipe. The bottom waterproof structure 44 includes a waterproof reinforcement layer 441 with a structure approximately in the shape of a funnel. The waterproof reinforcement layer 441 is sleeved on the outer periphery of the steel pipe and is tightly connected to the outer surface of the steel pipe. The maximum size of the lower end of the waterproof reinforcement layer 441 is greater than the maximum size of the upper end.
[0049] The concrete filling 45 uses concrete of the same grade as the building main structure bottom plate 8, and its water-resistance grade is not lower than that of the main structure bottom plate 8, and its thickness is not less than 100 mm. Its main function is to provide a restraining reaction force to the concrete cushion layer or waterproof layer 7 to prevent the concrete cushion layer or waterproof layer 7 from bulging upward and cracking due to loss of restraint, thereby reducing the waterproof quality of the structure.
[0050] Specifically, the top sealing structure 42 also includes a mounting flange 422 fixed to the outside of the steel pipe, the upper end surface of the mounting flange 422 is flush with the upper end surface of the steel pipe, and the cover plate 421 is located above the mounting flange 422 and is detachably fixedly connected to the mounting flange 422. The inner diameter of the mounting flange 422 is consistent with the outer diameter of the steel pipe 41, and the two are welded together. A plurality of bolt holes are provided on the mounting flange 422, the diameter of the cover plate 421 is consistent with the outer diameter of the mounting flange 422, and a plurality of bolt holes corresponding to the mounting flange 422 are reserved on the cover plate 421, and the cover plate 421 is fixedly connected to the mounting flange 422 by bolts, so as to close the upper end of the pre-buried grouting pipe 4.
[0051] Specifically, the middle waterproof structure 43 also includes a water stop strip 432. The inner diameter of the water stop flange 431 is consistent with the outer diameter of the steel pipe 41, and the two are welded and connected, which can prevent water from entering between the water stop flange 431 and the steel pipe 41. The water stop strip 432 is pasted on the lower surface of the connection position between the water stop flange 431 and the steel pipe 41. The water stop strip 432 is annular, has water swelling performance, has good water blocking performance, and can further prevent water from entering between the water stop flange 431 and the steel pipe 41. The upper surface of the water stop strip 432 is tightly connected to the lower surface of the water stop flange 431, and the inner side of the water stop strip 432 is tightly connected to the outer surface of the steel pipe 41.
[0052] Specifically, the bottom waterproof structure 44 is located at the bottom of the steel pipe 41, and the longitudinal section of the waterproof reinforcement layer 441 is approximately L-shaped. The waterproof reinforcement layer 441 includes a cylindrical body 4411 and an annular plate 4413 fixedly connected from top to bottom. The lower end of the cylindrical body 4411 is tightly connected to the inner circle of the annular plate 4413, and the inner surface of the cylindrical body 4411 is tightly linked to the outer surface of the steel pipe 41.
[0053] Specifically, the bottom waterproof structure 44 further includes a metal hoop 443, which is in a circular ring shape and is fastened to the outside of the cylindrical body 4411 to tightly connect the cylindrical body 4411 with the steel pipe 41. The cylindrical body 4411 and the annular plate 4413 are tightly connected through an annular chamfered structure 4412, and a sealant 442 is filled between the chamfered structure 4412 and the outer surface of the steel pipe 41. The connection node between the cylindrical body 4411 and the annular plate 4413 is chamfered to form the chamfered structure 4412. The provision of the sealant 442 can prevent water from entering between the cylindrical body 4411 and the steel pipe 41.
[0054] Specifically, refer to the attached Figure 6 The metal hoop 443 includes two semi-circular clamps 4431 that are butted against each other. The inner surface of the clamps 4431 is structurally adapted to the outer surface of the cylindrical body 4411. Both ends of each clamp 4431 are provided with a connecting portion 4432 on one side away from the axis of the clamp 4431. Each connecting portion 4432 is provided with a bolt hole. When the two clamps 4431 are butted against each other, the bolt holes on the two connecting portions 4432 that are close to each other on the two clamps 4431 are coaxially arranged. The two connecting portions 4432 that are close to each other can be fixedly connected by bolt connection to form the metal hoop 443, thereby tightly connecting the cylindrical body 4411 and the steel pipe 41.
[0055] If the pre-buried grouting pipe 4 is arranged within the 3m range of the tunnel structure outline and arranged in a 2m×2m plum blossom shape, the height of the pre-buried grouting pipe 4 is consistent with the thickness of the main structure bottom plate 8 of the high-rise building under construction, and the diameter of the steel pipe 41 is determined according to the drill rod size of the drilling and grouting machine and the spacing of the steel bars of the main structure bottom plate 8 on site, so as to ensure the construction space of the drill rod and meet the steel bar arrangement requirements of the bottom plate 8. The pre-buried grouting pipe 4 of this scheme is pre-buried in the structure of the bottom plate 8 of the high-rise building under construction and is located above the waterproof structure of the bottom plate 8. Several pre-buried grouting pipes 4 provide ground construction conditions for the treatment of the karst cave of the shield tunnel under the high-rise building under construction, ensure the quality of the karst cave reinforcement treatment, greatly reduce the risk of shield construction, and ensure that the construction work will not pose a safety threat to the adjacent high-rise buildings. It solves the problem that there is no ground construction condition for the treatment of the karst cave of the shield tunnel under the high-rise building under construction before the shield construction, and the treatment range in the cave is limited and the treatment quality is poor.
[0056] Reference Figures 1 to 6 A method for treating a karst cave in a shield tunnel under a high-rise building under construction is performed using the pre-buried grouting pipe 4 as described above, comprising the following steps:
[0057] S1. Pre-buried grouting pipes 4: After the concrete cushion layer and waterproof layer 7 of the main structure bottom plate 8 of the high-rise building under construction above the tunnel are completed, when the structural steel bars are tied, a number of pre-buried grouting pipes 4 are pre-buried at intervals within the shield tunnel karst cave treatment range 1. Each pre-buried grouting pipe 4 is fixedly connected to the structural steel bars. Each pre-buried grouting pipe 4 is installed and positioned by the steel bar spacing of the bottom plate 8. When the concrete of the bottom plate 8 is poured, each pre-buried grouting pipe 4 is stabilized to prevent the grouting pipe 4 from being displaced or tilted. Among them, the shield tunnel karst cave treatment range 1 is centered on the shield tunnel structure outline 2, extending 3m to its left and right sides and bottom, and the upper treatment range extends upward to the ground surface. The horizontal cross-section of the treatment range is rectangular.
[0058] S2. Cave exploration: When the preliminary exploration points 5 within the shield tunnel cave treatment range 1 reveal the development of caves, and they have not been treated during the construction of the high-rise building foundation, the exploration points that reveal the development of caves are taken as the center, and cave exploration drilling is carried out in several pre-buried grouting pipes 4 pre-buried near each exploration point to determine the horizontal range and vertical range of the cave. Among them, when the cave exploration drilling is carried out, it is terminated until the cave exploration drilling does not reveal the cave or the exploration reaches the horizontal boundary range of the cave treatment, so as to determine the boundary and size of the cave. When drilling for cave exploration, the cover plate 421 can be opened to drill through the bottom concrete filling 45 in the steel pipe 41. Among them, the layout of the cave treatment range and the pre-buried grouting pipes on the horizontal plane can be referred to. Figure 2 shown.
[0059] S3. Grouting and filling the cave: Select some pre-buried grouting pipes 4 within the scope of the cave treatment plane, and drill holes in these pre-buried grouting pipes as grouting holes, and select some pre-buried grouting pipes 4 as exhaust holes. Use the main structure floor 8 of the high-rise building as a construction platform, and grout the cave through each grouting hole. When drilling the grouting hole, you can open the cover plate 421, drill through the bottom concrete filling 45 in the steel pipe 41. Among them, some of the cave exploration holes or grouting holes also serve as exhaust holes, and the exhaust holes are arranged at the top of the cave. Refer to the cave boundary 3 Figure 2 As shown in the figure, during the grouting filling process of the cave, the specific treatment method is as follows according to the size and filling condition of the cave revealed by the side drilling:
[0060] When the cave is fully filled, a standard penetration test is carried out on the filling material. When the standard penetration number is greater than 10, grouting filling treatment is not required. When the standard penetration number is less than 10, grouting treatment is required.
[0061] When the cave is an unfilled cave with a height of less than 3m or a semi-filled cave with a height of less than 3m, cement slurry is used for compaction grouting.
[0062] When the cave is an unfilled cave or semi-filled cave with a height greater than or equal to 3m, cement mortar is first used for filling, and then cement slurry compaction grouting is performed. If the boundary of the cave exceeds the cave treatment range, before the cave grouting filling grouting is performed, double liquid slurry is first used to seal the boundary of the cave treatment range to form a water-stopping and slurry-stopping curtain, and then cement slurry compaction grouting is performed inward.
[0063] S4. Grouting effect detection: The secondary grouting method is used to check the cave grouting filling rate, and the standard penetration method is used to determine the cave grouting filling density.
[0064] S5. Use double liquid slurry to timely seal the drilled holes below each pre-buried grouting pipe 4 to prevent water from seeping out from below the drilled holes and damaging the waterproof layer 7 of the bottom plate 8 of the main structure of the building.
[0065] S6. After completing the double-liquid slurry sealing and water stopping, backfill the micro-expansion waterproof concrete into each pre-buried grouting pipe 4. After the backfilling is completed, install the cover plate 421 to seal the pipe opening of each pre-buried grouting pipe 4. After the sealing is completed, pour the micro-expansion fiber concrete on the outside and top of the cover plate 421 to seal and form a sealing structure 6, and complete the restoration of the building main structure base plate 8 structure and decoration.
[0066] For other contents of the pre-buried grouting pipe and the method for treating the karst cave of a shield tunnel under a high-rise building under construction described in the present invention, please refer to the prior art and will not be repeated here.
[0067] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Therefore, any modification, equivalent change and modification made to the above embodiment based on the technical essence of the present invention without departing from the technical solution of the present invention shall still fall within the scope of the technical solution of the present invention.
Claims
1. A pre-buried grouting pipe, characterized in that: It includes a steel pipe and a top sealing structure, a middle waterproof structure, and a bottom waterproof structure connected to the steel pipe in sequence from top to bottom, and the bottom of the steel pipe is filled with concrete; The top sealing structure includes a cover plate, which is detachably mounted on the upper end of the steel pipe and is used to seal the upper end of the steel pipe; The middle waterproof structure includes a water-stop flange, which is sleeved on the outside of the steel pipe and tightly connected to the outer surface of the steel pipe; The bottom waterproof structure includes a waterproof reinforcement layer with a structure approximately in the shape of a funnel. The waterproof reinforcement layer is sleeved on the outer periphery of the steel pipe and is tightly connected to the outer surface of the steel pipe. The maximum size of the lower end of the waterproof reinforcement layer is greater than the maximum size of the upper end.
2. The pre-buried grouting pipe according to claim 1, characterized in that: The top sealing structure also includes a mounting flange fixed to the outside of the steel pipe, the upper end surface of the mounting flange is flush with the upper end surface of the steel pipe, and the cover plate is located above the mounting flange and is detachably fixedly connected to the mounting flange.
3. The pre-buried grouting pipe according to claim 1, characterized in that: The middle waterproof structure also includes a water stop strip, which is ring-shaped, with the upper surface of the water stop strip tightly connected to the lower surface of the water stop flange, and the inner side of the water stop strip tightly connected to the outer surface of the steel pipe.
4. The pre-buried grouting pipe according to claim 1, characterized in that: The longitudinal section of the waterproof reinforcement layer is approximately L-shaped, and the waterproof reinforcement layer includes a cylindrical body and an annular plate which are fixedly connected in sequence from top to bottom, the lower end of the cylindrical body is tightly connected to the inner circle of the annular plate, and the inner surface of the cylindrical body is tightly connected to the outer surface of the steel pipe; The bottom waterproof structure also includes a metal hoop, which is fastened to the outside of the cylindrical body to tightly connect the cylindrical body and the steel pipe; The cylindrical body and the annular plate are tightly connected via an annular chamfered structure, and sealant is filled between the chamfered structure and the outer surface of the steel pipe.
5. A method for treating a karst cave in a shield tunnel under a high-rise building under construction, characterized in that: The method is carried out using the pre-buried grouting pipe according to any one of claims 1 to 4, comprising the following steps: S1. Pre-buried grouting pipes: After the concrete cushion layer and waterproof layer of the main structure bottom plate of the high-rise building under construction above the tunnel are completed, when the structural steel bars are tied, several grouting pipes are pre-buried at intervals within the karst treatment range of the shield tunnel, and each pre-buried grouting pipe is fixedly connected to the structural steel bars; S2. Karst cave exploration: When the previous exploration points within the shield tunnel karst cave treatment range reveal the presence of karst caves, and the ground has not been treated during the construction of the high-rise building foundation, the exploration points revealing the presence of karst caves are taken as the center, and karst cave exploration drilling is carried out in several pre-buried grouting pipes near each exploration point to determine the horizontal and vertical ranges of the karst caves; S3. Grouting and filling of caves: Select some pre-buried grouting pipe holes as grouting holes in the karst cave treatment plane, and select some pre-buried grouting pipe holes as exhaust holes. Use the main structure floor of the high-rise building as a construction platform, and grout the caves through the grouting holes on the main structure floor platform of the high-rise building; S4. Grouting effect detection: Use the secondary grouting method to check the cave grouting filling rate, and use the standard penetration method to measure the cave grouting filling density; S5. After the grouting filling of the cave is completed, double liquid slurry is used to seal the bottom of the pre-buried grouting pipe of each completed hole to prevent water from bubbling up from below the hole to damage the waterproof layer of the main structure of the building; S6. Backfill the micro-expansion waterproof concrete into each pre-buried grouting pipe, and then seal the pipe openings of each pre-buried grouting pipe. After the sealing is completed, restore the base plate structure of the main building structure.
6. The method for treating the karst cave of a shield tunnel under a high-rise building under construction according to claim 5 is characterized by: In step S1, the shield tunnel karst cave treatment range is centered on the tunnel structure outline, extending 3m to the left and right sides and the bottom, and the upper treatment range extends upward to the ground surface. The horizontal cross-section of the treatment range is rectangular.
7. The method for treating the karst cave of a shield tunnel under a high-rise building under construction according to claim 5 is characterized by: In step S2, the process is terminated until the cave exploration drilling fails to reveal the cave or reaches the horizontal boundary range of the cave processing, so as to determine the boundary and size of the cave.
8. The method for treating the karst cave of a shield tunnel under a high-rise building under construction according to claim 5 is characterized by: In step S3, some of the karst cave side drilling holes or grouting holes also serve as exhaust holes, and the exhaust hole drilling holes are arranged at the top of the karst cave.
9. The method for treating the karst cave of a shield tunnel under a high-rise building under construction according to claim 5, characterized in that: In step S3, during the grouting filling process of the cave, when the cave is a fully filled cave, a standard penetration test is performed on the filling material. When the standard penetration number is greater than 10, no filling treatment can be selected. When the standard penetration number is less than 10, the cave needs to be grouting treated; when the cave is an unfilled cave or a semi-filled cave with a height of less than 3m, cement slurry is used for compaction grouting; when the cave is an unfilled cave or a semi-filled cave with a height greater than or equal to 3m, cement mortar is first used for filling, and then cement slurry is used for compaction grouting.
10. The method for treating the karst cave of a shield tunnel under a high-rise building under construction according to claim 5, characterized in that: In step S3, if the boundary of the cave exceeds the cave treatment range, before grouting the cave, double-liquid slurry is first used to seal the boundary of the cave treatment range to form a water-stopping and slurry-stopping curtain, and then cement slurry is used for compaction grouting inward.