Early dismantling construction method for scattered splicing formwork

By designing the disassembled formwork early to remove the frame body, supporting it in the middle of the span of the building components, and starting to remove it when the concrete reaches 50% strength, the problem of long-term removal of the formwork in the existing technology is solved, and the formwork support frame body is realized Early demolition and shortening of construction progress have reduced costs.

CN119083712AInactive Publication Date: 2024-12-06CHINA MCC22 GROUP CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411428391.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-14
Publication Date
2024-12-06
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

During construction, the removal of the formwork support frame for the large-span beam and slab structure requires waiting for the concrete strength to reach more than 70%, which usually takes 28 days, resulting in low utilization rate of the support frame and high construction cost.

Method used

Design a frame body of a disassembled formwork, including the bottom support, the bottom torsion sleeve and the top torsion sleeve. By adjusting the screw connection, the frame body is supported in the middle of the component and the concrete strength reaches 50%. When removing the formwork, the frame body will be removed early, and then the concrete poured meets the design requirements.

Benefits of technology

The advance removal of the formwork support frame body is achieved, which reduces construction costs, shortens the project progress, and ensures the quality of concrete components.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083712A_ABST
    Figure CN119083712A_ABST
Patent Text Reader

Abstract

The invention relates to the field of building construction, in particular to a scattered splicing formwork early-dismantling construction method which comprises the steps that S1, a formwork early-dismantling frame body is designed; the template early-dismantling frame body comprises a bottom support, a bottom knob sleeve is inserted into the bottom support, the bottom knob sleeve is in threaded connection with an adjusting screw rod, the adjusting screw rod is in threaded connection with a top knob sleeve, and a top support is inserted into the top knob sleeve; s2, a formwork early-dismantling frame body is manufactured; s3, pouring a to-be-constructed component; s4, removing the template of the to-be-constructed component; and after the strength of the poured concrete reaches 50% of the design requirement, supporting frame bodies except the formwork early-dismantling frame body in the formwork are dismantled, and after the strength of the poured concrete reaches the design requirement, the formwork early-dismantling frame body is dismantled. The formwork early-dismantling frame body is arranged to be supported at the midspan position of the component, the formwork supporting frame body is dismantled in advance, the method is simple and easy to implement, convenient to operate and low in cost, the quality of the concrete component can be guaranteed to a great extent, the project progress is shortened, and the cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, in particular to a construction method for early dismantling of loose-assembled formwork. Background Art

[0002] Large-span beam-slab structures are common in building construction. After the beams and slabs are poured, it is usually necessary to wait until the concrete strength reaches 70% or above before the formwork support frame can be removed. Due to the influence of the construction environment, it takes at least 28 days for the concrete to reach the required strength, that is, it takes 28 days to remove the formwork support frame after the beams and slabs are poured, which reduces the turnover rate of the support frame and increases the construction cost. Summary of the invention

[0003] In view of the above problems, an embodiment of the present invention provides a construction method for early dismantling of loose formwork.

[0004] An embodiment of the present invention provides a method for early dismantling of a loose formwork, comprising: S1. Design template and dismantle the frame early The template early disassembly frame comprises a bottom bracket, a bottom twist sleeve is inserted on the bottom bracket, an adjusting screw is threadedly connected to the bottom twist sleeve, a top twist sleeve is threadedly connected to the adjusting screw, and a top bracket is inserted on the top twist sleeve; S2. Make templates and dismantle the frame early Calculate the size of each component in the early dismantling frame of the template according to the elevation of the component to be constructed, and cut the material according to the calculated sizes to obtain each component in the early dismantling frame of the template; S3, pouring of components to be constructed According to the design requirements, the formwork of the components to be constructed is supported, the mid-span position of the components to be constructed is determined, the formwork is disassembled and assembled, and then supported at the mid-span position below the formwork, and concrete is poured into the formwork; S4. Removal of formwork for construction components After the strength of the poured concrete reaches 50% of the design requirements, the supporting frames in the formwork except the formwork early dismantling frame are dismantled, and the formwork early dismantling frame is dismantled after the strength of the poured concrete reaches the design requirements.

[0005] Compared with the prior art, the beneficial effect of the present invention is that by setting up a formwork early dismantling frame to support the mid-span position of the component, the formwork support frame can be dismantled in advance, which is simple, easy to operate, and low in cost. It can greatly ensure the quality of concrete components, shorten the project progress, and reduce costs.

[0006] Optionally, the base bracket includes a base plate, a sleeve vertically fixed on the base plate, a rib plate arranged between the sleeve and the base plate, a plurality of groups of fixing holes are axially arranged on the sleeve, and a latch plate is passed through one group of the fixing holes.

[0007] Optionally, the bottom twist sleeve includes a sleeve tube section for being sleeved on the sleeve and a threaded tube section adapted to the size of the sleeve, the threaded tube section is coaxially connected to the sleeve tube section, the inner wall of the threaded tube section is provided with an internal thread adapted to the adjusting screw, and a handrail is provided between the outer wall of the sleeve tube section and the threaded tube section. BRIEF DESCRIPTION OF THE DRAWINGS

[0008] The drawings described herein are used to provide a further understanding of the present invention, constitute a part of the present application, and do not constitute a limitation of the present invention. In the drawings: Figure 1 A schematic diagram of a process flow of a loose formwork early disassembly construction method provided by an embodiment of the present invention; Figure 2 A schematic structural diagram of a template early disassembly frame provided by an embodiment of the present invention; Figure 3 A schematic structural diagram of a bottom support in a template early disassembly frame provided by an embodiment of the present invention; Figure 4 A schematic structural diagram of a bottom twist sleeve in a template early disassembly frame provided in an embodiment of the present invention.

[0009] Among them, 1. bottom support; 2. bottom twist sleeve; 3. adjustment screw; 4. top twist sleeve; 5. top support; 6. bottom plate; 7. sleeve; 8. fixing hole; 9. latch plate; 10. sleeve pipe section; 11. threaded pipe section; 12. handrail. DETAILED DESCRIPTION

[0010] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the embodiments and the accompanying drawings. Here, the illustrative embodiments of the present invention and their descriptions are used to explain the present invention, but are not intended to limit the present invention.

[0011] See also Figure 1 , an embodiment of the present invention provides a loose formwork early disassembly construction method, comprising: S1. Design template and dismantle the frame early The template early disassembly frame includes a bottom bracket 1, a bottom twist sleeve 2 is inserted on the bottom bracket 1, an adjusting screw 3 is threadedly connected to the bottom twist sleeve 2, a top twist sleeve 4 is threadedly connected to the adjusting screw 3, and a top bracket 5 is inserted on the top twist sleeve 4; S2. Make templates and dismantle the frame early The dimensions of each component in the early-dismantling formwork frame are calculated according to the elevation of the component to be constructed, and the components in the early-dismantling formwork frame are cut according to the calculated dimensions.

[0012] During implementation, taking common floor construction as an example, the net height of bottom support 1 is 1310mm; the net height of bottom / top twist sleeve is 1000mm; the net height of adjustment screw 3 is 2620mm; the net height of top support 5 is 1310mm, which is suitable for the frame support of horizontal components with a floor net height of 2620mm~4940mm.

[0013] S3, pouring of components to be constructed The formwork of the components to be constructed is supported according to the design requirements, the mid-span position of the components to be constructed is determined, the formwork frame is dismantled and assembled, and then supported at the mid-span position below the formwork, and concrete is poured into the formwork.

[0014] S4. Removal of formwork for construction components After the strength of the poured concrete reaches 50% of the design requirements, the supporting frames in the formwork except the formwork early dismantling frame are dismantled, and the formwork early dismantling frame is dismantled after the strength of the poured concrete reaches the design requirements.

[0015] During implementation, the bottom support 1 includes a bottom plate 6, a sleeve 7 vertically fixed on the bottom plate 6, a rib plate is arranged between the sleeve 7 and the bottom plate 6, a plurality of groups of fixing holes 8 are opened on the sleeve 7 and are axially opposite to each other, and a latch plate 9 is passed through one group of fixing holes 8; the structure of the top support 5 is the same as that of the bottom support 1.

[0016] During implementation, the bottom twist sleeve 2 includes a sleeve tube section 10 for being sleeved on the sleeve 7 and a threaded tube section 11 whose size is adapted to the sleeve 7. The threaded tube section 11 is coaxially connected to the sleeve tube section 10. The inner wall of the threaded tube section 11 is provided with an internal thread adapted to the adjusting screw 3. A handrail rod 12 is provided between the outer walls of the sleeve tube section 10 and the threaded tube section 11. The structure of the top twist sleeve 4 is the same as that of the bottom twist sleeve 2.

[0017] During implementation, the specific support process of the early dismantling formwork frame includes first threading the bottom twist sleeve 2 and the top twist sleeve 3 at both ends of the adjusting screw 3, selecting the fixing hole 8 at a suitable position according to the elevation of the component to be constructed and the size of each component, sleeve the bottom twist sleeve 2 on the bottom support 1 and insert the latch plate 9 into the fixed hole 8 at the selected position, insert the top support 5 into the top twist sleeve 4 and insert the latch plate 9 into the fixed hole 8 at the selected position, erect the assembled early dismantling formwork frame at the mid-span position, rotate the bottom twist sleeve 2 and / or the top twist sleeve 3 so that the early dismantling formwork frame is pressed against the formwork of the component to be constructed to complete the support.

[0018] The solution provided by the embodiment of the present invention realizes the early removal of the formwork support frame by setting up a formwork early removal frame to support the mid-span position of the component. It is simple, easy to operate, and has low cost. It can greatly ensure the quality of concrete components, shorten the project progress, and reduce costs.

[0019] The above description is only a preferred embodiment of the present invention and is not intended to limit the protection scope of the present invention. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention are included in the protection scope of the present invention.

Claims

1. A loose formwork early dismantling construction method, characterized in that: include: S1. Design template and dismantle the frame early The template early disassembly frame comprises a bottom bracket, a bottom twist sleeve is inserted on the bottom bracket, an adjusting screw is threadedly connected to the bottom twist sleeve, a top twist sleeve is threadedly connected to the adjusting screw, and a top bracket is inserted on the top twist sleeve; S2. Make templates and dismantle the frame early Calculate the size of each component in the early dismantling frame of the template according to the elevation of the component to be constructed, and cut the material according to the calculated sizes to obtain each component in the early dismantling frame of the template; S3, pouring of components to be constructed According to the design requirements, the formwork of the components to be constructed is supported, the mid-span position of the components to be constructed is determined, the formwork is disassembled and assembled, and then supported at the mid-span position below the formwork, and concrete is poured into the formwork; S4. Removal of formwork for components to be constructed After the strength of the poured concrete reaches 50% of the design requirements, the supporting frames in the formwork except the formwork early dismantling frame are dismantled, and the formwork early dismantling frame is dismantled after the strength of the poured concrete reaches the design requirements.

2. The early dismantling construction method of loose formwork according to claim 1, characterized in that: The bottom bracket comprises a bottom plate, a sleeve vertically fixed on the bottom plate, a rib plate arranged between the sleeve and the bottom plate, a plurality of groups of fixing holes are arranged on the sleeve in an axial direction, and a latch plate is passed through one group of fixing holes.

3. The early dismantling construction method of loose formwork according to claim 2, characterized in that: The bottom twist sleeve includes a sleeve tube section for being sleeved on the sleeve and a threaded tube section adapted to the size of the sleeve. The threaded tube section is coaxially connected to the sleeve tube section. The inner wall of the threaded tube section is provided with an internal thread adapted to the adjusting screw. A handrail is provided between the outer wall of the sleeve tube section and the threaded tube section.