Building construction management method based on BIM
By decomposing the construction into multiple stages and designing corresponding models for supervision and management, the problem of failure to effectively supervise multiple construction stages in the existing technology is solved, and the construction quality and management efficiency are improved.
Patent Information
- Application Number
- CN202411578348.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-07
- Publication Date
- 2024-12-06
AI Technical Summary
The existing BIM-based building construction management methods have not been effectively supervised for multiple building construction stages in combination with the BIM model, which affects the efficiency of construction quality management.
Decompose the construction into multiple stages, design the construction model for each stage, and use the BIM system to compare the size, position and acceptance standards of each component to ensure the construction of each stage. Meets design requirements.
The management efficiency and construction quality of building construction quality are improved. Through phased supervision and acceptance, each component and staged compliance with design requirements is ensured, and the construction errors and error rates are reduced.
Smart Images

Figure CN119090361A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of building construction, and in particular to a building construction management method based on BIM. Background Art
[0002] The core of BIM is to establish a virtual three-dimensional model of the building project and use digital technology to provide a complete and actual building project information database for this model. This information database not only contains geometric information, professional attributes and status information describing the building components, but also contains the status information of non-component objects. With the help of this three-dimensional model containing building project information, the degree of information integration of the building project is greatly improved. The existing BIM-based construction management method mainly uses the BIM model to grasp the information of the components involved in the tracking of the building, so as to grasp the situation of the building construction. For example, the announcement number CN113592283A involves a BIM-based construction equipment, construction management system and construction management method, that is, a 3D construction model is established through a BIM operation subsystem, and the model is managed through a BIM management center. However, the actual construction can be decomposed into multiple construction stages. The existing method does not combine the BIM model to supervise the multiple construction stages stage by stage, which affects the management efficiency of the construction quality and thus affects the construction quality. Summary of the invention
[0003] An object of the present invention is to solve at least the above problems and / or disadvantages and to provide at least the advantages which will be described hereinafter.
[0004] One object of the present invention is to provide a construction management method based on BIM, which decomposes construction into multiple construction stages, designs a corresponding construction model for each construction stage, and supervises and manages the construction results in stages in combination with the construction model of each stage, thereby improving the management efficiency of construction quality and improving construction quality.
[0005] In order to achieve these purposes and other advantages according to the present invention, a BIM-based building construction management method is provided, comprising: Step 1: decompose the construction into multiple construction stages, and design a construction model for each construction stage in the BIM system according to the multiple construction stages; the construction model for each construction stage includes multiple components and the size, construction location and acceptance criteria of each component, and an identity code is designed for each component; Step 2: Carry out construction from the first construction stage according to the order of the multiple construction stages. In the current construction stage, carry out construction according to the construction model corresponding to the current construction stage, set an identification tag for each component actually completed, and the identification tag is used to store the identity code of each component. When the construction of the current construction stage is completed, the actually completed building is compared with the construction model corresponding to the current construction stage. During the comparison process, the identification tag of each actually completed component in the actually completed building is identified one by one, and the identity code of each actually completed component is obtained. The size, construction position and acceptance index of each actually completed component are compared with the size, construction position and verification standard of the component in the corresponding construction model; if the size, construction position and acceptance standard of all actually completed components in the actually completed building are consistent with the size, construction position and acceptance standard of all components in the construction model corresponding to the current construction, it is determined that the current construction stage is completed, and the next construction stage is started. During the construction phase, a construction model corresponding to the next construction phase is provided; if any component in the actually completed building is inconsistent with the size, construction position or acceptance standard of the corresponding component in the construction model corresponding to the current construction phase, it is determined that the actually completed building does not meet the design requirements, the next construction phase is stopped and started, the construction model corresponding to the next construction phase is kept in an unviewable state, and the actually completed building corresponding to the current construction phase is corrected again. During the correction, the inconsistent components in the actually completed building are corrected, and the corrected building is compared again with the construction model corresponding to the current construction phase. If the sizes, construction positions and acceptance standards of all the actually completed components in the corrected building are consistent with those of all the components in the construction model corresponding to the current construction, it is determined that the current construction phase is completed, the next construction phase is started, and the construction model corresponding to the next construction phase is provided.
[0006] Preferably, in the BIM-based construction management method, in the step 2, the revised building is compared with the construction model corresponding to the current construction stage. If the comparison is consistent, the revised building is determined to meet the design requirements, including: comparing inconsistent components between the actually completed building corresponding to the current construction stage and the construction model corresponding to the current construction stage. If the inconsistent components are all consistent, the revised building is determined to meet the design requirements.
[0007] Preferably, in the BIM-based construction management method, in the step 2, the actually completed building is compared with the construction model corresponding to the current construction stage; if the comparison is inconsistent, it is determined that the actually completed building does not meet the design requirements, including: marking the inconsistent components in the actually completed building corresponding to the current construction stage and the construction model corresponding to the current construction stage.
[0008] Preferably, in the BIM-based construction management method, in the step one, after designing a construction model for each construction stage in the BIM system according to the multiple construction stages, key components are marked in the construction model of each construction stage; and in the step two, in the current construction stage, the marks of the key components are displayed in the provided construction model of the current construction stage.
[0009] Preferably, in the BIM-based construction management method, in the step one, the key components in the construction model of each construction stage are determined in the following manner: in the process of carrying out construction from the first construction stage multiple times in the order of the multiple construction stages, for any construction stage, the inconsistent components between the actually completed building in the corresponding construction stage and the construction model corresponding to the corresponding construction stage are counted, and the inconsistent components with an occurrence frequency higher than a set threshold are determined as key components.
[0010] Preferably, in the BIM-based construction management method, in the step 2, when the current construction phase is started, the current construction phase is marked as started, and when the current construction phase is completed, the current construction phase is marked as completed, and the actual construction period of the current construction phase is determined based on the start mark and the completion mark.
[0011] Preferably, in the BIM-based construction management method, in the step 2, when the current construction phase is started, the current construction phase is marked as started, the current consumed time of the current construction phase is determined according to the current time and the start mark, and the gap between the current consumed time and the design construction period of the current construction phase is updated in real time.
[0012] The present invention has at least the following beneficial effects: The present invention provides a construction management method based on BIM, comprising: step 1, decomposing construction into multiple construction stages, designing a construction model for each construction stage in a BIM system according to the multiple construction stages; the construction model of each construction stage includes multiple components and the size, construction position and acceptance standard of each component, and designing an identity code for each component; step 2, performing construction from the first construction stage according to the order of the multiple construction stages, performing construction in the current construction stage according to the construction model corresponding to the current construction stage, setting an identification tag for each actually completed component, the identification tag being used to store the identity code of each component, and when the construction of the current construction stage is completed, comparing the actually completed building with the construction model corresponding to the current construction stage, identifying the identification tag of each actually completed component in the actually completed building one by one during the comparison process, obtaining the identity code of each actually completed component, and comparing the size, construction position and acceptance index of each actually completed component with the size, construction position and verification standard of the component in the corresponding construction model; as shown in FIG. If the size, building position and acceptance standard of the actually completed components are consistent with those of all components in the construction model corresponding to the current construction, the current construction stage is determined to be completed, the next construction stage is started, and the construction model corresponding to the next construction stage is provided; if there is any component in the actually completed building that is inconsistent with the size, building position or acceptance standard of the corresponding component in the construction model corresponding to the current construction stage, the actually completed building is determined to be inconsistent with the design requirements, the next construction stage is stopped, the construction model corresponding to the next construction stage is kept in an unviewable state, and the actually completed building corresponding to the current construction stage is corrected again. When correcting, the inconsistent components in the actually completed building are corrected, and the corrected building is compared again with the construction model corresponding to the current construction stage. If the size, building position and acceptance standard of all actually completed components in the corrected building are consistent with those of all components in the construction model corresponding to the current construction, the current construction stage is determined to be completed, the next construction stage is started, and the construction model corresponding to the next construction stage is provided.The present invention decomposes construction into multiple construction stages, designs a corresponding construction model for each construction stage, supervises and manages construction results in stages in combination with the construction model of each stage, and when managing the construction results of each stage, compares the size, building position and acceptance standard of each component in the actually completed building with the indicators such as the size, building position and acceptance standard of the corresponding component in the model one by one, thereby improving the management efficiency of construction quality and improving construction quality.
[0013] Other advantages, objectives and features of the present invention will be embodied in part through the following description, and in part will be understood by those skilled in the art through study and practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 This is a flowchart of a BIM-based construction management method according to an embodiment of the present invention. DETAILED DESCRIPTION
[0015] The present invention is further described in detail below in conjunction with the accompanying drawings so that those skilled in the art can implement the invention with reference to the description.
[0016] like Figure 1As shown, an embodiment of the present invention provides a BIM-based construction management method, including: step 1, model design stage: decompose construction into multiple construction stages, and design a construction model for each construction stage in the BIM system according to the multiple construction stages; the construction model of each construction stage includes multiple components and the size, construction position and acceptance standard of each component, and an identity code is designed for each component; step 2, construction stage: perform construction from the first construction stage according to the order of the multiple construction stages, perform construction in the current construction stage according to the construction model corresponding to the current construction stage, set an identification tag for each actually completed component, and the identification tag is used to store the identity code of each component. When the construction of the current construction stage is completed, the actually completed building is compared with the construction model corresponding to the current construction stage. During the comparison process, the identification tag of each actually completed component in the actually completed building is identified one by one, and the identity code of each actually completed component is obtained. The size, construction position and acceptance index of each actually completed component are compared with the size, construction position and verification standard of the component in the corresponding construction model; as described in the embodiment If the sizes, building positions and acceptance standards of all the actually completed components in the actually completed building are consistent with those of all the components in the construction model corresponding to the current construction, then the current construction stage is determined to be completed, the next construction stage is started, and the construction model corresponding to the next construction stage is provided; if there is any component in the actually completed building that is inconsistent with the size, building position or acceptance standard of the corresponding component in the construction model corresponding to the current construction stage, then the actually completed building is determined to be not in compliance with the design requirements, the next construction stage is stopped, the construction model corresponding to the next construction stage is kept in an unviewable state, and the actually completed building corresponding to the current construction stage is corrected again. When correcting, the inconsistent components in the actually completed building are corrected, and the corrected building is compared again with the construction model corresponding to the current construction stage. If the sizes, building positions and acceptance standards of all the actually completed components in the corrected building are consistent with those of all the components in the construction model corresponding to the current construction, then the current construction stage is determined to be completed, the next construction stage is started, and the construction model corresponding to the next construction stage is provided.
[0017] The present invention first decomposes the construction into multiple construction stages, and then designs the corresponding construction model according to each stage. During the actual construction, the construction is first carried out from the first stage, and during the construction, the construction must be carried out according to the construction model provided by the system. After the construction is completed, the actually completed building is compared with the construction model of the current stage. If the comparison is consistent, it is considered that the construction of the current stage meets the design requirements and can enter the next stage, and the system provides the construction model of the next stage. If the comparison is inconsistent, it is considered that the construction of the current stage does not meet the design requirements, and the building actually constructed in the current stage needs to be corrected. After that, the corrected building is compared with the construction model of the stage again. If the comparison is consistent, it can be considered that the construction of the current stage after correction meets the design requirements and can enter the next stage. The system provides the construction model of the next stage as the construction basis of the next stage. That is to say, when the building quality of the previous stage does not meet the standard, the actual construction process cannot proceed to the next stage. Through the above process, the construction can be supervised and accepted in stages, the management efficiency of the construction can be improved, and the construction quality can be finally improved.
[0018] In the above comparison process, in order to further improve the supervision quality of the construction quality of each stage, the construction model of each stage is further decomposed into multiple components, and an identity code is set for each component, and the size, building position and acceptance criteria of each component are recorded. When comparing the actual completed building with the construction model, the size, building position and acceptance criteria of each component in the actual completed building are compared with each component in the construction model. If multiple indicators can reach consistency, it is determined that the component meets the design requirements. As long as any indicator is not consistent, it is considered that the component does not meet the design requirements and needs to be corrected. When correcting, the inconsistent components need to be corrected so that they are corrected to the size, building position, acceptance criteria and other indicators in the model. After correction, if all components in the actual construction building can meet the design requirements after comparison again, it is determined that the current construction stage is completed and the next stage is started. The present invention compares each component of the current stage one by one in the staged comparison. Once a component is found not to meet the design requirements, it can be corrected immediately, thereby improving the supervision quality of building construction quality. Compared with a one-time acceptance, the acceptance of components in stages is also helpful to improve the construction quality.
[0019] In a preferred embodiment, in the BIM-based construction management method, in the step 2, the revised building is compared with the construction model corresponding to the current construction stage. If the comparison is consistent, the revised building is determined to meet the design requirements, including: comparing the inconsistent components between the actually completed building corresponding to the current construction stage and the construction model corresponding to the current construction stage. If the inconsistent components are all consistent, the revised building is determined to meet the design requirements.
[0020] When the actual completed building of a certain stage does not meet the standard, the actual completed building of that stage must be revised, and after the revision, it can be compared again. When comparing, the inconsistent components between the building before revision and the building construction model can be directly compared. If these inconsistent components can reach a consensus, it is considered that the revised building meets the design requirements and can enter the next stage. For the consistent components between the building before revision and the building construction model, since they have been compared for the first time, they do not need to be compared again here, thereby improving management efficiency.
[0021] In a preferred embodiment, in the BIM-based construction management method, in the step 2, the actually completed building is compared with the construction model corresponding to the current construction stage; if the comparison is inconsistent, it is determined that the actually completed building does not meet the design requirements, including: marking the inconsistent components in the actually completed building corresponding to the current construction stage and the construction model corresponding to the current construction stage.
[0022] When performing the first comparison, the inconsistent components between the actual completed building and the construction model at that stage can be marked in the construction model. When performing the second comparison, the revised building can be directly compared with the marked components in the construction model to improve the comparison efficiency and thus speed up the progress.
[0023] In a preferred embodiment, in the BIM-based construction management method, in the step one, after designing a construction model for each construction stage in the BIM system according to the multiple construction stages, key components are marked in the construction model of each construction stage; in the step two, in the current construction stage, the marks of the key components are displayed in the provided construction model of the current construction stage.
[0024] When designing the construction model of each stage, key components can be marked in the model at the same time. During actual construction, when the system provides the construction model of the corresponding stage, the marking of key components can be displayed in the model. The marking of key components can remind construction personnel to pay attention to the construction of these components, thereby improving construction quality, reducing the probability of errors, and improving the efficiency of acceptance.
[0025] In a preferred embodiment, in the BIM-based construction management method, in the step one, the key components in the construction model of each construction stage are determined in the following manner: in the process of carrying out construction from the first construction stage multiple times in the order of the multiple construction stages, for any construction stage, the inconsistent components between the actually completed building in the corresponding construction stage and the construction model corresponding to the corresponding construction stage are counted, and the inconsistent components with an occurrence frequency higher than a set threshold are determined as key components.
[0026] Key components can be marked based on experience. They can also be determined by the method provided by the present invention. Specifically, unqualified components in each construction stage can be counted in multiple construction projects, that is, components that are inconsistent between the actual completed building and the construction model. If an unqualified component appears frequently and its frequency of occurrence is higher than the set threshold, it means that the component is a component that is prone to errors during construction, and the component is determined to be a key component. When designing the model, the key component will be marked to remind construction personnel to focus on it, reduce the probability of errors, and improve the efficiency of acceptance.
[0027] In a preferred embodiment, in the BIM-based construction management method, in the step 2, when the current construction phase is started, the current construction phase is marked as started, and when the current construction phase is completed, the current construction phase is marked as completed, and the actual construction period of the current construction phase is determined based on the start mark and the completion mark.
[0028] From the start of the current construction phase to the completion of this phase, the start and completion time nodes are marked respectively, and finally the actual construction period is calculated based on the two time marks. Through the above process, the actual construction efficiency of each construction phase can be mastered.
[0029] In a preferred embodiment, in the BIM-based construction management method, in the step 2, when the current construction phase is started, the current construction phase is marked as started, the current consumed time of the current construction phase is determined based on the current time and the start mark, and the gap between the current consumed time and the design construction period of the current construction phase is updated in real time.
[0030] It is also possible to calculate the time spent in the current stage, that is, the current consumed time, based on the start mark and the current time, and compare the current consumed time with the pre-set design construction period to calculate the difference between the two, so that construction personnel can grasp the construction progress in time to speed up the construction.
[0031] In summary, the present invention provides a construction management method based on BIM, comprising: step 1, decomposing construction into multiple construction stages, designing a construction model for each construction stage in the BIM system according to the multiple construction stages; the construction model of each construction stage includes multiple components and the size, construction position and acceptance criteria of each component, and designing an identity code for each component; step 2, performing construction from the first construction stage according to the order of the multiple construction stages, performing construction in the current construction stage according to the construction model corresponding to the current construction stage, setting an identification tag for each component actually completed, the identification tag being used to store the identity code of each component, and when the construction of the current construction stage is completed, comparing the actually completed building with the construction model corresponding to the current construction stage, and in the comparison process, identifying the identification tag of each actually completed component in the actually completed building one by one, obtaining the identity code of each actually completed component, and comparing the size, construction position and acceptance index of each actually completed component with the size, construction position and verification standard of the component in the corresponding construction model; as shown in the actually completed building If the sizes, building positions and acceptance standards of all the actually completed components are consistent with those of all the components in the construction model corresponding to the current construction, then the current construction stage is determined to be completed, and the next construction stage is started, and the construction model corresponding to the next construction stage is provided; if there is any component in the actually completed building that is inconsistent with the size, building position or acceptance standard of the corresponding component in the construction model corresponding to the current construction stage, then the actually completed building is determined to be not in compliance with the design requirements, the next construction stage is stopped, the construction model corresponding to the next construction stage is kept in an unviewable state, and the actually completed building corresponding to the current construction stage is corrected again. When correcting, the inconsistent components in the actually completed building are corrected, and the corrected building is compared again with the construction model corresponding to the current construction stage. If the sizes, building positions and acceptance standards of all the actually completed components in the corrected building are consistent with those of all the components in the construction model corresponding to the current construction, then the current construction stage is determined to be completed, the next construction stage is started, and the construction model corresponding to the next construction stage is provided.The present invention decomposes construction into multiple construction stages, designs a corresponding construction model for each construction stage, supervises and manages construction results in stages in combination with the construction model of each stage, and when managing the construction results of each stage, compares the size, building position and acceptance standard of each component in the actually completed building with the indicators such as the size, building position and acceptance standard of the corresponding component in the model one by one, thereby improving the management efficiency of construction quality and improving construction quality.
[0032] Although the embodiments of the present invention have been disclosed above, they are not limited to the applications listed in the specification and the embodiments. It can be fully applied to various fields suitable for the present invention. For those familiar with the art, additional modifications can be easily realized. Therefore, without departing from the general concept defined by the claims and equivalent scope, the present invention is not limited to the specific details and the illustrations shown and described here.
Claims
1. A BIM-based construction management method, characterized in that: include: Step 1: Decompose the construction into multiple construction stages, and design a construction model for each construction stage in the BIM system according to the multiple construction stages; The building construction model of each building construction stage includes a plurality of components and the size, building location and acceptance criteria of each component, and an identity code is designed for each component; Step 2: Perform construction from the first construction stage according to the order of the multiple construction stages. In the current construction stage, perform construction according to the construction model corresponding to the current construction stage, set an identification tag for each component actually completed, and the identification tag is used to store the identity code of each component. When the construction of the current construction stage is completed, the actually completed building is compared with the construction model corresponding to the current construction stage. During the comparison process, the identification tag of each actually completed component in the actually completed building is identified one by one, the identity code of each actually completed component is obtained, and the size, construction position and acceptance index of each actually completed component are compared with the size, construction position and verification standard of the component in the corresponding construction model. If the sizes, building positions and acceptance standards of all the actually completed components in the actually completed building are consistent with those of all the components in the construction model corresponding to the current construction, then the current construction stage is determined to be completed, and the next construction stage is started, and the construction model corresponding to the next construction stage is provided; if there is any component in the actually completed building that is inconsistent with the size, building position or acceptance standard of the corresponding component in the construction model corresponding to the current construction stage, then the actually completed building is determined to be inconsistent with the design requirements, the next construction stage is stopped, the construction model corresponding to the next construction stage is kept in an unviewable state, and the actually completed building corresponding to the current construction stage is corrected again. When correcting, the inconsistent components in the actually completed building are corrected, and the corrected building is compared again with the construction model corresponding to the current construction stage. If the sizes, building positions and acceptance standards of all the actually completed components in the corrected building are consistent with those of all the components in the construction model corresponding to the current construction, then the current construction stage is determined to be completed, the next construction stage is started, and the construction model corresponding to the next construction stage is provided.
2. The BIM-based construction management method according to claim 1, characterized in that: In the step 2, the revised building is compared with the construction model corresponding to the current construction stage. If the comparison is consistent, the revised building is determined to meet the design requirements, including: comparing the inconsistent components between the actually completed building corresponding to the current construction stage and the construction model corresponding to the current construction stage. If the inconsistent components are all consistent, the revised building is determined to meet the design requirements.
3. The BIM-based construction management method according to claim 2, characterized in that: In the step 2, the actually completed building is compared with the building construction model corresponding to the current building construction stage; If the comparison is inconsistent, it is determined that the actually completed building does not meet the design requirements, including: marking the inconsistent components in the actually completed building corresponding to the current building construction stage and the building construction model corresponding to the current building construction stage.
4. The BIM-based construction management method according to claim 1, characterized in that: In the step 1, after designing a building construction model for each building construction stage in the BIM system according to the multiple building construction stages, marking key components in the building construction model for each building construction stage; In the step 2, at the current construction stage, the markings of the key components are displayed in the provided construction model of the current construction stage.
5. The BIM-based construction management method according to claim 4, characterized in that: In the step one, the key components in the construction model of each construction stage are determined in the following manner: in the process of carrying out construction from the first construction stage multiple times in the order of the multiple construction stages, for any construction stage, the inconsistent components between the actually completed building in the corresponding construction stage and the construction model corresponding to the corresponding construction stage are counted, and the inconsistent components with an occurrence frequency higher than a set threshold are determined as key components.
6. The BIM-based construction management method according to claim 1, characterized in that: In the step 2, when the current construction phase is started, the current construction phase is marked as started, and when the current construction phase is completed, the current construction phase is marked as completed, and the actual construction period of the current construction phase is determined based on the start mark and the completion mark.
7. The BIM-based construction management method according to claim 6, characterized in that: In step 2, when the current construction phase is started, the current construction phase is marked as started, the current consumed time of the current construction phase is determined based on the current time and the start mark, and the gap between the current consumed time and the design construction period of the current construction phase is updated in real time.
Citation Information
Patent Citations
Virtual body and entity checking and verifying system based on BIM
CN107967375A
Method and system for controlling concrete structure construction quality based on BIM technology
CN108197802A
BIM-based construction method and management system
CN112990844A
Engineering management method and device based on BIM model
CN116720820A
Engineering progress evaluation method and device and storage medium
CN118278784A