Hoisting construction method using steel trestle as construction platform
The use of standardized steel trestle components and advanced construction techniques enhances the efficiency and cost-effectiveness of bridge construction by reducing time, manpower, and material requirements, while ensuring high construction accuracy and flexibility.
Patent Information
- Application Number
- CN202411490673.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-24
- Publication Date
- 2024-12-06
AI Technical Summary
Traditional construction platform construction methods for steel trestles in bridge construction are time-consuming, require significant manpower and materials, and are not standardized, leading to increased costs and complexity, especially in challenging environments.
A hoisting construction method using standardized, factory-produced steel trestle components combined with efficient hoisting technology and advanced construction techniques, including three-dimensional coordinate positioning and automatic precision leveling, to facilitate rapid assembly and disassembly of steel trestles as construction platforms.
This method significantly reduces construction time, material consumption, and costs while ensuring high construction accuracy and quality, allowing for flexible and efficient use of prefabricated steel trestles, thereby improving construction efficiency and reducing waste.
Smart Images

Figure CN119083335A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of steel trestle bridges, and more specifically to a hoisting construction method using a steel trestle bridge as a construction platform. Background Art
[0002] In the field of bridge construction and large equipment installation, the construction platform is an important step to ensure safe and efficient construction. Traditional construction platform construction methods often require a lot of time, manpower and materials, and the construction environment is complex and changeable, especially on water or in special terrain conditions, the construction difficulty and cost are further increased. Therefore, it is particularly important to develop a fast, efficient, adaptable and low-cost construction platform construction method.
[0003] With the continuous advancement of steel structure technology, steel trestles, as a prefabricated structure, are widely used in various engineering constructions due to their stable structure, easy assembly and disassembly, and strong adaptability. Steel trestles can not only be used as transportation channels, but also as construction platforms for various hoisting operations. However, when steel trestles in the prior art are used as construction platforms, there are still some shortcomings, such as long construction period, high material consumption, and low degree of standardization. Summary of the invention
[0004] In order to overcome the above-mentioned deficiencies in the prior art, the present invention provides a hoisting construction method using a steel trestle as a construction platform. The hoisting construction method uses standardized, factory-produced steel trestle components, combined with efficient hoisting technology and advanced construction technology, to achieve rapid construction and efficient use of the construction platform.
[0005] In order to solve the above technical problems, the technical solution adopted by the present invention is: A hoisting construction method using a steel trestle as a construction platform comprises the following steps: S1. Construction preparation work; S2. Fabrication of assembled cantilever guided positioning pile frame; S3, installation of assembled cantilever guide positioning pile frame; S4, making steel pipe piles and positioning the steel pipe piles; S5, vibrate and sink the steel pipe pile; S6. Level the pile top and install the steel pipe pile top distribution beam and connecting support; S7, assembly and transportation of main trusses, and overall hoisting and erection of main trusses of beams; S8, bridge deck module production, laying of bridge deck system, laying of water pipes, cables and communication facilities; S9, bridge deck railing production, installation of guardrails; S10. Steel platform construction.
[0006] In the step S1, the three-dimensional coordinate positioning technology of the total station is used for the construction of the bridge head and the control of the axis of the trestle and the construction control of the upper structure. The total station is used to accurately position the assembled cantilever guide positioning frame in three dimensions, and the automatic precision level is used for leveling height measurement technology, which is used in the whole process of the trestle construction.
[0007] In step S4, the steel pipe pile is completed in the steel component processing yard. First, the existing 45a I-beam is laid flat on the leveled floor as a mold, and the steel pipe is placed on the I-beam for docking. After the steel pipe enters the site, the interface is first leveled, and the deformed or uneven pipe mouth is cut off, and then the angle steel is welded around the steel pipe as the fulcrum of the fall chain. Before welding, the steel pipe interface is first closely attached to the fall chain, and then the level of the joint is checked with a level ruler. If it is not closely attached and not level, continue to adjust it until it is horizontal and closely attached before welding. First, weld along the interface. After the weld is qualified, four reinforcement plates are evenly distributed on the steel pipe and welded evenly around it.
[0008] In step S5, the first hole steel pipe pile construction method is to first stake out the first row of steel pipe piles on the river bank, and the steel pipe piles are constructed by the "fishing method". A 50t crawler crane is used in conjunction with a DZJ90A hydraulic vibration pile hammer to sink the steel pipe piles. When the first steel pipe pile is driven in, a standard section is driven in first, and the construction time of the hydraulic vibration pile hammer is observed and recorded. After the construction of the first standard section is completed, the second non-standard section of the steel pipe pile is hoisted, and a 50t crawler crane is used in conjunction with manual positioning to the first section of the pipe pile. Position, technicians need to check the flatness and fit of the docking interface on site, and weld when it is completely tight. Electric welders are required to weld from both sides at the same time and ensure that the weld is full. Pay attention to knocking off the welding slag during welding, and then evenly distribute 4 reinforcement plates on the steel pipe in a week for welding; after qualified welding, the second section of pipe piles can be driven in. During the process of driving the pipe piles, pay attention to observe the working amplitude of DZJ90A hydraulic vibration pile hammer and keep records. Stop driving in time when the vibration pile hammer can no longer be driven to prevent damage to the top of the pipe pile.
[0009] In step S5, after the cantilever positioning guide frame is installed, the exact position of the pre-sunken steel pipe pile is measured by a total station, the fine-tuning system of the guide frame is adjusted to complete the precise positioning, and the sinking amount of the pipe pile is monitored by a level; the crawler crane uses a hook to lift the bottom section of the steel pipe pile to the designed pile position, and the steel pipe pile is allowed to sink into the soil along the guide wheel of the positioning guide frame under the action of its own weight, and the crawler crane is used to lift the vibrating hammer and the hydraulic clamp to the top of the steel pipe pile, and the top of the steel pipe pile is clamped with a hydraulic clamp to check that the verticality of the pile meets the requirements, and then the vibrating hammer is started to vibrate, and each vibration lasts no more than 10 to 15 minutes.
[0010] In step S6, the piles are driven to the designed elevation and the deflection and the depth of the piles are checked. After the errors meet the requirements of the specification, the steel pipe pile diagonal brace, flat joint, bracket, and pile top distribution beam are constructed; the top of the cantilever assembly bracket is measured, and the design elevation of the steel pipe top is found out and issued based on this as the reference plane. The operator gas cuts the notch of the pile top according to the design size according to the technical instructions, and welds the brackets on the steel pipes on both sides of the notch; after the pile top distribution beam is manufactured in the back field, it is transported to the site, and the crawler crane is used for two-point lifting. The operator stands on the cantilever assembly guide frame platform to work, and directs the crane to put the distribution beam into the notch, and then installs the brackets to weld on the distribution beam and the steel pipe pile; the operator measures the net distance between the steel pipe piles and then cuts the horizontal rod and the diagonal rod of the scissors brace, and the horizontal rod is installed first and the diagonal rod is installed later; the rod is lifted by the crane and moved to the specified position, and an operator stands at each end of the horizontal rod and moves to the designed position for welding. After the installation of the horizontal rod, the diagonal rod is installed, and the installation steps of the diagonal rod are the same as those of the horizontal rod.
[0011] In step S7, the Bailey beam is assembled. First, a 25t crane is used to hoist the first Bailey sheet to the assembly position, and then the Bailey sheet is supported by steel to prevent tilting. Then the first sheet of the adjacent group is assembled. When the Bailey sheet is hoisted to a horizontal distance of 90 cm from the first sheet, a 90-type connector is installed. The connector and the Bailey sheet are connected by bolts. The second sheet of the first group is installed. After the male heads of the two Bailey sheets are placed in place, the two Bailey sheets are manually connected by special pins. If the resistance of the pin is large during installation, a flat hammer can be used to knock until it is installed in place. After the pin is in place, a safety card is installed to prevent Stop the pin from falling off during operation; then install the 90-type connector, install the second set of the second Bailey piece, repeat the above steps to lengthen 4 pieces in a single group; for the transportation of Bailey beams, the assembled Bailey beams are tied with two steel wire ropes with a diameter of not less than 12.5mm at 2.6m from the end of the Bailey beam, and hoisted at two points with a 25t crane, and the Bailey beams are hoisted to a 13m long flatbed truck, and reinforced with steel wire ropes, and then transported to the assembly site, and rubber pads are used to isolate the steel wire ropes from the direct contact positions of the Bailey beams to protect the steel wire ropes; Bailey beam installation, on the trestle The installation of the lower structure is carried out by a 50t crawler crane. The Bailey truss longitudinal beam is laid on the load-bearing beam. The Bailey truss is assembled in blocks in advance and transported to the laying position for lifting and installation. When the Bailey beam is erected, firstly measure and lay out on the top crossbeam of the lower structure to determine the exact position of the Bailey frame and lay the shock-absorbing rubber sheet flat on the crossbeam. Then, the assembled unit Bailey beam is lifted to the designed position by a crawler crane. The rear-end operator fastens the safety belt to the laid Bailey beam to direct the Bailey beam to be precisely positioned. After positioning, the Bailey beam pin is inserted into the Bailey beam pin hole to connect it to the Bailey beam of the built trestle. At the same time, install the pin safety card in place. After the rear end is installed, move the lifting point to the front end for precise alignment of the front end. The crane lifts the front end Bailey beam and leaves it 1.5cm away from the crossbeam to accurately position the Bailey beam and install the shock-absorbing rubber pad. After it is in place, slowly lower the Bailey beam and weld 21cm long 8a channel steel on the crossbeams on both sides of the Bailey beam. The channel steel is placed vertically close to the lower chord of the Bailey beam. After the installation of the limit channel steels on both sides is completed, press the 34.6cm long channel steel horizontally on the top of the lower chord. After adjusting the position, weld the vertical channel steel and the horizontal channel steel. It is strictly forbidden to spark or weld on the Bailey beam during the process.
[0012] In step S8, after the bridge deck is processed, a 25t truck crane is used to lay the deck flat on a flatbed truck. The bridge decks are stacked "one front and one back", reinforced with steel wire ropes, and transported to the site for hoisting. When the bridge deck is installed, the female head is connected to the existing bridge deck longitudinally. When placed horizontally, a Bailey sheet corresponds to the bottom of each U-bolt pressure beam to facilitate the installation of the U-bolt. After the bridge deck is installed in place, the U-bolts and pressure plates are installed manually.
[0013] In step S9, a 1.2m high handrail is provided on both sides of the trestle, and two crossbars are provided, which are made of φ48x2.5mm ordinary steel pipes. The handrails on the main bridge side are disconnected when encountering the branch trestle. A column is provided every 1.5m of the handrails, which are welded to the crossbeam of the bridge deck. The crossbars are 60cm and 120cm away from the bridge deck respectively, and the crossbars are connected with the vertical bars by welding.
[0014] In step S10, the steel platform is connected to the steel trestle at the pier position, and consists of four parts: foundation φ529mm steel pipe pile vibration sinking, I-beam main beam erection, Bailey sheet erection, platform panel paving and railing installation. The steel pipe pile foundation construction adopts crawler crane with DZJ90A vibrating hammer to sink piles; the main beam and distribution beam are manufactured on the shore and transported to the site for erection; the panel is directly laid on site.
[0015] Compared with the prior art, the present invention has the following beneficial effects: By using the steel trestle as a construction platform and using equipment such as cranes and guide frames for hoisting operations, the construction efficiency can be greatly improved. Compared with traditional construction methods, this method can save a lot of manpower, material resources and time costs, thereby speeding up the construction progress; in the design and construction process of the steel trestle, factory processing and standardized parts are adopted, with unified specifications and reliable structures. This can not only improve the construction accuracy, but also ensure that the construction quality meets the design requirements and reduce errors and defects in the construction process; by optimizing the design of structures such as Bailey beams, materials and construction costs can be saved while ensuring the structural force. In addition, the large-scale use of prefabricated steel trestles can also reduce on-site welding and other processes, further reducing construction costs; the use of prefabricated steel trestles and steel platforms makes on-site disassembly and assembly simpler and faster, thereby improving the turnover efficiency of materials. This can not only reduce waste during the construction process, but also improve the flexibility and variability of the entire construction process. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a flow chart of the construction of the trestle in the present invention; Figure 2 It is a construction flow chart of the trestle superstructure in the present invention; Figure 3 This is a schematic diagram of Bailey beam installation in the present invention. DETAILED DESCRIPTION
[0017] In order to more clearly understand the above-mentioned purpose, features and advantages of the present invention, the present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments. It should be noted that the embodiments of the present application and the features in the embodiments can be combined with each other without conflict.
[0018] In the following description, many specific details are set forth to facilitate a full understanding of the present invention. However, the present invention may also be implemented in other ways different from the description. Therefore, the protection scope of the present invention is not limited to the specific embodiments disclosed below.
[0019] like Figures 1 to 3 As shown, a hoisting construction method using a steel trestle as a construction platform comprises the following steps: S1. Construction preparation work; S2. Fabrication of assembled cantilever guided positioning pile frame; S3, installation of assembled cantilever guide positioning pile frame; S4, making steel pipe piles and positioning the steel pipe piles; S5, vibrate and sink the steel pipe pile; S6. Level the pile top and install the steel pipe pile top distribution beam and connecting support; S7, assembly and transportation of main trusses, and overall hoisting and erection of main trusses of beams; S8, bridge deck module production, laying of bridge deck system, laying of water pipes, cables and communication facilities; S9, bridge deck railing production, installation of guardrails; S10. Steel platform construction.
[0020] Preferably, in step S1, the three-dimensional coordinate positioning technology of the total station is used for the construction of the bridge head and the control of the pier axis, the superstructure and other construction controls. The total station is used to accurately perform three-dimensional positioning of the assembled cantilever guide positioning frame, and the automatic precision level is used for leveling elevation measurement technology, which is used in the entire process of pier construction.
[0021] Preferably, in step S4, the steel pipe pile is completed in the steel component processing field. First, the existing 45a I-beam is laid flat on the leveled floor as a mold, and the steel pipe is placed on the I-beam for docking. After the steel pipe enters the site, the interface is first leveled, and the deformed or uneven pipe mouth is cut off, and then the angle steel is welded around the steel pipe as the fulcrum of the fall chain. Before welding, the steel pipe interface is first closely attached to the fall chain, and then the level of the joint is checked with a level ruler. If it is not closely attached and not level, continue to adjust it until it is horizontal and closely attached before welding. First, weld along the interface around the interface, and after the weld is qualified, evenly distribute four reinforcement plates on the steel pipe around the circle for welding.
[0022] When purchasing steel pipes, the best length is 12m. The processing and manufacturing of steel pipe piles are carried out in the factory. After the steel pipes enter the factory, the wall thickness of the steel pipes must be inspected and accepted as required. All materials must meet the standards and requirements. Auxiliary materials such as welding rods, welding wires, and fluxes should match the steel plate materials, and their technical indicators must not be lower than the mechanical properties of the parent material.
[0023] The steel pipe pile has a diameter of φ529mm and a wall thickness of 8mm, and is made of Q235 steel. Each trestle steel pipe pile is processed in multiple sections. Considering the maximum transportation length of the steel pipe pile and the requirements for connecting the piles, the standard configuration of the steel pipe pile is planned to be 12m sections, and the non-standard configuration is planned to be 12m / section + adjustment section.
[0024] Preferably, in step S5, the first hole steel pipe pile construction method is to first stake out the first row of steel pipe piles on the river bank, the steel pipe piles are constructed by the "fishing method", and a 50t crawler crane is used in conjunction with a DZJ90A hydraulic vibration pile hammer to sink the steel pipe piles. When the first steel pipe pile is driven in, a standard section is driven in first, and the construction time of the hydraulic vibration pile hammer is observed and recorded; after the construction of the first standard section is completed, the second non-standard section of the steel pipe pile is hoisted, and a 50t crawler crane is used in conjunction with manual positioning to the first section of the pipe pile. The technician needs to check the flatness and fit of the docking interface on site. Welding should be carried out when it is completely tight. Electric welders are required to weld from both sides at the same time and ensure that the weld is full. Pay attention to knocking off the welding slag during welding, and then evenly distribute 4 reinforcement plates on the steel pipe in a week for welding; after the welding is qualified, the second section of the pipe pile is driven in. During the process of driving the pipe pile, pay attention to observe the working amplitude of the DZJ90A hydraulic vibration pile hammer and keep a record. Stop driving in time when the vibration pile hammer can no longer be driven to prevent damage to the top of the pipe pile.
[0025] Preferably, in step S5, after the cantilever positioning guide frame is installed, the exact position of the pre-sunken steel pipe pile is measured by a total station, the fine-tuning system of the guide frame is adjusted to complete the precise positioning, and the sinking amount of the pipe pile is monitored by a level; the crawler crane uses a hook to lift the bottom section of the steel pipe pile to the designed pile position, and the steel pipe pile is allowed to sink into the soil along the guide wheel of the positioning guide frame under the action of its own weight, and the crawler crane is used to lift the vibrating hammer and the hydraulic clamp to the top of the steel pipe pile, and the top of the steel pipe pile is clamped with a hydraulic clamp to check that the verticality of the pile meets the requirements, and then the vibrating hammer is started to vibrate, and each vibration lasts no more than 10 to 15 minutes.
[0026] When sinking piles, the middle pile should be constructed first, followed by the piles on both sides. During the process of sinking piles, the surveyor should direct the precise positioning on site, and during the process of driving the steel pipe piles, the pile position and the verticality of the piles should be constantly checked, and the pile top elevation should be well controlled. After all the equipment is ready, the pile hammer can be used to drive the steel pipe piles.
[0027] Preferably, in step S6, the piles are driven to the designed elevation and the deflection and the depth of penetration of the piles are checked. After the errors meet the requirements of the specifications, the steel pipe pile diagonal brace, flat joint, corbel, and pile top distribution beam are constructed; the top of the cantilever assembly bracket is measured, and the design elevation of the steel pipe top is found out and issued based on this as the reference plane. The operating personnel gas cut the notch on the pile top according to the design size according to the technical instructions, and weld the corbels on the steel pipes on both sides of the notch; after the pile top distribution beam is manufactured in the back field, it is transported to the site and hoisted at two points by a crawler crane. In this method, the operator stands on the cantilever assembly guide frame platform and directs the crane to put the distribution beam into the slot, and then installs the corbel by welding it to the distribution beam and the steel pipe pile; the operator measures the net distance between the steel pipe piles and then cuts the horizontal and diagonal rods of the scissors brace, installing the horizontal rod first and then the diagonal rod; the crane is used to lift the rod and move it to the designated position, with an operator standing at each end of the horizontal rod and moving it to the designed position for welding. After the horizontal rod is installed, the diagonal rod is installed, and the diagonal rod installation steps are the same as those for the horizontal rod.
[0028] Preferably, in step S7, the Bailey beam is assembled. First, a 25t crane is used to hoist the first Bailey sheet to the assembly position, and then the Bailey sheet is supported by steel to prevent tilting. Then, the first sheet of the adjacent group is assembled. When the Bailey sheet is hoisted to a horizontal distance of 90 cm from the first sheet, a 90-type connector is installed. The connector and the Bailey sheet are connected by bolts. The second sheet of the first group is installed. After the male heads of the two Bailey sheets are placed in place, the two Bailey sheets are manually connected by special pins. If the resistance of the pin is large during installation, a flat hammer can be used to knock until it is installed in place. After the pin is in place, the safety card is installed. Prevent the pin from falling off during operation; then install the 90-type connector, install the second set of the second Bailey piece, repeat the above steps to lengthen 4 pieces in a single group; transportation of Bailey beams, the assembled Bailey beams are tied with two steel wire ropes with a diameter of not less than 12.5mm at 2.6m from the end of the Bailey beam, and hoisted at two points with a 25t crane, and the Bailey beams are hoisted to a 13m long flatbed truck, and reinforced with steel wire ropes, and then transported to the assembly site, and rubber pads are used to isolate the wire ropes from the direct contact position of the Bailey beams to protect the wire ropes; Bailey beam installation, trestle The installation of the upper structure is carried out by a 50t crawler crane. The Bailey truss longitudinal beam is laid on the load-bearing beam. The Bailey truss is assembled in blocks in advance and transported to the laying position for lifting and installation. When the Bailey beam is erected, first measure and lay out on the top crossbeam of the lower structure to determine the exact position of the Bailey frame and lay the shock-absorbing rubber sheet flat on the crossbeam. Then use the crawler crane to lift the assembled unit Bailey beam to the designed position. The rear-end operator fastens the safety belt to the laid Bailey beam and directs the Bailey beam to be precisely positioned. After positioning, the Bailey beam pin is inserted into the Bailey beam pin hole and connected to the Bailey beam of the built trestle. At the same time, install the pin safety card in place. After the rear end is installed, move the lifting point to the front end for precise alignment of the front end. The crane lifts the front end Bailey beam and leaves it 1.5cm away from the crossbeam to accurately position the Bailey beam and install the shock-absorbing rubber pad. After it is in place, slowly lower the Bailey beam and weld 21cm long 8a channel steel on the crossbeams on both sides of the Bailey beam. The channel steel is placed vertically close to the lower chord of the Bailey beam. After the installation of the limit channel steels on both sides is completed, press the 34.6cm long channel steel horizontally on the top of the lower chord. After adjusting the position, weld the vertical channel steel and the horizontal channel steel. It is strictly forbidden to spark or weld on the Bailey beam during the process.
[0029] Preferably, in step S8, after the bridge deck is processed, a 25t truck crane is used to lay the deck flat on a flatbed truck, the bridge decks are stacked "one front and one back", reinforced with steel wire ropes, and transported to the site for hoisting. When the bridge deck is installed, the female head is connected to the existing bridge deck longitudinally. When placed horizontally, a Bailey piece corresponds to the bottom of each U-bolt pressure beam to facilitate the installation of the U-bolt. After the bridge deck is installed in place, the U-bolts and pressure plates are installed manually.
[0030] The processing of the bridge deck system adopts the rear standardized and factory-made block production. The block length of the bridge deck is designed according to the width of the trestle bridge deck of 6m, and the block width is designed to be 1.5m considering the beam spacing and transportation requirements. The longitudinal beam under the panel is I25 I-beam with a spacing of 1.5m. First, the processing platform is leveled with a level. The processing platform can be assembled with existing I-beams and steel plates. First, the panel is laid on the processing platform, and the position of the I-beam is drawn on the paved surface according to the spacing of 1.5m. The I-beam is placed along the length of the steel plate with a 25t truck crane. The center of the first I-beam corresponds to the edge of the steel plate, and the arrangement is arranged in sequence according to the spacing of 1.5m. The position of the last I-beam is located at the edge of the other side of the steel plate. The I-beam is not installed, so that the bridge deck forms a "yin and yang joint" for easy on-site assembly. The flange of the I-beam is intermittently welded to the steel plate, with a weld length of 10cm and a weld spacing of 20cm. The weld form is a fillet weld, and the weld leg size is 6mm. After the bridge deck distribution beam is welded, the bridge deck reinforcement U-bolt pressure beam is installed. The pressure beam is located 0.5m and 4.5m away from the edge of the panel, and 6 are set for each panel. The pressure beam is made of 8a channel steel with a length of 28cm. It is horizontally moved from the gap between the I-beams of the bridge deck to the designed position and welded to the I-beams.
[0031] Preferably, in step S9, railings with a height of 1.2m are provided on both sides of the trestle, and two cross bars are provided, which are made of φ48x2.5mm ordinary steel pipes, and are disconnected when encountering the branch trestle on the main bridge side. A column is provided every 1.5m of the railing, which is welded to the crossbeam of the bridge deck. The cross bars are 60cm and 120cm away from the bridge deck respectively, and the cross bars are connected with the vertical bars by welding.
[0032] The dismantling of the pier is carried out after the pier has been in operation for a long time, the main project has been completed, and the mission of the pier has ended. Before dismantling the pier, the structural safety of the undismantled section of the pier should be checked first, and the dismantling construction can only be carried out after the structural safety is ensured.
[0033] The bridge deck and Bailey beam were removed manually with a 50t crawler crane and transported to the rear stacking site by trailer. The steel pipe piles of the lower structure were pulled out by parking a 50t crawler crane on the trestle and using a vibrating hammer to pull out the steel pipe piles hole by hole.
[0034] Preferably, in step S10, the steel platform is connected to the steel trestle at the pier position, and consists of four parts: foundation φ529mm steel pipe pile vibration sinking, I-beam main beam erection, Bailey sheet erection, platform panel paving and railing installation. The steel pipe pile foundation construction adopts crawler crane with DZJ90A vibrating hammer to sink piles; the main beam and distribution beam are manufactured on the shore and transported to the site for erection; the panel is directly laid on site.
[0035] Only the preferred embodiments of the present invention are described in detail above, but the present invention is not limited to the above embodiments. Various changes can be made within the knowledge scope of ordinary technicians in this field without departing from the purpose of the present invention, and various changes should be included in the protection scope of the present invention.
Claims
1. A hoisting construction method using a steel trestle as a construction platform, characterized in that: The following steps are involved: S1. Construction preparation work; S2. Fabrication of assembled cantilever guided positioning pile frame; S3, installation of assembled cantilever guide positioning pile frame; S4, making steel pipe piles and positioning the steel pipe piles; S5, vibrate and sink the steel pipe pile; S6. Level the pile top and install the steel pipe pile top distribution beam and connecting support; S7, assembly and transportation of main trusses, and overall hoisting and erection of main trusses of beams; S8, bridge deck module production, laying of bridge deck system, laying of water pipes, cables and communication facilities; S9, bridge deck railing production, installation of guardrails; S10. Steel platform construction.
2. The method for hoisting construction using a steel trestle as a construction platform according to claim 1, characterized in that: In the step S1, the three-dimensional coordinate positioning technology of the total station is used for the construction of the bridge head and the control of the axis of the trestle and the construction control of the upper structure. The total station is used to accurately position the assembled cantilever guide positioning frame in three dimensions, and the automatic precision level is used for leveling height measurement technology, which is used in the whole process of the trestle construction.
3. The method for hoisting construction using a steel trestle as a construction platform according to claim 1, characterized in that: In step S4, the steel pipe pile is completed in the steel component processing yard. First, the existing 45a I-beam is laid flat on the leveled floor as a mold, and the steel pipe is placed on the I-beam for docking. After the steel pipe enters the site, the interface is first leveled, and the deformed or uneven pipe mouth is cut off, and then the angle steel is welded around the steel pipe as the fulcrum of the fall chain. Before welding, the steel pipe interface is first closely attached to the fall chain, and then the level of the joint is checked with a level ruler. If it is not closely attached and not level, continue to adjust it until it is horizontal and closely attached before welding. First, weld along the interface. After the weld is qualified, four reinforcement plates are evenly distributed on the steel pipe and welded evenly around it.
4. The method for hoisting construction using a steel trestle as a construction platform according to claim 1, characterized in that: In step S5, the first hole steel pipe pile construction method is to first stake out the first row of steel pipe piles on the river bank, and the steel pipe piles are constructed by the "fishing method". A 50t crawler crane is used in conjunction with a DZJ90A hydraulic vibration pile hammer to sink the steel pipe piles. When the first steel pipe pile is driven in, a standard section is driven in first, and the construction time of the hydraulic vibration pile hammer is observed and recorded. After the construction of the first standard section is completed, the second non-standard section of the steel pipe pile is hoisted, and a 50t crawler crane is used in conjunction with manual positioning to the first section of the pipe pile. Position, technicians need to check the flatness and fit of the docking interface on site, and weld when it is completely tight. Electric welders are required to weld from both sides at the same time and ensure that the weld is full. Pay attention to knocking off the welding slag during welding, and then evenly distribute 4 reinforcement plates on the steel pipe in a week for welding; after qualified welding, the second section of pipe piles can be driven in. During the process of driving the pipe piles, pay attention to observe the working amplitude of DZJ90A hydraulic vibration pile hammer and keep records. Stop driving in time when the vibration pile hammer can no longer be driven to prevent damage to the top of the pipe pile.
5. The method for hoisting construction using a steel trestle as a construction platform according to claim 1, characterized in that: In step S5, after the cantilever positioning guide frame is installed, the exact position of the pre-sunken steel pipe pile is measured by a total station, the fine-tuning system of the guide frame is adjusted to complete the precise positioning, and the sinking amount of the pipe pile is monitored by a level; the crawler crane uses a hook to lift the bottom section of the steel pipe pile to the designed pile position, and the steel pipe pile is allowed to sink into the soil along the guide wheel of the positioning guide frame under the action of its own weight, and the crawler crane is used to lift the vibrating hammer and the hydraulic clamp to the top of the steel pipe pile, and the top of the steel pipe pile is clamped with a hydraulic clamp to check that the verticality of the pile meets the requirements, and then the vibrating hammer is started to vibrate, and each vibration lasts no more than 10 to 15 minutes.
6. The method for hoisting construction using a steel trestle as a construction platform according to claim 1, characterized in that: In step S6, the piles are driven to the designed elevation and the deflection and the depth of the piles are checked. After the errors meet the requirements of the specification, the steel pipe pile diagonal brace, flat joint, bracket, and pile top distribution beam are constructed; the top of the cantilever assembly bracket is measured, and the design elevation of the steel pipe top is found out and issued based on this as the reference plane. The operator gas cuts the notch of the pile top according to the design size according to the technical instructions, and welds the brackets on the steel pipes on both sides of the notch; after the pile top distribution beam is manufactured in the back field, it is transported to the site, and the crawler crane is used for two-point lifting. The operator stands on the cantilever assembly guide frame platform to work, and directs the crane to put the distribution beam into the notch, and then installs the brackets to weld on the distribution beam and the steel pipe pile; the operator measures the net distance between the steel pipe piles and then cuts the horizontal rod and the diagonal rod of the scissors brace, and the horizontal rod is installed first and the diagonal rod is installed later; the rod is lifted by the crane and moved to the specified position, and an operator stands at each end of the horizontal rod and moves to the designed position for welding. After the installation of the horizontal rod, the diagonal rod is installed, and the installation steps of the diagonal rod are the same as those of the horizontal rod.
7. The method for hoisting construction using a steel trestle as a construction platform according to claim 1, characterized in that: In step S7, the Bailey beam is assembled. First, a 25t crane is used to hoist the first Bailey sheet to the assembly position, and then the Bailey sheet is supported by steel to prevent tilting. Then the first sheet of the adjacent group is assembled. When the Bailey sheet is hoisted to a horizontal distance of 90 cm from the first sheet, a 90-type connector is installed. The connector and the Bailey sheet are connected by bolts. The second sheet of the first group is installed. After the male heads of the two Bailey sheets are placed in place, the two Bailey sheets are manually connected by special pins. If the resistance of the pin is large during installation, a flat hammer can be used to knock until it is installed in place. After the pin is in place, a safety card is installed to prevent Stop the pin from falling off during operation; then install the 90-type connector, install the second set of the second Bailey piece, repeat the above steps to lengthen 4 pieces in a single group; for the transportation of Bailey beams, the assembled Bailey beams are tied with two steel wire ropes with a diameter of not less than 12.5mm at 2.6m from the end of the Bailey beam, and hoisted at two points with a 25t crane, and the Bailey beams are hoisted to a 13m long flatbed truck, and reinforced with steel wire ropes, and then transported to the assembly site, and rubber pads are used to isolate the steel wire ropes from the direct contact positions of the Bailey beams to protect the steel wire ropes; Bailey beam installation, on the trestle The installation of the lower structure is carried out by a 50t crawler crane. The Bailey truss longitudinal beam is laid on the load-bearing beam. The Bailey truss is assembled in blocks in advance and transported to the laying position for lifting and installation. When the Bailey beam is erected, firstly measure and lay out on the top crossbeam of the lower structure to determine the exact position of the Bailey frame and lay the shock-absorbing rubber sheet flat on the crossbeam. Then, the assembled unit Bailey beam is lifted to the designed position by a crawler crane. The rear-end operator fastens the safety belt to the laid Bailey beam to direct the Bailey beam to be precisely positioned. After positioning, the Bailey beam pin is inserted into the Bailey beam pin hole to connect it to the Bailey beam of the built trestle. At the same time, install the pin safety card in place. After the rear end is installed, move the lifting point to the front end for precise alignment of the front end. The crane lifts the front end Bailey beam and leaves it 1.5cm away from the crossbeam to accurately position the Bailey beam and install the shock-absorbing rubber pad. After it is in place, slowly lower the Bailey beam and weld 21cm long 8a channel steel on the crossbeams on both sides of the Bailey beam. The channel steel is placed vertically close to the lower chord of the Bailey beam. After the installation of the limit channel steels on both sides is completed, press the 34.6cm long channel steel horizontally on the top of the lower chord. After adjusting the position, weld the vertical channel steel and the horizontal channel steel. It is strictly forbidden to spark or weld on the Bailey beam during the process.
8. The method for hoisting construction using a steel trestle as a construction platform according to claim 1, characterized in that: In step S8, after the bridge deck is processed, a 25t truck crane is used to lay the deck flat on a flatbed truck, the bridge deck is stacked "one front and one back", and then reinforced with steel wire ropes, and transported to the site for hoisting. When the bridge deck is installed, the female head is connected to the existing bridge deck longitudinally. When placed horizontally, a Bailey sheet corresponds to the bottom of each U-bolt pressure beam, which is convenient for the installation of the U-bolt. After the bridge deck is installed in place, the U bolts and pressure plates are installed manually.
9. The method for hoisting construction using a steel trestle as a construction platform according to claim 1, characterized in that: In step S9, a 1.2m high handrail is provided on both sides of the trestle, and two crossbars are provided, which are made of φ48x2.5mm ordinary steel pipes. The handrails on the main bridge side are disconnected when encountering the branch trestle. A column is provided every 1.5m of the handrails, which are welded to the crossbeam of the bridge deck. The crossbars are 60cm and 120cm away from the bridge deck respectively, and the crossbars are connected with the vertical bars by welding.
10. The method for hoisting construction using a steel trestle as a construction platform according to claim 1, characterized in that: In step S10, the steel platform is connected to the steel trestle at the pier position, and consists of four parts: foundation φ529mm steel pipe pile vibration sinking, I-beam main beam erection, Bailey sheet erection, platform panel paving and railing installation. The steel pipe pile foundation construction adopts crawler crane with DZJ90A vibrating hammer to sink piles; the main beam and distribution beam are manufactured on the shore and transported to the site for erection; the panel is directly laid on site.