Fabricated concrete structure connecting device and connecting method

By designing the prefabricated concrete structure connection device, using the combination of fixed columns and sealing mechanisms, the problems of complex construction and difficulty in repairing the plugging project are solved, and efficient water flow sealing and construction efficiency are achieved.

CN119083377AInactive Publication Date: 2024-12-06KANGBODA CONSTR TECH GRP CO LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202411303201.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-19
Publication Date
2024-12-06
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The construction process of the existing plugging project is complex, requires high technical level, is difficult to construct, takes a long time and has low repair capabilities.

Method used

A prefabricated concrete structure connection device is designed, including fixed columns, sealing mechanisms and fixing mechanisms. Through components such as anchor claws, anchor rods, scissor arms, connecting plates, limit rings, etc., the water flow of the embankment is sealed. The construction process is simplified by filling concrete with the first and second sealing columns.

Benefits of technology

Effectively sealing the water flow, reducing the impact of the water flow, reducing construction difficulty and repair costs, and improving construction efficiency and repair capabilities.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083377A_ABST
    Figure CN119083377A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of fabricated buildings, and particularly relates to a fabricated concrete structure connecting device and a connecting method.The fabricated concrete structure connecting device comprises a fixing column, and a fixing mechanism and a plugging mechanism are arranged on the surface of the fixing column; the fixing mechanism realizes the action of fixing the plugging mechanism by the anchor fluke; the blocking mechanism achieves the action that the first blocking column and the second blocking column block a large gap. According to the fabricated concrete structure connecting device and method, the fixing mechanism and the plugging mechanism are arranged, a plurality of first plugging columns and a plurality of second plugging columns are connected to plug water flow, the fixing mechanism is connected with a traction buckle through a traction rope, and the surfaces of a plurality of pull rings are slidably connected with the surface of a steel cable; and the surface of the steel cable is in sliding connection with the surfaces of the multiple traction buckles. The technical problems that the construction process of an existing plugging project is complex, the construction difficulty is large, consumed time is long, and the re-repairing capacity is relatively low are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of prefabricated buildings, and in particular to a prefabricated concrete structure connection device and a connection method. Background Art

[0002] Prefabricated buildings are a new type of construction method, in which building components are prefabricated in factories and then transported to construction sites for assembly. This construction method has the advantages of improving building quality, shortening construction period, reducing construction costs and environmental protection. In prefabricated buildings, the quality of the core area of ​​the components is directly related to the structural safety and service life of the entire building. Therefore, it is of great practical significance to study a new casting method for connecting structural components of prefabricated buildings.

[0003] In actual use, when a river bursts its dike, a blocking project is implemented to return the water to the old river channel. Soil and materials are used to block the two dikes at the mouth, and the construction process of blocking to the dragon mouth and finally closing the gap is relatively complicated, requiring a high level of technology, and is difficult to construct. It takes a long time and has a relatively low ability to repair it again, which makes it inconvenient to use. Summary of the invention

[0004] Based on the technical problems that the existing plugging project construction process is relatively complicated, requires a high level of technology, is difficult to construct, takes a long time and has a relatively low re-repair ability, the present invention proposes an assembled concrete structure connection device and connection method.

[0005] The present invention provides an assembled concrete structure connection device, comprising a fixing column, wherein a fixing mechanism and a blocking mechanism are respectively provided on the surface of the fixing column;

[0006] The fixing mechanism is located above the blocking mechanism;

[0007] The fixing mechanism includes an anchor claw, and the fixing mechanism realizes the action of the anchor claw fixing the blocking mechanism;

[0008] The blocking mechanism includes a first blocking column and a second blocking column, and the blocking mechanism enables the first blocking column and the second blocking column to block a larger gap.

[0009] Preferably, the blocking mechanism further comprises an anchor rod, a base is fixedly connected to the surface of the anchor rod, the surface of the base is rotatably connected to the surface of the anchor claw, and the two anchor claws are symmetrically distributed around the axis of the base.

[0010] Preferably, a scissor arm is fixedly connected to the surface of the base, and the two scissor arms are symmetrically distributed with the axis of the base as the center. The surface of the anchor rod is slidably connected to a connecting plate, and the surface of the scissor arm is fixedly connected to the surface of the connecting plate.

[0011] Preferably, a connecting rod is rotatably connected to the surface of the connecting plate, the surface of the connecting rod is rotatably connected to the surface of the fluke, and a plurality of the flukes are symmetrically distributed around the axis of the connecting plate.

[0012] Preferably, one end of the anchor rod is fixedly connected to a connecting ring, a traction rope is fixedly connected to the surface of the connecting ring, one end of the traction rope is fixedly connected to a traction buckle, and the surface of the fluke is slidably connected to the surface of the fixing column.

[0013] Preferably, the sealing mechanism also includes a first limiting ring and a second limiting ring, the surface of the first limiting ring and the surface of the second limiting ring are fixedly connected to the surface of the first blocking column and the surface of the second blocking column respectively, and a plurality of the first limiting rings and the second limiting rings are distributed in a linear array with the axes of the first blocking column and the second blocking column as the center, and the surface of the first limiting ring and the surface of the second limiting ring are slidably connected.

[0014] Preferably, both the first blocking column and the second blocking column are hexagonal columns, and the main body is thick at both ends and narrow in the middle, and the surface of the first blocking column and the surface of the second blocking column are both provided with a center hole and a pressure relief hole.

[0015] Preferably, the surface of the first blocking column and the surface of the second blocking column are distributed and fixedly connected with a first slider and a second slider, the surface of the first blocking column and the surface of the second blocking column are respectively provided with a first slide groove and a second slide groove, a plurality of the first sliders and a plurality of the first slide grooves are symmetrically distributed with the axis of the first blocking column as the center, a plurality of the second sliders and a plurality of the second slide grooves are symmetrically distributed with the axis of the second blocking column as the center, the surface of the first slider is slidably connected to the surface of the second slide groove, and the surface of the second slider is slidably connected to the surface of the first slide groove.

[0016] Preferably, both ends of the first blocking column and the second blocking column are fixedly connected with a lifting ring and a pulling ring respectively, the surface of the lifting ring and the surface of the pulling ring are slidably connected with a sliding rope, the surface of the sliding rope is slidably connected to the surface of the traction buckle, and a column is arranged between the first blocking column and the second blocking column, and a plurality of the columns are distributed in a linear array in the axial direction of the first blocking column, and concrete is poured on the outer side of the column.

[0017] Preferably, a method for using a high and low voltage complete set of power distribution cabinets is characterized by comprising the following steps:

[0018] Step 1: Before use, multiple first blocking columns and multiple second blocking columns are connected, and the surfaces of the first blocking columns and the second blocking columns are fixedly connected with the first slider and the second slider, the surfaces of the first blocking columns and the second blocking columns are respectively provided with the first slide groove and the second slide groove, the surface of the first slider is slidably connected to the surface of the second slide groove, the surface of the second slider is slidably connected to the surface of the first slide groove, the surface of the first blocking column and the second blocking column are respectively fixedly connected with the first limiting ring and the second limiting ring, the surface of the first limiting ring and the surface of the second limiting ring are slidably connected, and the surfaces of multiple pull rings and the surfaces of multiple hanging rings are slidably connected to the surface of the slide rope.

[0019] Step 2: The surface of the zip line is slidably connected to the surfaces of multiple traction buckles, and a traction buckle is provided between the two lifting rings. One end of the anchor rod is fixedly connected to a connecting ring, and the surface of the connecting ring is connected to the surface of the traction buckle through a traction rope. The surface of the anchor rod is fixedly connected to a base, and the surface of the base is rotatably connected to the surface of the anchor claw. The surface of the base is fixedly connected to a scissors arm, and the surface of the anchor rod is slidably connected to a connecting plate. The surface of the scissors arm is fixedly connected to the surface of the connecting plate, and the surface of the connecting plate is rotatably connected to a connecting rod, and the surface of the connecting rod is rotatably connected to the surface of the anchor claw. The scissor wall drives the connecting plate to slide along the surface of the anchor rod, and the surface of the connecting plate is rotatably connected to the surface of the anchor claw through the connecting rod. The rotation angle of the anchor claw is adjusted so that the surface of the anchor claw is slidably connected to the surface of the fixed column to limit the position of the fixing mechanism.

[0020] Step three: After the fixing mechanism and the blocking mechanism are connected, the water flow at the dike mouth is blocked. Vertical columns are set in the gaps between the first plurality of blocking columns and the second plurality of blocking columns of the blocking mechanism. Concrete is filled on the outside of the vertical columns to connect the gaps between the first plurality of blocking columns and the second plurality of blocking columns. After the connection is completed, the fixing mechanism is disassembled.

[0021] The beneficial effects of the present invention are:

[0022] By setting a fixing mechanism and a sealing mechanism, multiple first sealing columns and multiple second sealing columns are connected to block the water flow, and the water flows through the central holes opened on the surfaces of the first sealing columns and the second sealing columns, reducing the impact of the water flow on the first sealing columns and the second sealing columns. The fixing mechanism is connected to the traction buckle through a traction rope, and the surfaces of multiple pull rings are slidingly connected to the surfaces of the steel cables, and the surfaces of the steel cables are slidingly connected to the surfaces of multiple traction buckles, which solves the technical problems of the existing plugging project that the construction process is complicated, requires a high level of technology, is difficult to construct, takes a long time, and has a relatively low ability to repair again. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 A schematic diagram of an assembled concrete structure connection device proposed by the present invention;

[0024] Figure 2 A three-dimensional diagram of a connecting rod structure of an assembled concrete structure connecting device proposed by the present invention;

[0025] Figure 3 A front view of a base structure of an assembled concrete structure connection device proposed by the present invention;

[0026] Figure 4 A three-dimensional diagram of the column structure of an assembled concrete structure connection device proposed by the present invention;

[0027] Figure 5 A three-dimensional diagram of the second blocking column structure of an assembled concrete structure connection device proposed by the present invention;

[0028] Figure 6 This is a front view of a pull ring structure of an assembled concrete structure connection device proposed by the present invention.

[0029] In the figure: 1. fixed column; 2. anchor claw; 3. first blocking column; 4. second blocking column; 201. anchor rod; 202. base; 203. scissor arm; 204. connecting plate; 205. connecting rod; 206. connecting ring; 207. traction rope; 208. traction buckle; 401. first limiting ring; 402. second limiting ring; 403. center hole; 404. pressure relief hole; 405. first slider; 406. second slider; 407. first slide groove; 408. second slide groove; 409. lifting ring; 410. pull ring; 411. slide rope; 412. column. DETAILED DESCRIPTION

[0030] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.

[0031] Reference Figure 1-Figure 6 , an assembled concrete structure connection device, comprising a fixing column 1, the surface of which is provided with a fixing mechanism and a blocking mechanism;

[0032] The fixing mechanism is located above the blocking mechanism;

[0033] The fixing mechanism includes an anchor claw 2, and the fixing mechanism realizes the action of the anchor claw 2 fixing the blocking mechanism;

[0034] The blocking mechanism includes a first blocking column 3 and a second blocking column 4, and the blocking mechanism enables the first blocking column 3 and the second blocking column 4 to block a larger gap.

[0035] The blocking mechanism further comprises an anchor rod 201 , the surface of which is fixedly connected to a base 202 , the surface of the base 202 is rotatably connected to the surface of the fluke 2 , and the two flukes 2 are symmetrically distributed around the axis of the base 202 .

[0036] Furthermore, the fluke 2 is rotated on the surface of the base 202 to adjust the opening angle.

[0037] The surface of the base 202 is fixedly connected to a scissor arm 203 , and the two scissor arms 203 are symmetrically distributed around the axis of the base 202 . The surface of the anchor rod 201 is slidably connected to a connecting plate 204 , and the surface of the scissor arm 203 is fixedly connected to the surface of the connecting plate 204 .

[0038] Furthermore, the scissor arm 203 drives the connecting plate 204 to slide along the surface of the anchor rod 201 .

[0039] The surface of the connecting plate 204 is rotatably connected to a connecting rod 205 , and the surface of the connecting rod 205 is rotatably connected to the surface of the fluke 2 . The plurality of flukes 2 are symmetrically distributed with the axis of the connecting plate 204 as the center.

[0040] Furthermore, the connecting rod 205 slides along the surface of the anchor rod 201 to drive the fluke 2 to rotate.

[0041] One end of the anchor rod 201 is fixedly connected to a connecting ring 206 , a traction rope 207 is fixedly connected to the surface of the connecting ring 206 , one end of the traction rope 207 is fixedly connected to a traction buckle 208 , and the surface of the fluke 2 is slidably connected to the surface of the fixing column 1 .

[0042] Furthermore, the surface of the fluke 2 is connected to the surface of the fixing column 1 to fix the position of the anchor rod 201 .

[0043] The sealing mechanism also includes a first limiting ring 401 and a second limiting ring 402. The surface of the first limiting ring 401 and the surface of the second limiting ring 402 are fixedly connected to the surface of the first blocking column 3 and the surface of the second blocking column 4 respectively. A plurality of first limiting rings 401 and second limiting rings 402 are distributed in a linear array with the axes of the first blocking column 3 and the second blocking column 4 as the center respectively. The surface of the first limiting ring 401 and the surface of the second limiting ring 402 are slidably connected.

[0044] Furthermore, the surface of the first limiting ring 401 and the surface of the second limiting ring 402 are slidably connected so that the first blocking column 3 and the second blocking column 4 are neatly arranged.

[0045] The first blocking column 3 and the second blocking column 4 are both hexagonal columns, and the two ends of the main body are thick and the middle is narrow. The surfaces of the first blocking column 3 and the second blocking column 4 are both provided with a center hole 403 and a pressure relief hole 404.

[0046] Furthermore, the rear end of the center hole 403 is reduced to facilitate plugging, and the pressure relief hole 404 reduces the impact pressure of the water flow.

[0047] The surface of the first blocking column 3 and the surface of the second blocking column 4 are fixedly connected with the first slider 405 and the second slider 406. The surface of the first blocking column 3 and the surface of the second blocking column 4 are respectively provided with a first slide groove 407 and a second slide groove 408. A plurality of first sliders 405 and a plurality of first slide grooves 407 are symmetrically distributed with the axis of the first blocking column 3 as the center, and a plurality of second sliders 406 and a plurality of second slide grooves 408 are symmetrically distributed with the axis of the second blocking column 4 as the center. The surface of the first slider 405 is slidably connected to the surface of the second slide groove 408, and the surface of the second slider 406 is slidably connected to the surface of the first slide groove 407.

[0048] Furthermore, a plurality of first blocking columns 3 and a plurality of second blocking columns 4 are connected, a surface of the first slider 405 is slidably connected to a surface of the second slide groove 408 , and a surface of the second slider 406 is slidably connected to a surface of the first slide groove 407 .

[0049] The two ends of the first blocking column 3 and the second blocking column 4 are respectively fixedly connected with a lifting ring 409 and a pulling ring 410, the surface of the lifting ring 409 and the surface of the pulling ring 410 are both slidably connected with a sliding rope 411, the surface of the sliding rope 411 is slidably connected to the surface of the traction buckle 208, and a column 412 is arranged between the first blocking column 3 and the second blocking column 4, and a plurality of columns 412 are distributed in a linear array in the axial direction of the first blocking column 3, and concrete is poured on the outer side of the column 412.

[0050] Furthermore, the plurality of first blocking columns 3 and the plurality of second blocking columns 4 are placed in the blocking positions through the sliding connection of the surface of the hanging ring 409 , the surface of the pulling ring 410 , and the sliding rope 411 .

[0051] A method for using a high and low voltage complete set of power distribution cabinets, characterized in that it comprises the following steps:

[0052] Step 1: Before use, multiple first blocking columns 3 and multiple second blocking columns 4 are connected, and the surfaces of the first blocking columns 3 and the second blocking columns 4 are distributed and fixedly connected with the first slider 405 and the second slider 406. The surfaces of the first blocking columns 3 and the second blocking columns 4 are respectively provided with a first slide groove 407 and a second slide groove 408. The surface of the first slider 405 is slidably connected to the surface of the second slide groove 408, and the surface of the second slider 406 is slidably connected to the surface of the first slide groove 407. The surfaces of the first blocking columns 3 and the second blocking columns 4 are respectively fixedly connected with the first limiting ring 401 and the second limiting ring 402. The surfaces of the first limiting ring 401 and the second limiting ring 402 are slidably connected. The surfaces of the multiple pull rings 410 and the surfaces of the multiple hanging rings 409 are all slidably connected to the surface of the slide rope 411.

[0053] Step 2: The surface of the zip line 411 is slidably connected to the surfaces of multiple traction buckles 208, and a traction buckle 208 is provided between the two lifting rings 409. One end of the anchor rod 201 is fixedly connected to a connecting ring 206, and the surface of the connecting ring 206 is connected to the surface of the traction buckle 208 through a traction rope 207. The surface of the anchor rod 201 is fixedly connected to the base 202, and the surface of the base 202 is rotatably connected to the surface of the fluke 2. The surface of the base 202 is fixedly connected to the scissor arm 203, and the surface of the anchor rod 201 is slidably connected to the connecting plate 204, and the surface of the scissor arm 203 is fixedly connected to the surface of the connecting plate 204. The surface of the connecting plate 204 is rotatably connected to the connecting rod 205, and the surface of the connecting rod 205 is rotatably connected to the surface of the fluke 2. The scissor wall drives the connecting plate 204 to slide along the surface of the anchor rod 201, and the surface of the connecting plate 204 is rotatably connected to the surface of the fluke 2 through the connecting rod 205. The rotation angle of the fluke 2 is adjusted so that the surface of the fluke 2 is slidably connected to the surface of the fixing column 1 to limit the position of the fixing mechanism.

[0054] Step three: After the fixing mechanism and the sealing mechanism are connected, the water flow at the embankment mouth is blocked. A column 412 is set in the gap between the multiple first blocking columns 3 and the multiple second blocking columns 4 of the sealing mechanism. Concrete is filled into the outer side of the column 412 to connect the gap between the multiple first blocking columns 3 and the multiple second blocking columns 4. After the connection is completed, the fixing mechanism is disassembled.

[0055] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.

Claims

1. An assembled concrete structure connection device, comprising a fixing column (1), characterized in that: The surface of the fixing column (1) is respectively provided with a fixing mechanism and a blocking mechanism; The fixing mechanism is located above the blocking mechanism; The fixing mechanism comprises an anchor claw (2), and the fixing mechanism realizes the action of the anchor claw (2) fixing the blocking mechanism; The blocking mechanism comprises a first blocking column (3) and a second blocking column (4), and the blocking mechanism enables the first blocking column (3) and the second blocking column (4) to block a relatively large gap.

2. The assembled concrete structure connection device according to claim 1, characterized in that: The blocking mechanism further comprises an anchor rod (201), the surface of the anchor rod (201) being fixedly connected to a base (202), the surface of the base (202) being rotatably connected to the surface of the anchor claws (2), and the two anchor claws (2) being symmetrically distributed with the axis of the base (202) as the center.

3. The assembled concrete structure connection device according to claim 2, characterized in that: The surface of the base (202) is fixedly connected to a scissor arm (203), and the two scissor arms (203) are symmetrically distributed with the axis of the base (202) as the center. The surface of the anchor rod (201) is slidably connected to a connecting plate (204), and the surface of the scissor arm (203) is fixedly connected to the surface of the connecting plate (204).

4. The assembled concrete structure connection device according to claim 3, characterized in that: The surface of the connecting plate (204) is rotatably connected to a connecting rod (205), the surface of the connecting rod (205) is rotatably connected to the surface of the fluke (2), and a plurality of flukes (2) are symmetrically distributed with the axis of the connecting plate (204) as the center.

5. The assembled concrete structure connection device according to claim 1, characterized in that: One end of the anchor rod (201) is fixedly connected to a connecting ring (206), a traction rope (207) is fixedly connected to the surface of the connecting ring (206), one end of the traction rope (207) is fixedly connected to a traction buckle (208), and the surface of the fluke (2) is slidably connected to the surface of the fixing column (1).

6. The assembled concrete structure connection device according to claim 1, characterized in that: The sealing mechanism also includes a first limiting ring (401) and a second limiting ring (402), the surface of the first limiting ring (401) and the surface of the second limiting ring (402) are respectively fixedly connected to the surface of the first blocking column (3) and the surface of the second blocking column (4), a plurality of the first limiting rings (401) and the second limiting rings (402) are respectively distributed in a linear array with the axes of the first blocking column (3) and the second blocking column (4) as the center, and the surface of the first limiting ring (401) and the surface of the second limiting ring (402) are slidably connected.

7. The assembled concrete structure connection device according to claim 1, characterized in that: The first blocking column (3) and the second blocking column (4) are both hexagonal columns with thick ends and narrow middle. The surfaces of the first blocking column (3) and the second blocking column (4) are both provided with a center hole (403) and a pressure relief hole (404).

8. The assembled concrete structure connection device according to claim 1, characterized in that: The surface of the first blocking column (3) and the surface of the second blocking column (4) are fixedly connected with a first slider (405) and a second slider (406); the surface of the first blocking column (3) and the surface of the second blocking column (4) are respectively provided with a first slide groove (407) and a second slide groove (408); a plurality of the first sliders (405) and a plurality of the first slide grooves (407) are symmetrically distributed with the axis of the first blocking column (3) as the center; a plurality of the second sliders (406) and a plurality of the second slide grooves (408) are symmetrically distributed with the axis of the second blocking column (4) as the center; the surface of the first slider (405) is slidably connected to the surface of the second slide groove (408); the surface of the second slider (406) is slidably connected to the surface of the first slide groove (407).

9. The assembled concrete structure connection device according to claim 5, characterized in that: The two ends of the first blocking column (3) and the second blocking column (4) are respectively fixedly connected with a lifting ring (409) and a pulling ring (410), and the surfaces of the lifting ring (409) and the pulling ring (410) are both slidably connected with a sliding rope (411), and the surface of the sliding rope (411) is slidably connected to the surface of the traction buckle (208). A column (412) is arranged between the first blocking column (3) and the second blocking column (4), and a plurality of the columns (412) are distributed in a linear array in the axial direction of the first blocking column (3), and concrete is poured on the outer side of the column (412).

10. An assembled concrete structure connection device and connection method according to any one of claims 1 to 9, characterized in that: The following steps are involved: Step 1: Before use, a plurality of first blocking columns (3) and a plurality of second blocking columns (4) are connected, and the surface of the first blocking column (3) and the surface of the second blocking column (4) are fixedly connected with a first slider (405) and a second slider (406), and the surface of the first blocking column (3) and the surface of the second blocking column (4) are respectively provided with a first slide groove (407) and a second slide groove (408), and the surface of the first slider (405) is slidably connected to the surface of the second slide groove (408), and the surface of the second slider (406) is slidably connected to the surface of the first slide groove (407), and the surface of the first blocking column (3) and the surface of the second blocking column (4) are respectively fixedly connected with a first limiting ring (401) and a second limiting ring (402), and the surface of the first limiting ring (401) and the surface of the second limiting ring (402) are slidably connected, and the surfaces of the plurality of pull rings (410) and the surfaces of the plurality of hanging rings (409) are slidably connected to the surface of the sliding rope (411); Step 2: The surface of the zip line (411) is slidably connected to the surfaces of the plurality of traction buckles (208), a traction buckle (208) is provided between the two lifting rings (409), one end of the anchor rod (201) is fixedly connected to the connecting ring (206), the surface of the connecting ring (206) is connected to the surface of the traction buckle (208) through the traction rope (207), the surface of the anchor rod (201) is fixedly connected to the base (202), the surface of the base (202) is rotatably connected to the surface of the anchor claw (2), the surface of the base (202) is fixedly connected to the scissor arm (203), the surface of the anchor rod (201) The surface is slidably connected with a connecting plate (204), the surface of the scissor arm (203) is fixedly connected to the surface of the connecting plate (204), the surface of the connecting plate (204) is rotatably connected with a connecting rod (205), the surface of the connecting rod (205) is rotatably connected to the surface of the anchor claw (2), the scissor wall drives the connecting plate (204) to slide along the surface of the anchor rod (201), the surface of the connecting plate (204) is rotatably connected to the surface of the anchor claw (2) through the connecting rod (205), the rotation angle of the anchor claw (2) is adjusted, the surface of the anchor claw (2) is slidably connected to the surface of the fixing column (1), and the position of the fixing mechanism is limited; Step three: After the fixing mechanism and the blocking mechanism are connected, the water flow at the dike mouth is blocked. A column (412) is set in the gap between the first blocking columns (3) and the second blocking columns (4) of the blocking mechanism. Concrete is filled into the outer side of the column (412) to connect the gap between the first blocking columns (3) and the second blocking columns (4). After the connection is completed, the fixing mechanism is disassembled.

Citation Information

Patent Citations

  • Rapid dike leaking stoppage equipment

    CN105714740A

  • Rapid blocking device for embankment breach

    CN107142898A

  • High stable device of blocking up

    CN207775821U

  • Quick blocking device for dike breach in hydraulic engineering construction

    CN208981277U

  • Dam prefabricated part convenient to install

    CN215948075U