Modularized steel wire load-holding corrosion device

Through the modularly designed wire load-holding corrosion device, the efficient clamping of steel wires of different numbers and lengths is achieved by using spliced ​​steel plates and clamping anchors, which solves the problems of complex installation and fixed size of existing devices, and improves the applicability of the test and efficiency.

CN119064253APending Publication Date: 2024-12-03CHINA RAILWAY MAJOR BRIDGE ENG GRP CO LTD +4
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411334706.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-24
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

The existing wire load-holding corrosion devices are complex in transportation and installation, and the size is fixed, making them difficult to adapt to different models of salt spray boxes, and cannot be applied efficiently and conveniently to corrosion tests of different numbers and lengths of steel wires.

Method used

A modular steel wire load-holding corrosion device is designed, and the integral steel plate is formed by splicing multiple module steel plates, combining clamping anchors and loading mechanisms to realize load adjustment and clamping of steel wires, adapting to different sizes of salt spray boxes and steel wires. length.

Benefits of technology

It realizes rapid installation and modular transportation, can clamp steel wires of different numbers and lengths, simulates stress corrosion under actual working conditions, and enhances the efficiency and applicability of the test.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119064253A_ABST
    Figure CN119064253A_ABST
Patent Text Reader

Abstract

The invention relates to a modularized steel wire load-holding corrosion device which comprises a plurality of module steel plates which are spliced to form two integral steel plates. The clamping anchorage device is mounted on the two integral steel plates and is used for clamping a steel wire; and the loading mechanism is arranged between the two integral steel plates and is used for adjusting the distance between the two integral steel plates and applying a load to the steel wire. Load is applied to the steel wire through the clamping anchorage device and the loading mechanism, the tensioning state of the steel wire is kept, the stress condition of the steel wire under the actual working condition is simulated, and stress accelerated corrosion of the steel wire in the actual environment is effectively reduced. Clamping of any number of steel wires is achieved through splicing of the multiple module steel plates, the steel wire load-holding corrosion device can adapt to the sizes of salt mist boxes of different models by adjusting the splicing mode of the module steel plates, the distance between the two whole steel plates is adjusted through the loading mechanism, and the steel wires of different lengths can be clamped; the purpose of clamping steel wires with different numbers and lengths is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of steel wire sustained load corrosion detection, and in particular to a modular steel wire sustained load corrosion device. Background Art

[0002] In recent years, my country's long-span bridge system has developed rapidly, among which cable-stayed bridges and suspension bridges have been widely used due to their strong spanning capacity and reasonable stress performance; but there are also some problems such as corrosion and degradation of bridge steel wires during long-term service, which seriously affects the service safety of long-span bridges. In addition to the chemical reaction between steel wires and water vapor, oxygen and acidic ions in the environment during use, which leads to surface corrosion, there is also stress-accelerated corrosion under the combined action of stress and corrosive media. At present, steel wire corrosion tests mainly use salt spray chambers to artificially simulate chemical corrosion in the environment, but there is little research on stress corrosion schemes for steel wires.

[0003] In the related art, the steel wire load-supported corrosion device has the problems of complex transportation and installation, fixed device size, difficulty in adapting to salt spray chambers of different models, and can only meet the corrosion test of steel wires of fixed number and length, and cannot be efficiently and conveniently used in the steel wire load-supported corrosion test. Summary of the invention

[0004] The present application provides a modular steel wire sustained load corrosion device, which can solve the problems of the steel wire sustained load corrosion device in the related art, such as complex transportation and installation, fixed device size, difficulty in adapting to salt spray chambers of different models, and only being able to meet the corrosion test of steel wires of a fixed number and length, and not being able to be efficiently and conveniently applied to the steel wire sustained load corrosion test.

[0005] In the first aspect, an embodiment of the present application provides a modular steel wire load-holding corrosion device, which includes: a plurality of modular steel plates, which are spliced ​​to form two integral steel plates; a clamping anchor, which is installed on the two integral steel plates and is used to clamp the steel wire; and a loading mechanism, which is installed between the two integral steel plates and is used to adjust the distance between the two integral steel plates and apply a load to the steel wire.

[0006] In combination with the first aspect, in one implementation, the module steel plate is square, and four sides are provided with connecting tenons and connecting mortise and tenon joints, and two adjacent module steel plates are spliced ​​by the connecting tenons and connecting mortise and tenon joints.

[0007] In combination with the first aspect, in one embodiment, a first mounting hole is provided on the module steel plate, the first mounting hole is connected to the connecting mortise, a second mounting hole is provided on the connecting mortise, and connecting bolts are installed in the first mounting hole of one module steel plate and the second mounting hole of another adjacent module steel plate.

[0008] In combination with the first aspect, in one embodiment, two adjacent module steel plates are provided with matching semicircular third mounting holes on their sides close to each other, and after the two module steel plates are spliced ​​together, the third mounting holes can form a circular hole, and the loading mechanism is installed in the circular hole.

[0009] In combination with the first aspect, in one embodiment, the loading mechanism includes: a support screw rod, which is passed through the circular hole; a loading nut, which is installed on the support screw rod, and the loading nut is located on the side where the two integral steel plates are close to each other; a positioning nut, which is installed on the support screw rod, and the positioning nut is located on the side where the two integral steel plates are away from each other.

[0010] In combination with the first aspect, in one embodiment, reinforcing steel plates are provided on both sides of the circular hole, a fifth mounting hole is provided in the center of the reinforcing steel plate, the support screw is passed through the fifth mounting hole, and grooves are provided around the reinforcing steel plate.

[0011] In combination with the first aspect, in one embodiment, sixth mounting holes are opened at four corners of the reinforcement steel plate, connecting bolts are installed in the sixth mounting holes, and the connecting bolts are fixed in the first mounting holes of the module steel plate.

[0012] In combination with the first aspect, in one embodiment, the clamping anchor comprises an anchor sleeve and a clamp sleeved on the inner side of the anchor sleeve, a wire hole is provided in the clamp, and an inner wall of the wire hole is provided with a thread.

[0013] In combination with the first aspect, in one embodiment, the anchor sleeve is in a cylindrical shape with a conical cavity formed inside, and the clamp is in a shape matching the cavity.

[0014] In combination with the first aspect, in one embodiment, the clamp is formed by a plurality of clips, and the outer sides of the plurality of clips are fixed by a circular ring.

[0015] In a second aspect, an embodiment of the present application provides a method for using a modular steel wire load-holding corrosion device, which may include the following steps:

[0016] Determine the number of modular steel plates according to the number of steel wires required for the test, splice multiple modular steel plates into the integral steel plate through the connecting tenons and mortises, and further fix the connecting bolts through the second mounting hole and the first mounting hole; place the steel wire in the fourth mounting hole; install the clamping anchors at both ends of the steel wire to fasten it to the integral steel plate, and at this time, the bottom of the clamping anchor should fit with the integral steel plate; place the support screw in the third mounting hole; tighten the positioning nut according to the length of the steel wire required for the test to adjust the distance between the integral steel plates, and pre-tighten the loading nut after the distance between the integral steel plates reaches the test requirements; tighten the loading nut to tension the steel wire, and tighten the positioning nut after the steel wire is tensioned to the test load to complete the assembly of the steel wire load-holding corrosion device; finally, place the installed steel wire load-holding corrosion device in a salt spray chamber to conduct an indoor accelerated corrosion test.

[0017] In combination with the second aspect, in one embodiment, after a plurality of the modular steel plates are assembled into the integral steel plate, in order to enhance the overall stability and rigidity of the steel wire load-bearing corrosion device, it also includes: adding reinforcing steel plates between the modular steel plates, a fifth mounting hole is opened in the middle of the reinforcing steel plate to place the loading mechanism, and sixth mounting holes are opened around the four sides to place the connecting bolts.

[0018] In combination with the second aspect, in one embodiment, when the strength of the steel wires is too high or the number is too large, jacks may be arranged on both sides of the device to assist in loading.

[0019] In combination with the second aspect, in one embodiment, a strain gauge may be arranged on the surface of the steel wire or a pressure sensor may be arranged under the clamping anchor to verify that the steel wire reaches a specified load.

[0020] In combination with the second aspect, in one implementation, the number of module steel plates 1 can be flexibly arranged according to the size of the salt spray box, and multiple steel wire load-holding corrosion devices can be placed in one salt spray box.

[0021] The principles of the modular steel wire load-holding corrosion device provided by the embodiment of the present invention include:

[0022] The modular steel wire load-holding corrosion device provided in the embodiment of the present invention applies load to the steel wire through a clamping anchor and a loading mechanism and maintains its tensioned state, so as to simulate the stress condition of the steel wire under actual working conditions and effectively restore the stress-accelerated corrosion of the steel wire in the actual environment; the clamping of any number of steel wires can be achieved by assembling multiple modular steel plates, and the steel wire load-holding corrosion device can be adapted to the size of the salt spray chamber by adjusting the splicing method of the modular steel plates, so as to achieve the purposes of rapid installation, modular transportation, and clamping of different numbers of steel wires.

[0023] The beneficial effects brought by the technical solution provided by the embodiments of the present application include:

[0024] The embodiment of the present invention provides a modular steel wire load-holding corrosion device, which applies load to the steel wire through a clamping anchor and a loading mechanism and maintains its tensioned state to simulate the stress condition of the steel wire under actual working conditions, and effectively restores the stress-accelerated corrosion of the steel wire in the actual environment; the clamping of any number of steel wires can be achieved by assembling multiple modular steel plates, and the steel wire load-holding corrosion device can be adapted to the sizes of salt spray chambers of different models by adjusting the splicing method of the modular steel plates; the distance between the two integral steel plates is adjusted by the loading mechanism, so that steel wires of different lengths can be clamped, thereby achieving the purposes of rapid installation, modular transportation, and clamping of steel wires of different numbers and lengths. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0026] Figure 1 A schematic diagram of the structure of a modular steel wire load-holding corrosion device provided in an embodiment of the present invention for two steel wires;

[0027] Figure 2 A schematic diagram of the structure of a modular steel wire load-holding corrosion device provided in an embodiment of the present invention for four steel wires;

[0028] Figure 3 A schematic diagram of the structure of a loading mechanism provided by an embodiment of the present invention;

[0029] Figure 4 A schematic diagram of the structure of a clamping anchor provided by an embodiment of the present invention;

[0030] Figure 5 A schematic diagram of the structure of a clamp provided in an embodiment of the present invention; Figure 6 A schematic diagram of the structure of a modular steel wire load-holding corrosion device provided in an embodiment of the present invention for four steel wires;

[0031] Figure 7 A schematic structural diagram of a reinforced steel plate provided in an embodiment of the present invention.

[0032] Numbers in the figure:

[0033] 1. Module steel plate; 11. Connecting tenon; 12. Connecting mortise; 13. First mounting hole; 14. Second mounting hole; 15. Third mounting hole; 16. Fourth mounting hole; 2. Clamping anchor; 21. Anchor sleeve; 22. Clamp; 23. Clip; 24. Ring; 3. Loading mechanism; 31. Support screw; 32. Positioning nut; 33. Loading nut; 4. Connecting bolt; 5. Reinforcement steel plate; 51. Fifth mounting hole; 52. Sixth mounting hole; 53. Groove; 10. Integral steel plate. DETAILED DESCRIPTION

[0034] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0035] The embodiment of the present application provides a modular steel wire sustained load corrosion device, which can solve the problems of the steel wire sustained load corrosion device in the related art, such as complex transportation and installation, fixed device size, difficulty in adapting to salt spray chambers of different models, and only being able to meet the corrosion test of steel wires of a fixed number and length, and not being able to be efficiently and conveniently applied to the steel wire sustained load corrosion test.

[0036] See also Figure 1 As shown, a modular steel wire load-holding corrosion device is provided for an embodiment of the present invention, which may include: a plurality of modular steel plates 1, wherein the plurality of modular steel plates 1 are spliced ​​together through connecting tenons 11 and connecting mortise 12 to form two integral steel plates 10, a fourth mounting hole 16 and a third mounting hole 15 are provided on the modular steel plates 1 to place steel wires and a loading mechanism 3 respectively, a second mounting hole 14 and a hole four are provided on the connecting tenons 11 and the connecting mortise 12 to place connecting bolts 4 respectively; a plurality of clamping anchors 2, wherein the clamping anchors 2 include anchor sleeves 21 and clamps 22 for clamping and tightening steel wires, and a steel wire Two clamping anchors 2 are provided; at least one loading mechanism 3, which consists of a supporting screw 31, a positioning nut 32 and a loading nut 33, wherein the supporting screw 31 is placed in the third mounting hole 15 of the module steel plate 1, the positioning nut 32 is used to adjust and fix the distance between the two integral steel plates 10, and the loading nut 33 is used to apply a load to the steel wire; a plurality of connecting bolts 4, which fix the plurality of module steel plates 1 through the second mounting holes 14 and the first mounting holes 13 on the connecting tenons 11 and the connecting mortises 12, thereby improving the stability of the integral steel plate 10.

[0037] Specifically, the steel wire load-holding corrosion device provided by the embodiment of the present invention includes components such as a module steel plate 1, a clamping anchor 2, a loading mechanism 3 and a connecting bolt 4, which are detachable and easy to install, and are convenient for transportation and storage; in addition, the device tensions the steel wire and maintains it within a certain stress range through the clamping anchor 2 and the loading mechanism 3, so the loading is simple and the operation is convenient; finally, the device splices a plurality of module steel plates 1 into an integral steel plate 10 of different shapes, thereby achieving the clamping and loading of any number of steel wires, and can adapt to different salt spray chamber sizes, has a wide range of applications, and can meet the requirements of most steel wire stress corrosion tests.

[0038] like Figure 1 As shown, one embodiment of the steel wire load-holding corrosion device of the present invention is shown, which includes four module steel plates 1, four clamping anchors 2, a loading mechanism 3 and eight connecting bolts 4, which can clamp and tighten two steel wires; by adding module steel plates 1 and other components, the installation and loading of multiple steel wires can be realized.

[0039] Specifically, if the number of steel wires required for the test is N, 2N modular steel plates 1 and 2N clamping anchors 2 are required, and a corresponding number of loading mechanisms 3 and connecting bolts 4 are selected according to the shape of the overall steel plate 10 .

[0040] like Figure 1 As shown, in some embodiments, the modular steel plate 1 provided in the embodiment of the present invention is spliced ​​into an integral steel plate 10 by connecting tenons 11 and mortises 12, and is further fixed by connecting bolts 4.

[0041] Specifically, each side of the module steel plate 1 has a connecting tenon 11 and a connecting mortise 12 for splicing in various directions, thereby forming an integral steel plate 10 of different shapes, which can be placed in a salt spray chamber of any volume.

[0042] Preferably, the length and width of the module steel plate 1 should be equal to facilitate the assembly of the connecting tenon 11 and the connecting mortise 12, and should not be less than 120 mm to facilitate the anchoring of multiple groups of steel wires and the tightening of the loading nut 33; in addition, the thickness of the module steel plate 1 should not be less than 20 mm to meet the force requirements of the device.

[0043] Preferably, the fourth mounting hole 16 of the modular steel plate 1 should be slightly larger than the diameter of the steel wire; for a steel wire with a diameter of 5 mm, the diameter of the fourth mounting hole 16 can be selected to be 6 mm; for a steel wire with a diameter of 7 mm, the diameter of the fourth mounting hole 16 can be selected to be 8 mm.

[0044] Preferably, the module steel plate 1 needs to be made of stainless steel or undergo anti-corrosion treatment such as galvanizing or spraying to prevent the corrosion of the steel plate from affecting the steel wire.

[0045] Specifically, the connecting tenon 11 and the connecting mortise 12 have the same size, so as to realize the connection of multiple module steel plates 1; the connecting tenon 11 and the connecting mortise 12 are respectively provided with a second mounting hole 14 and a first mounting hole 13 at the ends thereof, and after the mortise and tenon connection, the second mounting hole 14 and the first mounting hole 13 should be in the same position to facilitate the placement of the connecting bolt 4.

[0046] Specifically, the connecting bolt 4 should be a bolt of M5 or above in "Tightening Mechanical Properties of Stainless Steel Bolts, Screws and Studs" (GB / T3098.6-2023), and the diameter of the second mounting hole 14 and the first mounting hole 13 should be slightly larger than the diameter of the connecting bolt 4 for easy connection.

[0047] See also Figure 4 and Figure 5 As shown, in some embodiments, a clamping anchor 2 is provided for an embodiment of the present invention, and the clamping anchor 2 includes an anchor sleeve 21 and a clamp 22; the anchor sleeve 21 is used to fix the clamp 22, and a wire hole is left inside the clamp 22. Different types of clamps 22 need to be selected according to different wire diameters.

[0048] Preferably, the anchor sleeve 21 can be made of 40Cr material, and the clamp 22 can be made of 20CrMnTi material; the anchor sleeve 21 has an outer shape of a cylinder, and a conical cavity is provided inside to fix the clip and thus tighten the steel wire, and the clamp 22 is composed of a plurality of clips 23, the appearance of the clip 23 matches the cavity of the anchor sleeve 21, and a groove is provided on it to place an elastic ring 24 for fixing, and a thread is provided on the inner side of the clip 23 for tightening the steel wire.

[0049] See also Figure 3 As shown, a loading mechanism 3 is provided in an embodiment of the present invention, and the loading mechanism 3 includes a supporting screw 31, a positioning nut 32 and a loading nut 33; the supporting screw 31 is used to connect and support the two integral steel plates 10, the positioning nut 32 is used to fix the positions of the two integral steel plates 10 to ensure that the distance between the steel wires meets the test requirements, and the loading nut 33 is used to apply load and cooperate with the clamping anchor 2 to maintain the steel wire at a certain stress level.

[0050] Specifically, the support screw 31 should adopt a full-thread screw with specifications of M20 or above in the "Stainless Steel Bolts, Screws and Studs for Mechanical Properties of Fasteners" (GB / T3098.6-2023), and the positioning nut 32 and the loading nut 33 should adopt nuts with specifications of M20 or above in the "Stainless Steel Nuts for Mechanical Properties of Fasteners" (GB / T 3098.15-2023).

[0051] Specifically, the loading nut 33 is placed in the third mounting hole 15 between the plurality of module steel plates 1 . The diameter of the third mounting hole 15 should be adjusted according to different types of loading nuts 33 , and the diameter of the third mounting hole 15 should be slightly larger than the loading nut 33 .

[0052] like Figure 2 and Figure 6 As shown, two types of four-wire load-holding corrosion devices provided by the embodiments of the present invention are based on Figure 1 The basic steel wire load-holding corrosion device realizes the installation and loading of four steel wires by adding components such as module steel plates 1 and loading nuts 33; since the module steel plates 1 are provided with connecting tenons 11 and connecting mortises 12 on all sides, multiple module steel plates 1 can be spliced ​​into integral steel plates 10 of different shapes, which can adapt to salt spray chambers of different volumes.

[0053] like Figure 7 As shown, in some embodiments, when there are too many modular steel plates 1, in order to further enhance the stability of the overall steel plate 10, an embodiment of the present invention provides a reinforcing steel plate 5, grooves are arranged around the reinforcing steel plate 5 to avoid collision with the clamping anchor 2, a fifth mounting hole 51 is opened in the middle to place the loading mechanism 3, and sixth mounting holes 52 are opened around to place the connecting bolts 4.

[0054] like Figure 6 As shown, the reinforced four-wire load-holding corrosion device provided in an embodiment of the present invention can further enhance the stability of the overall steel plate 10 by adding a reinforced steel plate 5 on the overall steel plate 10, and the reinforced steel plate 5 can be adapted to overall steel plates 10 of different shapes.

[0055] The embodiment of the present invention also provides a method for using the modular steel wire load-holding corrosion device, which may include the following steps:

[0056] The number of the module steel plates 1 is determined according to the number of steel wires required for the test, and multiple module steel plates 1 are spliced ​​into the integral steel plate 10 through the connecting tenons 11 and mortises 12, and the connecting bolts 4 are passed through the second mounting holes 14 and the first mounting holes 13 to further fix them.

[0057] Place the steel wire in the fourth mounting hole 16 ; install the clamping anchor 2 at both ends of the steel wire to fasten it to the integral steel plate 10 , and at this time, the bottom of the clamping anchor 2 should fit with the integral steel plate 10 .

[0058] Place the support screw 31 in the third mounting hole 15; tighten the positioning nut 32 according to the required length of the steel wire for the test to adjust the distance between the integral steel plates 10, and pre-tighten the loading nut 33 after the distance between the integral steel plates 10 reaches the test requirement.

[0059] The loading nut 33 is tightened to tension the steel wire, and after the steel wire is tensioned to the test load, the positioning nut 32 is tightened to complete the assembly of the steel wire load-holding corrosion device.

[0060] Finally, the installed steel wire load-holding corrosion device is placed in a salt spray chamber for an indoor accelerated corrosion test.

[0061] In some embodiments, after a plurality of the modular steel plates 1 are assembled into the integral steel plate 10, in order to enhance the overall stability and rigidity of the steel wire load-supported corrosion device, it also includes: adding a reinforcing steel plate 5 between the modular steel plates 1, a fifth mounting hole 51 is opened in the middle of the reinforcing steel plate 5 to place the loading mechanism 3, and sixth mounting holes 52 are opened around it to place the connecting bolts 4.

[0062] Furthermore, when the strength of the steel wires is too high or the number is too large, jacks can be arranged on both sides of the device to assist in loading.

[0063] Furthermore, strain gauges may be arranged on the surface of the steel wire or pressure sensors may be arranged under the clamping anchor 2 to verify that the steel wire reaches a specified load.

[0064] Furthermore, the number of the module steel plates 1 can be flexibly arranged according to the size of the salt spray box, and a plurality of steel wire load-holding corrosion devices can be placed in one salt spray box.

[0065] The principles of the modular steel wire load-holding corrosion device provided by the embodiment of the present invention include:

[0066] The modular steel wire load-holding corrosion device provided in the embodiment of the present invention applies load to the steel wire and maintains its tensioned state through the clamping anchor 2 and the loading mechanism 3, so as to simulate the stress condition of the steel wire under actual working conditions and effectively restore the stress-accelerated corrosion of the steel wire in the actual environment; the clamping of any number of steel wires can be achieved by assembling multiple modular steel plates 1, and the steel wire load-holding corrosion device can be adapted to the size of the salt spray chamber by adjusting the splicing method of the modular steel plates 1, so as to achieve the purpose of rapid installation, modular transportation, and clamping of different numbers of steel wires.

[0067] In the description of the present application, it should be noted that the terms "upper", "lower", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present application. Unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be a connection between the two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present application can be understood according to the specific circumstances.

[0068] It should be noted that, in this application, relational terms such as "first" and "second" are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the presence of other identical elements in the process, method, article or device including the elements.

[0069] The above description is only a specific implementation of the present application, so that those skilled in the art can understand or implement the present application. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein can be implemented in other embodiments without departing from the spirit or scope of the present application. Therefore, the present application will not be limited to the embodiments shown herein, but will conform to the widest range consistent with the principles and novel features applied for herein.

Claims

1. A modular steel wire load-holding corrosion device, characterized in that: It includes: A plurality of modular steel plates (1) are spliced ​​together to form two integral steel plates (10); A clamping anchor (2), which is installed on the two integral steel plates (10) and is used to clamp the steel wire; And a loading mechanism (3) is installed between the two integral steel plates (10) and is used to adjust the distance between the two integral steel plates (10) and apply a load to the steel wire.

2. The modular steel wire load-holding corrosion device according to claim 1, characterized in that: The module steel plate (1) is square, and four sides are provided with connecting tenons (11) and connecting mortises (12); two adjacent module steel plates (1) are spliced ​​together via the connecting tenons (11) and the connecting mortises (12).

3. The modular steel wire load-holding corrosion device according to claim 2, characterized in that: The module steel plate (1) is provided with a first mounting hole (13), the first mounting hole (13) is connected to the connecting mortise (12), the connecting mortise (11) is provided with a second mounting hole (14), and connecting bolts (4) are installed in the first mounting hole (13) of one module steel plate (1) and the second mounting hole (14) of another adjacent module steel plate (1).

4. The modular steel wire sustained load corrosion device according to claim 1, characterized in that: A matching semicircular third mounting hole (15) is provided on the side close to each other of two adjacent module steel plates (1); after the two module steel plates (1) are spliced ​​together, the third mounting hole (15) can form a circular hole, in which the loading mechanism (3) is installed.

5. The modular steel wire load-holding corrosion device according to claim 4, characterized in that: The loading mechanism (3) comprises: A support screw (31) is inserted into the circular hole; A loading nut (33) mounted on the support screw (31), wherein the loading nut (33) is located on a side where the two integral steel plates (10) are close to each other; A positioning nut (32) is mounted on the supporting screw rod (31), and the positioning nut (32) is located on a side of the two integral steel plates (10) that is away from each other.

6. The modular steel wire sustained load corrosion device according to claim 5, characterized in that: Reinforcement steel plates (5) are provided on both sides of the circular hole, a fifth mounting hole (51) is provided in the center of the reinforcement steel plate (5), the support screw (31) is inserted into the fifth mounting hole (51), and grooves (53) are provided around the reinforcement steel plate (5).

7. The modular steel wire sustained load corrosion device according to claim 6, characterized in that: Sixth mounting holes (52) are provided at four corners of the reinforcing steel plate (5), connecting bolts (4) are installed in the sixth mounting holes (52), and the connecting bolts (4) are fixed in the first mounting holes (13) of the module steel plate (1).

8. The modular steel wire sustained load corrosion device according to claim 1, characterized in that: The clamping anchor (2) comprises an anchor sleeve (21) and a clamp (22) sleeved on the inner side of the anchor sleeve (21); a wire hole is provided in the clamp (22); and a thread is provided on the inner wall of the wire hole.

9. The modular steel wire sustained load corrosion device according to claim 8, characterized in that: The anchor sleeve (21) is cylindrical in shape and has a conical cavity inside, and the clamp (22) is in a shape matching the cavity.

10. The modular steel wire sustained load corrosion device according to claim 8, characterized in that: The clamp (22) is formed by surrounding a plurality of clamps (23), and the outer sides of the plurality of clamps (23) are fixed by a circular ring (24).