Construction method of CFG pile composite foundation mattress layer

Through the construction method of flexible composite mattress cushion, fluid solidified soil and geosteel-plastic grille are used to solve the problems of water seepage and pile top piercing of traditional gravel mattresses, and the bearing capacity and structural stability of the composite foundation are improved. , reducing pollution and resource consumption.

CN119083405APending Publication Date: 2024-12-06SHENZHEN HONGYEJI GEOTECHNICAL TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411195084.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-29
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

There are pore channels that penetrate up and down in the traditional gravel mattress, which leads to groundwater seepage and generates buoyancy that threatens structural safety. The material lacks flexibility, resulting in piercing of pile tops and failure of the structure.

Method used

The flexible composite mattress cushion method is adopted, and the fluid solidified soil and geosteel-plastic grille are used to strengthen the structure through concrete pile caps and steel mesh to avoid seepage and puncture of pile tops, and improve load-bearing capacity.

Benefits of technology

It effectively avoids buoyancy damage to the foundation, reduces the risk of piercing on the pile top, improves the bearing capacity and structural stability of the composite foundation, and reduces pollution and resource consumption.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083405A_ABST
    Figure CN119083405A_ABST
Patent Text Reader

Abstract

The invention provides a construction method of a CFG pile composite foundation mattress layer, and relates to the technical field of building construction.The construction method of the CFG pile composite foundation mattress layer comprises the steps that each CFG pile cap construction area is excavated to a certain range below the elevation position of the bottom of a CFG pile cap according to the pile cap excavation range; concrete is poured into the construction area of the CFG pile cap to the elevation position of the bottom of the CFG pile cap, and a pile cap cushion layer is formed after the concrete is hardened; the geotechnical steel-plastic grating is laid within the depth range of the area where the flexible composite mattress layer is constructed, flow-state solidified soil prepared in advance is poured into the area where the flexible composite mattress layer is constructed, and the flow-state solidified soil is formed by mixing and stirring a rock-soil solidifying agent and engineering muck mud according to a certain proportion. Compared with the prior art, the construction method of the CFG pile composite foundation mattress layer has the advantages that the original pressure bearing effect of the composite foundation is not changed, and meanwhile, the composite foundation has certain anti-seepage and anti-floating effects.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a construction method for a CFG pile composite foundation cushion layer. Background Art

[0002] In the design and construction of the podium foundation of a high-rise building where the soil condition is poor and the construction period and construction cost are taken into consideration, a combination of shallow foundation + composite foundation is often selected. In order to ensure that the load of the superstructure is smoothly transferred to the composite foundation soil layer through the foundation, a cushion layer structure needs to be set between the superstructure foundation and the composite foundation soil layer. Therefore, the cushion layer structure is also a bridge for the interaction between the foundation and the foundation soil layer. It has the function of bearing the vertical pressure transmitted from the shallow foundation, improving the stress condition of the reinforcement body (CFG pile) in the composite foundation, coordinating the load distribution of the reinforcement body and the soil body in the composite foundation, and truly making all parts of the foundation bear stress together, thereby improving the bearing capacity of the foundation and reducing the foundation settlement. Therefore, the construction of the cushion layer is an indispensable link in the process of forming a composite foundation.

[0003] At present, combined with Figure 5 As shown in the figure, in the podium building designed with shallow foundation + composite foundation, the basement bottom is basically a traditional gravel cushion structure composed of loose materials such as sand and stone. During construction, due to the structural characteristics of the sand and stone materials themselves, even after multiple mechanical rolling to reach the designed density, there are still inevitably pore channels b that penetrate up and down in the gravel cushion structure a. When the upper structure begins to be put into use, due to the effect of pore water pressure, groundwater c will penetrate into the gravel cushion along the through pore channel b. As time goes by, when the groundwater that penetrates into the gravel cushion structure a is connected with the surrounding groundwater, a large amount of buoyancy will be generated at the base, seriously threatening the safety of the podium structure.

[0004] At the same time, in order to adapt to the development needs of urban modernization, the functions of podium buildings have gradually become richer and more diverse. During the use of the conventional cushion layer constructed of sand and stone materials, due to the lack of adhesion between the sand and stone, the vertical reinforcement (CFG pile) in the composite foundation below will penetrate into the cushion layer under the action of the upper load, causing the cushion layer structure to fail, seriously affecting the bearing function of the composite foundation and causing the foundation settlement to increase, thus endangering the normal use and safety of the structure.

[0005] On the other hand, the raw materials such as gravel and sand used in traditional cushion layers need to go through mining and secondary processing before they can be used in construction. During the production process, pollutants such as dust, wastewater and exhaust gas lead to excessive consumption of natural resources and serious damage to the ecological environment. In addition, when mining raw materials such as sand and gravel, the surface vegetation may be destroyed, exacerbating soil erosion. At the same time, since the sand and stone used in the traditional cushion layer structure are loose materials, they need to be spread on site first and rolled into shape according to the density required by the design. Therefore, more construction machinery is required and the construction efficiency is low. Summary of the invention

[0006] The problem to be solved by the present invention is: how to solve the problem that there are currently vertically connected channels in the crushed stone cushion layer, groundwater easily seeps and gathers around the base to generate a large amount of buoyancy, endangering the safety and stability of the podium foundation, and the loose material constituting the crushed stone cushion layer lacks a certain degree of flexibility, which makes it easy for the pile top to penetrate too much and cause the cushion structure to fail.

[0007] The present invention provides a construction method of a CFG pile composite foundation cushion layer, comprising:

[0008] After the construction of CFG piles in the composite foundation is completed, excavation is carried out on the surface of the area where the flexible composite cushion layer is to be constructed to the bottom elevation of the flexible composite cushion layer structure;

[0009] Determine the pile cut-off line and pile cap excavation range of each CFG pile;

[0010] According to the pile cap excavation range, excavate each CFG pile cap construction area to a certain range below the bottom elevation of the CFG pile cap, cut off the CFG pile head according to the pile cutting line, grind it flat, and then clean, level and compact each CFG pile cap construction area;

[0011] Pouring concrete into the CFG pile cap construction area to the bottom elevation of the CFG pile cap, and forming a pile cap cushion after hardening;

[0012] Placing a bidirectional steel mesh on the top surface of the CFG pile, and filling the CFG pile cap construction area with concrete to form the CFG pile cap;

[0013] Laying the geotechnical steel-plastic grid within the depth range of the flexible composite cushion layer area, and pouring the pre-prepared fluidized solidified soil into the flexible composite cushion layer area, wherein the fluidized solidified soil is formed by mixing and stirring a rock and soil curing agent and engineering slag mud in a certain proportion;

[0014] The fluidized solidified soil is watered and maintained until the fluidized solidified soil solidifies and reaches a desired strength.

[0015] Compared with the prior art, the construction method of the CFG pile composite foundation cushion layer of the present invention has the following innovations and foreseeable benefits:

[0016] (1) The flexible composite cushion structure is cast by fluidized solidified soil, wherein the fluidized solidified soil is mixed and stirred by rock and soil curing agent and engineering waste mud in a certain proportion. Compared with the traditional cushion layer constructed by loose materials such as sand and stone, the dense fluidized solidified soil replaces the gravel with a large number of voids, thus avoiding the buoyancy damage to the foundation caused by the water accumulation in the voids and the connection with the surrounding seepage channels;

[0017] (2) The main raw material of fluidized solidified soil is the excavated soil from the construction site. The production process is to turn the waste soil into treasure and reuse it as a resource, thus solving the problem of environmental pollution caused by the inability to dispose of the waste soil after it is transported out;

[0018] (3) In order to reduce the stress concentration at the top of the CFG pile, a pile cap structure is configured at the top of the CFG pile, which effectively disperses the stress transmitted from the upper structure load to the pile top and avoids the situation where the reinforcement (CFG pile) penetrates and causes the cushion layer structure to be damaged;

[0019] (4) Geotechnical steel-plastic grids with significant tensile strength are also added to the cushion structure, and are closely combined with the fluidized solidified soil. This makes the composite cushion layer have a larger flexible displacement space when subjected to upper loads compared to the gravel cushion layer, thus reducing the possibility of vertical penetration of the reinforcement (CFG pile) in the composite foundation, leading to structural failure.

[0020] (5) After solidification, the strength and stiffness of fluidized solidified soil are between those of low-grade concrete and untreated original soil. While having certain compressive strength and bearing capacity, it also has good deformation coordination effect.

[0021] Optionally, before excavating the ground surface of the flexible composite cushion layer area to the bottom elevation of the flexible composite cushion layer structure, the construction method of the CFG pile composite foundation cushion layer further includes:

[0022] According to the strength design requirements of the flexible composite mattress layer structure, the mix ratio of the fluidized solidified soil is designed;

[0023] Verify through indoor tests to determine the mix ratio of the fluidized solidified soil that meets the design requirements;

[0024] The fluidized solidified soil is prepared according to the mix ratio that meets the design requirements.

[0025] Optionally, preparing the fluidized solidified soil according to the mix ratio that meets the design requirements includes:

[0026] Pour the prepared mud into a mixing bucket, and then add the rock and soil solidifying agent into the mud according to the mixing ratio;

[0027] The specific gravity and fluidity of the fluidized solidified soil are measured while stirring in the stirring barrel until the design requirements are met.

[0028] Optionally, the geotechnical solidifying agent is a mixture of an inorganic non-metallic material and a water reducing agent, wherein the inorganic non-metallic material accounts for 99% to 99.5% and the water reducing agent accounts for 0.5% to 1%.

[0029] Optionally, the inorganic non-metallic material is a mixture of any three or more of cement, mineral powder, gypsum, fly ash and quicklime in different proportions, wherein the cement accounts for 10% to 60%, the mineral powder accounts for 15% to 60%, the gypsum accounts for 5% to 40%, the fly ash accounts for 0 to 25%, and the quicklime accounts for 5% to 30%.

[0030] Optionally, the water reducer is composed of one or more of a lignin sulfonate water reducer, a naphthalene water reducer, a polycarboxylic acid water reducer and an aminosulfonate water reducer.

[0031] Optionally, the plane size of the CFG pile cap construction area is consistent with the outer edge of the CFG pile cap, and the depth of the CFG pile cap construction area is the sum of the thickness of the CFG pile cap and the thickness of the pile cap cushion layer.

[0032] Optionally, the geotechnical steel-plastic grid is composed of high-strength steel wires woven in warp and weft, and high-density polyethylene is wrapped around the high-strength steel wires.

[0033] Optionally, before pouring the pre-prepared fluidized solidified soil into the area where the flexible composite cushion layer is to be constructed, the construction method of the CFG pile composite foundation cushion layer further comprises:

[0034] The theoretical pouring volume of the flexible composite mattress layer structure is calculated, and the ratio of the actual pouring volume to the theoretical pouring volume is greater than or equal to 1.05.

[0035] Optionally, the step of sprinkling water on the fluidized solidified soil until the fluidized solidified soil solidifies and reaches a desired strength includes:

[0036] After the preset pouring time is completed, watering the fluidized solidified soil;

[0037] A film is covered on the surface of the fluidized solidified soil until the fluidized solidified soil solidifies and reaches a desired strength. BRIEF DESCRIPTION OF THE DRAWINGS

[0038] Figure 1It is a flow chart of a construction method of a CFG pile composite foundation cushion layer according to an embodiment of the present invention;

[0039] Figure 2 The structure of the CFG pile composite foundation cushion layer according to the embodiment of the present invention is shown in FIG. Figure 1 ;

[0040] Figure 3 The structure of the CFG pile composite foundation cushion layer according to the embodiment of the present invention is shown in FIG. Figure 2 ;

[0041] Figure 4 It is a plan view of the geotechnical steel-plastic grid according to an embodiment of the present invention;

[0042] Figure 5 Schematic diagram of the structure of a traditional gravel mattress.

[0043] Description of reference numerals:

[0044] 1. Flexible composite cushion structure; 2. Fluidized solidified soil; 3. Geotechnical steel-plastic grid; 4. Podium foundation; 5. CFG piles; 6. CFG pile caps; 7. Area for applying flexible composite cushion; 8. Bottom elevation of CFG pile caps; 9. CFG pile heads (need to be cut off); 10. Bottom elevation of CFG pile cap cushion; 11. CFG pile cap cushion; 12. Remaining cavity in the excavation area of ​​CFG pile caps; 13. Top surface of CFG piles. DETAILED DESCRIPTION

[0045] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, specific embodiments of the present invention are described in detail below with reference to the accompanying drawings.

[0046] In the description of the present invention, the directions or positional relationships indicated by “up”, “down”, “left”, “right”, “top”, “bottom”, “front”, “back”, “inside” and “outside” are based on the directions or positional relationships shown in the accompanying drawings and are only for the convenience of describing the present invention. They do not indicate or imply that the device referred to must have a specific direction, be constructed and operated in a specific direction. Therefore, they should not be understood as limiting the scope of protection of the present invention.

[0047] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0048] In the description of this specification, the description with reference to the terms "embodiment", "one embodiment" and "one implementation" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or implementation are included in at least one embodiment or implementation of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or implementation. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or implementations in a suitable manner.

[0049] Moreover, the Z-axis in the accompanying drawings represents the vertical direction, that is, the up and down position, and the positive direction of the Z-axis (that is, the direction of the arrow of the Z-axis) represents the top, and the negative direction of the Z-axis (that is, the direction opposite to the positive direction of the Z-axis) represents the bottom; the X-axis in the accompanying drawings represents the horizontal direction, that is, the left and right position, and the positive direction of the X-axis (that is, the direction of the arrow of the X-axis) represents the left, and the negative direction of the X-axis (that is, the direction opposite to the positive direction of the X-axis) represents the right; the Y-axis in the accompanying drawings represents the longitudinal direction, that is, the front and back position, and the positive direction of the Y-axis (that is, the direction of the arrow of the Y-axis) represents the front, and the negative direction of the Y-axis (that is, the direction opposite to the positive direction of the Y-axis) represents the back.

[0050] It should also be noted that the aforementioned Z-axis, X-axis and Y-axis are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation of the present invention.

[0051] like Figures 1 to 2 As shown, the construction method of the CFG pile composite foundation cushion layer according to the embodiment of the present invention comprises:

[0052] Step S1, after the construction of the CFG piles 5 in the composite foundation is completed, excavation is carried out on the surface of the flexible composite cushion layer area 7 to the bottom elevation position of the flexible composite cushion layer structure 1;

[0053] Step S2, determining the pile cut line and pile cap excavation range of each CFG pile 5;

[0054] Step S3, excavating each CFG pile cap construction area to a certain range below the CFG pile cap bottom elevation position 8 according to the pile cap excavation range, cutting off the CFG pile head 9 according to the pile cutting line, and cleaning, leveling and compacting each CFG pile cap construction area after grinding and leveling;

[0055] Step S4, pouring concrete into the CFG pile cap construction area to the bottom elevation position 8 of the CFG pile cap, and forming a pile cap cushion layer 11 after the concrete is hardened;

[0056] Step S5, placing a bidirectional steel mesh on the top surface 13 of the CFG pile, and filling the CFG pile cap construction area with concrete to form a CFG pile cap 6;

[0057] Step S6, laying the geotechnical steel-plastic grid 3 within the depth range of the flexible composite cushion layer area 7, and pouring the pre-prepared fluidized solidified soil into the flexible composite cushion layer area 7, wherein the fluidized solidified soil is formed by mixing and stirring a rock and soil curing agent and engineering slag mud in a certain proportion;

[0058] Step S7, watering and curing the fluidized solidified soil until the fluidized solidified soil solidifies and reaches a desired strength.

[0059] In this embodiment, combined with the attached Figure 1 To Attachment Figure 4 As shown, in step S1, after the construction of the CFG pile 5 in the composite foundation is completed, the long spiral drill and other auxiliary construction equipment are removed from the construction area, and the site is cleaned to ensure that the construction area is flat and clean before the construction of the flexible composite cushion layer structure 1, and the measurement and setting out work is done well. After the concrete strength of the CFG pile 5 reaches the design requirements, according to the construction plan, the ground surface of the flexible composite cushion layer structure area 7 is excavated to the bottom elevation of the flexible composite cushion layer structure 1. In step S2, in order to reduce the stress concentration at the top of the CFG pile 5 and protect its structural integrity, after excavating to the bottom elevation of the flexible composite cushion layer structure 1, the pile cut line and the pile cap excavation range are determined according to the plane size and thickness of the CFG pile cap 6 in the construction drawings and the actual over-filling height of each CFG pile 5. In step S3, after excavating the construction area of ​​each CFG pile cap 6 to a certain range below the elevation position 8 of the bottom of the CFG pile cap, use small machinery or manual removal to cut off the CFG pile head 9, and then grind the CFG pile head 9 with a hand grinding wheel to expose the fresh concrete surface, which is the top surface 13 of the CFG pile after the cut pile head is polished and leveled. Then, the excavation surface and side wall of each CFG pile cap 6 construction area are cleaned, leveled and compacted. In step S4, after the excavation surface of the pile cap area is cleaned, leveled and compacted, concrete is poured from the excavation surface position to the elevation position 8 of the bottom of the CFG pile cap. After the concrete hardens, the CFG pile cap cushion layer 11 is formed, which also serves as the bottom mold of the CFG pile cap 7. In step S5, after the concrete strength of the CFG pile cap cushion layer 11 reaches the requirement, the pre-made bidirectional steel mesh is placed on the top surface 13 of the CFG pile (attached Figure 3The CFG pile cap 6 is formed by filling the remaining cavity 12 in the excavation area of ​​the CFG pile cap with concrete that meets the design strength. The concrete is vibrated with a vibrating rod while pouring to ensure that the concrete is dense and free of bubbles. In step S6, after the pile cap construction is completed and maintained until the concrete strength reaches the design requirements, the upper and lower layers of geo-steel-plastic grids 3 are laid and installed within the depth range of the flexible composite cushion layer structure 1. After the geo-steel-plastic grids 3 are installed, the fluidized solidified soil 2 prepared in advance is poured into the flexible composite cushion layer area 7. The fluidized solidified soil 2 should be poured continuously at one time. In step S7, in order to prevent the fluidized solidified soil 2 from losing water and shrinking, resulting in poor anti-seepage effect of the cushion layer, the fluidized solidified soil 2 should be sprinkled with water after the preset pouring time (preferably 6 hours) is completed. After the sprinkling is completed, a film is covered on the surface of the fluidized solidified soil 2 until the fluidized solidified soil 2 solidifies and reaches a strength that can be used for subsequent construction.

[0060] Compared with the prior art, the construction method of the CFG pile composite foundation cushion layer of the present invention has the following innovations and foreseeable benefits:

[0061] (1) The flexible composite cushion structure is cast by fluidized solidified soil, wherein the fluidized solidified soil is mixed and stirred by rock and soil curing agent and engineering waste mud in a certain proportion. Compared with the traditional cushion layer constructed by loose materials such as sand and stone, the dense fluidized solidified soil replaces the gravel with a large number of voids, thus avoiding the buoyancy damage to the foundation caused by the water accumulation in the voids and the connection with the surrounding seepage channels;

[0062] (2) The main raw material of fluidized solidified soil is the excavated soil from the construction site. The production process is to turn the waste soil into treasure and reuse it as a resource, thus solving the problem of environmental pollution caused by the inability to dispose of the waste soil after it is transported out;

[0063] (3) In order to reduce the stress concentration at the top of the CFG pile, a pile cap structure is configured at the top of the CFG pile, which effectively disperses the stress transmitted from the upper structure load to the pile top and avoids the situation where the reinforcement (CFG pile) penetrates and causes the cushion layer structure to be damaged;

[0064] (5) Geotechnical steel-plastic grids with significant tensile strength are also added to the cushion structure, and are closely combined with the fluidized solidified soil. This makes the composite cushion layer have a larger flexible displacement space when subjected to upper loads compared to the gravel cushion layer, thus reducing the possibility of vertical penetration of the reinforcement (CFG pile) in the composite foundation, leading to structural failure.

[0065] (6) After solidification, the strength and stiffness of fluidized solidified soil are between those of low-grade concrete and untreated original soil. While having certain compressive strength and bearing capacity, it also has good deformation coordination effect.

[0066] The construction method of the CFG pile composite foundation cushion layer of the present invention aims to not change the original pressure-bearing function of the composite foundation, but also enable the composite foundation to have certain anti-seepage and anti-floating functions, thereby preventing the podium structure from being damaged due to insufficient anti-floating. At the same time, using engineering excavation debris instead of sand, stone, etc. as the raw material of the cushion layer can effectively solve the problems of over-exploitation, wastewater, waste gas and debris disposal, and save resources and protect the environment.

[0067] Furthermore, before excavating the surface of the flexible composite cushion layer area 7 to the bottom elevation of the flexible composite cushion layer structure 1, the construction method of the CFG pile composite foundation cushion layer also includes:

[0068] According to the strength design requirements of the flexible composite cushion layer structure 1, the mix ratio of the fluidized solidified soil is designed;

[0069] Verify through indoor tests to determine the mix ratio of the fluidized solidified soil that meets the design requirements;

[0070] The fluidized solidified soil is prepared according to the mix ratio that meets the design requirements.

[0071] Furthermore, the preparing the fluidized solidified soil according to the mix ratio that meets the design requirements includes:

[0072] Pour the prepared mud into a mixing bucket, and then add the rock and soil solidifying agent into the mud according to the mixing ratio;

[0073] The specific gravity and fluidity of the fluidized solidified soil are measured while stirring in the stirring barrel until the design requirements are met.

[0074] In this embodiment, the source of the slurry for the fluidized solidified soil can be the excavated soil from the underground engineering site, which is then transported to the fluidized solidified soil production site, and then poured into the sand washing equipment by an excavator, and processed through processes such as sand and soil separation and water washing. Alternatively, the engineering slag excavated on site can be directly sieved to remove particles with a particle size greater than 0.5 mm, and the remaining part can be used as the slurry for making the fluidized solidified soil. Pour the prepared slurry into a mixing barrel, and then add a rock and soil curing agent to the slurry according to a determined mix ratio. While stirring, measure the specific gravity and fluidity of the fluidized solidified soil. When it meets the design requirements, stop stirring. If it does not meet the requirements, continue stirring until it meets the requirements. The shortest mixing time for each plate of fluidized solidified soil should not be less than 2 minutes.

[0075] The flexible composite cushion layer structure 1 of the present invention is cast with fluidized solidified soil 2. The solidification principle is to add a geotechnical solidifying agent to the engineering slag slurry obtained through sand washing or screening process. The active ingredients in the solidifying agent are hydrated to form a variety of hydration products. The hydration products further react chemically with the soil particles in the slurry to form water-hardening and gas-hardening compounds such as silicates and aluminates. As the solidifying agent is continuously hydrated, the moisture between the soil particles gradually decreases, the soil shrinks, and the generated compounds gradually harden and fill the gaps between the soil particles, finally forming a dense, stable structure with a certain strength. Existing research reports have shown that when the dosage of geotechnical solidifier is within the normal range (generally 6% to 25%), its unconfined compressive strength can reach 1 to 5 MPa. However, due to its own high water content, high compression and other characteristics, the unconfined compressive strength of generally untreated shallow soft soil does not exceed 60 kPa. In comparison, the compressive strength and bearing capacity of fluidized solidified soil are significantly improved compared with the original soft soil. The concrete with a strength grade of about C15 (axial compressive strength of standard specimens is 15 MPa) commonly used as the bottom cushion of various reinforced concrete structures in engineering is still better than fluidized solidified soil in compressive strength and bearing capacity. However, considering the role of cushion concrete, construction cost and environmental protection, fluidized solidified soil has broad application prospects instead of low-grade concrete.

[0076] Furthermore, the geotechnical solidifying agent is a mixture of an inorganic non-metallic material and a water reducing agent, wherein the inorganic non-metallic material accounts for 99% to 99.5% and the water reducing agent accounts for 0.5% to 1%.

[0077] Furthermore, the inorganic non-metallic material is a mixture of any three or more of cement, mineral powder, gypsum, fly ash, and quicklime in different proportions, wherein the cement accounts for 10% to 60%, the mineral powder accounts for 15% to 60%, the gypsum accounts for 5% to 40%, the fly ash accounts for 0 to 25%, and the quicklime accounts for 5% to 30%.

[0078] Furthermore, the water reducer is composed of one or more of a lignin sulfonate water reducer, a naphthalene water reducer, a polycarboxylic acid water reducer and an aminosulfonate water reducer.

[0079] Furthermore, the plane size of the CFG pile cap construction area is consistent with the outer edge of the CFG pile cap 6 , and the depth of the CFG pile cap construction area is the sum of the thickness of the CFG pile cap 6 and the thickness of the pile cap cushion layer 11 .

[0080] In this embodiment, combined with the attached Figure 3As shown, the thickness of the pile cap cushion layer 11 is the distance between the CFG pile cap bottom elevation position 8 and the CFG pile cap cushion layer bottom elevation position 10 .

[0081] Furthermore, the geotechnical steel-plastic grid 3 is composed of high-strength steel wires woven in warp and weft, and high-density polyethylene is wrapped around the high-strength steel wires.

[0082] In this embodiment, combined with the attached Figure 4 As shown, the geo-steel-plastic grid 3 is a geosynthetic material, mainly composed of high-strength steel wires woven in warp and weft, and high-density polyethylene is wrapped outside the steel wires. The relevant technical parameters should comply with the relevant provisions of the "Transportation Industry Standard of the People's Republic of China" (JT / T925.1-2014). Among them, the tensile strength of the geo-steel-plastic grid 3 is not less than 30kN in the longitudinal and transverse ultimate tensile strength per linear meter, the width of a single strip is not less than 14mm, the thickness is not less than 2mm, and the longitudinal and transverse net mesh spacing is between 60mm and 180mm.

[0083] Furthermore, before pouring the fluidized solidified soil prepared in advance into the flexible composite cushion layer area 7, the construction method of the CFG pile composite foundation cushion layer also includes:

[0084] The theoretical pouring volume of the flexible composite mattress layer structure 1 is calculated, and the ratio of the actual pouring volume to the theoretical pouring volume is greater than or equal to 1.05.

[0085] Furthermore, the step of sprinkling water on the fluidized solidified soil until the fluidized solidified soil solidifies and reaches a desired strength includes:

[0086] After the preset pouring time is completed, watering the fluidized solidified soil;

[0087] A film is covered on the surface of the fluidized solidified soil until the fluidized solidified soil solidifies and reaches a desired strength.

[0088] In this embodiment, when curing the fluidized solidified soil 2, the fluidized solidified soil 2 should be sprinkled with water first, and then covered with a film. Before covering, the film surface facing the fluidized solidified soil 2 should be sprinkled with water to moisten it. The sealing curing time should be no less than 8 hours. After the fluidized solidified soil 2 solidifies, its strength increases with age and is between 1 and 5 MPa. The permeability coefficient of the fluidized solidified soil 2 after solidification should be less than 2×

[0089] 10 -7 cm / s.

[0090] Furthermore, the plane size of the CFG pile cap 6 is preferably 0.8m×0.8m to 1.0m×1.0m, the thickness is preferably 0.2m to 0.4m, and the pile cap material is reinforced concrete, the strength grade of which is consistent with the pile body strength of the CFG pile 5 and should not be lower than C20.

[0091] Furthermore, the concrete strength grade of the CFG pile cap cushion layer 11 in step S4 should not exceed C15.

[0092] Furthermore, the material of the CFG pile cap 6 in step S5 is reinforced concrete, and its strength grade is consistent with the pile body strength of the CFG pile 5. The CFG pile cap 6 is rigidly connected to the CFG pile 5. The length of the pile top that should be anchored into the pile cap should not exceed 100 mm. A single-layer bidirectional steel mesh is laid on the polished top surface of the pile. The steel bars are HRB400 grade, with a diameter of 8 to 14 mm and a spacing of 10 cm×10 cm to 15 cm×15 cm. A 180° hook is set at the end of the steel bar.

[0093] Furthermore, the geo-steel-plastic grid 3 in step S6 should be laid flat and tightened during laying, without wrinkles, curling or kinking, and its longitudinal overlap length should be 50 to 200 mm, and the transverse overlap length should be 15 to 100 mm. After the lower geo-steel-plastic grid 3 is laid, a horse stool can be set up by using the method of installing and fixing the steel mesh with a concrete slab to lay the upper geo-steel-plastic grid 3; after the upper and lower geo-steel-plastic grids are laid, the fluidized solidified soil 2 should be constructed as soon as possible.

[0094] Furthermore, the pouring method of the fluidized solidified soil 2 in step S6 should be determined according to the actual situation on site. If the pouring distance on site is small, the excavator bucket can be used as a container to pour the fluidized solidified soil 2 into the area to be poured. If the pouring distance on site is large, a concrete delivery pump truck (sky pump) or a concrete ground pump can be used for pouring. If the flow expansion degree of the prepared fluidized solidified soil 2 reaches more than 600 mm or the specific gravity is more than 1.27, the self-leveling characteristics of the fluidized solidified soil 2 can be utilized at this time, and the pouring method of the transport tank truck unloading can be adopted.

[0095] Furthermore, the time from the start of mixing to the completion of pouring of each plate of fluidized solidified soil 2 should not exceed 3 hours.

[0096] Furthermore, in step S6, when the thickness of the flexible composite mattress layer structure 1 exceeds 0.5 m, it should be poured in layers, and the thickness of the first pouring should not exceed 0.5 m.

[0097] Furthermore, in step S6, when pouring the fluidized solidified soil 2, if there is heavy rain or continuous drizzle, the unhardened surface of the filling body should be covered and no new operation section should be opened.

[0098] Although the present invention is disclosed as above, the protection scope of the present invention is not limited thereto. Those skilled in the art may make various changes and modifications without departing from the spirit and scope of the present invention, and these changes and modifications will fall within the protection scope of the present invention.

Claims

1. A construction method for a CFG pile composite foundation cushion layer. It is characterized in that include: After the construction of the CFG piles (5) in the composite foundation is completed, excavation is carried out on the surface of the flexible composite cushion layer area (7) to the bottom elevation of the flexible composite cushion layer structure (1); Determining the pile cut line and pile cap excavation range of each CFG pile (5); According to the pile cap excavation range, excavate each CFG pile cap construction area to a certain range below the CFG pile cap bottom elevation position (8), cut off the CFG pile head (9) according to the pile cutting line, grind it flat, and then clean, level and compact each CFG pile cap construction area; pouring concrete into the CFG pile cap construction area to the bottom elevation of the CFG pile cap (8), and forming a pile cap cushion layer (11) after the concrete is hardened; Placing a bidirectional steel mesh on the top surface (13) of the CFG pile, and filling the CFG pile cap construction area with concrete to form a CFG pile cap (6); The geotechnical steel-plastic grid (3) is laid within the depth range of the flexible composite cushion layer area (7), and the fluidized solidified soil prepared in advance is poured into the flexible composite cushion layer area (7), wherein the fluidized solidified soil is formed by mixing and stirring a rock and soil curing agent and engineering waste mud in a certain proportion; The fluidized solidified soil is watered and maintained until the fluidized solidified soil solidifies and reaches a desired strength.

2. The construction method of the CFG pile composite foundation cushion layer according to claim 1, It is characterized in that Before excavating the ground surface of the flexible composite cushion layer area (7) to the bottom elevation of the flexible composite cushion layer structure (1), the construction method of the CFG pile composite foundation cushion layer also includes: According to the strength design requirements of the flexible composite cushion layer structure (1), the mix ratio of the fluidized solidified soil is designed; Verify through indoor tests to determine the mix ratio of the fluidized solidified soil that meets the design requirements; The fluidized solidified soil is prepared according to the mix ratio that meets the design requirements.

3. The construction method of the CFG pile composite foundation cushion layer according to claim 1, It is characterized in that The step of preparing the fluidized solidified soil according to the mix ratio that meets the design requirements includes: Pour the prepared mud into a mixing bucket, and then add the rock and soil solidifying agent into the mud according to the mixing ratio; The specific gravity and fluidity of the fluidized solidified soil are measured while stirring in the stirring barrel until the design requirements are met.

4. The construction method of the CFG pile composite foundation cushion layer according to claim 1, It is characterized in that The geotechnical solidifying agent is a mixture of an inorganic non-metallic material and a water reducing agent, wherein the inorganic non-metallic material accounts for 99% to 99.5% and the water reducing agent accounts for 0.5% to 1%.

5. The construction method of the CFG pile composite foundation cushion layer according to claim 4, It is characterized in that The inorganic non-metallic material is formed by mixing any three or more of cement, mineral powder, gypsum, fly ash and quicklime in different proportions, wherein the cement accounts for 10% to 60%, the mineral powder accounts for 15% to 60%, the gypsum accounts for 5% to 40%, the fly ash accounts for 0 to 25%, and the quicklime accounts for 5% to 30%.

6. The construction method of the CFG pile composite foundation cushion layer according to claim 4, It is characterized in that The water reducer is composed of one or more of lignin sulfonate water reducer, naphthalene water reducer, polycarboxylic acid water reducer and aminosulfonate water reducer.

7. The construction method of the CFG pile composite foundation cushion layer according to claim 1, It is characterized in that The plane size of the CFG pile cap construction area is consistent with the outer edge of the CFG pile cap (6), and the depth of the CFG pile cap construction area is the sum of the thickness of the CFG pile cap (6) and the thickness of the pile cap cushion layer (11).

8. The construction method of the CFG pile composite foundation cushion layer according to claim 1, It is characterized in that The geotechnical steel-plastic grid (3) is composed of high-strength steel wires woven in warp and weft, and high-density polyethylene is wrapped around the high-strength steel wires.

9. The construction method of the CFG pile composite foundation cushion layer according to claim 1, It is characterized in that Before pouring the fluidized solidified soil prepared in advance into the flexible composite cushion layer area (7), the construction method of the CFG pile composite foundation cushion layer further comprises: The theoretical pouring volume of the flexible composite mattress layer structure (1) is calculated, and the ratio of the actual pouring volume to the theoretical pouring volume is greater than or equal to 1.

05.

10. The construction method of the CFG pile composite foundation cushion layer according to claim 1, It is characterized in that The step of sprinkling water on the fluidized solidified soil until the fluidized solidified soil solidifies and reaches the expected strength includes: After the preset pouring time is completed, watering the fluidized solidified soil; A film is covered on the surface of the fluidized solidified soil until the fluidized solidified soil solidifies and reaches a desired strength.