Construction method of hyperbolic special-shaped building

By establishing a three-dimensional model of the model, optimizing the design of the curtain wall keel, and combining three-dimensional scanning technology, the problems of high difficulty in construction of hyperbolic special-shaped buildings and complex installation of curtain wall systems are solved, efficient and precise construction and installation are achieved, ensuring the aesthetics of the building and Structural stability.

CN119083726AActive Publication Date: 2024-12-06SHANGHAI MECHANIZED CONSTR GRP
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411490442.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-24
Publication Date
2024-12-06
Estimated Expiration
2044-10-24

AI Technical Summary

Technical Problem

The construction of hyperbolic special-shaped buildings is difficult, especially when installing curtain wall systems, the lack of effective construction methods makes it difficult to ensure engineering efficiency and accuracy.

Method used

By establishing a three-dimensional model of the main steel structure and curtain wall system, mold clamping and processing, optimizing the design and installation of curtain wall keels, and using three-dimensional scanning technology for accurate measurement and adjustment, achieving efficient integrated lifting of the main steel structure and curtain wall system and Install.

Benefits of technology

It improves construction efficiency and accuracy, reduces construction difficulty, ensures the aesthetics of the building and structural stability, avoids the complexity and safety risks of high-altitude operations, and significantly improves the accuracy of curtain wall panel installation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083726A_ABST
    Figure CN119083726A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of building construction, and discloses a construction method of a hyperbolic special-shaped building, which comprises the following steps: according to a design drawing, a three-dimensional model of a main body steel structure and a three-dimensional model of a curtain wall system of the hyperbolic special-shaped building are respectively established, and the curtain wall system comprises curtain wall keels and curtain wall plates; the three-dimensional model of the main body steel structure and the three-dimensional model of the curtain wall system are subjected to mold closing, and an overall model is formed after mold closing; processing and manufacturing the main body steel structure and the curtain wall system according to the integral model; after machining and manufacturing are completed, the curtain wall keel is assembled to the main body steel structure firstly, integrated hoisting is conducted after assembling is completed, and then the curtain wall plate is installed to the curtain wall keel. The construction efficiency and precision can be effectively improved, and the construction difficulty is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a construction method of a hyperbolic special-shaped building. Background Art

[0002] With the development of society, steel structure buildings have gradually become a new type of building system. Due to its high strength, light weight, plasticity and flexibility, it has gradually replaced traditional concrete structures and become a trend in building development. Steel structures are widely used in buildings with special requirements for structural appearance and space, such as stadiums, airports, and railway stations. Spatial steel pipe structures are often used to achieve unique design effects. These structures often contain complex spatial distortions and multi-angle connections.

[0003] However, the installation and positioning of spatial steel tube structures is difficult, especially in the building form of hyperbolic special-shaped structures with strict requirements on appearance. Such buildings usually also need to be equipped with curtain wall systems, but the complexity of special-shaped steel tube structures brings greater challenges to the installation of curtain wall systems. At present, there is a lack of an effective construction method for this type of hyperbolic special-shaped building structure, which increases the difficulty of construction, makes it difficult to effectively respond to complex design and construction requirements, and makes it difficult to ensure engineering efficiency and accuracy.

[0004] Therefore, it is urgent to propose a construction method for hyperbolic special-shaped buildings to solve the above technical problems. Summary of the invention

[0005] The purpose of the present invention is to provide a construction method for a hyperbolic special-shaped building, which can effectively improve construction efficiency and precision and reduce construction difficulty.

[0006] As conceived above, the technical solution adopted by the present invention is:

[0007] The present invention provides a construction method for a hyperbolic special-shaped building, comprising:

[0008] According to the design drawings, three-dimensional models of the main steel structure and curtain wall system of the hyperbolic special-shaped building are respectively established, wherein the curtain wall system includes curtain wall keels and curtain wall panels;

[0009] Combining the three-dimensional model of the main steel structure with the three-dimensional model of the curtain wall system to form an overall model;

[0010] Processing and manufacturing the main steel structure and the curtain wall system according to the overall model;

[0011] After the processing and manufacturing is completed, the curtain wall keel is first assembled to the main steel structure, and after the assembly is completed, it is hoisted as an integrated whole, and then the curtain wall panel is installed to the curtain wall keel.

[0012] In some embodiments, the curtain wall keel includes a main keel and a secondary keel;

[0013] According to the design drawings, three-dimensional models of the main steel structure and curtain wall system of the hyperbolic special-shaped building are established respectively, including:

[0014] The main steel structure is optimized into a straight line, the main keel is optimized into a single curve, the secondary keel is optimized into a straight line, and a three-dimensional model of the main steel structure and the curtain wall keel is generated according to the optimization results.

[0015] In some embodiments, the three-dimensional model of the main steel structure and the three-dimensional model of the curtain wall system are molded together to form an overall model, including:

[0016] After generating the three-dimensional models of the main steel structure and the curtain wall keel according to the optimization results, the positioning points of the main steel structure, the main keel and the secondary keel are determined and reviewed through the cross-sectional views at different elevations;

[0017] Determine the relative position relationship between the curtain wall system and the main steel structure according to the positioning points of the main steel structure, the main keel and the secondary keel;

[0018] Potential collision points are identified by using collision detection tools, and the three-dimensional model of the main steel structure or the three-dimensional model of the curtain wall system is adjusted according to the collision detection results.

[0019] In some embodiments, the main steel structure is processed and manufactured according to the overall model, including:

[0020] Determine the measurement point position of each component in the main steel structure according to the on-site construction sequence and the actual on-site working conditions, and feed the measurement point position back to the overall model so that the measurement point position is converted into a processing coordinate;

[0021] Processing the main steel structure according to the processing coordinates;

[0022] After the processing is completed, the processing coordinates of each component in the main steel structure are re-measured, and the re-measured data are fed back to the three-dimensional model of the main steel structure to calculate the deviation of the processing coordinates.

[0023] In some embodiments, the main steel structure is processed according to the processing coordinates, and after the processing is completed, the process further includes:

[0024] The three-dimensional scanning technology is used to measure each component in the main steel structure, and the measurement results are imported into the three-dimensional model of the main steel structure for mold fitting.

[0025] In some embodiments, the curtain wall system is processed and manufactured according to the overall model, including:

[0026] Adjust the three-dimensional model of the curtain wall keel in the curtain wall system according to the measured data of the main steel structure, and perform paperless drawing and cutting based on the adjusted model;

[0027] The curtain wall keel is bent by a bending device;

[0028] Use the 1:1 keel bending drawing to check the accuracy of the curtain wall keel after bending.

[0029] In some embodiments, after the processing and manufacturing is completed, the curtain wall keel is first assembled to the main steel structure, and after the assembly is completed, an integrated hoisting is performed, which specifically includes:

[0030] Performing a three-dimensional scan on the connection structure of the main steel structure and determining the three-dimensional coordinates of the connection structure, and feeding the three-dimensional coordinates back to the overall model for comparison and adjustment;

[0031] The curtain wall keels are assembled into a plurality of first units, the plurality of first units are assembled with the main steel structure, and the assembled curtain wall keels and the main steel structure are hoisted in an integrated manner.

[0032] In some embodiments, the curtain wall keel is assembled into a plurality of first units, the plurality of first units are assembled with the main steel structure, and after the assembled curtain wall keel and the main steel structure are hoisted as a whole, the method further includes:

[0033] The actual measurement points of the hoisted main steel structure and the curtain wall keel are re-measured, and the hoisted main steel structure and the curtain wall keel are three-dimensionally scanned, and the measurement results are correspondingly imported into the three-dimensional model of the main steel structure and the three-dimensional model of the curtain wall system for mold matching.

[0034] In some embodiments, installing the curtain wall panel to the curtain wall keel specifically includes:

[0035] The curtain wall panels are assembled into a plurality of second units, and the plurality of second units are sequentially installed to the curtain wall keels.

[0036] In some embodiments, after the curtain wall system is installed, the method further includes:

[0037] The facade of the curtain wall system is three-dimensionally scanned, the scan data is fed back to the original overall model for comparison, and adjustments or repairs are made according to the comparison results.

[0038] Beneficial effects of the present invention:

[0039] The construction method of the hyperbolic special-shaped building provided by the present invention realizes the accurate expression and coordination of the complex geometric form of the building by establishing a three-dimensional model of the main steel structure and the curtain wall system in the early stage of construction. First, by forming a three-dimensional model through in-depth design, the geometric characteristics of the hyperbolic special-shaped structure can be accurately restored; secondly, the main steel structure and the curtain wall system are three-dimensionally molded, which effectively improves the synergy between different systems, reduces the occurrence of on-site adjustments and errors, and makes processing and installation more efficient and accurate. Due to the accuracy of the three-dimensional model, the entire construction process can be better controlled, which helps to reduce the difficulty of construction, improve engineering efficiency and construction accuracy, and ensure the aesthetics and structural stability of the hyperbolic special-shaped building. In addition, the curtain wall keel and the main steel structure are pre-integrated and assembled, and high-precision assembly can be performed on the ground, avoiding the complexity and safety risks of installing components one by one in high-altitude operations, significantly improving the construction efficiency and installation accuracy, and greatly ensuring the accuracy of subsequent curtain wall panel installation. BRIEF DESCRIPTION OF THE DRAWINGS

[0040] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments of the present invention. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the contents of the embodiments of the present invention and these drawings without paying any creative work.

[0041] Figure 1 It is a flow chart of a construction method of a hyperbolic special-shaped building provided by an embodiment of the present invention;

[0042] Figure 2 is a flow chart of a method for three-dimensional mold closing provided by an embodiment of the present invention;

[0043] Figure 3 It is a schematic diagram of a keel bending drawing provided by an embodiment of the present invention;

[0044] Figure 4 yes Figure 3 A partial enlarged view of the middle A;

[0045] Figure 5 It is a schematic diagram of installing a connecting piece provided by an embodiment of the present invention to a concrete structure.

[0046] In the figure:

[0047] 100. Keel bending error control line;

[0048] 200, keel theoretical edge;

[0049] 300, connector;

[0050] 400. Concrete structure. DETAILED DESCRIPTION

[0051] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.

[0052] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0053] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.

[0054] In the description of the present invention, it should be noted that the terms "upper", "lower", "left", "right", "vertical", "horizontal", "inside", "outside", etc. indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, or are the positions or positional relationships in which the inventive product is usually placed when in use. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", "third", etc. are only used to distinguish the description, and cannot be understood as indicating or implying relative importance. In the description of the present invention, unless otherwise specified, "multiple" means two or more.

[0055] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "disposed" and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0056] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them. Moreover, a first feature being "above", "above" and "above" a second feature includes that the first feature is directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature includes that the first feature is directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.

[0057] Embodiments of the present invention are described in detail below, examples of which are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, and cannot be understood as limiting the present invention.

[0058] like Figure 1 As shown, the construction method of the hyperbolic special-shaped building provided in this embodiment includes:

[0059] S1. According to the design drawings, three-dimensional models of the main steel structure and curtain wall system of the hyperbolic special-shaped building are established respectively, wherein the curtain wall system includes curtain wall keels and curtain wall panels;

[0060] S2, combining the three-dimensional model of the main steel structure and the three-dimensional model of the curtain wall system to form an overall model;

[0061] S3. Process and manufacture the main steel structure and curtain wall system according to the overall model;

[0062] S4. After processing and manufacturing, first assemble the curtain wall keel to the main steel structure, then hoist it as an integrated whole, and then install the curtain wall panels to the curtain wall keel.

[0063] Among them, the three-dimensional model can be a BIM model (Building Information Modeling), which refers to a digital three-dimensional model created based on architectural design drawings, including shape, material, connection method, etc.

[0064] The construction method of the hyperbolic special-shaped building provided in this embodiment realizes the accurate expression and coordination of the complex geometric form of the building by establishing a three-dimensional model of the main steel structure and the curtain wall system in the early stage of construction. First, by deepening the design to form a three-dimensional model, the geometric characteristics of the hyperbolic special-shaped structure can be accurately restored; secondly, the main steel structure and the curtain wall system are three-dimensionally molded, which effectively improves the synergy between different systems, reduces the occurrence of on-site adjustments and errors, and makes processing and installation more efficient and accurate. Due to the accuracy of the three-dimensional model, the entire construction process can be better controlled, which helps to reduce the difficulty of construction, improve engineering efficiency and construction accuracy, and ensure the aesthetics and structural stability of the hyperbolic special-shaped building. In addition, the curtain wall keel and the main steel structure are pre-integrated and assembled, and high-precision assembly can be performed on the ground, avoiding the complexity and safety risks of installing components one by one in high-altitude operations, significantly improving the construction efficiency and installation accuracy, and greatly ensuring the accuracy of subsequent curtain wall panel installation.

[0065] In some embodiments, the curtain wall keel includes a main keel and a secondary keel.

[0066] Exemplarily, the material of the main keel and the secondary keel may be aluminum or aluminum alloy.

[0067] Usually, the main steel structure, as the main load-bearing structure of the hyperbolic special-shaped building, is connected to the concrete structure of the hyperbolic special-shaped building. The main keel is connected to the main steel structure and plays the main supporting role of the external curtain wall panels. The secondary keel is connected to the main keel to further refine the support for the curtain wall panels and ensure the stability and precise positioning of the curtain wall panels.

[0068] In step S1, according to the design drawings, three-dimensional models of the main steel structure and curtain wall system of the hyperbolic special-shaped building are respectively established, which specifically includes:

[0069] The main steel structure is optimized into a straight line, the main keel is optimized into a single curve, and the secondary keel is optimized into a straight line, and a three-dimensional model of the main steel structure and curtain wall keel is generated based on the optimization results.

[0070] Specifically, according to the positional relationship between the finished surface of the curtain wall panels and the finished surface of the curtain wall keels in the design drawings, the data can be analyzed by parametric method to optimize the main steel structure into a straight line to enhance its bearing capacity; the main keel can be designed into a single curved shape to meet the requirements of the building's appearance; and the secondary keel can be optimized into a straight line shape for easy installation and connection. This optimization helps to simplify the construction process and improve the operability and accuracy of the construction. Through the above optimization results, a model containing all keel structures is finally generated, which provides accurate theoretical data support for actual construction and ensures that each component can be accurately installed in actual construction.

[0071] like Figure 2As shown, in some embodiments, in step S2, the three-dimensional model of the main steel structure and the three-dimensional model of the curtain wall system are molded together to form an overall model, including:

[0072] S21. After generating the three-dimensional model of the main steel structure and curtain wall keel according to the optimization results, determine the positioning points of the main steel structure, the main keel and the secondary keel through the cross-sections at different elevations and conduct a review;

[0073] S22. Determine the relative position relationship between the curtain wall system and the main steel structure according to the positioning points of the main steel structure, the main keel and the secondary keel;

[0074] S23. Identify potential collision points through collision detection tools, and adjust the three-dimensional model of the main steel structure or the three-dimensional model of the curtain wall system according to the collision detection results.

[0075] The cross-sectional view accurately reflects the connection and arrangement of components at different heights, which can effectively avoid positioning errors caused by spatial complexity. In addition, the review of the positioning points can ensure that the position of each component corresponds accurately, thus providing an accurate basis for the coordination between models. After the positioning points are clear, the precise relative position relationship between the main steel structure and the curtain wall system is established to ensure that the various systems can fit perfectly during mold closing and avoid model mismatch caused by position errors. Furthermore, the application of collision detection tools can automatically identify potential conflict areas, so as to make timely adjustments to potential collision points, ensuring the integrity of the mold closing and the smooth progress of subsequent installation.

[0076] Exemplarily, when step S21 is implemented, the main steel structure is first positioned, and three elevation positions are selected for the main steel structure, including elevation positioning point one, elevation positioning point two and elevation positioning point three. The transverse sections of the main steel structure at different elevation positions are associated with the axis line, and the main steel structure is positioned by the transverse section diagrams of elevation positioning point one and elevation positioning point two, and is verified by the transverse section diagram of elevation positioning point three; secondly, the main keel is positioned, and the coordinates of the starting point of the main keel and the coordinates of the intersection point one of the main keel and the main steel structure are used for positioning, and the coordinates of the intersection point two of the main keel and the main steel structure are used for verification; finally, the secondary keel is positioned, and the secondary keel is positioned according to the coordinates of the secondary keel connection point on the main keel.

[0077] In some embodiments, the step S3 of processing and manufacturing the main steel structure according to the overall model includes:

[0078] Determine the measurement points of each component in the main steel structure according to the on-site construction sequence and actual on-site working conditions, and feed the measurement points back to the overall model to convert the measurement points into processing coordinates;

[0079] Process the main steel structure according to the processing coordinates;

[0080] After the processing is completed, the processing coordinates of each component in the main steel structure are remeasured, and the remeasured data are fed back to the three-dimensional model of the main steel structure to calculate the deviation of the processing coordinates.

[0081] Determining the processing coordinates based on the 3D model can accurately reflect the actual position and size requirements of each component in the main steel structure in space, ensuring the processing accuracy. After the processing is completed, each component is re-tested and the re-test data is fed back to the 3D model, which can quickly verify the matching degree between the processing results and the design model, timely discover deviations or non-compliance with requirements and make timely adjustments, further improving the processing accuracy and quality control.

[0082] Furthermore, in some embodiments, the main steel structure is processed according to the processing coordinates, and after the processing is completed, it also includes:

[0083] The 3D scanning technology is used to measure the components in the main steel structure, and the measurement results are imported into the 3D model of the main steel structure for mold fitting.

[0084] Through such a setting, 3D scanning technology can quickly and comprehensively obtain the actual geometric data of the main steel structure. Compared with traditional measurement methods, it has higher accuracy and wider coverage, and is especially suitable for complex hyperbolic special-shaped structures. The measurement results are imported into the 3D model for mold closing, and the actual processing results can be intuitively compared with the design model to quickly find possible deviations or non-compliance with requirements. This process ensures that the overall size and shape of each component in the main steel structure are highly consistent with the design model, thereby reducing errors and adjustment requirements in subsequent installation links.

[0085] In some embodiments, the step S3 of processing and manufacturing the curtain wall system according to the overall model includes:

[0086] Adjust the 3D model of the curtain wall keel in the curtain wall system according to the measured data of the main steel structure, and perform paperless drawing and cutting based on the adjusted model;

[0087] The curtain wall keel is bent by bending equipment;

[0088] Use the 1:1 keel bending drawing to check the accuracy of the curtain wall keel after bending. Specifically, the bent curtain wall keel can be compared and checked with the keel bending drawing 2 to 3 times to avoid the bending rebound affecting the accuracy.

[0089] Through the combination of model adjustment, bending and precision review, the production accuracy and installation efficiency of the curtain wall system are improved, the rework and adjustment workload during construction is reduced, and the high consistency and aesthetics of the curtain wall system and the main structure are ensured.

[0090] like Figure 3 and Figure 4 As shown in the figure, the 1:1 keel bending drawing includes the keel bending error control line 100 and the keel theoretical edge line 200. For the convenience of distinction, Figure 4 The keel bending error control line 100 is a solid line, and the keel theoretical edge line 200 is a dotted line. The keel theoretical edge line 200 is the curve shape that the keel should reach in an ideal state, and the keel bending error control line 100 is an upper and lower limit range set for the theoretical edge line to ensure that the error in the bending process is controlled within an acceptable range. If the keel exceeds the range of the keel bending error control line 100, it is necessary to readjust the bending until the keel shape meets the design requirements.

[0091] Furthermore, the 1:1 keel bending drawing may also include positioning point marks, such as the main keel starting point mark, the main keel support positioning point mark, the secondary keel positioning point mark, etc. These positioning point marks can be referenced during the keel bending process to ensure that the shape of the keel after bending is consistent with the positioning points in the design model, thereby providing an accurate benchmark for subsequent installation.

[0092] It should be noted that: in some embodiments, the main keel in the curtain wall keel is selected to be bent, and in other embodiments, both the main keel and the secondary keel in the curtain wall keel can be bent. The specific method can be determined according to actual conditions.

[0093] Optionally, the stretch-bending equipment may be configured as a hydraulic stretch-bending machine, a CNC stretch-bending machine, etc., which is not specifically limited herein.

[0094] In some embodiments, in step S4, after the processing and manufacturing is completed, the curtain wall keel is first assembled to the main steel structure, and after the assembly is completed, an integrated hoisting is performed, which specifically includes:

[0095] Conduct 3D scanning on the connection structure of the main steel structure and determine the 3D coordinates of the connection structure, and feed the 3D coordinates back to the overall model for comparison and adjustment;

[0096] The curtain wall keels are assembled into a plurality of first units, the plurality of first units are assembled with the main steel structure, and the assembled curtain wall keels and the main steel structure are hoisted in an integrated manner.

[0097] That is: after the processing and production is completed, when installing on site, the connection structure of the main steel structure is first controlled for accuracy, that is, the previous process is measured and scanned on site before the main steel structure is installed. Through three-dimensional scanning and model comparison, if there is a deviation, it is adjusted in time. If there is an unadjustable deviation, the main steel structure needs to be adjusted to eliminate the error. After the accuracy inspection of the main steel structure meets the requirements, the curtain wall keel and the main steel structure are installed. During installation, the curtain wall keel is assembled in a modular form of multiple first units. For example, the curtain wall keel can be shipped to the site as a frame for assembly with the main steel structure. Such a modular assembly method can improve construction efficiency and shorten the construction period.

[0098] Furthermore, in some embodiments, after assembling the curtain wall keels into a plurality of first units, assembling the plurality of first units with the main steel structure, and hoisting the assembled curtain wall keels and the main steel structure as an integrated whole, the method further includes:

[0099] The actual measurement points of the hoisted main steel structure and curtain wall keels are re-measured, and the hoisted main steel structure and curtain wall keels are 3D scanned. The measurement results are imported into the 3D model of the main steel structure and the 3D model of the curtain wall system for mold matching.

[0100] Through such a setting, deviations generated during the installation process can be discovered in time, ensuring that the positioning and shape of each component are consistent with the design model, avoiding subsequent adjustments and rework, and significantly improving installation accuracy and construction efficiency.

[0101] In actual construction, due to the large size of the building, the main steel structure can usually be divided into multiple sections. The first unit in the curtain wall keel is assembled on the corresponding section, and then the assembled sections and the first unit are hoisted in sequence. Before installing each section, the errors that cannot be eliminated on site in the previous section need to be fed back to the processing plant for component adjustment. After adjustment, the installation process of the previous section that has been installed is referred to to continue the installation of the subsequent sections.

[0102] like Figure 5 As shown, in some embodiments, the main steel structure is connected to the concrete structure 400 of the building via a connector 300 .

[0103] Preferably, the connecting member 300 is arranged obliquely relative to the concrete structure 400, and the connection portion with the concrete structure 400 can move up and down to absorb the stress generated by the main steel structure.

[0104] In some embodiments, the step S4 of installing the curtain wall panels to the curtain wall keels specifically includes:

[0105] The curtain wall panels are assembled into a plurality of second units, and the plurality of second units are sequentially installed to the curtain wall keels. Specifically, the second units can be installed layer by layer from top to bottom through a scaffold.

[0106] Through this setting, the curtain wall panels can be pre-assembled into a modular second unit, which can be assembled and debugged in a standardized manner on the ground to ensure that the connection between the panels is tight and meets the design requirements, avoiding the accumulation of errors and on-site adjustment problems during the installation of each panel, further optimizing the construction process and improving the overall installation efficiency and accuracy.

[0107] Optionally, the curtain wall panels can be set as aluminum panels. Of course, in other embodiments, the curtain wall panels can also be set as other materials, such as stainless steel panels, glass panels, etc., which can be determined according to actual conditions.

[0108] In some embodiments, the curtain wall panel can be configured as an inner and outer two-layer structure. For example, the outer layer can be made of aluminum veneer for external protection and decoration, while the inner layer can be made of aluminum plate or other materials to increase structural stability, waterproof and heat insulation, etc. The inner and outer two-layer design helps to improve the overall performance of the curtain wall panel.

[0109] Specifically, the inner layer structure can be set to a 1.2mm thick waterproof aluminum plate, which is installed on the curtain wall keel. The outer layer structure can be set to a 4mm thick aluminum plate, which can be installed on the inner layer waterproof aluminum plate through T-shaped aluminum alloy adapters, aluminum round tubes, aluminum alloy clamps, etc. The specific steps during installation are mature existing technologies in this field and will not be introduced in detail here.

[0110] In some embodiments, after the curtain wall system is installed, the method further includes:

[0111] The facade of the curtain wall system is scanned in three dimensions, and the scan data is fed back to the original overall model for comparison, and adjustments or repairs are made based on the comparison results.

[0112] Through such a setting, 3D scanning technology can fully obtain the actual geometric data of the facade of the curtain wall system, such as the actual shape and size, and compare it with the design model to promptly identify areas with large deviations. In addition, combined with real-time feedback and adjustment mechanisms, it not only improves the accuracy and quality after construction, but also provides reliable data support for subsequent maintenance and management, ensuring the long-term durability of the building and the optimization of its use function.

[0113] Alternatively, the 3D scanning can be performed by a high-precision 3D laser scanner.

[0114] Note that the above are only preferred embodiments of the present invention and the technical principles used. Those skilled in the art will understand that the present invention is not limited to the specific embodiments described herein, and that various obvious changes, readjustments and substitutions can be made by those skilled in the art without departing from the scope of protection of the present invention. Therefore, although the present invention has been described in more detail through the above embodiments, the present invention is not limited to the above embodiments, and may include more other equivalent embodiments without departing from the concept of the present invention, and the scope of the present invention is determined by the scope of the appended claims.

Claims

1. A method for constructing a hyperbolic special-shaped building, characterized in that: include: According to the design drawings, three-dimensional models of the main steel structure and curtain wall system of the hyperbolic special-shaped building are respectively established, wherein the curtain wall system includes curtain wall keels and curtain wall panels; Combining the three-dimensional model of the main steel structure with the three-dimensional model of the curtain wall system to form an overall model; Processing and manufacturing the main steel structure and the curtain wall system according to the overall model; After the processing and manufacturing is completed, the curtain wall keel is first assembled to the main steel structure, and after the assembly is completed, it is hoisted as an integrated whole, and then the curtain wall panel is installed to the curtain wall keel.

2. The construction method of a hyperbolic special-shaped building according to claim 1, characterized in that: The curtain wall keel includes a main keel and a secondary keel; According to the design drawings, three-dimensional models of the main steel structure and curtain wall system of the hyperbolic special-shaped building are established respectively, including: The main steel structure is optimized into a straight line, the main keel is optimized into a single curve, the secondary keel is optimized into a straight line, and a three-dimensional model of the main steel structure and the curtain wall keel is generated according to the optimization results.

3. The construction method of a hyperbolic special-shaped building according to claim 2, characterized in that: The three-dimensional model of the main steel structure and the three-dimensional model of the curtain wall system are molded together to form an overall model, including: After generating the three-dimensional models of the main steel structure and the curtain wall keel according to the optimization results, the positioning points of the main steel structure, the main keel and the secondary keel are determined and reviewed through the cross-sectional views at different elevations; Determine the relative position relationship between the curtain wall system and the main steel structure according to the positioning points of the main steel structure, the main keel and the secondary keel; Potential collision points are identified by using collision detection tools, and the three-dimensional model of the main steel structure or the three-dimensional model of the curtain wall system is adjusted according to the collision detection results.

4. The construction method of a hyperbolic special-shaped building according to claim 1, characterized in that: The main steel structure is processed and manufactured according to the overall model, including: Determine the measurement point position of each component in the main steel structure according to the on-site construction sequence and the actual on-site working conditions, and feed the measurement point position back to the overall model so that the measurement point position is converted into a processing coordinate; Processing the main steel structure according to the processing coordinates; After the processing is completed, the processing coordinates of each component in the main steel structure are re-measured, and the re-measured data are fed back to the three-dimensional model of the main steel structure to calculate the deviation of the processing coordinates.

5. The construction method of a hyperbolic special-shaped building according to claim 4, characterized in that: The main steel structure is processed according to the processing coordinates, and after the processing is completed, the method further includes: The three-dimensional scanning technology is used to measure each component in the main steel structure, and the measurement results are imported into the three-dimensional model of the main steel structure for mold fitting.

6. The construction method of a hyperbolic special-shaped building according to claim 4, characterized in that: Processing and manufacturing the curtain wall system according to the overall model includes: Adjust the three-dimensional model of the curtain wall keel in the curtain wall system according to the measured data of the main steel structure, and perform paperless drawing and cutting based on the adjusted model; The curtain wall keel is bent by a bending device; Use the 1:1 keel bending drawing to check the accuracy of the curtain wall keel after bending.

7. The construction method of a hyperbolic special-shaped building according to any one of claims 1 to 6, characterized in that: After processing and manufacturing, the curtain wall keel is first assembled to the main steel structure, and then hoisted in an integrated manner, which specifically includes: Performing a three-dimensional scan on the connection structure of the main steel structure and determining the three-dimensional coordinates of the connection structure, and feeding the three-dimensional coordinates back to the overall model for comparison and adjustment; The curtain wall keels are assembled into a plurality of first units, the plurality of first units are assembled with the main steel structure, and the assembled curtain wall keels and the main steel structure are hoisted in an integrated manner.

8. The construction method of a hyperbolic special-shaped building according to claim 7, characterized in that: Assembling the curtain wall keels into a plurality of first units, assembling the plurality of first units with the main steel structure, and integrally hoisting the assembled curtain wall keels and the main steel structure, the method further includes: The actual measurement points of the hoisted main steel structure and the curtain wall keel are re-measured, and the hoisted main steel structure and the curtain wall keel are three-dimensionally scanned, and the measurement results are correspondingly imported into the three-dimensional model of the main steel structure and the three-dimensional model of the curtain wall system for mold matching.

9. The construction method of a hyperbolic special-shaped building according to any one of claims 1 to 6, characterized in that: Installing the curtain wall panels to the curtain wall keels specifically includes: The curtain wall panels are assembled into a plurality of second units, and the plurality of second units are sequentially installed to the curtain wall keels.

10. The construction method of a hyperbolic special-shaped building according to any one of claims 1 to 6, characterized in that: After the curtain wall system is installed, it also includes: The facade of the curtain wall system is three-dimensionally scanned, the scan data is fed back to the original overall model for comparison, and adjustments or repairs are made according to the comparison results.

Citation Information

Patent Citations

  • BIM-based pre-assembling method for double-curved glass curtain wall

    CN106013535A

  • Three-dimensional adjustable system of complex multi-curve modeling veneer

    CN112227635A

  • Scaffold-free hyperbolic roof cornice curtain wall construction method based on BIM (Building Information Modeling)

    CN114753649A

  • Double-curved-surface metal curtain wall unit type installation construction method capable of achieving error compensation

    CN117569610A

  • Curved special-shaped metal roof of stadium and construction method

    CN117803140A