Roof waterproof construction method

By using a crack monitoring system in roof waterproof construction, the accuracy of crack identification and repair during construction is solved, efficient crack repair is achieved, resource waste and water leakage risks are reduced, and construction efficiency is improved.

CN119062067APending Publication Date: 2024-12-03CHINA RAILWAY SIXTH GROUP CO LTD +1
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202411233039.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-04
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

In roof waterproofing construction, cracks are prone to occur during concrete pouring, resulting in water leakage. The existing technology relies on the experience of construction personnel for identification and treatment. The accuracy is not high and there is no consideration for the severity of cracks and the expansion speed, resulting in waste of resources or The repair effect is not good.

Method used

Use a crack monitoring system to monitor concrete cracks in real time. By calculating the crack degree and judging the value and expansion speed, assessing the risk level and marking the priority repair area and delaying repair area, combining adjacent priority repair areas for sorting and repairing, accurately identifying high-risk areas and giving priority to it. repair.

Benefits of technology

Reduce the hidden dangers of water leakage caused by cracks, accurately allocate repair resources, improve construction efficiency, ensure that cracks in key areas are treated in a timely manner, and significantly improve the overall repair efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119062067A_ABST
    Figure CN119062067A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of waterproof construction, and discloses a roof waterproof construction method which comprises the following steps: constructing a roof protective layer, erecting a reinforcing mesh, pouring concrete and pasting a film for maintenance. Wherein after concrete is poured, a crack monitoring system is arranged to monitor concrete cracks in real time, and the system specifically comprises a crack monitoring and processing module in the construction process. Therefore, when roof waterproof construction is carried out, the concrete pouring area is monitored and analyzed, the area with cracks is obtained in time, the crack area is subjected to risk grade division, the high-risk area is repaired preferentially, then the hidden danger of water leakage caused by the cracks is reduced, and the construction efficiency is improved. And meanwhile, the adjacent preferential repair areas are combined into the preferential repair integration area, and the preferential repair integration area is sorted according to the area size for repair, so that repair resources can be distributed more accurately, scattered and repeated construction processes are avoided, the movement and preparation time of constructors is shortened, and the construction efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of waterproof construction, and in particular to a roof waterproof construction method. Background Art

[0002] The main purpose of roof waterproofing is to prevent rainwater from penetrating into the interior of the building through the roof, ensuring that the building is dry and comfortable. The project includes roof structures, waterproof layers, waterproof materials, roof accessories, drainage systems and other related projects. The roof is the uppermost covering and load-bearing structure of the house, and its waterproof performance is extremely important.

[0003] In a roof waterproofing construction method disclosed in Chinese patent CN116290604A, the following steps are set: S1, preparation work, cleaning the roof; S2, slope finding, making the highest and lowest control points, and then filling with cement mortar, and making a transition surface at the angle with the wall;

[0004] S3, waterproof construction, apply waterproof material on the slope surface, then lay waterproof coiled material, and conduct water storage test after laying; S4, thermal insulation construction, lay thermal insulation board; S5, roof protection layer construction, erect steel mesh, pour concrete, and apply film for maintenance, which solves the following problems: when carrying out roof waterproof construction, first clean up the debris on the roof, then make a highest point and a lowest point according to the actual situation, then fill it with cement mortar, and then make a transition surface at the angle with the wall; after the concrete maintenance is completed, apply waterproof material on the concrete slope surface, and apply it several times; then after it is naturally dried, lay waterproof coiled material, and then conduct water storage test to observe waterproofing, after the water storage test is completed, lay thermal insulation board, then erect steel mesh and pour concrete, and finally apply film for maintenance; the above process makes the application of waterproof coating convenient through the setting of transition surface, reduces the situation that it is not convenient to apply waterproof coating at right angles, thereby reducing the situation of water seepage at corners, so that the waterproof effect can be maintained;

[0005] However, in the above-disclosed prior art, cracks may appear due to various factors during concrete pouring, which in turn affects the waterproof quality of the roof and causes water leakage. Currently, the identification and treatment of crack problems mainly rely on the experience of construction workers. The identification of this method is subject to the subjective judgment of construction workers and is not accurate. At the same time, the crack area is repaired uniformly, and the severity and expansion speed of the cracks are not considered, which may lead to waste of resources or poor repair effect.

[0006] In view of this, we proposed a roof waterproofing construction method. Summary of the invention

[0007] The object of the present invention is to provide a roof waterproofing construction method to solve the above-mentioned problems.

[0008] The purpose of the present invention can be achieved through the following technical solutions:

[0009] A roof waterproofing construction method comprises the following steps: roof protection layer construction, steel mesh installation, concrete pouring, and film curing; wherein, after the concrete is poured, a crack monitoring system is provided to monitor concrete cracks in real time, specifically comprising: a crack monitoring and processing module: during the construction process, concrete cracks are monitored, crack data are collected, and processed to calculate a crack degree judgment value; a crack degree judgment module: obtaining a crack degree judgment value of each crack area, judging the risk level of each crack area, evaluating the repair priority of the crack area, marking the crack area as a priority repair area or as a delayed repair area, and integrating the priority repair areas; a newly added crack area acquisition module: extracting an area where new cracks appear in a non-crack area as a newly added crack area, and marking the newly added crack area as a delayed repair area; a crack growth judgment module: based on the delayed repair area obtained above, obtaining a crack degree judgment value expansion speed, processing, and calculating an expansion evaluation value; a delayed repair area priority judgment module: obtaining an expansion evaluation value corresponding to each delayed repair area, and comparing them to judge the repair priority of the delayed repair area.

[0010] As a further solution of the present invention: the process of obtaining the crack degree judgment value is as follows:

[0011] Obtain crack area ratio, crack length ratio and crack width ratio;

[0012] Substitute into the formula PD=a1*MJ+a2*CD+a3*KD to calculate the crack degree judgment value, where MJ is the crack area ratio, CD is the crack length ratio, KD is the crack width ratio, and a1, a2, and a3 are preset proportional coefficients.

[0013] As a further solution of the present invention: the process of obtaining the crack length ratio and the crack width ratio is:

[0014] Divide the concrete pouring area into a number of monitoring areas in a grid format, and obtain crack data of each monitoring area, wherein the crack data includes crack length and crack width;

[0015] The monitoring area containing cracks is marked as a crack area, and the monitoring area without cracks is marked as a non-crack area;

[0016] In each crack area, the maximum crack length is extracted, and the ratio of the maximum crack length to the crack length threshold is calculated to obtain the crack length ratio; the maximum crack width is extracted, and the ratio of the maximum crack width to the crack width threshold is calculated to obtain the crack width ratio.

[0017] As a further solution of the present invention: the process of obtaining the crack area ratio is:

[0018] In each crack area, each crack area value is obtained, all crack area values ​​are summed up to obtain the total crack area value, and the total crack area value is ratioed with the area of ​​the corresponding monitoring area to obtain the crack area ratio.

[0019] As a further solution of the present invention: the process of marking the crack area as a priority repair area or marking it as a delayed repair area includes:

[0020] Obtaining a crack degree judgment value for each monitoring area, and comparing the crack degree judgment value for each monitoring area with a crack degree judgment threshold value;

[0021] If the crack degree judgment value is less than or equal to the crack degree judgment threshold, a low risk signal is generated;

[0022] If the crack degree judgment value is greater than the crack degree judgment threshold, a high risk signal is generated;

[0023] The crack area corresponding to the high-risk signal is obtained and marked as the priority repair area, and the crack area corresponding to the low-risk signal is obtained and marked as the delayed repair area.

[0024] As a further solution of the present invention: the process of integrating the priority repair areas is:

[0025] Based on the marked priority repair regions, all adjacent priority repair regions are merged into a larger region, marking the priority repair integration region;

[0026] Among them, the adjacent priority repair areas include upper and lower adjacent areas and left and right adjacent areas;

[0027] The area values ​​of the priority repair integration regions are obtained, and all the area values ​​of the priority repair integration regions are sorted in order from large to small, and crack repair is performed on the priority repair integration regions based on the sorted order.

[0028] As a further solution of the present invention: the process of obtaining the extended evaluation value is:

[0029] Obtain the original crack degree judgment value and the total slope value;

[0030] Substitute into the formula The extended evaluation value KZ is calculated, where YS represents the original crack degree judgment value, XL represents the total slope value, and s1 and s2 are preset proportional coefficients.

[0031] As a further solution of the present invention: the process of obtaining the original crack degree judgment value and the slope total value is:

[0032] Preset monitoring cycle and divide the monitoring cycle into multiple monitoring periods;

[0033] In each delayed repair area, the end time point of each monitoring period in the monitoring cycle is marked as the analysis time point, and a two-dimensional model is established with the analysis time point as the X-axis and the crack degree judgment value expansion speed as the Y-axis. The crack degree judgment value expansion speed is substituted into the two-dimensional model to draw a line segment graph of the crack degree judgment value expansion speed;

[0034] Mark the corresponding straight line segment between two adjacent analysis time points as a sub-broken line segment, obtain the slope value of each sub-broken line segment, and sum the slope values ​​of all sub-broken line segments to obtain the total slope value;

[0035] In each delayed repair area, the corresponding crack degree judgment value at the start time of the monitoring period is obtained and marked as the original crack degree judgment value.

[0036] As a further solution of the present invention: the process of obtaining the crack degree judgment value expansion speed in each monitoring period is as follows:

[0037] Obtain the crack degree judgment value at the start time point of each monitoring period, marked as the initial crack degree judgment value, obtain the crack degree judgment value at the end time point of each monitoring period, marked as the end crack degree judgment value, calculate the difference between the end crack degree judgment value corresponding to each monitoring period and the initial crack degree judgment value, calculate the ratio of the obtained difference to the time difference of the monitoring period, and obtain the crack degree judgment value expansion speed;

[0038] The time difference of the monitoring period is the difference between the end time point of the monitoring period and the start time point of the monitoring period.

[0039] As a further solution of the present invention: the process of determining the repair priority of the delayed repair area is:

[0040] Obtaining an extended evaluation value corresponding to each delayed repair area, and comparing the extended evaluation value with a first evaluation threshold and a second evaluation threshold respectively;

[0041] If the extended evaluation value is less than or equal to the first evaluation threshold, the deferred repair area is marked as a non-priority area;

[0042] If the first evaluation threshold is less than the extended evaluation value and less than the second evaluation threshold, the deferred repair area is marked as a secondary priority area;

[0043] If the extended evaluation value is greater than or equal to the second evaluation threshold, the deferred repair area is marked as a priority area.

[0044] Beneficial effects of the present invention:

[0045] (1) First, by obtaining the crack data of each monitoring area in the concrete pouring area, the monitoring area is divided into a crack area and a non-crack area, the crack area is analyzed, the crack degree judgment value of each crack area is calculated, and the risk level of each crack area is evaluated based on the crack degree judgment value and the crack degree judgment threshold. The crack area is marked as a priority repair area and a delayed repair area according to the risk level, and the adjacent areas in all priority repair areas are merged and marked as priority repair integration areas. Then, the marked priority repair integration areas are sorted in order from large to small in area, and cracks in the priority repair integration areas are repaired according to the sorted order. Therefore, when performing roof waterproofing construction, the concrete pouring area can be monitored and analyzed to timely obtain the area with cracks therein, and the crack area is divided into risk levels, and the high-risk area is repaired first, thereby reducing the hidden danger of water leakage caused by cracks. At the same time, the adjacent priority repair areas are merged into priority repair integration areas, and repaired according to the area size. This can more accurately allocate repair resources, avoid scattered and repeated construction processes, reduce the movement and preparation time of construction personnel, and improve construction efficiency;

[0046] (2) By obtaining the deferred repair area, the expansion speed of the crack degree judgment value of the deferred repair area is analyzed, the total slope value is calculated, the original crack degree judgment value of the deferred repair area is obtained, and the expansion speed value is calculated based on the obtained total slope value and the original crack degree judgment value. By comparing the expansion speed value with the first evaluation threshold and the second evaluation threshold, the deferred repair area is divided into a priority area, a sub-priority area and a non-priority area, and the cracks in the deferred repair area are repaired based on the divided repair priority. Therefore, the repair priority of the deferred repair area can be divided by calculating and comparing the expansion evaluation value, and it can be accurately identified which areas are rapidly deteriorating cracks and need to be repaired immediately or earlier. This avoids the average allocation of resources and ensures that cracks in key areas are dealt with in a timely manner, thereby significantly improving the overall repair efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0047] The present invention will be further described below in conjunction with the accompanying drawings.

[0048] Figure 1 It is a schematic diagram of a process of a roof waterproofing construction method of the present invention;

[0049] Figure 2It is a schematic diagram of a crack monitoring system for a roof waterproofing construction method of the present invention;

[0050] Figure 3 It is a schematic diagram of obtaining an extended evaluation value in a roof waterproofing construction method of the present invention. DETAILED DESCRIPTION

[0051] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0052] Example 1

[0053] See also Figure 1 As shown, the present invention is a roof waterproofing construction method, comprising the following steps:

[0054] Step 1: Preparation work, cleaning the roof;

[0055] Step 2: Find the slope, make the highest and lowest control points, then fill with cement mortar, and make a transition surface at the angle with the wall;

[0056] Step 3: Waterproof construction, apply waterproof material on the slope surface, then lay the waterproof membrane, and conduct water storage test after laying;

[0057] Step 4: Insulation construction, laying insulation board;

[0058] Step 5: Construction of roof protection layer, installation of steel mesh, pouring of concrete, and film curing;

[0059] It should be noted that in step five, cracks appearing when pouring concrete will affect the quality of the waterproof layer and the safety of the structure. Therefore, a crack monitoring system needs to be set up during construction to monitor the concrete cracks in real time.

[0060] Example 2

[0061] Based on the above examples, please refer to Figure 2 As shown, the present invention is a roof waterproofing construction method, wherein the crack monitoring system specifically includes:

[0062] Crack monitoring and processing module: During the construction process, monitor concrete cracks, collect crack data, process it, and calculate the crack degree judgment value;

[0063] In some implementations, the concrete pouring area is divided into a plurality of monitoring areas in a grid format, and crack data of each monitoring area is obtained, wherein the crack data includes crack length, crack width and crack area;

[0064] The method of obtaining crack data includes but is not limited to: using drones, high-definition cameras and other equipment to take high-definition images of the roof concrete pouring area, and then using image processing software (such as Photoshop) to identify and mark the cracks, and then measure the length and width of the cracks, and automatically calculate the pixel area occupied by the cracks, and then convert the pixel area into the actual crack area;

[0065] The monitoring area containing cracks is marked as a crack area, and the monitoring area without cracks is marked as a non-crack area;

[0066] In each crack region, obtain each crack area value, sum up all the crack area values ​​to obtain the total crack area value, and perform ratio processing on the total crack area value and the area of ​​the corresponding monitoring region to obtain the crack area ratio;

[0067] In each crack region, the maximum crack length is extracted, and the ratio of the maximum crack length to the crack length threshold is calculated to obtain the crack length ratio; the maximum crack width is extracted, and the ratio of the maximum crack width to the crack width threshold is calculated to obtain the crack width ratio;

[0068] The crack length threshold and crack width threshold are set by technicians in this field based on historical experimental data.

[0069] Substitute into the formula PD = a1*MJ+a2*CD+a3*KD to calculate the crack degree judgment value, where MJ is the crack area ratio, CD is the crack length ratio, KD is the crack width ratio, and a1, a2, and a3 are preset proportional coefficients;

[0070] It should be explained that the meaning reflected by the crack degree judgment value is: the crack degree judgment value is calculated by the crack area ratio, crack length ratio and crack width ratio, that is, the larger the crack area ratio is, the larger the area of ​​the crack in the corresponding crack region is, and the higher the crack risk degree of the crack region is; that is, the larger the crack length ratio is, the larger the maximum crack length in the corresponding crack region is, and the higher the crack risk degree of the crack region is; that is, the larger the crack width ratio is, the larger the maximum crack width in the corresponding crack region is, and the higher the crack risk degree of the crack region is;

[0071] Crack degree judgment module: obtains the crack degree judgment value of each crack area, determines the risk level of each crack area, and evaluates the repair priority of the crack area;

[0072] In some embodiments, a crack degree judgment value of each monitoring area is obtained, and the crack degree judgment value of each monitoring area is compared with a crack degree judgment threshold value, wherein the crack degree judgment threshold value is a critical value used to judge the crack risk level, and is set by a person skilled in the art based on a summary of multiple historical experimental data;

[0073] If the crack degree judgment value is less than or equal to the crack degree judgment threshold, it means that the crack degree corresponding to the monitoring area is low, and a low risk signal is generated;

[0074] If the crack degree judgment value is greater than the crack degree judgment threshold, it means that the crack degree corresponding to the monitoring area is high, and a high-risk signal is generated;

[0075] Obtain the crack area corresponding to the high-risk signal, mark it as the priority repair area, obtain the crack area corresponding to the low-risk signal, mark it as the delayed repair area;

[0076] Based on the marked priority repair regions, all adjacent priority repair regions are merged into a larger region, marking the priority repair integration region;

[0077] Among them, the adjacent priority repair areas include upper and lower adjacent areas and left and right adjacent areas;

[0078] Obtaining the area value of the priority repair integration area, sorting all the area values ​​of the priority repair integration area in descending order, and repairing the cracks in the priority repair integration area based on the sorted order;

[0079] It should be explained that by sorting the area values ​​of the priority repair integration areas from large to small, the areas with the largest area and the most serious cracks can be repaired first. These large areas or serious cracks often have a greater impact on structural safety or functional use. Therefore, giving priority to them can eliminate potential safety hazards more quickly and reduce further damage that may be caused by the expansion of cracks;

[0080] The core technology of this embodiment is: first, by acquiring the crack data of each monitoring area in the concrete pouring area, the monitoring area is divided into a crack area and a non-crack area, the crack area is analyzed, the crack degree judgment value of each crack area is calculated, and the risk level of each crack area is evaluated based on the crack degree judgment value and the crack degree judgment threshold, and the crack area is marked as a priority repair area and a delayed repair area according to the risk level, and the adjacent areas in all priority repair areas are merged and marked as priority repair integration areas, and then the marked priority repair integration areas are sorted in order from large to small in area, and cracks in the priority repair integration areas are repaired according to the sorted order, so that when performing roof waterproofing construction, by monitoring and analyzing the concrete pouring area, the area with cracks therein can be obtained in time, and the risk level of the crack area can be divided, and the high-risk area can be repaired first, thereby reducing the hidden danger of water leakage caused by cracks. At the same time, the adjacent priority repair areas are merged into priority repair integration areas, and repaired in order of area size, which can more accurately allocate repair resources, avoid scattered and repeated construction processes, reduce the movement and preparation time of construction personnel, and improve construction efficiency.

[0081] Example 3

[0082] Based on the above examples, please refer to Figure 2 - Figure 3 As shown, the present invention is a roof waterproofing construction method, wherein the crack monitoring system specifically includes:

[0083] Added a new crack area acquisition module: obtains new crack areas and marks them as delayed repair areas;

[0084] In some embodiments, a region where a new crack appears in a non-crack region is extracted as a newly added crack region, and the newly added crack region is marked as a delayed repair region;

[0085] It is necessary to explain that the reasons for the emergence of newly added crack areas include, but are not limited to: the expansion of cracks existing in the crack area to the non-crack area over time or the emergence of new cracks due to other factors;

[0086] Crack growth judgment module: based on the above-obtained delayed repair area, obtain the crack degree judgment value expansion speed, process it, and calculate the expansion evaluation value;

[0087] In some embodiments, a monitoring cycle is preset, the monitoring cycle is divided into a plurality of monitoring periods, and the expansion speed of the crack degree judgment value of the delayed repair area in each monitoring period is calculated;

[0088] It should be noted that during the repair process of the priority repair integration area, the delayed repair area is analyzed, so the preset monitoring period is shorter than the repair time of the priority repair integration area;

[0089] Among them, the division of the preset monitoring cycle and monitoring period is set by the staff in this field based on experience;

[0090] Exemplarily, the process of obtaining the crack degree judgment value and the expansion speed is as follows:

[0091] Obtain the crack degree judgment value at the start time point of each monitoring period, marked as the initial crack degree judgment value, obtain the crack degree judgment value at the end time point of each monitoring period, marked as the end crack degree judgment value, calculate the difference between the end crack degree judgment value corresponding to each monitoring period and the initial crack degree judgment value, calculate the ratio of the obtained difference to the time difference of the monitoring period, and obtain the crack degree judgment value expansion speed;

[0092] The time difference of the monitoring period is the difference between the end time point of the monitoring period and the start time point of the monitoring period;

[0093] In each delayed repair area, the end time point of each monitoring period in the monitoring cycle is marked as the analysis time point, and a two-dimensional model is established with the analysis time point as the X-axis and the crack degree judgment value expansion speed as the Y-axis. The crack degree judgment value expansion speed is substituted into the two-dimensional model to draw a line segment graph of the crack degree judgment value expansion speed;

[0094] Mark the corresponding straight line segment between two adjacent analysis time points as a sub-broken line segment, obtain the slope value of each sub-broken line segment, and sum the slope values ​​of all sub-broken line segments to obtain the total slope value;

[0095] In each delayed repair area, the corresponding crack degree judgment value at the start time of the monitoring period is obtained and marked as the original crack degree judgment value;

[0096] Substitute into the formula The extended evaluation value KZ is calculated, where YS represents the original crack degree judgment value, XL represents the total slope value, and s1 and s2 are preset proportional coefficients;

[0097] It should be explained that the meaning reflected by the extended assessment value is: the extended assessment value is calculated by the original crack degree judgment value and the total slope value, that is, the larger the original crack degree judgment value is, the more serious the original crack corresponding to the delayed repair area is, and it needs to be repaired first, that is, the larger the total slope value is, the greater the change value of the crack degree judgment value expansion speed in the delayed repair area during the monitoring period, and the greater the degree of change of the crack corresponding to the delayed repair area is, and it needs to be repaired first;

[0098] Delayed repair area priority judgment module: obtains the extended evaluation value corresponding to each delayed repair area, compares them, and determines the repair priority of the delayed repair area;

[0099] In some embodiments, an extended evaluation value corresponding to each delayed repair area is obtained, and the extended evaluation value is compared with a first evaluation threshold and a second evaluation threshold, respectively, wherein the first evaluation threshold is less than the second evaluation threshold, and the first evaluation threshold and the second evaluation threshold are summarized and set by a person skilled in the art based on historical multiple experimental data;

[0100] If the extended evaluation value is less than or equal to the first evaluation threshold, the deferred repair area is marked as a non-priority area;

[0101] If the first evaluation threshold is less than the extended evaluation value and less than the second evaluation threshold, the deferred repair area is marked as a secondary priority area;

[0102] If the extended evaluation value is greater than or equal to the second evaluation threshold, marking the deferred repair area as a priority area;

[0103] Based on the above-mentioned priority areas, the monitoring period is reduced to monitor them more frequently, so as to timely understand the crack expansion situation;

[0104] In the process of repairing the deferred repair areas, repair them in the order of priority areas, sub-priority areas and non-priority areas;

[0105] The core technology of this embodiment is as follows: by acquiring the deferred repair area, analyzing the expansion speed of the crack degree judgment value of the deferred repair area, calculating the total slope value, acquiring the original crack degree judgment value of the deferred repair area, and calculating the expansion speed value based on the acquired total slope value and the original crack degree judgment value, dividing the deferred repair area into priority area, sub-priority area and non-priority area by comparing the expansion speed value with the first evaluation threshold and the second evaluation threshold respectively, and repairing the cracks in the deferred repair area based on the divided repair priority, so that the repair priority of the deferred repair area can be divided by calculating and comparing the expansion evaluation values, and it can be accurately identified which areas are rapidly deteriorating and need to be repaired immediately or earlier, which avoids the average allocation of resources and ensures that cracks in key areas are dealt with in a timely manner, thereby significantly improving the overall repair efficiency.

[0106] The above is a detailed description of an embodiment of the present invention, but the content is only a preferred embodiment of the present invention and cannot be considered to limit the scope of implementation of the present invention. All equivalent changes and improvements made within the scope of the present invention should still fall within the scope of the patent coverage of the present invention.

Claims

1. A roof waterproofing construction method, It is characterized in that The process includes the following steps: construction of roof protection layer, erection of steel mesh, pouring of concrete, and film curing; Among them, after pouring concrete, a crack monitoring system is set up to monitor concrete cracks in real time, including: Crack monitoring and processing module: During the construction process, monitor concrete cracks, collect crack data, process it, and calculate the crack degree judgment value; Crack degree judgment module: obtains the crack degree judgment value of each crack area, judges the risk level of each crack area, evaluates the repair priority of the crack area, marks the crack area as a priority repair area or a delayed repair area, and integrates the priority repair areas; New crack area acquisition module: extract the area with new cracks in the non-crack area as the new crack area, and mark the new crack area as the delayed repair area; Crack growth judgment module: based on the above-obtained delayed repair area, obtain the crack degree judgment value expansion speed, process it, and calculate the expansion evaluation value; Delayed repair area priority judgment module: obtains the extended evaluation value corresponding to each delayed repair area, compares them, and determines the repair priority of the delayed repair area.

2. A roof waterproofing construction method according to claim 1, It is characterized in that The process of obtaining the crack degree judgment value is as follows: Obtain crack area ratio, crack length ratio and crack width ratio; Substitute into the formula PD=a1*MJ+a2*CD+a3*KD to calculate the crack degree judgment value, where MJ is the crack area ratio, CD is the crack length ratio, KD is the crack width ratio, and a1, a2, and a3 are preset proportional coefficients.

3. A roof waterproofing construction method according to claim 2, It is characterized in that The process of obtaining the crack length ratio and crack width ratio is as follows: Divide the concrete pouring area into several monitoring areas in a grid format, and obtain crack data of each monitoring area, including crack length, crack width and crack area; The monitoring area containing cracks is marked as a crack area, and the monitoring area without cracks is marked as a non-crack area; In each crack area, the maximum crack length is extracted, and the ratio of the maximum crack length to the crack length threshold is calculated to obtain the crack length ratio; the maximum crack width is extracted, and the ratio of the maximum crack width to the crack width threshold is calculated to obtain the crack width ratio.

4. A roof waterproofing construction method according to claim 2, It is characterized in that The process of obtaining the crack area ratio is as follows: In each crack area, each crack area value is obtained, all crack area values ​​are summed up to obtain the total crack area value, and the total crack area value is ratioed with the area of ​​the corresponding monitoring area to obtain the crack area ratio.

5. A roof waterproofing construction method according to claim 1, It is characterized in that The process of marking crack areas as priority repair areas or marking them for later repair includes: Obtaining a crack degree judgment value for each monitoring area, and comparing the crack degree judgment value for each monitoring area with a crack degree judgment threshold value; If the crack degree judgment value is less than or equal to the crack degree judgment threshold, a low risk signal is generated; If the crack degree judgment value is greater than the crack degree judgment threshold, a high risk signal is generated; The crack area corresponding to the high-risk signal is obtained and marked as the priority repair area, and the crack area corresponding to the low-risk signal is obtained and marked as the delayed repair area.

6. A roof waterproofing construction method according to claim 1, It is characterized in that The process for consolidating priority restoration areas is as follows: Based on the marked priority repair regions, all adjacent priority repair regions are merged into a larger region, marking the priority repair integration region; Among them, the adjacent priority repair areas include upper and lower adjacent areas and left and right adjacent areas; The area values ​​of the priority repair integration regions are obtained, and all the area values ​​of the priority repair integration regions are sorted in order from large to small, and crack repair is performed on the priority repair integration regions based on the sorted order.

7. A roof waterproofing construction method according to claim 1, It is characterized in that The process of obtaining the extended evaluation value is as follows: Obtain the original crack degree judgment value and slope total value; Substitute into the formula The extended evaluation value KZ is calculated, where YS represents the original crack degree judgment value, XL represents the total slope value, and s1 and s2 are preset proportional coefficients.

8. A roof waterproofing construction method according to claim 7, It is characterized in that The process of obtaining the original crack degree judgment value and the total slope value is as follows: Preset monitoring cycle and divide the monitoring cycle into multiple monitoring periods; In each delayed repair area, the end time point of each monitoring period in the monitoring cycle is marked as the analysis time point, and a two-dimensional model is established with the analysis time point as the X-axis and the crack degree judgment value expansion speed as the Y-axis. The crack degree judgment value expansion speed is substituted into the two-dimensional model to draw a line segment graph of the crack degree judgment value expansion speed; Mark the corresponding straight line segment between two adjacent analysis time points as a sub-broken line segment, obtain the slope value of each sub-broken line segment, and sum the slope values ​​of all sub-broken line segments to obtain the total slope value; In each delayed repair area, the corresponding crack degree judgment value at the start time of the monitoring period is obtained and marked as the original crack degree judgment value.

9. A roof waterproofing construction method according to claim 8, It is characterized in that The process of obtaining the crack degree judgment value and expansion speed in each monitoring period is as follows: Obtain the crack degree judgment value at the start time point of each monitoring period, marked as the initial crack degree judgment value, obtain the crack degree judgment value at the end time point of each monitoring period, marked as the end crack degree judgment value, calculate the difference between the end crack degree judgment value corresponding to each monitoring period and the initial crack degree judgment value, calculate the ratio of the obtained difference to the time difference of the monitoring period, and obtain the crack degree judgment value expansion speed; The time difference of the monitoring period is the difference between the end time point of the monitoring period and the start time point of the monitoring period.

10. A roof waterproofing construction method according to claim 1, It is characterized in that The process of determining the repair priority of the deferred repair area is as follows: Obtaining an extended evaluation value corresponding to each delayed repair area, and comparing the extended evaluation value with a first evaluation threshold and a second evaluation threshold respectively; If the extended evaluation value is less than or equal to the first evaluation threshold, the deferred repair area is marked as a non-priority area; If the first evaluation threshold is less than the extended evaluation value and less than the second evaluation threshold, the deferred repair area is marked as a secondary priority area; If the extended evaluation value is greater than or equal to the second evaluation threshold, the deferred repair area is marked as a priority area.

Citation Information

Cited By

  • Road maintenance road construction sequence determination method, system, equipment and medium

    CN119809268A

  • Crack detection method and system for soft soil foundation treatment

    CN119919359A