Construction method for installing spherical net rack through rail sliding method

The spherical mesh installation is divided and slipped through the track sliding method, which solves the construction problems of medium and large mesh installations in small spaces, improves construction efficiency and safety, reduces material and lifting costs, and achieves efficient spherical mesh installation.

CN119083741APending Publication Date: 2024-12-06CHINA CHEM ENG SECOND CONSTR
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202411513063.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-28
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

In a narrow space, the spherical mesh with a large span and cannot be assembled on the ground is difficult to construct, resulting in low construction efficiency and long construction cycle.

Method used

The track sliding method is used to divide the spherical mesh into multiple assembly units, and the assembly unit is sequentially assembled on the high-altitude facility construction platform and movable the assembly unit along the track using sliding tracks and traction devices to realize the gradual installation of the spherical mesh.

Benefits of technology

It improves construction efficiency, shortens construction cycle, reduces material and lifting costs, and ensures construction safety and site utilization efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083741A_ABST
    Figure CN119083741A_ABST
Patent Text Reader

Abstract

The invention discloses a construction method for installing a spherical net rack through a rail sliding method. The spherical net rack to be erected is divided into a plurality of assembling units; a construction platform used for assembling any assembling unit is erected at the high altitude, and the construction platform is located below the elevation of the concrete beam at the sliding starting end; sliding rails are laid on the tops of the concrete beams on the two sides of the sliding direction; the assembling units are sequentially assembled on the construction platform according to the sequence, a plurality of rolling supports are supported at the bottoms of the two sides of the assembled assembling units, each rolling support comprises a rolling wheel, and the rolling wheels are installed in the sliding rails in a rolling fit mode; traction devices are used for pulling the assembling units to move in the sliding direction; the splicing unit at the tail end is spliced on the construction platform in situ; according to the construction method, the scheme of'high-altitude block assembling and accumulative sliding 'is adopted for construction, the problem of translation of the large steel structure net rack in a narrow space is solved, the procedures of all-round scaffolding, large hoisting and the like are omitted or reduced, and the construction efficiency is high.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of steel grid construction, and in particular to a construction method for installing a spherical grid using a track sliding method. Background Art

[0002] At present, the installation method of spherical grid is high-altitude bulk method. During the installation process, it is usually necessary to set up a full-floor scaffolding and cooperate with large-scale hoisting for hoisting. When the space is small and the construction site is insufficient, it is very difficult to assemble and hoist the spherical grid on site for sub-units with large spans that cannot be assembled on the ground, resulting in low construction efficiency and affecting the construction period. Therefore, a construction method is urgently needed to solve the problems faced by the installation of spherical grids. Summary of the invention

[0003] The technical problem to be solved by the present invention is to provide a construction method for installing a spherical grid by a track sliding method, which can improve the construction efficiency and shorten the construction period.

[0004] In order to solve the above technical problems, the technical solution adopted by the present invention is: A construction method for installing a spherical grid using a track sliding method, comprising: Step 1: divide the spherical grid to be erected into several assembly units; Step 2: Set up a construction platform for assembling any assembly unit at high altitude, the construction platform is located below the concrete beam elevation at the sliding start end; lay sliding tracks on the top of the concrete beams on both sides of the sliding direction; Step 4: assemble the assembly units in sequence on the construction platform, support multiple rolling supports at the bottom of both sides of the assembled assembly units, wherein the rolling supports include rollers, and the rollers are rollingly mounted in the sliding track; and the assembly units are pulled by the traction device to move along the sliding direction; First, the assembly unit at the starting end is assembled on the construction platform. After the assembly is completed, the assembly unit at the starting end is pulled by a traction device to move along the sliding direction and stops after the end thereof slides out of the construction platform. Then, the middle assembly units are paired on the construction platform in turn, and any assembly unit that has been paired moves along the sliding direction together with the assembly unit that has moved to the previous position until it reaches the installation position of each assembly unit; The assembly units at the end are assembled in situ on the construction platform; Step 5: Install the spherical grid support and remove the rolling support and sliding track.

[0005] As a preferred embodiment, guide rail sizes are arranged on the sliding track, with every 50 mm as a sliding process.

[0006] As a preferred embodiment, embedded parts are symmetrically embedded on both sides of the sliding track installation position along the axial direction on the concrete beam surface, and the sliding track and the embedded parts are connected and fixed by welding.

[0007] As a preferred embodiment, the traction device is a winch or an electric hoist, and the traction device is connected to the rolling bearing supporting the assembly unit through a wire rope, and connects the rolling bearings of two adjacent assembly units.

[0008] As a preferred embodiment, traction devices are provided at both the front end and the rear end in the sliding direction.

[0009] As a preferred embodiment, the rolling bearing further comprises a support portion and a traction ring, the roller is installed at the bottom of the support portion through a roller bracket, a traction ring is arranged on the roller bracket, and the chord ball on the grid is installed and supported at the top of the support portion.

[0010] As a preferred embodiment, the rolling bearing also includes a door-shaped support rib, which includes a top horizontal support plate and vertical plates fixed vertically downward on both sides of the horizontal support plate. The chord ball on the grid is supported on the horizontal support plate, and a gap is left between the vertical plate and the sliding track.

[0011] As a preferred implementation, in step five, when removing the rolling bearings and sliding tracks, first install shims between the bottom of the supporting ribs and the moving tracks as temporary supports, remove the rollers and remove the sliding tracks at the corresponding parts of the rollers, then install the bearings at the bottom of the upper chord balls of the truss, and finally remove the supporting ribs and the remaining sliding tracks.

[0012] The present invention adopts the "high-altitude block assembly + cumulative sliding" scheme for the construction of steel grid structures in confined spaces, and uses a track sliding method to put the components in place, thereby overcoming the difficult problem of translation of large steel structure grids in a small space, eliminating or reducing procedures such as full-floor scaffolding and large-scale hoisting, having high construction efficiency, greatly reducing the cost of construction turnover materials, saving large-scale hoisting costs, etc.

[0013] In addition, the construction process of the present invention is basically completed on a prefabricated construction platform, which is highly efficient and safe; and the overall construction site is greatly reduced by adopting a construction method of prefabricated groups of units. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] The drawings herein are used to provide further explanation of the present invention and constitute a part of this application. The illustrative embodiments of the present invention and their description are used to explain the present invention and do not constitute improper limitations on the present invention.

[0015] Figure 1 A plan view of the steel structure construction site described in the embodiment; Figures 2 to 8It is a schematic diagram of the sliding and installation steps of the spherical grid partial assembly unit described in the embodiment; Fig. 9 This is a schematic diagram of the construction scope of the grid sliding; Fig.10 is a schematic diagram of traction control strategy; Fig.11 This is the layout diagram of the sliding track; Fig.12 is a schematic diagram of the rolling bearing structure; Figures 13 to 16 Schematic diagram for removing the rolling bearing and sliding track.

[0016] In the figure, 1-construction platform, 2-sliding track, 3-wire rope, 4-rolling bearing, 5-concrete beam, 6-grid upper chord structure, 7-grid upper chord ball, 8-grid upper chord rod, 9-roller, 10-support part, 11-roller bracket, 12-support rib plate, 13-added rib plate, 14-shim, 15-bearing. DETAILED DESCRIPTION

[0017] In order to make those skilled in the art better understand the present invention, the present invention is further clearly and completely described below in conjunction with the accompanying drawings and embodiments. It should be noted that, in the absence of conflict, the features in the embodiments and examples of this application can be combined with each other.

[0018] In order to solve the problem of the difficulty of translating the spherical grid in a narrow space and to avoid the need for scaffolding and large-scale hoisting during the installation process, a typical embodiment of the present invention provides a construction method for installing the spherical grid by a track sliding method, comprising: Step 1: divide the spherical grid to be erected into several assembly units; Step 2: Set up a construction platform for assembling any assembly unit at high altitude, the construction platform is located below the concrete beam elevation at the sliding start end; lay sliding tracks on the top of the concrete beams on both sides of the sliding direction; Step 4: assemble the assembly units in sequence on the construction platform, support multiple rolling supports at the bottom of both sides of the assembled assembly units, wherein the rolling supports include rollers, and the rollers are rollingly mounted in the sliding track; and the assembly units are pulled by the traction device to move along the sliding direction; First, the assembly unit at the starting end is assembled on the construction platform. After the assembly is completed, the assembly unit at the starting end is pulled by a traction device to move along the sliding direction and stops after the end thereof slides out of the construction platform. Then, the middle assembly units are paired on the construction platform in turn, and any assembly unit that has been paired moves along the sliding direction together with the assembly unit that has moved to the previous position until it reaches the installation position of each assembly unit; The assembly units at the end are assembled in situ on the construction platform; Step 5: Install the spherical grid support and remove the rolling support and sliding track.

[0019] A relatively specific embodiment is taken as an example below to make it easier for those skilled in the art to understand the technical solution provided by the present invention. This embodiment involves a spherical grid with a span of 48 meters and a length of 300 meters.

[0020] Figure 1 This is the plan layout of the steel structure construction site described in this embodiment. Both sides are assembly areas, and the assembly area inward is a sliding area. The construction platform is set up in the assembly area, and construction is carried out inward from both sides.

[0021] The spherical grid in this embodiment includes axes 1-32. According to the characteristics of the project, the installation sequence is determined and the units are installed. The components between the two axes are used as an assembly unit. A tire frame is made on the high-altitude platform and the installation is accumulated and slipped. The steps of installing from axis 13 to axis 1 are used as an example to illustrate.

[0022] First, set up a construction platform near axis 1 ( Figure 2 ), assemble and weld the 13-11 axis grid into an integral unit on the construction platform ( Figure 3 ), use the concrete beam to install the sliding track, and slide the 13-11 axis grid out of the construction platform as a whole ( Figure 4 ). Assemble the 11-9 axis grid and connect it with the 11 axis grid that has been removed from the construction platform ( Figure 5 ), slide the 13-9 axis grid forward until the 9 axis moves out of the construction platform ( Figure 6 ). Assemble the 7-9 grid on the construction platform and connect it to the removed 9 axis, and slide the 13-7 axis grid forward as a whole until the 7 axis grid is moved out of the construction platform. Assemble the 5-7 grid on the construction platform and connect it to the removed 7 axis, and slide the 13-5 axis grid forward as a whole until the 5 axis grid is moved out of the construction platform. Assemble the 3-5 grid on the construction platform and connect it to the 5 axis that has been removed from the frame, and slide the 13-3 axis grid forward as a whole until it reaches the installation position shown in the drawing ( Figure 7 Finally, assemble the 1-3 grids in situ on the construction platform and connect them to the 3 axes of the removed tire frame ( Figure 8 ).

[0023] The on-site assembly process of the steel grid is as follows: ① According to the construction drawings, check the specifications and dimensions of the ball and rod, make the lower chord grid of the first unit, and measure the axis and diagonal dimensions of the lower chord of the first unit.

[0024] ②Put the first prefabricated lower chord unit on the support and make the center of the ball coincide with the center of the support. Determine the center point again from the center of the column and move the grid to adjust to prevent the overall offset and twisting after the grid is assembled.

[0025] ③ Assemble the upper ball rod and the belly rod in bulk to ensure the stability of the single grid. When assembling and spot welding, ensure that the steel pipe rod fits the ball. The spot welding work is performed by qualified welders.

[0026] ④ Assemble the first unit grid in the following order: lower chord, web, upper chord. Assemble from the middle to both sides to release the accumulated errors to both sides.

[0027] ⑤ Check the axis offset and longitudinal and transverse length deviation frequently during the assembly process. Adjust the lower chord node elevation and axis and diagonal dimension deviation at any time. Measure with a level, steel tape measure and wire. Measure the node height with a level and adjust (prepare wedge blocks in advance) so that the adjacent error is less than ±3mm.

[0028] ⑥Grid assembly process Step 1: Measure and lay out, position the grid welding ball supports and install the welding balls, and place the lower line and lower chord rods within the range of 11~13 (20~22) axes on the assembly platform.

[0029] Step 2: Assemble the middle and lower chords into a right cone shape at the on-site assembly site.

[0030] Step 3: Install the horizontal bar connected to the center chord ball.

[0031] During the assembly process, the axis offset and vertical and horizontal length deviations are often checked. The deviation is controlled within 1 / 2000 of the total length and no more than 30mm. The center deviation allowable span is 1 / 3000 and no more than 30mm. The grid diagonal size error is ±3mm, and the grid axis and vertebral allowable deviation is ±2mm.

[0032] Control of grid deflection requires pre-arching of the grid frame during assembly (pre-arching is 1 / 400 of the short span), and the amount of arching is controlled by a level, while the deflection of the grid frame is controlled. The viewing point is selected on a fixed building object and marked for easy observation at any time, and the results of multiple tests should be recorded.

[0033] In this embodiment, the steel grid structure adopts the "high-altitude block assembly + cumulative sliding" scheme for construction, and its sliding range is as follows: Fig. 9 As shown, it includes the first to fifth sliding units and the sixth assembly unit (in-situ assembly).

[0034] This embodiment adopts roller bearing and grooved guide rail guidance, and the traction device adopts a winch or an electric hoist, such as Fig.10As shown, the traction device is connected to the rolling bearing supporting the assembly unit through a steel wire rope, and the rolling bearings of two adjacent assembly units are connected. Traction devices are provided at the front and rear ends of the sliding direction, and a group at the front end serves as a traction end to provide traction power. In order to prevent the traction inertia of the grid, this embodiment adds a set of traction devices at the rear end of the sliding direction as a reverse traction end to play a backward driving brake role. Taking the sliding of the fifth sliding unit as an example, the rolling bearing at the front end of the first sliding unit is connected to the traction end, the rolling bearing at the end of the fifth sliding unit is connected to the reverse traction end, and the rolling bearings of the remaining sliding units serve as driven ends.

[0035] In this embodiment, the sliding track is connected to the concrete structure beam at an elevation of +14.800 meters. The sliding track layout diagram is as follows: Fig.11 As shown in the figure, the sliding track is laid on the concrete beams of the 2-A axis and the 2-J axis. Embedded parts are symmetrically embedded on both sides of the sliding track installation position along the axis direction on the concrete beam surface. The embedded parts are used to fix it to the concrete platform every 3 meters along the axis direction. The straightness and flatness of the track must be ensured when installing the track. When installing the track, the track and the embedded parts are connected and fixed by welding.

[0036] When laying the track, one section is laid every 12m to ensure that each section of track has good connectivity, is stable and reliable, and that the track is laid in concentric circles.

[0037] The guide rail size is accurately laid out on the sliding track, with a layout accuracy of millimeters. Every 50mm is a sliding process, and after the error is coordinated, the next sliding process is carried out. When an error occurs in each sliding process, the reverse traction point is used to correct it.

[0038] Since the sliding track is laid on the concrete beam, it is necessary to ensure that the concrete beam is flat, firm and dense, and the uneven places should be leveled and pressed. The track can be laid only when the strength of the concrete beam test block reaches more than 75% of the design value. Set the reference point on the concrete beam to control the elevation to be consistent.

[0039] like Fig.12 As shown, the rolling support provided in this embodiment mainly consists of a roller 9, a support portion 10 and a traction ring. The roller 9 is installed at the bottom of the support portion 10 through a roller bracket 11, a traction ring is provided on the roller bracket 11, and the mesh frame upper string ball 7 is installed and supported on the top of the support portion 10.

[0040] like Fig.12 As shown, as a temporary support, the rolling bearing also includes a door-shaped support rib 12, which includes a horizontal support plate on the top and vertical plates fixed vertically downward on both sides of the horizontal support plate. The grid upper chord ball 7 and the grid upper chord frame 8 are supported on the horizontal support plate, and a gap is left between the vertical plate and the sliding track 2 for installing shims.

[0041] The roller is a processed part, which is made of waste steel plates to adapt to the groove of the channel steel. The support part 10 and the supporting rib 12 are made of waste steel on site. The traction ring is made of round steel or purchased finished retaining ring, and the column pin is made of high-strength stud bolts. Finally, it is assembled according to the drawings.

[0042] After the grid frame is completely slid into place, the rolling support and the sliding track are removed, and a pad 14 is installed between the bottom of the supporting rib 12 and the moving track as a temporary support ( Fig.13 ), remove the roller 9 and remove the sliding track at the corresponding part of the roller ( Fig.14 ), and then install the support 15 at the bottom of the chord ball 7 on the grid ( Fig.15 ), and finally remove the supporting ribs 12 and the remaining sliding rails ( Fig.16 ).

[0043] The scope of protection claimed by the present invention is not limited to the above specific embodiments. For those skilled in the art, the present invention may have various deformations and changes. Any modifications, improvements and equivalent substitutions made within the concept and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A construction method for installing a spherical grid using a track sliding method. It is characterized in that include: Step 1: divide the spherical grid to be erected into several assembly units; Step 2: Set up a construction platform for assembling any assembly unit at high altitude, the construction platform is located below the concrete beam elevation at the sliding start end; lay sliding tracks on the top of the concrete beams on both sides of the sliding direction; Step 4: assemble the assembly units in sequence on the construction platform, support multiple rolling supports at the bottom of both sides of the assembled assembly units, wherein the rolling supports include rollers, and the rollers are rollingly mounted in the sliding track; and the assembly units are pulled by the traction device to move along the sliding direction; First, the assembly unit at the starting end is assembled on the construction platform. After the assembly is completed, the assembly unit at the starting end is pulled by a traction device to move along the sliding direction and stops after the end thereof slides out of the construction platform. Then, the middle assembly units are paired on the construction platform in turn, and any assembly unit that has been paired moves along the sliding direction together with the assembly unit that has moved to the previous position until it reaches the installation position of each assembly unit; The assembly units at the end are assembled in situ on the construction platform; Step 5: Install the spherical grid support and remove the rolling support and sliding track.

2. According to the track sliding method for installing a spherical grid construction method according to claim 1, Features: The sliding track is provided with guide rail sizes, with every 50 mm being a sliding process.

3. The method for installing a spherical grid by rail sliding method according to claim 2, Features: Embedded parts are symmetrically embedded on both sides of the sliding track installation position along the axial direction on the concrete beam surface, and the sliding track and the embedded parts are connected and fixed by welding.

4. The method for installing a spherical grid by rail sliding method according to claim 1, 2 or 3, Features: The traction device is a winch or an electric hoist, and the traction device is connected to the rolling support supporting the assembly unit through a steel wire rope, and connects the rolling supports of two adjacent assembly units.

5. The method for installing a spherical grid by rail sliding method according to claim 4, Features: Traction devices are arranged at the front end and the rear end in the sliding direction.

6. The method for installing a spherical grid by rail sliding method according to claim 1 or 5, Features: The rolling support also includes a support part and a traction ring. The roller is installed at the bottom of the support part through a roller bracket. The traction ring is arranged on the roller bracket. The chord ball on the grid is installed and supported on the top of the support part.

7. The method for installing a spherical grid by rail sliding method according to claim 6, Features: The rolling bearing also includes a door-shaped supporting rib plate, which includes a top horizontal supporting plate and vertical plates fixed vertically downward on both sides of the horizontal supporting plate. The chord ball on the grid is supported on the horizontal supporting plate, and a gap is left between the vertical plate and the sliding track.

8. The method for installing a spherical grid by rail sliding method according to claim 7, Features: In step five, when removing the rolling bearing and the sliding track, first install a shim between the bottom of the supporting rib and the moving track as a temporary support, remove the roller and remove the sliding track at the corresponding part of the roller, then install the bearing at the bottom of the upper chord ball of the truss, and finally remove the supporting rib and the remaining sliding track.

Citation Information

Patent Citations

  • Space truss structure aerial pairing integral slide installation method

    CN101775907A

  • Large-size net rack suspension cable mounting platform and suspension cable construction method

    CN101787795A

  • High altitude spherical net rack splicing method based on large gymnasium frame continuous beam

    CN103603502A

  • Large-span net rack aloft pairing, installing and overall horizontal moving method

    CN104594642A

  • Truss sliding structure

    CN204456914U