Construction site arrangement optimization method and system, readable storage medium and electronic equipment
The integration of oblique photogrammetry and BIM with an ant colony algorithm optimizes construction site layout, addressing inaccuracies and inefficiencies in traditional methods by providing precise 3D models and optimizing resource allocation and safety, thus enhancing construction efficiency and safety.
Patent Information
- Application Number
- CN202411212813.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-30
- Publication Date
- 2024-12-03
AI Technical Summary
Traditional construction site layout methods rely on manual measurements and two-dimensional drawings, leading to inaccuracies, inefficiencies, and lack of scientific optimization, resulting in high costs, long durations, and safety risks.
A method combining oblique photogrammetry and BIM technology to create high-precision 3D models, integrated with an ant colony algorithm for optimizing site layout by minimizing transportation costs and safety risks, using optimization indicators and constraints to determine the final layout plan.
Improves accuracy and efficiency by reducing on-site surveys, minimizing errors, and optimizing resource allocation, thereby enhancing construction management and safety.
Smart Images

Figure CN119067261A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of construction layout, and in particular to a construction site layout optimization method, system, readable storage medium and electronic device. Background Art
[0002] In the construction of traditional building projects, because the projects are large, the cycle is long, and there are many stages, as an important part of the engineering construction organization design and the beginning of on-site construction, the general construction plan layout needs to be arranged in accordance with the requirements of the construction plan and progress, and the road traffic, material warehouses, processing sites, major machinery and equipment, temporary houses, pipelines, etc. on the construction site should be reasonably planned and arranged, so as to correctly handle the spatial relationship between the various facilities required during the construction of the entire site and the permanent structures and planned projects.
[0003] Currently, construction site layout usually relies on traditional two-dimensional drawings and manual measurement methods, which is not only time-consuming but also prone to errors. Based on this, BIM technology can provide more intuitive and detailed construction information through the establishment of a three-dimensional model, while oblique photogrammetry technology can quickly obtain a real three-dimensional model of the construction site. The combination of these two technologies can significantly improve the accuracy and efficiency of construction site layout. However, in actual applications, the combination of BIM and oblique photogrammetry technology is still in its early stages, and there are the following specific shortcomings:
[0004] 1. Accuracy issues: Traditional measurement methods rely on manual operation and empirical judgment, which are prone to errors. In addition, measurement is difficult and inefficient in complex terrain and large construction sites.
[0005] 2. Inefficiency: Traditional construction site layout requires multiple on-site surveys and repeated adjustments, which is time-consuming and labor-intensive, and is easily affected by weather and site conditions.
[0006] 3. Lack of optimization means: The existing construction site layout method lacks scientific optimization means and cannot make full use of site resources, resulting in long material transportation distances, high costs, and high safety risks. Summary of the invention
[0007] Based on this, the purpose of this application is to propose a construction site layout optimization method, system, readable storage medium and electronic device, aiming to solve the problems of low measurement accuracy, low layout efficiency and poor layout effect of traditional construction site layout methods.
[0008] In a first aspect, the present application proposes a method for optimizing construction site layout, the method comprising:
[0009] Acquire oblique photogrammetry data of a target construction site, and construct a real-scene three-dimensional model corresponding to the target construction site according to the oblique photogrammetry data;
[0010] Obtaining construction drawings of the target construction site, and constructing a building information model based on the construction drawings;
[0011] The real-scene three-dimensional model is integrated with the building information model to obtain an initial site layout plan corresponding to the target construction site;
[0012] Defining optimization indicators, and constructing an objective function corresponding to the preliminary layout plan based on the optimization indicators, wherein the optimization indicators include transportation costs and safety risks between facilities;
[0013] The objective function is solved, and a final site layout plan is obtained according to the solution result.
[0014] Furthermore, the step of acquiring oblique photogrammetry data of the target construction site and constructing a real-scene three-dimensional model corresponding to the target construction site according to the oblique photogrammetry data includes:
[0015] The oblique photography data includes oblique image data, POS attribute data, and image control point coordinate data;
[0016] Create a new project to add images, and assign the oblique image data, the POS attribute data, and the image control point coordinate data to the corresponding photo group;
[0017] Import the coordinates of image control points and image thorn points, and obtain the coordinates of all control points in the survey area based on the principle of aerial triangulation. Use beam regional network adjustment to obtain the coordinates of the image's exterior orientation elements and unknown points to obtain a sparse point cloud image.
[0018] Select the tile coordinate system, modify the tile size, generate a dense point cloud using feature-based multi-view image dense matching, obtain a triangular mesh TIN model, and paste the texture information in the mapped image source into the triangular mesh model to obtain a real-life 3D model.
[0019] Furthermore, the step of obtaining the construction drawings of the target construction site and constructing the building information model according to the construction drawings includes:
[0020] Create elevations and axis grids, and build the project civil model, electromechanical pipeline model, and steel structure model;
[0021] A building information model is established based on the project civil engineering model, mechanical and electrical pipeline model, and steel structure modeling, and the building information model is linked to the schedule, and the start time and completion time are added item by item, and the building information model is exported and saved in a first preset format.
[0022] Furthermore, the step of defining optimization indicators and constructing an objective function corresponding to the preliminary layout plan based on the optimization indicators, wherein the optimization indicators include transportation costs and safety risks, comprises:
[0023] The objective function is constructed according to the following formula:
[0024]
[0025] Among them, f1(x) represents the objective function corresponding to the transportation cost between facilities, f2(x) represents the objective function corresponding to the safety risk, and R ij represents the transportation cost relationship between facilities i and j, E ij represents the safety risk correlation value between facilities i and j, d kl represents the centroid distance between spatial position k and spatial position l, x ik represents the situation where facility i is placed at spatial position k, x jl Represents the situation of placing facility j at spatial location l.
[0026] Furthermore, the step of defining optimization indicators and constructing an objective function corresponding to the preliminary layout plan based on the optimization indicators, wherein the optimization indicators include transportation costs and safety risks, further includes:
[0027] The intra-site overlap constraint condition on the objective function is constructed according to the following formula:
[0028]
[0029] Among them, (x i ,y i )、(x j ,y j ) represent the centroid coordinates of facilities i and j respectively, Δx ij Indicates the minimum safe distance between facilities i and j on the x coordinate, Δy ij Indicates the minimum safe distance between facilities i and j on the y coordinate, L i , W i denote the length and width of facility i, L j , W j denote the length and width of facility j respectively;
[0030] The transport volume constraint condition of the objective function is constructed according to the following formula:
[0031] t ij q ijk ≥Q ijk
[0032] Among them, t ijrepresents the transportation frequency between facilities i and j, q ijk represents the single transportation volume of material k between facilities i and j, Q ijk Represents the maximum resource demand for material k between facilities i and j.
[0033] Furthermore, the step of solving the objective function and obtaining the final site layout plan according to the solution result includes:
[0034] Define transportation cost and safety risk as primary indicators, and define material flow, information flow, personnel flow, and safety risk sources under transportation cost as secondary indicators, and accident probability and accident impact degree under safety risk as secondary indicators;
[0035] The weights of all secondary indicators are obtained, and the objective function is solved based on the transportation cost between facilities, the safety risk relationship value and the weight of each indicator based on the ant colony algorithm.
[0036] In a second aspect, the present application proposes a construction site layout optimization system, the system comprising:
[0037] A three-dimensional model building module, used to obtain oblique photogrammetry data of a target construction site, and build a real-scene three-dimensional model corresponding to the target construction site according to the oblique photogrammetry data;
[0038] A BIM model building module is used to obtain construction drawings of the target construction site and build a building information model based on the construction drawings;
[0039] A model fusion module, used to fuse the real-scene three-dimensional model with the building information model to obtain an initial site layout plan corresponding to the target construction site;
[0040] An objective function construction module, used to define optimization indicators and construct an objective function corresponding to the preliminary layout plan based on the optimization indicators, wherein the optimization indicators include transportation costs and safety risks between facilities;
[0041] The solution module is used to solve the objective function and obtain the final site layout plan according to the solution result.
[0042] Furthermore, the three-dimensional model building module is also used for:
[0043] The oblique photography data includes oblique image data, POS attribute data, and image control point coordinate data;
[0044] Create a new project to add images, and assign the oblique image data, the POS attribute data, and the image control point coordinate data to the corresponding photo group;
[0045] Import the coordinates of image control points and image thorn points, and obtain the coordinates of all control points in the survey area based on the principle of aerial triangulation. Use beam regional network adjustment to obtain the coordinates of the image's exterior orientation elements and unknown points to obtain a sparse point cloud image.
[0046] Select the tile coordinate system, modify the tile size, generate a dense point cloud using feature-based multi-view image dense matching, obtain a triangular mesh TIN model, and paste the texture information in the mapped image source into the triangular mesh model to obtain a real-life 3D model.
[0047] In a third aspect, the present application also provides a readable storage medium, wherein the readable storage medium stores one or more programs, which, when executed, implement the construction site layout optimization method as described above.
[0048] In a fourth aspect, the present application further provides an electronic device, the electronic device comprising a memory and a processor, wherein:
[0049] The memory is used to store computer programs;
[0050] When the processor is used to execute the computer program stored in the memory, the above-mentioned construction site layout optimization method is implemented.
[0051] Compared with the prior art, this application has the following advantages:
[0052] 1. High precision: The high-precision real-life 3D model obtained by this application through oblique photogrammetry technology can capture the topography and surrounding environment of the construction site in detail, providing more accurate geographic information data than traditional measurement methods. Combined with BIM technology, this precise geographic information is integrated into the building information model, so that the construction site layout can more accurately reflect the actual situation. This can not only improve the accuracy and feasibility of the construction plan, but also effectively avoid design modifications and construction delays caused by measurement errors, thereby greatly improving the accuracy of the site layout and overall construction efficiency.
[0053] 2. Efficiency improvement: The present invention utilizes BIM and oblique photogrammetry technology to quickly generate a high-precision three-dimensional model of the construction site, greatly reducing the number and time of on-site surveys. Traditional on-site survey methods are not only time-consuming and labor-intensive, but also easily affected by factors such as weather and terrain, resulting in incomplete data or large errors. Through oblique photography technology, comprehensive on-site data can be obtained in a short period of time, and combined with BIM technology, these data can be converted into detailed three-dimensional models. This not only improves the efficiency of site layout, but also allows for multiple simulations and optimizations in the early stages of the design to discover and solve potential problems in advance, thereby speeding up construction progress and reducing manpower and time costs.
[0054] 3. Scientific optimization: The present invention introduces an ant colony algorithm to optimize the layout of the construction site. By simulating the foraging behavior of ants, the location of material yards, construction roads and temporary facilities can be scientifically and reasonably arranged. The ant colony algorithm searches for the optimal path in continuous iteration, which helps to optimize resource allocation and logistics routes, thereby reducing transportation costs. The algorithm can evaluate the safety risks of different layout plans, select the safest plan, and reduce potential dangers during the construction process. In addition, through scientific optimization, the site layout is more efficient, reducing resource waste and construction interference, and improving the overall construction management level and the smoothness of project execution.
[0055] Additional aspects and advantages of the present application will be given in part in the following description, and in part will become apparent from the following description, or will be understood through the embodiments of the present application. BRIEF DESCRIPTION OF THE DRAWINGS
[0056] The drawings constituting part of the present application are used to provide a further understanding of the present application. The exemplary embodiments and descriptions of the present application are used to explain the present application and do not constitute an improper limitation on the present application. In the drawings:
[0057] Figure 1 A flowchart of a construction site layout optimization method in one embodiment of the present application;
[0058] Figure 2 This is a flow chart of the ant colony algorithm used in one embodiment of the present application;
[0059] Figure 3 It is a structural schematic diagram of a construction site layout optimization system in one embodiment of the present application.
[0060] The following specific implementation methods will further illustrate the present application in conjunction with the above-mentioned drawings. DETAILED DESCRIPTION
[0061] The present application will be described in detail below with reference to the accompanying drawings and in combination with embodiments. It should be noted that the embodiments and features in the embodiments of the present application can be combined with each other without conflict.
[0062] The following detailed descriptions are all exemplary descriptions, and are intended to provide further detailed descriptions of the present application. Unless otherwise specified, all technical terms used in the present application have the same meanings as those generally understood by those skilled in the art to which the present application belongs. The terms used in the present application are only for describing specific embodiments, and are not intended to limit the exemplary embodiments according to the present application.
[0063] See also Figure 1 , which is a flow chart of a construction site layout optimization method in an embodiment of the present application, the method includes steps S101 to S105, wherein:
[0064] Step S101: Obtain oblique photogrammetry data of a target construction site, and construct a real-scene three-dimensional model corresponding to the target construction site according to the oblique photogrammetry data;
[0065] It should be noted that in the process of constructing a real-life 3D model, firstly, oblique image data and POS attribute data are obtained by drone aerial photography, and the coordinate data of the image control points in the survey area are collected by GPS-RTK to obtain oblique photogrammetry data. Then, data preprocessing is performed to check whether the oblique image data and POS attribute data meet the requirements, and photos with large distortion and uneven color difference are eliminated. Then, a new project is created in the Smart3D to add images, and the oblique image data and image control point coordinate data are assigned to their corresponding photo groups; then, the image control points and image thorn point coordinates are imported, and the coordinates of all control points in the survey area are obtained by the principle of aerial triangulation, and the external orientation elements of the image and the coordinates of unknown points are obtained by beam regional network adjustment to obtain a sparse point cloud image; then, the tile coordinate system is selected, the tile size is modified, and a dense point cloud is generated by feature-based multi-view image dense matching to obtain a triangular mesh TIN model, and the texture information in the mapped image source is pasted into the triangular mesh model to obtain a high-precision real-life 3D model.
[0066] Step S102: Obtain construction drawings of the target construction site, and construct a building information model according to the construction drawings;
[0067] It should be noted that, in some embodiments, the specific process of constructing a building information model is:
[0068] (1) Create elevations and axis grids: Open the Rev it2019 software and execute the "elevation" and "axis grid" commands to create a three-dimensional spatial coordinate system of field, width, and height to ensure that the "family" added later is in the correct position.
[0069] (2) Establishment of civil engineering model: The core of Revit modeling is to parameterize element information. The family file refers to the cellular basis of the Revit model. The civil engineering model of the project is established by adding common component families such as walls, columns, beams, slabs, stairs, etc. to the corresponding positions in the drawings.
[0070] (3) Establishment of mechanical and electrical pipeline model: According to professional classification, pipelines can be divided into water supply and drainage pipes, power and low-voltage electric wire pipes, ventilation and air conditioning and HVAC pipelines. There are many types of pipelines and their layout is intricate. In the modeling process, it is necessary to adopt a classification and layered approach to establish them one by one, so as to provide a model basis for the later mechanical and electrical pipeline in-depth design, collision inspection, auxiliary drawing meeting, etc.
[0071] (4) Steel structure modeling: Use the steel structure catalog of the BIM software to complete the modeling of the steel structure nodes. The model can be used for scheme simulation later to improve the steel structure construction process.
[0072] (5) Establish a BI M3D model based on the drawings: Import the BI M3D model into Autodesk Navigation Management, and then link the professional classification information of the 3D model with the schedule of Microsoft Project. When linking, you need to add relevant parameters such as start time and completion time one by one. You can adjust them through TimeLiner. Finally, set the behavior of the visual simulation to the growth state to generate a BI M4D model that can simulate the construction process. Finally, export and save the model in the first preset format (.fbx format).
[0073] Step S103: fusing the real-scene 3D model with the building information model to obtain an initial site layout plan corresponding to the target construction site;
[0074] In this step, Sky line software is used to fuse the two models. Sky line software, namely Sky line Globe, is a digital earth platform software that integrates data management and three-dimensional modeling. It can use the data of drone aerial photogrammetry to simulate the real world in three dimensions. It is also compatible with data from other software such as BIM to achieve the effect of model fusion.
[0075] Step S104: defining optimization indicators, and constructing an objective function corresponding to the preliminary layout plan based on the optimization indicators, wherein the optimization indicators include transportation costs and safety risks between facilities;
[0076] In some embodiments, the site layout based on BIM+ oblique photography technology is mainly evaluated from two aspects: transportation and safety risks. This step involves constructing an objective function with the lowest transportation cost and the lowest safety risk between facilities. Specifically, the objective function is constructed according to the following formula:
[0077]
[0078] Among them, f1(x) represents the objective function corresponding to the transportation cost between facilities, f2(x) represents the objective function corresponding to the safety risk, and R ij represents the transportation cost relationship between facilities i and j, E ij represents the safety risk correlation value between facilities i and j, d kl represents the centroid distance between spatial position k and spatial position l, x ik represents the situation where facility i is placed at spatial position k, x jl Represents the situation of placing facility j at spatial location l.
[0079] In addition, in some embodiments, the site scope will be analyzed considering the constraints, and the facility location cannot exceed the boundary area. However, the construction site layout based on BIM+ oblique photography technology of the present invention can already meet this requirement when the model is constructed, so this factor is no longer used as a constraint, and the site overlap constraint and avoidance of construction facility location conflict must be avoided, and the facility location cannot overlap with the internal roads of the construction site. Usually, the facility location can be determined by the centroid coordinates and facility size, and a safe distance must be maintained between facilities and facilities, and between facilities and roads. Based on this, the site overlap constraint on the objective function is constructed according to the following formula:
[0080]
[0081] Among them, (x i ,y i )、(x j ,y j ) represent the centroid coordinates of facilities i and j respectively, Δx ij Indicates the minimum safe distance between facilities i and j on the x coordinate, Δy ij Indicates the minimum safe distance between facilities i and j on the y coordinate, L i , W i denote the length and width of facility i, L j , W j denote the length and width of facility j respectively;
[0082] In addition, considering that the daily resource transportation volume should be greater than or equal to the daily resource consumption, the transportation volume constraint condition of the objective function is constructed according to the following formula:
[0083] t ij q ijk ≥Q ijk
[0084] Among them, t ij represents the transportation frequency between facilities i and j, q ijk represents the single transportation volume of material k between facilities i and j, Q ijk Represents the maximum resource demand for material k between facilities i and j.
[0085] In addition, before the site layout is carried out, the DEM file is generated by using the real-life 3D model, and the real-life 3D model and the building information model are comprehensively compared. Taking into account the actual situation, the functional zoning of the construction site is carried out according to the principles of site leveling and land division, and then the optimal construction channel is selected to simulate earth excavation. According to the temporary facilities, mechanical equipment, and personnel production and office needs in the later construction stage, preliminary site layout is carried out, and the traffic organization, the use of large equipment, material stacking, processing site and temporary facilities layout are simulated. Comprehensively considering the relevant factors of transportation cost and safety risk, the site layout is carried out reasonably, and the site layout plan is obtained.
[0086] In addition, after analysis, the engineering quantities of facilities related to transportation efficiency, cost, and safety risks were extracted from the model. Based on the topological relationship between facilities, the coordinates and geometric dimensions of the relevant facilities were obtained by using the aerial survey function of drone oblique photography technology. The facilities were approximated as regular geometric figures, so the geometric dimensions were extracted in batches according to length and width.
[0087] Step S105: Solve the objective function and obtain the final site layout plan according to the solution result.
[0088] It should be pointed out that in some embodiments, before solving the objective function, it is necessary to set two first-level indicators, namely, transportation cost and safety risk, and set six second-level indicators, namely, material flow, information flow, personnel flow, source of safety risk, probability of accident occurrence, and degree of accident impact. According to the logistics and non-logistics relationship between the indicators, these indicators can be divided into six intensity levels: A, E, I, O, U, and X. The division of levels here is mainly through surveys and interviews with project managers and participants, and the degree level of the corresponding indicators can be obtained based on actual data analysis. In addition, the weight information of each second-level evaluation indicator is determined, as shown in Table 1 below:
[0089] Table 1
[0090]
[0091] Next, the relationship value between facilities can be calculated according to the degree level and the weight of the evaluation index, and the formula can be input into the Excel table for calculation and solution; by combining the initial plan for the construction site layout, the transportation cost between facilities, the safety risk relationship value and the level weight of each index determined above are input into the objective function for solution to obtain the objective function value of the plan.
[0092] In some embodiments, python3.0 is used to implement the ant colony algorithm to optimize and analyze the preliminary layout plan. Since the construction of the objective function is a multidimensional function and has many constraints, the initial ant colony size is increased to 10,000, the maximum number of iterations is increased to 200, the information importance factor, the heuristic function importance factor and the pheromone volatility factor are set to 4, 1 and 0.5 respectively, and the objective function is optimized. The objective function is lower than the initial plan, indicating that the optimization plan has a certain effect in reducing transportation costs and reducing safety risks.
[0093] By modifying the temporary facility layout according to the optimized situation, the optimized layout model, i.e. the final site layout plan, can be obtained.
[0094] It should also be noted that the swarm algorithm is derived from the foraging process of ants. Ants communicate and cooperate with their companions by releasing pheromones to transport food that is dozens of times heavier than their own weight into the anthill. Pheromones are the medium for ant colonies to communicate and transmit information. Ants can not only sense pheromones in the environment, but also judge the distance of the return path by the concentration of pheromones. Ants foraging will most likely choose a path with a high pheromone concentration. Later ants will continue to release pheromones by taking this path, thus forming a positive feedback mechanism of the information mechanism. However, as time goes by, the concentration of pheromones on the road will also decrease. The process of the ant colony algorithm is as follows: Figure 2 shown.
[0095] In summary, the above-mentioned construction site layout optimization method has the following advantages:
[0096] 1. High precision: The high-precision real-life 3D model obtained by this application through oblique photogrammetry technology can capture the topography and surrounding environment of the construction site in detail, providing more accurate geographic information data than traditional measurement methods. Combined with BIM technology, this precise geographic information is integrated into the building information model, so that the construction site layout can more accurately reflect the actual situation. This can not only improve the accuracy and feasibility of the construction plan, but also effectively avoid design modifications and construction delays caused by measurement errors, thereby greatly improving the accuracy of the site layout and overall construction efficiency.
[0097] 2. Efficiency improvement: The present invention utilizes BIM and oblique photogrammetry technology to quickly generate a high-precision three-dimensional model of the construction site, greatly reducing the number and time of on-site surveys. Traditional on-site survey methods are not only time-consuming and labor-intensive, but also easily affected by factors such as weather and terrain, resulting in incomplete data or large errors. Through oblique photography technology, comprehensive on-site data can be obtained in a short period of time, and combined with BIM technology, these data can be converted into detailed three-dimensional models. This not only improves the efficiency of site layout, but also allows for multiple simulations and optimizations in the early stages of the design to discover and solve potential problems in advance, thereby speeding up construction progress and reducing manpower and time costs.
[0098] 3. Scientific optimization: The present invention introduces an ant colony algorithm to optimize the layout of the construction site. By simulating the foraging behavior of ants, the location of material yards, construction roads and temporary facilities can be scientifically and reasonably arranged. The ant colony algorithm searches for the optimal path in continuous iteration, which helps to optimize resource allocation and logistics routes, thereby reducing transportation costs. The algorithm can evaluate the safety risks of different layout plans, select the safest plan, and reduce potential dangers during the construction process. In addition, through scientific optimization, the site layout is more efficient, reducing resource waste and construction interference, and improving the overall construction management level and the smoothness of project execution.
[0099] See also Figure 3 , which is a schematic diagram of the structure of a construction site layout optimization system in one embodiment of the present application, the system includes:
[0100] A three-dimensional model building module 10 is used to obtain oblique photogrammetry data of a target construction site, and to build a real-scene three-dimensional model corresponding to the target construction site according to the oblique photogrammetry data;
[0101] Furthermore, in some optional embodiments, the three-dimensional model building module 10 is also used for:
[0102] The oblique photography data includes oblique image data, POS attribute data, and image control point coordinate data;
[0103] Create a new project to add images, and assign the oblique image data, the POS attribute data, and the image control point coordinate data to the corresponding photo group;
[0104] Import the coordinates of image control points and image thorn points, and obtain the coordinates of all control points in the survey area based on the principle of aerial triangulation. Use beam regional network adjustment to obtain the coordinates of the image's exterior orientation elements and unknown points to obtain a sparse point cloud image.
[0105] Select the tile coordinate system, modify the tile size, generate a dense point cloud using feature-based multi-view image dense matching, obtain a triangular mesh TIN model, and paste the texture information in the mapped image source into the triangular mesh model to obtain a real-life 3D model.
[0106] A BIM model building module 20 is used to obtain construction drawings of a target construction site and build a building information model according to the construction drawings;
[0107] Furthermore, in some optional embodiments, the BIM model construction module 20 is also used for:
[0108] Create elevations and axis grids, and build the project civil model, electromechanical pipeline model, and steel structure model;
[0109] A building information model is established based on the project civil engineering model, mechanical and electrical pipeline model, and steel structure modeling, and the building information model is linked to the schedule, and the start time and completion time are added item by item, and the building information model is exported and saved in a first preset format.
[0110] A model fusion module 30 is used to fuse the real-scene three-dimensional model with the building information model to obtain an initial site layout plan corresponding to the target construction site;
[0111] An objective function construction module 40 is used to define optimization indicators and construct an objective function corresponding to the preliminary layout plan based on the optimization indicators, wherein the optimization indicators include transportation costs and safety risks between facilities;
[0112] Furthermore, in some optional embodiments, the objective function construction module 40 is further used to:
[0113] The objective function is constructed according to the following formula:
[0114]
[0115] Among them, f1(x) represents the objective function corresponding to the transportation cost between facilities, f2(x) represents the objective function corresponding to the safety risk, and R ij represents the transportation cost relationship between facilities i and j, E ij represents the safety risk correlation value between facilities i and j, d kl represents the centroid distance between spatial position k and spatial position l, x ik represents the situation where facility i is placed at spatial position k, x jl represents the situation of placing facility j at spatial location l;
[0116] The intra-site overlap constraint condition on the objective function is constructed according to the following formula:
[0117]
[0118] Among them, (x i ,y i )、(x j ,y j ) represent the centroid coordinates of facilities i and j respectively, Δx ij Indicates the minimum safe distance between facilities i and j on the x coordinate, Δy ij Indicates the minimum safe distance between facilities i and j on the y coordinate, L i , W i denote the length and width of facility i, L j , W j denote the length and width of facility j respectively;
[0119] The transport volume constraint condition of the objective function is constructed according to the following formula:
[0120] t ij q ijk ≥Q ijk
[0121] Among them, t ij represents the transportation frequency between facilities i and j, q ijk represents the single transportation volume of material k between facilities i and j, Q ijk Represents the maximum resource demand for material k between facilities i and j.
[0122] The solution module 50 is used to solve the objective function and obtain the final site layout plan according to the solution result.
[0123] Further, in some optional embodiments, the solution module 50 is further configured to:
[0124] Define transportation cost and safety risk as primary indicators, and define material flow, information flow, personnel flow, and safety risk sources under transportation cost as secondary indicators, and accident probability and accident impact degree under safety risk as secondary indicators;
[0125] The weights of all secondary indicators are obtained, and the objective function is solved based on the transportation cost between facilities, the safety risk relationship value and the weight of each indicator based on the ant colony algorithm.
[0126] On the other hand, the present application also proposes a readable storage medium, on which one or more programs are stored, and when the program is executed by a processor, the above-mentioned construction site layout optimization method is implemented.
[0127] On the other hand, the present application also proposes an electronic device, including a memory and a processor, wherein the memory is used to store computer programs, and the processor is used to execute the computer programs stored in the memory to implement the above-mentioned construction site layout optimization method.
[0128] It is known from common technical knowledge that the present application can be implemented by other embodiments that do not deviate from its spirit or essential features. Therefore, the above disclosed embodiments are only illustrative in all respects and are not exclusive. All changes within the scope of the present application or within the scope equivalent to the present application are included in the present application.
[0129] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems, or computer program products. Therefore, the present application may adopt the form of a complete hardware embodiment, a complete software embodiment, or an embodiment in combination with software and hardware. Moreover, the present application may adopt the form of a computer program product implemented in one or more computer-readable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) that contain computer-usable program code.
[0130] The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0131] These computer program instructions may also be stored in a computer readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer readable memory produce an article of manufacture including an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0132] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1A process or multiple processes and / or boxes Figure 1 A step that specifies a function in one or more boxes.
[0133] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present application rather than to limit it. Although the present application has been described in detail with reference to the above embodiments, ordinary technicians in the relevant field should understand that the specific implementation methods of the present application can still be modified or replaced by equivalents, and any modifications or equivalent replacements that do not depart from the spirit and scope of the present application should be included in the scope of protection of the claims of the present application.
Claims
1. A construction site layout optimization method, characterized in that: The method comprises: Acquire oblique photogrammetry data of a target construction site, and construct a real-scene three-dimensional model corresponding to the target construction site according to the oblique photogrammetry data; Obtaining construction drawings of the target construction site, and constructing a building information model based on the construction drawings; The real-scene three-dimensional model is integrated with the building information model to obtain an initial site layout plan corresponding to the target construction site; Defining optimization indicators, and constructing an objective function corresponding to the preliminary layout plan based on the optimization indicators, wherein the optimization indicators include transportation costs and safety risks between facilities; The objective function is solved, and a final site layout plan is obtained according to the solution result.
2. The construction site layout optimization method according to claim 1, characterized in that: The step of acquiring oblique photogrammetry data of the target construction site and constructing a real-scene three-dimensional model corresponding to the target construction site according to the oblique photogrammetry data comprises: The oblique photography data includes oblique image data, POS attribute data, and image control point coordinate data; Create a new project to add images, and assign the oblique image data, the POS attribute data, and the image control point coordinate data to the corresponding photo group; Import the coordinates of image control points and image thorn points, and obtain the coordinates of all control points in the survey area based on the principle of aerial triangulation. Use beam regional network adjustment to obtain the coordinates of the image's exterior orientation elements and unknown points to obtain a sparse point cloud image. Select the tile coordinate system, modify the tile size, generate a dense point cloud using feature-based multi-view image dense matching, obtain a triangular mesh TIN model, and paste the texture information in the mapped image source into the triangular mesh model to obtain a real-life 3D model.
3. The construction site layout optimization method according to claim 2, characterized in that: The step of obtaining the construction drawings of the target construction site and constructing a building information model according to the construction drawings includes: Create elevations and axis grids, and build the project civil model, electromechanical pipeline model, and steel structure model; A building information model is established based on the project civil engineering model, mechanical and electrical pipeline model, and steel structure modeling, and the building information model is linked to the schedule, and the start time and completion time are added item by item, and the building information model is exported and saved in a first preset format.
4. The construction site layout optimization method according to claim 3, characterized in that: The step of defining optimization indicators and constructing an objective function corresponding to the preliminary layout plan based on the optimization indicators, wherein the optimization indicators include transportation costs and safety risks between facilities, comprises: The objective function is constructed according to the following formula: Among them, f1(x) represents the objective function corresponding to the transportation cost between facilities, f2(x) represents the objective function corresponding to the safety risk, and R ij represents the transportation cost relationship between facilities i and j, E ij represents the safety risk correlation value between facilities i and j, d kl represents the centroid distance between spatial position k and spatial position l, x ik represents the situation where facility i is placed at spatial position k, x jl Represents the situation of placing facility j at spatial location l.
5. The construction site layout optimization method according to claim 4, characterized in that: The step of defining optimization indicators and constructing an objective function corresponding to the preliminary layout plan based on the optimization indicators, wherein the optimization indicators include transportation costs and safety risks between facilities, further includes: The intra-site overlap constraint condition on the objective function is constructed according to the following formula: Among them, (x i ,y i )、(x j ,y j ) represent the centroid coordinates of facilities i and j, respectively, Δx ij Indicates the minimum safe distance between facilities i and j on the x coordinate, Δy ij Indicates the minimum safe distance between facilities i and j on the y coordinate, L i , W i denote the length and width of facility i, L j , W j denote the length and width of facility j respectively; The transport volume constraint condition of the objective function is constructed according to the following formula: t ij q ijk ≥Q ijk Among them, t ij represents the transportation frequency between facilities i and j, q ijk represents the single transportation volume of material k between facilities i and j, Q ijk Represents the maximum resource demand for material k between facilities i and j.
6. The construction site layout optimization method according to claim 5, characterized in that: The step of solving the objective function and obtaining the final site layout plan according to the solution result includes: Define transportation cost and safety risk as primary indicators, and define material flow, information flow, personnel flow, and safety risk sources under transportation cost as secondary indicators, and accident probability and accident impact degree under safety risk as secondary indicators; The weights of all secondary indicators are obtained, and the objective function is solved based on the transportation cost between facilities, the safety risk relationship value and the weight of each indicator based on the ant colony algorithm.
7. A construction site layout optimization system, characterized in that: The system comprises: A three-dimensional model building module, used to obtain oblique photogrammetry data of a target construction site, and build a real-scene three-dimensional model corresponding to the target construction site according to the oblique photogrammetry data; A BIM model building module is used to obtain construction drawings of the target construction site and build a building information model based on the construction drawings; A model fusion module, used to fuse the real-scene three-dimensional model with the building information model to obtain an initial site layout plan corresponding to the target construction site; An objective function construction module, used to define optimization indicators and construct an objective function corresponding to the preliminary layout plan based on the optimization indicators, wherein the optimization indicators include transportation costs and safety risks between facilities; The solution module is used to solve the objective function and obtain the final site layout plan according to the solution result.
8. The construction site layout optimization system according to claim 7, characterized in that: The three-dimensional model building module is also used for: The oblique photography data includes oblique image data, POS attribute data, and image control point coordinate data; Create a new project to add images, and assign the oblique image data, the POS attribute data, and the image control point coordinate data to the corresponding photo group; Import the coordinates of image control points and image thorn points, and obtain the coordinates of all control points in the survey area based on the principle of aerial triangulation. Use beam regional network adjustment to obtain the coordinates of the image's exterior orientation elements and unknown points to obtain a sparse point cloud image. Select the tile coordinate system, modify the tile size, generate a dense point cloud using feature-based multi-view image dense matching, obtain a triangular mesh TIN model, and paste the texture information in the mapped image source into the triangular mesh model to obtain a real-life 3D model.
9. A readable storage medium, characterized in that: include: The readable storage medium stores one or more programs, which, when executed by a processor, implement the construction site layout optimization method as described in any one of claims 1-6.
10. An electronic device, comprising a memory and a processor, wherein: The memory is used to store computer programs; When the processor is used to execute the computer program stored in the memory, the construction site layout optimization method as described in any one of claims 1-6 is implemented.
Citation Information
Cited By
Construction site layout planning optimization method integrating BIM (Building Information Modeling) and GIS (Geographic Information System) advantages
CN119720358A
Construction site arrangement method
CN119962022A
Intelligent optimized arrangement method for shield construction site
CN121030859A
Construction site layout optimization method based on digital twinning
CN122595395A