Optimal configuration method and device for electric energy replacement equipment based on power grid bearing capacity
By optimizing the number and location of electrical energy replacement equipment, the poor energy allocation problem caused by insufficient factors in the prior art is solved, and the stable operation of the power grid and reduced energy consumption are achieved.
Patent Information
- Application Number
- CN202411577854.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-07
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2044-11-07
AI Technical Summary
There are few influencing factors considered in existing electrical energy substitution technologies, which leads to the unsatisfactory number and location of electrical energy substitution equipment and the inability to efficiently allocate energy.
By obtaining the historical load information, environmental factor information and building heat storage parameter information on the demand side, using the power distribution system to maximize the load power as the objective function, and based on the target constraints and the target comprehensive energy output model, the configuration of the power substitution equipment is optimized. Quantity and location.
It improves the accuracy of the number and location of electrical energy substitute equipment, realizes efficient energy allocation, reduces energy consumption, and ensures the stable operation of the power grid.
Smart Images

Figure CN119070309A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of electric energy substitution, and more specifically to a method and device for optimizing configuration of electric energy substitution equipment based on the carrying capacity of a power grid. Background Art
[0002] With the rapid development of new energy technologies, electric energy substitution technology is showing its important practical significance. This technology helps promote the green and low-carbon transformation of energy consumption by using electric energy to replace the direct consumption of fossil energy such as coal, oil and natural gas.
[0003] In the process of realizing the concept of the present invention, the inventors found that the electric energy substitution schemes in the related art took into account fewer influencing factors, resulting in the number of electric energy substitution devices and the location of the electric energy substitution devices in the provided electric energy substitution schemes being less than ideal, and thus failing to achieve efficient allocation of energy. Summary of the invention
[0004] In view of the above problems, the present invention provides a method and device for optimizing the configuration of electric energy replacement equipment based on the carrying capacity of the power grid.
[0005] According to a first aspect of the present invention, there is provided a method for optimizing configuration of electric energy substitution equipment based on the carrying capacity of a power grid, the method comprising: obtaining historical load information, historical environmental factor information, parameter information of the electric energy substitution equipment to be configured, and thermal storage parameter information of the buildings on the demand side on the demand side; taking maximizing the load power accommodated by the distribution system as the objective function, based on target constraints, a target load model, and a target comprehensive energy output model, processing the historical load information, the historical environmental factor information, the parameter information of the electric energy substitution equipment to be configured, and the thermal storage parameter information of the buildings on the demand side on the demand side, generating quantity information of the electric energy substitution equipment to be configured and target position information of each electric energy substitution equipment to be configured in the distribution system; and configuring each electric energy substitution equipment to be configured in the distribution system based on the target position information and the quantity information.
[0006] A second aspect of the present invention provides an optimization configuration device for electric energy replacement equipment based on the carrying capacity of a power grid, comprising: an acquisition module, a processing module and a configuration module.
[0007] The acquisition module is used to obtain historical load information, historical environmental factor information, parameter information of the electric energy replacement equipment to be configured, and thermal storage parameter information of the building on the demand side.
[0008] The processing module is used to process the historical load information on the demand side, the historical environmental factor information, the parameter information of the electric energy replacement equipment to be configured, and the thermal storage parameter information of the building on the demand side, with the maximization of the load power accommodated by the distribution system as the objective function, based on the target constraint conditions, the target load model and the target comprehensive energy output model, to generate the quantity information of the electric energy replacement equipment to be configured and the target position information of each electric energy replacement equipment to be configured in the distribution system.
[0009] A configuration module is used to configure each electric energy replacement device to be configured in the above-mentioned power distribution system based on the above-mentioned target location information and the above-mentioned quantity information.
[0010] A third aspect of the present invention provides an electronic device, comprising: one or more processors; a memory for storing one or more computer programs, wherein the one or more processors execute the one or more computer programs to implement the steps of the above method.
[0011] The fourth aspect of the present invention further provides a computer-readable storage medium having a computer program or instructions stored thereon, which implements the steps of the above method when the computer program or instructions are executed by a processor.
[0012] The fifth aspect of the present invention also provides a computer program product, including a computer program or instructions, which implement the steps of the above method when executed by a processor.
[0013] According to the method and device for optimizing configuration of electric energy substitution equipment based on grid carrying capacity provided by the present invention, based on the grid carrying capacity, taking maximizing the load power accommodated by the distribution system as the objective function, and based on the target constraint conditions, the target load model and the target comprehensive energy output model, the historical load information on the demand side, the historical environmental factor information, the parameter information of the electric energy substitution equipment to be configured and the heat storage parameter information of the building on the demand side are obtained, and the quantity information of the electric energy substitution equipment to be configured and the target position information of each electric energy substitution equipment to be configured in the distribution system can be generated. Since the grid carrying capacity, the historical load information, the historical environmental factor information, the parameter information of the electric energy substitution equipment and the heat storage parameter information of the building are taken into consideration, the accuracy of the quantity of the electric energy substitution equipment to be configured and the position in the distribution system is improved, so as to obtain a more ideal electric energy substitution scheme, realize the efficient allocation of energy, and further realize the reduction of energy consumption under the premise of ensuring the stable operation of the power grid. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] The above contents and other objects, features and advantages of the present invention will become more apparent through the following description of the embodiments of the present invention with reference to the accompanying drawings, in which:
[0015] Figure 1An application scenario diagram of a method for optimizing configuration of electric energy replacement equipment based on grid carrying capacity according to an embodiment of the present invention is shown.
[0016] Figure 2 A flow chart of a method for optimizing configuration of electric energy replacement equipment based on grid carrying capacity according to an embodiment of the present invention is shown.
[0017] Figure 3 A structural diagram of a power distribution system according to an embodiment of the present invention is shown.
[0018] Figure 4 A schematic diagram showing the demand for electricity, cooling and heating loads according to an embodiment of the present invention is shown.
[0019] Figure 5A A schematic diagram of the output of electric loads in a power distribution system in scenario 1 according to an embodiment of the present invention is shown.
[0020] Figure 5B A schematic diagram of the output of the cold load in the power distribution system in scenario 1 according to an embodiment of the present invention is shown.
[0021] Figure 5C A schematic diagram of the output of thermal load in a power distribution system in scenario 1 according to an embodiment of the present invention is shown.
[0022] Fig. 6A A schematic diagram of the output of electric loads in a power distribution system in scenario 2 according to an embodiment of the present invention is shown.
[0023] Figure 6B A schematic diagram of the output of the cold load in the power distribution system in scenario 2 according to an embodiment of the present invention is shown.
[0024] Figure 6C A schematic diagram of the output of thermal load in a power distribution system in scenario 2 according to an embodiment of the present invention is shown.
[0025] Fig. 7A A schematic diagram of the output of electric loads in a power distribution system in scenario 3 according to an embodiment of the present invention is shown.
[0026] Figure 7B A schematic diagram of the output of the cold load in the power distribution system in scenario 3 according to an embodiment of the present invention is shown.
[0027] Figure 7C A schematic diagram of the output of thermal load in a power distribution system in scenario 3 according to an embodiment of the present invention is shown.
[0028] Figure 8 A structural diagram of a 33-node power distribution system according to an embodiment of the present invention is shown.
[0029] Fig. 9A schematic diagram of voltages at nodes of a 33-node power distribution system according to an embodiment of the present invention is shown.
[0030] Fig.10 A schematic diagram of electricity, cooling, heating loads and wind and solar power according to an embodiment of the present invention is shown.
[0031] Fig.11 A structural block diagram of a device for optimizing configuration of electric energy replacement equipment based on grid carrying capacity according to an embodiment of the present invention is shown.
[0032] Fig.12 A block diagram of an electronic device suitable for implementing an optimization configuration method of electric energy replacement equipment based on grid carrying capacity according to an embodiment of the present invention is shown. DETAILED DESCRIPTION
[0033] Below, embodiments of the present invention will be described with reference to the accompanying drawings. However, it should be understood that these descriptions are exemplary only and are not intended to limit the scope of the present invention. In the following detailed description, for ease of explanation, many specific details are set forth to provide a comprehensive understanding of embodiments of the present invention. However, it is apparent that one or more embodiments may also be implemented without these specific details. In addition, in the following description, descriptions of known structures and technologies are omitted to avoid unnecessary confusion of concepts of the present invention.
[0034] In the technical solution of the present invention, the user information (including but not limited to user personal information, user image information, user device information, such as location information, etc.) and data (including but not limited to data used for analysis, stored data, displayed data, etc.) involved are all information and data authorized by the user or fully authorized by all parties, and the collection, storage, use, processing, transmission, provision, disclosure and application of the relevant data comply with relevant laws, regulations and standards, take necessary confidentiality measures, do not violate public order and good morals, and provide corresponding operation entrances for users to choose to authorize or refuse.
[0035] In the scenario of using personal information for automated decision-making, the methods, devices, and systems provided by the embodiments of the present invention provide users with corresponding operation portals for users to choose to agree or reject the automated decision-making results; if the user chooses to reject, the expert decision-making process will be entered. The expression "automated decision-making" here refers to the activity of automatically analyzing and evaluating an individual's behavioral habits, interests and hobbies, or economic, health, credit status, etc. through computer programs, and making decisions. The expression "expert decision-making" here refers to the activity of making decisions by people who specialize in a certain field, have specialized experience, knowledge and skills, and have reached a certain level of professionalism.
[0036] In the process of implementing the present invention, it was found that the related art electric energy substitution schemes considered fewer influencing factors, resulting in the number of electric energy substitution devices and the location of the electric energy substitution devices in the provided electric energy substitution schemes being less than ideal, and thus failing to achieve efficient allocation of energy.
[0037] In view of this, an embodiment of the present invention provides a method for optimizing configuration of electric energy replacement equipment based on the carrying capacity of a power grid.
[0038] Figure 1 An application scenario diagram of a method for optimizing configuration of electric energy replacement equipment based on grid carrying capacity according to an embodiment of the present invention is shown.
[0039] like Figure 1 As shown, the application scenario 100 according to this embodiment may include a first terminal device 101, a second terminal device 102, a third terminal device 103, a network 104, and a server 105. The network 104 is used to provide a medium for a communication link between the first terminal device 101, the second terminal device 102, the third terminal device 103, and the server 105. The network 104 may include various connection types, such as wired, wireless communication links, or optical fiber cables, etc.
[0040] The user can use the first terminal device 101, the second terminal device 102, and the third terminal device 103 to interact with the server 105 through the network 104 to receive or send messages, etc. Various communication client applications can be installed on the first terminal device 101, the second terminal device 102, and the third terminal device 103, such as shopping applications, web browser applications, search applications, instant messaging tools, email clients, social platform software, etc. (only for example).
[0041] The first terminal device 101, the second terminal device 102, and the third terminal device 103 may be various electronic devices having display screens and supporting web browsing, including but not limited to smart phones, tablet computers, laptop computers, desktop computers, and the like.
[0042] The server 105 may be a server that provides various services, such as a background management server (only as an example) that provides support for websites browsed by users using the first terminal device 101, the second terminal device 102, and the third terminal device 103. The background management server may analyze and process the received data such as user requests, and feed back the processing results (such as web pages, information, or data obtained or generated according to user requests) to the terminal device.
[0043] It should be noted that the optimization configuration method of the electric energy replacement device based on the grid carrying capacity provided in the embodiment of the present invention can generally be executed by the server 105. Accordingly, the optimization configuration device of the electric energy replacement device based on the grid carrying capacity provided in the embodiment of the present invention can generally be set in the server 105. The optimization configuration method of the electric energy replacement device based on the grid carrying capacity provided in the embodiment of the present invention can also be executed by a server or server cluster that is different from the server 105 and can communicate with the first terminal device 101, the second terminal device 102, the third terminal device 103 and / or the server 105. Accordingly, the optimization configuration device of the electric energy replacement device based on the grid carrying capacity provided in the embodiment of the present invention can also be set in a server or server cluster that is different from the server 105 and can communicate with the first terminal device 101, the second terminal device 102, the third terminal device 103 and / or the server 105.
[0044] It should be understood that Figure 1 The number of the first terminal device, the second terminal device, the third terminal device, the fourth terminal device, the network and the server in the embodiment is only for illustration. According to the implementation requirements, there may be any number of the first terminal device, the second terminal device, the third terminal device, the fourth terminal device, the network and the server.
[0045] The following will be based on Figure 1 The scene described by Figure 2~Figure 10 The optimized configuration method of the electric energy replacement equipment based on the carrying capacity of the power grid in the disclosed embodiment is described in detail.
[0046] Figure 2 A flow chart of a method for optimizing configuration of electric energy replacement equipment based on grid carrying capacity according to an embodiment of the present invention is shown.
[0047] like Figure 2 As shown, the method 200 for optimizing configuration of electric energy replacement equipment based on grid carrying capacity of this embodiment includes operations S210 to S230.
[0048] In operation S210, historical load information, historical environmental factor information, parameter information of the electric energy replacement equipment to be configured, and thermal storage parameter information of the building on the demand side are obtained.
[0049] In operation S220, taking maximization of the load power accommodated by the distribution system as the objective function, based on the target constraints, the target load model and the target comprehensive energy output model, the historical load information on the demand side, the historical environmental factor information, the parameter information of the electric energy substitution equipment to be configured and the thermal storage parameter information of the building on the demand side are processed to generate the quantity information of the electric energy substitution equipment to be configured and the target location information of each electric energy substitution equipment to be configured in the distribution system.
[0050] In operation S230 , each to-be-configured electric energy replacement device is configured in the power distribution system based on the target location information and the quantity information.
[0051] According to an embodiment of the present invention, electric energy substitution equipment can represent equipment that uses electric energy to replace fossil energy such as coal, oil, and natural gas in the terminal energy consumption link. Electric energy substitution equipment can improve fuel utilization, reduce pollutant emissions, and optimize terminal energy structure characteristics through large-scale centralized conversion. Electric energy substitution equipment can include various types, such as electric boilers (EB), heat pumps (HP), and electric storage air conditioners (AC).
[0052] According to an embodiment of the present invention, the demand side may characterize the user side using the electric energy replacement device. The historical load information may include the user's historical electric load, historical cooling load, historical heating load, etc. For example, the user's historical electric load may be the electric load information of the same month of the previous year. The historical environmental factor information may include information such as historical indoor and outdoor temperature, historical wind speed, and historical light intensity.
[0053] According to an embodiment of the present invention, the parameter information of the electric energy replacement device may include the output power, heating power, cooling power, etc. of the electric energy replacement device. For example, the heating power of a heat pump, the cooling power of an air conditioner, the rated conversion efficiency of a gas turbine, etc. The demand-side building heat storage parameter information may include the comprehensive heat transfer coefficient of the building in the target area, the building surface area, the building volume, etc.
[0054] According to an embodiment of the present invention, the target constraint condition may characterize the constraint during the actual operation of the distribution system. For example, the target constraint condition may include the active-reactive power flow constraint of the distribution network, the safe operation constraint of the distribution network, the transferable load constraint, the equipment output constraint, the equipment climbing constraint, the power balance constraint, and the substitution cost constraint. The target load model may characterize a model constructed by multiple load types. For example, the target load model may include a demand-side responsive electric load model, a cooling load model, and a heating load model. The target comprehensive energy output model may characterize a model consisting of multiple output modes. For example, the target comprehensive energy output model may include a wind and solar output model, a combined heat and cooling system output model, a gas boiler output model, an electric boiler output model, and a heat pump output model.
[0055] According to an embodiment of the present invention, the electric energy replacement equipment to be configured may be an electric boiler, a heat pump, and an electric cold storage air conditioner. An electric boiler is an electric heating technology that converts electrical energy into thermal energy to heat water to produce hot water with a certain temperature or steam with a certain pressure. Compared with traditional coal-fired, oil-fired, and gas-fired boilers, electric boilers have the advantages of being clean and environmentally friendly, low noise, simple structure, small footprint, unmanned operation, simple maintenance, stable operation, flexible regulation, high thermal efficiency (above 98%), and long service life. The fuel cost of electric boilers is relatively high, but they are clean energy and do not emit pollutants.
[0056] According to an embodiment of the present invention, a heat pump is a device that utilizes a low-temperature heat source, absorbs the heat therein, and transfers it to a high-level heat source after the compressor increases the temperature and pressure. Since the heat of the low-temperature heat source is recycled and utilized, the energy efficiency of the heat pump is relatively high. The heat pump system is an energy transport system rather than an energy conversion system. Usually, a heat pump system is driven by one energy source, which can transport and utilize three or four times the energy. This is equivalent to consuming 1 kWh of electricity to generate 3 to 4 kWh of heat. Its energy efficiency can reach 3 to 4 times, with excellent energy-saving and emission-reduction effects and considerable benefits.
[0057] According to an embodiment of the present invention, the electric cold storage air conditioner is a system that utilizes the low or flat electricity price period of the night power grid, the refrigeration host is fully loaded for cooling and the cold storage equipment stores the cold energy, and then releases the cold energy to meet the peak air conditioning load needs during the peak electricity price period of the power grid. The system automatically operates through intelligent control, and the cooling power consumption is mainly concentrated in the low electricity consumption period at night, realizing the "peak shifting and valley filling" of the electricity load, improving the stability of the power grid, and reducing the operating costs of the air conditioner. The electric cold storage air conditioner is suitable for commercial office buildings and urban complexes, which have the same cooling load peak and electricity peak, and the duration is long.
[0058] According to an embodiment of the present invention, the power distribution system may be a 33-node power distribution system. The power distribution system may be a periodic scheduling system, for example, a complete scheduling cycle may be 24 hours.
[0059] According to an embodiment of the present invention, the objective function is to maximize the load power accommodated by the distribution system. Based on the target constraints, the target load model and the target comprehensive energy output model, the historical load information on the demand side, the historical environmental factor information, the parameter information of the electric energy replacement equipment to be configured and the heat storage parameter information of the building on the demand side are processed to generate the quantity information of the electric boilers, heat pumps and air conditioners to be configured and the target position information of the electric boilers, heat pumps and air conditioners in the distribution system. That is, it can be generated which nodes in the 33-node distribution system the electric boilers, heat pumps and air conditioners are configured at.
[0060] According to an embodiment of the present invention, the objective function is to maximize the load power accommodated by the power distribution system. , as shown in formula (1).
[0061] (1)
[0062] in, represents the number of electric boiler users, represents the number of heat pump users, represents the number of air-conditioning users, represents the weight of the electric boiler in the target area, represents the weight of the heat pump in the target area, Represents the weight of the air conditioner in the target area.
[0063] According to an embodiment of the present invention, each electric energy replacement device to be configured can be reconfigured in the power distribution system based on the target location information and quantity information. One target location information can install a single electric energy replacement device or multiple electric energy replacement devices. For example, in a 33-node power distribution system, in the case of 0 electric boilers, 5 heat pumps and 10 air conditioners, 5 heat pumps can be installed at the 21st node, 1 air conditioner can be installed at the 9th node, and 9 air conditioners can be installed at the 10th node.
[0064] According to an embodiment of the present invention, based on the carrying capacity of the power grid, with maximizing the load power accommodated by the distribution system as the objective function, and based on the target constraints, the target load model and the target comprehensive energy output model, the historical load information on the demand side, the historical environmental factor information, the parameter information of the electric energy replacement equipment to be configured and the heat storage parameter information of the building on the demand side are obtained, and the quantity information of the electric energy replacement equipment to be configured and the target position information of each electric energy replacement equipment to be configured in the distribution system can be generated. Since the carrying capacity of the power grid, the historical load information, the historical environmental factor information, the parameter information of the electric energy replacement equipment and the heat storage parameter information of the building are taken into consideration, the accuracy of the number of electric energy replacement equipment to be configured and the position in the distribution system is improved, so as to obtain a more ideal electric energy substitution plan, realize the efficient allocation of energy, and then realize the reduction of energy consumption under the premise of ensuring the stable operation of the power grid.
[0065] According to an embodiment of the present invention, the above-mentioned optimization configuration method of electric energy replacement equipment based on the carrying capacity of the power grid also includes: taking the demand-side response electric load parameters in the distribution system after the electric energy replacement equipment to be configured is introduced into the distribution system, and based on the balance relationship between the shiftable electric load on the demand side and the electric load after the demand response, constructing a demand-side responsive electric load model; taking the cold load change parameters on the demand side after the electric energy replacement equipment to be configured is introduced into the distribution system as variables, and based on the balance relationship between the cold load change on the demand side and the cold load after the demand response, constructing a cold load model; and taking the historical temperature parameters as variables, and based on the thermal balance relationship between the historical temperature parameters and the building's heat storage parameter information, constructing a heat load model.
[0066] According to an embodiment of the present invention, the target load model may include a demand-side responsive electric load model, a cooling load model, and a heating load model.
[0067] According to an embodiment of the present invention, the shiftable electric load on the demand side can represent the load whose power supply time on the demand side can be changed according to the plan. Specifically, the total power supply of the load remains unchanged within the predetermined time period, but the power supply time period can be changed. The post-demand response electric load represents the electric load after the demand response is completed.
[0068] According to an embodiment of the present invention, historical load information may include historical electric loads. After the electric energy substitution device to be configured is introduced into the distribution system, the demand-side response electric load parameter in the distribution system can be used as a variable, and a demand-side responsive electric load model can be constructed based on the balance relationship between the shiftable electric load on the demand side and the electric load after the demand response. Specifically, after the electric energy substitution device to be configured is introduced into the distribution system, the demand-side response electric load parameter in the distribution system can be used as a variable to construct a first association relationship between the demand-side response electric load parameter and the historical electric load and the electric load parameter after the demand response; based on the constraint relationship between the electric load parameter after the demand response, the historical electric load and the electric load limit parameter of the distribution system after the electric energy substitution device to be configured is connected to the distribution system, a first constraint relationship is constructed; when the first association relationship and the first constraint relationship are determined, the demand-side responsive electric load model is constructed according to the first association relationship and the first constraint relationship as follows: Formulas (2) and (3)
[0069] (2)
[0070] (3)
[0071] in, represents the historical electricity load information on the demand side during period t, represents the demand side response load parameter for period t, It represents the maximum electrical load allowed by the power distribution system during period t. It represents the proportion of the maximum transferable load in period t, represents the electric load after demand response in period t, and N represents the number of periods.
[0072] According to an embodiment of the present invention, the demand side response electric load parameter may include a transfer-out translatable electric load and a transfer-in translatable electric load, that is, A positive number indicates that the transferable electrical load is output. A negative number indicates that the load is shifted to a transferable load. The sum of the demand-side response load parameter and the load after demand response is less than the maximum load allowed by the distribution system.
[0073] According to an embodiment of the present invention, historical load information may also include historical cooling load. After the electric energy replacement equipment to be configured is introduced into the power distribution system, the cooling load change parameter on the demand side may be used as a variable, and a cooling load model may be constructed based on the balance relationship between the cooling load change on the demand side and the cooling load after the demand response. Specifically, after the electric energy replacement equipment to be configured is introduced into the power distribution system, the cooling load change parameter on the demand side may be used as a variable, and a second association relationship may be constructed based on the cooling load change on the demand side, the balance relationship between the cooling load after the demand response, and the historical cooling load; based on the building heat storage parameter information and the predetermined temperature limit parameter on the demand side, a second constraint relationship for the cooling load change on the demand side may be constructed; when the second association relationship and the second constraint relationship are determined, a cooling load model may be generated based on the second association relationship and the second constraint relationship as follows: Formula (4).
[0074] (4)
[0075] in, represents the actual cooling load, that is, the cooling load after considering user demand. represents the basic cooling load during period t, represents the internal cooling load of the building during period t, i.e., the flexible cooling load. represents the minimum cooling load during period t, represents the maximum cooling load during period t, is the thermal resistance of the building, represents the external temperature of the building during period t, Indicates the lowest building internal temperature acceptable to users, Indicates the maximum building internal temperature acceptable to users.
[0076] According to an embodiment of the present invention, users have a somatic acceptance range for the cooling temperature inside the building, that is, the somatic acceptance range is from the lowest building internal temperature acceptable to the user to the highest building internal temperature acceptable to the user.
[0077] According to an embodiment of the present invention, the heat storage parameter information of a building can characterize the heat storage capacity of the building envelope. The stronger the heat storage capacity of the building, the less susceptible the internal temperature of the building is to the external environment, and the greater the thermal inertia of the building. According to the thermal balance theory, when the heat supply inside the building is greater than the heat dissipation of the building through the envelope, the heat is accumulated in the building and the temperature inside the building rises; when the heat supply inside the building is less than the heat dissipation of the building through the envelope, the heat is released from the building and the temperature inside the building drops.
[0078] According to an embodiment of the present invention, a heat load model can be constructed based on the heat balance relationship between the historical temperature parameters and the building heat storage parameter information, taking the historical temperature parameters as variables. Since the historical temperature parameters can include the historical indoor temperature and the historical outdoor temperature. The indoor temperature is the temperature inside the building, and the outdoor temperature is the temperature outside the building. Therefore, a heat load model can be constructed based on the historical indoor temperature, the historical outdoor temperature and the building heat storage parameter information, as shown in the following formula (5).
[0079] (5)
[0080] in, represents the indoor temperature during period t, represents the outdoor temperature during period t, K represents the comprehensive heat transfer coefficient of the building, F represents the surface area of the building, V represents the volume of the building, represents the specific heat capacity of indoor air, represents the density of indoor air, Represents the actual heat load demand.
[0081] According to an embodiment of the present invention, the above formula (5) is a first-order differential equation. Since the outdoor temperature does not change much in a short period of time, it can be assumed that the outdoor temperature is a constant in a certain period of time. Therefore, according to the general solution of the first-order linear homogeneous differential equation, a linearized heat balance equation can be obtained, as shown in the following formula (6).
[0082] (6)
[0083] in, represents the indoor temperature during the period t-1, Indicates a time interval.
[0084] According to an embodiment of the present invention, the above formula (6) is transformed to obtain the heat load model as follows: formula (7).
[0085] (7)
[0086] According to an embodiment of the present invention, since the target load model includes an electric load model that takes into account the responsiveness of the demand side, a thermal load model that takes into account the thermal balance of the user's building, and a cooling load model that takes into account the user's needs, the indicator dimension of the target model is expanded, thereby achieving comprehensive allocation of energy and further improving the stability and reliability of the distribution system.
[0087] According to an embodiment of the present invention, the method for optimizing configuration of electric energy replacement equipment based on grid carrying capacity further includes:
[0088] The output model of the combined heat and power system is constructed based on the relationship between the gas volume of the gas turbine and the electric power of the combined heat and power system, the relationship between the thermal power of the refrigerator and the cooling power of the combined heat and power system, and the relationship between the electric power and the heating power of the combined heat and power system; the gas boiler output model is constructed based on the relationship between the air intake volume of the gas boiler and the heating power of the gas boiler; the electric boiler output model is constructed based on the relationship between the power consumption of the electric boiler and the heating power of the electric boiler; the heat pump output model is constructed based on the relationship between the power consumption of the heat pump and the heating power of the heat pump; and the wind and solar output model is constructed based on the relationship between the wind speed and the output power of the fan, and the relationship between the light intensity and the output power of the photovoltaic unit.
[0089] Figure 3 A structural diagram of a power distribution system according to an embodiment of the present invention is shown.
[0090] like Figure 3 As shown, the power distribution system includes gas boilers, combined heat and power systems, electric boilers, heat pumps, and air conditioners.
[0091] According to an embodiment of the present invention, the cooling load can be supplied by a lithium bromide refrigerator or an air conditioner, and the heating load can be provided by a gas boiler (GB) or a combined cooling, heating and power system (CCHP), or by electric boilers, heat pumps and other electric energy replacement equipment. The grid carrying capacity of the electric energy replacement equipment is calculated in the power distribution energy system.
[0092] According to an embodiment of the present invention, the target comprehensive energy output model is an output model of the distribution system, and the target comprehensive energy output model may include a wind and solar output model, a combined heat and power system output model, a gas boiler output model, an electric boiler output model and a heat pump output model.
[0093] According to an embodiment of the present invention, a wind-solar output model can characterize an output model based on a wind turbine and a photovoltaic unit. A combined heat and power system output model can characterize an output model based on a distributed energy system based on the concept of energy cascade utilization. The combined heat and power system uses natural gas as the main fuel. The high-temperature flue gas obtained after the combustion of natural gas is first used for power generation through small gas turbines, gas internal combustion engines and other equipment. The waste heat is then used for heating in winter and cooling in summer by driving an absorption refrigerator. At the same time, domestic hot water can be provided, making full use of the exhaust heat. A gas boiler output model can characterize an output model constructed using a gas boiler. An electric boiler output model can characterize an output model constructed using an electric boiler. A heat pump output model can be added to an output model constructed using a heat pump.
[0094] According to an embodiment of the present invention, a combined heat and power system output model can be constructed based on the relationship between the gas flow of the gas turbine and the electric power of the combined heat and power system, the relationship between the thermal power of the refrigerator and the cooling power of the combined heat and power system, and the relationship between the electric power and the heating power of the combined heat and power system, including the following formulas (8) to (16).
[0095] According to an embodiment of the present invention, the output power of the combined heat and power system is , as shown in formula (8).
[0096] (8)
[0097] in, It represents the gas volume of the gas turbine at time t, in m 3 , It represents the rated conversion efficiency of the gas turbine. For example, the rated conversion efficiency of the gas turbine can be 0.35. β represents the lower calorific value of natural gas. For example, the lower calorific value of natural gas is 9.7kWh / m 3 .
[0098] According to an embodiment of the present invention, the refrigeration machine may include the refrigeration of the air conditioner of the combined heat and power system. The refrigeration power of the combined heat and power system is the refrigeration power of the lithium bromide refrigeration machine. The lithium bromide refrigeration machine is driven by the waste heat recovered by the waste heat boiler. The refrigeration power generated by the lithium bromide refrigeration machine depends on the amount of waste heat absorbed, as shown in the following formula (9).
[0099] (9)
[0100] in, represents the cooling power of the combined heating and power system, Indicates the cooling power of the lithium bromide refrigerator, Indicates the efficiency of a lithium bromide refrigerator. For example, the efficiency of a lithium bromide refrigerator can be 0.9. It represents the thermal power input to the lithium bromide refrigerator at time t, in kW.
[0101] According to an embodiment of the present invention, the refrigerator may be an air conditioner (AC), and the cooling power of the refrigerator is , as shown in formula (10).
[0102] (10)
[0103] in, represents the power consumption of the refrigerator at time t, is the refrigeration energy efficiency ratio of the refrigerator.
[0104] According to an embodiment of the present invention, the heating power of the combined cooling, heating and power system , as shown in formula (11).
[0105] (11)
[0106] in, Indicates the efficiency of the waste heat boiler. For example, the efficiency of the waste heat boiler can be 0.75. Represents the electrical efficiency of the gas turbine.
[0107] According to an embodiment of the present invention, a gas boiler output model may be constructed based on the relationship between the gas boiler air intake volume and the heating power of the gas boiler, as shown in the following formula (12).
[0108] (12)
[0109] in, Indicates the heating power of the gas boiler. Indicates the air intake volume of the gas boiler at time t, in m 3 , It represents the thermal efficiency of the gas boiler. For example, the thermal efficiency of the gas boiler can be 0.9.
[0110] According to an embodiment of the present invention, an electric boiler output model may be constructed based on the relationship between the power consumption of the electric boiler and the heating power of the electric boiler, as shown in the following formula (13).
[0111] (13)
[0112] in, Indicates the heating power of the electric boiler. represents the power consumption of the electric boiler at time t, It represents the heating energy efficiency ratio of the electric boiler. For example, the heating energy efficiency ratio of the electric boiler can be 0.95.
[0113] According to an embodiment of the present invention, a heat pump output model may be constructed based on the relationship between the power consumption of the heat pump and the heating power of the heat pump, as shown in the following formula (14).
[0114] (14)
[0115] in, Indicates the heating power of the heat pump, represents the power consumption of the electric boiler at time t, It represents the heating energy efficiency ratio of the heat pump. For example, the heating energy efficiency ratio of the heat pump can be 3.
[0116] According to an embodiment of the present invention, the output of a wind turbine may be affected by wind speed. The output of a photovoltaic unit may be affected by light intensity. A wind-solar output model may be constructed based on the relationship between wind speed and wind turbine output power, and the relationship between light intensity and photovoltaic unit output power, including the following formulas (15) and (16).
[0117] (15)
[0118] (16)
[0119] in, represents the fan output at time t, Indicates the rated output of the fan. represents the wind speed at time t, Indicates the cut-in wind speed, Indicates the cut-out wind speed, Indicates the rated wind speed, represents the output of the photovoltaic unit at time t, represents the light intensity at time t, M represents the illuminated area, Indicates transformation efficiency.
[0120] Figure 4 A schematic diagram showing the demand for electricity, cooling and heating loads according to an embodiment of the present invention is shown.
[0121] like Figure 4 As shown in the figure, the demand for electricity, cooling and heating loads of the distribution system on a certain day is obtained by considering demand response for electric load, user demand for cooling load and thermal balance of buildings for heating load. It can be seen that the daily change trend of electric load is basically the same, the change of cooling load depends on user demand, the change of heating load is mainly related to outdoor temperature, and the total amount of heating load will also change in different months. The early morning period is the low electricity period, and the electric load reaches its peak from noon to afternoon; the cooling load reaches its peak in the afternoon, and the basic cooling level is maintained in other periods; the outdoor temperature is the lowest at night and in the early morning, and the heating load reaches its peak. After the outdoor temperature rises at noon, the heating load reaches its trough.
[0122] According to an embodiment of the present invention, the target comprehensive energy output model comprehensively considers multiple processing methods such as wind and solar output, combined heat and power system output, gas boiler output, electric boiler output and heat pump output, so as to achieve reduction in energy consumption while ensuring the stability of the power grid, promote the sustainable development of energy, improve the safety and reliability of the power system, and explore new paths for energy transformation.
[0123] According to an embodiment of the present invention, the target constraints may include distribution network active-reactive power flow constraints, distribution network safe operation constraints, transferable load constraints, equipment output constraints, equipment ramp constraints, power balance constraints, and replacement cost constraints.
[0124] According to an embodiment of the present invention, for a radial distribution network, the active-reactive power flow constraint of the distribution network is as follows: Formula (17).
[0125] (17)
[0126] in, represents the active load at node i at time t, represents the reactive load at node i at time t, represents the active power on line (i, j) at time t, represents the reactive power on line (i, j) at time t, represents the active power on line (k, i) at time t, represents the reactive power on line (k, i) at time t, represents the resistance on line (i, j), represents the inductive reactance value on line (i, j), represents the resistance on the line (k, i), represents the inductive reactance value on line (k, i), represents the voltage amplitude at node i at time t, represents the voltage amplitude at node j at time t, represents the current amplitude on line (i, j) at time t, represents the length of line (k, i), and E represents the set of nodes in the power distribution system.
[0127] According to an embodiment of the present invention, the above distribution network active-reactive power flow constraints are nonlinear models, which are highly non-convex and difficult to solve. The following uses a second-order cone model to transform the constraints, and transforms the non-convex distribution network load carrying capacity optimization model into a mixed integer second-order cone programming problem to meet the requirements of the cone search space and improve the solution efficiency.
[0128] According to an embodiment of the present invention, and Replace the quadratic terms of branch current and node voltage in the above distribution network active-reactive power flow constraint formula (17) respectively, as shown in the following formula (18).
[0129] (18)
[0130] According to an embodiment of the present invention, further relaxation processing is performed on the above formula (18) after variable substitution to obtain a standard second-order cone form, as shown in the following formula (19).
[0131] (19)
[0132] According to an embodiment of the present invention, the safe operation constraints of the distribution network mainly consider the node voltage and branch current, and the safe operation constraints of the distribution network are as follows: Formula (20).
[0133] (20)
[0134] in, represents the voltage amplitude at node i at time t, represents the current amplitude of branch ij at time t, represents the maximum voltage amplitude at node i, represents the minimum value of the voltage amplitude at node i, Indicates the maximum value of the current amplitude in branch ij.
[0135] According to an embodiment of the present invention, considering that the electric load demand side has a transferable attribute, the load transfer-out and load transfer-in are subdivided on the basis of formula (2), and the load transfer constraint is as follows: formula (21).
[0136] (twenty one)
[0137] in, Indicates the load state variable of node i at time t, represents the load state variable of node i at time t, represents the load power transferred to node i at time t, represents the load power transferred out by node i at time t, The upper limit of the load power transferred out of node i at time t.
[0138] According to an embodiment of the present invention, the device output should satisfy the upper and lower power constraints, and the device output constraint is as follows: Formula (22).
[0139] (twenty two)
[0140] in, The value indicating the maximum power output of the combined cooling, heating and power system. The value indicating the maximum heat output of the combined cooling, heating and power system. The value indicating the maximum heat output of a gas boiler. represents the thermal output of the combined cooling, heating and power system, It represents the electrical output of the combined heating, cooling and power system. Indicates the thermal output of the gas boiler. Indicates the thermal output of the electric boiler. Indicates the capacity of a single electric boiler. represents the heat output of the heat pump, represents the capacity of the heat pump, Indicates the total output of the air conditioner. Indicates the capacity of the air conditioner. Indicates the number of electric boilers installed. Indicates the number of heat pumps installed, Indicates the number of air conditioners installed.
[0141] According to an embodiment of the present invention, the electric energy replacement device should satisfy the device ramp constraint at any time, as shown in the following formula (23).
[0142] (twenty three)
[0143] in, It indicates the ramp-down rate of the active power output of the combined heating, cooling and power system. Indicates the ramp rate of the gas boiler’s output active power. Indicates the ramp rate of the active power output of the electric boiler. Indicates the ramp rate of the heat pump output active power, It indicates the ramp rate of the active power output of the combined heating, cooling and power system. Indicates the ramp rate of the gas boiler’s output active power. Indicates the ramp rate of the active power output of the electric boiler. The ramp rate of the heat pump output active power.
[0144] According to an embodiment of the present invention, when adding electric energy replacement equipment to the power distribution system for energy scheduling optimization, it is necessary to ensure the balance of electric, cold and hot power, and the power balance constraint is as follows: Formula (24).
[0145] (twenty four)
[0146] Among them, Pg represents the power supply from the upper power grid. Indicates the thermal power of the electric boiler, represents the thermal power of the lithium bromide thermal refrigerator, represents the total output of the wind turbine. Represents the total output of the photovoltaic unit, is the thermal power of the heat pump, Indicates the total cooling power output, represents the cooling power of the combined heating and power system, Indicates the cooling power of the air conditioner.
[0147] According to an embodiment of the present invention, the total cost of each electric energy replacement equipment during the investment phase, operation phase, and demolition phase should not exceed the maximum limit of the budgeted cost.
[0148] According to an embodiment of the present invention, the annual cost method is used in the investment phase to compare the replacement costs of various electric energy replacement equipment. The calculation of the annual cost method is as follows: Formula (25).
[0149] (25)
[0150] in, represents the annual cost value of the electric energy replacement equipment, K represents the initial investment amount of the electric energy replacement equipment, n represents the service life of the electric energy replacement equipment, i represents the investment return rate, and the standard discount rate within the department can be 8%.
[0151] Table 1 Annual value of investment costs for different equipment
[0152]
[0153] As shown in Table 1, this is the annual cost table of three types of electricity replacement equipment: electric boilers, heat pumps, and air conditioners.
[0154] According to an embodiment of the present invention, the fuel cost is considered in the operation phase. The fuel cost can represent the fuel cost that must be consumed to maintain the heating demand, and the calculation of the fuel cost is as follows: Formula (26).
[0155] (26)
[0156] in, represents fuel cost, Q represents fuel consumption, Indicates the unit price of fuel, Indicates the electricity price, Indicates the electrical power consumed, Indicates the natural gas price, in yuan / m 3 , V represents the gas volume, the unit is m 3 .
[0157] According to an embodiment of the present invention, the operation and maintenance fee may represent the investment cost necessary to maintain the normal operation of the heating system when a power distribution system fails. The operation and maintenance fee is calculated as shown in the following formula (27).
[0158] (27)
[0159] in, Indicates maintenance cost, Indicates the repair rate.
[0160] According to an embodiment of the present invention, the dismantling stage mainly involves dismantling or scrapping the electric energy replacement equipment, as well as recycling related material resources. The dismantling costs mainly refer to the costs incurred when the related equipment, materials, etc. have reached their service life and cannot be used any more, as well as the costs incurred when the old equipment is handled when the equipment is replaced or dismantled. If some equipment still has residual value at the time of scrapping, the residual value can offset the related expenses as a reduction in the scrapping cost. Assuming that the residual value of the equipment is CZ (yuan) at the time of scrapping, and the cost of the scrapping stage is RC (yuan), the cost of the dismantling stage can be expressed as formula (28).
[0161] (28)
[0162] According to an embodiment of the present invention, the annual value of the total cost of the life cycle of each electric energy replacement device is calculated from the investment stage of the electric energy replacement equipment, including the cost of upgrading the electric energy replacement equipment and replacing the original equipment during the operation stage and maintenance stage. The unit capacity investment is multiplied by the equipment capacity, and then the fuel cost and maintenance cost during the operation of the equipment are added. The various costs are added together to calculate the annual value of the total cost of the life cycle of each equipment, as shown in the following formula (29).
[0163] (29)
[0164] According to an embodiment of the present invention, in order to achieve the feasibility and sustainability of the electric energy substitution solution, a substitution cost constraint is imposed on the full-cycle cost of the electric energy substitution equipment, so as to ensure that the power grid operates safely and stably at a certain cost and achieves the maximum degree of electric energy substitution that can be carried. The substitution cost constraint is as follows: Formula (30).
[0165] (30)
[0166] Among them, C represents the total cost of the entire cycle of investment phase, operation phase and maintenance phase. Indicates the maximum limit of the full-cycle cost. For example, the maximum limit of the full-cycle cost can be 2.5 million yuan. Indicates the annual cost of the electric boiler, represents the annual cost of the heat pump, Indicates the annual cost of air conditioning, Indicates the capacity of a single electric boiler. represents the capacity of the heat pump, Indicates the capacity of the air conditioner. Indicates the number of electric boilers installed. Indicates the number of heat pumps installed, Indicates the number of air conditioners installed. represents the maintenance rate of electric boilers, represents the maintenance rate of the heat pump, Indicates the maintenance rate of the air conditioner, Indicates the maintenance cost of the electric boiler. represents the maintenance cost of the heat pump, Indicates the maintenance cost of the air conditioner.
[0167] According to the embodiment of the present invention, by using the target constraint condition to constrain the operation of the power distribution system, the safety and stability of the operation of the power distribution system can be improved.
[0168] According to the embodiment of the present invention, the heat pumps and air conditioners in the target area in the building field have high weights and low initial investment and operation and maintenance costs; corresponding electricity price subsidies have been issued for electric boiler technology, and the peak and valley time-of-use electricity prices in the target area are shown in Table 3, but because their heating efficiency is not as good as that of heat pumps, the overall cost is still somewhat lower than that of coal-fired boilers. The weights of the three types of electric energy replacement equipment are shown in Table 2.
[0169] Table 2 Weights of electric energy replacement equipment in target areas
[0170]
[0171] Table 3 Time-of-use electricity price standards (unit: yuan / kWh)
[0172]
[0173] According to an embodiment of the present invention, three different scenarios can be selected for comparative analysis, and the model can be solved after the constraints are relaxed by a second-order cone. Scenario 1 is to optimize the scheduling of electric energy replacement equipment by considering only the grid carrying capacity; Scenario 2 is to optimize the scheduling by adding cost constraints on the basis of Scenario 1; Scenario 3 is to optimize the scheduling by adding the weight of the target area on the basis of Scenario 2.
[0174] According to an embodiment of the present invention, simulations are performed for the above-mentioned scenarios 1 to 3, and the maximum number of electric energy replacement devices that the distribution system can accommodate is shown in Table 4. Among them, the individual power of air conditioners is relatively small, and the temperature control load starts and stops frequently, so the distribution network can accommodate a large number of them. Electric boilers and heat pumps have large power and work for a long time, which will cause a large load pressure on the distribution network, so the distribution network can accommodate a small number of them. After adding the cost factor, the output of the heat pump decreases and the output of the electric boiler increases. This is because although the efficiency of the electric boiler is not as good as the heat pump, the installation and operation costs are lower than the heat pump. Under the cost constraint, the two cooperate in output; after adding the weight factor of the target area, the heat pump still has a greater advantage in heating than the electric boiler, and the output of the air conditioner has also increased.
[0175] Table 4 The maximum number of electric energy replacement equipment carrying capacity in scenarios 1 to 3
[0176]
[0177] Figure 5A A schematic diagram of the output of electric loads in a power distribution system in scenario 1 according to an embodiment of the present invention is shown. Figure 5B A schematic diagram of the output of the cold load in the power distribution system in scenario 1 according to an embodiment of the present invention is shown. Figure 5C A schematic diagram of the output of thermal load in a power distribution system in scenario 1 according to an embodiment of the present invention is shown.
[0178] According to an embodiment of the present invention, Figures 5A to 7C Where Pg represents the power supply from the upper grid, AC represents the output of air conditioner, HP represents the output of heat pump, WT represents the output of wind turbine, PV represents the output of photovoltaic unit, GB represents the output of gas boiler, CCHP represents the combined heating, cooling and power system, Pe_IN represents the total electric power output, where the total electric power output is equal to the electric load demand, Pl_IN represents the total cooling power output, and Ph_IN represents the total heating power output.
[0179] like Figure 5A~5C As shown in the figure, the electric load is jointly borne by the CCHP unit output and the fan output from dusk to dawn, and the increased output during the "peak period" is compensated by the photovoltaic output; the cooling load is jointly provided by the air conditioner and the CCHP unit; 11:00 and 16:00 are the two peak periods of cooling load, during which the CCHP unit output is almost unchanged, and the air conditioner increases the output to adapt to the load peak and valley changes. This is because the air conditioner is a flexible resource and is convenient and controllable. The heat load "valley period" is mainly provided by the heat pump. When the load increases, the CCHP unit and the heat pump jointly output. The heat pump output decreases from dusk to night, and the CCHP unit bears the main output. This is because the ambient temperature at night is usually lower than that during the day, which affects the heating efficiency of the heat pump. The heat pump works by absorbing heat from the environment. When the ambient temperature decreases, the heat pump needs more energy to extract the same amount of heat from the low temperature environment, which may lead to a reduction in output at night. The gas boiler output is low during the entire scheduling cycle. Since the thermal efficiency of the electric boiler is not as good as that of the heat pump, there is no electric boiler output.
[0180] Fig. 6A A schematic diagram of the output of electric loads in a power distribution system in scenario 2 according to an embodiment of the present invention is shown. Figure 6B A schematic diagram of the output of the cold load in the power distribution system in scenario 2 according to an embodiment of the present invention is shown. Figure 6C A schematic diagram of the output of thermal load in a power distribution system in scenario 2 according to an embodiment of the present invention is shown.
[0181] like Figure 6A~6CAs shown in the figure, the output of electricity and cooling loads has no significant change compared with scenario 1; the output of the heat pump has decreased compared with scenario 1, and the output also reaches the valley when the heat load is low. This is because during the heat load valley period, the heat pump may not be able to provide enough instant hot water and needs to rely on the hot water storage tank to meet the demand. Insufficient water storage capacity or poor insulation effect of the hot water storage tank will cause the output of the heat pump to decrease during these periods. Although the efficiency of the electric boiler is not as good as that of the heat pump, its output has increased due to its economic advantages, and it has a uniform output in each period. The remaining heat load is still provided by the CCHP unit and the gas boiler.
[0182] Fig. 7A A schematic diagram of the output of electric loads in a power distribution system in scenario 3 according to an embodiment of the present invention is shown. Figure 7B A schematic diagram of the output of the cold load in the power distribution system in scenario 3 according to an embodiment of the present invention is shown. Figure 7C A schematic diagram of the output of thermal load in a power distribution system in scenario 3 according to an embodiment of the present invention is shown.
[0183] like Figures 7A to 7C As shown in the figure, compared with scenario 2, for different weights of the target area, the output of CCHP units during the peak period of electric load has decreased; the output of air conditioners in the cooling load has increased from 1200kW to 1800kW per period, and the output of CCHP units has decreased; the output of heat pumps in the heating load has increased slightly, and CCHP units bear the main output from night to early morning. Due to the low weight of heat pumps and the comprehensive efficiency factors, the economic advantages of electric boilers have not been revealed, so electric boilers do not participate in the output. Compared with scenario 1, the output of air conditioners has increased and the output of heat pumps has decreased, which is consistent with the fact that the weight of air conditioners is higher than that of heat pumps.
[0184] Figure 8 A structural diagram of a 33-node power distribution system according to an embodiment of the present invention is shown.
[0185] like Figure 8 As shown, the power distribution system may include 33 nodes, and the electric energy replacement equipment may be installed on the 33 nodes.
[0186] Fig. 9 A schematic diagram of voltages at nodes of a 33-node power distribution system according to an embodiment of the present invention is shown.
[0187] like Fig. 9As shown in the figure, the voltage of nodes 1-18 slowly decreases from the peak value, and at nodes 19-22, 23-25, and 26-33, it slowly decreases after reaching the interval peak value, which is in line with the power flow distribution of the IEEE33 node system. The voltage fluctuation in each period is not large, and the voltage of each node is around 1, which meets the national standard that the voltage fluctuation range is within ±10% of the rated voltage, and there is no voltage over-limit or too low phenomenon, indicating that the distribution network is still safe and stable after adding the power replacement equipment. While increasing the number of power replacement equipment, it can prevent the voltage from fluctuating greatly and does not exceed the load carrying capacity of the distribution network, which verifies the feasibility of the built model.
[0188] Fig.10 A schematic diagram of electricity, cooling, heating loads and wind and solar output according to an embodiment of the present invention is shown.
[0189] like Fig.10 As shown in the figure, the electric load is the electric load after demand response, and the cooling load and electric load are Figure 4 The data are consistent, and wind and solar output data are also considered, among which the load side parameters are shown in Table 5.
[0190] Table 5 Load side parameter settings
[0191]
[0192] Based on the above-mentioned method for optimizing configuration of electric energy replacement equipment based on grid carrying capacity, the present invention also provides an apparatus for optimizing configuration of electric energy replacement equipment based on grid carrying capacity. Fig.11 The device is described in detail.
[0193] Fig.11 A structural block diagram of a device for optimizing configuration of electric energy replacement equipment based on grid carrying capacity according to an embodiment of the present invention is shown.
[0194] like Fig.11 As shown, the device 1100 for optimizing configuration of electric energy replacement equipment based on grid carrying capacity of this embodiment includes an acquisition module 1110 , a processing module 1120 and a configuration module 1130 .
[0195] The acquisition module 1110 is used to acquire historical load information, historical environmental factor information, parameter information of the electric energy replacement equipment to be configured, and thermal storage parameter information of the building on the demand side. In one embodiment, the acquisition module 1110 can be used to perform the operation S210 described above, which will not be repeated here.
[0196] The processing module 1120 is used to process the historical load information, historical environmental factor information, parameter information of the electric energy replacement equipment to be configured, and thermal storage parameter information of the building on the demand side based on the target constraint conditions, the target load model, and the target comprehensive energy output model, with the distribution system accommodating load power maximization as the objective function, to generate the quantity information of the electric energy replacement equipment to be configured and the target location information of each electric energy replacement equipment to be configured in the distribution system. In one embodiment, the processing module 1120 can be used to perform the operation S220 described above, which will not be repeated here.
[0197] The configuration module 1130 is used to configure each electric energy replacement device to be configured in the power distribution system based on the target location information and the quantity information. In one embodiment, the configuration module 1130 can be used to perform the operation S230 described above, which will not be described in detail here.
[0198] According to an embodiment of the present invention, the target load model includes: a demand-side responsive electric load model, a cooling load model, and a heating load model; the above-mentioned optimization configuration device for electric energy replacement equipment based on the carrying capacity of the power grid also includes: a first building block, a second building block, and a third building block.
[0199] The first construction module is used to construct a demand-side responsive electric load model based on the balance relationship between the demand-side shiftable electric load and the electric load after demand response, taking the demand-side responsive electric load parameters in the distribution system after the electric energy replacement equipment to be configured is introduced into the distribution system as variables.
[0200] The second construction module is used to construct a cooling load model based on the balance relationship between the cooling load change on the demand side and the cooling load after the demand response, taking the cooling load change parameter on the demand side after the electric energy replacement equipment to be configured is introduced into the distribution system as a variable.
[0201] The third construction module is used to construct a heat load model based on the heat balance relationship between the historical temperature parameters and the building heat storage parameter information, using the historical temperature parameters as variables.
[0202] According to an embodiment of the present invention, the historical load information includes historical electric load; the first building module includes: a first building submodule, a second building submodule and a third building submodule.
[0203] The first construction submodule is used to construct a first correlation relationship between the demand-side response electric load parameter and the historical electric load and the electric load parameter after demand response, using the demand-side response electric load parameter in the distribution system after the electric energy replacement equipment to be configured is introduced into the distribution system as a variable.
[0204] The second construction submodule is used to construct a first constraint relationship based on the constraint relationship between the post-demand response electric load parameters, the historical electric load and the electric load limit parameters of the distribution system after the electric energy replacement equipment to be configured is connected to the distribution system.
[0205] The third construction submodule is used to construct a demand-side responsive electric load model according to the first association relationship and the first constraint relationship.
[0206] According to an embodiment of the present invention, the historical load information includes historical cooling load; the second building module includes: a fourth building submodule, a fifth building submodule and a sixth building submodule.
[0207] The fourth construction submodule is used to construct a second association relationship based on the change in the cooling load on the demand side, the balance relationship between the cooling load after the demand response, and the historical cooling load, after introducing the electric energy replacement equipment to be configured in the power distribution system as a variable;
[0208] a fifth construction submodule, configured to construct a second constraint relationship for a change in cooling load on the demand side based on the building thermal storage parameter information and a predetermined temperature limit parameter on the demand side; and
[0209] The sixth construction submodule is used to generate a cooling load model according to the second association relationship and the second constraint relationship.
[0210] According to an embodiment of the present invention, the historical environmental factor information includes historical indoor temperature and historical outdoor temperature.
[0211] The seventh construction submodule is used to construct a heat load model based on historical indoor temperature, historical outdoor temperature and building heat storage parameter information.
[0212] According to an embodiment of the present invention, the target comprehensive energy output model includes: a wind and solar output model, a combined heat and power system output model, a gas boiler output model, an electric boiler output model and a heat pump output model; the above-mentioned optimization configuration device of electric energy replacement equipment based on the carrying capacity of the power grid also includes: a fourth building block, a fifth building block, a sixth building block, a seventh building block and an eighth building block.
[0213] The fourth construction module is used to construct an output model of the combined heat and power system based on the relationship between the gas volume of the gas turbine and the electric power of the combined heat and power system, the relationship between the thermal power of the refrigerator and the cooling power of the combined heat and power system, and the relationship between the electric power and the heating power of the combined heat and power system.
[0214] The fifth building module is used to build a gas boiler output model based on the relationship between the air intake volume of the gas boiler and the heating power of the gas boiler.
[0215] The sixth construction module is used to construct an electric boiler output model based on the relationship between the power consumption of the electric boiler and the heating power of the electric boiler.
[0216] The seventh building block is used to build a heat pump output model based on the relationship between the power consumption of the heat pump and the heating power of the heat pump.
[0217] The eighth construction module is used to construct a wind-solar output model based on the relationship between wind speed and wind turbine output power, and the relationship between light intensity and photovoltaic unit output power.
[0218] According to an embodiment of the present invention, any multiple modules among the acquisition module 1110, the processing module 1120 and the configuration module 1130 can be combined into one module for implementation, or any one of the modules can be split into multiple modules. Alternatively, at least part of the functions of one or more of these modules can be combined with at least part of the functions of other modules and implemented in one module. According to an embodiment of the present invention, at least one of the acquisition module 1110, the processing module 1120 and the configuration module 1130 can be at least partially implemented as a hardware circuit, such as a field programmable gate array (FPGA), a programmable logic array (PLA), a system on a chip, a system on a substrate, a system on a package, an application-specific integrated circuit (ASIC), or can be implemented by hardware or firmware such as any other reasonable way of integrating or packaging the circuit, or implemented in any one of the three implementation methods of software, hardware and firmware or in any appropriate combination of any of them. Alternatively, at least one of the acquisition module 1110, the processing module 1120 and the configuration module 1130 can be at least partially implemented as a computer program module, and when the computer program module is run, the corresponding function can be executed.
[0219] Fig.12 A block diagram of an electronic device suitable for implementing an optimization configuration method of electric energy replacement equipment based on grid carrying capacity according to an embodiment of the present invention is shown.
[0220] like Fig.12As shown, the electronic device 1200 according to an embodiment of the present invention includes a processor 1201, which can perform various appropriate actions and processes according to the program stored in the ROM 1202 or the program loaded from the storage part 1208 to the RAM (Random Access Memory). The processor 1201 may include, for example, a general-purpose microprocessor (such as a CPU), an instruction set processor and / or a related chipset and / or a special-purpose microprocessor (for example, an application-specific integrated circuit (ASIC)), etc. The processor 1201 may also include an onboard memory for caching purposes. The processor 1201 may include a single processing unit or multiple processing units for performing different actions of the method flow according to an embodiment of the present invention.
[0221] In RAM 1203, various programs and data required for the operation of electronic device 1200 are stored. Processor 1201, ROM 1202 and RAM 1203 are connected to each other via bus 1204. Processor 1201 performs various operations of the method flow according to the embodiment of the present invention by executing the program in ROM 1202 and / or RAM 1203. It should be noted that the program can also be stored in one or more memories other than ROM 1202 and RAM 1203. Processor 1201 can also perform various operations of the method flow according to the embodiment of the present invention by executing the program stored in the one or more memories.
[0222] According to an embodiment of the present invention, the electronic device 1200 may further include an I / O interface 1205, which is also connected to the bus 1204. The electronic device 1200 may further include one or more of the following components connected to the I / O interface 1205: an input portion 1206 including a keyboard, a mouse, etc.; an output portion 1207 including a cathode ray tube (CRT), a liquid crystal display (LCD), etc., and a speaker, etc.; a storage portion 1208 including a hard disk, etc.; and a communication portion 1209 including a network interface card such as a LAN card, a modem, etc. The communication portion 1209 performs communication processing via a network such as the Internet. A drive 1210 is also connected to the I / O interface 1205 as needed. A removable medium 1211, such as a magnetic disk, an optical disk, a magneto-optical disk, a semiconductor memory, etc., is installed on the drive 1210 as needed, so that a computer program read therefrom is installed into the storage portion 1208 as needed.
[0223] The present invention also provides a computer-readable storage medium, which may be included in the device / apparatus / system described in the above embodiment; or may exist independently without being assembled into the device / apparatus / system. The above computer-readable storage medium carries one or more programs, and when the above one or more programs are executed, the method according to the embodiment of the present invention is implemented.
[0224] The embodiment of the present invention also includes a computer program product, which includes a computer program, and the computer program contains program code for executing the method shown in the flowchart. When the computer program product is run in a computer system, the program code is used to enable the computer system to implement the optimization configuration method of electric energy replacement equipment based on power grid carrying capacity provided by the embodiment of the present invention.
[0225] The embodiments of the present invention are described above. However, these embodiments are only for the purpose of illustration, and are not intended to limit the scope of the present invention. Although each embodiment is described above, it does not mean that the measures in each embodiment cannot be used in combination advantageously. Without departing from the scope of the present invention, those skilled in the art may make various substitutions and modifications, which should all fall within the scope of the present invention.
Claims
1. A method for optimizing the configuration of electric energy replacement equipment based on the carrying capacity of a power grid, characterized in that: The method comprises: Acquire historical load information, historical environmental factor information, parameter information of the electric energy replacement equipment to be configured, and thermal storage parameter information of the building on the demand side; Taking maximizing the load power accommodated by the distribution system as the objective function, based on the target constraint conditions, the target load model and the target comprehensive energy output model, the historical load information on the demand side, the historical environmental factor information, the parameter information of the electric energy replacement equipment to be configured and the thermal storage parameter information of the building on the demand side are processed to generate the quantity information of the electric energy replacement equipment to be configured and the target location information of each electric energy replacement equipment to be configured in the distribution system; and Based on the target location information and the quantity information, each electric energy replacement device to be configured is configured in the power distribution system.
2. The method according to claim 1, characterized in that The target load model includes: a demand-side responsive electric load model, a cooling load model, and a heating load model; the method further includes: Taking the demand-side response electric load parameter in the power distribution system after the electric energy replacement device to be configured is introduced into the power distribution system as a variable, and based on the balance relationship between the shiftable electric load on the demand side and the electric load after demand response, constructing the demand-side responsive electric load model; Taking the cooling load change parameter of the demand side after the electric energy replacement device to be configured is introduced into the power distribution system as a variable, and constructing the cooling load model based on the balance relationship between the cooling load change on the demand side and the cooling load after demand response; and The heat load model is constructed by taking the historical temperature parameters as variables and based on the heat balance relationship between the historical temperature parameters and the building heat storage parameter information.
3. The method according to claim 2, characterized in that The historical load information includes historical electric load; The method of constructing the demand-side responsive electric load model based on the balance relationship between the demand-side shiftable electric load and the electric load after demand response, taking the demand-side responsive electric load parameter in the distribution system after the electric energy replacement device to be configured is introduced into the distribution system as a variable, comprises: Taking the demand-side response electric load parameter in the power distribution system after the electric energy replacement device to be configured is introduced into the power distribution system as a variable, constructing a first association relationship between the demand-side response electric load parameter and the historical electric load and the electric load parameter after demand response; Constructing a first constraint relationship based on the constraint relationship between the post-demand response electric load parameter, the historical electric load and the electric load limit parameter of the distribution system after the electric energy replacement device to be configured is connected to the distribution system; and The demand-side responsive electrical load model is constructed according to the first association relationship and the first constraint relationship.
4. The method according to claim 2, characterized in that: The historical load information includes historical cooling load; Taking the cooling load change parameter of the demand side after the electric energy replacement device to be configured is introduced into the power distribution system as a variable, and based on the balance relationship between the cooling load change on the demand side and the cooling load after the demand response, the cooling load model is constructed, including: Taking the cooling load change parameter of the demand side after the electric energy replacement device to be configured is introduced into the power distribution system as a variable, a second association relationship is constructed according to the cooling load change on the demand side, the balance relationship between the cooling load after the demand response and the historical cooling load; Based on the building thermal storage parameter information and the predetermined temperature limit parameter on the demand side, constructing a second constraint relationship for the change of the cooling load on the demand side; and The cooling load model is generated according to the second association relationship and the second constraint relationship.
5. The method according to claim 2, characterized in that: The historical environmental factor information includes historical indoor temperature and historical outdoor temperature; The heat load model is constructed based on the historical indoor temperature, the historical outdoor temperature and the building heat storage parameter information.
6. The method according to claim 1, characterized in that The target comprehensive energy output model includes: a wind and solar output model, a combined heat and power system output model, a gas boiler output model, an electric boiler output model and a heat pump output model; the method also includes: Constructing the output model of the combined heat, power and cooling system based on the relationship between the gas volume of the gas turbine and the electric power of the combined heat, power and cooling system, the relationship between the thermal power of the refrigerator and the cooling power of the combined heat, power and cooling system, and the relationship between the electric power and the heating power of the combined heat, power and cooling system; Constructing the gas boiler output model based on the relationship between the gas intake volume and the heating power of the gas boiler; Constructing the electric boiler output model based on the relationship between the electric boiler's power consumption and the electric boiler's heating power; Constructing the heat pump output model based on the relationship between the power consumption of the heat pump and the heating power of the heat pump; and The wind-solar output model is constructed based on the relationship between wind speed and wind turbine output power, and the relationship between light intensity and photovoltaic unit output power.
7. The method according to claim 1, characterized in that The target constraints include: active-reactive power flow constraints of the distribution network, safe operation constraints of the distribution network, transferable load constraints, equipment output constraints, equipment ramp constraints, power balance constraints, and replacement cost constraints.
8. An optimal configuration device for electric energy replacement equipment based on the carrying capacity of the power grid, characterized in that: The device comprises: An acquisition module, used to acquire historical load information, historical environmental factor information, parameter information of electric energy replacement equipment to be configured, and thermal storage parameter information of buildings on the demand side; a processing module, configured to process the historical load information on the demand side, the historical environmental factor information, the parameter information of the electric energy replacement equipment to be configured, and the thermal storage parameter information of the building on the demand side, taking the maximization of the load power accommodated by the distribution system as the objective function, based on the target constraint conditions, the target load model, and the target comprehensive energy output model, to generate the quantity information of the electric energy replacement equipment to be configured and the target location information of each electric energy replacement equipment to be configured in the distribution system; and A configuration module is used to configure each electric energy replacement device to be configured in the power distribution system based on the target location information and the quantity information.
9. An electronic device, comprising: one or more processors; a memory for storing one or more computer programs, It is characterized in that the one or more processors execute the one or more computer programs to implement the steps of the method according to any one of claims 1 to 8.
10. A computer-readable storage medium having a computer program or instruction stored thereon, characterized in that: When the computer program or instruction is executed by a processor, the steps of the method according to any one of claims 1 to 8 are implemented.
Citation Information
Patent Citations
A day-ahead collaborative optimization operation method of a regional comprehensive energy system
CN109543889A
Building type comprehensive energy system operation optimization method and device and terminal equipment
CN112598195A
New energy addressing and sizing optimization method considering electric energy substitution influence
CN114118529A
Energy optimization configuration method and device for comprehensive energy system of agricultural park
CN116128154A