Thick film temperature monitoring method and device, storage medium and heating system
By collecting the E-FAST signal value only when the thick film device is in the working-on state in the thick film heating system, the problems of low efficiency and high cost of monitoring thick film temperature are solved, and efficient and economical monitoring of thick film temperature is achieved.
Patent Information
- Application Number
- CN202310668131.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-06-06
- Publication Date
- 2024-12-06
AI Technical Summary
The temperature monitoring efficiency of thick films in the prior art is low and costly, making it difficult to effectively monitor the temperature changes of thick films in heating scenarios.
By obtaining the E-FAST signal value output by the thick film device in the AC half wave as the effective signal value in the heating system, the signal acquisition is performed only when the thick film device is in the working opening state, and the thick film is monitored based on the collected signal value. The global temperature condition of the global area is optimized to improve monitoring efficiency.
It improves the working efficiency of thick film temperature monitoring, reduces monitoring costs, and ensures accurate monitoring and real-time response to thick film temperature changes.
Smart Images

Figure CN119085877A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of thick film technology, and in particular to a thick film temperature monitoring method, device, storage medium, and heating system. Background Art
[0002] Thick film is generally used in heating scenarios. It will output a weak sinusoidal signal (E-FAST signal) when working. If local overheating occurs, the amplitude of the E-FAST signal will increase significantly. At present, the E-FAST signal value is generally collected at fixed time intervals, and the thick film temperature is monitored based on the collected E-FAST signal value. However, this method of monitoring the thick film temperature is inefficient and costly. Based on this, how to improve the efficiency of monitoring the thick film temperature to reduce costs is a technical problem that needs to be solved urgently. Summary of the invention
[0003] The embodiments of the present application provide a thick film temperature monitoring method, device, storage medium, and heating system. The technical solution provided in the present application can improve the work efficiency of thick film temperature monitoring, thereby reducing the cost of thick film temperature monitoring.
[0004] Other features and advantages of the present application will become apparent from the following detailed description, or may be learned in part by the practice of the present application.
[0005] According to a first aspect of an embodiment of the present application, a thick film temperature monitoring method is provided, which is applied to a heating system, wherein the heating system includes a thick film device, and the method includes: within any heating cycle, if the thick film device is in an on-state and outputs an E-FAST signal within a current AC half-wave, then obtaining the E-FAST signal value output by the thick film device within the current AC half-wave as a valid E-FAST signal value; and based on the valid E-FAST signal value, monitoring the global temperature condition of the thick film device.
[0006] In some embodiments of the present application, based on the aforementioned scheme, the method further includes: in any heating cycle, if the intersection of two adjacent AC half-waves is detected, it is determined whether the thick film device is in a working on state in the current AC half-wave and outputs an E-FAST signal.
[0007] In some embodiments of the present application, based on the aforementioned scheme, the method further includes: if the thick film device does not output an E-FAST signal within the current AC half-wave, then obtaining other signal values generated by the heating system within the current AC half-wave.
[0008] In some embodiments of the present application, based on the aforementioned solution, the method further includes: if the thick film device is in a working off state in the current AC half-wave, then obtaining other signal values generated by the heating system in the current AC half-wave.
[0009] In some embodiments of the present application, based on the aforementioned scheme, the method also includes: before the heating system enters the first heating cycle, if the intersection of two adjacent AC half-waves is detected, then the target time for the heating system to enter the first heating cycle is calculated, and the heating system is controlled to enter the first heating cycle at the target time.
[0010] In some embodiments of the present application, based on the aforementioned scheme, the method also includes: obtaining the required heating power output by the thick film device, and obtaining the full load heating power of the thick film device when working at full load; according to the required heating power and the full load heating power, determining the number of AC half-waves in which the thick film device is in the working on state and the number of AC half-waves in which the thick film device is in the working off state within a heating cycle.
[0011] In some embodiments of the present application, based on the aforementioned scheme, the method further includes: determining the distribution order of the AC half-waves of the thick film device in the working on state in one heating cycle according to the number of AC half-waves of the thick film device in the working on state and the number of AC half-waves of the thick film device in the working off state in one heating cycle, and determining the distribution order of the AC half-waves of the thick film device in the working off state in one heating cycle.
[0012] In some embodiments of the present application, based on the aforementioned solution, the thick film device is in an on-state and outputs an E-FAST signal within the first AC half-wave of any heating cycle.
[0013] In some embodiments of the present application, based on the aforementioned scheme, obtaining the E-FAST signal value output by the thick film device within the current AC half-wave as a valid E-FAST signal value includes: obtaining the E-FAST signal value output by the thick film device within the current AC half-wave at a preset time interval to obtain multiple candidate E-FAST signal values; determining the maximum candidate E-FAST signal value from the multiple candidate E-FAST signal values as a valid E-FAST signal value.
[0014] In some embodiments of the present application, based on the aforementioned scheme, obtaining the E-FAST signal value output by the thick film device within the current AC half-wave as a valid E-FAST signal value includes: obtaining the peak value of the E-FAST signal output by the thick film device within the current AC half-wave as a valid E-FAST signal value.
[0015] In some embodiments of the present application, based on the aforementioned scheme, the global temperature condition of the thick film device is monitored based on the effective E-FAST signal value, including: if the effective E-FAST signal value is greater than a preset threshold, triggering a protection action for the thick film device.
[0016] According to the second aspect of an embodiment of the present application, a thick film temperature monitoring device is provided, which is arranged in a heating system, wherein the heating system includes a thick film device, and the thick film temperature monitoring device includes: an acquisition unit, which is used to, within any heating cycle, if the thick film device is in a working on state and outputs an E-FAST signal within a current AC half-wave, obtain the E-FAST signal value output by the thick film device within the current AC half-wave as a valid E-FAST signal value; and a monitoring unit, which is used to monitor the global temperature condition of the thick film device based on the valid E-FAST signal value.
[0017] According to a third aspect of an embodiment of the present application, a computer-readable storage medium is provided, characterized in that at least one program code is stored in the computer-readable storage medium, and the at least one program code is loaded and executed by a processor to implement the operations performed by the method described in any one of the first aspects above.
[0018] According to a fourth aspect of an embodiment of the present application, a heating system is provided, comprising one or more processors and one or more memories, wherein at least one program code is stored in the one or more memories, and the at least one program code is loaded and executed by the one or more processors to implement the operations performed by the method described in any one of the first aspects above.
[0019] The technical solution of the present application is applied to a heating system, which includes a thick film device. In the provided thick film temperature monitoring method, in any heating cycle, if the thick film device is in a working on state and outputs an E-FAST signal in the current AC half-wave, the E-FAST signal value output by the thick film device in the current AC half-wave is obtained as an effective E-FAST signal value; then based on the effective E-FAST signal value, the global domain temperature condition of the thick film device is monitored. It can be seen that through the technical solution of the present application, there is no need to continuously and uninterruptedly obtain the E-FAST signal value in a heating cycle of the thick film device. The E-FAST signal value will only be obtained when the AC half-wave is the thick film device in the working on state and outputs the E-FAST signal. It is not difficult to understand that since the acquisition timing of the E-FAST signal is specifically limited, the controller can complete the acquisition of other signals in the time period when the E-FAST signal value is not obtained, thereby improving the working efficiency of the controller, that is, improving the working efficiency of monitoring the thick film temperature, and thus reducing the cost of monitoring the thick film temperature.
[0020] It should be understood that the foregoing general description and the following detailed description are exemplary and explanatory only and are not restrictive of the present application. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] The drawings herein are incorporated into the specification and constitute a part of the specification, showing embodiments consistent with the present application, and together with the specification, are used to explain the principles of the present application. Obviously, the drawings described below are only some embodiments of the present application, and for ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work. In the drawings:
[0022] Figure 1 A schematic structural diagram of a heating system according to an embodiment of the present application is shown;
[0023] Figure 2 A schematic diagram of a thick film temperature monitoring method according to an embodiment of the present application is shown;
[0024] Figure 3 A schematic diagram of an alternating current half wave according to an embodiment of the present application is shown;
[0025] Figure 4 A detailed flow chart of determining the number of AC half-waves in which a thick film device is in an on-state and the number of AC half-waves in an off-state during a heating cycle according to an embodiment of the present application is shown;
[0026] Figure 5A detailed flow chart of obtaining the E-FAST signal value output by the thick film device in the current AC half-wave as the effective E-FAST signal value according to one embodiment of the present application is shown;
[0027] Figure 6 A block diagram of a thick film temperature monitoring device according to an embodiment of the present application is shown;
[0028] Figure 7 A schematic diagram of the structure of a computer system suitable for implementing the heating system of an embodiment of the present application is shown. DETAILED DESCRIPTION
[0029] Example embodiments will now be described more fully with reference to the accompanying drawings. However, example embodiments can be implemented in a variety of forms and should not be construed as limited to the examples set forth herein; rather, these embodiments are provided so that this application will be more comprehensive and complete and fully convey the concept of the example embodiments to those skilled in the art.
[0030] In addition, described feature, structure or characteristic can be combined in one or more embodiments in any suitable manner. In the following description, many specific details are provided to provide a full understanding of the embodiments of the present application. However, those skilled in the art will appreciate that the technical scheme of the present application can be put into practice without one or more of the specific details, or other methods, components, devices, steps, etc. can be adopted. In other cases, known methods, devices, realizations or operations are not shown or described in detail to avoid blurring the various aspects of the application.
[0031] The block diagrams shown in the accompanying drawings are merely functional entities and do not necessarily correspond to physically independent entities. That is, these functional entities may be implemented in software form, or in one or more hardware modules or integrated circuits, or in different networks and / or processor devices and / or microcontroller devices.
[0032] The flowcharts shown in the accompanying drawings are only exemplary and do not necessarily include all the contents and operations / steps, nor must they be executed in the order described. For example, some operations / steps can be decomposed, and some operations / steps can be combined or partially combined, so the actual execution order may change according to actual conditions.
[0033] It should be noted that the "multiple" mentioned in this article refers to two or more. "And / or" describes the association relationship of the associated objects, indicating that there can be three relationships. For example, A and / or B can mean: A exists alone, A and B exist at the same time, and B exists alone. The character " / " generally indicates that the associated objects before and after are in an "or" relationship.
[0034] It should be noted that the terms "first", "second", etc. in the specification and claims of the present application and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the objects used in this way can be interchanged where appropriate, so that the embodiments of the present application described herein can be implemented in an order other than those shown or described.
[0035] In order to make the purpose, technical solution and advantages of the present invention clearer, the technical solution in the embodiment of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiment of the present invention. Obviously, the described embodiment is only a part of the embodiment of the present invention, not all the embodiments. Based on the embodiment of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0036] In the following, some embodiments of the thick film temperature monitoring method of the present application will be described in detail with reference to the accompanying drawings. In the absence of conflict, the following embodiments and features in the embodiments can be combined with each other.
[0037] It should be noted that the technical solution of the present application is applied to a heating system, which includes a thick film device.
[0038] In order to enable those skilled in the art to better understand the technical solution of the present application, Figure 1 The structure of a heating system according to an embodiment of the present application is described.
[0039] See also Figure 1 , shows a schematic structural diagram of a heating system according to an embodiment of the present application.
[0040] The heating system can be connected to the neutral line and the live line of the power grid to provide power for the heating system.
[0041] The zero-crossing circuit in the heating system can be directly connected to the power grid to realize zero-crossing detection of the AC power output from the power grid, that is, the intersection point of two adjacent AC half-waves can be detected.
[0042] The E-FAST signal output by the thick film device in the heating system is relatively weak and cannot be directly detected by the controller (MCU). The E-FAST signal value can be collected and processed by the E-FAST signal detection circuit and then given to the controller, so that the controller can obtain the E-FAST signal value.
[0043] The thick film device in the heating system has an instant heating function. At the same time, the thick film device can output a rectified half-wave E-FAST signal. If the thick film device is locally overheated during heating, the amplitude of the E-FAST signal will increase significantly. Therefore, by collecting the E-FAST signal, the global temperature condition of the thick film device can be monitored.
[0044] The thick film switch in the heating system determines the working on state and the working off state of the thick film device. When the thick film switch is in the closed state, the thick film device is in the working on state, and when the thick film switch is in the open state, the thick film device is in the working off state. The thick film switch can perform the opening and closing actions according to the instructions sent by the received controller.
[0045] See also Figure 2 , shows a schematic flow chart of a thick film temperature monitoring method according to an embodiment of the present application, specifically including S110 to S120.
[0046] S110, in any heating cycle, if the thick film device is in the working on state and outputs an E-FAST signal in the current AC half-wave, the E-FAST signal value output by the thick film device in the current AC half-wave is obtained as the effective E-FAST signal value.
[0047] In order to make those skilled in the art better understand this embodiment, Figure 3 The concepts and implementation methods in this embodiment are explained.
[0048] See also Figure 3 , shows a schematic diagram of an AC half-wave according to an embodiment of the present application.
[0049] Among them, the time period from t1 to t2 is the first heating cycle. It can be understood that the time length of each heating cycle of the thick film device is consistent, and the time length of the heating cycle can be set according to actual conditions, such as Figure 3 The duration of one heating cycle shown is 8 AC half-wave cycles, or 80 ms.
[0050] It should be noted that in this application, when the heating system is plugged in (ie, connected to the power grid), it does not mean that the heating system will start working immediately, that is, the heating system will not immediately enter the first heating cycle. Before the heating system enters the first heating cycle, it can be executed as follows S10A.
[0051] S10A, before the heating system enters the first heating cycle, if the intersection of two adjacent AC half-waves is detected, the target time for the heating system to enter the first heating cycle is calculated, and the heating system is controlled to enter the first heating cycle at the target time.
[0052] In some embodiments, the following may be used: Figure 1 The zero-crossing circuit shown detects the intersection of two adjacent AC half-waves and can be as follows: Figure 1 The controller shown calculates the target time.
[0053] For example, if Figure 3 If the heating system is powered on at time t0 as shown, the power grid will input AC power to the heating system from time t0, and the zero-crossing point of the input AC power will be detected at time t1 through the zero-crossing circuit, which is the intersection of two adjacent AC half-waves. Then the controller calculates the target time for the heating system to enter the first heating cycle at time t1.
[0054] In some embodiments, the target time is an integer multiple of the AC half-wave period from the time when the crossing point is detected, such as 0 times, 1 times, 2 times, etc., of the AC half-wave period.
[0055] Among them, 0 times means that when the zero-crossing circuit detects the intersection of two adjacent AC half-waves, it will immediately control the heating system to enter the first heating cycle; 1 times means that when the zero-crossing circuit detects the intersection of two adjacent AC half-waves, it will control the heating system to enter the first heating cycle after another AC half-wave cycle. Figure 3 The first heating cycle shown is when the zero-crossing circuit detects the intersection of two adjacent AC half-waves and immediately controls the heating system to enter the first heating cycle.
[0056] In some embodiments, the target time is one heating cycle from the time when the intersection is detected, and each heating cycle entered controls the first AC half-wave to be in the working start state of the thick film device, and the E-FAST signal is output within the first AC half-wave. It can be understood that this embodiment can ensure that a valid E-FAST signal value can be detected in each heating cycle, avoiding the occurrence of missed detection signals due to too short a heating cycle or too few AC half-waves in the working start state.
[0057] In this embodiment, the target time for the heating system to enter the first heating cycle is calculated by detecting the intersection point of two adjacent AC half-waves, so that the heating system can enter the first heating cycle at a zero crossing point, preventing voltage shock to the heating system, thereby increasing the service life of the heating system.
[0058] Continue to see Figure 3 , wherein, in the first heating cycle, the shaded AC half-wave is the AC half-wave when the thick film device is in the working on state, and the blank AC half-wave is the AC half-wave when the thick film device is in the working off state.
[0059] It should be noted that the thick film device in the present application will output power within the AC half-wave when it is in the working on state during a heating cycle, and will not output power within the AC half-wave when it is in the working off state, so that the actual power output within a heating cycle matches the heating power required by the heating system.
[0060] In each heating cycle, the number and distribution order of the AC half-waves in which the thick film device is in the working on state are related to the heating power required by the heating stage of the heating system. Figure 4 The steps shown determine the number of AC half-waves in which the thick film device is in an operational on state and the number of AC half-waves in which the thick film device is in an operational off state during a heating cycle, and include S100 to S200.
[0061] S100, obtaining the required heating power output by the thick film device, and obtaining the full-load heating power of the thick film device when working at full load.
[0062] In some embodiments, the required heating power that the thick film device needs to output in each heating cycle and the full-load heating power when working at full load can be obtained before the heating system enters the first heating cycle or when entering the first heating cycle.
[0063] In some implementations, when the heating system enters a certain heating cycle, the required heating power that the thick film device needs to output during the heating cycle and the full-load heating power of the thick film device when working at full load can be obtained.
[0064] Continue to see Figure 4 , S200, determining the number of AC half-waves in which the thick film device is in an on-state and the number of AC half-waves in an off-state in a heating cycle according to the required heating power and the full-load heating power.
[0065] In this embodiment, the specific calculation formula is:
[0066] W required heating power = W full load heating power * N / (N + M), where N is the number of AC half waves in which the thick film device is in the working on state in one heating cycle; M is the number of AC half waves in which the thick film device is in the working off state in one heating cycle.
[0067] For example, if it is calculated that the required heating power that the thick film device needs to output in the first heating cycle of the heating system is 400W, and the full-load heating power of the thick film device when working at full load is 800W, then it can be determined that the number of AC half-waves in which the thick film device is in the working on state in the first heating cycle of the heating system is 4, and the number of AC half-waves in which the thick film device is in the working off state is 4. The number of AC half-waves in various states can be as follows: Figure 3As shown, in the first heating cycle of the heating system, there are 4 shaded AC half-waves and 4 blank AC half-waves.
[0068] In this embodiment, after determining the number of AC half-waves in which the thick film device is in the working on state and the number of AC half-waves in the working off state within a heating cycle, the distribution order of the AC half-waves in various states within a heating cycle can also be determined based on the determined number. Specifically, it can be performed as follows S10B.
[0069] S10B, determining the distribution order of the AC half-waves in the working on state of the thick film device in one heating cycle, and determining the distribution order of the AC half-waves in the working off state of the thick film device in one heating cycle according to the number of AC half-waves in the working on state of the thick film device and the number of AC half-waves in the working off state of the thick film device.
[0070] In some embodiments, the distribution order of the AC half-waves in various states in any heating cycle may be to distribute the AC half-waves in the working on state first, and then distribute the AC half-waves in the working off state.
[0071] In some embodiments, the thick film device can be in an operational on state and output an E-FAST signal during the first AC half-wave of any heating cycle. Figure 3 The first AC half-wave of the first heating cycle is shown as a shaded portion, where an output E-FAST signal is present.
[0072] In some implementations, the distribution order of the AC half-waves in various states in any heating cycle may be randomly distributed.
[0073] Specifically, the present application does not limit the specific implementation method of how to determine the distribution order according to the number of AC half-waves in various states, and can be designed according to actual conditions.
[0074] Continue to see Figure 3 , wherein the rectified half-wave of the dotted line portion represents the output E-FAST signal. The E-FAST signal output by the present application is a rectified half-wave, which can improve the efficiency of monitoring the thick film temperature compared to the sine wave E-FAST signal of the prior art.
[0075] It should be noted that within an E-FAST signal half-wave, only when the AC half-wave is in the working on state can a valid E-FAST signal value be obtained. If within an E-FAST signal half-wave, the AC half-wave is in the working off state, only an invalid E-FAST signal value will be obtained. Figure 3In the first heating cycle shown, valid E-FAST signal values can only be obtained within 4 corresponding AC half waves.
[0076] Therefore, in order to improve the working efficiency of monitoring the thick film temperature, the present application may be performed according to the following S10C before obtaining the E-FAST signal value.
[0077] S10C, in any heating cycle, if the intersection of two adjacent AC half-waves is detected, it is determined whether the thick film device is in the working on state in the current AC half-wave and an E-FAST signal is output.
[0078] In some implementations, the crossing point between two adjacent AC half-waves may be detected by a zero-crossing circuit.
[0079] For example, in Figure 3 At the time t1 shown, because it is determined that the thick film device is in the on state and outputs the E-FAST signal in the current AC half-wave, the E-FAST signal value is obtained in the current AC half-wave.
[0080] In this embodiment, by judging at the intersection whether the current AC half-wave is in the working on state and outputting the E-FAST signal, it is possible to effectively avoid obtaining the E-FAST signal value when the current AC half-wave is in the working off state or when the E-FAST signal is not output, thereby improving the efficiency of monitoring the thick film temperature.
[0081] In the present application, in order to further improve the working efficiency of monitoring the thick film temperature, the following step S10D may also be performed.
[0082] S10D: If the thick film device does not output an E-FAST signal within the current AC half-wave, then obtain other signal values generated by the heating system within the current AC half-wave.
[0083] It should be noted that, in this embodiment, the other signal values include but are not limited to temperature sensor voltage AD values, AC voltage AD values, and the like.
[0084] For example, in Figure 3 In the first heating cycle shown, it can be clearly seen that the thick film device does not output the E-FAST signal within the AC half-waves corresponding to 1 and 3, so other signal values can be obtained within the AC half-waves corresponding to 1 and 3.
[0085] In the present application, in order to further improve the working efficiency of monitoring the thick film temperature, the following step S10E may also be performed.
[0086] S10E: If the thick film device is in a closed working state in the current AC half-wave, then obtaining other signal values generated by the heating system in the current AC half-wave.
[0087] For example, in Figure 3 In the first heating cycle shown, the thick film device is in the working off state in the AC half-waves corresponding to 2 and 3, so the E-FAST signal value is not obtained in the AC half-waves corresponding to 2 and 3. Even if there is an output E-FAST signal in the AC half-wave corresponding to 2, if the E-FAST signal is collected in the AC half-wave, only an invalid E-FAST signal value will be obtained. Therefore, in this embodiment, the working efficiency of monitoring the thick film temperature can be greatly improved.
[0088] Continue to see Figure 2 In S110, the E-FAST signal value output by the thick film device within the current AC half-wave is obtained. As implementation methods of the effective E-FAST signal value, there are at least the following two implementation methods.
[0089] The first implementation method can be as follows Figure 5 Execute in the manner shown.
[0090] See also Figure 5 , shows a detailed flow chart of obtaining the E-FAST signal value output by the thick film device within the current AC half-wave as the effective E-FAST signal value according to an embodiment of the present application, specifically including S111 to S112.
[0091] S111, acquiring the E-FAST signal value output by the thick film device within the current AC half-wave at a preset time interval to obtain a plurality of candidate E-FAST signal values.
[0092] It should be noted that the preset time interval can be set to 100us, 125us, etc., and the specific application is not limited here.
[0093] S112, determining a maximum candidate E-FAST signal value from the multiple candidate E-FAST signal values as a valid E-FAST signal value.
[0094] Because if the heating system is locally overheated during heating, the amplitude of the E-FAST signal will increase. It can be understood that in this embodiment, the maximum candidate E-FAST signal value is used as the effective E-FAST signal value, which can reflect whether there is a change in the amplitude of the E-FAST signal within an AC half-wave, thereby facilitating the detection of the global temperature condition of the thick film device.
[0095] A second implementation manner is to obtain the peak value of the E-FAST signal output by the thick film device within the current AC half-wave as the effective E-FAST signal value.
[0096] In this embodiment, the peak value of the output E-FAST signal wave can be obtained by continuously acquiring the form of the E-FAST signal within the current AC half-wave.
[0097] Continue to see Figure 2 , S120, monitoring the global temperature condition of the thick film device based on the effective E-FAST signal value.
[0098] In some implementations, the implementation of monitoring the global temperature status of the thick film device based on the effective E-FAST signal value can be performed as follows S121.
[0099] S121: If the effective E-FAST signal value is greater than a preset threshold, triggering a protection action for the thick film device.
[0100] It should be noted that the preset threshold can be designed according to actual conditions and is not limited in this application.
[0101] It should also be noted that the protection action may be to shut down the heating system to protect the heating system, or to reduce the required heating power of the current heating cycle to protect the heating system. Specifically, the specific execution action for protecting the heating system can be designed according to actual conditions, and this application does not limit this.
[0102] In the technical solutions provided in some embodiments of the present application, it is applied to a heating system, which includes a thick film device. In the thick film temperature monitoring method provided, in any heating cycle, if the thick film device is in a working on state and outputs an E-FAST signal in the current AC half-wave, the E-FAST signal value output by the thick film device in the current AC half-wave is obtained as an effective E-FAST signal value; then based on the effective E-FAST signal value, the global domain temperature condition of the thick film device is monitored. It can be seen that through the technical solution of the present application, there is no need to continuously and uninterruptedly obtain the E-FAST signal value in a heating cycle of the thick film device. The E-FAST signal value will only be obtained when the AC half-wave is the thick film device in the working on state and outputs the E-FAST signal. It is not difficult to understand that since the acquisition timing of the E-FAST signal is specifically limited, the controller can complete the acquisition of other signals in the time period when the E-FAST signal value is not obtained, thereby improving the working efficiency of the controller, that is, improving the working efficiency of monitoring the thick film temperature, and thus reducing the cost of monitoring the thick film temperature.
[0103] The following describes an apparatus embodiment of the present application, which can be used to perform the thick film temperature monitoring method in the above-mentioned embodiment of the present application. For details not disclosed in the apparatus embodiment of the present application, please refer to the above-mentioned embodiment of the thick film temperature monitoring method of the present application.
[0104] Figure 6 A block diagram of a thick film temperature monitoring device according to an embodiment of the present application is shown.
[0105] Reference Figure 6 As shown, a thick film temperature monitoring device 600 according to an embodiment of the present application is arranged in a heating system, the heating system includes a thick film device, and the thick film temperature monitoring device 600 includes: an acquisition unit 601 and a monitoring unit 602 .
[0106] Among them, the acquisition unit 601 is used to obtain the E-FAST signal value output by the thick film device within the current AC half-wave as the effective E-FAST signal value if the thick film device is in the working on state and outputs the E-FAST signal within any heating cycle; the monitoring unit 602 is used to monitor the global temperature status of the thick film device based on the effective E-FAST signal value.
[0107] In some embodiments of the present application, based on the aforementioned scheme, the thick film temperature monitoring device 600 also includes a judgment unit, which is used to: in any heating cycle, if the intersection of two adjacent AC half-waves is detected, then determine whether the thick film device is in a working on state in the current AC half-wave and output an E-FAST signal.
[0108] In some embodiments of the present application, based on the aforementioned scheme, the acquisition unit 601 is also used for: if the thick film device does not output an E-FAST signal within the current AC half-wave, then acquiring other signal values generated by the heating system within the current AC half-wave.
[0109] In some embodiments of the present application, based on the above scheme, the acquisition unit 601 is also used for: if the thick film device is in a working off state in the current AC half-wave, then acquiring other signal values generated by the heating system in the current AC half-wave.
[0110] In some embodiments of the present application, based on the aforementioned scheme, the thick film temperature monitoring device 600 also includes a calculation unit, which is used to: before the heating system enters the first heating cycle, if the intersection of two adjacent AC half-waves is detected, calculate the target time for the heating system to enter the first heating cycle, and control the heating system to enter the first heating cycle at the target time.
[0111] In some embodiments of the present application, based on the aforementioned scheme, the thick film temperature monitoring device 600 also includes a determination unit, which is used to: obtain the required heating power output by the thick film device, and obtain the full load heating power of the thick film device when working at full load; according to the required heating power and the full load heating power, determine the number of AC half-waves in which the thick film device is in the working on state and the number of AC half-waves in which the thick film device is in the working off state within a heating cycle.
[0112] In some embodiments of the present application, based on the aforementioned scheme, the determination unit is also used to: determine the distribution order of the AC half-waves of the thick film device in the working on state in a heating cycle according to the number of AC half-waves of the thick film device in the working on state and the number of AC half-waves in the working off state in a heating cycle, and determine the distribution order of the AC half-waves of the thick film device in the working off state in a heating cycle.
[0113] In some embodiments of the present application, based on the aforementioned solution, the determination unit is further used to: determine that the thick film device is in a working on state and outputs an E-FAST signal within the first AC half-wave of any heating cycle.
[0114] In some embodiments of the present application, based on the aforementioned scheme, the acquisition unit 601 is also used to: acquire the E-FAST signal value output by the thick film device within the current AC half-wave at a preset time interval to obtain multiple candidate E-FAST signal values; determine the maximum candidate E-FAST signal value from the multiple candidate E-FAST signal values as the valid E-FAST signal value.
[0115] In some embodiments of the present application, based on the aforementioned solution, the acquisition unit 601 is further used to: acquire the peak value of the E-FAST signal output by the thick film device within the current AC half-wave as a valid E-FAST signal value.
[0116] In some embodiments of the present application, based on the above-mentioned solution, the monitoring unit 602 is further used to: trigger a protection action for the thick film device if the effective E-FAST signal value is greater than a preset threshold.
[0117] Figure 7 A schematic diagram of the structure of a computer system suitable for implementing the heating system of an embodiment of the present application is shown.
[0118] It should be noted that Figure 7 The computer system 700 of the heating system shown is only an example and should not bring any limitation to the functions and scope of use of the embodiments of the present application.
[0119] like Figure 7 As shown, the computer system 700 includes a central processing unit (CPU) 701, which can perform various appropriate actions and processes according to the program stored in the read-only memory (ROM) 702 or the program loaded from the storage part 708 to the random access memory (RAM) 703, such as executing the method described in the above embodiment. In the RAM 703, various programs and data required for system operation are also stored. The CPU 701, the ROM 702 and the RAM 703 are connected to each other via a bus 704. An input / output (I / O) interface 705 is also connected to the bus 704.
[0120] The following components are connected to the I / O interface 705: an input section 706 including a keyboard, a mouse, etc.; an output section 707 including a cathode ray tube (CRT), a liquid crystal display (LCD), etc., and a speaker, etc.; a storage section 708 including a hard disk, etc.; and a communication section 709 including a network interface card such as a LAN (Local Area Network) card, a modem, etc. The communication section 709 performs communication processing via a network such as the Internet. A drive 710 is also connected to the I / O interface 705 as needed. A removable medium 711, such as a magnetic disk, an optical disk, a magneto-optical disk, a semiconductor memory, etc., is installed on the drive 710 as needed so that a computer program read therefrom is installed into the storage section 708 as needed.
[0121] In particular, according to an embodiment of the present application, the process described above with reference to the flowchart can be implemented as a computer software program. For example, an embodiment of the present application includes a computer program product, which includes a computer program carried on a computer-readable medium, and the computer program includes a program code for executing the method shown in the flowchart. In such an embodiment, the computer program can be downloaded and installed from a network through a communication section 709, and / or installed from a removable medium 711. When the computer program is executed by a central processing unit (CPU) 701, various functions defined in the system of the present application are executed.
[0122] It should be noted that the computer-readable medium shown in the embodiment of the present application may be a computer-readable signal medium or a computer-readable storage medium or any combination of the above two. The computer-readable storage medium may be, for example, - but not limited to - an electrical, magnetic, optical, electromagnetic, infrared, or semiconductor system, device or device, or any combination of the above. More specific examples of computer-readable storage media may include, but are not limited to: an electrical connection with one or more wires, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM), a flash memory, an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the above. In the present application, a computer-readable storage medium may be any tangible medium containing or storing a program, which may be used by an instruction execution system, device or device or used in combination with it. In the present application, a computer-readable signal medium may include a data signal propagated in a baseband or as part of a carrier wave, wherein a computer-readable program code is carried. Such propagated data signals may take a variety of forms, including but not limited to electromagnetic signals, optical signals, or any suitable combination of the above. Computer-readable signal media may also be any computer-readable medium other than computer-readable storage media, which may send, propagate, or transmit programs for use by or in conjunction with an instruction execution system, apparatus, or device. The program code contained on the computer-readable medium may be transmitted using any appropriate medium, including but not limited to: wireless, wired, etc., or any suitable combination of the above.
[0123] The flowchart and block diagram in the accompanying drawings illustrate the possible architecture, functions and operations of the system, method and computer program product according to various embodiments of the present application. Wherein, each box in the flowchart or block diagram can represent a module, a program segment, or a part of the code, and the above-mentioned module, program segment, or a part of the code contains one or more executable instructions for realizing the specified logical function. It should also be noted that in some alternative implementations, the functions marked in the box can also occur in a different order from the order marked in the accompanying drawings. For example, two boxes represented in succession can actually be executed substantially in parallel, and they can sometimes be executed in the opposite order, depending on the functions involved. It should also be noted that each box in the block diagram or flowchart, and the combination of boxes in the block diagram or flowchart can be implemented with a dedicated hardware-based system that performs a specified function or operation, or can be implemented with a combination of dedicated hardware and computer instructions.
[0124] The units involved in the embodiments described in this application may be implemented by software or hardware, and the units described may also be set in a processor. The names of these units do not, in some cases, constitute limitations on the units themselves.
[0125] As another aspect, the present application further provides a computer program product or a computer program, the computer program product or the computer program comprising computer instructions, the computer instructions being stored in a computer-readable storage medium. A processor of a computer device reads the computer instructions from the computer-readable storage medium, and the processor executes the computer instructions, so that the computer device executes the thick film temperature monitoring method described in the above embodiment.
[0126] As another aspect, the present application also provides a computer-readable medium, which may be included in the heating system described in the above embodiment; or may exist independently without being assembled into the heating system. The above computer-readable medium carries one or more programs, and when the above one or more programs are executed by a heating system, the heating system implements the thick film temperature monitoring method described in the above embodiment.
[0127] It should be noted that, although several modules or units of the equipment for action execution are mentioned in the above detailed description, this division is not mandatory. In fact, according to the embodiments of the present application, the features and functions of two or more modules or units described above can be embodied in one module or unit. On the contrary, the features and functions of one module or unit described above can be further divided into being embodied by multiple modules or units.
[0128] Through the description of the above implementation methods, it is easy for those skilled in the art to understand that the example implementation methods described here can be implemented by software or by combining software with necessary hardware. Therefore, the technical solution according to the implementation methods of the present application can be embodied in the form of a software product, which can be stored in a non-volatile storage medium (which can be a CD-ROM, a USB flash drive, a mobile hard disk, etc.) or on a network, and includes several instructions to enable a computing device (which can be a personal computer, a server, a touch terminal, or a network device, etc.) to execute the method according to the implementation methods of the present application.
[0129] Those skilled in the art will readily appreciate other embodiments of the present application after considering the specification and practicing the embodiments disclosed herein. The present application is intended to cover any variations, uses or adaptations of the present application, which follow the general principles of the present application and include common knowledge or customary techniques in the art that are not disclosed in the present application. It should be understood that the present application is not limited to the precise structures described above and shown in the accompanying drawings, and various modifications and changes can be made without departing from the scope thereof. The scope of the present application is limited only by the appended claims.
Claims
1. A thick film temperature monitoring method, characterized in that: Applied to a heating system, the heating system comprising a thick film device, the method comprising: In any heating cycle, if the thick film device is in a working on state and outputs an E-FAST signal in a current AC half-wave, the E-FAST signal value output by the thick film device in the current AC half-wave is obtained as a valid E-FAST signal value; Based on the effective E-FAST signal value, a global temperature condition of the thick film device is monitored.
2. The method according to claim 1, characterized in that The method further comprises: In any heating cycle, if the intersection of two adjacent AC half-waves is detected, it is determined whether the thick film device is in the working on state in the current AC half-wave and outputs an E-FAST signal.
3. The method according to claim 1, characterized in that The method further comprises: If the thick film device does not output an E-FAST signal within the current AC half-wave, then other signal values generated by the heating system within the current AC half-wave are obtained.
4. The method according to claim 1, characterized in that: The method further comprises: If the thick film device is in the working closed state in the current AC half-wave, then other signal values generated by the heating system in the current AC half-wave are obtained.
5. The method according to claim 1, characterized in that The method further comprises: Before the heating system enters the first heating cycle, if the intersection of two adjacent AC half-waves is detected, the target time for the heating system to enter the first heating cycle is calculated, and the heating system is controlled to enter the first heating cycle at the target time.
6. The method according to claim 1, characterized in that The method further comprises: Obtaining the required heating power output by the thick film device, and obtaining the full-load heating power of the thick film device when working at full load; According to the required heating power and the full-load heating power, the number of AC half-waves in which the thick film device is in an on-state and the number of AC half-waves in which the thick film device is in an off-state in a heating cycle are determined.
7. The method according to claim 6, characterized in that The method further comprises: According to the number of AC half-waves in which the thick film device is in the working on state and the number of AC half-waves in the working off state in a heating cycle, the distribution order of the AC half-waves in which the thick film device is in the working on state in a heating cycle is determined, and the distribution order of the AC half-waves in which the thick film device is in the working off state in a heating cycle is determined.
8. The method according to claim 7, characterized in that The thick film device is in an operating on state and outputs an E-FAST signal within the first AC half-wave of any heating cycle.
9. The method according to claim 1, characterized in that: The step of obtaining the E-FAST signal value output by the thick film device in the current AC half-wave as a valid E-FAST signal value includes: Acquire the E-FAST signal value output by the thick film device in the current AC half-wave at a preset time interval to obtain a plurality of candidate E-FAST signal values; A maximum candidate E-FAST signal value is determined from the plurality of candidate E-FAST signal values as a valid E-FAST signal value.
10. The method according to claim 1, characterized in that The step of obtaining the E-FAST signal value output by the thick film device in the current AC half-wave as a valid E-FAST signal value includes: The peak value of the E-FAST signal output by the thick film device within the current AC half-wave is obtained as the effective E-FAST signal value.
11. The method according to claim 1, characterized in that: The monitoring of the global temperature condition of the thick film device based on the effective E-FAST signal value comprises: If the effective E-FAST signal value is greater than a preset threshold, a protection action for the thick film device is triggered.
12. A thick film temperature monitoring device, characterized in that: The heating system includes a thick film device, and the thick film temperature monitoring device includes: an acquisition unit, configured to acquire, in any heating cycle, if the thick film device is in a working on state and outputs an E-FAST signal in a current AC half-wave, an E-FAST signal value output by the thick film device in the current AC half-wave as a valid E-FAST signal value; A monitoring unit is used to monitor the global temperature status of the thick film device based on the effective E-FAST signal value.
13. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores at least one program code, and the at least one program code is loaded and executed by a processor to implement the operations performed by the method according to any one of claims 1 to 11.
14. A heating system, characterized in that: The method comprises one or more processors and one or more memories, wherein at least one program code is stored in the one or more memories, and the at least one program code is loaded and executed by the one or more processors to implement the method according to any one of claims 1 to 11.