By predicting and allocating item information and item quantity of order processing shifts, combining priority and distribution strategies, the problems of low supply chain production capacity and efficiency in the existing technology are solved, and the order processing efficiency is improved and capacity balance is achieved.
Patent Information
- Application Number
- CN202310627620.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-05-30
- Publication Date
- 2024-12-03
AI Technical Summary
The existing technology fails to effectively balance the production capacity in the warehouse, the transportation allocation of the warehouse-to-order transfer nodes, and the production plan of the transfer nodes in the order during the order processing, resulting in low supply chain capacity and order processing efficiency.
By predicting the production volume and supply volume of each order processing shift in the warehouse, distribute item information and item volume, and determine the target distribution strategy based on the preset priority strategy, supply interval and distance interval, and generate production orders to coordinate transfers in orders. The demands of transportation nodes and warehouses balance the processing efficiency of distribution transportation and warehouses.
The processing efficiency of transfer nodes and warehouses in orders has been improved, the supply chain capacity balance has been achieved, and the order processing efficiency has been improved.
Smart Images

Figure CN119067572A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of smart supply chain technology, and in particular to an order processing method, a fulfillment service end and a system. Background Art
[0002] The supply chain of online shopping mall orders is mainly warehouse-order transit and distribution node-user delivery node. Among them, the production plan of the warehouse, the transportation allocation from the warehouse to the order transit and distribution node, and the production plan of the order transit and distribution node will directly affect the production capacity of the entire supply chain and the order processing efficiency.
[0003] At present, in the order production process, the warehouse capacity is mainly considered, and the vehicle is dispatched for transportation after the warehouse capacity reaches the full truck quantity of the order transfer and distribution node dimension. It does not balance the balance between the warehouse capacity, the transportation allocation from the warehouse to the order transfer and distribution node, and the production plan of the order transfer and distribution node, resulting in low supply chain capacity and order processing efficiency. Summary of the invention
[0004] In view of this, an embodiment of the present invention provides an order processing method, a fulfillment service end and a system, which can effectively balance the supply chain capacity and improve the order processing efficiency.
[0005] To achieve the above objective, according to one aspect of an embodiment of the present invention, an order processing method is provided, comprising:
[0006] Predicting the production volume of each order processing shift of the warehouse and the first supply volume provided by the warehouse for the order transfer and distribution node, and allocating item information and item quantity to the order processing shift according to the production volume of the order processing shift;
[0007] For each of the order processing shifts, according to a preset order transfer and delivery node priority strategy, orders of the order transfer and delivery nodes, and item information and item quantity allocated to the order processing shift, a first production order is generated for the order processing shift, and the first production order is provided to a warehouse management server corresponding to the warehouse;
[0008] Determine a target distribution strategy for the order transit distribution node according to the association between the preset supply interval, distance interval and distribution strategy, the first supply quantity of the order transit distribution node and the distance between the order transit distribution node and the warehouse;
[0009] According to the distribution wave indicated by the target distribution strategy and the distribution ratio and distribution time corresponding to the distribution wave, a second production order and a third production order are generated for the order transit distribution node and the transportation allocation server respectively, and the second production order is provided to the corresponding order transit distribution node service, and the third production order is provided to the corresponding transportation allocation server.
[0010] Optionally, allocating item information and item quantity to the order processing shift includes:
[0011] When an initial production order sent by the order service end is obtained, statistics are collected on the item information and item quantity contained in the initial production order, wherein the item information and the item quantity correspond to orders of one or more order transfer and distribution nodes contained in the initial production order;
[0012] According to the predicted production volume of each of the order processing shifts, statistical results and the item supply situation corresponding to the item information, an order processing shift is allocated to the item information and item quantity included in the initial production order.
[0013] Optionally, the item supply status indicates the inventory quantity of the item and / or a second supply quantity provided by the supplier corresponding to the initial production order to the warehouse and a supply time corresponding to the second supply quantity;
[0014] Based on the item inventory quantity of the item information and / or the second supply quantity provided by the supplier corresponding to the initial production order to the warehouse and the supply time corresponding to the second supply quantity, the step of allocating order processing shifts for the item information and item quantity contained in the initial production order is performed.
[0015] Optionally, generating a first production order for the order processing shift includes:
[0016] Further allocating order transfer and delivery nodes for the item information and item quantity allocated to the order processing shift according to a preset order transfer and delivery node priority strategy and the orders of the order transfer and delivery nodes;
[0017] According to the result of further allocating the transfer and delivery nodes in the order, a first production order is generated for the order processing shift.
[0018] Optionally, determining a target delivery strategy for the order transit delivery node includes:
[0019] For each order transfer and delivery node assigned with item information and item quantity, perform the following operations:
[0020] According to a plurality of preset supply intervals and a plurality of distance intervals, determining a target supply interval to which the first supply quantity of the order transfer and delivery node belongs and a target distance interval to which the distance between the order transfer and delivery node and the warehouse belongs;
[0021] According to the association relationship between the preset supply interval, the distance interval and the distribution strategy, the target distribution strategy corresponding to the target supply interval and the target distance interval is determined.
[0022] Optionally, generating a first production order for the order processing shift includes:
[0023] Matching the order transfer and delivery node with the item information and item quantity allocated to the order processing shift according to the relationship between the first supply quantity and the priority of the order transfer and delivery node indicated by the preset order transfer and delivery node priority strategy and the preset delivery strategy corresponding to the first supply quantity;
[0024] According to the matching result, adding the matched order transfer and delivery node information to the item information and the item quantity;
[0025] According to the distribution wave indicated by the distribution strategy and the distribution ratio and distribution time corresponding to the distribution wave, the distribution time is further added to the item information and the item quantity to obtain a first production order.
[0026] Optionally, before matching the item information and item quantity allocated to the order processing shift with the order transfer and delivery node, the method further includes:
[0027] Filtering out first item information belonging to the direct delivery type and first item quantity corresponding to the first item information from the item information and item quantity allocated to the order processing shift;
[0028] Adding a preset first clearing time for the first item information and the first item quantity;
[0029] For the item information and item quantity assigned to the order processing shift, and the non-direct delivery type item information and item quantity that have not been screened out, the step of matching the item information and item quantity assigned to the order processing shift with the order transfer and distribution node is performed.
[0030] Optionally, before matching the item information and item quantity allocated to the order processing shift with the order transfer and delivery node, the method further includes:
[0031] Determine whether the quantity of items allocated to the order processing shift exceeds a preset shift threshold. If so, execute the step of matching the item information and item quantity allocated to the order processing shift with the order transfer and delivery node; otherwise, directly add a preset second clearing time for the item information and the item quantity.
[0032] Optionally, after determining that the quantity of items allocated to the order processing shift exceeds a preset shift threshold and before matching the item information and item quantity allocated to the order processing shift with the order transfer and delivery node, the method further includes:
[0033] Filtering out second item information belonging to a preset time-limit type and a second item quantity corresponding to the second item information from the item information assigned to the order processing shift;
[0034] Adding a preset third clearing time corresponding to the second item information and the second item quantity;
[0035] Match the order transfer and delivery nodes based on the remaining item information and item quantity without added clearance time.
[0036] In a second aspect, an embodiment of the present invention provides an order fulfillment service end, including: a prediction module and a generation module, wherein:
[0037] The prediction module is used to predict the production volume of each order processing shift of the warehouse and the first supply volume provided by the warehouse for the order transfer and distribution node, and allocate item information and item quantity to the order processing shift according to the production volume of the order processing shift;
[0038] The generation module is used to generate a first production order for each of the order processing shifts according to a preset order transit and distribution node priority strategy, the order of the order transit and distribution node, and the item information and item quantity allocated to the order processing shift, and provide the first production order to the warehouse management server corresponding to the warehouse; determine a target distribution strategy for the order transit and distribution node according to the association between the preset supply interval, distance interval and distribution strategy, the first supply quantity of the order transit and distribution node, and the distance between the order transit and distribution node and the warehouse; generate a second production order and a third production order for the order transit and distribution node and the transportation and dispatching server respectively according to the distribution wave indicated by the target distribution strategy and the distribution ratio and distribution time corresponding to the distribution wave, provide the second production order to the corresponding order transit and distribution node server, and provide the third production order to the corresponding transportation and dispatching server.
[0039] In a third aspect, an embodiment of the present invention provides an order processing system, including: a warehouse management server, an order transfer and distribution node server, a transportation and distribution server, and the order fulfillment server provided by the embodiment of the second aspect above, wherein:
[0040] The warehouse management server is used to receive the first production order provided by the order fulfillment server, and perform outbound processing on the items stored in the warehouse and / or the items transported to the warehouse based on the first production order;
[0041] The order transfer and delivery node service end is used to receive the second production order provided by the order fulfillment service end, and to perform delivery processing on the items stored in the warehouse and / or the items transported to the warehouse based on the second production order;
[0042] The transport dispatching service end is used to receive the third production order provided by the order fulfillment service end, and arrange the vehicle wiring based on the third production order.
[0043] An embodiment of the above invention has the following advantages or beneficial effects: by predicting the production volume of each order processing shift of the warehouse and the first supply volume provided by the warehouse for the order transit and distribution node, and according to the production volume of the order processing shift, allocating item information and item quantity to the order processing shift, and then for each order processing shift, according to the preset order transit and distribution node priority strategy, the order of the order transit and distribution node, and the item information and item quantity allocated to the order processing shift, a first production order is generated for the order processing shift, and the first production order is provided to the warehouse management server corresponding to the warehouse. Since the generation of the first production order comprehensively considers the order transit and distribution node priority, the order of the order transit and distribution node, and the item information and item quantity allocated to the order processing shift, the first production order coordinates the demand of the order transit and distribution node and the item information and item quantity allocated to the order processing shift of the warehouse, so as to balance the demand of the order transit and distribution node with the warehouse's outbound delivery, so as to improve the order processing efficiency of the order transit and distribution node and the warehouse. Furthermore, by configuring distribution strategies for different supply intervals and distance intervals, different order transit and distribution nodes can have differentiated distribution strategies. Then, the distribution strategy is determined by comprehensively considering the predicted first supply provided by the warehouse to the order transit and distribution node and the distance between the order transit and distribution node and the warehouse (this distance will directly affect the distribution). This distribution strategy balances the distribution and the supply of the warehouse to the order transit and distribution node, so as to improve the processing efficiency of the warehouse and distribution. That is, the second production order and the third production order are generated for the order transit and distribution node and the transportation dispatch service end respectively through the distribution strategy, so as to further balance the production capacity of the distribution, warehouse and order transit and distribution nodes, improve the processing efficiency of the orders of the order transit and distribution nodes, and effectively balance the supply chain capacity and improve the order processing efficiency.
[0044] The further effects of the above-mentioned non-conventional optional manner will be described below in conjunction with the specific implementation manner. BRIEF DESCRIPTION OF THE DRAWINGS
[0045] The accompanying drawings are used to better understand the present invention and do not constitute an improper limitation of the present invention.
[0046] Figure 1 is an exemplary system architecture diagram to which embodiments of the present invention may be applied;
[0047] Figure 2 is a schematic diagram of the main process of the order processing method according to an embodiment of the present invention;
[0048] Figure 3 is a schematic diagram of a main process of generating a first production order for an order processing shift according to an embodiment of the present invention;
[0049] Figure 4 It is a schematic diagram of the main process of matching the item information and item quantity assigned to the order processing shift with the order transfer and delivery node according to an embodiment of the present invention;
[0050] Figure 5 is a schematic diagram of the main flow of an order processing method according to another embodiment of the present invention;
[0051] Figure 6 It is a schematic diagram of the main process of determining a target distribution strategy for an order transit distribution node according to an embodiment of the present invention;
[0052] Figure 7 is a schematic diagram of main modules of an order fulfillment server according to an embodiment of the present invention;
[0053] Figure 8 is a schematic diagram of main devices of an order processing system according to an embodiment of the present invention;
[0054] Fig. 9A It is a schematic diagram of the main process of regulating the production plan of the warehouse during the order processing according to an embodiment of the present invention;
[0055] Fig. 9B It is a schematic diagram of the main process of regulating the order transfer and distribution nodes and the production plan of transportation during the order processing process according to an embodiment of the present invention;
[0056] Fig.10 It is a schematic diagram of the structure of a computer system suitable for implementing a server of an embodiment of the present invention. DETAILED DESCRIPTION
[0057] The following is a description of exemplary embodiments of the present invention in conjunction with the accompanying drawings, including various details of the embodiments of the present invention to facilitate understanding, which should be considered as merely exemplary. Therefore, it should be recognized by those of ordinary skill in the art that various changes and modifications may be made to the embodiments described herein without departing from the scope and spirit of the present invention. Similarly, for clarity and conciseness, the description of well-known functions and structures is omitted in the following description.
[0058] In order to balance the supply chain capacity of orders generated by e-commerce and improve the processing efficiency of orders on the supply chain, an embodiment of the present invention provides an order processing method for e-commerce. In particular, it is aimed at processing orders generated by e-commerce in community group buying scenarios. Figure 1 An exemplary system architecture 100 is shown to which the order processing method according to an embodiment of the present invention can be applied.
[0059] like Figure 1 As shown, the system architecture 100 may include terminal devices 101, 102, 103, a user distribution node server 104, an order transfer and delivery node server 105, a warehouse management server 106, a transportation and dispatching server 107, a network 108, and an order fulfillment server 109. The network 108 is used to provide a medium for communication links between the terminal devices 101, 102, 103 and the user distribution node server 104, between the user distribution node server 104 and the order transfer and delivery node server 105, between the order transfer and delivery node server 105 and the order fulfillment server 109, between the warehouse management server 106 and the order fulfillment server 109, and between the transportation and dispatching server 107 and the order fulfillment server 109. The network 108 may include various connection types, such as wired, wireless communication links or optical fiber cables, etc.
[0060] The user uses the terminal devices 101, 102, 103 to interact with the user distribution node server 104 through the network 108 to receive or send information, etc. For example, the terminal devices 101, 102, 103 send the ordered item information and item quantity to the user distribution node server 104, and the user distribution node server 104 generates an e-commerce production order for the terminal devices 101, 102, 103, and sends the e-commerce production order to the terminal devices 101, 102, 103, etc. Various communication client applications can be installed on the terminal devices 101, 102, 103, such as e-commerce shopping applications, community group purchase order management applications, web browser applications, search applications, instant messaging tools, email clients, social platform software, etc. (only as examples).
[0061] The order fulfillment server 109 may be a server that provides various services, such as a background management server that provides support for the production capacity of the supply chain composed of warehouses, order transfer and distribution nodes, and transportation (only as an example). The background management server may process the data involved in the warehouse, order transfer and distribution nodes, and transportation process, and provide the processing results (such as production orders indicating the production plan of the warehouse, order transfer and distribution nodes, and transportation, etc. - only as an example) to the order transfer and distribution node server 105, the warehouse management server 106, and the transportation dispatch server 107.
[0062] The order transfer and delivery node server 105 arranges loading and unloading personnel, etc. according to the received production order indicating the production plan of the order transfer and delivery node.
[0063] The warehouse management server 106 arranges the shipment, distribution, and loading of goods according to the received production order indicating the production plan of the order transfer and distribution node.
[0064] The transport dispatching server 107 dispatches transport vehicles between the warehouse and the order transfer and delivery node according to the received production order indicating the production plan of the order transfer and delivery node.
[0065] The terminal devices 101 , 102 , and 103 may be various electronic devices having display screens and supporting web browsing, including but not limited to desktop computers, laptop computers, smart phones, tablet computers, and the like.
[0066] It should be noted that the order processing method provided in the embodiment of the present invention is generally completed through the order fulfillment server 109.
[0067] In addition, for community group buying scenarios, the order transfer and delivery nodes can be the grid stations of community group buying, and accordingly, the user distribution node servers can be the servers corresponding to the community group points. For retail scenarios, the order transfer and delivery nodes can be the transit warehouses,
[0068] It should be understood that Figure 1 The number of terminal devices, user distribution node servers, order transfer and delivery node servers, warehouse management servers, transportation and dispatching servers, networks and order fulfillment servers in the embodiment is only illustrative. According to the implementation requirements, there can be any number of terminal devices, user distribution node servers, order transfer and delivery node servers, warehouse management servers, transportation and dispatching servers, networks and order fulfillment servers.
[0069] Figure 2 FIG. 1 is a schematic diagram of the main flow of an order processing method according to an embodiment of the present invention. Figure 2 As shown, the order processing method may include the following steps:
[0070] Step S201: predicting the production volume of each order processing shift of the warehouse and the first supply volume provided by the warehouse for the order transfer and distribution node, and allocating item information and item quantity to the order processing shift according to the production volume of the order processing shift;
[0071] Among them, the order processing shift generally refers to the time period configured in the warehouse for picking, packing, distribution, loading, etc. for implementing the warehouse's production plan or processing production orders in the warehouse. Generally, there will be a fixed clearing time at the end of an order processing shift (that is, all or most of the items produced by the order processing shift are shipped out of the warehouse). For example, two order processing shifts can be set up in one day, one of which is from 4:00 to 12:00 and the other is from 14:00 to 21:00, etc.
[0072] Among them, the production volume of an order processing shift generally refers to the volume of items that can be processed by inputting historical data of the order processing shift in the warehouse that is related to the order processing timeliness, such as labor efficiency data, floor efficiency data, platform data, vehicle type information, delivery time, arrival time, and fulfillment timeliness into a preset cost model (the cost model is some existing training models, which is obtained by training with the above-mentioned historical data related to the order processing timeliness), and predicting the proportion of items that the order processing shift can process on the basis of minimizing the warehouse cost, and determining the volume of items that can be completed by the order processing shift through the proportion of items and the predicted volume of items processed by the warehouse throughout the day (the volume of items processed by the warehouse throughout the day is generally predicted based on the weekly, monthly, historical data average, etc. of the historical volume of items processed by the warehouse).
[0073] Among them, the first supply quantity provided by the warehouse for the order transit and distribution node (hereinafter referred to as the first supply quantity of the order transit and distribution node) is calculated based on the predicted production volume of the order processing shift and the proportion of the quantity provided by the warehouse for the order transit and distribution node (the proportion of the quantity is determined by the historical quantity provided by the warehouse for the order transit and distribution node). The first supply quantity is the sum of the predicted quantities of items provided by the warehouse for the order transit and distribution node in all order processing shifts of the day. In particular, for the scenario of community group buying, the first supply quantity provided by the warehouse for the order transit and distribution node may be the first supply quantity provided by the warehouse for the grid station. For the retail scenario, the first supply quantity provided by the warehouse for the order transit and distribution node may be the first supply quantity provided by the warehouse for the distribution transit warehouse.
[0074] Step S202: for each order processing shift, according to the preset order transfer and distribution node priority strategy, the order of the order transfer and distribution node, and the item information and item quantity allocated to the order processing shift, a first production order is generated for the order processing shift, and the first production order is provided to the warehouse management server corresponding to the warehouse;
[0075] Among them, the priority strategy of the order transfer and distribution node is generally determined based on the size of the quantity of items required by the order transfer and distribution node. Generally speaking, the larger the quantity of items required by the order transfer and distribution node, the higher the corresponding priority level. However, by comprehensively considering that the vehicle has a certain carrying capacity and reducing the influence of the deviation of the predicted first supply provided by the warehouse for the order transfer and distribution node on the priority of the order transfer and distribution node, the embodiment of the present invention configures the priority according to the item quantity interval, wherein the larger the interval value, the higher the priority corresponding to the item quantity interval. For example, the configured item quantity interval and priority can be the priority of more than 15,000 items>the priority of 10,000 to 15,000 items>the priority of 5001 to 9999 items>the priority of 3001 to 5000 items>the priority of 1001 to 3000 items>the priority of 1 to 1000 items. That is, if the first supply provided by the warehouse for two order transfer and distribution nodes belongs to the same item quantity interval, the first supply provided by the warehouse for the two order transfer and distribution nodes has the same processing priority.
[0076] Among them, the order of the order transfer and distribution node is generally a document allocated to the warehouse, generated based on the items ordered by the user and received by the order transfer and distribution node, and contains order transfer and distribution node information, item information, item quantity, group purchase time, etc. Among them, for the community group purchase scenario, the items ordered by the user can be the items ordered at the community group purchase point.
[0077] Among them, the first production order generally refers to a document that includes warehouse information, order transit and distribution node information, item information (such as sku information of items in the warehouse), item quantity and clearance time, so that the warehouse can arrange the production plan of the order processing shift according to the first production order.
[0078] Step S203: determining a target delivery strategy for the order transit delivery node according to the association between the preset supply interval, distance interval and delivery strategy, the first supply quantity of the order transit delivery node and the distance between the order transit delivery node and the warehouse;
[0079] The supply interval is the item quantity interval configured above to obtain the priority of the order transfer and distribution node. The distance interval is a distance segment divided based on the distance from the warehouse to multiple order transfer and distribution nodes, for example, the distance intervals are: 0-100km, 101-150km, 151-250km, 251-300km, etc.
[0080] Among them, the distribution strategy is based on a combination of supply intervals and distance intervals to determine the time point when the vehicle arrives at the order transfer and distribution node and the percentage of the quantity of items transported by the vehicle at that time point to the first supply quantity of the order transfer and distribution node (i.e. the proportion of items in the order transfer and distribution node). For example, for the combination of a supply interval of 5001 to 10000 pieces and a distance interval of 0 to 100 km, the time points for the vehicle to arrive at the order transfer and distribution node are determined to be 2:00 and 4:00, among which, the proportion of items transported to the order transfer and distribution node when the vehicle arrives at the order transfer and distribution node at 2:00 is 40%, and the proportion of items transported to the order transfer and distribution node when the vehicle arrives at the order transfer and distribution node at 4:00 is 60%; for another example, for the combination of a supply interval of 5001 to 10000 pieces and a distance interval of 101 to 150 km, the time points for the vehicle to arrive at the order transfer and distribution node are determined to be 3:00 and 5:00, among which, the proportion of items transported to the order transfer and distribution node when the vehicle arrives at the order transfer and distribution node at 3:00 is 40%, and the proportion of items transported to the order transfer and distribution node when the vehicle arrives at the order transfer and distribution node at 5:00 is 60%, and so on.
[0081] Step S204: According to the distribution wave indicated by the target distribution strategy and the distribution ratio and distribution time corresponding to the distribution wave, a second production order and a third production order are generated for the order transit distribution node and the transportation dispatching server respectively, and the second production order is provided to the corresponding order transit distribution node server, and the third production order is provided to the corresponding transportation dispatching server.
[0082] Among them, the distribution wave generally refers to the batch of vehicles sent to the order transfer distribution node within a day (wherein, vehicles arriving at the same time point belong to the same vehicle batch). The distribution ratio is the aforementioned ratio of items at the order transfer distribution node corresponding to the time point when the vehicle arrives at the order transfer distribution node, and the distribution time is the aforementioned time point when the vehicle arrives at the order transfer distribution node.
[0083] Among them, the second production order is a document that includes order transfer and distribution node information, item information (warehouse sku information), item quantity and latest arrival time (that is, the time point when the aforementioned vehicle arrives at the order transfer and distribution node).
[0084] Among them, the third production order includes warehouse information, order transfer and distribution node information, latest arrival time (that is, the time point when the aforementioned vehicle arrives at the order transfer and distribution node), item information (warehouse sku information), item quantity and clearance time of the order processing shift.
[0085] exist Figure 2 In the illustrated embodiment, the production volume of each order processing shift of the warehouse and the first supply volume provided by the warehouse for the order transit and distribution node are predicted, and item information and item quantity are allocated to the order processing shift according to the production volume of the order processing shift. Then, for each order processing shift, according to the preset order transit and distribution node priority strategy, the orders of the order transit and distribution node, and the item information and item quantity allocated to the order processing shift, a first production order is generated for the order processing shift, and the first production order is provided to the warehouse management server corresponding to the warehouse. Since the generation of the first production order comprehensively considers the order transit and distribution node priority, the orders of the order transit and distribution node, and the item information and item quantity allocated to the order processing shift, the first production order coordinates the demand of the order transit and distribution node and the item information and item quantity allocated to the order processing shift of the warehouse, so as to balance the demand of the order transit and distribution node with the warehouse's outbound delivery, so as to improve the order processing efficiency of the order transit and distribution node and the warehouse. Furthermore, by configuring distribution strategies for different supply intervals and distance intervals, different order transit and distribution nodes can have differentiated distribution strategies. Then, the distribution strategy is determined by comprehensively considering the predicted first supply provided by the warehouse to the order transit and distribution node and the distance between the order transit and distribution node and the warehouse (this distance will directly affect the distribution). This distribution strategy balances the distribution and the supply of the warehouse to the order transit and distribution node, so as to improve the processing efficiency of the warehouse and distribution. That is, the second production order and the third production order are generated for the order transit and distribution node and the transportation dispatch service end respectively through the distribution strategy, so as to further balance the production capacity of the distribution, warehouse and order transit and distribution nodes, improve the processing efficiency of the orders of the order transit and distribution nodes, and effectively balance the supply chain capacity and improve the order processing efficiency.
[0086] Among them, the specific implementation method of allocating item information and item quantity to order processing shifts may include: when an initial production order sent by an order service end is obtained, statistics are performed on the item information and item quantity contained in the initial production order, wherein the item information and item quantity correspond to orders of one or more order transfer and distribution nodes contained in the initial production order; and order processing shifts are allocated to the item information and item quantity contained in the initial production order based on the predicted production volume of each order processing shift, the statistical results, and the item supply situation corresponding to the item information.
[0087] Among them, the above-mentioned initial production order is a document generated by the order service end according to the supplier's supply wave, which contains orders that need to be processed by the warehouse for each order transfer and distribution node. It records the item information and item quantity of the order placed by the order transfer and distribution node, as well as the information and item quantity of the supplier's provided items and the time point of arrival at the warehouse, so that the item information and item quantity that can be provided by the supplier's supply wave can be comprehensively considered in the subsequent generation of the first production order. It can avoid the tedious operation of putting the goods provided by the supplier on the shelves first and then taking them off the shelves, improve processing efficiency, reduce processing costs, and better meet the needs of order transfer and distribution node orders.
[0088] Correspondingly, the above-mentioned first production order is also generated according to the supplier's supply waves. For example, if the supplier has four supply waves in one day, four first production orders are generated for the warehouse to comprehensively consider the supplier's supply and ensure that the orders at the order transfer and distribution nodes can be processed relatively evenly within one day or one order processing shift, thereby ensuring order processing efficiency.
[0089] Specifically, the above-mentioned item supply situation indicates the item inventory and / or the second supply quantity provided by the supplier corresponding to the initial production order to the warehouse and the supply time corresponding to the second supply quantity; accordingly, based on the item inventory of the item information and / or the second supply quantity provided by the supplier corresponding to the initial production order to the warehouse and the supply time corresponding to the second supply quantity, the above-mentioned step of allocating order processing shifts for the item information and item quantity included in the initial production order is performed. Among them, the item inventory generally refers to the item quantity of a certain item that has been put on the shelf in the warehouse.
[0090] Among them, the supply time of the supplier (i.e. the above-mentioned supplier) for the initial production order can be obtained from the procurement system. For example, the estimated arrival time of the items supplied by the supplier is compared with the clearing time of the order processing shift. If the clearing time of the order processing shift is 21:00, and the arrival time of the items supplied by the supplier is earlier than 21:00, the comprehensive inventory of the items supplied by the supplier can be included in the scope of consideration of the items and item quantities required for the first production order of the order processing shift, ensuring that the orders at the order transfer and distribution nodes can be processed relatively evenly within one day or one order processing shift, thereby ensuring the efficiency of order processing.
[0091] Specifically, the specific implementation of generating the first production order for the order processing shift may include: further allocating order transfer and distribution nodes for the item information and item quantity allocated to the order processing shift according to the preset order transfer and distribution node priority strategy and the order of the order transfer and distribution node; and generating the first production order for the order processing shift according to the result of further allocating the order transfer and distribution node. That is, the priority of the order transfer and distribution node is determined for the supply interval where the order of the order transfer and distribution node containing the item quantity is located, and the item information and item quantity are preferentially allocated to the order transfer and distribution node with a high priority. For example, if the order package of order transfer and distribution node 1 contains 5,500 items of item information A, the order package of order transfer and distribution node 2 contains 3,500 items of item information A, and the order package of order transfer and distribution node 3 contains 500 items of item information A, the item quantity of item information A is allocated to order transfer and distribution node 1 first, then the item quantity of item information A is allocated to order transfer and distribution node 2, and finally the item quantity of item information A is allocated to order transfer and distribution node 3. Among them, the item quantity of item information allocated to each order transfer and distribution node is determined by comprehensively considering the distribution wave, the item ratio corresponding to the distribution wave, and the item quantity of item information on the first production order. For example, the quantity of item information A on the first production order is 3000, among which the proportion of items in the delivery wave corresponding to order transit and distribution node 1 is 40%, then the quantity of item information A allocated is 5500×40%=2200, and the proportion of items in the delivery wave corresponding to order transit and distribution node 2 is 100%, then the quantity of item information A allocated to order transit and distribution node 2 is 3000-2200=800, and finally the quantity of item information A allocated to order transit and distribution node 3 is 0. For another example, the quantity of item information A on the first production order is 5500, among which the proportion of items in the delivery wave corresponding to order transit and distribution node 1 is 40%, then the quantity of item information A allocated is 5500×40%=2200, and the proportion of items in the delivery wave corresponding to order transit and distribution node 2 is 100%, then the quantity of item information A allocated to order transit and distribution node 2 is 3000, and finally the quantity of item information A allocated to order transit and distribution node 3 is 5500-2200-3000=300.
[0092] Through the above processing process, the first production order in the warehouse can process and distribute items according to the dimensions of the transfer and distribution nodes in the order, further reducing the processing flow of the supply chain, so as to further improve the processing efficiency of the supply chain and reduce the operating costs of the supply chain.
[0093] Furthermore, if Figure 3 As shown, the specific implementation method of generating the first production order for the order processing shift may include the following steps:
[0094] Step S301: matching the order transfer and delivery node with the item information and item quantity assigned to the order processing shift according to the relationship between the first supply quantity and the priority of the order transfer and delivery node indicated by the preset order transfer and delivery node priority strategy and the delivery strategy corresponding to the preset first supply quantity;
[0095] The distribution strategy corresponding to the preset first supply quantity may be as shown in Table 1 below.
[0096] Table 1
[0097]
[0098]
[0099] For example, as shown in Table 1, for a supply range of more than 15,000 items in the distance range of 0 to 100 km, there are four distribution waves, and the corresponding item proportions and distribution times are: 20%, 0:00; 20%, 1:00; 25%, 3:00; 35%, 4:00.
[0100] For example, the aforementioned priority is to allocate the quantity of item information A to order transit and distribution node 1, then allocate the quantity of item information A to order transit and distribution node 2, and finally allocate the quantity of item information A to order transit and distribution node 3. For the quantity of item information A on the first production order of 5500, among which, the proportion of items in distribution wave 1 corresponding to order transit and distribution node 1 is 40%, then the quantity of item information A allocated is 5500×40%=2200, and the proportion of items in the distribution wave corresponding to order transit and distribution node 2 is 100%, then the quantity of item information A allocated to order transit and distribution node 2 is 3000, and finally the quantity of item information A allocated to order transit and distribution node 3 is 5500-2200-3000=300.
[0101] Step S302: according to the matching result, adding the matched order transfer and delivery node information to the item information and item quantity;
[0102] That is, add the order transit and distribution node information of order transit and distribution node 1 for item information A and its corresponding item quantity 2200, add the order transit and distribution node information of order transit and distribution node 2 for item information A and its corresponding item quantity 3000, and add the order transit and distribution node information of order transit and distribution node 3 for item information A and its corresponding item quantity 300.
[0103] Step S303: According to the delivery wave indicated by the delivery strategy and the delivery ratio and delivery time corresponding to the delivery wave, the delivery time is further added to the item information and the item quantity to obtain the first production order.
[0104] For example, the delivery time of the delivery wave 1 of the aforementioned order transit delivery node 1 is 2:00, the delivery time of the delivery wave of the order transit delivery node 2 is 5:00, and the delivery time of the delivery wave of the order transit delivery node 3 is 6:00. Then, the delivery time 2:00 is further added to the item information A and its corresponding item quantity 2200, the delivery time 5:00 is further added to the item information A and its corresponding item quantity 3000, and the delivery time 6:00 is further added to the item information A and its corresponding item quantity 300.
[0105] In summary, the above-mentioned first production order contains the information of each order transfer and distribution node, the item information and item quantity corresponding to the order transfer and distribution node information, and the corresponding delivery time, so that the subsequent warehouse management server can arrange personnel, coordinate item sorting, distribution sequence, time control, etc. according to the information contained in the first production order, so as to facilitate the subsequent process collaboration with the supply chain and meet the needs of transportation and order transfer and distribution nodes.
[0106] Furthermore, in order to meet the special needs of special types of items such as direct delivery (directly delivered to users), Figure 4 As shown, before the item information and item quantity assigned to the above order processing shift are matched with the order transfer and delivery node, the following steps may be further included:
[0107] Step S401: Filtering out first item information belonging to the direct delivery type and first item quantity corresponding to the first item information from the item information and item quantity assigned to the order processing shift;
[0108] Step S402: adding a preset first clearing time for the first item information and the first item quantity;
[0109] The first clearing time can be customized according to needs.
[0110] Step S403: For the item information and item quantity assigned to the order processing shift, and the non-direct delivery type item information and item quantity that have not been screened out, the step of matching the item information and item quantity assigned to the order processing shift with the order transfer and delivery node is performed.
[0111] Through the above process, it is possible to separate directly shipped items from items entering the order transfer and distribution node to meet the needs of multiple scenarios.
[0112] Furthermore, before matching the item information and item quantity assigned to the order processing shift with the order transfer and delivery node, it may further include: judging whether the item quantity assigned to the order processing shift exceeds the preset shift threshold, if so, executing the step of matching the item information and item quantity assigned to the order processing shift with the order transfer and delivery node; otherwise, directly adding a preset second clearing time for the item information and item quantity. Among them, the shift threshold can be set according to demand, for example, it can be 60% of the predicted production volume of the order processing shift. By judging whether the item quantity assigned to the order processing shift exceeds the preset shift threshold, in the case of a small amount of items, the items are processed faster and do not need to reach the clearing time of the order processing shift to complete, then a preset second clearing time before the clearing time of the order processing shift can be assigned to these items, and the preset second clearing time is generally before the clearing time of the order processing shift, so that when the item quantity is small, the processing efficiency of the warehouse can still be guaranteed, and the items are prevented from being piled up until the second half of the order processing shift.
[0113] In addition, in the embodiment of the present invention, Figure 5 As shown, after determining that the quantity of items assigned to the order processing shift exceeds the preset shift threshold, before matching the item information and item quantity assigned to the order processing shift with the order transfer and delivery node, the following steps may be further included:
[0114] Step S501: Filtering out second item information belonging to a preset time-limit type and a second item quantity corresponding to the second item information from the item information assigned to the order processing shift;
[0115] This time-sensitive type refers to items with a delivery time limit, such as fresh produce, fruits and vegetables, etc.
[0116] Step S502: adding a preset third clearing time corresponding to the second item information and the second item quantity;
[0117] Among them, the third clearing time is generally customized according to actual needs.
[0118] Step S503: Match the order transfer and delivery nodes with the remaining item information and item quantity that have not been added with the clearance time.
[0119] Through the above process, time-sensitive items and regular items can be processed separately to ensure the processing timeliness of the time-sensitive items.
[0120] Specifically, the specific implementation method of determining the target delivery strategy for the order transfer delivery node may include: for each order transfer delivery node assigned to the item information and item quantity, executing the following Figure 6 The individual steps shown:
[0121] Step S601: determining a target supply interval to which a first supply quantity of an order transfer and delivery node belongs and a target distance interval to which a distance between the order transfer and delivery node and a warehouse belongs according to a plurality of preset supply intervals and a plurality of distance intervals;
[0122] Step S602: Determine a target distribution strategy corresponding to a target supply interval and a target distance interval according to the association relationship among preset supply intervals, distance intervals, and distribution strategies.
[0123] For example, taking the distribution strategy given in Table 1 as an example, the first supply quantity of the order transit distribution node is 10,500, and its target supply range is 10,000 to 15,000 pieces. The distance between the order transit distribution node and the warehouse is 200 km, and its target distance range is 151 to 250 km. The corresponding distribution strategy is three distribution waves: the proportion of items in the first distribution wave is 25%, and the corresponding distribution time is 3:00; the proportion of items in the second distribution wave is 35%, and the corresponding distribution time is 5:00; the proportion of items in the third distribution wave is 40%, and the corresponding distribution time is 6:00.
[0124] Furthermore, the second production order generated for the order transfer and distribution node service end and the third production order generated for the transport and distribution service end can be obtained by integrating the first production order and the distribution strategy. For example, the item information, corresponding item quantity, order transfer and distribution node information, clearing time / distribution time, etc. of each order transfer and distribution node can be extracted from the first production order, and the extracted item information, corresponding item quantity, order transfer and distribution node information, clearing time / distribution time, etc. of each order transfer and distribution node constitute a second production order for the order transfer and distribution node.
[0125] Figure 7 Schematic diagram of the structure of an order fulfillment service provided by an embodiment of the present invention. Figure 7 As shown, the order fulfillment server 700 may include: a prediction module 701 and a generation module 702, wherein:
[0126] The prediction module 701 is used to predict the production volume of each order processing shift of the warehouse and the first supply volume provided by the warehouse for the order transfer and distribution node, and allocate item information and item quantity to the order processing shift according to the production volume of the order processing shift;
[0127] Generation module 702 is used to generate a first production order for each order processing shift according to a preset order transit and distribution node priority strategy, orders of the order transit and distribution node, and item information and item quantity allocated to the order processing shift, and provide the first production order to the warehouse management server corresponding to the warehouse; determine a target distribution strategy for the order transit and distribution node according to the preset relationship between the supply interval, distance interval and distribution strategy, the first supply quantity of the order transit and distribution node, and the distance between the order transit and distribution node and the warehouse; generate a second production order and a third production order for the order transit and distribution node and the transport dispatch server respectively according to the distribution wave indicated by the target distribution strategy and the distribution ratio and distribution time corresponding to the distribution wave, provide the second production order to the corresponding order transit and distribution node server, and provide the third production order to the corresponding transport dispatch server.
[0128] In an embodiment of the present invention, the prediction module 701 is further used to, upon obtaining an initial production order sent by an order service end, count the item information and item quantity contained in the initial production order, wherein the item information and item quantity correspond to orders of one or more order transfer and distribution nodes contained in the initial production order; and allocate order processing shifts for the item information and item quantity contained in the initial production order based on the predicted production volume of each order processing shift, the statistical results, and the item supply situation corresponding to the item information.
[0129] In an embodiment of the present invention, the item supply situation indicates the item inventory quantity and / or the second supply quantity provided by the supplier corresponding to the initial production order to the warehouse and the supply time corresponding to the second supply quantity; the prediction module 701 is further used to execute the step of allocating order processing shifts for the item information and item quantity contained in the initial production order based on the item inventory quantity of the item information and / or the second supply quantity provided by the supplier corresponding to the initial production order to the warehouse and the supply time corresponding to the second supply quantity.
[0130] In an embodiment of the present invention, the generation module 702 is further used to further allocate the order transfer and distribution node for the item information and item quantity assigned to the order processing shift according to the preset order transfer and distribution node priority strategy and the order of the order transfer and distribution node; and generate the first production order for the order processing shift based on the result of further allocating the order transfer and distribution node.
[0131] In an embodiment of the present invention, the generation module 702 is further used to perform the following operations for each order transit and distribution node assigned to item information and item quantity: determine, based on a preset plurality of supply intervals and a preset plurality of distance intervals, a target supply interval to which the first supply quantity of the order transit and distribution node belongs and a target distance interval to which the distance between the order transit and distribution node and the warehouse belongs; and determine, based on the relationship between the preset supply intervals, distance intervals and distribution strategies, a target distribution strategy corresponding to the target supply interval and the target distance interval.
[0132] In an embodiment of the present invention, the generation module 702 is further used to match the order transit and distribution node for the item information and item quantity allocated to the order processing shift according to the relationship between the first supply quantity and the priority of the order transit and distribution node indicated by the preset order transit and distribution node priority strategy and the distribution strategy corresponding to the preset first supply quantity; according to the matching result, add the matched order transit and distribution node information to the item information and item quantity; according to the distribution wave indicated by the distribution strategy and the distribution ratio and distribution time corresponding to the distribution wave, further add the distribution time to the item information and item quantity to obtain the first production order.
[0133] In an embodiment of the present invention, the prediction module 701 is further used to filter out first item information of a direct delivery type and a first item quantity corresponding to the first item information from the item information and item quantity assigned to the order processing shift; add a preset first clearance time for the first item information and the first item quantity; and, for the item information and item quantity of non-direct delivery type that have not been filtered out among the item information and item quantity assigned to the order processing shift, perform the step of matching the item information and item quantity assigned to the order processing shift with the transfer and distribution node in the order.
[0134] In the embodiment of the present invention, the prediction module 701 is further used to determine whether the quantity of items allocated to the order processing shift exceeds a preset shift threshold. If so, the step of matching the item information and item quantity allocated to the order processing shift with the order transfer and distribution node is executed; otherwise, the preset second clearing time is directly added to the item information and item quantity.
[0135] In the embodiment of the present invention, the prediction module 701 is further used to filter out second item information belonging to a preset time-limit type and a second item quantity corresponding to the second item information from the item information assigned to the order processing shift; add a preset third clearance time corresponding to the second item information and the second item quantity; and match the order transit and distribution node for the remaining item information and item quantity without added clearance time.
[0136] Figure 8 Schematic diagram of the structure of an order processing system provided by an embodiment of the present invention. Figure 8As shown, the order processing system may include: a warehouse management server 801, an order transfer and distribution node server 802, a transportation and distribution server 803 and Figure 7 The order fulfillment server 700 shown, wherein:
[0137] The warehouse management server 801 is used to receive the first production order provided by the order fulfillment server 700, and perform outbound processing on the items stored in the warehouse and / or the items transported to the warehouse based on the first production order;
[0138] The order transfer and delivery node service end 802 is used to receive the second production order provided by the order fulfillment service end 700, and perform delivery processing on the items stored in the warehouse and / or the items transported to the warehouse based on the second production order;
[0139] The transport dispatching service end 803 is used to receive the third production order provided by the order fulfillment service end 700, and arrange the vehicle route based on the third production order.
[0140] The above-mentioned warehouse management server 801, order transfer and distribution node server 802 and transportation allocation server 803 coordinate and balance personnel and vehicle scheduling with reference to the production order, which can help reduce supply chain costs and help improve supply chain processing efficiency.
[0141] The following takes the interaction process between the order system, order fulfillment server, warehouse management server, order transfer and distribution node server, and transportation and dispatch server as an example to explain in detail the order processing process provided by the embodiment of the present invention. Fig. 9A It shows the main process of regulating the warehouse production plan during order processing. Fig. 9B The main process of regulating the order transfer and distribution nodes and the production plan of transportation during the order processing is shown. Fig. 9A As shown, the main process of regulating the production plan of the warehouse during the order processing may include the following steps:
[0142] Step S900: The order fulfillment service end predicts the production volume of each order processing shift of the warehouse and the first supply volume provided by the warehouse for the order transit and distribution node;
[0143] Step S901: the order system sends the initial production order of the production wave to the order fulfillment server;
[0144] Step S902: the order fulfillment server collects statistics on the item information and item quantity included in the initial production order;
[0145] This step can be used to count the item information (such as sku information) and the total quantity of items in each order's transfer and distribution nodes or direct delivery users.
[0146] The item information and item quantity correspond to the orders of the transfer and distribution nodes in one or more orders included in the initial production order.
[0147] Step S903: the order fulfillment server allocates an order processing shift for the item information and item quantity included in the initial production order according to the predicted production volume of each order processing shift, the statistical results, and the item supply situation corresponding to the item information;
[0148] The item supply status indicates the inventory quantity of the item and / or a second supply quantity provided by the supplier corresponding to the initial production order to the warehouse and a supply time corresponding to the second supply quantity.
[0149] That is, through this step, the order processing shift can be allocated with items provided by the supplier (supplier) that have inventory and / or can arrive at the warehouse within the processing time range of the order processing shift. The order processing shift is allocated for item information and item quantity by comprehensively considering the inventory in the warehouse and the supply provided by the supplier to ensure that the allocated item information and item quantity can be processed in the order processing shift, avoiding the idleness of the order processing shift due to out-of-stock, and the backlog of the processing quantity of the subsequent order processing shift.
[0150] This process completes the allocation of item information and item quantity to the order processing shift based on the initial production order, item inventory and supplier's supply status.
[0151] Step S904: Filter out first item information belonging to the direct delivery type and the first item quantity corresponding to the first item information from the item information and item quantity assigned to the order processing shift; execute step S905 for the first item information and the first item quantity; execute step S906 for the item information and item quantity that are not filtered out from the item information and item quantity assigned to the order processing shift;
[0152] Step S905: adding a preset first clearing time to the first item information and the first item quantity, and ending the current process;
[0153] Through the above steps S904 and S905, independent process processing of direct delivery type items is achieved.
[0154] Step S906: Determine whether the quantity of items assigned to the order processing shift exceeds the preset shift threshold. If yes, execute step S907; otherwise, execute step S909;
[0155] Step S907: Filtering out second item information belonging to a preset time-limit type and a second item quantity corresponding to the second item information from the item information assigned to the order processing shift;
[0156] Step S908: adding a preset third clearing time corresponding to the second item information and the second item quantity, and executing step S910;
[0157] Through step S907 and step S908, it is possible to process items with strict timeliness requirements, such as fresh food, fruits and vegetables, etc., through independent processes to meet more scene requirements.
[0158] Step S909: directly adding the preset second clearing time to the item information and item quantity, and ending the current process;
[0159] Step S910: matching the order transfer and delivery node with the item information and item quantity assigned to the order processing shift according to the relationship between the first supply quantity and the priority of the order transfer and delivery node indicated by the preset order transfer and delivery node priority strategy and the delivery strategy corresponding to the preset first supply quantity;
[0160] Among them, the relationship between the first supply quantity and the priority of the order transit and distribution node indicated by the order transit and distribution node priority strategy and the distribution strategy corresponding to the preset first supply quantity have been stated before and will not be repeated here.
[0161] Step S911: according to the matching result, adding the matched order transfer and delivery node information to the item information and item quantity;
[0162] Step S912: according to the delivery wave indicated by the delivery strategy and the delivery ratio and delivery time corresponding to the delivery wave, the delivery time is further added to the item information and the item quantity to obtain the first production order;
[0163] Step S913: the order fulfillment server provides the first production order to the warehouse management server corresponding to the warehouse;
[0164] Step S914: the warehouse management server matches the inventory for the item information included in the first production order. If the inventory is not matched, step S915 is executed; if the inventory is matched, step S918 is executed;
[0165] Step S915: Determine whether the items supplied by the supplier have arrived. If they have arrived, execute step S916; if they have not arrived, execute step S917;
[0166] Step S916: inspect and accept the items entering the cross-docking pool, and execute step S918;
[0167] Step S917: temporarily suspend the item information, wait for subsequent processing, and end the current process;
[0168] Step S918: Generate distribution tasks for the item information according to the item quantity required by the order transfer and delivery node, and send the distribution tasks to the warehouse so that the warehouse staff can distribute and load the items.
[0169] Furthermore, taking the supply interval, distance interval and distribution strategy given in Table 1 as an example, Fig. 9B As shown in the figure, the main process of regulating the order transfer and distribution nodes and the production plan of transportation is to perform the following steps for each order transfer and distribution node assigned to the item information and item quantity:
[0170] Step S919: the order fulfillment server determines the target supply interval to which the first supply quantity of the order transit delivery node belongs and the target distance interval to which the distance between the order transit delivery node and the warehouse belongs according to the preset multiple supply intervals and multiple distance intervals;
[0171] The first supply quantity of the order transfer and distribution node is obtained in the above step S900. For example, if the first supply quantity of the order transfer and distribution node is 4500 and the distance between the order transfer and distribution node and the warehouse is 160km, the first supply quantity of the order transfer and distribution node belongs to the supply interval of 3001 to 5000 pieces in Table 1, and the distance between the order transfer and distribution node and the warehouse belongs to the distance interval of 151 to 250km.
[0172] Step S920: determining a target delivery strategy corresponding to a target supply interval and a target distance interval according to a preset association relationship between a supply interval, a distance interval, and a delivery strategy;
[0173] For example, for the combination of supply range 3001-5000 pieces and distance range 151-250 km, the corresponding strategy is: item ratio 100% and delivery time 6:00.
[0174] Step S921: according to the delivery wave indicated by the target delivery strategy and the delivery ratio and delivery time corresponding to the delivery wave, a second production order and a third production order are generated for the order transfer delivery node and the transport dispatching service end respectively, and steps S922 and S924 are executed;
[0175] Step S922: the order fulfillment server provides the second production order to the corresponding order transfer and delivery node server;
[0176] Step S923: the order transfer and distribution node service end arranges the order transfer and distribution node personnel to unload, distribute and deliver the goods according to the second production order, and ends the current process;
[0177] Step S924: the order fulfillment server provides the third production order to the corresponding transportation dispatch server;
[0178] Step S925: The transport dispatching service arranges the ferrying of vehicles according to the third production order.
[0179] Reference below Fig.10 , which shows a structural diagram of a computer system 1000 of a server used for a supply chain fulfillment scheduling platform and a cross-border docking platform suitable for implementing an embodiment of the present invention. Fig.10 The server shown is only an example and should not bring any limitation to the functions and scope of use of the embodiments of the present invention.
[0180] like Fig.10 As shown, the computer system 1000 includes a central processing unit (CPU) 1001, which can perform various appropriate actions and processes according to a program stored in a read-only memory (ROM) 1002 or a program loaded from a storage part 1008 into a random access memory (RAM) 1003. In the RAM 1003, various programs and data required for the operation of the system 1000 are also stored. The CPU 1001, the ROM 1002, and the RAM 1003 are connected to each other via a bus 1004. An input / output (I / O) interface 1005 is also connected to the bus 1004.
[0181] The following components are connected to the I / O interface 1005: an input section 1006 including a keyboard, a mouse, etc.; an output section 1007 including a cathode ray tube (CRT), a liquid crystal display (LCD), etc., and a speaker, etc.; a storage section 1008 including a hard disk, etc.; and a communication section 1009 including a network interface card such as a LAN card, a modem, etc. The communication section 1009 performs communication processing via a network such as the Internet. A drive 1010 is also connected to the I / O interface 1005 as needed. A removable medium 1011, such as a magnetic disk, an optical disk, a magneto-optical disk, a semiconductor memory, etc., is installed on the drive 1010 as needed, so that a computer program read therefrom is installed into the storage section 1008 as needed.
[0182] In particular, according to the embodiments disclosed in the present invention, the process described above with reference to the flowchart can be implemented as a computer software program. For example, the embodiments disclosed in the present invention include a computer program product, which includes a computer program carried on a computer-readable medium, and the computer program includes a program code for executing the method shown in the flowchart. In such an embodiment, the computer program can be downloaded and installed from the network through the communication part 1009, and / or installed from the removable medium 1011. When the computer program is executed by the central processing unit (CPU) 1001, the above-mentioned functions defined in the system of the present invention are executed.
[0183] It should be noted that the computer-readable medium shown in the present invention may be a computer-readable signal medium or a computer-readable storage medium or any combination of the above two. The computer-readable storage medium may be, for example, but not limited to, an electrical, magnetic, optical, electromagnetic, infrared, or semiconductor system, device or device, or any combination of the above. More specific examples of computer-readable storage media may include, but are not limited to: an electrical connection with one or more wires, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the above. In the present invention, a computer-readable storage medium may be any tangible medium containing or storing a program that can be used by or in combination with an instruction execution system, device or device. In the present invention, a computer-readable signal medium may include a data signal propagated in a baseband or as part of a carrier wave, which carries a computer-readable program code. This propagated data signal may take a variety of forms, including but not limited to electromagnetic signals, optical signals, or any suitable combination of the above. Computer-readable signal media may also be any computer-readable medium other than computer-readable storage media, which may send, propagate or transmit a program for use by or in conjunction with an instruction execution system, apparatus or device. The program code contained on the computer-readable medium may be transmitted using any appropriate medium, including but not limited to: wireless, wire, optical cable, RF, etc., or any suitable combination of the above.
[0184] The flow chart and block diagram in the accompanying drawings illustrate the possible architecture, function and operation of the system, method and computer program product according to various embodiments of the present invention. In this regard, each box in the flow chart or block diagram can represent a module, a program segment, or a part of a code, and the above-mentioned module, program segment, or a part of a code contains one or more executable instructions for realizing the specified logical function. It should also be noted that in some alternative implementations, the functions marked in the box can also occur in a different order from the order marked in the accompanying drawings. For example, two boxes represented in succession can actually be executed substantially in parallel, and they can sometimes be executed in the opposite order, depending on the functions involved. It should also be noted that each box in the block diagram or flow chart, and the combination of the boxes in the block diagram or flow chart can be implemented with a dedicated hardware-based system that performs a specified function or operation, or can be implemented with a combination of dedicated hardware and computer instructions.
[0185] The modules involved in the embodiments of the present invention may be implemented in software or hardware. The modules described may also be set in a processor, for example, they may be described as: a processor includes a prediction module and a generation module. The names of these modules do not constitute limitations on the modules themselves in some cases. For example, the prediction module may also be described as "a module for predicting the production volume of each order processing shift of the warehouse and the first supply volume provided by the warehouse for the order transfer and distribution node".
[0186] As another aspect, the present invention also provides a computer-readable medium, which may be included in the device described in the above embodiment; or it may exist independently without being assembled into the device. The above computer-readable medium carries one or more programs. When the above one or more programs are executed by a device, the device includes: predicting the production volume of each order processing shift of the warehouse and the first supply volume provided by the warehouse for the order transit and distribution node, and allocating item information and item quantity to the order processing shift according to the production volume of the order processing shift; for each order processing shift, according to the preset order transit and distribution node priority strategy, the order of the order transit and distribution node, and the item information and item quantity allocated to the order processing shift, generate a first production order for the order processing shift, and submit the first production order to the warehouse. Supply the warehouse management server corresponding to the warehouse; determine the target distribution strategy for the order transit distribution node according to the preset supply interval, the relationship between the distance interval and the distribution strategy, the first supply quantity of the order transit distribution node, and the distance between the order transit distribution node and the warehouse; generate the second production order and the third production order for the order transit distribution node and the transport dispatch server respectively according to the distribution wave indicated by the target distribution strategy and the distribution ratio and distribution time corresponding to the distribution wave, provide the second production order to the corresponding order transit distribution node server, and provide the third production order to the corresponding transport dispatch server.
[0187] According to the technical solution of the embodiment of the present invention, by predicting the production volume of each order processing shift of the warehouse and the first supply volume provided by the warehouse for the order transit and distribution node, and allocating item information and item quantity to the order processing shift according to the production volume of the order processing shift, then for each order processing shift, according to the preset order transit and distribution node priority strategy, the order of the order transit and distribution node, and the item information and item quantity allocated to the order processing shift, a first production order is generated for the order processing shift, and the first production order is provided to the warehouse management server corresponding to the warehouse. Since the generation of the first production order comprehensively considers the order transit and distribution node priority, the order of the order transit and distribution node, and the item information and item quantity allocated to the order processing shift, the first production order coordinates the demand of the order transit and distribution node and the item information and item quantity allocated to the order processing shift of the warehouse, so as to balance the demand of the order transit and distribution node with the warehouse's outbound delivery, so as to improve the order processing efficiency of the order transit and distribution node and the warehouse. Furthermore, by configuring distribution strategies for different supply intervals and distance intervals, different order transit and distribution nodes can have differentiated distribution strategies. Then, the distribution strategy is determined by comprehensively considering the predicted first supply provided by the warehouse to the order transit and distribution node and the distance between the order transit and distribution node and the warehouse (this distance will directly affect the distribution). This distribution strategy balances the distribution and the supply of the warehouse to the order transit and distribution node, so as to improve the processing efficiency of the warehouse and distribution. That is, the second production order and the third production order are generated for the order transit and distribution node and the transportation dispatch service end respectively through the distribution strategy, so as to further balance the production capacity of the distribution, warehouse and order transit and distribution nodes, improve the processing efficiency of the orders of the order transit and distribution nodes, and effectively balance the supply chain capacity and improve the order processing efficiency.
[0188] The above specific implementations do not constitute a limitation on the protection scope of the present invention. It should be understood by those skilled in the art that various modifications, combinations, sub-combinations and substitutions may occur depending on design requirements and other factors. Any modification, equivalent substitution and improvement made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. An order processing method, characterized in that: include: Predicting the production volume of each order processing shift of the warehouse and the first supply volume provided by the warehouse for the order transfer and distribution node, and allocating item information and item quantity to the order processing shift according to the production volume of the order processing shift; For each of the order processing shifts, according to a preset order transfer and delivery node priority strategy, orders of the order transfer and delivery nodes, and item information and item quantity allocated to the order processing shift, a first production order is generated for the order processing shift, and the first production order is provided to a warehouse management server corresponding to the warehouse; Determine a target distribution strategy for the order transit distribution node according to the association between the preset supply interval, distance interval and distribution strategy, the first supply quantity of the order transit distribution node and the distance between the order transit distribution node and the warehouse; According to the distribution wave indicated by the target distribution strategy and the distribution ratio and distribution time corresponding to the distribution wave, a second production order and a third production order are generated for the order transit distribution node and the transportation allocation server respectively, and the second production order is provided to the corresponding order transit distribution node service, and the third production order is provided to the corresponding transportation allocation server.
2. The order processing method according to claim 1, characterized in that: The allocating item information and item quantity to the order processing shift includes: When an initial production order sent by the order service end is obtained, statistics are collected on the item information and item quantity contained in the initial production order, wherein the item information and the item quantity correspond to orders of one or more order transfer and distribution nodes contained in the initial production order; According to the predicted production volume of each of the order processing shifts, statistical results and the item supply situation corresponding to the item information, an order processing shift is allocated to the item information and item quantity included in the initial production order.
3. The order processing method according to claim 2, characterized in that: The item supply status indicates the inventory quantity of the item and / or a second supply quantity provided to the warehouse by the supplier corresponding to the initial production order and a supply time corresponding to the second supply quantity; Based on the item inventory quantity of the item information and / or the second supply quantity provided by the supplier corresponding to the initial production order to the warehouse and the supply time corresponding to the second supply quantity, the step of allocating order processing shifts for the item information and item quantity contained in the initial production order is performed.
4. The order processing method according to claim 1, characterized in that: Generating a first production order for the order processing shift includes: Further allocating order transfer and delivery nodes for the item information and item quantity allocated to the order processing shift according to a preset order transfer and delivery node priority strategy and the orders of the order transfer and delivery nodes; According to the result of further allocating the transfer and delivery nodes in the order, a first production order is generated for the order processing shift.
5. The order processing method according to claim 1, characterized in that: Determining a target delivery strategy for the order transit delivery node includes: For each order transfer and delivery node assigned with item information and item quantity, perform the following operations: According to a plurality of preset supply intervals and a plurality of distance intervals, determining a target supply interval to which the first supply quantity of the order transfer and delivery node belongs and a target distance interval to which the distance between the order transfer and delivery node and the warehouse belongs; According to the association between the preset supply interval, the distance interval and the distribution strategy, the target distribution strategy corresponding to the target supply interval and the target distance interval is determined.
6. The order processing method according to claim 1, characterized in that: Generating a first production order for the order processing shift includes: Matching the order transfer and delivery node with the item information and item quantity allocated to the order processing shift according to the relationship between the first supply quantity and the priority of the order transfer and delivery node indicated by the preset order transfer and delivery node priority strategy and the preset delivery strategy corresponding to the first supply quantity; According to the matching result, adding the matched order transfer and delivery node information to the item information and the item quantity; According to the distribution wave indicated by the distribution strategy and the distribution ratio and distribution time corresponding to the distribution wave, the distribution time is further added to the item information and the item quantity to obtain a first production order.
7. The order processing method according to claim 6, characterized in that: Before matching the item information and item quantity allocated to the order processing shift with the order transfer and delivery node, the method further includes: Filtering out first item information belonging to the direct delivery type and first item quantity corresponding to the first item information from the item information and item quantity allocated to the order processing shift; Adding a preset first clearing time for the first item information and the first item quantity; For the item information and item quantity assigned to the order processing shift, and the non-direct delivery type item information and item quantity that have not been screened out, the step of matching the item information and item quantity assigned to the order processing shift with the order transfer and distribution node is performed.
8. The order processing method according to claim 6 or 7, characterized in that: Before matching the item information and item quantity allocated to the order processing shift with the order transfer and delivery node, the method further includes: Determine whether the quantity of items allocated to the order processing shift exceeds a preset shift threshold. If so, execute the step of matching the item information and item quantity allocated to the order processing shift with the order transfer and delivery node; otherwise, directly add a preset second clearing time for the item information and the item quantity.
9. The order processing method according to claim 8, characterized in that: After determining that the quantity of items allocated to the order processing shift exceeds a preset shift threshold, and before matching the item information and item quantity allocated to the order processing shift with the order transfer and delivery node, the method further includes: Filtering out second item information belonging to a preset time-limit type and a second item quantity corresponding to the second item information from the item information assigned to the order processing shift; Adding a preset third clearing time corresponding to the second item information and the second item quantity; Match the order transfer and delivery nodes based on the remaining item information and item quantity without added clearance time.
10. An order fulfillment service, characterized in that: include: Prediction module and generation module, where The prediction module is used to predict the production volume of each order processing shift of the warehouse and the first supply volume provided by the warehouse for the order transfer and distribution node, and allocate item information and item quantity to the order processing shift according to the production volume of the order processing shift; The generating module is used to generate a first production order for each of the order processing shifts according to a preset order transfer and distribution node priority strategy, the orders of the order transfer and distribution nodes, and the item information and item quantity allocated to the order processing shift, and provide the first production order to the warehouse management server corresponding to the warehouse; According to the association relationship between the preset supply interval, distance interval and distribution strategy, the first supply quantity of the order transit distribution node and the distance between the order transit distribution node and the warehouse, a target distribution strategy is determined for the order transit distribution node; according to the distribution wave indicated by the target distribution strategy and the distribution ratio and distribution time corresponding to the distribution wave, a second production order and a third production order are generated for the order transit distribution node and the transport dispatch service end respectively, the second production order is provided to the corresponding order transit distribution node service end, and the third production order is provided to the corresponding transport dispatch service end.
11. An order processing system, characterized in that: include: Warehouse management server, order transfer and distribution node server, transportation dispatch server and order fulfillment server as claimed in claim 10, wherein: The warehouse management server is used to receive the first production order provided by the order fulfillment server, and perform outbound processing on the items stored in the warehouse and / or the items transported to the warehouse based on the first production order; The order transfer and delivery node service end is used to receive the second production order provided by the order fulfillment service end, and to perform delivery processing on the items stored in the warehouse and / or the items transported to the warehouse based on the second production order; The transport dispatching service end is used to receive the third production order provided by the order fulfillment service end, and arrange the vehicle wiring based on the third production order.
12. An electronic device, characterized in that: include: one or more processors; a storage device for storing one or more programs, When the one or more programs are executed by the one or more processors, the one or more processors implement the method according to any one of claims 1 to 9.
13. A computer readable medium having a computer program stored thereon, characterized in that: When the program is executed by a processor, the method according to any one of claims 1 to 9 is implemented.