Fabricated concrete frame beam structure and construction method

By adopting prefabricated concrete frame beam structure in industrial buildings, using prefabricated frame beams to erect on existing frame columns and carrying out cast-in-place concrete construction, the problem of large workload and long cycle in the existing technology is solved, and convenience is achieved Improvement of performance and structural strength.

CN119083657AInactive Publication Date: 2024-12-06ZHEJIANG ELECTRIC POWER DESIGN INST
View PDF 13 Cites 0 Cited by

Patent Information

Application Number
CN202411240724.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-05
Publication Date
2024-12-06
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The cast-in-place construction of pure concrete frame structures in industrial buildings leads to a large workload and long cycle of formwork construction, which makes it impossible to achieve the convenience of prefabricated structures.

Method used

Adopt the structure of prefabricated concrete frame beams, including existing frame columns and prefabricated frame beams. The prefabricated frame beams are erected on the existing frame columns, and formwork is installed between the existing frame columns and prefabricated frame beams for cast-in-place concrete construction to reduce the The quantity and workload of formwork support are shortened to shorten the construction cycle.

Benefits of technology

The number of formwork support and workload is greatly reduced, the construction cycle is shortened, and the convenience of prefabricated structure is achieved. The connection strength between prefabricated frame beams and existing frame columns is increased through the concrete of the rear cast beams, ensuring the overall structure. Stability and strength.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083657A_ABST
    Figure CN119083657A_ABST
Patent Text Reader

Abstract

The invention discloses a fabricated concrete frame beam structure and a construction method, and aims to overcome the defects that a large number of pure concrete frame structures exist in industrial buildings, cast-in-place concrete construction is generally adopted, the formwork construction workload is large, and the construction period is long. The structure comprises existing frame columns and prefabricated frame beams, the prefabricated frame beams are erected on the existing frame columns, cast-in-place concrete is arranged at the upper ends of the existing frame columns, and the prefabricated frame beams and the existing frame columns are poured into a whole through the cast-in-place concrete. According to the fabricated concrete frame beam structure, the number of the formwork supports is greatly reduced, the workload of the formwork supports is reduced, the construction period is shortened, and the purpose that the fabricated structure is convenient to construct is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of industrial buildings, and more specifically, to an assembled concrete frame beam structure and a construction method. Background Art

[0002] Common prefabricated structures of public and civil buildings are usually prefabricated structures of floor slabs, while the primary and secondary beam frames still need to be cast in situ, which cannot achieve the goal of convenient construction required by prefabricated structures. At present, there are a large number of pure concrete frame structures in industrial buildings, which are usually constructed with cast-in-situ concrete, which has the disadvantages of large formwork construction workload and long construction period. Summary of the invention

[0003] In order to overcome the above-mentioned shortcomings, the present invention provides an assembled concrete frame beam structure and a construction method, which greatly reduces the number of formwork supports, reduces the workload of formwork supports, shortens the construction period, and achieves the goal of convenient construction of assembled structures.

[0004] In order to solve the above technical problems, the present invention adopts the following technical solutions: an assembled concrete frame beam structure, comprising existing frame columns and prefabricated frame beams, the prefabricated frame beams are erected on the existing frame columns, cast-in-place concrete is arranged on the upper ends of the existing frame columns, and the cast-in-place concrete casts the prefabricated frame beams and the existing frame columns into a whole.

[0005] The assembled concrete frame beam structure includes existing frame columns, prefabricated frame beams, and cast-in-place concrete. The prefabricated frame beams can be erected and constructed, so they can be prefabricated in advance. During the entire concrete frame beam construction process, the number of template supports can be reduced, thereby reducing the workload of template support, which is conducive to shortening the construction period. During construction, after the existing frame columns are cast, the prefabricated frame beams are overlapped to the upper end of the existing frame beams, and then the templates are installed between the existing frame columns and the prefabricated frame beams to facilitate the construction of cast-in-place concrete. After the cast-in-place concrete is poured, the prefabricated frame beams and the existing frame columns are cast into a whole.

[0006] The prefabricated concrete frame beam structure of this patent application greatly reduces the number of formwork supports, reduces the workload of formwork supports, shortens the construction period, and achieves the goal of convenient construction of prefabricated structures.

[0007] Preferably, post-cast beam concrete is arranged on the upper part of the prefabricated frame beam, and the post-cast beam concrete and the cast-in-place concrete are cast integrally.

[0008] The post-cast beam concrete increases the length of the connection between the precast frame beam and the cast-in-place concrete, which is beneficial to increase the connection strength between the precast frame beam and the existing frame column, thereby ensuring the structural strength of the entire prefabricated concrete frame beam.

[0009] Preferably, upper longitudinal connecting steel bars are arranged in the post-cast concrete, the upper longitudinal connecting steel bars pass through the post-cast beam concrete, and the upper longitudinal connecting steel bars are connected to the prefabricated frame beam.

[0010] The upper longitudinal connecting steel bars are connected to the prefabricated frame beams to ensure structural strength.

[0011] Preferably, upper longitudinal reinforcement bars are arranged in the prefabricated frame beams, and the upper longitudinal connecting reinforcement bars are connected to the upper longitudinal reinforcement bars of the beams.

[0012] The upper longitudinal connecting steel bars are connected to the upper longitudinal steel bars of the beam, so that the post-poured concrete has good integrity with the prefabricated frame beam after pouring.

[0013] Preferably, column longitudinal reinforcement and connecting waist reinforcement are arranged in the cast-in-place concrete, the connecting waist reinforcement is connected to the prefabricated frame beam, and the column longitudinal reinforcement is formed by extending upward from the existing frame column.

[0014] The existing frame columns are equipped with longitudinal reinforcement bars extending upward to ensure the strength of the connection between the cast-in-place concrete and the existing frame columns, thus forming a stable structure. The waist reinforcement is connected to the prefabricated frame beams to ensure the strength of the connection between the prefabricated frame beams and the cast-in-place concrete.

[0015] Preferably, a beam waist reinforcement is arranged in the prefabricated frame beam, and a steel bar connecting sleeve is connected to the end of the beam waist reinforcement. The steel bar connecting sleeve is embedded in the end of the prefabricated frame beam, and the waist reinforcement is connected to the steel bar connecting sleeve.

[0016] The steel bar connecting sleeve facilitates the connection between the waist reinforcement and the beam waist reinforcement.

[0017] Preferably, two connecting waist reinforcements connected to two relatively arranged prefabricated frame beams are welded together accordingly, a positioning joint is arranged at the welding point, two sliding sleeves are arranged on the positioning joint, locking screws are connected to the sleeves, racks are arranged on the sleeves, gears are installed between the two racks on the positioning joint, both racks are meshed with the gears for transmission, and the two connecting waist reinforcements are connected to the two slideways by insertion.

[0018] The two connecting waist bars are pre-tightened and positioned by the positioning joint before welding. When pre-tightening and positioning the connecting waist bars, first put one connecting waist bar together with a sleeve on the positioning joint, then slide the entire positioning joint along the connecting waist bar, put the other connecting waist bar together with another sleeve on the positioning joint, and adjust the position of the positioning joint so that the ends of the two connecting waist bars are exposed from the ends of the sleeves. Then turn the locking screw, and the end of the locking screw abuts against the outer wall of the connecting waist bar, so that the sleeve and the connecting waist bar are connected as a whole. Finally, turn the gear to move the two racks towards each other, thereby achieving pre-tightening and positioning of the two connecting waist bars. Finally, weld the two connecting waist bars.

[0019] The positioning joint facilitates the welding positioning of the two connecting waist bars, ensures that the two connecting waist bars are in a tensioned state, and meets the seismic anchoring requirements of the connecting waist bars. The two connecting waist bars are reliably positioned during welding, which facilitates the welding operation.

[0020] Preferably, an outwardly protruding column side mounting corbel is provided on the overlapping side of the upper part of the existing frame column and the prefabricated frame beam, and the prefabricated frame beam is overlapped on the column side mounting corbel.

[0021] The corbels installed on the column side provide the prefabricated frame beams with sufficient overlapping area, facilitating the overlapping operation of the prefabricated frame beams.

[0022] A method for constructing an assembled concrete frame beam realizes the construction of an assembled concrete frame beam structure, comprising the following steps: S1, pouring existing frame columns; S2, erecting prefabricated frame beams on existing frame columns; S3, connecting connecting waist reinforcement with beam waist reinforcement, sleeve column stirrups around the column longitudinal reinforcement, weld together the lower longitudinal reinforcements of two prefabricated frame beams extending outward, and connect the upper longitudinal connecting reinforcements between the upper longitudinal reinforcements of the two prefabricated frame beams extending outward; S4, supporting formwork around the cast-in-place concrete to be poured; S5, pouring the cast-in-place concrete.

[0023] During the construction of prefabricated concrete frame beams, the prefabricated frame beams are placed on the upper end of the existing frame columns, and then the steel bars in the cast-in-place concrete are laid out and connected. Then the formwork is installed, and finally the cast-in-place concrete is poured. Thus, the prefabricated frame beams and the existing frame columns are cast into a whole. The prefabricated frame beams are prefabricated in advance, which can reduce the number of template supports during the entire concrete frame beam construction process, thereby reducing the workload of template support and helping to shorten the construction period.

[0024] Preferably, in S2, the prefabricated frame beam is corrected by first installing a correction mechanism on the upper end of the existing frame column, installing an end face correction piston cylinder and a side face correction piston cylinder on the correction mechanism, and extending telescopic rods of the end face correction piston cylinder and the side face correction piston cylinder outward to correct the prefabricated frame beam.

[0025] During the erection of prefabricated frame beams, the correction mechanism is used to correct the deviation to ensure the accuracy of the erection position of the prefabricated frame beams.

[0026] Compared with the prior art, the beneficial effects of the present invention are: (1) The prefabricated concrete frame beam structure of the present patent application greatly reduces the number of formwork supports, reduces the workload of formwork supports, shortens the construction period, and achieves the goal of convenient construction of prefabricated structures; (2) The post-cast beam concrete is cast together on the upper part of the cast-in-place concrete, which increases the length of the connection between the prefabricated frame beam and the cast-in-place concrete, which is beneficial to increase the connection strength between the prefabricated frame beam and the existing frame column, thereby ensuring the structural strength of the entire prefabricated concrete frame beam; (3) The connection positioning joint between the two connecting waist bars facilitates the welding positioning of the two connecting waist bars, ensures that the two connecting waist bars are in a tensioned state, meets the seismic anchoring requirements of the connecting waist bars, and reliably positions the two connecting waist bars during welding, facilitating the welding operation. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a structural schematic diagram of the present invention.

[0028] Figure 2 It is a schematic diagram of cast-in-place concrete of the present invention.

[0029] Figure 3 It is a schematic diagram of the prefabricated frame beam of the present invention.

[0030] Figure 4 It is a schematic diagram of the connection of existing frame columns of the present invention.

[0031] Figure 5 The present invention Figure 1 Schematic diagram of aa in.

[0032] Figure 6 The present invention Figure 1 Schematic diagram of bb in.

[0033] Figure 7 The present invention Figure 1 Schematic diagram of cc in .

[0034] Figure 8 It is a schematic diagram of formwork of the present invention.

[0035] Fig. 9 It is a schematic diagram of the deviation correction mechanism of the present invention.

[0036] Fig.10 It is a schematic diagram of a positioning joint of the present invention.

[0037] Fig.11 It is a top view of the positioning joint of the present invention.

[0038] In the figure: 1. existing frame column, 2. prefabricated frame beam, 3. bracket installed on the column side, 4. cast-in-place concrete, 5. post-cast beam concrete, 6. upper longitudinal connecting steel bars, 7. upper longitudinal steel bars of beam, 8. longitudinal steel bars of column, 9. connecting waist bars, 10. waist bars of beam, 11. steel bar connecting sleeve, 12. positioning joint, 13. sliding sleeve, 14. sliding hole, 15. notch, 16. locking screw, 17. rack, 18. gear, 19. base, 20. connecting cover, 21. slide groove , 22. avoidance groove, 23. rotating column, 24. ratchet, 25. pawl, 26. column stirrups, 27. longitudinal reinforcement of the lower part of the beam, 28. correction mechanism, 29. end face correction piston cylinder, 30. side correction piston cylinder, 31. support rod, 32. fixed seat, 33. clamping seat, 34. fastening screw sleeve, 35. driving wheel, 36. driven gear ring, 37. active gear ring, 38. formwork, 39. upper connecting rod, 40. lower connecting rod, 41. connecting plate, 42. beam stirrups. DETAILED DESCRIPTION

[0039] The technical solution of the present invention is further described in detail below through specific embodiments and in conjunction with the accompanying drawings: Example 1: An assembled concrete frame beam structure (see attached Figure 1 To Attachment Figure 7 ), including an existing frame column 1 and a prefabricated frame beam 2, the prefabricated frame beam 2 is erected on the existing frame column 1, and the prefabricated frame beam 2 is erected on both sides of the existing frame column 1. A column side mounting bracket 3 protruding outward is arranged on the overlap side of the upper part of the existing frame column 1 and the prefabricated frame beam 2, and the prefabricated frame beam 2 is overlapped on the column side mounting bracket 3. Cast-in-place concrete 4 is arranged on the upper end of the existing frame column 1, and the cast-in-place concrete 4 casts the prefabricated frame beam 2 and the existing frame column 1 into a whole.

[0040] Post-cast beam concrete 5 is provided on the upper part of the precast frame beam 2, and the post-cast beam concrete 5 and the cast-in-place concrete 4 are cast in one piece. Upper longitudinal connecting steel bars 6 are provided in the post-cast concrete, and the upper longitudinal connecting steel bars 6 pass through the post-cast beam concrete 5, and are connected to the precast frame beam 2. Upper longitudinal steel bars 7 are provided in the precast frame beam 2, and the upper longitudinal connecting steel bars 6 are connected to the upper longitudinal steel bars 7. The post-cast beam concrete 5 increases the length of the connection between the precast frame beam 2 and the cast-in-place concrete 4, which is beneficial to increase the connection strength between the precast frame beam 2 and the existing frame column 1, thereby ensuring the structural strength of the entire assembled concrete frame beam.

[0041] The column longitudinal reinforcement 8 and the connecting waist reinforcement 9 are arranged in the cast-in-place concrete 4, and the connecting waist reinforcement 9 is connected to the prefabricated frame beam 2. The column longitudinal reinforcement 8 is formed by extending upward from the existing frame column 1. The beam waist reinforcement 10 is arranged in the prefabricated frame beam 2, and the end of the beam waist reinforcement 10 is connected to the steel bar connecting sleeve 11, which is pre-buried in the end of the prefabricated frame beam 2, and the connecting waist reinforcement 9 is connected to the steel bar connecting sleeve 11.

[0042] like Figures 1 to 7 As shown, the assembled concrete frame beam structure of the present invention mainly includes an existing frame column 1, a prefabricated frame beam 2, and cast-in-place concrete 4; the existing frame column 1 is composed of a column longitudinal steel bar 8, a column stirrup 26, a column side installation corbel 3, and concrete. The prefabricated frame beam 2 is composed of a beam upper longitudinal steel bar a, a beam upper longitudinal steel bar b, a beam lower longitudinal steel bar 27, a beam stirrup 42, a beam waist bar 10, and concrete. The post-cast beam concrete 5 is composed of an upper longitudinal connecting steel bar a, an upper longitudinal connecting steel bar b, and concrete.

[0043] The column longitudinal reinforcement 8, the existing concrete, and the column side mounting bracket 3 are first cast and constructed. The column side mounting bracket 3 is used to place the prefabricated frame beam 2; the column stirrups 26 are installed after the prefabricated frame beam 2 is placed.

[0044] The arrangement of the lower longitudinal reinforcement 27 of the beam should be adjusted according to the positioning of the column longitudinal reinforcement 8 and the arrangement of the lower longitudinal reinforcement 27 of the beam in the adjacent span precast frame beam 2, provided that the calculation is satisfied; the length of the lower longitudinal reinforcement 27 of the beam extending out of the end surface of the precast frame beam 2 should meet the seismic anchorage requirements of the tension reinforcement. The beam waist reinforcement 10 has a steel bar connection sleeve 11 reserved at the end of the precast frame beam 2; the connecting waist reinforcement 9 is connected to the beam waist reinforcement 10 through the steel bar connection sleeve 11; the connecting waist reinforcement 9 should be adjusted according to the positioning of the column longitudinal reinforcement 8 and the arrangement of the beam waist reinforcement 10 in the adjacent span precast frame beam 2; the length of the connecting waist reinforcement 9 should meet the seismic anchorage requirements of the tension reinforcement; the connecting waist reinforcement 9 should be installed in sequence from bottom to top with the column stirrups 26 in the order of height.

[0045] A post-cast beam concrete section 5 with a length of s and a height of H1 is reserved at the upper part of the end of the precast frame beam 2 for pouring the post-cast beam concrete 5; the length of the upper longitudinal reinforcement a of the beam in the post-cast beam concrete section 5 is s1; the end distance s2 between the upper longitudinal reinforcement a of the beam and the upper longitudinal reinforcement b of the beam is not less than 35 times the diameter of the reinforcement and not less than 500mm. The length of the upper longitudinal reinforcement b of the beam in the post-cast beam concrete section 5 is (s1+s2). The number and area of ​​the upper longitudinal reinforcement a of the beam and the upper longitudinal reinforcement b of the beam are equal; the upper longitudinal reinforcement a of the beam and the upper longitudinal reinforcement b of the beam should be arranged alternately; the distance s3 from the end of the upper longitudinal reinforcement b of the beam to the end of the precast frame beam 2 is 1 / 3 of the total length of the precast frame beam 2.

[0046] The upper longitudinal connecting steel bars a and the upper longitudinal connecting steel bars b should be installed only after the column stirrups 26 within the height range of the cast-in-place concrete H2 are installed; the upper longitudinal connecting steel bars a and the upper longitudinal connecting steel bars b should be continuous throughout the cast-in-place concrete 4; the arrangement of the upper longitudinal connecting steel bars a and the upper longitudinal connecting steel bars b should be adjusted according to the positioning of the column longitudinal steel bars 8, provided that the calculation requirements are met.

[0047] The connection form between the upper longitudinal steel bar a of the beam and the upper longitudinal connecting steel bar a is welding, and the connection length s4 is 10 times the diameter of the steel bar; the connection form between the upper longitudinal steel bar b of the beam and the upper longitudinal connecting steel bar b is welding, and the connection length is s4; the length s1 of the upper longitudinal steel bar a of the beam in the post-cast beam concrete section 5 is not less than s4.

[0048] The beam stirrups 42 are processed and installed in an open form to ensure that the upper longitudinal connecting steel bars a and the upper longitudinal connecting steel bars b have installation space; after the upper longitudinal connecting steel bars a and the upper longitudinal connecting steel bars b are installed, the beam stirrups 42 are bent and closed; the cast-in-place concrete 4 can only be constructed after the beam stirrups 42 are bent and closed.

[0049] The upper surface of the existing frame column 1, the interface between the precast frame beam 2 and the post-cast beam concrete 5 section, and the end surface of the precast beam frame are roughened to form a rough surface with a concave-convex difference of not less than 6 mm.

[0050] The assembled concrete frame beam structure includes an existing frame column 1, a prefabricated frame beam 2, and cast-in-place concrete 4. The prefabricated frame beam 2 can be erected and constructed, so it can be prefabricated in advance. During the entire concrete frame beam construction process, the number of template supports can be reduced, thereby reducing the workload of template support, which is conducive to shortening the construction period. During construction, after the existing frame column 1 is cast, the prefabricated frame beam 2 is overlapped to the upper end of the existing frame beam, and then the template is installed between the existing frame column 1 and the prefabricated frame beam 2 to facilitate the construction of cast-in-place concrete 4. After the cast-in-place concrete 4 is cast, the prefabricated frame beam 2 and the existing frame column 1 are cast into a whole.

[0051] A method for constructing an assembled concrete frame beam, which realizes the construction of an assembled concrete frame beam structure, comprises the following steps: S1, pouring the existing frame column 1; first install the column longitudinal reinforcement 8 and column stirrups 26 in the existing frame column 1, and then cast concrete on the formwork 38, thereby forming the existing frame column 1 with the column side installed corbel 3, and the column longitudinal reinforcement 8 extends upward from the existing frame column 1.

[0052] S2, the prefabricated frame beam 2 is placed on the existing frame column 1; the end of the prefabricated frame beam 2 is placed on the column side mounting bracket 3, and the column side mounting bracket 3 on both sides of the existing frame column 1 are both overlapped with the prefabricated frame beam 2.

[0053] S3, connect the connecting waist reinforcement 9 with the beam waist reinforcement 10, cover the column stirrups 26 around the column longitudinal reinforcement 8, weld the lower longitudinal reinforcements 27 of the two prefabricated frame beams 2 extending outwards together, and connect the upper longitudinal connecting reinforcements 6 between the upper longitudinal reinforcements 7 of the two prefabricated frame beams 2 extending outwards.

[0054] S4, supporting formwork 38 around the cast-in-place concrete 4 to be poured.

[0055] S5, pouring cast-in-place concrete 4.

[0056] During the construction of the assembled concrete frame beam, the prefabricated frame beam 2 is erected on the upper end of the existing frame column 1, and then the steel bars in the cast-in-place concrete 4 are arranged and connected. Then the formwork 38 is installed, and finally the cast-in-place concrete 4 is poured. Thus, the prefabricated frame beam 2 and the existing frame column 1 are cast into a whole. The prefabricated frame beam 2 is prefabricated in advance, which can reduce the number of template supports during the entire concrete frame beam construction process, thereby reducing the workload of template support, which is conducive to shortening the construction period.

[0057] Example 2: An assembled concrete frame beam structure (see attached Figure 1 To Attachment Fig.11 ), including an existing frame column 1 and a prefabricated frame beam 2, the prefabricated frame beam 2 is erected on the existing frame column 1, and the prefabricated frame beam 2 is erected on both sides of the existing frame column 1. A column side mounting bracket 3 protruding outward is arranged on the overlap side of the upper part of the existing frame column 1 and the prefabricated frame beam 2, and the prefabricated frame beam 2 is overlapped on the column side mounting bracket 3. Cast-in-place concrete 4 is arranged on the upper end of the existing frame column 1, and the cast-in-place concrete 4 casts the prefabricated frame beam 2 and the existing frame column 1 into a whole.

[0058] Post-cast beam concrete 5 is provided on the upper part of the precast frame beam 2, and the post-cast beam concrete 5 and the cast-in-place concrete 4 are cast in one piece. Upper longitudinal connecting steel bars 6 are provided in the post-cast concrete, and the upper longitudinal connecting steel bars 6 pass through the post-cast beam concrete 5, and are connected to the precast frame beam 2. Upper longitudinal steel bars 7 are provided in the precast frame beam 2, and the upper longitudinal connecting steel bars 6 are connected to the upper longitudinal steel bars 7. The post-cast beam concrete 5 increases the length of the connection between the precast frame beam 2 and the cast-in-place concrete 4, which is beneficial to increase the connection strength between the precast frame beam 2 and the existing frame column 1, thereby ensuring the structural strength of the entire assembled concrete frame beam.

[0059] The column longitudinal reinforcement 8 and the connecting waist reinforcement 9 are arranged in the cast-in-place concrete 4, and the connecting waist reinforcement 9 is connected to the prefabricated frame beam 2. The column longitudinal reinforcement 8 is formed by extending upward from the existing frame column 1. The beam waist reinforcement 10 is arranged in the prefabricated frame beam 2, and the end of the beam waist reinforcement 10 is connected to the steel bar connecting sleeve 11, which is pre-buried in the end of the prefabricated frame beam 2, and the connecting waist reinforcement 9 is connected to the steel bar connecting sleeve 11.

[0060] The two connecting waist bars 9 connected to the two prefabricated frame beams 2 arranged opposite to each other are welded together, and a positioning joint 12 is arranged at the welding place. Two sliding sleeves 13 that can slide are arranged on the positioning joint 12. Sliding holes 14 are arranged on the positioning joint 12 and the sliding sleeves 13 correspondingly. The two sliding holes 14 are connected, and the sliding sleeves 13 are slidably connected with the sliding holes 14. Notches 15 are arranged on both sliding sleeves 13, and the notches 15 on the two sliding sleeves 13 are arranged correspondingly. A locking screw 16 is connected to the sliding sleeve 13, and a rack 17 is arranged on the sliding sleeve 13. A gear 18 is installed between the two racks 17 on the positioning joint 12. Both racks 17 are meshed with the gear 18 for transmission, and the gear 18 is arranged to rotate. The two connecting waist bars 9 are plug-in connected with the two slideways. A one-way rotating component is installed between the gear 18 and the positioning joint 12 so that the gear 18 can only rotate in one direction, thereby realizing the tension between the two connecting waist bars 9. The positioning joint 12 includes a base 19 and a connection cover 20 which are fastened together, a sliding hole 14 is provided on the base 19, a sliding groove 21 is provided on the connection cover 20 corresponding to the rack 17, the rack 17 is placed in the sliding groove 21, an avoidance groove 22 is provided on the upper surface of the connection cover 20, the locking screw 16 passes through the avoidance groove 22, the gear 18 is rotatably mounted on the connection cover 20, a rotating column 23 is provided on the gear 18, the rotating column 23 extends outward from the connection cover 20, the one-way rotation component includes a ratchet 24 and a pawl 25, a circle of ratchet 24 is provided on the outer wall of the gear 18, the pawl 25 is rotatably mounted on the connection cover 20, and a positioning spring is installed between the pawl 25 and the connection cover 20. The locking screw 16 and the rotating column 23 can be operated and rotated using the same set of hardware tools, without the need to switch tools in the middle, which is conducive to improving work efficiency.

[0061] The two connecting waist bars 9 are pre-tightened and positioned by the positioning joint 12 before welding. When pre-tightening and positioning the connecting waist bars 9, first put one connecting waist bar 9 together with a sliding sleeve 13 on the positioning joint 12, then slide the entire positioning joint 12 along the connecting waist bar 9, and then put another connecting waist bar 9 together with another sliding sleeve 13 on the positioning joint 12, and adjust the position of the positioning joint 12 so that the ends of the two connecting waist bars 9 are exposed from the ends of the two sliding sleeves 13 respectively. Then turn the locking screw 16, and the end of the locking screw 16 abuts against the outer wall of the connecting waist bar 9, so that the sliding sleeve 13 and the connecting waist bar 9 are connected as a whole. Finally, turn the gear 18 to move the two racks 17 in a direction close to each other, thereby achieving pre-tightening and positioning of the two connecting waist bars 9. Finally, weld the two connecting waist bars 9.

[0062] The positioning joint 12 facilitates the welding positioning of the two connecting waist bars 9, ensures that the two connecting waist bars 9 are in a tensioned state, and meets the seismic anchoring requirements of the connecting waist bars 9. The two connecting waist bars 9 are reliably positioned during welding, which facilitates the welding operation.

[0063] like Figures 1 to 7As shown, the assembled concrete frame beam structure of the present invention mainly includes an existing frame column 1, a prefabricated frame beam 2, and cast-in-place concrete 4; the existing frame column 1 is composed of a column longitudinal steel bar 8, a column stirrup 26, a column side installation corbel 3, and concrete. The prefabricated frame beam 2 is composed of a beam upper longitudinal steel bar a, a beam upper longitudinal steel bar b, a beam lower longitudinal steel bar 27, a beam stirrup 42, a beam waist bar 10, and concrete. The post-cast beam concrete 5 is composed of an upper longitudinal connecting steel bar a, an upper longitudinal connecting steel bar b, and concrete.

[0064] The column longitudinal reinforcement 8, the existing concrete, and the column side mounting bracket 3 are first cast and constructed. The column side mounting bracket 3 is used to place the prefabricated frame beam 2; the column stirrups 26 are installed after the prefabricated frame beam 2 is placed.

[0065] The arrangement of the lower longitudinal reinforcement 27 of the beam should be adjusted according to the positioning of the column longitudinal reinforcement 8 and the arrangement of the lower longitudinal reinforcement 27 of the beam in the adjacent span precast frame beam 2, provided that the calculation is satisfied; the length of the lower longitudinal reinforcement 27 of the beam extending out of the end surface of the precast frame beam 2 should meet the seismic anchorage requirements of the tension reinforcement. The beam waist reinforcement 10 has a steel bar connection sleeve 11 reserved at the end of the precast frame beam 2; the connecting waist reinforcement 9 is connected to the beam waist reinforcement 10 through the steel bar connection sleeve 11; the connecting waist reinforcement 9 should be adjusted according to the positioning of the column longitudinal reinforcement 8 and the arrangement of the beam waist reinforcement 10 in the adjacent span precast frame beam 2; the length of the connecting waist reinforcement 9 should meet the seismic anchorage requirements of the tension reinforcement; the connecting waist reinforcement 9 should be installed in sequence from bottom to top with the column stirrups 26 in the order of height.

[0066] A post-cast beam concrete section 5 with a length of s and a height of H1 is reserved at the upper part of the end of the precast frame beam 2 for pouring the post-cast beam concrete 5; the length of the upper longitudinal reinforcement a of the beam in the post-cast beam concrete section 5 is s1; the end distance s2 between the upper longitudinal reinforcement a of the beam and the upper longitudinal reinforcement b of the beam is not less than 35 times the diameter of the reinforcement and not less than 500mm. The length of the upper longitudinal reinforcement b of the beam in the post-cast beam concrete section 5 is (s1+s2). The number and area of ​​the upper longitudinal reinforcement a of the beam and the upper longitudinal reinforcement b of the beam are equal; the upper longitudinal reinforcement a of the beam and the upper longitudinal reinforcement b of the beam should be arranged alternately; the distance s3 from the end of the upper longitudinal reinforcement b of the beam to the end of the precast frame beam 2 is 1 / 3 of the total length of the precast frame beam 2.

[0067] The upper longitudinal connecting steel bars a and the upper longitudinal connecting steel bars b should be installed only after the column stirrups 26 within the H2 height range of the cast-in-place concrete are installed; the upper longitudinal connecting steel bars a and the upper longitudinal connecting steel bars b should be continuous throughout the cast-in-place concrete 4; the arrangement of the upper longitudinal connecting steel bars a and the upper longitudinal connecting steel bars b should be adjusted according to the positioning of the column longitudinal steel bars 8, provided that the calculation requirements are met.

[0068] The connection form between the upper longitudinal steel bar a of the beam and the upper longitudinal connecting steel bar a is welding, and the connection length s4 is 10 times the diameter of the steel bar; the connection form between the upper longitudinal steel bar b of the beam and the upper longitudinal connecting steel bar b is welding, and the connection length is s4; the length s1 of the upper longitudinal steel bar a of the beam in the post-cast beam concrete section 5 is not less than s4.

[0069] The beam stirrups 42 are processed and installed in an open form to ensure that the upper longitudinal connecting steel bars a and the upper longitudinal connecting steel bars b have installation space; after the upper longitudinal connecting steel bars a and the upper longitudinal connecting steel bars b are installed, the beam stirrups 42 are bent and closed; the cast-in-place concrete 4 can only be constructed after the beam stirrups 42 are bent and closed.

[0070] The upper surface of the existing frame column 1, the interface between the precast frame beam 2 and the post-cast beam concrete 5 section, and the end surface of the precast beam frame are roughened to form a rough surface with a concave-convex difference of not less than 6 mm.

[0071] The assembled concrete frame beam structure includes an existing frame column 1, a prefabricated frame beam 2, and cast-in-place concrete 4. The prefabricated frame beam 2 can be erected and constructed, so it can be prefabricated in advance. During the entire concrete frame beam construction process, the number of template supports can be reduced, thereby reducing the workload of template support, which is conducive to shortening the construction period. During construction, after the existing frame column 1 is cast, the prefabricated frame beam 2 is overlapped to the upper end of the existing frame beam, and then the template is installed between the existing frame column 1 and the prefabricated frame beam 2 to facilitate the construction of cast-in-place concrete 4. After the cast-in-place concrete 4 is cast, the prefabricated frame beam 2 and the existing frame column 1 are cast into a whole.

[0072] A method for constructing an assembled concrete frame beam, which realizes the construction of an assembled concrete frame beam structure, comprises the following steps: S1, pouring the existing frame column 1; first install the column longitudinal reinforcement 8 and column stirrups 26 in the existing frame column 1, and then cast concrete on the formwork 38, thereby forming the existing frame column 1 with the column side installed corbel 3, and the column longitudinal reinforcement 8 extends upward from the existing frame column 1.

[0073] S2, the prefabricated frame beam 2 is erected on the existing frame column 1; the end of the prefabricated frame beam 2 is erected on the column side mounting bracket 3, and the column side mounting bracket 3 on both sides of the existing frame column 1 is overlapped with the prefabricated frame beam 2. In S2, the prefabricated frame beam 2 is corrected, and the correction mechanism 28 is first installed on the upper end of the existing frame column 1, and the end face correction piston cylinder 29 and the side correction piston cylinder 30 are installed on the correction mechanism 28. The end face correction piston cylinder 29 and the side correction piston cylinder 30 are both hydraulic cylinders, and the telescopic rods of the end face correction piston cylinder 29 and the side correction piston cylinder 30 extend outward to correct the prefabricated frame beam 2. Two opposite end face correction piston cylinders 29 and two pairs of side correction piston cylinders 30 are installed on the correction mechanism 28. One pair of side correction piston cylinders 30 are placed on both sides of one prefabricated frame beam 2, and the other pair of side correction piston cylinders 30 are placed on both sides of another prefabricated frame beam 2. The correcting mechanism 28 includes two support rods 31 and a fixed seat 32 and a clamping seat 33 respectively arranged on both sides of the support rod 31. The fixed seat 32 is fixed to the support rod 31, and the clamping seat 33 is connected to the support rod 31 in a sleeve manner. The support rod 31 is threadedly connected with a fastening screw sleeve 34, and a rotatable driving wheel 35 is arranged on the clamping seat 33. A driven gear ring 36 is arranged on the outer wall of the fastening screw sleeve 34, and an active gear ring 37 is arranged on the outer wall of the driving wheel 35. The driven gear ring 36 and the active gear ring 37 are meshed for transmission. The rotation of the driving wheel 35 drives the rotation of the fastening screw sleeve 34, so that the clamping seat 33 and the fixed seat 32 are tightly clamped to the side wall of the existing frame column 1 to realize the installation and fixation of the entire correcting mechanism 28.

[0074] S3, connect the connecting waist reinforcement 9 with the beam waist reinforcement 10, put the column stirrups 26 around the column longitudinal reinforcement 8, weld the lower longitudinal reinforcements 27 of the two prefabricated frame beams 2 extending outward, and connect the upper longitudinal connecting reinforcements 6 between the upper longitudinal reinforcements 7 of the two prefabricated frame beams 2 extending outward. The two connecting waist reinforcements 9 are pre-tightened and positioned by the positioning joint 12 before welding. When the connecting waist reinforcement 9 is pre-tightened and positioned, first put one connecting waist reinforcement 9 together with a sliding sleeve 13 on the positioning joint 12, then slide the entire positioning joint 12 along the connecting waist reinforcement 9, and then put another connecting waist reinforcement 9 together with another sliding sleeve 13 on the positioning joint 12, and adjust the position of the positioning joint 12 so that the ends of the two connecting waist reinforcements 9 are exposed from the ends of the two sliding sleeves 13 respectively. Then turn the locking screw 16, and the end of the locking screw 16 abuts against the outer wall of the connecting waist reinforcement 9, so that the sliding sleeve 13 and the connecting waist reinforcement 9 are connected into a whole. Finally, the gear 18 is rotated to move the two racks 17 toward each other, thereby realizing the pre-tightening positioning of the two connecting waist bars 9. Finally, the two connecting waist bars 9 are welded.

[0075] S4, a formwork 38 is formed around the cast-in-place concrete 4 to be poured. An upper connecting rod 39 and a lower connecting rod 40 are detachably connected between the two supporting forms 38, a connecting plate 41 is provided on the supporting formwork 38, and a connecting hole is provided on the connecting plate 41. Both ends of the upper connecting rod 39 are inserted into the two connecting holes and fastened by nuts, and both ends of the lower connecting rod 40 are inserted into the two connecting holes and fastened by nuts. The upper connecting rod 39 is supported to the upper part of the prefabricated frame beam 2 to realize the positioning of the entire supporting formwork 38.

[0076] S5, pouring cast-in-place concrete 4.

[0077] During the construction of the assembled concrete frame beam, the prefabricated frame beam 2 is erected on the upper end of the existing frame column 1, and then the steel bars in the cast-in-place concrete 4 are arranged and connected. Then the formwork 38 is installed, and finally the cast-in-place concrete 4 is poured. Thus, the prefabricated frame beam 2 and the existing frame column 1 are cast into a whole. The prefabricated frame beam 2 is prefabricated in advance, which can reduce the number of template supports during the entire concrete frame beam construction process, thereby reducing the workload of template support, which is conducive to shortening the construction period.

[0078] The above embodiments are only preferred solutions of the present invention and are not intended to limit the present invention in any form. There are other variations and modifications without exceeding the technical solutions described in the claims.

Claims

1. An assembled concrete frame beam structure, characterized in that: It includes existing frame columns and prefabricated frame beams. The prefabricated frame beams are erected on the existing frame columns. Cast-in-place concrete is arranged on the upper ends of the existing frame columns. The cast-in-place concrete casts the prefabricated frame beams and the existing frame columns into a whole.

2. The assembled concrete frame beam structure according to claim 1 is characterized in that: Post-cast beam concrete is arranged on the upper part of the prefabricated frame beam, and the post-cast beam concrete and the cast-in-place concrete are cast in one piece.

3. The assembled concrete frame beam structure according to claim 2 is characterized in that: Upper longitudinal connecting steel bars are arranged in the post-cast concrete, pass through the post-cast beam concrete, and are connected to the prefabricated frame beam.

4. The assembled concrete frame beam structure according to claim 3 is characterized in that: Upper longitudinal reinforcements are arranged in the prefabricated frame beams, and the upper longitudinal connecting reinforcements are connected to the upper longitudinal reinforcements of the beams.

5. The assembled concrete frame beam structure according to claim 1 is characterized in that: Column longitudinal reinforcement and connecting waist reinforcement are arranged in the cast-in-place concrete. The connecting waist reinforcement is connected to the prefabricated frame beam. The column longitudinal reinforcement is formed by extending upward from the existing frame column.

6. The assembled concrete frame beam structure according to claim 5 is characterized in that: Beam waist reinforcement is arranged in the prefabricated frame beam, and the end of the beam waist reinforcement is connected with a steel bar connecting sleeve. The steel bar connecting sleeve is embedded in the end of the prefabricated frame beam, and the waist reinforcement is connected to the steel bar connecting sleeve.

7. The assembled concrete frame beam structure according to claim 5 is characterized in that: Two connecting waist bars connected to two relatively prefabricated frame beams are welded together accordingly, a positioning joint is arranged at the welding point, two sliding sleeves are arranged on the positioning joint, locking screws are connected to the sleeves, racks are arranged on the sleeves, gears are installed between the two racks on the positioning joint, both racks are meshed with the gears for transmission, and the two connecting waist bars are connected to the two slideways by insertion.

8. The assembled concrete frame beam structure according to any one of claims 1 to 7, characterized in that: A column side mounting bracket protruding outward is arranged on the overlapped side of the upper part of the existing frame column and the prefabricated frame beam, and the prefabricated frame beam is overlapped on the column side mounting bracket.

9. A method for constructing an assembled concrete frame beam, characterized in that: The construction of the assembled concrete frame beam structure as described in any one of claims 1 to 8 comprises the following steps: S1, casting existing frame columns; S2, erecting prefabricated frame beams on existing frame columns; S3, connecting connecting waist reinforcement with beam waist reinforcement, sleeve column stirrups around the column longitudinal reinforcement, weld together the lower longitudinal reinforcements of the two prefabricated frame beams extending outward, and connect the upper longitudinal connecting reinforcements between the upper longitudinal reinforcements of the two prefabricated frame beams extending outward; S4, supporting formwork around the cast-in-place concrete to be cast; S5, casting the cast-in-place concrete.

10. The method for constructing an assembled concrete frame beam according to claim 9, characterized in that: In S2, the prefabricated frame beam is corrected. First, the correction mechanism is installed on the upper end of the existing frame column, and the end face correction piston cylinder and the side face correction piston cylinder are installed on the correction mechanism. The telescopic rods of the end face correction piston cylinder and the side face correction piston cylinder are extended outward to correct the prefabricated frame beam.

Citation Information

Patent Citations

  • Beam-bottom medium-strength prestressed steel bar and ordinary steel bar sleeve connecting beam-column joint

    CN105625573A

  • Prefabricated hollow column and superposed beam connecting structure and construction method

    CN110565796A

  • Fabricated beam-slab structure suitable for large-span high-clearance building and construction method thereof

    CN112593632A

  • Automatic welding device for lap joint and assembly of reinforcing steel bars

    CN115846961A

  • Assembled integral type double-faced superposed beam-column joint connecting structure and construction method

    CN117364954A