By designing a shared semi-continuous transportation system layout method in open-pit coal mines, the problem of winter production difficulties of open-pit coal mines in northern China has been solved, efficient use and seasonal flexibility of the system throughout the year, and the utilization rate of coal resources has been improved and Emergency supply guarantee capacity reduces costs and operational difficulties.
Patent Information
- Application Number
- CN202411222756.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-02
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2044-09-02
AI Technical Summary
In open-pit coal mines in northern my country, semi-continuous process systems have difficulty in production in winter, resulting in high unit capacity, long cost, and low mining efficiency, which affects the utilization rate of coal resources.
A method for laying a common semi-continuous transportation system for open-pit coal mines is designed, including setting up a crushing station and lifting belt conveyor on the production surface of the open-pit mine, a trunk belt conveyor, a diversion transfer belt conveyor and coal storage in both directions. The layout of belt conveyors and other equipment can achieve efficient annual utilization and seasonal flexibility by adjusting the equipment position and transportation direction.
The total production capacity of the open-pit mine semi-continuous process system has been improved, the coal supply capacity has been expanded, the elastic transformation of coal mine production capacity has been promoted, the emergency supply guarantee capacity has been enhanced, the system cost and operation difficulty has been reduced, and dust pollution has been avoided.
Smart Images

Figure CN119062340A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to an open-pit mining method, in particular to an open-pit coal mining and stripping common semi-continuous transportation system arrangement method, belonging to the field of open-pit mining. Background Art
[0002] Semi-continuous process is conducive to reducing production costs and carbon emissions in the production process, and has a very high promotion value in open-pit mining process, but the process still has the following problems or shortcomings. On the one hand, in recent years, the application proportion of semi-continuous process in coal production links of large open-pit coal mines in my country has gradually expanded, but with the continuous improvement of my country's requirements for emergency peak-shaving capacity of thermal power, higher requirements have been put forward for the stability of semi-continuous process system of open-pit mines and the instantaneous overload capacity of the system. On the other hand, since most of my country's open-pit coal mines are located in the north, the production of semi-continuous process system is difficult in winter, and generally needs to be shut down for 3 to 5 months, resulting in large unit capacity investment, high cost and long investment recovery period of the system. Therefore, it is difficult to promote the semi-continuous process of stripping, and it is urgent to design and improve new layout methods to improve the utilization rate of coal resources in mining. Summary of the invention
[0003] In view of the problems existing in the above-mentioned prior art, the purpose of the present invention is to provide a method for arranging a semi-continuous transportation system shared by open-pit coal mining, so as to solve the problems of unreasonable layout of the existing semi-continuous mining process in coal mining, low mining efficiency due to the inability to survive in the northern winter, etc.
[0004] To achieve the above object, the technical solution adopted by the present invention is:
[0005] A method for arranging a semi-continuous transportation system for open-pit coal mining and stripping, comprising the following steps:
[0006] S1: A crushing station is set up on the production working surface of the open-pit mine, and the crushing station is connected to the receiving side of the lifting belt conveyor. The unloading side of the lifting belt conveyor extends along the production working surface and lifts and transports the coal material to the first or second end step of the surface around the open-pit mine, and the lifting belt conveyor is also arranged to the adjacent coal seam step;
[0007] S2: The main belt conveyor is arranged on the surface around the open-pit mine, and one side of its receiving end is connected to the discharge end of the lifting belt conveyor. The discharge end of the main belt conveyor is located in the open-pit mine dump. The main belt conveyor adjusts the positions of the receiving end and the discharge end in time as the mining and stripping work line moves forward;
[0008] S3: The diverting transfer belt conveyor is located on the step of the dumping field in the extended direction of the main belt conveyor, and is arranged perpendicular to the dumping work line. Its receiving end is connected to the discharge end of the main belt conveyor, and the discharge end of the diverting transfer belt conveyor is connected to the coal conveying belt conveyor. A sliding chute is installed on the frame of the diverting transfer belt conveyor, and a discharge car is installed on the chute. The discharge car can travel along the belt;
[0009] S4: The coal storage bidirectional belt conveyor is arranged on one side of the soil dumping site near the end wall, with a length of 300 to 500 meters. One end is located below the unloading vehicle of the diversion transfer belt conveyor, and is equipped with a dual-purpose device for receiving and unloading materials. The lower part of the other end is connected to a rotating unloading trough. The upper end of the rotating unloading trough is funnel-shaped and is installed on the surface of a rotatable disc as a whole. The large mouth of the funnel is aligned with the discharge port of the coal storage bidirectional belt conveyor to receive materials. The small mouth of the funnel can rotate with the rotatable disc and be aligned with the coal unloading belt or the soil dumping belt conveyor respectively, so as to transfer the transported raw coal to the coal unloading belt and transport it to the coal storage yard of the soil dumping flat plate, or transfer the transported stripping material to the soil dumping belt conveyor and finally discharge it. A loading funnel is installed near the unloading end of the coal storage bidirectional belt conveyor. By changing the transportation direction, the stockpiled raw coal is transported back to the diversion transfer belt conveyor;
[0010] S5: The soil discharge belt conveyor discharges the stripping material to the soil discharge step. The coal transport belt conveyor is connected to the surface transportation system of the open-pit mine to transport the material to the designated location on the surface. In summer, when the demand for coal is low, the system is mainly used for stripping. The crushed stripping material is transported to the open-pit mine soil discharge yard (7) through the lifting belt conveyor (3), the main belt conveyor (6), the diversion transfer belt conveyor (8), the coal storage bidirectional belt conveyor (11), and the soil discharge belt conveyor (15). When the soil discharge belt conveyor (15) is moved, it is used for coal mining. In winter, when the demand for coal is high, the system is mainly used for coal mining. The raw coal is transported out through the lifting belt conveyor (3), the main belt conveyor (6), the diversion transfer belt conveyor (8), and the coal transport belt conveyor (9). When the coal transport belt conveyor (9) fails, the raw coal is stored on the flat plate of the dumping yard through the coal storage bidirectional belt conveyor (11); when the crushing station (1), the lifting belt conveyor (3), the main belt conveyor (6) and the like fail or the crushing station (1) and the lifting belt conveyor (3) need to be relocated, the raw coal stored in the coal storage yard is collected to meet the market demand, and the daily coal mining operation time is the ratio of the daily coal demand to the system coal mining capacity.
[0011] Furthermore, the crushing station and the lifting belt conveyor are arranged in groups, with at least two groups arranged.
[0012] Furthermore, a vibration device is arranged inside the rotary discharge chute 12 .
[0013] Preferably, in step S5, the material is first discharged to the bottom of the belt, and then gradually covered from the low place to the high place.
[0014] The beneficial effects of the method of the present invention are:
[0015] Realize efficient use of the crushing station, lifting belt conveyor, and trunk belt conveyor system throughout the year; improve the total production capacity of the semi-continuous process system of the open-pit mine, expand the coal supply capacity in the peak season, and promote the transformation of coal mine production capacity from rigid to elastic; use the step space slightly below the surface of the inner dump to store coal, which has less impact on the original production system of the open-pit mine, improves the emergency supply capacity of the open-pit mine, and avoids dust pollution in the open-pit coal storage yard. The equipment required by the system is all existing equipment, which can be standardized, reducing system costs and operating difficulties. The semi-continuous process system of mining and stripping shares one end wall, leaving one end wall for trucks to use, avoiding the intersection of different transportation methods. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is the layout diagram of the mine system;
[0017] Figure 2 Provide a simplified diagram of the system layout;
[0018] Figure 3 It is the relationship diagram between the diversion transfer belt conveyor and the coal storage bidirectional belt conveyor;
[0019] Figure 4 This is the relationship diagram between the coal storage bidirectional belt conveyor and the adjacent systems.
[0020] In the figure, 1-crushing station; 2-production working face; 3-lifting belt conveyor; 4-surrounding surface of open-pit mine; 5-end wall; 6-main line belt conveyor; 7-open-pit mine spoil dump; 8-diversion transfer belt conveyor; 9-coal belt conveyor; 10-unloading vehicle, 11-coal storage bidirectional belt conveyor; 12-rotating unloading chute; 13-rotatable disc, 14-coal unloading belt, 15-soil discharge belt conveyor, 16-coal storage yard. DETAILED DESCRIPTION
[0021] The present invention will be further described in detail below in conjunction with the accompanying drawings.
[0022] A method for arranging a semi-continuous transportation system for open-pit coal mining and stripping, comprising the following steps:
[0023] S1: On the production working face 2 of the open-pit mine, a crushing station 1 is set up, and the crushing station 1 is connected to the receiving side of the lifting belt conveyor 3. The unloading side of the lifting belt conveyor 3 extends along the production working face and lifts and transports the coal material to the first or second end wall 5 step of the surface 4 around the open-pit mine, and the lifting belt conveyor 3 is also arranged to the adjacent coal seam step. In order to increase the mining efficiency, the crushing station 1 and the lifting belt conveyor 3 are arranged in groups, at least 2 groups are arranged, and alternate relocation can be achieved to maintain the continuity of open-pit mine production. The group configuration can also avoid the failure of individual equipment causing the entire system to stop working and delay mining.
[0024] S2: The main belt conveyor 6 is arranged on the surface 4 around the open-pit mine, and one side of its receiving end is connected to the discharge end of the lifting belt conveyor 3. The discharge end of the main belt conveyor 6 is located at the open-pit mine dump 7. The main belt conveyor 6 moves forward along the mining and stripping line, and the positions of the receiving end and the discharge end are adjusted in time. Figure 1 and 2 shown.
[0025] S3: The diverting transfer belt conveyor 8 is located in the extension direction of the main belt conveyor 6 on the step of the dumping field, and is arranged perpendicular to the dumping working line. Its receiving end is connected to the discharge end of the main belt conveyor 6, and the discharge end of the diverting transfer belt conveyor 8 is connected to the coal conveying belt conveyor 9. A slidable chute is installed on the frame of the diverting transfer belt conveyor 8, and a discharge vehicle 10 is installed on the chute. The discharge vehicle 10 can travel along the belt;
[0026] S4: The coal storage bidirectional belt conveyor 11 is arranged on the side of the dumping site near the end wall 5, with a length of 300 to 500 meters. One end is located below the unloading vehicle 10 of the diversion transfer belt conveyor 8, and is equipped with a dual-purpose device for receiving and unloading materials. The lower part of the other end is connected to a rotating unloading trough 12. The upper end of the rotating unloading trough 12 is funnel-shaped and is installed on the surface of a rotatable disc 13. The large mouth of the funnel is aligned with the discharge port of the coal storage bidirectional belt conveyor 11 to receive materials. The small mouth of the funnel can rotate with the rotatable disc 13 and is aligned with the coal unloading belt 14 or the dumping belt conveyor 15 respectively, so as to transfer the transported raw coal to the coal unloading belt 14 and transport it to the coal storage field 16 of the dumping site flat plate, or transfer the transported stripping material to the dumping belt conveyor 15 and finally discard it. When transporting large pieces of coal materials, too much material will accumulate in the channel, and it will be blocked because there is no time to transport it. In order to avoid this problem inside, a vibration device is arranged inside the rotating unloading trough 12. A loading hopper is installed near the unloading end of the coal storage bidirectional belt conveyor 11, which changes the transportation direction and transports the stored raw coal back to the diversion transfer belt conveyor 8. Figure 3 and 4 shown.
[0027] S5: The soil discharge belt conveyor 15 discharges the stripping material to the soil discharge step, and the coal conveyor belt conveyor 9 is connected to the surface transportation system of the open-pit mine to transport the material to the designated position on the surface. The soil discharge first discharges the material to the bottom of the belt, gradually covers from low to high, and gradually discharges soil from low to high, so that the mining surface is kept as flat as possible without landslides.
[0028] The method of the present invention is adopted to implement the layout of the semi-continuous transportation system for mining and stripping in the open-pit mine, which can realize the simultaneous mining of coal resources and the disposal of waste materials. On the production working face 2 of the open-pit mine, the mined raw coal materials are crushed by the crushing station 1 and then transported to the end wall 5 at a higher horizontal height by the lifting belt conveyor 3, and then transported to the main belt conveyor 6, and transported along the forward movement of the mining and stripping working line to the subsequent diversion transfer belt conveyor 8, and then transported to the surface of the open-pit mine by the coal conveying belt conveyor 9 arranged immediately afterwards, and transported out in a centralized manner.
[0029] A sliding chute for the unloading vehicle 10 to travel is installed on the diverting and transferring belt conveyor 8, so that the unloading vehicle 10 can transfer materials from the diverting and transferring belt conveyor 8 to the coal storage bidirectional belt conveyor 11, because both ends of the coal storage bidirectional belt conveyor 11 can receive and discharge materials, and free back and forth transfer can be achieved. The materials transported by the coal storage bidirectional belt conveyor 11 pass through the rotating unloading chute 12 and selectively fall onto the coal unloading belt 14 or the soil discharge belt conveyor 15. When coal needs to be transported, the coal unloading belt 14 is selected to transport it to the coal storage field 16 on the soil discharge field flat plate. When waste materials such as stripping materials need to be transported, the soil discharge belt conveyor 15 is selected to send the materials out for disposal.
[0030] According to the production characteristics of the open-pit mine in different seasons, the operation process of different transportation systems is determined. Summer is the traditional off-season for coal demand, and the system is mainly stripping. The crushed stripping material is transported to the dumping site through the lifting belt conveyor 3, the main belt conveyor 6 system, the diversion transfer belt conveyor 8, the coal storage two-way belt conveyor 11, and the soil removal belt conveyor 15 system. The soil removal belt conveyor 15 is used for coal mining when it is relocated; winter is the traditional peak season for coal demand, and the system is mainly coal mining. The crushed raw coal is transported out through the lifting belt conveyor 3, the main belt conveyor 6 system, the diversion transfer belt conveyor 8, and the coal conveying belt conveyor 9 system. When the coal conveying belt conveyor 9 system fails, the raw coal is stored on the dumping site flat plate through the coal storage two-way belt conveyor 11; when the crushing station 1, the lifting belt conveyor 3, the main belt conveyor 6 system, etc. fail or the crushing station 1 and the lifting belt conveyor 3 need to be relocated, the raw coal stored in the coal storage site 16 is collected to meet market demand. The system adopts a time-sharing operation mode for mining and stripping, giving priority to the production needs of raw coal. The daily coal mining operation time during normal production period is:
[0031] T=Q / q
[0032] Where: T is the time the system serves coal mining operations, h; Q is the daily coal demand of the open-pit mine, t; q is the system coal mining capacity, t / h.
[0033] The whole system has a reasonable layout and is easy to operate. It can realize seasonal production, which is more reasonable and efficient.
Claims
1. A method for arranging a semi-continuous transportation system for open-pit coal mining, characterized in that: The following steps are involved: S1: A crushing station (1) is arranged on the production working face (2) of an open-pit mine, and the crushing station (1) is connected to the receiving side of a lifting belt conveyor (3). The unloading side of the lifting belt conveyor (3) extends along the production working face (2) and lifts and transports the coal material to the first or second end wall (5) step of the surface (4) around the open-pit mine, and the lifting belt conveyor (3) is also arranged to the adjacent coal seam step; S2: The main line belt conveyor (6) is arranged on the surface (4) around the open-pit mine, and one side of its receiving end is connected to the discharge end of the lifting belt conveyor (3). The discharge end of the main line belt conveyor (6) is located in the open-pit mine dump (7). The main line belt conveyor (6) adjusts the positions of the receiving end and the discharge end in time as the mining and stripping working line moves forward; S3: The diverting transfer belt conveyor (8) is located on the step of the dumping field in the extension direction of the main belt conveyor (6), and is arranged perpendicular to the dumping working line. Its receiving end is connected to the discharge end of the main belt conveyor (6), and the discharge end of the diverting transfer belt conveyor (8) is connected to the coal conveying belt conveyor (9). A slidable chute is installed on the frame of the diverting transfer belt conveyor (8), and a discharge vehicle (10) is installed on the chute. The discharge vehicle (10) can travel along the belt; S4: The coal storage bidirectional belt conveyor (11) is arranged on one side of the dumping site close to the end wall (5), with a length of 300 to 500 meters. One end is located below the unloading vehicle (10) of the diversion and transfer belt conveyor (8), and is equipped with a dual-purpose device for receiving and unloading materials. The lower part of the other end is connected to a rotating unloading trough (12). The upper end of the rotating unloading trough (12) is funnel-shaped and is integrally installed on the surface of a rotatable disc (13). The large mouth of the funnel is aligned with the discharge port of the coal storage bidirectional belt conveyor (11) to receive materials, and the small mouth of the funnel is aligned with the discharge port of the coal storage bidirectional belt conveyor (11) to receive materials. The opening can rotate with the rotatable disc (13) and be aligned with the coal unloading belt (14) or the soil discharge belt conveyor (15) respectively, so as to transfer the transported raw coal to the coal unloading belt (14) and transport it to the coal storage yard (16) on the soil discharge flat plate, or transfer the transported stripping material to the soil discharge belt conveyor (15) and finally discharge it. A loading funnel is installed near the unloading end of the coal storage bidirectional belt conveyor (11), and the stored raw coal is transported back to the diversion transfer belt conveyor (11) by changing the transportation direction; S5: The soil discharge belt conveyor (15) discharges the stripping material to the soil discharge step. The coal transport belt conveyor (9) is connected to the surface transportation system of the open-pit mine to transport the material to the designated location on the surface. In summer, when the demand for coal is low, the system is mainly used for stripping. The crushed stripping material is transported to the open-pit mine soil discharge yard (7) through the lifting belt conveyor (3), the main belt conveyor (6), the diversion transfer belt conveyor (8), the coal storage bidirectional belt conveyor (11), and the soil discharge belt conveyor (15). When the soil discharge belt conveyor (15) is moved, it is used for coal mining. In winter, when the demand for coal is high, the system is mainly used for coal mining. The crushed raw coal is transported out through the lifting belt conveyor (3), the main belt conveyor (6), the diversion transfer belt conveyor (8), and the coal transport belt conveyor (9). When the coal transport belt conveyor (9) fails, the raw coal is stored on the flat plate of the dumping yard through the coal storage bidirectional belt conveyor (11); when the crushing station (1), the lifting belt conveyor (3), the main belt conveyor (6) and the like fail or the crushing station (1) and the lifting belt conveyor (3) need to be relocated, the raw coal stored in the coal storage yard is collected to meet the market demand, and the daily coal mining operation time is the ratio of the daily coal demand to the system coal mining capacity.
2. The method for arranging a semi-continuous transportation system for open-pit coal mining and stripping according to claim 1 is characterized in that: The crushing station (1) and the lifting belt conveyor (3) are arranged in a group.
3. A method for arranging a semi-continuous transportation system for open-pit coal mining and stripping according to claim 1 or 2, characterized in that: A vibration device is arranged inside the rotary discharge chute (12).
4. A method for arranging a semi-continuous transportation system for open-pit coal mining and stripping according to claim 1 or 2, characterized in that: Step S5: First, the material is discharged to the bottom of the belt, and then gradually covered from the low to the high.
Citation Information
Patent Citations
Pumper and pipeline transportation type semicontinuous mining transportation technology for open-pit mine
CN104847357A
Semi-continuous mining system of single body moving type complete equipment
CN107100626A
Device and method for continuous mining of medium-thickness coal seam of inner dumping open pit coal mine
CN108756875A
Stripping semi-continuous dumping process for open pit coal mine
CN113047840A
Energy-saving transportation mining method for open pit coal mine
CN113847034A