Debugging method and system for LNG cold energy power generation device

Through systematic propane replacement, filling and performance test methods, the problem of lack of standardization for the debugging of LNG cold energy power generation devices is solved, and the operating efficiency and safety of the equipment are improved. It is suitable for the debugging of cold energy power generation devices in LNG receiving stations.

CN119086132APending Publication Date: 2024-12-06CNOOC GAS & POWER GRP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411261060.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-10
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

The existing LNG cold energy power generation device debugging methods lack systematicity and standardization, which makes it difficult to improve the operating efficiency and safety of equipment. The operating methods of different operators vary greatly, which may lead to safety accidents.

Method used

A systematic debugging method including propane replacement and filling, split intermediate medium gasifier, propane circulation pump and turbine/generator performance test is proposed to ensure the operating procedures and standards of each stage, through propane replacement and filling module, The performance test module is fully debugged.

Benefits of technology

Without affecting the gasification and outbound production of the LNG receiving station, the debugging quality, safety and efficiency of the LNG cooling power generation device is significantly improved, ensuring the safe and smooth operation of the equipment, and is suitable for low-temperature Rankine cycle single-stage LNG cooling power generation system. .

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119086132A_ABST
    Figure CN119086132A_ABST
Patent Text Reader

Abstract

The invention relates to a debugging method and system for an LNG (Liquefied Natural Gas) cold energy power generation device, and is characterized in that the method comprises the following steps: carrying out propane replacement and filling on the LNG cold energy power generation device; carrying out performance test on the split type intermediate medium gasifier in the LNG cold energy power generation device; performing a performance test on a propane circulating pump in the LNG cold energy power generation device; performing performance test on a turbine and a generator in the LNG cold energy power generation device; the LNG cold energy power generation device debugging method has general applicability and can be widely applied to the field of debugging of cold energy power generation devices in LNG receiving stations.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of liquefied natural gas (LNG) cold energy power generation, and in particular to a debugging method and system for an LNG cold energy power generation device. Background Art

[0002] In recent years, cold energy power generation has become a major innovation in the cold energy utilization industry. Compared with traditional thermal power generation, it has significant advantages in energy saving and environmental protection.

[0003] At present, the existing debugging of LNG cold energy power generation equipment is generally monotonous according to the debugging experience of the receiving station. For example, the functional debugging of the equipment before leaving the factory or after installation, the parameters obtained can only be used as performance test or factory acceptance criteria, and cannot be used as a reference in the actual operation of the system. At the same time, there is no systematic summary and induction of the entire debugging process. The operation methods and operation effects of on-site operators of different levels will be quite different, which will affect the equipment operation efficiency and production and operation costs, and cannot effectively improve the debugging quality, safety and efficiency of LNG cold energy power generation equipment, and even serious safety accidents may occur. Summary of the invention

[0004] In view of the above problems, an object of the present invention is to provide a debugging method and system for an LNG cold energy power generation device, which can effectively improve the debugging quality, safety and efficiency of the LNG cold energy power generation device.

[0005] To achieve the above object, the present invention adopts the following technical solutions: In a first aspect, a debugging method for an LNG cold energy power generation device is provided, comprising: Propane replacement and filling of LNG cold energy power generation equipment; Conduct performance tests on the split intermediate medium vaporizer in the LNG cold energy power generation device; Conduct performance tests on propane circulation pumps in LNG cold energy power generation equipment; Conduct performance tests on turbines and generators in LNG cold energy power generation equipment; Stop the propane circulation pump, turbine and generator to complete the commissioning of the LNG cold energy power generation unit.

[0006] Furthermore, the standard for completion of the propane replacement and filling is that the propane content in the process gas pipeline of the LNG cold energy power generation device meets the set value and the propane liquid levels of the intermediate medium vaporizer, LNG vaporizer and propane circulation pump meet the set value.

[0007] Furthermore, the performance test of the split intermediate medium gasifier in the LNG cold energy power generation device includes: Establish seawater flow rates for natural gas heaters; Establish LNG / NG flow rates for LNG vaporizers; Keep the LNG flow of the LNG vaporizer at the load flow, and ensure stable operation for no less than the preset time.

[0008] Further, the establishing of the seawater flow rate of the natural gas heater includes: Open the seawater inlet valve and the seawater outlet valve; Open the first exhaust valve and the second exhaust valve, and when the sound of water flowing through the exhaust valve reaches a preset time, close the first exhaust valve and the second exhaust valve; Gradually increase the seawater flow rate of the natural gas heater to the rated flow rate; Open the natural gas outlet valve to balance the natural gas heater output pressure and the downstream natural gas pipeline pressure.

[0009] Further, the establishing of the LNG / NG flow rate of the LNG vaporizer includes: Open the LNG inlet flow control valve and adjust the opening of the liquid-phase connecting valve to ensure that the propane liquid level of the intermediate medium vaporizer and the LNG vaporizer is within the set range; Monitor the tube side temperature of the LNG vaporizer through a temperature sensor; Increase the opening of the LNG inlet flow control valve and monitor the LNG inlet flow through the flow sensor.

[0010] Furthermore, the performance test of the propane circulating pump in the LNG cold energy power generation device includes: Start the propane circulation pump: Adjust the opening of the LNG inlet flow control valve so that the LNG flow of the LNG vaporizer drops to 40% of the rated load; Adjust the opening of the liquid-phase connecting valve to ensure that the propane liquid level of the intermediate medium vaporizer and the LNG vaporizer is within the set range; Shield the low-low interlock of the propane circulating pump, make sure that the opening of the return valve of the propane circulating pump reaches the set value, start the propane circulating pump, make sure that the motor ampere rises to the starting current value, and drops to the normal ampere range within several seconds; Automatically adjust the liquid level of the intermediate medium vaporizer through the liquid level regulating valve; Close the liquid phase connecting valve and gradually close the gas phase bypass valve until the shell side pressure of the LNG vaporizer reaches the set value; Open the low-low interlock of the propane circulation pump and adjust the opening of the reflux valve of the propane circulation pump so that the flow rates of the propane circulation pump are the minimum flow rate, 95% of the rated flow rate, the rated flow rate, the flow rate close to the best efficiency point and 120% of the rated flow rate respectively; Adjust the opening of the LNG inlet flow control valve so that the LNG flow of the LNG vaporizer increases to the rated load; Shut down the propane circulation pump: Adjust the opening of the LNG inlet flow control valve so that the LNG flow of the LNG vaporizer drops to 40% of the rated load; Close the liquid level regulating valve and adjust the opening of the reflux valve of the propane circulating pump to reduce the flow rate of the propane circulating pump to the minimum flow rate; Stop the propane circulation pump; Fully open the liquid-phase connecting valve and the gas-phase connecting valve; Open the gas phase bypass valve until the opening reaches 100%, with each step not exceeding 5±1%.

[0011] Furthermore, the performance test of the turbine and the generator in the LNG cold energy power generation device includes: Start the lubricating oil system, N2 sealing system and sealing oil system in the turbine; Start the propane circulation pump and adjust the opening of the LNG inlet flow control valve so that the LNG flow of the LNG vaporizer is 50% of the rated load; Start the process gas sealing system in the turbine and turn on the turbine and generator; Start the grid connection procedure for turbines and generators; Close the turbine start valve.

[0012] Furthermore, the stopping of the propane circulation pump, the turbine and the generator to complete the commissioning of the LNG cold energy power generation device includes: Open the gas phase bypass valve until the opening reaches 100%, and close the turbine quick-closing valve and the adjustable nozzle; Open the turbine drain valve; Close the lubricating oil system, process gas sealing system, sealing oil system and turbine outlet valve in the turbine to complete the turbine shutdown; Send a pump stop command to the propane circulation pump to stop the propane circulation pump.

[0013] Furthermore, the stopping of the propane circulation pump, the turbine and the generator to complete the commissioning of the LNG cold energy power generation device also includes: When the LNG flow rate is at rated load, start the turbine and generator again, repeat the performance test of the turbine and generator in the LNG cold energy power generation device, and complete the full load test.

[0014] On the other hand, a debugging system for an LNG cold energy power generation device is provided, comprising: Propane replacement and filling module, used for propane replacement and filling of LNG cold energy power generation equipment; The first performance test module is used to perform a performance test on a split intermediate medium gasifier in an LNG cold energy power generation device; The second performance test module is used to perform performance tests on the propane circulation pump in the LNG cold energy power generation device; The third energy test module is used to perform performance tests on turbines and generators in LNG cold energy power generation devices.

[0015] The present invention adopts the above technical solution, which has the following advantages: 1. The debugging method of the LNG cold energy power generation device proposed in the present invention can effectively improve the debugging quality, safety and efficiency of the LNG cold energy power generation project without affecting the gasification and export production of the LNG receiving station.

[0016] 2. The present invention determines the operation process and completion standards of each stage of debugging to ensure the safe and smooth operation of the equipment, thereby ensuring the normal operation of production operations.

[0017] 3. The overall debugging method of the LNG cold energy power generation device proposed in the present invention is applicable to a single-stage LNG cold energy power generation system based on a low-temperature Rankine cycle and has universal applicability.

[0018] In summary, the present invention can be widely used in the field of commissioning of cold energy power generation devices in LNG receiving stations. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Various other advantages and benefits will become apparent to those of ordinary skill in the art by reading the detailed description of the preferred embodiments below. The accompanying drawings are only for the purpose of illustrating the preferred embodiments and are not to be considered as limiting the present invention. Throughout the accompanying drawings, the same reference numerals are used to represent the same components. In the accompanying drawings: Figure 1 It is a structural schematic diagram of an LNG cold energy power generation device provided by one embodiment of the present invention; Figure 2 It is a schematic diagram of a method flow provided by an embodiment of the present invention. DETAILED DESCRIPTION

[0020] The exemplary embodiments of the present invention will be described in more detail below with reference to the accompanying drawings. Although the exemplary embodiments of the present invention are shown in the accompanying drawings, it should be understood that the present invention can be implemented in various forms and should not be limited by the embodiments described herein. On the contrary, these embodiments are provided in order to enable a more thorough understanding of the present invention and to fully convey the scope of the present invention to those skilled in the art.

[0021] It should be understood that the terms used herein are only for the purpose of describing specific example embodiments and are not intended to be limiting. Unless the context clearly indicates otherwise, the singular forms "one", "an" and "said" as used herein may also be meant to include plural forms. The terms "include", "comprise", "contain", and "have" are inclusive, and therefore specify the existence of stated features, steps, operations, elements and / or parts, but do not exclude the existence or addition of one or more other features, steps, operations, elements, parts, and / or combinations thereof. The method steps, processes, and operations described herein are not interpreted as necessarily requiring them to be performed in the specific order described or illustrated, unless the execution order is clearly indicated. It should also be understood that additional or alternative steps may be used.

[0022] Although the terms first, second, third, etc. can be used in the text to describe multiple elements, components, regions, layers and / or sections, these elements, components, regions, layers and / or sections should not be limited by these terms. These terms can only be used to distinguish an element, component, region, layer or section from another region, layer or section. Unless the context clearly indicates, terms such as "first", "second" and other numerical terms do not imply order or sequence when used in the text. Therefore, the first element, component, region, layer or section discussed below can be referred to as the second element, component, region, layer or section without departing from the teaching of the example embodiments.

[0023] Since the existing debugging of LNG cold energy power generation devices is generally monotonous according to the debugging experience of the receiving station, such as the functional debugging of the equipment before leaving the factory or after installation, the parameters obtained can only be used as performance tests or factory acceptance standards, but cannot be used as a reference in the actual operation of the system. At the same time, there is no systematic summary and induction of the entire debugging process. The operation methods and operation effects of on-site operators of different levels will be quite different, which will affect the equipment operation efficiency and production and operation costs, and cannot effectively improve the debugging quality, safety and efficiency of the LNG cold energy power generation device. In serious cases, safety accidents may even occur. The embodiment of the present invention provides a debugging method for an LNG cold energy power generation device, including: propane replacement and filling of the LNG cold energy power generation device; performance test of the split intermediate medium vaporizer in the LNG cold energy power generation device; performance test of the propane circulation pump in the LNG cold energy power generation device; performance test of the turbine and generator in the LNG cold energy power generation device; stop the propane circulation pump, turbine and generator to complete the debugging of the LNG cold energy power generation device. The present invention combines the external transmission production equipment of the LNG receiving station to propose a comprehensive, systematic and complete debugging scheme. Without affecting the gasification and export production of the LNG receiving station, the commissioning quality, safety and efficiency of the LNG cold energy power generation project can be effectively improved.

[0024] Example 1 Before describing the method of the present invention, the structure of the LNG cold energy power generation device is described in detail. Figure 1 As shown, the LNG cold energy power generation device includes a split intermediate medium vaporizer 1, a propane circulation pump 2, a turbine 3 and a generator 4, wherein the split intermediate medium vaporizer 1 includes an intermediate medium vaporizer 1-1, a natural gas heater 1-2 and an LNG vaporizer 1-3.

[0025] The intermediate medium vaporizer 1-1 is provided with a first exhaust valve 5, a first outlet at one end of the intermediate medium vaporizer 1-1 is connected to a seawater outlet 7 through a seawater outlet valve 6, the other end of the intermediate medium vaporizer 1-1 is connected to one end of a natural gas heater 1-2, and a second outlet of the intermediate medium vaporizer 1-1 is connected to one end of a turbine outlet valve 10 through a gas phase bypass valve 8 and a gas phase connecting valve 9 connected in parallel. The second outlet of the intermediate medium vaporizer 1-1 is also connected to one end of a turbine 3 and a turbine discharge valve 13 respectively through a turbine start valve 11 and a turbine fast closing valve 12 connected in parallel, an adjustable nozzle 14 is provided at the turbine 3, and the turbine 3 is also connected to a generator 4 and one end of a turbine outlet valve 10 respectively. The other end of the turbine outlet valve 10 is connected to the first inlet of the LNG vaporizer 1-3.

[0026] The first outlet of the LNG vaporizer 1-3 is connected to the first inlet of the intermediate medium vaporizer 1-1 through the liquid phase connecting valve 15, the second outlet of the LNG vaporizer 1-3 is connected to the propane circulation pump return valve 16 and one end of the liquid level regulating valve 17 through the propane circulation pump 2, the other end of the propane circulation pump return valve 16 is connected to the second inlet of the LNG vaporizer 1-3, and the other end of the liquid level regulating valve 17 is connected to the second inlet of the intermediate medium vaporizer 1-1. The third inlet of the LNG vaporizer 1-3 is connected to the LNG inlet 19 through the LNG inlet flow regulating valve 18, and the third outlet of the LNG vaporizer 1-3 is connected to the first inlet of the natural gas heater 1-2. A flow sensor 20 is provided at the LNG inlet flow regulating valve 18 for monitoring the LNG inlet flow. A temperature sensor 21 is provided on the LNG vaporizer 1-3 for monitoring the pipe side temperature of the LNG vaporizer 1-3.

[0027] The natural gas heater 1 - 2 is provided with a second exhaust valve 22 , and the second inlet at the other end of the natural gas heater 1 - 2 is connected to the seawater inlet 24 through the seawater inlet valve 23 , and the outlet of the natural gas heater 1 - 2 is connected to the normal temperature natural gas outlet 26 through the natural gas outlet valve 25 .

[0028] like Figure 2 As shown, this embodiment provides a debugging method for an LNG cold energy power generation device, comprising the following steps: 1) Replace and fill the LNG cold energy power generation device with propane.

[0029] Specifically, the standard for completion of propane replacement and filling is that the propane content of the process gas pipeline of the LNG cold energy power generation device meets the set value and the propane liquid level of the intermediate medium vaporizer 1-1, the LNG vaporizer 1-3 and the propane circulation pump 2 meets the set value.

[0030] For example: the standard for completion of propane replacement and filling is that the propane content of the process gas pipeline of the LNG cold energy power generation device reaches above 98mol% Vol, the liquid level of the intermediate medium vaporizer 1-1 is 1500±80mm, the liquid level of the LNG vaporizer 1-3 is 850±80mm, and the propane circulation pump 2 is completely immersed in propane.

[0031] 2) Perform performance tests on the split intermediate medium vaporizer 1 in the LNG cold energy power generation device, specifically: 2.1) Establish seawater flow rate for natural gas heater 1-2: 2.1.1) Open the seawater inlet valve 23 and the seawater outlet valve 6.

[0032] 2.1.2) Open the first exhaust valve 5 and the second exhaust valve 22. When there is a steady sound of water flowing through the exhaust valves, close the first exhaust valve 5 and the second exhaust valve 22.

[0033] 2.1.3) Gradually increase the seawater flow rate of natural gas heater 1-2 to the rated flow rate.

[0034] Specifically, when increasing the seawater flow rate, make sure there is no abnormal noise, no abnormal vibration, and no leakage at the flange connection.

[0035] 2.1.4) Open the natural gas outlet valve 25 to balance the external transmission pressure of the natural gas heater 1-2 and the pressure of the downstream natural gas pipeline network.

[0036] 2.2) Establish LNG / NG flow rate of LNG vaporizer 1-3: 2.2.1) Open the LNG inlet flow control valve 18, adjust the opening of the liquid phase connecting valve 15, and ensure that the propane liquid level of the intermediate medium vaporizer 1-1 and the LNG vaporizer 1-3 is within the set range. For example: ensure that the propane liquid level of the LNG vaporizer 1-3 is within the range of 850±80mm, and the propane liquid level of the intermediate medium vaporizer 1-1 is within 1500±80mm.

[0037] 2.2.2) The temperature sensor 21 is used to monitor the tube side temperature of the LNG vaporizer 1-3 to reach -100°C slowly enough, and the temperature drop rate does not exceed -50°C / h.

[0038] 2.2.3) Increase the opening of the LNG inlet flow control valve 18 and monitor the LNG inlet flow through the flow sensor 20.

[0039] Specifically, the flow rate changes are 25%, 50%, 75%, 100% and 105% of the rated flow rate, respectively, and each load flow rate is maintained for at least 30 minutes.

[0040] 2.3) Maintain the LNG flow rate of LNG vaporizers 1-3 at the load flow rate and operate stably for no less than 24 hours.

[0041] 3) Carry out performance test on propane circulation pump 2 in LNG cold energy power generation device, specifically: 3.1) Start the propane circulation pump: 3.1.1) Adjust the opening of the LNG inlet flow control valve 18 so that the LNG flow of the LNG vaporizer 1-3 drops to 40% of the rated load.

[0042] 3.1.2) Adjust the opening of the liquid phase connecting valve 15 to ensure that the propane liquid level of the intermediate medium vaporizer 1-1 and the LNG vaporizer 1-3 is within the set range. For example: ensure that the propane liquid level of the LNG vaporizer 1-3 is within the range of 850±80mm and the propane liquid level of the intermediate medium vaporizer 1-1 is within 1500±80mm.

[0043] 3.1.3) Shield the low-low interlock of the propane circulating pump 2, make sure the opening of the propane circulating pump return valve 16 is set to 40±10%, start the propane circulating pump 2, make sure the motor ampere rises to the starting current value and drops to the normal ampere range within 3 seconds.

[0044] 3.1.4) The liquid level of the intermediate medium vaporizer 1-1 is automatically adjusted by the liquid level regulating valve 17.

[0045] 3.1.5) Close the liquid phase connecting valve 15 and gradually close the gas phase bypass valve 8 until the shell side pressure of the LNG vaporizer 1-3 reaches the set value (e.g. 0.02±0.001MPaG).

[0046] 3.1.6) Open the low-low interlock of the propane circulating pump 2, and adjust the opening of the propane circulating pump reflux valve 16 so that the flow rates of the propane circulating pump 2 are the minimum flow rate, 95% of the rated flow rate, the rated flow rate, the approximate best efficiency point flow rate and 120% of the rated flow rate, respectively. Each adjustment maintains the flow rate stable for 5 minutes.

[0047] 3.1.7) Adjust the opening of the LNG inlet flow control valve 18 so that the LNG flow of the LNG vaporizer 1-3 increases to the rated load.

[0048] 3.2) Turn off the propane circulation pump: 3.2.1) Adjust the opening of the LNG inlet flow control valve 18 so that the LNG flow of the LNG vaporizer 1-3 drops to 40% of the rated load.

[0049] 3.2.2) Close the liquid level regulating valve 17 and adjust the opening of the propane circulating pump return valve 16 to reduce the flow rate of the propane circulating pump 2 to the minimum flow rate.

[0050] 3.2.3) Stop propane circulation pump 2.

[0051] 3.2.4) Fully open the liquid communication valve 15 and the gas communication valve 9.

[0052] 3.2.5) Open the gas phase bypass valve 8 until the opening reaches 100%, with each step not exceeding 5±1%.

[0053] 4) Perform performance tests on the turbine 3 and generator 4 in the LNG cold energy power generation device, specifically: 4.1) Start the lubricating oil system, N2 sealing system and sealing oil system in turbine 3.

[0054] 4.2) Repeat the above step 3.1), start the propane circulation pump 2, and adjust the opening of the LNG inlet flow regulating valve 18 so that the LNG flow of the LNG vaporizer 1-3 is 50% of the rated load.

[0055] 4.3) Start the process gas sealing system in turbine 3, and turn on turbine 3 and generator 4.

[0056] Specifically, the opening of the adjustable nozzle 14 is adjusted to 30±5%, and the turbine start valve 11 is gradually opened, so that the turbine 3 gradually increases to the rated speed (for example, 3000 rpm, with a high and low limit of ±20-40 rpm) and stabilizes for 30 minutes.

[0057] 4.4) Start the grid connection procedure for turbine 3 and generator 4.

[0058] Specifically, after the turbine 3 and the generator 4 are connected to the grid, the turbine start valve 11 continues to be opened until it is fully opened, the turbine quick-closing valve 12 is gradually opened, and the gas phase bypass valve 8 is gradually fully closed. During the process, the opening of the adjustable nozzle 14 is adjusted so that the shell side pressure of the LNG gasifier 1-3 is stabilized at the set value (for example, 0.02±0.001MPa).

[0059] 4.5) Close the turbine start valve 11.

[0060] 5) Stop the propane circulation pump 2, turbine 3 and generator 4, and complete the commissioning of the LNG cold energy power generation device, specifically: 5.1) Slowly open the gas phase bypass valve 8 until the opening reaches 100%, gradually close the turbine quick closing valve 12, and close the adjustable nozzle 14.

[0061] 5.2) Open the turbine drain valve 13.

[0062] 5.3) Close the lubricating oil system, process gas sealing system, sealing oil system and turbine outlet valve 10 in turbine 3 to complete the shutdown of turbine 3.

[0063] 5.4) Send a pump stop command to propane circulation pump 2 to stop propane circulation pump 2.

[0064] 5.5) When the LNG flow rate is at rated load, start the turbine 3 and the generator 4 again, and repeat the above step 4) to complete the full load test.

[0065] Embodiment 2 This embodiment provides a debugging system for an LNG cold energy power generation device, including: The propane replacement and filling module is used for propane replacement and filling of LNG cold energy power generation equipment.

[0066] The first performance test module is used to perform a performance test on the split intermediate medium gasifier 1 in the LNG cold energy power generation device.

[0067] The second performance test module is used to perform a performance test on a propane circulation pump in an LNG cold energy power generation device.

[0068] The third energy test module is used to perform performance tests on turbines and generators in LNG cold energy power generation devices.

[0069] The above embodiments are only used to illustrate the present invention, wherein the structure, connection mode and manufacturing process of each component may be changed. Any equivalent transformations and improvements based on the technical solution of the present invention should not be excluded from the protection scope of the present invention.

Claims

1. A method for debugging an LNG cold energy power generation device, characterized in that: include: Propane replacement and filling of LNG cold energy power generation equipment; Conduct performance tests on the split intermediate medium vaporizer in the LNG cold energy power generation device; Conduct performance tests on propane circulation pumps in LNG cold energy power generation equipment; Conduct performance tests on turbines and generators in LNG cold energy power generation equipment; Stop the propane circulation pump, turbine and generator to complete the commissioning of the LNG cold energy power generation unit.

2. The debugging method of the LNG cold energy power generation device according to claim 1, characterized in that: The standard for completion of propane replacement and filling is that the propane content in the process gas pipeline of the LNG cold energy power generation device meets the set value and the propane liquid levels of the intermediate medium vaporizer, LNG vaporizer and propane circulation pump meet the set value.

3. The debugging method of the LNG cold energy power generation device according to claim 2, characterized in that: The performance test of the split intermediate medium gasifier in the LNG cold energy power generation device includes: Establish seawater flow rates for natural gas heaters; Establish LNG / NG flow rates for LNG vaporizers; Keep the LNG flow of the LNG vaporizer at the load flow, and ensure stable operation for no less than the preset time.

4. A debugging method for an LNG cold energy power generation device as claimed in claim 3, characterized in that: The method of establishing the seawater flow rate of the natural gas heater includes: Open the seawater inlet valve and the seawater outlet valve; Open the first exhaust valve and the second exhaust valve, and when the sound of water flowing through the exhaust valve reaches a preset time, close the first exhaust valve and the second exhaust valve; Gradually increase the seawater flow rate of the natural gas heater to the rated flow rate; Open the natural gas outlet valve to balance the natural gas heater output pressure and the downstream natural gas pipeline pressure.

5. The debugging method of the LNG cold energy power generation device according to claim 3, characterized in that: The establishing of the LNG / NG flow rate of the LNG vaporizer comprises: Open the LNG inlet flow control valve and adjust the opening of the liquid-phase connecting valve to ensure that the propane liquid level of the intermediate medium vaporizer and the LNG vaporizer is within the set range; Monitor the tube side temperature of the LNG vaporizer through a temperature sensor; Increase the opening of the LNG inlet flow control valve and monitor the LNG inlet flow through the flow sensor.

6. The debugging method of the LNG cold energy power generation device according to claim 1, characterized in that: The performance test of the propane circulating pump in the LNG cold energy power generation device includes: Start the propane circulation pump: Adjust the opening of the LNG inlet flow control valve so that the LNG flow of the LNG vaporizer drops to 40% of the rated load; Adjust the opening of the liquid-phase connecting valve to ensure that the propane liquid level of the intermediate medium vaporizer and the LNG vaporizer is within the set range; Shield the low-low interlock of the propane circulating pump, make sure that the opening of the return valve of the propane circulating pump reaches the set value, start the propane circulating pump, make sure that the motor ampere rises to the starting current value, and drops to the normal ampere range within several seconds; Automatically adjust the liquid level of the intermediate medium vaporizer through the liquid level regulating valve; Close the liquid phase connecting valve and gradually close the gas phase bypass valve until the shell side pressure of the LNG vaporizer reaches the set value; Open the low-low interlock of the propane circulation pump and adjust the opening of the reflux valve of the propane circulation pump so that the flow rates of the propane circulation pump are the minimum flow rate, 95% of the rated flow rate, the rated flow rate, the flow rate close to the best efficiency point and 120% of the rated flow rate respectively; Adjust the opening of the LNG inlet flow control valve so that the LNG flow of the LNG vaporizer increases to the rated load; Shut down the propane circulation pump: Adjust the opening of the LNG inlet flow control valve so that the LNG flow of the LNG vaporizer drops to 40% of the rated load; Close the liquid level regulating valve and adjust the opening of the reflux valve of the propane circulating pump to reduce the flow rate of the propane circulating pump to the minimum flow rate; Stop the propane circulation pump; Fully open the liquid-phase connecting valve and the gas-phase connecting valve; Open the gas phase bypass valve until the opening reaches 100%, with each step not exceeding 5±1%.

7. The debugging method of the LNG cold energy power generation device according to claim 1, characterized in that: The performance test of the turbine and the generator in the LNG cold energy power generation device includes: Start the lubricating oil system, N2 sealing system and sealing oil system in the turbine; Start the propane circulation pump and adjust the opening of the LNG inlet flow control valve so that the LNG flow of the LNG vaporizer is 50% of the rated load; Start the process gas sealing system in the turbine and turn on the turbine and generator; Start the grid connection procedure for turbines and generators; Close the turbine start valve.

8. The debugging method of the LNG cold energy power generation device according to claim 5, characterized in that: The stopping of the propane circulation pump, turbine and generator to complete the commissioning of the LNG cold energy power generation device includes: Open the gas phase bypass valve until the opening reaches 100%, and close the turbine quick-closing valve and the adjustable nozzle; Open the turbine drain valve; Close the lubricating oil system, process gas sealing system, sealing oil system and turbine outlet valve in the turbine to complete turbine shutdown; Send a pump stop command to the propane circulation pump to stop the propane circulation pump.

9. The debugging method of the LNG cold energy power generation device according to claim 5, characterized in that: The stopping of the propane circulation pump, the turbine and the generator to complete the commissioning of the LNG cold energy power generation device also includes: When the LNG flow rate is at rated load, start the turbine and generator again, repeat the performance test of the turbine and generator in the LNG cold energy power generation device, and complete the full load test.

10. A debugging system for an LNG cold energy power generation device, characterized in that: include: Propane replacement and filling module, used for propane replacement and filling of LNG cold energy power generation equipment; The first performance test module is used to perform a performance test on a split intermediate medium gasifier in an LNG cold energy power generation device; The second performance test module is used to perform performance tests on the propane circulation pump in the LNG cold energy power generation device; The third energy test module is used to perform performance tests on turbines and generators in LNG cold energy power generation devices.