Pipeline risk evaluation method and device, electronic equipment and readable storage medium

By evaluating the basic attribute information of gas PE pipelines, dividing pipeline evaluation units, rating failure possibility and failure consequence scores, and calculating risk values, the problem of lack of risk assessment system in gas pipeline management is solved, and the safety of pipelines is improved Manage integrity.

CN119067293APending Publication Date: 2024-12-03BOCOM SMART INFORMATION TECH CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411074659.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-06
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

The existing technology lacks a risk assessment system for gas PE pipelines, making it difficult to achieve integrity management of gas pipelines.

Method used

A pipeline risk assessment method is proposed. By obtaining the basic attribute information of the pipeline, dividing the pipeline evaluation unit, determining the target evaluation model based on the pressure level and material, scoring the failure possibility and failure consequence score, calculating the risk value, and then determining the risk level of the pipeline .

Benefits of technology

A scientific and reasonable risk assessment of gas pipelines has been achieved, the safety of pipelines has been improved, the probability of gas pipeline accidents has been reduced, and the integrity management of pipelines has been improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119067293A_ABST
    Figure CN119067293A_ABST
Patent Text Reader

Abstract

The invention provides a pipeline risk evaluation method and device, electronic equipment and a readable storage medium. The method comprises the following steps: acquiring basic attribute information of a pipeline; dividing pipelines according to the basic attribute information, and generating pipeline evaluation units; determining a target evaluation model according to the pressure grade and the pipeline material corresponding to the pipeline evaluation unit; and determining a failure possibility score and a failure consequence score of the pipeline evaluation unit based on the target evaluation model, and determining a risk value of the pipeline evaluation unit based on the failure possibility score and the failure consequence score. And dividing the pipeline based on the basic attribute information to generate pipeline evaluation units, and determining failure possibility scores and failure consequence scores of the pipeline evaluation units through the target evaluation model so as to determine risk values of the pipeline evaluation units. Through the determined risk value, the operation personnel can quickly process the pipeline evaluation unit with the risk, the safety of the pipeline is improved, the accident occurrence probability of the gas pipeline is reduced, and the integrity management of the pipeline is perfected.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] Embodiments of the present invention relate to the field of pipeline management, and in particular to a pipeline risk assessment method, device, electronic device, and readable storage medium. Background Art

[0002] Gas PE (polyethylene) pipes are widely used in urban gas transmission systems due to their advantages such as lightness, corrosion resistance, and long service life. Assessing the risk of PE gas pipelines is a key link in achieving safe pipeline operation.

[0003] The research on pipeline evaluation system in related technologies mainly focuses on oil and gas pipelines. Although gas pipelines have also been widely used, an evaluation system for gas pipelines has not yet been established, which makes it difficult to achieve integrity management for gas pipelines. Summary of the invention

[0004] In view of the above problems, embodiments of the present invention are proposed to provide a pipeline risk assessment method, device, electronic device and readable storage medium that overcome the above problems or at least partially solve the above problems.

[0005] In a first aspect, an embodiment of the present application discloses a pipeline risk assessment method, the method comprising:

[0006] Get the basic property information of the pipeline;

[0007] Divide pipelines according to the basic attribute information to generate pipeline evaluation units;

[0008] Determine a target evaluation model according to the pressure level and pipeline material corresponding to the pipeline evaluation unit;

[0009] A failure possibility score and a failure consequence score of the pipeline evaluation unit are determined based on the target evaluation model, and a risk value of the pipeline evaluation unit is determined based on the failure possibility score and the failure consequence score.

[0010] Optionally, the basic attribute information includes: basic pipeline data and pipeline line information, and the dividing of pipelines according to the basic attribute information to generate pipeline evaluation units includes:

[0011] Divide the pipeline into sections according to the basic data of the pipeline and the pipeline line information to obtain the pipeline section to be evaluated;

[0012] The pipeline sections to be evaluated whose line information meets preset conditions are merged, and the merged pipeline sections to be evaluated are used as pipeline evaluation units.

[0013] Optionally, the target evaluation model includes: a failure possibility scoring model and a failure consequence scoring model, and the target evaluation model is determined according to the pressure level and pipeline material corresponding to the pipeline evaluation unit, including:

[0014] Determine a failure possibility scoring model and a failure consequence scoring model according to the pressure level and pipeline material corresponding to the pipeline evaluation unit;

[0015] The determining of the failure possibility score and the failure consequence score of the pipeline evaluation unit based on the target evaluation model includes:

[0016] Scoring the pipeline evaluation unit according to the failure possibility scoring model to obtain the failure possibility score;

[0017] The pipeline evaluation unit is scored according to the failure consequence scoring model to obtain a failure consequence score.

[0018] Optionally, determining the risk value of the pipeline assessment unit based on the failure possibility score and the failure consequence score includes:

[0019] The ratio of the failure possibility score to the failure consequence score is used as the risk value;

[0020] After determining the risk value of the pipeline assessment unit based on the failure possibility score and the failure consequence score, the method further includes:

[0021] The risk level of the pipeline assessment unit is determined according to the risk value.

[0022] Optionally, the method further comprises:

[0023] In response to the first operation, determining a target evaluation index; the target evaluation index includes: a failure possibility index and a failure consequence index;

[0024] In response to the second operation, determining the scores and weights corresponding to the respective indicators in the target evaluation indicators;

[0025] Based on the scores and weights corresponding to each of the indicators, an indicator template is generated, and the indicator template is used as the target scoring model; the indicator template includes a failure possibility evaluation template and a failure consequence scoring template.

[0026] Optionally, after generating the indicator template based on the scores and weights corresponding to the respective indicators, the method further includes:

[0027] In response to the third operation, the scores and weights corresponding to the various indicators in the target evaluation indicators are modified to generate a new indicator template.

[0028] Optionally, after determining the risk value of the pipeline assessment unit based on the failure possibility score and the failure consequence score, the method further includes:

[0029] Comparing the historical risk value and the current risk value of the pipeline evaluation unit based on a preset comparison condition to generate a comparison result;

[0030] The comparison results are presented in the form of tables or charts.

[0031] In a second aspect, an embodiment of the present application discloses a pipeline risk assessment device, the device comprising:

[0032] The acquisition module is used to obtain the basic attribute information of the pipeline;

[0033] A division module, used to divide the pipeline according to the basic attribute information and generate pipeline evaluation units;

[0034] A selection module, used to determine a target evaluation model according to the pressure level and pipeline material corresponding to the pipeline evaluation unit;

[0035] An evaluation module is used to determine a failure possibility score and a failure consequence score of the pipeline evaluation unit based on the target evaluation model, and to determine a risk value of the pipeline evaluation unit based on the failure possibility score and the failure consequence score.

[0036] In a third aspect, an embodiment of the present application further discloses an electronic device, comprising a processor and a memory, wherein the memory stores programs or instructions that can be executed on the processor, and when the program or instructions are executed by the processor, the steps of the pipeline risk assessment method described in the first aspect are implemented.

[0037] In a fourth aspect, an embodiment of the present application further discloses a readable storage medium, on which a program or instruction is stored. When the program or instruction is executed by a processor, the steps of the pipeline risk assessment method described in the first aspect are implemented.

[0038] In an embodiment of the present application, basic attribute information of the pipeline is obtained; the pipeline is divided according to the basic attribute information to generate pipeline evaluation units; a target evaluation model is determined according to the pressure level and pipeline material corresponding to the pipeline evaluation unit; the failure possibility score and failure consequence score of the pipeline evaluation unit are determined based on the target evaluation model, and the risk value of the pipeline evaluation unit is determined based on the failure possibility score and failure consequence score. The method of the present application first obtains the basic attribute information of the pipeline, divides the pipeline based on the basic attribute information, generates pipeline evaluation units, and the pipeline evaluation units can be used as the object of an evaluation. After the pipeline evaluation unit to be evaluated is determined, the target evaluation model corresponding to the pipeline evaluation unit can be determined. The failure possibility score and failure consequence score of the pipeline evaluation unit are determined by the target evaluation model, thereby determining the risk value of the pipeline evaluation unit. The determined risk value can enable the operator to quickly handle the pipeline evaluation unit with risks, improve the safety of the pipeline, reduce the probability of gas pipeline accidents, and improve the integrity management of the pipeline. BRIEF DESCRIPTION OF THE DRAWINGS

[0039] Figure 1 It is a flow chart of the steps of a pipeline risk assessment method provided by an embodiment of the present invention;

[0040] Figure 2 It is a flowchart of another pipeline risk assessment method provided by an embodiment of the present invention;

[0041] Figure 3 A pipeline risk assessment device provided by an embodiment of the present invention;

[0042] Figure 4 is a block diagram of an electronic device provided by an embodiment of the present invention;

[0043] Figure 5 is a block diagram of another electronic device according to another embodiment of the present invention. DETAILED DESCRIPTION

[0044] The exemplary embodiments of the present invention will be described in more detail below with reference to the accompanying drawings. Although the exemplary embodiments of the present invention are shown in the accompanying drawings, it should be understood that the present invention can be implemented in various forms and should not be limited by the embodiments set forth herein. On the contrary, these embodiments are provided in order to enable a more thorough understanding of the present invention and to enable the scope of the present invention to be fully communicated to those skilled in the art.

[0045] The concepts involved in this application are explained below.

[0046] refer to Figure 1 , which shows a pipeline risk assessment method provided by an embodiment of the present application, the method comprising:

[0047] Step 101, obtaining basic attribute information of the pipeline.

[0048] In an embodiment of the present invention, the basic attribute information of the pipeline includes basic data of the pipeline in any area, pipeline line information, operation data, surrounding environment data, pipeline operation information data, etc. For example, the basic data may include the pipeline commissioning time, pipe diameter, material, mileage, burial depth, etc., the pipeline line information may include the pipeline line name, length, starting point, end point, spatial information, etc., the operation data may include the operating pressure of the pipeline, the conveying medium, etc., the surrounding environment data may include topography, population size, specific places, flammable and explosive places, third-party pipeline intersections, etc., the pipeline operation information data may include the pipeline network operation information of the basic operation platform such as: patrol, inspection, construction site, hidden dangers, repair and maintenance, pipeline network detection and other related data, as well as other data associated with the risk assessment of the pipeline, which is not limited in the embodiment of the present application.

[0049] The basic attribute information of the pipeline can reflect the information of the pipeline itself and the status of its operation. By analyzing the basic attribute information of the pipeline, it can be determined whether there are risk points in the pipeline, and the failure conditions and consequences of the risk points can be scored to obtain the risk value of the pipeline, so as to timely control the existing risk points and ensure the safe operation of the pipeline.

[0050] Step 102: divide the pipeline according to the basic attribute information and generate a pipeline evaluation unit.

[0051] In the embodiment of the present invention, there may be differences in indicators such as pressure level, laying method, material, pipe diameter, split point, laying environment, and commissioning time for pipelines in any area. Therefore, before risk assessment of the pipelines, the pipelines in the area can be divided into pipeline evaluation units, and the pipeline evaluation units are used as the objects for one evaluation, so as to conveniently and accurately realize the evaluation of a certain part of the pipeline.

[0052] Specifically, a set of key attributes for dividing the pipeline can be determined from the basic attribute information of the pipeline. For example, the set of key attributes for dividing the pipeline can include: pressure level, laying method, material, pipe diameter, splitting point, laying environment, commissioning time, etc. When dividing the pipeline, the selected pipeline to be divided can be calculated based on the above key attribute set, and the pipeline can be divided into pipe segments, and the divided pipe segments can be used as a pipeline evaluation unit.

[0053] Furthermore, the present application can be implemented based on a visual operation interface. For example, pipelines in an area can be displayed in the visual operation interface. Based on the interaction with the visual operation interface, a target pipeline for pipeline division can be selected. The pipe segment corresponding to the target pipeline can be automatically calculated and displayed through a set of key attributes of the target pipeline, so that the user can select the corresponding pipe segment as a pipeline evaluation unit to perform risk assessment.

[0054] Step 103: determining a target evaluation model according to the pressure level and pipeline material corresponding to the pipeline evaluation unit.

[0055] In an embodiment of the present invention, when the pressure level and pipeline material corresponding to the pipeline evaluation unit are different, different target evaluation models can be applied for evaluation. For example, if the pipe section in the pipeline evaluation unit is a pipe section with a high pressure level and a metal material, then it can correspond to target evaluation model A. If the pressure level is a pipe section with a low pressure and a metal material, then it can correspond to target evaluation model B. That is, the present application designs different target evaluation models in advance for different evaluation scenarios. During the evaluation, the adapted target evaluation model can be determined based on the attributes of the unit to be evaluated for evaluation, so as to ensure the accuracy of the evaluation of the pipeline evaluation unit.

[0056] Furthermore, the possibility and consequence of pipeline failure are usually determined by a series of factors. Therefore, the target evaluation model can be a pre-set model for evaluating the risk of the pipeline based on the basic attribute information of the pipeline. The target evaluation model can quantitatively calculate the failure possibility of the pipeline based on the set indicators to obtain the failure possibility score and the failure consequence score, so as to evaluate the pipeline evaluation unit through the quantitative score.

[0057] Step 104: determine a failure possibility score and a failure consequence score of the pipeline evaluation unit based on the target evaluation model, and determine a risk value of the pipeline evaluation unit based on the failure possibility score and the failure consequence score.

[0058] In an embodiment of the present invention, the failure causes of the pipeline evaluation unit may include: aging of pipeline materials, for example, material durability, manufacturing defects and time factors will affect the risk of pipeline damage or leakage; pipeline operating environment, such as harsh conditions such as pressure, temperature, corrosive environment, etc., which may also cause pipeline failure; pipeline maintenance history, such as if the pipeline is frequently repaired or has not been maintained for a long time, the possibility of failure will be higher, and other failure causes related to pipeline risks. Therefore, the target evaluation unit can analyze and calculate the above-mentioned pipeline indicators that may cause failure causes, determine the possible risk events of the pipeline, and score the failure possibility of the risk events.

[0059] The pipeline failure consequence score can reflect the severity of the failure consequence caused by the failure event. For example, the severity of the failure consequence can be reflected in the severity of the accident, such as: if the pipeline ruptures, it may cause natural gas leakage, fire or poisoning; the scope of impact, such as the location of the pipeline and the density of the surrounding population will affect the number of people affected by the accident and property losses; environmental impact, if it is in a water source or sensitive ecological area, the impact on environmental damage is greater, etc. Therefore, when calculating the failure consequence score, the consequences of the failure event can be scored based on the possible failure event that is judged. Specifically, different weight values ​​and scores can be set for each indicator that affects the severity of the failure consequence to determine the failure consequence score corresponding to the failure event. After determining the failure possibility score and the failure consequence score, the risk value of the pipeline evaluation unit can be comprehensively determined. The risk value can reflect the current risk level of the pipeline evaluation unit, so that the operator can make reasonable disposal measures for the pipeline evaluation unit based on the risk value, and achieve more efficient and scientific pipeline risk inspection and maintenance.

[0060] In summary, in the embodiment of the present application, the basic attribute information of the pipeline is obtained; the pipeline is divided according to the basic attribute information to generate a pipeline evaluation unit; the target evaluation model is determined according to the pressure level and pipeline material corresponding to the pipeline evaluation unit; the failure possibility score and failure consequence score of the pipeline evaluation unit are determined based on the target evaluation model, and the risk value of the pipeline evaluation unit is determined based on the failure possibility score and failure consequence score. The method of the present application first obtains the basic attribute information of the pipeline, divides the pipeline based on the basic attribute information, generates pipeline evaluation units, and the pipeline evaluation unit can be used as an object for an evaluation. After determining the pipeline evaluation unit to be evaluated, the target evaluation model corresponding to the pipeline evaluation unit can be determined. The failure possibility score and failure consequence score of the pipeline evaluation unit are determined by the target evaluation model, thereby determining the risk value of the pipeline evaluation unit. The determined risk value can enable the operator to quickly handle the pipeline evaluation unit with risks, improve the safety of the pipeline, reduce the probability of gas pipeline accidents, and improve the integrity management of the pipeline.

[0061] refer to Figure 2 , which shows a flowchart of the steps of another pipeline risk assessment method provided by an embodiment of the present application, including:

[0062] Step 201, obtaining basic attribute information of the pipeline.

[0063] This step refers to step 101 and will not be described again here.

[0064] Step 202, the basic attribute information includes: basic pipeline data and pipeline line information; the pipeline is divided into sections according to the basic pipeline data and pipeline line information to obtain the sections to be evaluated.

[0065] Step 203: merge the pipeline sections to be evaluated whose line information meets preset conditions, and use the merged pipeline sections to be evaluated as pipeline evaluation units.

[0066] In the embodiment of the present invention, for step 202 and step 203, the basic attribute information includes: basic data of the pipeline and pipeline line information, the basic data of the pipeline includes the time of commissioning, diameter, material, mileage, burial depth, pressure level, laying method, laying environment, etc. of the pipeline, and the pipeline line information includes: pipeline line name, length, starting point, end point, spatial information, etc. The pipeline can be divided based on the above parameters. For example, the rules for pipeline division can be set, and the rules include: pipe section length, pressure level, material, etc. The pipeline is divided according to the preset division rules, and multiple pipe sections to be evaluated are obtained after division.

[0067] Furthermore, after obtaining the pipe sections to be evaluated, the pipe sections to be evaluated that meet the preset conditions can be merged based on the line information corresponding to the pipe sections, wherein the line information can be information characterizing the spatial position of the pipe sections, and whether the pipe sections are adjacent to each other can be determined through the line information of the pipe sections. If the distance between two pipe sections to be evaluated meets the preset conditions, it is determined that the two pipe sections to be evaluated are adjacent, and the adjacent pipe sections to be evaluated can be merged to obtain a pipeline evaluation unit. The adjacent pipe sections are merged, which can facilitate the subsequent management of the pipeline evaluation unit as a whole.

[0068] In addition, the method of the present application can be applied to a pipeline management system, which can be a system for risk assessment and risk display of pipelines. Through interaction with the pipeline management system, users can select pipelines or merge pipe segments. For example, the pipeline management system can automatically merge pipe segments to be evaluated that meet the preset conditions based on the preset conditions set by the user, or it can merge the selected pipe segments to be evaluated based on the manual operation of the user. The final obtained pipeline evaluation unit can be exported as a table and used for other services. In addition, the pipeline management system can include a GIS map, which can be positioned and rendered in the GIS map based on the basic information of the pipeline and the obtained pipeline evaluation unit, and visualized display can be achieved in the GIS map, so that users can intuitively understand the deployment and operation of the pipeline. The pipeline management system can also include a query module, which can query matching pipe segments in the system by inputting pipeline names, pipe segment lengths, etc., and directly locate the pipe segments, or filter matching pipe segments from the pipeline management system by setting filtering conditions for display, which is not limited in the embodiments of the present application.

[0069] Step 204: determining a target evaluation model according to the pressure level and pipeline material corresponding to the pipeline evaluation unit.

[0070] This step may refer to step 103 and will not be described again here.

[0071] Step 205: determine the failure possibility score and failure consequence score of the pipeline evaluation unit based on the target evaluation model, and determine the risk value of the pipeline evaluation unit based on the failure possibility score and failure consequence score.

[0072] In an embodiment of the present invention, the target evaluation model can determine the risk events that may exist in the pipeline evaluation unit based on the basic attribute information corresponding to the pipeline evaluation unit, such as: pipeline material and corrosion conditions, natural disasters (such as earthquakes, floods), geological conditions, etc. For each risk event, its impact on the safety of the pipeline system can be quantified. The quantification process can be to collect data and use the designed target evaluation model to estimate the probability score and consequence score of the risk occurrence. For example: corrosion rate can be used to predict the remaining life of the pipeline, geological survey data can be used to assess the impact of geological conditions on pipeline stability, and historical accident data can be used to estimate the probability of risk occurrence under similar conditions. The risk value can be calculated as a whole through the parameter values ​​of each risk indicator. Each calculation indicator in the target evaluation model can correspond to different risk events and impact levels to reflect the importance of the indicator to the overall risk, thereby calculating the overall risk value of the pipeline evaluation unit.

[0073] Optionally, step 205 includes:

[0074] Sub-step 2051, scoring the pipeline evaluation unit according to the failure possibility scoring model to obtain the failure possibility score;

[0075] Sub-step 2052: scoring the pipeline evaluation unit according to the failure consequence scoring model to obtain a failure consequence score.

[0076] In the embodiment of the present invention, for sub-steps 2051 and 2052, the failure possibility scoring model may be a pre-set model for performing failure possibility scoring, and the failure consequence scoring model may score the pipeline evaluation unit. The specific implementation method may refer to the description of step 104, which will not be repeated here.

[0077] Optionally, step 205 includes:

[0078] Sub-step 2053: taking the ratio of the failure possibility score to the failure consequence score as the risk value.

[0079] In an embodiment of the present invention, the risk value can be calculated based on the following formula:

[0080] R=P / C

[0081] Among them, R is the risk value, P is the failure possibility score, and C is the failure consequence score. The size of the risk value can reflect the risk level of the pipeline evaluation unit, and then determine the control measures for the pipeline evaluation unit.

[0082] Optionally, after step 205, the method further includes:

[0083] Step 206: Determine the risk level of the pipeline assessment unit according to the risk value.

[0084] In an embodiment of the present invention, the risk level can be divided into several levels such as high, relatively high, medium, and low. A matching interval between the risk value and the risk level can be set, and the risk level is determined according to the risk value, thereby determining the urgency of the pipeline evaluation unit to eliminate the risk, which is convenient for operators to reasonably arrange pipeline maintenance plans.

[0085] Specifically, risks can be ranked according to risk levels, and the risks to be dealt with first can be determined. For high risks, corresponding prevention and emergency response measures can be formulated, such as strengthening inspections, installing monitoring equipment, setting up safety zones, etc. In addition, risk status can be regularly evaluated and updated, and risk assessment strategies can be adjusted as the environment changes and new technologies are applied.

[0086] Optionally, the method further comprises:

[0087] Step 207, in response to the first operation, determining a target evaluation index; the target evaluation index includes: a failure possibility index and a failure consequence index;

[0088] Step 208, in response to the second operation, determining the scores and weights corresponding to the various indicators in the target evaluation indicators;

[0089] Step 209, based on the scores and weights corresponding to each of the indicators, an indicator template is generated, and the indicator template is used as the target scoring model; the indicator template includes a failure possibility evaluation template and a failure consequence scoring template.

[0090] In the embodiment of the present invention, for steps 207 to 209, the pipeline management system may pre-define a model for risk rating and indicators of the model. For example, if the target evaluation model includes failure possibility evaluation and failure consequence scoring, then the failure possibility indicator for implementing the failure possibility evaluation and the failure consequence indicator for failure consequence scoring may be pre-set.

[0091] For failure possibility indicators, a failure possibility evaluation system can be formed based on scoring rules and saved as a failure possibility evaluation template. For failure consequence indicators, a failure consequence scoring system can be formed based on scoring rules and saved as a failure consequence equalization template.

[0092] Specifically, multiple failure possibility evaluation templates and multiple failure consequence scoring templates can be newly created in the pipeline management system. Each of the multiple failure possibility evaluation templates can include different failure possibility indicators. At the same time, the same failure possibility indicator can correspond to different scores and weights in different failure possibility evaluation templates. Similarly, each of the multiple failure consequence scoring templates can include different failure consequence indicators. At the same time, the same failure consequence indicator can correspond to different scores and weights in different failure consequence scoring templates. When evaluating the risk value of the pipeline evaluation unit, the appropriate failure possibility evaluation template and failure consequence scoring template can be selected based on actual needs to ensure the accuracy of the evaluation results.

[0093] Optionally, after step 209, the method further includes:

[0094] Step 210, in response to the third operation, modify the scores and weights corresponding to each indicator in the target evaluation indicator to generate a new indicator template.

[0095] In the embodiment of the present invention, based on the pipeline management system, the existing indicator template can also be modified, including modifying the indicators included in the indicator template, the scores and weights corresponding to the indicators, etc., so that the modified indicator template is suitable for actual needs.

[0096] Furthermore, historical failure events can be collected and analyzed, and the current indicators and the scores and weights corresponding to the indicators can be adjusted based on the results of the analysis to optimize the indicator template. For example, if the indicators that lead to failure event A are found to be indicator 1, indicator 2, and indicator 3 after analysis, then when modifying the indicator template, the scores and weights corresponding to indicator 1, indicator 2, and indicator 3 can be appropriately increased to make the score calculated by the indicator template more accurate.

[0097] Specifically, a failure event refers to an event that fails to achieve the expected function or performance standard due to some reason. Failure events are crucial to risk management. Based on the feedback from failure events, possible weaknesses or deficiencies in pipeline management can be revealed.

[0098] The target evaluation model can be a model that includes risk identification, risk analysis, and risk evaluation. In the target evaluation model, various indicators (such as probability, impact, vulnerability, etc.) can be used to quantify risks in order to better manage pipeline risks. Therefore, after each failure event occurs, the specific circumstances of each failure event can be recorded in detail, including the time, location, cause, scope of impact, and consequences. Use tools such as 5Why and fault tree analysis (FTA) to deeply explore the root causes of failure events. Evaluate the impact of failure events on pipelines, including direct economic losses, environmental impacts, and usage impacts. According to the frequency of failure events, the indicators corresponding to the failure probability and failure consequences can be adjusted. For example, based on the actual impact of the failure event, the weight value of the corresponding indicator in the failure consequence score can be updated. Based on the analysis of the failure event, the parts of the pipeline that are prone to failure can also be identified, and relevant indicators can be added or adjusted to provide feedback. After the indicator is updated, the updated indicator template can also be used for simulation testing to verify its accuracy and effectiveness. By continuously collecting new failure event information, the target evaluation model is continuously optimized and updated to make the target evaluation model more accurate.

[0099] In this application, failure events are used to update the indicators of the target evaluation model, which can improve the risk management level, ensure that the target evaluation model is more accurate and effective, provide strong guarantees for the stable operation of the pipeline, and cope with the increasingly complex and changing risk environment.

[0100] Optionally, after step 205, the method further includes:

[0101] Step 211 : Compare the historical risk value and the current risk value of the pipeline evaluation unit based on preset comparison conditions to generate a comparison result.

[0102] Step 212: present the comparison result in a table or chart.

[0103] In the embodiment of the present invention, with respect to step 211 and step 212, in order to more clearly represent the operation status of the pipeline, the risk value may be analyzed and displayed in a graphical form to intuitively represent the historical change process of the pipeline.

[0104] For example, the pipeline management system can display the comparison of the risk history of the pipeline evaluation unit. The previous risk assessment results of the same pipeline can be compared according to the set comparison conditions (risk distribution, index score, leakage consequences, weight changes, sensitive factors, etc.). The display form of the comparison results can include table comparison and chart comparison, etc., which is not limited in the embodiments of the present application.

[0105] In addition, the pipeline management system can also display pipeline risks in real time: in the pipeline digital management interface, set up a risk display layer, and based on the latest risk assessment results, display the risk distribution status of pipelines in the area, and display it in multiple colors according to the risk classification results to facilitate daily management.

[0106] In summary, the basic attribute information of the pipeline is obtained; the pipeline is divided according to the basic attribute information to generate pipeline evaluation units; the target evaluation model is determined according to the pressure level and pipeline material corresponding to the pipeline evaluation unit; the failure possibility score and failure consequence score of the pipeline evaluation unit are determined based on the target evaluation model, and the risk value of the pipeline evaluation unit is determined based on the failure possibility score and failure consequence score. The method of the present application first obtains the basic attribute information of the pipeline, divides the pipeline based on the basic attribute information, and generates pipeline evaluation units. The pipeline evaluation unit can be used as an object for an evaluation. After determining the pipeline evaluation unit to be evaluated, the target evaluation model corresponding to the pipeline evaluation unit can be determined. The failure possibility score and failure consequence score of the pipeline evaluation unit are determined by the target evaluation model, so as to determine the risk value of the pipeline evaluation unit. The determined risk value can enable the operating personnel to quickly deal with the pipeline evaluation unit with risks, improve the safety of the pipeline, reduce the probability of gas pipeline accidents, and improve the integrity management of the pipeline.

[0107] refer to Figure 3 , which shows a pipeline risk assessment device provided by an embodiment of the present application, comprising:

[0108] The acquisition module 301 is used to acquire basic attribute information of the pipeline;

[0109] A division module 302, configured to divide pipelines according to the basic attribute information and generate pipeline evaluation units;

[0110] A selection module 303 is used to determine a target evaluation model according to the pressure level and pipeline material corresponding to the pipeline evaluation unit;

[0111] The evaluation module 304 is used to determine the failure possibility score and the failure consequence score of the pipeline evaluation unit based on the target evaluation model, and determine the risk value of the pipeline evaluation unit based on the failure possibility score and the failure consequence score.

[0112] Optionally, the basic attribute information includes: pipeline basic data and pipeline line information, and the division module includes:

[0113] Divide the pipeline into sections according to the basic data of the pipeline and the pipeline line information to obtain the pipeline section to be evaluated;

[0114] The merging submodule is used to merge the pipeline sections to be evaluated whose line information meets preset conditions, and use the merged pipeline sections to be evaluated as pipeline evaluation units.

[0115] Optionally, the target evaluation model includes: a failure possibility scoring model and a failure consequence scoring model, and the selection module includes:

[0116] A determination submodule, used to determine a failure possibility scoring model and a failure consequence scoring model according to the pressure level and pipeline material corresponding to the pipeline evaluation unit;

[0117] The evaluation module comprises:

[0118] A first evaluation submodule, configured to score the pipeline evaluation unit according to the failure possibility scoring model to obtain the failure possibility score;

[0119] The second evaluation submodule is used to score the pipeline evaluation unit according to the failure consequence scoring model to obtain a failure consequence score.

[0120] Optionally, the evaluation module includes:

[0121] a calculation submodule, configured to use the ratio of the failure possibility score to the failure consequence score as the risk value;

[0122] After determining the risk value of the pipeline evaluation unit based on the failure possibility score and the failure consequence score, the device further includes:

[0123] The level determination module is used to determine the risk level of the pipeline assessment unit according to the risk value.

[0124] Optionally, the device further comprises:

[0125] A first setting module is used to determine a target evaluation index in response to a first operation; the target evaluation index includes: a failure possibility index and a failure consequence index;

[0126] A second setting module, used to determine the scores and weights corresponding to each indicator in the target evaluation indicator in response to the second operation;

[0127] A generation module is used to generate an indicator template based on the scores and weights corresponding to each of the indicators, and use the indicator template as the target scoring model; the indicator template includes a failure possibility evaluation template and a failure consequence scoring template.

[0128] Optionally, after generating the indicator template based on the scores and weights corresponding to the indicators, the device further includes:

[0129] The updating module is used to modify the scores and weights corresponding to each indicator in the target evaluation indicator in response to the third operation, and generate a new indicator template.

[0130] Optionally, after determining the risk value of the pipeline assessment unit based on the failure possibility score and the failure consequence score, the device further comprises:

[0131] A comparison module, used to compare the historical risk value and the current risk value of the pipeline evaluation unit based on a preset comparison condition to generate a comparison result;

[0132] The display module is used to display the comparison results in the form of a table or a chart.

[0133] In summary, in the embodiment of the present application, the basic attribute information of the pipeline is obtained; the pipeline is divided according to the basic attribute information to generate a pipeline evaluation unit; the target evaluation model is determined according to the pressure level and pipeline material corresponding to the pipeline evaluation unit; the failure possibility score and failure consequence score of the pipeline evaluation unit are determined based on the target evaluation model, and the risk value of the pipeline evaluation unit is determined based on the failure possibility score and failure consequence score. The method of the present application first obtains the basic attribute information of the pipeline, divides the pipeline based on the basic attribute information, generates pipeline evaluation units, and the pipeline evaluation unit can be used as an object for an evaluation. After determining the pipeline evaluation unit to be evaluated, the target evaluation model corresponding to the pipeline evaluation unit can be determined. The failure possibility score and failure consequence score of the pipeline evaluation unit are determined by the target evaluation model, thereby determining the risk value of the pipeline evaluation unit. The determined risk value can enable the operator to quickly handle the pipeline evaluation unit with risks, improve the safety of the pipeline, reduce the probability of gas pipeline accidents, and improve the integrity management of the pipeline.

[0134] Figure 4 A block diagram of an electronic device 600 is shown according to an exemplary embodiment. For example, the electronic device 600 may be a mobile phone, a computer, a digital broadcast terminal, a messaging device, a game console, a tablet device, a medical device, a fitness device, a personal digital assistant, etc.

[0135] Reference Figure 4 , the sub-device 600 may include one or more of the following components: a processing component 602 , a memory 604 , a power component 606 , a multimedia component 608 , an audio component 610 , an input / output (I / O) interface 612 , a sensor component 614 , and a communication component 616 .

[0136] The processing component 602 generally controls the overall operation of the electronic device 600, such as operations associated with display, phone calls, data communications, camera operations, and recording operations. The processing component 602 may include one or more processors 620 to execute instructions to complete all or part of the steps of the above-mentioned method. In addition, the processing component 602 may include one or more modules to facilitate the interaction between the processing component 602 and other components. For example, the processing component 602 may include a multimedia module to facilitate the interaction between the multimedia component 608 and the processing component 602.

[0137] The memory 604 is used to store various types of data to support the operation of the electronic device 600. Examples of such data include instructions for any application or method operating on the electronic device 600, contact data, phone book data, messages, pictures, multimedia, etc. The memory 604 can be implemented by any type of volatile or non-volatile storage device or a combination thereof, such as static random access memory (SRAM), electrically erasable programmable read-only memory (EEPROM), erasable programmable read-only memory (EPROM), programmable read-only memory (PROM), read-only memory (ROM), magnetic memory, flash memory, magnetic disk or optical disk.

[0138] The power supply component 606 provides power to the various components of the electronic device 600. The power supply component 606 may include a power management system, one or more power supplies, and other components associated with generating, managing, and distributing power to the electronic device 600.

[0139] The multimedia component 608 includes a screen that provides an output interface between the electronic device 600 and the user. In some embodiments, the screen may include a liquid crystal display (LCD) and a touch panel (TP). If the screen includes a touch panel, the screen may be implemented as a touch screen to receive input signals from the user. The touch panel includes one or more touch sensors to sense touch, slide, and gestures on the touch panel. The touch sensor may not only sense the boundaries of the touch or slide action, but also detect the duration and pressure associated with the touch or slide operation. In some embodiments, the multimedia component 608 includes a front camera and / or a rear camera. When the electronic device 600 is in an operating mode, such as a shooting mode or a multimedia mode, the front camera and / or the rear camera may receive external multimedia data. Each front camera and the rear camera may be a fixed optical lens system or have a focal length and optical zoom capability.

[0140] The audio component 610 is used to output and / or input audio signals. For example, the audio component 610 includes a microphone (MIC), and when the electronic device 600 is in an operating mode, such as a call mode, a recording mode, and a voice recognition mode, the microphone is used to receive an external audio signal. The received audio signal can be further stored in the memory 604 or sent via the communication component 616. In some embodiments, the audio component 610 also includes a speaker for outputting audio signals.

[0141] I / O interface 612 provides an interface between processing component 602 and peripheral interface modules, such as keyboards, click wheels, buttons, etc. These buttons may include but are not limited to: a home button, a volume button, a start button, and a lock button.

[0142] The sensor assembly 614 includes one or more sensors for providing various aspects of status assessment for the electronic device 600. For example, the sensor assembly 614 can detect the open / closed state of the electronic device 600, the relative positioning of the components, such as the display and keypad of the electronic device 600, and the sensor assembly 614 can also detect the position change of the electronic device 600 or a component of the electronic device 600, the presence or absence of contact between the user and the electronic device 600, the orientation or acceleration / deceleration of the electronic device 600, and the temperature change of the electronic device 600. The sensor assembly 614 may include a proximity sensor configured to detect the presence of a nearby object without any physical contact. The sensor assembly 614 may also include an optical sensor, such as a CMOS or CCD image sensor, for use in imaging applications. In some embodiments, the sensor assembly 614 may also include an acceleration sensor, a gyroscope sensor, a magnetic sensor, a pressure sensor, or a temperature sensor.

[0143] The communication component 616 is used to facilitate wired or wireless communication between the electronic device 600 and other devices. The electronic device 600 can access a wireless network based on a communication standard, such as WiFi, a carrier network (such as 2G, 3G, 4G or 5G), or a combination thereof. In an exemplary embodiment, the communication component 616 receives a broadcast signal or broadcast-related information from an external broadcast management system via a broadcast channel. In an exemplary embodiment, the communication component 616 also includes a near field communication (NFC) module to facilitate short-range communication. For example, the NFC module can be implemented based on radio frequency identification (RFID) technology, infrared data association (IrDA) technology, ultra-wideband (UWB) technology, Bluetooth (BT) technology and other technologies.

[0144] In an exemplary embodiment, the electronic device 600 may be implemented by one or more application-specific integrated circuits (ASICs), digital signal processors (DSPs), digital signal processing devices (DSPDs), programmable logic devices (PLDs), field programmable gate arrays (FPGAs), controllers, microcontrollers, microprocessors, or other electronic components to implement the pipeline risk assessment method provided in the embodiments of the present application.

[0145] In an exemplary embodiment, a non-transitory computer-readable storage medium including instructions is also provided, such as a memory 604 including instructions, and the instructions can be executed by a processor 620 of an electronic device 600 to perform the above method. For example, the non-transitory storage medium can be a ROM, a random access memory (RAM), a CD-ROM, a magnetic tape, a floppy disk, an optical data storage device, etc.

[0146] Figure 5 A block diagram of an electronic device 700 is shown according to an exemplary embodiment. For example, the electronic device 700 can be provided as a server. Figure 5 The electronic device 700 includes a processing component 722, which further includes one or more processors, and a memory resource represented by a memory 732 for storing instructions executable by the processing component 722, such as an application. The application stored in the memory 732 may include one or more modules, each corresponding to a set of instructions. In addition, the processing component 722 is configured to execute instructions to perform a pipeline risk assessment method provided in an embodiment of the present application.

[0147] The electronic device 700 may also include a power supply component 726 configured to perform power management of the electronic device 700, a wired or wireless network interface 750 configured to connect the electronic device 700 to a network, and an input / output (I / O) interface 758. The electronic device 700 may operate based on an operating system stored in the memory 732, such as Windows Server™, Mac OS X™, Unix™, Linux™, FreeBSD™ or the like.

[0148] Those skilled in the art will readily appreciate other embodiments of the present application after considering the specification and practicing the application disclosed herein. The present application is intended to cover any modification, use or adaptation of the present application, which follows the general principles of the present application and includes common knowledge or customary techniques in the art that are not disclosed in the present disclosure. The specification and examples are intended to be exemplary only, and the true scope and spirit of the present application are indicated by the following claims.

[0149] It should be understood that the present application is not limited to the precise structures that have been described above and shown in the drawings, and that various modifications and changes may be made without departing from the scope thereof. The scope of the present application is limited only by the appended claims.

Claims

1. A pipeline risk assessment method, characterized in that: The method comprises: Get basic property information of the pipeline; Divide pipelines according to the basic attribute information to generate pipeline evaluation units; Determine a target evaluation model according to the pressure level and pipeline material corresponding to the pipeline evaluation unit; A failure possibility score and a failure consequence score of the pipeline evaluation unit are determined based on the target evaluation model, and a risk value of the pipeline evaluation unit is determined based on the failure possibility score and the failure consequence score.

2. The method according to claim 1, characterized in that The basic attribute information includes: basic pipeline data and pipeline line information. The pipeline is divided according to the basic attribute information to generate a pipeline evaluation unit, including: Divide the pipeline into sections according to the basic data of the pipeline and the pipeline line information to obtain the pipeline section to be evaluated; The pipeline sections to be evaluated whose line information meets preset conditions are merged, and the merged pipeline sections to be evaluated are used as pipeline evaluation units.

3. The method according to claim 1, characterized in that The target evaluation model includes: a failure possibility scoring model and a failure consequence scoring model. The target evaluation model determined according to the pressure level and pipeline material corresponding to the pipeline evaluation unit includes: Determine a failure possibility scoring model and a failure consequence scoring model according to the pressure level and pipeline material corresponding to the pipeline evaluation unit; The determining of the failure possibility score and the failure consequence score of the pipeline evaluation unit based on the target evaluation model includes: Scoring the pipeline evaluation unit according to the failure possibility scoring model to obtain the failure possibility score; The pipeline evaluation unit is scored according to the failure consequence scoring model to obtain a failure consequence score.

4. The method according to claim 1, characterized in that: The step of determining the risk value of the pipeline assessment unit based on the failure possibility score and the failure consequence score includes: The ratio of the failure possibility score to the failure consequence score is used as the risk value; After determining the risk value of the pipeline assessment unit based on the failure possibility score and the failure consequence score, the method further includes: The risk level of the pipeline assessment unit is determined according to the risk value.

5. The method according to claim 1, characterized in that The method further comprises: In response to the first operation, determining a target evaluation index; the target evaluation index includes: a failure possibility index and a failure consequence index; In response to the second operation, determining the scores and weights corresponding to the respective indicators in the target evaluation indicators; Based on the scores and weights corresponding to each of the indicators, an indicator template is generated, and the indicator template is used as the target scoring model; the indicator template includes a failure possibility evaluation template and a failure consequence scoring template.

6. The method according to claim 5, characterized in that After generating the indicator template based on the scores and weights corresponding to the various indicators, the method further includes: In response to the third operation, the scores and weights corresponding to the various indicators in the target evaluation indicators are modified to generate a new indicator template.

7. The method according to claim 1, characterized in that After determining the risk value of the pipeline assessment unit based on the failure possibility score and the failure consequence score, the method further includes: Comparing the historical risk value and the current risk value of the pipeline evaluation unit based on a preset comparison condition to generate a comparison result; The comparison results are presented in the form of tables or charts.

8. A pipeline risk assessment device, characterized in that: The device comprises: The acquisition module is used to obtain the basic attribute information of the pipeline; A division module, used to divide the pipeline according to the basic attribute information and generate pipeline evaluation units; A selection module, used to determine a target evaluation model according to the pressure level and pipeline material corresponding to the pipeline evaluation unit; An evaluation module is used to determine a failure possibility score and a failure consequence score of the pipeline evaluation unit based on the target evaluation model, and to determine a risk value of the pipeline evaluation unit based on the failure possibility score and the failure consequence score.

9. An electronic device, characterized in that: The method comprises a processor and a memory, wherein the memory stores a program or instruction that can be run on the processor, and when the program or instruction is executed by the processor, the steps of the pipeline risk assessment method according to any one of claims 1 to 7 are implemented.

10. A readable storage medium, characterized in that: The readable storage medium stores a program or instruction, and when the program or instruction is executed by the processor, the steps of the pipeline risk assessment method according to any one of claims 1 to 7 are implemented.

Citation Information

Cited By

  • Pipe network health evaluation method and system based on big data analysis

    CN120410504A