Novel crane beam and brake truss mechanism for pipe pile workshop
By introducing adjustable support beam assembly and continuous triangular brake truss accessories into the crane beam, the bending and assembly error problems of crane beam during operation is solved, and the structural stability and safety are improved. It is suitable for a wide range of complex applications. Scene.
Patent Information
- Application Number
- CN202411217305.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-02
- Publication Date
- 2024-12-06
AI Technical Summary
During operation, the existing crane beams are heavy in weight and the pressure on the sides of the main beam is prone to bending. The overall lifting structure is positioned and installed, and cannot be adjusted according to actual conditions, resulting in greater safety risks of use.
A new type of crane beam and brake truss mechanism is designed, including adjustable support beam assembly and continuous triangular brake truss accessories. Through fine adjustment of support beam assembly and the use of gap filling plates, it can adapt to different application scenarios and eliminate Assembly errors improve structural stability and safety.
By fine-tuning the support beam assembly and filling assembly errors, the stability and safety of the crane beam are improved, the deformation of the main beam is avoided, and the service life and application effect of the structure are enhanced.
Smart Images

Figure CN119079792A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of crane beams, and in particular relates to a novel crane beam and a brake truss mechanism used in a pipe pile workshop. Background Art
[0002] As the name implies, crane beams are beam structures that support the operation of bridge cranes. They have clear definitions, structural characteristics, functions and design requirements. Crane beams come in a variety of forms, including steel beams, combined I-beams, box beams and crane trusses. The choice of these forms depends on specific engineering requirements and design conditions.
[0003] Chinese patent (CN104071701A) discloses a multifunctional crane beam, including: side support columns, extension platforms, foundation platforms, connecting columns, main suspension beams and hook devices, the main suspension beams include a beam body, columns, derivative frames, reinforcement ribs, suspension beam ends, guide rails and pulley blocks, the foundation platforms are arranged at the bottoms of the side support columns and the connecting columns, the extension platforms are arranged at the sides of the side support columns, the side support columns are located at the opposite sides of the connecting columns, and the extension platforms face the connecting columns. In the above manner, the multifunctional crane beam has a more reasonable structure, a higher load-bearing capacity, and is easy to use, and can carry out large-scale loading activities at the same time. Although today's crane beams can be installed and operated for cranes, the cranes are generally heavy during operation, and the side of the main beam bears great pressure, making it very easy to bend. At the same time, the overall lifting structure is a fixed installation type, and its position cannot be improved according to actual conditions. In addition, due to the production errors of various components, some major weighing components will have some deviations and gaps when they are matched. The crane beam has a great safety hazard in use and the actual application effect is not good. In order to solve the above problems, a new crane beam and brake truss mechanism for a pipe pile workshop is urgently needed. Summary of the invention
[0004] The purpose of the present invention is to solve the problem that although the current crane beam can be installed and operated for the crane, the crane is generally heavy during operation, the pressure on the side of the main beam is large, and it is very easy to bend, etc. At the same time, the overall lifting structure is a positioning installation type, and its position cannot be improved according to the actual situation. At the same time, due to the production errors of various components, some major weighing components will have some deviations and gaps when they are matched, and the crane beam has a large safety hazard in use and the actual application effect is not good. A new type of crane beam and brake truss mechanism for a pipe pile workshop is proposed.
[0005] In order to achieve the above-mentioned purpose, the present invention adopts the following technical scheme: a new type of crane beam and brake truss mechanism for a pipe pile workshop, comprising a base, a plurality of main beam assemblies are longitudinally arranged on the top surface of the base, a structural connecting beam is fixedly installed on the top surface of the plurality of main beam assemblies, a crane signal receiving module is arranged at the bottom of the structural connecting beam, a support beam assembly is arranged on one side of the main beam assembly, a crane beam accessory is arranged on the top surface of the support beam assembly, and brake truss accessories are arranged on the outer walls on both sides of the main beam assembly, the main beam assembly is used for supporting the overall structure and the crane, the crane beam accessories are used for stable support and travel of the crane, the brake truss accessories are used for protecting the structural stability of the crane beam accessories during the operation and braking of the crane, and the support beam assembly is used for stable installation and support of the crane beam accessories.
[0006] As a further description of the above technical solution:
[0007] The main beam assembly comprises a longitudinal main beam, a side travel groove is arranged on one side outer wall of the longitudinal main beam, beam side grooves are arranged on the other two side outer walls of the longitudinal main beam, and a plurality of positioning holes are arranged inside the beam side grooves.
[0008] As a further description of the above technical solution:
[0009] The crane beam accessories include a crane crossbeam, a crane travel track is fixedly installed on the top surface of the crane crossbeam, mounting bottom grooves are arranged on both sides of the bottom surface of the crane crossbeam, and a rolling bottom shaft is rotatably installed inside the mounting bottom groove via a rotating shaft.
[0010] As a further description of the above technical solution:
[0011] The support beam assembly includes a supporting horn, one end of which is fixedly mounted with two reinforcing ribs, the reinforcing ribs are slidably connected to the side travel groove, a gasket is fixedly mounted on the top surface of the supporting horn, a connecting plate is fixedly mounted on the top surface of the gasket, and a bottom bolt is rotatably mounted on the connecting plate.
[0012] As a further description of the above technical solution:
[0013] One end of the bottom bolt is threadedly connected to a threaded hole arranged on the bottom surface of the crane beam, the rolling bottom shaft is rollingly connected to the gasket, and a gap filling plate is movably installed at the center position of the top surface of the gasket.
[0014] As a further description of the above technical solution:
[0015] The outer walls on both sides of the gap filling plate are in close contact with the side walls of the two crane beams. The gap filling plate and the crane beams are fixedly connected by positioning bolts, and the external threads of the positioning bolts are equipped with positioning nuts.
[0016] As a further description of the above technical solution:
[0017] One side of the positioning nut is in close contact with and squeezed against a side wall of one end of the crane beam, and the reinforcing rib plate is fixedly installed in the side groove of the beam through a connecting bolt, and one end of the connecting bolt is threadedly installed in the interior of the positioning hole.
[0018] Furthermore, by providing an adjustable support beam assembly on the main beam assembly, this design can make the structure fine-tuned according to the working conditions, so that the structure can be suitable for more extensive and complex application scenarios. At the same time, when assembling the structure, it can fill in and eliminate assembly errors caused by the design of the main load-bearing components, thereby improving the stability of the overall structural parts, greatly improving the safety of the overall structural parts, eliminating safety hazards, and ensuring the service life of the structure under continuous high loads.
[0019] As a further description of the above technical solution:
[0020] The brake truss accessories include a connecting piece and a connecting plate. The connecting piece is fixedly installed on the outer wall of one side of the longitudinal main beam. The connecting piece is threadedly connected to the threaded hole set on the top surface of the crane cross beam through a fixing bolt, and the connecting plate is transversely fixedly installed inside the side groove of the beam.
[0021] As a further description of the above technical solution:
[0022] A transverse connecting plate is transversely fixedly installed at one end of the connecting plate, an inclined side plate is obliquely fixedly installed on an outer wall of one side of the connecting plate, and a connecting groove plate is fixedly installed on the inner side of the transverse connecting plate.
[0023] As a further description of the above technical solution:
[0024] A brake truss is fixedly mounted on one end of the connecting slot plate. The brake truss is triangular in shape. The brake truss and the inclined side plate are fixedly mounted on the top surface of the crane beam by assembling bolts.
[0025] In summary, due to the adoption of the above technical solution, the beneficial effects of the present invention are:
[0026] 1. In the present invention, an adjustable support beam assembly is provided on the main beam assembly. In practical applications, the position of the support beam assembly can be adjusted according to the needs of the crane operation, thereby adjusting the operating state and position of the crane. It is only necessary to move the support horn to a suitable position, and use various connecting bolts to fix the support horn and the reinforcing rib plate to one side of the main beam assembly for subsequent bearing of the crane and crane beam accessories. Since the reinforcing rib plate is completely horizontally placed in the beam side groove of the main beam assembly, when a large pressure is placed on the support horn, the reinforcing rib plate can effectively withstand the bending moment and shear force from the support horn, thereby avoiding longitudinal deformation of the longitudinal main beam. In addition, a gap filling plate is provided in the support beam assembly, and the gap filling plate can It can effectively fill the assembly gap caused by errors in the design and manufacturing of crane beam accessories, and can eliminate and fill errors in the main load-bearing components of the overall structure. The structure can also serve as a medium for connecting each group of crane beam accessories, which can greatly improve the stability and integrity of each crane beam accessory after connection and assembly. Through this design, the structure can be fine-tuned according to the working conditions, so that the structure can be suitable for more extensive and complex application scenarios. At the same time, when assembling, the structure can fill and eliminate assembly errors caused by the design of the main load-bearing components, thereby improving the stability of the overall structural parts, greatly improving the safety of the overall structural parts, eliminating safety hazards, and ensuring the service life of the structure under continuous high loads.
[0027] 2. In the present invention, by matching with the easy-to-adjust crane beam accessories, when assembling the crane beam accessories, the two ends of the crane beam accessories are respectively carried on the connecting plates, at which time the rolling bottom shaft at the bottom of the crane beam accessories can contact the gasket, and when splicing and debugging the crane beam accessories, it is necessary to adjust the position of the crane beam accessories, because the rolling bottom shaft is arranged at the bottom of the crane beam accessories, the rolling bottom shaft can be easily micro-distanced on the gasket, so as to realize the overall position debugging of the crane beam accessories until the crane beam accessories can reach the most suitable assembly position, through this design, the crane beam accessories with wheels on both sides are adopted, so that when the crane beam accessories are assembled and debugged, the crane beam accessories can be effectively moved to reach the optimal assembly position, which effectively solves the problem that the crane beam accessories cannot be effectively adjusted in position after being carried on the support beam assembly due to their heavy weight, and greatly improves the overall application effect of the structure.
[0028] 3. In the present invention, a continuous triangular brake truss accessory is installed, which is clamped between the side grooves of each longitudinal main beam during installation. Since its main body is composed of multiple continuous triangular structures, each triangular structure has extremely strong stability, which improves the stability of the overall brake truss accessory. At the same time, the brake truss accessory can effectively avoid deformation of the main beam assembly caused by a large horizontal force on the crane beam accessories when the crane is in operation, and can ensure the stability of the overall structure when the crane is running and braking, thereby improving the actual application effect of the overall structure. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 It is a three-dimensional structural schematic diagram of a new type of crane beam and brake truss mechanism used in a pipe pile workshop.
[0030] Figure 2 This is a three-dimensional structural schematic diagram from another angle of a new type of crane beam and brake truss mechanism used in a pipe pile workshop.
[0031] Figure 3 It is a schematic diagram of the exploded three-dimensional structure of a new type of crane beam and brake truss mechanism used in a pipe pile workshop.
[0032] Figure 4 It is a schematic diagram of the exploded three-dimensional structure of the main beam assembly and the supporting beam assembly in a new type of crane beam and brake truss mechanism used in a pipe pile workshop.
[0033] Figure 5 It is a three-dimensional structural schematic diagram from another angle of the main beam assembly, support beam assembly and crane beam accessories in a new type of crane beam and brake truss mechanism used in a pipe pile workshop.
[0034] Figure 6 The diagram is an exploded three-dimensional structure diagram of a main beam assembly, a support beam assembly and crane beam accessories in a new type of crane beam and brake truss mechanism used in a pipe pile workshop.
[0035] Figure 7 It is a schematic diagram of the exploded three-dimensional structure of a new type of crane beam and support beam assembly in a brake truss mechanism used in a pipe pile workshop.
[0036] Figure 8 The exploded three-dimensional structural diagram of a new type of crane beam and a crane beam accessory in a brake truss mechanism used in a pipe pile workshop.
[0037] Fig. 9 A new type of crane beam and brake truss mechanism for pipe pile workshop Figure 1 Schematic diagram of the enlarged structure at point A in the middle.
[0038] Legend:
[0039] 1. Base; 2. Main beam assembly; 21. Side travel groove; 22. Longitudinal main beam; 23. Positioning hole; 24. Beam side groove; 3. Structural connecting beam; 4. Brake truss accessories; 41. Connectors; 42. Connecting plates; 43. Inclined side plates; 44. Horizontal connecting plates; 45. Connecting groove plates; 46. Brake truss; 5. Support beam assembly; 51. Gap filling plate; 52. Positioning bolts; 53. Positioning nuts; 54. Connecting bolts; 55. Bottom bolts; 56. Connecting plates; 57. Gaskets; 58. Support horns; 59. Reinforcement plates; 6. Crane beam accessories; 61. Crane travel rails; 62. Crane beams; 63. Installing bottom grooves; 64. Rolling bottom shafts. DETAILED DESCRIPTION
[0040] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0041] See also Figure 1-Figure 9 The present invention provides a technical solution: a new type of crane beam and brake truss mechanism for a pipe pile workshop, comprising a base 1, a plurality of main beam assemblies 2 are longitudinally arranged on the top surface of the base 1, a structural connecting crossbeam 3 is fixedly installed on the top surface of the plurality of main beam assemblies 2, a crane signal receiving module is arranged at the bottom of the structural connecting crossbeam 3, a support beam assembly 5 is arranged on one side of the main beam assembly 2, a crane beam accessory 6 is arranged on the top surface of the support beam assembly 5, and brake truss accessories 4 are arranged on the outer walls of both sides of the main beam assembly 2, the main beam assembly 2 is used for supporting the overall structure and the crane, the crane beam accessory 6 is used for stable support and walking of the crane, the brake truss accessory 4 is used for protecting the structural stability of the crane beam accessory 6 during the operation and braking of the crane, and the support beam assembly 5 is used for stable installation and support of the crane beam accessory 6.
[0042] The main beam assembly 2 includes a longitudinal main beam 22 , a side travel groove 21 is provided on one outer wall of the longitudinal main beam 22 , beam side grooves 24 are provided on the other two outer walls of the longitudinal main beam 22 , and a plurality of positioning holes 23 are provided inside the beam side grooves 24 .
[0043] The crane beam accessory 6 includes a crane cross beam 62, on the top surface of which a crane travel track 61 is fixedly installed, and both sides of the bottom surface of the crane cross beam 62 are provided with mounting bottom grooves 63, inside of which a rolling bottom shaft 64 is rotatably installed via a rotating shaft.
[0044] The specific implementation method is as follows: when assembling the crane beam accessory 6, the two ends of the crane beam accessory 6 are respectively carried on the connecting plate 56. At this time, the rolling bottom shaft 64 at the bottom of the crane beam accessory 6 can contact the gasket 57. When splicing and debugging the crane beam accessory 6, it is necessary to adjust the position of the crane beam accessory 6. Since the rolling bottom shaft 64 is set at the bottom of the crane beam accessory 6, the rolling bottom shaft 64 can be easily micro-distanced on the gasket 57, thereby realizing the overall position debugging of the crane beam accessory 6 until the crane beam accessory 6 can reach the most suitable assembly position.
[0045] Through this design, the crane beam accessory 6 is designed with wheels on both sides, which can effectively move the crane beam accessory 6 when it is assembled and debugged, so that it can reach the optimal assembly position, effectively solving the problem that the crane beam accessory 6 cannot be effectively adjusted in position after it is loaded on the support beam assembly 5 due to its heavy weight, thereby greatly improving the overall application effect of the structure.
[0046] The support beam assembly 5 includes a support horn 58, one end of which is fixedly mounted with two reinforcing ribs 59, the reinforcing ribs 59 are slidably connected to the side travel groove 21, a gasket 57 is fixedly mounted on the top surface of the support horn 58, a connecting piece 56 is fixedly mounted on the top surface of the gasket 57, a bottom bolt 55 is rotatably mounted on the connecting piece 56, one end of the bottom bolt 55 is threadedly connected to a threaded hole provided on the bottom surface of the crane cross beam 62, the rolling bottom shaft 64 is rollingly connected to the gasket 57, and the center of the top surface of the gasket 57 is fixedly mounted on the top surface of the gasket 57. A gap filling plate 51 is movably installed at the position, and the outer walls on both sides of the gap filling plate 51 are in close contact with the side walls of the two crane beams 62. The gap filling plate 51 and the crane beam 62 are fixedly connected by positioning bolts 52. A positioning nut 53 is installed on the external thread of the positioning bolt 52. One side of the positioning nut 53 is in close contact and squeezed with the side wall of one end of the crane beam 62. The reinforcing rib plate 59 is fixedly installed in the beam side groove 24 by connecting bolts 54, and one end of the connecting bolt 54 is threadedly installed in the interior of the positioning hole 23.
[0047] The specific implementation method is as follows: in actual application, the position of the support beam assembly 5 can be adjusted according to the needs of the crane operation, so as to adjust the operating state and position of the crane. It is only necessary to move the support horn 58 to a suitable position, and use each connecting bolt 54 to fix the support horn 58 and the reinforcing rib plate 59 to one side of the main beam assembly 2 for subsequent bearing of the crane and the crane beam accessories 6. Since the reinforcing rib plate 59 is completely horizontally placed in the beam side groove 24 of the main beam assembly 2, when a large pressure is placed on the support horn 58, the reinforcing rib plate 59 can be used to strengthen the support horn 58. The rib plate 59 can effectively withstand the bending moment and shear force from the supporting horn 58, avoiding longitudinal deformation of the longitudinal main beam 22, and a gap filling plate 51 is provided in the supporting beam assembly 5. The gap filling plate 51 can effectively fill the assembly gap caused by errors in the design and manufacturing of the crane beam accessories 6, and can eliminate and fill errors in the main load-bearing components of the overall structure. The structure can also serve as a medium for connecting each group of crane beam accessories 6, which can greatly improve the stability and integrity of each crane beam accessory 6 after connection and assembly.
[0048] Through this design, the structure can be fine-tuned according to the working conditions, making the structure suitable for more extensive and complex application scenarios. At the same time, when assembling the structure, the assembly errors caused by the design of the main load-bearing components can be filled and eliminated, thereby improving the stability of the overall structural parts, greatly improving the safety of the overall structural parts, eliminating safety hazards, and ensuring the service life of the structure under continuous high loads.
[0049] The brake truss accessory 4 includes a connecting piece 41 and a connecting plate 42, the connecting piece 41 is fixedly installed on the outer wall of one side of the longitudinal main beam 22, the connecting piece 41 is threadedly connected to the threaded hole set on the top surface of the crane cross beam 62 through a fixing bolt, the connecting plate 42 is transversely fixedly installed inside the beam side groove 24, one end of the connecting plate 42 is transversely fixedly installed with a transverse connecting plate 44, an inclined side plate 43 is obliquely fixedly installed on the outer wall of one side of the connecting plate 42, a connecting groove plate 45 is fixedly installed on the inner side of the transverse connecting plate 44, and a brake truss 46 is fixedly installed on one end of the connecting groove plate 45, and the brake truss 46 is triangular in shape, and the brake truss 46 and the inclined side plate 43 are both fixedly installed on the top surface of the crane cross beam 62 by assembling bolts.
[0050] The specific implementation method is as follows: the brake truss accessory 4 is clamped between the beam side grooves 24 of each longitudinal main beam 22 during installation. Since its main body is composed of multiple continuous triangular structures, each triangular structure has extremely strong stability, which improves the stability of the overall brake truss accessory 4. At the same time, the brake truss accessory 4 can effectively avoid the deformation of the main beam assembly 2 caused by the large horizontal force generated by the crane beam accessory 6 when the crane is in operation, and can ensure the stability of the overall structure when the crane is running and braking, thereby improving the actual application effect of the overall structure.
[0051] Working principle: In practical applications, the position of the support beam assembly 5 can be adjusted according to the needs of the crane operation, so as to adjust the operating state and position of the crane. It is only necessary to move the support horn 58 to a suitable position, and use each connecting bolt 54 to fix the support horn 58 and the reinforcing rib plate 59 to one side of the main beam assembly 2 for subsequent bearing of the crane and the crane beam accessories 6. Since the reinforcing rib plate 59 is completely horizontally placed in the beam side groove 24 of the main beam assembly 2, when a large pressure is placed on the support horn 58, the reinforcing rib plate 59 can effectively withstand the bending moment and shear force from the support horn 58, and avoid longitudinal deformation of the longitudinal main beam 22. In addition, a gap filling plate 51 is provided in the support beam assembly 5. The gap filling plate 51 can effectively fill the assembly gap caused by the error in the design and manufacture of the crane beam accessories 6, and can eliminate and fill the error of the main load-bearing components of the overall structure. The structure can also be used as a medium for connecting each group of crane beam accessories 6, which can greatly improve the stability and integrity of each crane beam accessory 6 after connection and assembly.
[0052] When assembling the crane beam accessory 6, the two ends of the crane beam accessory 6 are respectively carried on the connecting piece 56. At this time, the rolling bottom shaft 64 at the bottom of the crane beam accessory 6 can contact the gasket 57. When splicing and debugging the crane beam accessory 6, it is necessary to adjust the position of the crane beam accessory 6. Since the rolling bottom shaft 64 is set at the bottom of the crane beam accessory 6, the rolling bottom shaft 64 can be easily moved on the gasket 57 to achieve the overall position debugging of the crane beam accessory 6 until the crane beam accessory 6 can reach the most suitable assembly position.
[0053] The brake truss accessories 4 are clamped between the side grooves 24 of each longitudinal main beam 22 during installation. Since its main body is composed of multiple continuous triangular structures, each triangular structure has extremely strong stability, which improves the stability of the overall brake truss accessories 4. At the same time, the brake truss accessories 4 can effectively avoid deformation of the main beam assembly 2 caused by a large horizontal force generated by the crane beam accessories 6 when the crane is in operation, and can ensure the stability of the overall structure when the crane is running and braking.
[0054] The above are only preferred specific implementation modes of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical solutions and inventive concepts of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A novel crane beam and brake truss mechanism for a pipe pile workshop, comprising a base (1), Features: A plurality of main beam assemblies (2) are longitudinally arranged on the top surface of the base (1), and a structural connecting cross beam (3) is fixedly installed on the top surface of each of the plurality of main beam assemblies (2). A crane signal receiving module is arranged at the bottom of the structural connecting cross beam (3). A support beam assembly (5) is arranged on one side of the main beam assembly (2), and a crane beam accessory (6) is arranged on the top surface of the support beam assembly (5). Braking truss accessories (4) are arranged on the outer walls on both sides of the main beam assembly (2). The main beam assembly (2) is used for supporting the overall structure and the crane, and the crane beam accessory (6) is used for stable support and travel of the crane. The braking truss accessory (4) is used for protecting the structural stability of the crane beam accessory (6) during the operation and braking of the crane, and the support beam assembly (5) is used for stable installation and support of the crane beam accessory (6).
2. A new type of crane beam and brake truss mechanism for a pipe pile workshop according to claim 1, It is characterized in that The main beam assembly (2) comprises a longitudinal main beam (22), a side travel groove (21) is arranged on one side outer wall of the longitudinal main beam (22), beam side grooves (24) are arranged on the other two side outer walls of the longitudinal main beam (22), and a plurality of positioning holes (23) are arranged inside the beam side grooves (24).
3. A new type of crane beam and brake truss mechanism for a pipe pile workshop according to claim 2, It is characterized in that The crane beam accessory (6) comprises a crane cross beam (62), a crane travel track (61) is fixedly mounted on the top surface of the crane cross beam (62), mounting bottom grooves (63) are arranged on both sides of the bottom surface of the crane cross beam (62), and a rolling bottom shaft (64) is rotatably mounted inside the mounting bottom groove (63) via a rotating shaft.
4. A new type of crane beam and brake truss mechanism for a pipe pile workshop according to claim 3, It is characterized in that The support beam assembly (5) comprises a support horn (58), one end of which is fixedly mounted with two reinforcing ribs (59), the reinforcing ribs (59) being slidably connected to the side travel groove (21), a gasket (57) being fixedly mounted on the top surface of the support horn (58), a connecting plate (56) being fixedly mounted on the top surface of the gasket (57), and a bottom bolt (55) being rotatably mounted on the connecting plate (56).
5. A new type of crane beam and brake truss mechanism for a pipe pile workshop according to claim 4, It is characterized in that One end of the bottom bolt (55) is threadedly connected to a threaded hole provided on the bottom surface of the crane cross beam (62); the rolling bottom shaft (64) is rollingly connected to the gasket (57); and a gap filling plate (51) is movably installed at the center position of the top surface of the gasket (57).
6. A new type of crane beam and brake truss mechanism for a pipe pile workshop according to claim 5, It is characterized in that The outer walls on both sides of the gap filling plate (51) are in close contact with the side walls of the two crane beams (62), and the gap filling plate (51) and the crane beams (62) are fixedly connected by positioning bolts (52), and the external threads of the positioning bolts (52) are equipped with positioning nuts (53).
7. A novel crane beam and brake truss mechanism for a pipe pile workshop according to claim 6, It is characterized in that One side of the positioning nut (53) is in close contact with and squeezed against a side wall of one end of the crane cross beam (62); the reinforcing rib plate (59) is fixedly installed in the beam side groove (24) via a connecting bolt (54); one end of the connecting bolt (54) is threadedly installed inside the positioning hole (23).
8. A new type of crane beam and brake truss mechanism for a pipe pile workshop according to claim 7, It is characterized in that The brake truss accessory (4) comprises a connecting piece (41) and a connecting plate (42), wherein the connecting piece (41) is fixedly mounted on an outer wall of one side of the longitudinal main beam (22), the connecting piece (41) is threadedly connected to a threaded hole arranged on the top surface of the crane cross beam (62) via a fixing bolt, and the connecting plate (42) is transversely fixedly mounted inside the beam side groove (24).
9. A novel crane beam and brake truss mechanism for a pipe pile workshop according to claim 8, It is characterized in that A transverse connecting plate (44) is transversely fixedly installed at one end of the connecting plate (42), an inclined side plate (43) is obliquely fixedly installed on an outer wall of one side of the connecting plate (42), and a connecting groove plate (45) is fixedly installed on the inner side of the transverse connecting plate (44).
10. A novel crane beam and brake truss mechanism for a pipe pile workshop according to claim 9, It is characterized in that A brake truss (46) is fixedly mounted on one end of the connecting groove plate (45), and the brake truss (46) is triangular in shape. The brake truss (46) and the inclined side plate (43) are fixedly mounted on the top surface of the crane beam (62) by means of assembly bolts.