Pile pulling construction method of hydraulic full-sleeve full-slewing drilling machine

Through the construction method of hydraulic full-sleeved full-rotary drilling rig, the problems of low construction efficiency and great environmental impact of bridge pile foundation removal are solved, and efficient, environmentally friendly and accurate pile foundation removal is achieved, ensuring construction safety and quality.

CN119083433APending Publication Date: 2024-12-06SHENZHEN MUNICIPAL ENG CORP
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202411198432.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-29
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

The existing bridge pile foundation demolition construction methods are inefficient in construction, have a great impact on the surrounding environment, and the construction safety and quality cannot be guaranteed.

Method used

The construction method of hydraulic full-sleeved full-rotary drilling rig is adopted, including construction preparation, pipeline exploration and excavation, pile extraction and pipeline protection, pile positioning and platform laying, drilling rig positioning, sleeve burial and drilling, obstacle removal, and waste piles The steps of lifting, pile hole inspection and backfill are used to drill and cut through hydraulic drive and high-strength cutting heads to ensure verticality and accuracy.

Benefits of technology

It significantly improves the efficiency of pile pulling operations, reduces vibration and noise pollution to the environment, improves the accuracy and safety of construction, ensures the reliability of construction quality, and is suitable for different types of old piles and complex geological conditions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083433A_ABST
    Figure CN119083433A_ABST
Patent Text Reader

Abstract

The embodiment of the invention discloses a pile pulling construction method and device for a hydraulic full-sleeve full-slewing drilling machine, electronic equipment and a storage medium, and relates to the technical field of pile foundation dismantling construction. Comprising the following steps of construction preparation, pipeline exploring and digging, pile pulling pipeline protection, pile position lofting and platform laying, pile pulling drilling machine in-place, sleeve embedding and drilling, obstacle removing, waste pile hoisting away, pile hole checking, pile hole backfilling and sleeve pulling out. The hydraulic full-sleeve full-slewing drilling machine is high in construction speed, is hydraulically driven, is strong in power, and can quickly press a sleeve into a pile body and rotationally cut the sleeve, so that the construction period is greatly shortened; noise is low, noise generated by hydraulic driving is far lower than that generated by a traditional mechanical hammering method, a vibratory hammer method, a drilling machine drilling coring pile pulling method and the like, civilized construction can be achieved, interference to surrounding residents and the environment is reduced, equipment is simple, the site requirement is relatively low, the application range is wide, and the utilization rate and economic benefits of the equipment are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of pile foundation removal construction, and in particular to a pile extraction construction method of a hydraulic full-sleeve full-rotation drilling rig. Background Art

[0002] In the field of bridge engineering, the removal of bridge pile foundations is a critical and complex engineering task. With the acceleration of urbanization and the continuous expansion of transportation networks, the number of old bridge reconstruction, bridge reinforcement and expansion projects is increasing, and the requirements for bridge pile foundation removal technology are also getting higher and higher.

[0003] At present, the demolition construction of bridge pile foundation mainly adopts mechanical hammer method and static pressure method, static pile extraction method, air cap + vibration hammer pile extraction method, etc.

[0004] However, the methods of the prior art have defects to varying degrees in practical applications, which limit their application effects under specific conditions, have low construction efficiency, have a great impact on the surrounding environment, and cannot guarantee construction safety and quality.

[0005] Therefore, there is a need for a hydraulic full-sleeve full-rotation drilling rig pile extraction construction method that is efficient, environmentally friendly, precise, and can improve construction efficiency, reduce the impact on the surrounding environment, and ensure construction safety and quality. Summary of the invention

[0006] The embodiments of the present invention provide a hydraulic full-sleeve full-rotation drilling rig pile extraction construction method to solve the problems of low construction efficiency, great impact on the surrounding environment, and inability to ensure construction safety and quality in the prior art.

[0007] To achieve the above object, the present invention provides a full-rotation casing drilling rig pile extraction construction process, comprising the following steps:

[0008] S1. Construction preparation: Determine the pile position according to the basic information of the old pile, and select the appropriate steel casing and full-rotation drilling rig according to the pile diameter and pile depth of the old pile;

[0009] S2. Pipeline exploration: Manually excavate a well-shaped trench in the construction area to find and locate all underground pipelines, record the type, specification, direction and depth of the pipelines, and set up warning signs and cordons;

[0010] S3, protection of pile pulling pipelines: steel plates are laid under the full-rotation drilling rig; the steel plates are 3.0*3.0m in size and 25mm in thickness;

[0011] S4. Stakeout and platform laying: Use the total station to stake out and mark the old pile positions, level the surrounding land, and lay the working platform around the pile positions;

[0012] S5. Put the pile drilling rig in place; use the cross positioning method to lift the base plate to the pile center position, use a crawler crane to lift the full-rotation drilling rig directly above the base plate, and require that the center point of the main fixture of the drilling rig and the center point of the cross positioning be on a vertical line. After the drilling rig is in place, connect the auxiliary equipment to the drilling rig;

[0013] S6, casing burying and drilling; start the hydraulic pump station, gradually adjust the engine speed from low speed to high speed, adjust the drilling rig rotary hydraulic motor to 0 position, start the clamping cylinder button, and start the rotary drive system after confirming that the casing is clamped. After ensuring the verticality of the drilling rig, start the formal drilling. In the initial stage, control the drilling rig speed and rotation torque to ensure the stability of the equipment and the verticality of drilling;

[0014] S7. Obstacle removal: After the old pile is completely removed, the soil, rock, steel bars, concrete and other obstacles around the old pile are cut and separated by the high-strength cutter head installed at the head of the steel casing.

[0015] S8. Lifting away the waste pile: Use a grab bucket, crawler crane or manually tie up the pile head to lift away the old pile body after separation;

[0016] S9. Check the pile hole: Check whether there is any residue in the pile hole and ensure that the hole is clean;

[0017] S10, backfilling the pile hole and removing the casing; after the pile hole inspection is qualified, the pile hole is backfilled and the steel casing is removed.

[0018] Furthermore, in step S2, slope excavation is adopted with a slope gradient of 1:0.5, a trench width of 2m, a base width of 0.8m, an excavation depth of 1.5m below the original ground surface, and the earth at the excavated site is piled 3m away from the edge of the trench. The height of the earth pile shall not exceed 1.5m, and it is strictly prohibited to pile materials and heavy objects along the edge of the trench.

[0019] Furthermore, in step S3, the steel plate specification is 3.0*3.0m and the thickness is 25mm.

[0020] Furthermore, in step S4, the positions of the old piles are staked out and marked using a total station.

[0021] Furthermore, in step S5, the reaction weights in the auxiliary equipment should be placed symmetrically, and the end of the reaction fork in the auxiliary equipment away from the full-revolving drilling rig should be fixed with a crawler crane or a crawler track of an excavator.

[0022] Further, in step S6, the drilling rig rotary hydraulic motor is adjusted to the 0 position and then the clamping cylinder button is started.

[0023] Furthermore, in step S6, each section of casing is placed in a pipe clamping device, the pipe clamping hydraulic cylinder is retracted, and the verticality accuracy of the casing is adjusted to a required range using the drilling rig and the guide correction device. During the drilling process, the verticality of the casing is checked using the equipment's own horizontal monitoring system, and a theodolite is set up in two vertical directions of the casing three times per hole to perform verticality verification control. After each section of casing is connected and the verticality is checked, the casing is rotated by no less than 360° through the rotating device of the full-rotation drilling rig to reduce the frictional resistance between the casing and the soil, and then the blade teeth at the end of the casing are used to cut the soil or obstacles, pressed into the soil, and normal operation begins.

[0024] Furthermore, in step S7, there are four obstacle removal methods, including:

[0025] The first method: according to the torque force of the casing, the obstacle pile is twisted off, and then it is grabbed out with a grab bucket or lifted out with a crane using a rope below. For obstacle piles that are difficult to twist off, a wedge block is lowered to assist in twisting off the pile body;

[0026] The second method: using an impact hammer and a spiral drill to impact and break the obstacle pile;

[0027] The third method: pull out and straighten the twisted steel bars and then grab them;

[0028] Fourth type: The inner teeth of the casing cut through the concrete slab, making it easier to grab obstacles.

[0029] Furthermore, in step S8, a wedge hammer is used to embed into the gap between the old pile and the inner wall of the casing, and the old pile is twisted off by transmitting the rotational force of the full-rotation drilling rig through the wedge hammer and lifted and removed in sections, with the maximum section length being 7m.

[0030] Furthermore, in step S9, it is determined whether there are still broken old piles underground based on the length of the old piles pulled out and the hole depth. If there are, the obstacles inside the steel casing are removed by using the grab bucket until all the broken piles at the bottom are removed.

[0031] The present invention has the following beneficial effects:

[0032] 1. The present invention can efficiently remove obstacles such as soil, rock, steel bars, concrete, etc. around the old piles through the downward pressure and rotary torque generated by the full-rotation drilling rig, combined with the cutting action of the steel casing and the cutter head, and significantly improve the efficiency of the pile pulling operation.

[0033] 2. The present invention reduces vibration and noise pollution to the surrounding environment, is beneficial to protecting the construction area and its surrounding environment, and meets the environmental protection requirements of modern construction.

[0034] 3. The present invention improves the accuracy of the construction process and reduces the risk of misoperation and damage to adjacent structures through the precise cutting and separation action of the steel casing and the cutter head, as well as the precise extraction of the old pile body after separation by means of a grab bucket, crawler crane or manual labor.

[0035] 4. The present invention is suitable for pile pulling operations in pile foundation engineering. It is not only suitable for different types of old piles (such as piles with different pile diameters and pile depths), but can also cope with various complex geological conditions (such as soil layers, rock layers, etc.), and has a wide range of applications.

[0036] 5. The present invention ensures the safety of construction, reduces the safety risks caused by pipeline damage or other accidents, and ensures the reliability of construction quality. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in describing the embodiments of the present invention. Obviously, the drawings described below are only some embodiments of the present invention, and those skilled in the art can obtain other drawings based on these drawings without creative work.

[0038] Figure 1 It is a flow chart of a pile pulling construction method of a hydraulic full-sleeve full-rotation drilling rig of the present invention;

[0039] Figure 2 It is a schematic diagram of the specifications of the steel plate in step S3 of the pile pulling construction method of a hydraulic full-sleeve full-rotation drilling rig of the present invention;

[0040] Figure 3 It is a schematic diagram of obstacle removal in step S7 of a hydraulic full-sleeve full-rotation drilling rig pile pulling construction method of the present invention. DETAILED DESCRIPTION

[0041] Embodiments of the present invention are described in detail below, examples of which are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, and cannot be interpreted as limiting the present invention.

[0042] It will be understood by those skilled in the art that, unless expressly stated, the singular forms "one", "said", and "the" used herein may also include plural forms. It should be further understood that the term "comprising" used in the specification of the present disclosure refers to the presence of the features, integers, steps, operations, elements, and / or components, but does not exclude the presence or addition of one or more other features, integers, steps, operations, elements, components, and / or groups thereof. It should be understood that when we refer to an element as being "connected" or "coupled" to another element, it may be directly connected or coupled to the other element, or there may be intermediate elements. In addition, the "connection" or "coupling" used herein may include wireless connection or wireless coupling. The term "and / or" used herein includes all or any unit and all combinations of one or more associated listed items.

[0043] See also Figure 1 The embodiment of the present invention provides a hydraulic full-sleeve full-rotation drilling rig pile extraction construction method, comprising the following steps:

[0044] S1. Construction preparation: Determine the pile position according to the basic information of the old pile, and select the appropriate steel casing and full-rotation drilling rig according to the pile diameter and pile depth of the old pile.

[0045] Specifically, the pile position is determined according to the basic information of the original old pile, and the appropriate steel casing and full-rotation drilling rig are selected with reference to the parameters such as the pile diameter and pile depth of the old pile. In this embodiment, the old pile diameter is φ400mm, 600mm, 800mm, and the length is about 20m. Combined with the construction experience and the actual situation of this embodiment, a 150-type full-rotation drilling rig is selected to remove the old pile.

[0046] S2. Pipeline exploration: Manually excavate a tic-tac-toe trench in the construction area to find and locate all underground pipelines, record the type, specification, direction and depth of the pipelines, and set up warning signs and cordons.

[0047] Specifically, in order to prevent the situation where the actual existing pipelines are not marked in the drawings and the pipeline positions marked in the drawings are inconsistent or accurate, manual excavation of a well-shaped trench is used in the well construction area to find and locate all pipelines. The trench is excavated with a slope of 1:0.5, a trench width of 2m, a base width of 0.8m, and an excavation depth of 1.5m below the original ground surface. The earth at the excavation site is piled 3m away from the edge of the trench. The height of the earth pile shall not exceed 1.5m, and it is strictly prohibited to pile materials and other heavy objects along the edge of the trench.

[0048] In addition, ensure that underground pipelines are not damaged, and deal with unknown underground pipelines in a timely manner. Find out the type, specification, number, direction and depth of the pipelines and make records. Set up warning signs around them and use cordon lines to enclose and protect them. All underground pipelines found will be cleared and exposed to the ground. Find out the pipeline paths and buried depths. Do not miss or make the wrong excavation. Put up warning signs next to the excavated cables, and temporarily cover them with bricks, sand, etc. for protection. Report to the owner's relevant departments and rights-holding units in a timely manner for confirmation. Determine a protection plan for protection, and urge timely relocation.

[0049] S3, protection of pile extraction pipelines; steel plates are laid under the full-rotation drilling rig; the steel plates are 3.0*3.0m in size and 25mm in thickness.

[0050] Specifically, a steel plate is placed under the rotary equipment to disperse the pile pulling stress and reduce the pressure of the equipment on the pipeline during the pile pulling process. Figure 2 As shown, the steel plate specification is 3.0*3.0m and the thickness is 25mm.

[0051] S4. Pile position marking and platform laying: Use the total station to mark and stake out the old pile positions, level the surrounding land, and lay the working platform around the pile positions.

[0052] Specifically, according to the survey control network that has been set up on site, the positions of the old piles are marked with obvious objects using a total station; or the pile heads are directly exposed using an excavator to determine the center of the pile position. After the center of the pile position is confirmed, the surrounding land is leveled and a working platform is laid at the construction pile position to reduce the pressure at the center of the drilling rig and prevent the drilling rig from sinking or the ground from collapsing due to weak foundation.

[0053] S5. Put the pile drilling rig in place; use the cross positioning method to lift the base plate to the pile center position, use a crawler crane to lift the full-rotation drilling rig directly above the base plate, and require that the center point of the main fixture of the drilling rig and the center point of the cross positioning be on a vertical line. After the drilling rig is in place, connect the auxiliary equipment to the drilling rig.

[0054] Specifically, after the working platform is laid, the drilling rig equipment is put into place. First, the base plate is hoisted to the pile center position using the cross positioning method, and then the full-rotation drilling rig is hoisted directly above the base plate with a crawler crane. The center position point of the drilling rig main fixture and the center point of the cross positioning are required to be on a vertical line. After the drilling rig is in place, auxiliary equipment such as reaction forks, reaction frames, and counterweights are connected to the drilling rig.

[0055] Furthermore, the positioning steel plate is placed. The positioning steel plate must be placed flat, and the center of the hole of the positioning steel plate must accurately coincide with the center of the hole to be cleared. The four positioning base points of the positioning steel plate must all be in the center of the roadbed plate. The center of the hole of the positioning steel plate can be determined by two thin lines, and it can be placed to coincide with the pre-measured center of the hole to be cleared. The full-rotation drilling rig is placed, and the four legs of the drilling rig are all placed in the four base points of the positioning steel plate. After it is placed in place, the verticality of the drilling rig can be determined by the vertical monitoring system or theodolite of the drilling rig, and the drilling rig can be placed horizontally by adjusting the four leg cylinders. The hydraulic pump station is in place and connected to the hydraulic system of the drilling rig. The equipment is checked and debugged. And ensure that all systems are working properly (before starting, it is necessary to ensure that all systems of the pump station are working well, including oil, coolant, oil pipe connections, valves, etc.); install the counterweight frame and reaction counterweight of the full-revolving drilling rig, and pay attention to the symmetrical placement of the reaction counterweight; install the reaction fork. After the reaction fork is installed, the end of the reaction fork away from the full-revolving drilling rig is fixed with a crawler crane or the crawler of an excavator to prevent the reaction force generated by the drilling rig when it is loaded and rotating and cutting, causing the main body of the drilling rig to rotate; connect the drill bit (2m long) with the tool installed and a section of 6m or 3m sleeve, and then install it in the drilling rig; after the full-revolving drilling rig is in place, start the casing burying and drilling operations, and select a suitable crane according to the project needs.

[0056] S6. Casing burying and drilling; start the hydraulic pump station, gradually adjust the engine speed from low speed to high speed, adjust the drilling rig rotary hydraulic motor to 0 position, start the clamping cylinder button, and start the rotary drive system after confirming that the casing is clamped. After ensuring the verticality of the drilling rig, formal drilling begins. In the initial stage, control the drilling rig speed and rotation torque to ensure the stability of the equipment and the verticality of drilling.

[0057] Specifically, start the hydraulic pump station, gradually adjust the engine speed from low speed to high speed, adjust the drilling rig's rotary hydraulic motor to 0 position, start the clamping cylinder button, and confirm that the drilling rig's clamping mechanism has clamped the casing before starting the rotary drive system. The rotary motor must be initially started at a low speed. When the rotary resistance is stable and lower than the set value, the speed can be increased appropriately.

[0058] Furthermore, after the test run is normal and the verticality correction is completed, the formal drilling begins. The formal drilling is also at high engine speed, and the full rotary drilling rig has a low speed. When the pressure and torque are stable and have not reached the set value, the speed can be adjusted appropriately and the outrigger cylinder can be retracted for drilling. Generally, within the initial 5 meters, the drilling rig speed is controlled at 3 to 5 rpm, and the rotation torque is stable at about 30% to 50% of the rated maximum torque to ensure the stability of the initial drilling rig equipment and the verticality of drilling.

[0059] It should be noted that the accuracy of each section of casing pressed into the hole during the construction process will directly affect the construction quality of the borehole, especially the accuracy of the upper 5m range is the most important. Each section of casing is placed in the clamping device, the clamping hydraulic cylinder is retracted, and the verticality accuracy of the casing is adjusted to the required range using the drilling rig and the guide correction device. During the drilling process, the verticality of the casing is checked at any time using the equipment's own horizontal monitoring system, and the theodolite is set up in two vertical directions of the casing three times per hole for verticality review and control. After each section of casing is connected and the verticality is checked, the casing is rotated by no less than 360° through the rotary device of the full-rotation drilling rig to reduce the friction resistance between the casing and the soil, and then the blade teeth at the end of the casing are used to cut the soil or obstacles, press into the soil, and start normal operation.

[0060] S7. Obstacle removal: After the old pile is completely removed, the soil, rock, steel bars, concrete and other obstacles around the old pile are cut and separated by the high-strength cutter head installed at the head of the steel casing.

[0061] like Figure 3 As shown, there are mainly the following methods for removing obstacles: the first is to twist off the obstacle pile according to the torque force of the casing, and then grab it out with a grab bucket or lift it out with a crane with a rope below. For obstacle piles that are difficult to twist off, insert a wedge block to assist in twisting off the pile body; the second is to use an impact hammer and a spiral drill bit to impact and crush the obstacle pile; the third is to pull out the straightened and twisted steel bars and then grab them; the fourth is to use the inner teeth of the casing to cut the concrete slab to facilitate the grabbing of obstacles.

[0062] S8. Lift away the waste piles; use a grab bucket, crawler crane or manually tie up the pile heads to lift away the separated old pile bodies.

[0063] Specifically, a wedge hammer is used to embed into the gap between the old pile and the inner wall of the casing. The wedge hammer is used to transmit the rotational force of the full-rotation drill to twist the old pile off and lift it out in sections. The maximum length of the section is 7m. The crane is determined according to the actual needs of the project. The crane arm length is 16m and the maximum working radius is controlled within 8m. A cordon is set when lifting the waste pile. Unauthorized personnel are prohibited from entering. The pile body is processed after being pulled out.

[0064] S9. Pile hole inspection: Check whether there is any residue in the pile hole and ensure that the hole is clean.

[0065] Specifically, determine whether there are still broken old piles underground by measuring the length of the old piles that have been pulled out. Continue to use the grab bucket to remove obstacles inside the steel casing and then take out the broken piles at the bottom. Or, determine whether the pile pulling is complete by measuring the hole depth. After the pile pulling is completed, use an excavator to backfill the pipe with plain soil and pull out the outer casing while backfilling. After the construction is completed, lift the equipment to another pile position to start construction.

[0066] S10, backfilling the pile hole and removing the casing; after the pile hole inspection is qualified, the pile hole is backfilled and the steel casing is removed.

[0067] Specifically, pile hole filling is an important construction link of this project. The quality of pile hole filling will seriously affect the subsequent settlement of the surrounding soil and the subsequent shield crossing construction. After all the piles are removed, the steel casing is pulled out while backfilling the soil. At the same time, a grab bucket is used for impact compaction. When all the steel casing is pulled out, the soil is also filled to the ground at the same time.

[0068] Through the above process, the embodiment of the present invention combines the concepts of high efficiency and environmental protection, and uses the unique process of the full-rotation drilling rig to accurately and quickly remove old bridge piles. This method not only overcomes the limitations of traditional methods, such as low construction efficiency and great environmental impact, but also significantly improves the safety and quality of construction. Its refined operating procedures and advanced equipment selection demonstrate the outstanding achievements of modern engineering technology and are a major advancement in the field of bridge pile foundation removal.

[0069] Compared with the related art, the present invention has the following beneficial effects:

[0070] 1. The present invention is highly efficient and has a fast construction speed: the hydraulic full-sleeve full-rotation drilling rig adopts hydraulic drive and has strong power. It can quickly press the casing into the pile body and rotate and cut it, greatly shortening the construction period; high degree of automation: the equipment is equipped with an automatic horizontal adjustment mechanism and a drill load automatic control mechanism, which can automatically adjust the construction parameters, reduce manual operations, improve construction efficiency, and integrated equipment such as sleeve downward pressure verticality monitoring; strong adaptability: the equipment is simple and can be implemented with a car crane or a crawler crane.

[0071] 2. The present invention is environmentally friendly and has low noise: the noise generated by hydraulic drive is much lower than that of traditional mechanical hammering method, vibratory hammer method, drilling rig coring and pile pulling method, etc., which is conducive to civilized construction and reduces interference with surrounding residents and the environment; small vibration: small mechanical vibration reduces foundation disturbance during construction and reduces the impact on adjacent buildings and underground pipelines; no mud discharge: since no mud lubrication is required during construction, mud discharge and pollution are avoided, which meets modern environmental protection requirements.

[0072] 3. The present invention is safe and has high construction accuracy: the equipment is equipped with an automatic horizontal adjustment mechanism and a wedge-shaped clamping mechanism, which can ensure the vertical accuracy of the casing and reduce deviations and accident risks during construction; reduce disturbance to the foundation: during the insertion and removal of the casing, the disturbance to the foundation is small, which is conducive to maintaining the stability of the foundation.

[0073] 4. The present invention is economical and saves materials: since a casing is inserted into the hole, the hole wall will not collapse when taking soil, the cleaning effect of the loose soil at the bottom of the hole is good, the filling coefficient is small, and the use of backfill materials is saved; the equipment utilization rate is high: the equipment can be selected according to the size of the pile diameter. The hydraulic full-rotation drilling rig model is simple, the site requirements are relatively low, the application range is wide, and the equipment utilization rate and economic benefits are improved.

[0074] It should be understood that, although the steps in the flowchart of the accompanying drawings are displayed in sequence as indicated by the arrows, these steps are not necessarily executed in sequence in the order indicated by the arrows. Unless otherwise specified herein, there is no strict order restriction on the execution of these steps, and they can be executed in other orders. Moreover, at least a part of the steps in the flowchart of the accompanying drawings may include multiple sub-steps or multiple stages, and these sub-steps or stages are not necessarily executed at the same time, but can be executed at different times, and their execution order is not necessarily sequential, but can be executed in turn or alternately with other steps or at least a part of the sub-steps or stages of other steps.

[0075] The above descriptions are only some embodiments of the present invention. It should be pointed out that, for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principles of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.

Claims

1. A hydraulic full-sleeve full-rotation drilling rig pile extraction construction method, characterized in that: The following steps are involved: S1. Construction preparation: Determine the pile position according to the basic information of the old pile, and select the appropriate steel casing and full-rotation drilling rig according to the pile diameter and pile depth of the old pile; S2. Pipeline exploration: Manually excavate a tic-tac-toe trench in the construction area to find and locate all underground pipelines, record the type, specification, direction and depth of the pipelines, and set up warning signs and cordons; S3, protection of pile pulling pipelines; laying steel plates under the full-rotation drilling rig; S4. Stakeout and platform laying: Stake out and mark the old pile positions, level the surrounding land, and lay the working platform around the pile positions; S5. Put the pile drilling rig in place; use the cross positioning method to lift the base plate to the pile center position, use a crawler crane to lift the full-rotation drilling rig directly above the base plate, and require that the center point of the main fixture of the drilling rig and the center point of the cross positioning be on a vertical line. After the drilling rig is in place, connect the auxiliary equipment to the drilling rig; S6, casing embedding and drilling: Start the hydraulic pump station, gradually adjust the engine speed from low speed to high speed, start the clamping cylinder button, confirm that the casing is clamped and start the rotary drive system, ensure the verticality of the drilling rig and start the formal drilling. In the initial stage, control the drilling rig speed and rotation torque to ensure the stability of the equipment and the verticality of drilling; S7, obstacle removal: After the old pile is completely removed, the soil, rock, steel bars, concrete and other obstacles around the old pile are cut and separated by the high-strength cutter head installed on the head of the steel casing; S8. Lifting away the waste pile: Use a grab bucket, crawler crane or manually tie up the pile head to lift away the old pile body after separation; S9. Check the pile hole: Check whether there is any residue in the pile hole and ensure that the hole is clean; S10, backfilling the pile hole and removing the casing; after the pile hole inspection is qualified, the pile hole is backfilled and the steel casing is removed.

2. The method for pile extraction by a hydraulic full-sleeve full-rotation drilling rig as claimed in claim 1, characterized in that: In step S2, slope excavation is adopted with a slope gradient of 1:0.5, a trench width of 2m, a base width of 0.8m, an excavation depth of 1.5m below the original ground surface, and the earth at the excavation site is piled 3m away from the edge of the trench. The height of the earth pile shall not exceed 1.5m, and it is strictly prohibited to pile materials and heavy objects along the trench edge.

3. The method for pile extraction by a hydraulic full-sleeve full-rotation drilling rig as claimed in claim 1, characterized in that: In step S3, the steel plate has a specification of 3.0*3.0m and a thickness of 25mm.

4. The method for pile extraction by a hydraulic full-sleeve full-rotation drilling rig as claimed in claim 1, characterized in that: In step S4, the positions of the old piles are staked out and marked using a total station.

5. The method for pile extraction by a hydraulic full-sleeve full-rotation drilling rig as claimed in claim 1, characterized in that: In step S5, the reaction weights in the auxiliary equipment should be placed symmetrically, and the end of the reaction fork in the auxiliary equipment away from the full-revolving drilling rig should be fixed with a crawler crane or a crawler track of an excavator.

6. The method for pile extraction by a hydraulic full-sleeve full-rotation drilling rig as claimed in claim 1, characterized in that: In step S6, the drilling rig rotary hydraulic motor is adjusted to the 0 position and then the clamping cylinder button is started.

7. The method for pile extraction by a hydraulic full-sleeve full-rotation drilling rig as claimed in claim 1, characterized in that: In step S6, each section of casing is placed in a clamping device, the clamping hydraulic cylinder is retracted, and the verticality accuracy of the casing is adjusted to the required range using the drilling rig and the guide correction device. During the drilling process, the verticality of the casing is checked using the equipment's own horizontal monitoring system, and a theodolite is set up in two vertical directions of the casing three times per hole to check the verticality. After each section of casing is connected and the verticality is checked, the casing is rotated by no less than 360° through the rotary device of the full-rotation drilling rig to reduce the friction resistance between the casing and the soil, and then the blade teeth at the end of the casing are used to cut the soil or obstacles, pressed into the soil, and normal operation begins.

8. The method for pile extraction by a hydraulic full-sleeve full-rotation drilling rig as claimed in claim 1, characterized in that: In step S7, there are four obstacle removal methods, including: The first method: according to the torque force of the casing, the obstacle pile is twisted off, and then it is grabbed out with a grab bucket or lifted out with a crane using a rope below. For obstacle piles that are difficult to twist off, a wedge block is lowered to assist in twisting off the pile body; The second method: using an impact hammer and a spiral drill to impact and break the obstacle pile; The third method: pull out and straighten the twisted steel bars and then grab them; Fourth type: The inner teeth of the casing cut through the concrete slab, making it easier to grab obstacles.

9. The method for pile extraction by a hydraulic full-sleeve full-rotation drilling rig as claimed in claim 1, characterized in that: In step S8, a wedge hammer is used to embed into the gap between the old pile and the inner wall of the casing, and the old pile is twisted off by transmitting the rotational force of the full-rotation drilling rig through the wedge hammer and lifted and removed in sections, with the maximum length of the section being 7m.

10. The method for pile extraction by a hydraulic full-sleeve full-rotation drilling rig as claimed in claim 1, characterized in that: In step S9, it is determined whether there are still broken old piles underground based on the length of the old piles pulled out and the hole depth. If there are, the obstacles inside the steel casing are removed by using the grab bucket until all the broken piles at the bottom are removed.

Citation Information

Cited By

  • Construction method for removing reinforced concrete pipe piles in soft soil stratum

    CN119754291A

  • All-rotation all-casing drilling machine pile pulling and backfilling integrated construction equipment and technology

    CN122190251A