Quota man-hour determination method and device applied to ship, equipment and medium
By receiving basic hull data and the design quantity of sectioned plate material, the target execution procedure is used to determine the target working hours of the cold processing process of the hull plate, which solves the problem of inconsistent process standards in cross-factory construction, improves calculation accuracy and efficiency, and reduces the Data management costs.
Patent Information
- Application Number
- CN202411177225.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-26
- Publication Date
- 2024-12-06
AI Technical Summary
During the hull construction process, cross-factory construction results in inconsistent process standards and inconsistent evaluation of particle sizes. Manually calculating process duration from historical data has problems of inaccurate search, long time and high cost.
By receiving the basic data of the hull and the designed amount of the sectioned plate material, the target quota standard relationship table is retrieved, and the target working hours of the plate cold processing process are determined based on the target execution program analysis and processing.
It improves the accuracy and efficiency of the target working hours, reduces data management costs, and avoids the maintenance of historical data.
Smart Images

Figure CN119090472A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of data processing technology, and in particular to a method, device, equipment and medium for determining quota working hours used in ships. Background Art
[0002] During the shipbuilding process, one or more factories may jointly build the ship, that is, there is cross-factory construction. In this case, there are problems such as inconsistent process operation standards, inconsistent process evaluation granularity, and uneven production levels among the factories, resulting in large and complex historical data corresponding to each process.
[0003] When manually obtaining the corresponding data from historical data and calculating the duration of the process, there may be inaccurate search, too long search time and incorrect calculation, which makes it impossible to accurately evaluate the duration of the corresponding process in the hull construction process. In addition, the above method of processing through historical data may also involve the maintenance and management of historical data, resulting in high data management costs. Summary of the invention
[0004] The present invention provides a method, device, equipment and medium for determining the quota working hours used in ships, which effectively determines the target working hours corresponding to the plate cold processing process during the hull construction process, improves the accuracy and efficiency of calculating the target working hours, and reduces data management costs.
[0005] According to one aspect of the present invention, a method for determining quota working hours applied in a ship is provided, the method comprising:
[0006] Receiving basic hull data of a hull to be built and a designed quantity of blanking material of at least one segment plate;
[0007] Retrieving the target quota standard relationship table associated with the hull basic data, and coding the contents in the target quota standard relationship table to obtain the target execution program of the target quota standard relationship table;
[0008] Based on the target execution program, the material quantity of the blanking design of the segmented plate is analyzed and processed in turn to obtain the waiting man-hours for the blanking design quantity of each segmented plate;
[0009] Based on the waiting man-hours for the designed material quantities of all the segmented plates corresponding to the ship to be built, the target man-hours for cold working of the plates in each process of the ship to be built are determined.
[0010] According to another aspect of the present invention, there is provided a device for determining quota working hours for use in a ship, the device comprising:
[0011] A data receiving module, used for receiving basic hull data of a hull to be built and a designed material quantity of at least one segmented plate blanking;
[0012] The target execution program determination module is used to retrieve the target quota standard relationship table associated with the hull basic data, and code the contents in the target quota standard relationship table to obtain the target execution program of the target quota standard relationship table;
[0013] A module for determining the man-hours to be used is used to analyze and process the material quantities of the blanking design of the segmented plate in sequence based on the target execution program to obtain the man-hours to be used for the material quantities of the blanking design of each segmented plate;
[0014] The target working time determination module is used to determine the target working time for cold working of the plates in each process of the ship to be built based on the working time to be used for the design material quantity of all the segmented plates corresponding to the ship to be built.
[0015] According to another aspect of the present invention, there is provided an electronic device, the electronic device comprising:
[0016] at least one processor; and
[0017] a memory communicatively connected to at least one processor; wherein,
[0018] The memory stores a computer program that can be executed by at least one processor, and the computer program is executed by at least one processor so that the at least one processor can execute the method for determining the quota working hours applied to a ship according to any embodiment of the present invention.
[0019] According to another aspect of the present invention, a computer-readable storage medium is provided, which stores computer instructions for enabling a processor to implement the method for determining the quota working hours applied to a ship according to any embodiment of the present invention when the computer instructions are executed.
[0020] According to another aspect of the present invention, there is provided a computer program product, comprising a computer program, characterized in that when the computer program is executed by a processor, the computer program implements a method for determining quota working hours applied to a ship as in any embodiment of the present invention.
[0021] The technical solution of the embodiment of the present invention provides data support for the subsequent calculation of the target working hours by receiving the basic hull data of the hull to be built and the designed quantity of at least one segmented plate blanking. By retrieving the target quota standard relationship table associated with the basic hull data and coding the contents in the target quota standard relationship table, a target execution program is obtained, thereby realizing the programmatic processing of the target quota standard relationship table. Based on the target execution program, the designed quantity of segmented plate blanking is analyzed and processed in turn to obtain the waiting working hours for each segmented plate blanking designed quantity. Not only can the waiting working hours be effectively determined, but also the processing efficiency is improved compared to manual processing. The target working hours for the cold processing of the plates in each process of the hull to be built are determined by the waiting working hours for all the segmented plate blanking designed quantities corresponding to the hull to be built. Based on this, the target working hours for executing all plate cold processing processes are accurately determined. The present invention processes the design quantity of segmented plate blanking through a target execution program, which not only solves the problems of inaccurate search, low search efficiency and incorrect calculation caused by manual search and calculation of historical data in the prior art, improves the accuracy and efficiency of calculating target working hours, but also avoids the maintenance of historical data and reduces data costs.
[0022] It should be understood that the contents described in this section are not intended to identify the key or important features of the embodiments of the present invention, nor are they intended to limit the scope of the present invention. Other features of the present invention will become easily understood through the following description. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0024] Figure 1 This is a flow chart of a method for determining quota working hours applied to a ship provided by an embodiment of the present invention;
[0025] Figure 2 It is a table example diagram of the material quantity of the segmented plate blanking design provided by the embodiment of the present invention;
[0026] Figure 3 is an example diagram of a target quota standard relationship table provided by an embodiment of the present invention;
[0027] Figure 4 This is a flow chart of a method for determining quota working hours applied to a ship provided by an embodiment of the present invention;
[0028] Figure 5It is a structural schematic diagram of a device for determining quota working hours applied to a ship provided by an embodiment of the present invention;
[0029] Figure 6 The invention is a schematic diagram of the structure of an electronic device for implementing the method for determining the quota working hours applied in a ship according to an embodiment of the present invention. DETAILED DESCRIPTION
[0030] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.
[0031] It should be noted that the terms "first", "second", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present invention described herein can be implemented in an order other than those illustrated or described herein. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.
[0032] Embodiment 1
[0033] Figure 1 This is a flow chart of a method for determining standard working hours applied to ships, provided in the first embodiment of the present invention. This embodiment can be applied to the case of determining the duration corresponding to all plate cold processing procedures during the hull construction process. The method can be executed by a device for determining standard working hours applied to ships. The device for determining standard working hours applied to ships can be implemented in the form of hardware and / or software. The device for determining standard working hours applied to ships can be configured in electronic devices such as mobile phones, computers or servers. For example, the device for determining standard working hours can be configured in an electronic device that has an IO communication port, can access Web services and has a display screen, such as a desktop computer, a laptop computer or a tablet computer. Figure 1 As shown, the method includes:
[0034] S110, receiving basic hull data of a hull to be built and a designed material quantity of at least one segmented plate.
[0035] In order to increase the speed of hull construction, the hull is divided into multiple areas during the hull construction process, such as the bow area, the middle area, and the stern area. Each area is subdivided into multiple parts, each of which is called a segment. For example, the middle area of the hull can be divided into: multiple bottom segments, side segments (several on the left and starboard sides), deck segments, bulkhead segments, etc. The assembly and construction of the hull is achieved by processing multiple processes under each segment.
[0036] The multiple processes corresponding to each segment may include: 1) the pretreatment process of hull manufacturing, which is used to perform pretreatment such as rust removal, cleaning and primer coating on the plates and profiles required for building the hull; 2) the hull manufacturing cutting process, which is used to cut the plates and profiles required for building the hull into specified sizes and shapes; 3) the hull manufacturing docking process, which is used to connect multiple profiles of specific shapes into the required hull structural components through welding, bolting, etc.; 4) the hull manufacturing processing process may include: profile cold bending, plate cold processing, hot processing, and loose parts punching. Grinding and tooling, etc., among which, the cold processing of the plate is used to shape the plate into the shape required for hull construction according to the design requirements without heating; 5) Hull manufacturing welding, assembly and grinding process, used to weld the plate and profile into small components, medium components and large components, assemble the components together according to the design requirements, and grind and anti-corrosion treatment the welds after welding and assembly; 6) General assembly and loading process, used to further assemble the large components into the hull structure, and load the hull structure corresponding to each section to realize the overall construction of the hull. The embodiment of the present invention is mainly used to determine the working hours corresponding to the plate cold processing process in the hull construction process.
[0037] It should be noted that the plates mentioned in the above process may be materials used to construct the outer plates, decks, bulkheads and other parts of the hull to be built. The plates may be steel plates, aluminum alloy plates and other alloy plates. Profiles are materials used to construct the skeleton, cross beams and longitudinal girders and other parts of the hull to be built. Profiles may be steel sections, pipes or aluminum profiles.
[0038] In the embodiment of the present invention, the hull that needs to be built currently is taken as the hull to be built. The basic hull data may include data such as the construction plant of the hull to be built and the ship number corresponding to the hull to be built. For example, the basic hull data may include that the construction plant of the hull to be built is plant A and the ship number of the hull to be built is H2453.
[0039] Since there may be plate cold processing procedures in one or more sections. Therefore, if the working hours corresponding to the plate cold processing procedures are calculated, the design quantity of the blanking of at least one section plate can be obtained first. Among them, the design quantity of the blanking of the section plate includes multiple aspects of data, that is, it can include data such as ship number, section number, plate specifications (length, width, height), material, processing code, etc. Optionally, the design quantity of the blanking of the section plate can be stored in a corresponding Excel file or a corresponding database in a tabular form. Among them, the table of the design quantity of the blanking of the section plate corresponding to the plate cold processing procedure after storage can be as follows Figure 2 As shown. Figure 2 The design quantity table of the segmented plate blanking corresponding to the medium plate cold processing process may include data such as ship number H2453, segment number 101, part code, material, unit weight, processing / flow code, nesting card number, quantity, cutting length, specifications, etc.
[0040] Specifically, after receiving the construction task corresponding to the hull to be built, the basic hull data of the hull to be built carried in the construction task is determined. During the construction process of the hull to be built, the design quantity of the plate blanking of at least one section corresponding to the plate cold working process of the hull to be built can be determined through design drawings, corresponding process files and computer-aided design (CAD) software.
[0041] In an embodiment of the present invention, a method for determining basic hull data of a ship to be built and the design quantity of blanking of at least one segmented plate may be: receiving a ship number corresponding to the ship to be built, and determining the basic hull data of the ship to be built based on the ship number, wherein the basic hull data at least includes a construction plant for building the ship to be built, and determining a target quota standard relationship table based on the construction plant; and determining, based on the hull structure of the ship to be built, at least one segment for performing cold processing of plate and the design quantity of blanking of segmented plate corresponding to each segment.
[0042] Among them, the ship number of the hull to be built can be understood as the unique identifier corresponding to the hull to be built. The ship number is unique throughout the entire life cycle of ship design, construction, registration, operation and decommissioning. The ship number is used to distinguish and identify different ships. The ship number of the hull to be built usually consists of numbers and letters. For example, the ship number of the hull to be built may be H2453. The construction plant may be a plant used to perform plate cold processing procedures. For example, the construction plant may be Plant A, Plant B, and so on. The target quota standard relationship table can be understood as a data table determined according to the process documents, which consists of the construction plant of the hull to be built, the process name, the unit of quantity, the benchmark working hours, the plate thickness range and the corresponding working hour adjustment coefficient. For example, the target quota standard relationship table can be as follows Figure 3 shown.
[0043] Among them, in the target quota standard relationship table, the benchmark working hours can be understood as the basic working hours consumed by the plate cold processing process. Since the working hours consumed by the plate cold processing are affected by the plate thickness, different working hour adjustment coefficients are set for plates with different plate thickness ranges. The working hour adjustment coefficient can be understood as the coefficient value used to adjust the benchmark working hours. It can be understood that the plate thickness range and process adjustment coefficient to which the plate thickness belongs are determined by the plate thickness applied to the plate cold processing process of the hull to be built, so as to adjust the benchmark working hours based on the process adjustment coefficient.
[0044] It should be noted that due to differences in processing equipment, technical levels and processing raw materials equipped in different construction plants, the benchmark working hours, plate thickness ranges and process adjustment coefficients corresponding to different construction plants are different, that is, the target quota standard relationship tables corresponding to different construction plants are different.
[0045] The hull structure is the core part of the ship, which is composed of a series of plates and frames connected and supported by each other. Optionally, the hull structure can be composed of the deck, side plate, bottom plate, keel, side keel, keel, rib, bow column, stern column, etc. of the hull. In order to improve the efficiency of hull processing, the hull structure is usually divided into at least one section for processing. According to the material requirements corresponding to each section and the corresponding construction process, the specific section that needs to perform plate cold processing can be determined. For example, taking the hull to be built as a bulk carrier hull as an example, the hull structure of the bulk carrier can be divided into multiple deck sections, side plate sections and bottom sections. Since the side plate sections have curves and irregular shapes and need to withstand large water pressure, it may be necessary to perform plate cold processing operations to ensure the strength and stability of the side plate sections.
[0046] Specifically, the ship number corresponding to the hull to be built is received, and the basic data of the hull including the construction plant for building the hull to be built is determined according to the ship number. Since different construction plants correspond to different benchmark working hours, plate thickness ranges and process adjustment coefficients, the target quota standard relationship table corresponding to the current construction plant is determined. According to the construction process and material requirements of each section corresponding to the hull structure of the hull to be built, at least one section for performing plate cold working is determined. According to at least one section for performing plate cold working, the design material quantity of the section plate blanking corresponding to each section is calculated and determined through design drawings and process documents.
[0047] S120, retrieve the target quota standard relationship table associated with the hull basic data, and code the contents in the target quota standard relationship table to obtain the target execution program of the target quota standard relationship table.
[0048] The target execution program may be a code program for analyzing and processing the designed material quantity of the sectional plate blanking. The target execution program may be used to determine the man-hours corresponding to the designed material quantity of the sectional plate blanking.
[0049] Specifically, the target quota standard relationship table corresponding to the construction plant area is retrieved through the construction plant area in the basic data of the hull to be built. In order to facilitate the subsequent accurate determination of the man-hours required for the plate cold processing process, the benchmark man-hours, plate thickness range, and man-hour adjustment coefficients corresponding to the plate thickness range in the target quota standard relationship table can be coded to obtain a target execution program corresponding to the target quota standard relationship table, so as to determine the man-hours for the design quantity of each segmented plate blanking based on the target execution program.
[0050] S130, based on the target execution program, the designed material quantity of the blanking of the segmented plate is analyzed and processed in sequence to obtain the waiting man-hours for the designed material quantity of the blanking of each segmented plate.
[0051] The man-hours to be used can be understood as the man-hours corresponding to the designed material quantity of the sectional plate blanking. The man-hours to be used are calculated and determined based on the benchmark man-hours corresponding to the designed material quantity of the sectional plate blanking, the plate thickness range, and the man-hour adjustment coefficient.
[0052] Specifically, the design quantity of the blanking of the segmented plate is traversed according to the target execution program to determine at least one part for cold processing of the plate, the number of parts of each part, and the thickness of each part corresponding to the design quantity of the blanking of the segmented plate. The plate thickness range to which each part thickness belongs and the man-hour adjustment coefficient corresponding to the plate thickness range are determined through the target execution program. For each part, the base man-hour, man-hour adjustment coefficient, and number of parts corresponding to the current part are multiplied to obtain the man-hour corresponding to the current part. The man-hour to be used corresponding to the current design quantity of the blanking of the segmented plate is determined through the man-hour corresponding to at least one part.
[0053] In an embodiment of the present invention, the method of determining the waiting man-hours for each segmented plate blanking design quantity through the target execution program can be: for each segmented plate blanking design quantity, based on the target execution program, traverse the processing codes in the segmented plate blanking design quantity, determine at least one part code for cold processing of the plate, and obtain the number of parts corresponding to the part code; based on the target execution program, determine the target plate thickness range of the material to be processed under each part code and the corresponding target man-hour adjustment coefficient; based on the target man-hour adjustment coefficient of at least one part code associated with the segmented plate blanking design quantity, the base man-hour and the corresponding number of parts, determine the waiting man-hours for the segmented plate blanking design quantity.
[0054] Among them, the processing code is an identifier corresponding to the segmented plate blanking processing process, which is used to identify various information in the processing process. The processing code can be used to determine whether the plate cold processing is required during the processing of the segmented plate blanking design quantity. For example, if the processing code is empty, the plate cold processing is not required; correspondingly, if the processing code is not empty, the plate cold processing is required. In addition, since each processing code corresponds to a processing process of the segmented plate blanking design quantity, and each processing process can process at least one part, a processing code can correspond to the part code of at least one part. For example, Figure 2 The processing code "R / CC" in corresponds to the two part codes for cold processing of the plates, namely: "101-BX1A-DK5M-WR2" and "101-BX1A-DK5M-WR1". Parts refer to materials to be processed, which can be understood as plate materials to be cold processed. The number of parts refers to the number of plates to be cold processed. Since different parts have different specifications, that is, different materials to be processed have different plate thicknesses, the target plate thickness range and the corresponding target working time adjustment coefficient corresponding to each material to be processed can be determined. It can be understood that the plate thickness range corresponding to the material to be processed is the target plate thickness range. The working time adjustment coefficient corresponding to the target plate thickness range is the target working time adjustment coefficient.
[0055] Specifically, for each designed quantity of blanking of segmented plates, the processing codes in the designed quantity of blanking of segmented plates are traversed through the target execution program to determine at least one part code of the plate to be cold-processed corresponding to the processing code, as well as the number of parts for each part code. According to the target execution program, the target plate thickness range of the material to be processed and the corresponding target working time adjustment coefficient are determined for each part code. The working time corresponding to each part code is determined by multiplying the number of parts, the base working time, and the target working time adjustment coefficient corresponding to each part code. Since the designed quantity of blanking of segmented plates corresponds to at least one part code, the working time corresponding to at least one part code is accumulated to determine the working time to be used of the designed quantity of blanking of segmented plates.
[0056] For example, see Figure 2 .for Figure 2 The calculation method for the waiting working hours for the design quantity of cutting of the segmented plate with segment number 101 is as follows.
[0057] According to the target execution program, the processing codes of the design quantity of the segmented plate blanking are traversed, and the processing codes are "R / CC" and "R / FG". According to the processing code, at least one part code "101-BX1A-DK5M-WR2", "101-BX1A-DK5M-WR1", "101-01A-IB1C--WR2" and "101-01A-IB1C--WR1" to be cold-processed on the plate is determined. Since the working hours for each part code are calculated in the same way. Taking "101-BX1A-DK5M-WR2" as an example, it is determined that the number of parts corresponding to "101-BX1A-DK5M-WR2" is 1. According to the target execution program, the target plate thickness range of the material to be processed under "101-BX1A-DK5M-WR2" is determined to be [0,6), and the corresponding target working time adjustment coefficient is 1.00. The working time of the part code "101-BX1A-DK5M-WR2" is: base working time × target working time adjustment coefficient × number of parts, that is, 0.22 × 1.00 × 1 = 0.22. Each part code is processed in the above manner to obtain the working time corresponding to each part code. The working hours corresponding to the four part codes associated with the design quantity of the segmented plate blanking are accumulated to obtain the waiting working hours of the design quantity of the segmented plate blanking.
[0058] S140, based on the waiting man-hours for the design material quantities of all the segmented plates corresponding to the ship to be built, determine the target man-hours for cold working of the plates in each process of the ship to be built.
[0059] The target working hours can be understood as the time required to perform the cold processing procedures of the plates corresponding to all sections when building the hull to be built.
[0060] Specifically, during the construction of the ship to be built, there is at least one section that performs a plate cold working process. The waiting man-hours for the design quantities of the section plate blanking of all sections are accumulated to determine the target man-hours corresponding to the design quantities of the section plate blanking, that is, the target man-hours for the plate cold working.
[0061] In an embodiment of the present invention, a specific method for determining the target working time of the plate cold processing process based on the waiting working time of all the designed quantities of segmented plate blanking may be: obtaining the target working time by accumulating the waiting working time of all the designed quantities of segmented plate blanking corresponding to the hull to be built; after obtaining the target working time, the method further includes: generating feedback information based on the target working time and feeding it back.
[0062] The feedback information is used to inform the corresponding staff of the target working hours corresponding to the plate cold processing process.
[0063] Specifically, after determining the waiting man-hours for the design material quantity of the segmented plate blanking corresponding to each segment performing the plate cold working process, the waiting man-hours for the design material quantity of the segmented plate blanking of all segments are accumulated to obtain the target man-hours. Feedback information is generated based on the target man-hours, and the feedback information is fed back to the mobile phones, computers and other terminal devices of the relevant staff.
[0064] The technical solution of this embodiment provides data support for the subsequent calculation of the target working hours by receiving the basic hull data of the hull to be built and the design quantity of at least one segmented plate blanking. By calling the target quota standard relationship table associated with the basic hull data and coding the content in the target quota standard relationship table, a target execution program is obtained, and the program processing of the target quota standard relationship table is realized. Based on the target execution program, the design quantity of the blanking of the segmented plate is analyzed and processed in turn to obtain the waiting working hours of the design quantity of the blanking of each segmented plate. Not only can the waiting working hours be effectively determined, but also the processing efficiency is improved compared with manual processing. The target working hours of the plate cold processing of each process of the hull to be built are determined by the waiting working hours of all the design quantities of the blanking of the segmented plate corresponding to the hull to be built. Based on this, the target working hours for executing all the plate cold processing processes are accurately determined. The present invention processes the design quantity of the blanking of the segmented plate through the target execution program, which not only solves the problem of inaccurate search and low search efficiency caused by manual search of historical data in the prior art, improves the accuracy and efficiency of calculating the target working hours, but also avoids the maintenance of historical data and reduces data costs.
[0065] Embodiment 2
[0066] Figure 4 This is a flowchart of a method for determining the quota working hours applied to ships provided by the second embodiment of the present invention. This embodiment is based on the above embodiment and refines the step of "coding the contents in the target quota standard relationship table to obtain the target execution program of the target quota standard relationship table". The specific implementation method can refer to the technical solution of this embodiment. Among them, the technical terms that are the same or corresponding to the above embodiment are not repeated here. Figure 4 As shown, the method includes:
[0067] S210, receiving basic hull data of a hull to be built and a designed material quantity of at least one segmented plate.
[0068] S220, retrieve the target quota standard relationship table associated with the hull basic data.
[0069] S230, obtaining the reference working hours in the target quota standard relationship table and assigning them to the first preset variable, and assigning the plate thickness range and the corresponding working hours adjustment coefficient in the target quota standard relationship table to the second preset variable.
[0070] Among them, the target quota standard relationship table includes at least one plate thickness range and the man-hour adjustment coefficient corresponding to the plate thickness range. Optionally, the plate thickness range and the corresponding man-hour adjustment coefficient can be calculated based on the historical man-hours of the plate cold working process and the plate thickness. To facilitate subsequent processing, the plate thickness range is represented by the open interval symbols "(" and ")", the closed interval symbols "[" and "]" and the corresponding numbers. After the plate thickness range, there is the man-hour adjustment coefficient corresponding to the plate thickness range, and multiple plate thickness ranges are separated by semicolons.
[0071] For example, multiple plate thickness ranges can be expressed as "[0,6)1.00; [6,20)1.08; [20,100]1.54". It can be understood that when the plate thickness is greater than or equal to 0 mm and less than 6 mm, the man-hour adjustment coefficient is 1.00; when the plate thickness is greater than or equal to 6 mm and less than 20 mm, the man-hour adjustment coefficient is 1.08; when the plate thickness is greater than or equal to 20 mm and less than or equal to 100 mm, the man-hour adjustment coefficient is 1.54. In addition, if there is no plate thickness range or the plate thickness is not within the plate thickness range, the corresponding man-hour adjustment coefficient can be set to 1.00.
[0072] The first preset variable is a variable that is pre-set and used to characterize the benchmark working hours in the target execution program. For example, the first preset variable can be represented by "Jzgs". The second preset variable can be a variable that is pre-set and characterizes the plate thickness range and the corresponding working hour adjustment coefficient in the target execution program. For example, the second preset variable can be represented by "Expr".
[0073] Specifically, after retrieving the target quota standard relationship table, determine the reference working hours, plate thickness range, and working hour adjustment coefficient corresponding to the plate thickness range in the target quota relationship table. To facilitate the subsequent determination of the target execution program, assign the reference working hours to the first preset variable, assign the plate thickness range and the corresponding working hour adjustment coefficient to the second preset variable, and perform the analysis of the plate thickness range and the working hour adjustment coefficient based on the second preset variable.
[0074] For example, in conjunction with the above examples, see Figure 3 , assign the reference working hours to the first preset variable Jzgs, and assign the plate thickness range and working hours adjustment coefficient to the second preset variable Expr. That is, the first preset variable Jzgs = 0.22, and the second preset variable Expr is: [0,6) 1.00; [6,20) 1.08; [20,100] 1.54.
[0075] S240, parsing the character string length corresponding to the second preset variable in the target quota standard relationship table.
[0076] The character string length is the character string length corresponding to the second preset variable. The length of the character string can be used to determine whether there is a plate thickness range and a working time adjustment coefficient.
[0077] Specifically, the second preset variable corresponding to the plate thickness range and the man-hour adjustment coefficient in the target quota standard relationship table is parsed and processed to obtain the character string length corresponding to the second preset variable, so as to determine whether the plate thickness range and the man-hour adjustment coefficient exist in the target quota standard relationship table through the character string length. For example, if the character string length is 0, it means that the plate thickness range and the man-hour adjustment coefficient are not set in the target quota standard relationship table, and the man-hour adjustment coefficient can be set to 1. Correspondingly, if the character string length is not 0, the target execution program is determined according to the second preset variable corresponding to the plate thickness range and the man-hour adjustment coefficient.
[0078] S250. If the character string length is greater than a preset length threshold and there are preset characters, a target variable is created, and the first plate thickness range and the corresponding first working hour adjustment coefficient variable before the first preset character are assigned to the target variable, and the first plate thickness range and the first working hour adjustment coefficient in the second preset variable are deleted.
[0079] Among them, the preset length threshold is a preset standard value of the string length. Optionally, the preset length threshold is 0. The preset character can be understood as a character used to separate multiple plate thickness ranges. For example, if the second preset variable Expr is: [0,6)1.00; [6,20)1.08; [20,100]1.54, the preset character is a semicolon character. The target variable is used to characterize the plate thickness range and the man-hour adjustment coefficient variable of the parsed second preset variable. For example, the target variable can be represented by "S1". The first plate thickness range is the plate thickness range before the first preset character. The first man-hour adjustment coefficient is the man-hour adjustment coefficient before the first preset character.
[0080] Specifically, when the length of the character string is greater than the preset length threshold, it means that there is a plate thickness range and a work time adjustment coefficient in the second preset variable. If the length of the character string is greater than the preset length threshold and there are preset characters, it means that there are at least two plate thickness ranges and corresponding work time adjustment coefficients in the second preset variable. At this time, create a target variable, assign the first plate thickness range and the corresponding first work time adjustment coefficient before the first preset character to the target variable, and delete the first plate thickness range and the first work time adjustment coefficient in the second preset variable. Based on this, determine the first target variable obtained by traversing the second preset variable. Correspondingly, if the length of the character string is greater than the preset length threshold and there are no preset characters, it means that there is only one plate thickness range and the corresponding work time adjustment coefficient in the second preset variable. At this time, assign the plate thickness range and the work time adjustment coefficient in the second preset variable to the target variable, and set the second preset variable to empty.
[0081] Exemplarily, in combination with the above example, the second preset variable is Expr, the preset length threshold is 0, the preset character is a semicolon character, and the target variable is S1. If the string length of the second preset variable Expr is greater than 0 and there is a semicolon character in Expr, the first plate thickness range and the first man-hour adjustment coefficient before the semicolon character are assigned to the target variable S1, and the first plate thickness range, the first man-hour adjustment coefficient, and the first semicolon character in the second preset variable Expr are deleted. Correspondingly, if the string length of the second preset variable Expr is greater than 0 and there is no semicolon character in Expr, the plate thickness range and the man-hour adjustment coefficient in the second preset variable Expr are assigned to the target variable S1, and the second preset variable Expr is set to empty.
[0082] For example, the second preset variable Expr is [0,6)1.00; [6,20)1.08; [20,100]1.54. At this time, the string length of the second preset variable Expr is greater than 0 and there is a semicolon character. At this time, the [0,6)1.00 before the first semicolon character is assigned to the target variable S1, and the first semicolon character and [0,6)1.00 in the second preset variable are deleted to obtain the updated second preset variable [6,20)1.08; [20,100]1.54.
[0083] S260. Repeat the step of parsing the string length corresponding to the second preset variable in the target quota standard relationship table, and when the string length is greater than the preset length threshold and there are preset characters, create a target variable and update the data in the second preset variable until the string length in the second preset variable is less than the preset length threshold.
[0084] Specifically, the length of the string corresponding to the second preset variable in the target quota standard relationship table is determined by repeated analysis, and when the string length of the second preset variable is greater than the preset length threshold and there are preset characters, the target variable is created. The first plate thickness range and the corresponding first man-hour adjustment coefficient before the first preset character are assigned to the target variable, and the first plate thickness range and the first man-hour adjustment coefficient in the second preset variable are deleted until the string length of the second preset variable is less than the preset length threshold.
[0085] Exemplarily, in combination with the above example, the second preset variable [6,20)1.08;[20,100]1.54 after deleting the first semicolon character and [0,6)1.00 is parsed and processed to determine whether the string length of the second preset variable is greater than 0. If the string length of the second preset variable [6,20)1.08;[20,100]1.54 is greater than 0 and there is a semicolon character, a target variable S2 is created, and [6,20)1.08 before the first semicolon character in the second preset variable is assigned to the target variable S2, and the first semicolon character and [6,20)1.08 in the second preset variable are deleted to obtain the updated second preset variable [20,100]1.54.
[0086] It is determined again that the length of the string of the updated second preset variable is greater than 0, but there is no semicolon character in the second preset variable at this time, so a target variable S3 is created, [20,100]1.54 in the second preset variable is directly assigned to the target variable S3, and the second preset variable is set to empty. At this time, the second preset variable is less than or equal to the preset length threshold, and the parsing process of the second preset variable is stopped.
[0087] S270: Determine a target execution program based on the first preset variable and at least one target variable obtained after traversing the data in the second preset variable.
[0088] Specifically, a target execution program is determined based on a first preset variable corresponding to the benchmark working hours and at least one target variable obtained after traversing the plate thickness range and the corresponding working hour adjustment coefficient in the second preset variable, so as to analyze and process the material quantity of the segmented plate cutting design based on the determined target execution program, thereby determining the target working hours.
[0089] In an embodiment of the present invention, after obtaining the target variable, the plate thickness range query code and the corresponding work time adjustment coefficient determination code in the target execution program can also be determined based on the target variable, specifically in the following manner: if the first character in the target variable is the first preset symbol in the first preset symbol set, then add a target item to a predefined array and add a target content corresponding to the first preset symbol to the first part of the target item, and update the second character to the target content; delete the first second preset symbol of the target variable and all characters before the first second preset symbol to update the target variable; use the data content before the third preset symbol and the third preset symbol in the updated target variable as the data content of the second part of the target item, and delete the third preset symbol and all data before the third preset symbol in the target variable; use the remaining data content in the target variable as the third part in the target item to determine the plate thickness range query code and the corresponding work time adjustment coefficient determination code in the target execution program based on the first part, the second part and the third part in the target item.
[0090] Among them, the first preset symbol set is a preset set of symbols that the target variable may contain. For example, the first preset symbol set may include "(", "[", ")", "]", "." and ",". The first preset symbol is the first symbol that the target variable may contain in the first preset symbol set. For example, the first preset symbol may be "(" or "[". The predefined array is a preset multidimensional empty array. The predefined array is used to store the data content corresponding to the target variable. The target item may be an array item used to add to the predefined array. The target content can be understood as the data content corresponding to the target item. For example, if the first preset symbol is "(", the target content can be "<". The second character is the first numeric character in the target variable. The second preset symbol can be understood as a symbol used to separate two numeric characters in the target variable. For example, the second preset symbol can be a comma character. The third preset symbol is the third symbol corresponding to the target variable. For example, the third preset symbol can be ")" or "]".
[0091] For example, take the target variable [0,6)1.00 as an example, the first character in the target variable is "[", the first second preset symbol of the target variable is "," and the third preset symbol in the target variable is ")". Correspondingly, the target content corresponding to the first part of the target item is ">=" and "0", the data content of the second part of the target item is "6" and "<", and the data content of the third part of the target item is 1.00.
[0092] The plate thickness range query code is used to determine the plate thickness range to which the plate thickness belongs. The work time adjustment coefficient determination code is used to determine the work time adjustment coefficient determination code corresponding to the plate thickness range according to the plate thickness range.
[0093] Specifically, after obtaining the target variable, the characters contained in the target variable are traversed. If the first character in the target variable is the first preset symbol in the first preset symbol set, the target item is added to the predefined array, and the target content corresponding to the first preset symbol is added to the first part of the target item. The second character in the target variable is also updated to the target content. That is, at this time, the first part of the target item includes the data content corresponding to the first preset symbol and the second character. Delete the first second preset symbol and all characters before the first second preset symbol in the target variable, that is, delete the first preset symbol, the second character and the first second preset symbol in the target variable to obtain the updated target variable. The data content before the third preset symbol in the updated target variable and the third preset symbol are used as the third part of the target item, and the third preset symbol and all data before the third preset symbol are deleted to obtain the updated target variable. The remaining data content in the target variable at this time, that is, the working time adjustment coefficient, is used as the third part of the target item. Determine the plate thickness range query code and the working time adjustment coefficient code in the target execution program according to the first part, the second part and the third part of the target item.
[0094] Exemplarily, the predefined array can be represented as follows:
[0095] Type
[0096] Arr = Record of
[0097] Hd1:Float;
[0098] Exp1: String;
[0099] Hd2:Float;
[0100] Exp2: String;
[0101] Hdxs:Float;
[0102] End;
[0103] TArr:Array of Arr;
[0104] Among them, Hd1 represents the first thickness data in the plate thickness range, Hd2 represents the second thickness data in the plate thickness range, Exp1 represents the first symbol for comparing sizes corresponding to the plate thickness range, Exp2 represents the second symbol for comparing sizes corresponding to the plate thickness range, and Hdxs represents the working time adjustment coefficient corresponding to the plate thickness range.
[0105] Before determining each character of the target variable, it can be determined whether the format of the target variable is correct, that is, whether each character in the target variable is a number from "0" to "9", or a character in "(", "[", ")", "]", ".", ",". If so, it means that the format of the target variable is correct and the target variable can be parsed. If not, the target variable is re-determined according to the determination method of the target variable, that is, through S250.
[0106] When it is determined that the format of the target variable is correct, determine whether the first character of the target variable is "(" or "[". If so, add the target item to the array TArr. The first part of the target item is Hd1 and Exp1 in the array TArr, the second part of the target item is Hd2 and Exp2 in the array TArr, and the third part of the target item is Hdxs in TArr. Store ">" or ">=" in Exp1 of the first part of the target item, and store the second character of the target variable in Hd1 corresponding to the first part of the target item, and delete the first character, the second character and "," in the target variable to update the target variable. The third preset character of the updated target variable is stored in Exp1 of the first part of the target item. The third preset symbol and the data content before the third preset symbol are taken as the second part of the target item. That is, the "<" or "<=" corresponding to the third preset symbol is stored in Exp2 in the array TArr, and the data content before the third preset symbol is stored in Hd2 in the array TArr. Delete the third preset symbol in the target variable and all data before the third preset symbol. At this time, the remaining data content in the target variable is the working time adjustment coefficient, which is taken as the third part of the target item and stored in Hdxs of the array TArr. According to the array TArr corresponding to the first part, the second part and the third part of the target item, the plate thickness range query code and the corresponding working time adjustment coefficient determination code in the target execution program are determined.
[0107] Combined with the above example, the target variable [0,6)1.00 is used as an example for explanation. Each character in the target variable is traversed and processed to determine that the first character "[" of the target variable is the first preset symbol in the first preset symbol set, then the target item is added to the multidimensional empty array TArr, and the ">=" corresponding to "[" is added to the first part of the target item, that is, ">=" is stored in Exp1 of the array TArr, and the second character "0" of the target variable is stored in Hd1 of the array TArr. Delete the first character "[", the second character "0" and the second preset symbol "," in the target variable to obtain the updated target variable [6)1.00. The third preset symbol ")" of the updated target variable and the data content "6" before the third preset symbol ")" are used as the second part of the target item. That is, "6" is stored in Hd2 of the array TArr, and "<" is stored in Exp2 of the array TArr. Delete the third preset symbol in the target variable and all data before the third preset symbol. At this time, the target variable is 1.00. Take "1.00" as the third part of the target item and store it in Hdxs of the array TArr. At this time, in the array TArr corresponding to the first part, the second part and the third part of the target item, Hd1 is "0", Exp1 is ">=", Hd2 is "6", Exp2 is "<", and Hdxs is "1.00". According to the array of stored data content, determine the plate thickness range query code and the corresponding working time adjustment coefficient determination code in the target execution program.
[0108] In the implementation of the present invention, the method of determining the target execution program through the first preset variable and at least one target variable can be: determining the plate thickness range query code and the working time adjustment coefficient determination code in the target execution program according to the target item corresponding to each target variable in the predefined array; determining the target execution program based on the thickness range query code and the working time adjustment coefficient determination code corresponding to each target variable, and the first preset variable.
[0109] Specifically, according to the target item corresponding to each target variable in the predefined array, the plate thickness range query code is determined. According to the thickness range query code and the man-hour adjustment coefficient determination code corresponding to each target variable, and the first preset variable corresponding to the benchmark man-hour, the target execution program is determined. Based on this, when the design quantity of the segmented plate blanking is received, the plate thickness range corresponding to the design quantity of the segmented plate blanking is determined through the plate thickness range query code in the target execution program. And the man-hour adjustment coefficient corresponding to the plate thickness range is determined through the man-hour adjustment coefficient determination code. Through the man-hour adjustment coefficient and the first preset variable, the man-hour to be used corresponding to the design quantity of the segmented plate blanking can be determined.
[0110] S280, based on the target execution program, analyze and process the designed material quantity of the blanking of the segmented plate in turn to obtain the waiting man-hours of the designed material quantity of the blanking of each segmented plate.
[0111] Exemplarily, in combination with the above example, the plate thickness of the material to be processed under the current part code in the segmented plate blanking design quantity is Hd, and the number of parts is M to illustrate the target execution program's analysis process of the segmented plate blanking design quantity.
[0112] The target execution program is used to obtain the plate thickness Hd of the material to be processed under the current part code in the design quantity of the segmented plate blanking, as well as the number of parts M corresponding to the current part code. According to the plate thickness range query code in the target execution program, the array TArr is looped through (For i: = Low (TArr) To High (TArr) Do).
[0113] 1) If Exp1 in array TArr is ">", Exp2 is "<", and the plate thickness Hd is greater than Hd1 in array TArr and less than Hd2 in array TArr, the current plate thickness range is met. According to the work time adjustment coefficient determination code, the work time adjustment coefficient corresponding to the current plate thickness range is determined and assigned to the variable Hdxs, and the loop traversing the array is jumped out.
[0114] 2) If Exp1 in array TArr is ">", Exp2 is "<=", and the plate thickness Hd is greater than Hd1 in array TArr and less than or equal to Hd2 in array TArr, the current plate thickness range is met. According to the work time adjustment coefficient determination code, the work time adjustment coefficient corresponding to the current plate thickness range is determined and assigned to the variable Hdxs, and the loop traversing the array is jumped out.
[0115] 3) If Exp1 in array TArr is ">=", Exp2 is "<", and the plate thickness Hd is greater than or equal to Hd1 in array TArr and less than Hd2 in array TArr, the current plate thickness range is met. According to the work time adjustment coefficient determination code, the work time adjustment coefficient corresponding to the current plate thickness range is determined and assigned to the variable Hdxs, and the loop traversing the array is jumped out.
[0116] 4) If Exp1 in array TArr is ">=", Exp2 is "<=", and the plate thickness Hd is greater than or equal to Hd1 in array TArr and less than or equal to Hd2 in array TArr, the current plate thickness range is met. According to the work time adjustment coefficient determination code, the work time adjustment coefficient corresponding to the current plate thickness range is determined and assigned to the variable Hdxs, and the loop traversing the array is jumped out.
[0117] 5) If the array TArr is traversed and steps 1) to 4) do not find a satisfying plate thickness range, assign variable Hdxs=1.
[0118] 6) After determining the man-hour adjustment coefficient Hdxs, calculate the man-hour corresponding to the current part code, that is, man-hour = number of parts M × base man-hour Jzgs × man-hour adjustment coefficient Hdxs.
[0119] 7) Determine the man-hours to be used for the designed material quantity of the segmented plate blanking according to at least one part code associated with the designed material quantity of the segmented plate blanking and the man-hours corresponding to each part code.
[0120] S290. Based on the waiting man-hours for the design material quantities of all the segmented plates corresponding to the ship to be built, determine the target man-hours for cold working of the plates in each process of the ship to be built.
[0121] The technical solution of this embodiment obtains the benchmark working hours in the target quota standard relationship table and assigns them to the first preset variable, and assigns the plate thickness range and the corresponding working hour adjustment coefficient in the target quota standard relationship table to the second preset variable, so as to provide a variable basis for the subsequent determination of the target execution program. The character string length corresponding to the second preset variable in the target quota standard relationship table is parsed to determine the corresponding target variable according to the character string length. By parsing the second preset variable in the target quota standard relationship table, the target variable corresponding to the second preset variable can be accurately obtained, and the accuracy of the target variable is guaranteed. Based on the first preset variable and at least one target variable obtained after traversing the data in the second preset variable, the target execution program is determined, and the programmatic processing of the target quota standard relationship table is realized, which can not only ensure the accuracy of the data obtained by the subsequent traversal based on the target execution program, but also improve the processing efficiency compared to manual processing. The present invention determines a target execution program corresponding to a target quota standard relationship table, so that when the target working hours are subsequently determined according to the target execution degree, the target working hours corresponding to all plate cold processing procedures in the hull construction process can be effectively determined, thereby solving the problems of inaccurate search and low search efficiency caused by manual search of historical data in the prior art, improving the accuracy and efficiency of target working hour calculation and reducing data costs.
[0122] Embodiment 3
[0123] Figure 5 Schematic diagram of the structure of a device for determining the quota working hours used in a ship provided by the third embodiment of the present invention. Figure 5 As shown, the device includes: a data receiving module 310, a target execution program determination module 320, a to-be-used man-hour determination module 330 and a target man-hour determination module 340.
[0124] The data receiving module 310 is used to receive the basic hull data of the ship to be built and the designed quantity of at least one segmented plate blanking; the target execution program determination module 320 is used to retrieve the target quota standard relationship table associated with the basic hull data, and code the contents in the target quota standard relationship table to obtain the target execution program of the target quota standard relationship table; the waiting-for-use working time determination module 330 is used to analyze and process the designed quantity of segmented plate blanking in turn based on the target execution program to obtain the waiting-for-use working time for each segmented plate blanking designed quantity; the target working time determination module 340 is used to determine the target working time for the cold working of the plate in each process of the ship to be built based on the waiting-for-use working time of all the segmented plate blanking designed quantities corresponding to the ship to be built.
[0125] The technical solution of this embodiment provides data support for the subsequent calculation of the target working hours by receiving the basic hull data of the hull to be built and the design quantity of at least one segmented plate blanking. By calling the target quota standard relationship table associated with the basic hull data and coding the content in the target quota standard relationship table, a target execution program is obtained, and the program processing of the target quota standard relationship table is realized. Based on the target execution program, the design quantity of the blanking of the segmented plate is analyzed and processed in turn to obtain the waiting working hours of the design quantity of the blanking of each segmented plate. Not only can the waiting working hours be effectively determined, but also the processing efficiency is improved compared with manual processing. The target working hours of the plate cold processing of each process of the hull to be built are determined by the waiting working hours of all the design quantities of the blanking of the segmented plate corresponding to the hull to be built. Based on this, the target working hours for executing all the plate cold processing processes are accurately determined. The present invention processes the design quantity of the blanking of the segmented plate through the target execution program, which not only solves the problem of inaccurate search and low search efficiency caused by manual search of historical data in the prior art, improves the accuracy and efficiency of calculating the target working hours, but also avoids the maintenance of historical data and reduces data costs.
[0126] On the basis of the above embodiment, optionally, the device also includes a data determination module, which includes: a basic data determination unit, used to receive the ship number corresponding to the hull to be built, so as to determine the basic hull data of the hull to be built based on the ship number, wherein the hull basic data at least includes a construction plant for building the hull to be built, so as to determine the target quota standard relationship table based on the construction plant; a design quantity determination unit, used to determine at least one section for performing cold processing of the plate and the design quantity of the segmented plate cutting corresponding to each section according to the hull structure of the hull to be built.
[0127] Optionally, the target quota standard relationship table includes at least one plate thickness range and a working time adjustment coefficient corresponding to the plate thickness range, and the target execution program determines the module, which includes: a variable determination unit, used to obtain the benchmark working time in the target quota standard relationship table and assign it to a first preset variable, and assign the plate thickness range and the corresponding working time adjustment coefficient in the target quota standard relationship table to a second preset variable; a string parsing unit, used to parse the string length corresponding to the second preset variable in the target quota standard relationship table; a target variable determination unit, used to create a target variable if the string length is greater than a preset length threshold and there are preset characters, and assign the first plate before the first preset character The thickness range and the corresponding first working hour adjustment coefficient variable are assigned to the target variable, and the first plate thickness range and the first working hour adjustment coefficient in the second preset variable are deleted; a step repetition execution unit is used to repeatedly execute the step of parsing the string length corresponding to the second preset variable in the target quota standard relationship table, and when the string length is greater than the preset length threshold and there are preset characters, create a target variable and update the data in the second preset variable until the string length in the second preset variable is less than the preset length threshold; a target execution program determination unit is used to determine the target execution program based on the first preset variable and at least one target variable obtained after traversing the data in the second preset variable.
[0128] Optionally, after obtaining the target variable, the device also includes: a code determination module, which is used to add a target item to a predefined array and add a target content corresponding to the first preset symbol to the first part of the target item if the first character in the target variable is the first preset symbol in the first preset symbol set, and update the second character to the target content; delete the first second preset symbol of the target variable and all characters before the first second preset symbol to update the target variable; use the data content before the third preset symbol and the third preset symbol in the updated target variable as the data content of the second part of the target item, and delete the third preset symbol in the target variable and all data before the third preset symbol; use the remaining data content in the target variable as the third part in the target item to determine the plate thickness range query code and the corresponding working time adjustment coefficient determination code in the target execution program based on the first part, the second part and the third part of the target item.
[0129] Optionally, a target execution program determination unit is used to determine the plate thickness range query code and the working time adjustment coefficient determination code in the target execution program according to the target item corresponding to each target variable in a predefined array; determine the target execution program based on the thickness range query code and the working time adjustment coefficient determination code corresponding to each target variable, and the first preset variable.
[0130] Optionally, the module for determining the man-hours to be used includes: a unit for determining the number of parts, which is used to traverse the processing codes in the design quantity of segmented plate blanking for each segmented plate blanking design quantity based on a target execution program, determine at least one part code for cold processing of the plate, and obtain the number of parts corresponding to the part code; a unit for determining a thickness range and an adjustment coefficient, which is used to determine the target plate thickness range and the corresponding target man-hour adjustment coefficient of the material to be processed under each part code based on the target execution program; a unit for determining the man-hours to be used, which is used to determine the man-hours to be used for the design quantity of segmented plate blanking based on the target man-hour adjustment coefficient of at least one part code associated with the design quantity of segmented plate blanking, the base man-hour and the corresponding number of parts.
[0131] Optionally, the target working time determination module is used to obtain the target working time by accumulating the working time to be used for the design material quantity of all segmented plate blanking corresponding to the hull to be built; after obtaining the target working time, it also includes: generating and feeding back feedback information based on the target working time.
[0132] The device for determining the quota working hours applied in a ship provided in an embodiment of the present invention can execute the method for determining the quota working hours applied in a ship provided in any embodiment of the present invention, and has the functional modules and beneficial effects corresponding to the execution method.
[0133] Embodiment 4
[0134] Figure 6 1 is a schematic diagram of the structure of an electronic device provided in Embodiment 4 of the present invention. The electronic device 10 is intended to represent various forms of digital computers, such as laptop computers, desktop computers, workstations, personal digital assistants, servers, blade servers, mainframe computers, and other suitable computers. The electronic device may also represent various forms of mobile devices, such as personal digital processing, cellular phones, smart phones, wearable devices (such as helmets, glasses, watches, etc.) and other similar computing devices. The components shown herein, their connections and relationships, and their functions are merely examples and are not intended to limit the implementation of the present invention described and / or required herein.
[0135] like Figure 6As shown, the electronic device 10 includes at least one processor 11, and a memory connected to the at least one processor 11, such as a read-only memory (ROM) 12, a random access memory (RAM) 13, etc., wherein the memory stores a computer program that can be executed by at least one processor, and the processor 11 can perform various appropriate actions and processes according to the computer program stored in the read-only memory (ROM) 12 or the computer program loaded from the storage unit 18 to the random access memory (RAM) 13. In the RAM 13, various programs and data required for the operation of the electronic device 10 can also be stored. The processor 11, the ROM 12, and the RAM 13 are connected to each other through a bus 14. An input / output (I / O) interface 15 is also connected to the bus 14.
[0136] A number of components in the electronic device 10 are connected to the I / O interface 15, including: an input unit 16, such as a keyboard, a mouse, etc.; an output unit 17, such as various types of displays, speakers, etc.; a storage unit 18, such as a disk, an optical disk, etc.; and a communication unit 19, such as a network card, a modem, a wireless communication transceiver, etc. The communication unit 19 allows the electronic device 10 to exchange information / data with other devices through a computer network such as the Internet and / or various telecommunication networks.
[0137] The processor 11 may be a variety of general and / or special processing components with processing and computing capabilities. Some examples of the processor 11 include, but are not limited to, a central processing unit (CPU), a graphics processing unit (GPU), various special artificial intelligence (AI) computing chips, various processors running machine learning model algorithms, a digital signal processor (DSP), and any appropriate processor, controller, microcontroller, etc. The processor 11 executes the various methods and processes described above, such as the method for determining the quota working hours in a ship.
[0138] In some embodiments, the method for determining the quota time applied in a ship can be implemented as a computer program, which is tangibly contained in a computer-readable storage medium, such as a storage unit 18. In some embodiments, part or all of the computer program can be loaded and / or installed on the electronic device 10 via the ROM 12 and / or the communication unit 19. When the computer program is loaded into the RAM 13 and executed by the processor 11, one or more steps of the method for determining the quota time applied in a ship described above can be executed. Alternatively, in other embodiments, the processor 11 can be configured to execute the method for determining the quota time applied in a ship in any other appropriate manner (for example, by means of firmware).
[0139] Various implementations of the systems and techniques described above herein can be implemented in digital electronic circuit systems, integrated circuit systems, field programmable gate arrays (FPGAs), application specific integrated circuits (ASICs), application specific standard products (ASSPs), systems on chips (SOCs), load programmable logic devices (CPLDs), computer hardware, firmware, software, and / or combinations thereof. These various implementations can include: being implemented in one or more computer programs that can be executed and / or interpreted on a programmable system including at least one programmable processor, which can be a special purpose or general purpose programmable processor that can receive data and instructions from a storage system, at least one input device, and at least one output device, and transmit data and instructions to the storage system, the at least one input device, and the at least one output device.
[0140] The computer program for implementing the method for determining the quota working hours applied to ships of the present invention may be written in any combination of one or more programming languages. These computer programs may be provided to a processor of a general-purpose computer, a special-purpose computer or other programmable data processing device, so that when the computer program is executed by the processor, the functions / operations specified in the flow chart and / or block diagram are implemented. The computer program may be executed entirely on the machine, partially on the machine, partially on the machine and partially on a remote machine as a stand-alone software package, or entirely on a remote machine or server.
[0141] Embodiment 5
[0142] Embodiment 5 of the present invention further provides a computer-readable storage medium, wherein the computer-readable storage medium stores computer instructions, and the computer instructions are used to cause a processor to execute a method for determining a quota working time applied to a ship, the method comprising:
[0143] Receive basic hull data of a ship to be built and at least one designed quantity of plate blanking for a section; retrieve a target quota standard relationship table associated with the basic hull data, and code the contents in the target quota standard relationship table to obtain a target execution program for the target quota standard relationship table; analyze and process the designed quantity of plate blanking for a section in turn based on the target execution program to obtain the waiting working hours for the designed quantity of plate blanking for each section; determine the target working hours for cold working of the plate for each process of the ship to be built based on the waiting working hours for all the designed quantities of plate blanking for a section corresponding to the ship to be built.
[0144] In the context of the present invention, a computer-readable storage medium may be a tangible medium that may contain or store a computer program for use by or in combination with an instruction execution system, device or equipment. A computer-readable storage medium may include, but is not limited to, electronic, magnetic, optical, electromagnetic, infrared, or semiconductor systems, devices or equipment, or any suitable combination of the foregoing. Alternatively, a computer-readable storage medium may be a machine-readable signal medium. A more specific example of a machine-readable storage medium may include an electrical connection based on one or more lines, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the foregoing.
[0145] To provide interaction with a user, the systems and techniques described herein may be implemented on an electronic device having: a display device (e.g., a CRT (cathode ray tube) or LCD (liquid crystal display) monitor) for displaying information to the user; and a keyboard and a pointing device (e.g., a mouse or trackball) through which the user can provide input to the electronic device. Other types of devices may also be used to provide interaction with the user; for example, the feedback provided to the user may be any form of sensory feedback (e.g., visual feedback, auditory feedback, or tactile feedback); and input from the user may be received in any form (including acoustic input, voice input, or tactile input).
[0146] The systems and techniques described herein may be implemented in a computing system that includes backend components (e.g., as a data server), or a computing system that includes middleware components (e.g., an application server), or a computing system that includes frontend components (e.g., a user computer with a graphical user interface or a web browser through which a user can interact with implementations of the systems and techniques described herein), or a computing system that includes any combination of such backend components, middleware components, or frontend components. The components of the system may be interconnected by any form or medium of digital data communication (e.g., a communication network). Examples of communication networks include: a local area network (LAN), a wide area network (WAN), a blockchain network, and the Internet.
[0147] A computing system may include a client and a server. The client and the server are generally remote from each other and usually interact through a communication network. The client and server relationship is generated by computer programs running on the corresponding computers and having a client-server relationship with each other. The server may be a cloud server, also known as a cloud computing server or cloud host, which is a host product in the cloud computing service system to solve the defects of difficult management and weak business scalability in traditional physical hosts and VPS services.
[0148] It should be understood that the various forms of processes shown above can be used to reorder, add or delete steps. For example, the steps described in the present invention can be executed in parallel, sequentially or in different orders, as long as the desired results of the technical solution of the present invention can be achieved, and this document does not limit this.
[0149] The above specific implementations do not constitute a limitation on the protection scope of the present invention. It should be understood by those skilled in the art that various modifications, combinations, sub-combinations and substitutions can be made according to design requirements and other factors. Any modification, equivalent substitution and improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A method for determining the quota working hours used in ships, It is characterized in that include: Receiving basic hull data of a hull to be built and a designed quantity of blanking material of at least one segment plate; Retrieving a target quota standard relationship table associated with the hull basic data, and coding the contents in the target quota standard relationship table to obtain a target execution program of the target quota standard relationship table; Based on the target execution program, the designed material quantity of the blanking of the segmented plate is analyzed and processed in sequence to obtain the waiting man-hours for the designed material quantity of the blanking of each segmented plate; Based on the waiting man-hours for the designed material quantities of blanking of all segmented plates corresponding to the ship to be built, the target man-hours for cold working of the plates in each process of the ship to be built are determined.
2. The method according to claim 1, It is characterized in that Before receiving the basic data of the ship to be built and the designed quantity of blanking of at least one segmented plate, the method further includes: Receiving a ship number corresponding to a hull to be built, so as to determine the basic hull data of the hull to be built based on the ship number, wherein the basic hull data at least includes a construction plant where the hull to be built is built, so as to determine the target quota standard relationship table based on the construction plant; According to the hull structure of the ship to be built, at least one segment for performing cold working of the plate and the designed material quantity of the segment plate blanking corresponding to each segment are determined.
3. The method according to claim 1, It is characterized in that The target quota standard relationship table includes at least one plate thickness range and a working time adjustment coefficient corresponding to the plate thickness range. The coding process of the content in the target quota standard relationship table to obtain the target execution program of the target quota standard relationship table includes: Obtaining the reference working hours in the target quota standard relationship table and assigning them to a first preset variable, and assigning the plate thickness range and the corresponding working hours adjustment coefficient in the target quota standard relationship table to a second preset variable; Parsing the character string length corresponding to the second preset variable in the target quota standard relationship table; If the length of the character string is greater than a preset length threshold and there are preset characters, a target variable is created, and the first plate thickness range and the corresponding first man-hour adjustment coefficient variable before the first preset character are assigned to the target variable, and the first plate thickness range and the first man-hour adjustment coefficient in the second preset variable are deleted; Repeat the step of parsing the length of the string corresponding to the second preset variable in the target quota standard relationship table, and when the length of the string is greater than a preset length threshold and there are preset characters, create a target variable and update the data in the second preset variable, until the length of the string in the second preset variable is less than the preset length threshold; The target execution program is determined based on the first preset variable and at least one target variable obtained after traversing the data in the second preset variable.
4. The method according to claim 3, It is characterized in that After obtaining the target variable, the method further includes: If the first character in the target variable is a first preset symbol in a first preset symbol set, then adding a target item to a predefined array and adding a target content corresponding to the first preset symbol in a first part of the target item, and updating the second character to the target content; Deleting the first second preset symbol of the target variable and all characters before the first second preset symbol to update the target variable; Using the data content before the third preset symbol in the updated target variable and the third preset symbol as the data content of the second part in the target item, and deleting the third preset symbol in the target variable and all data before the third preset symbol; The remaining data content in the target variable is used as the third part in the target item to determine the plate thickness range query code and the corresponding working time adjustment coefficient determination code in the target execution program based on the first part, the second part and the third part in the target item.
5. The method according to claim 4, It is characterized in that The step of determining the target execution program based on the first preset variable and at least one target variable obtained after traversing the data in the second preset variable comprises: According to the target item corresponding to each target variable in the predefined array, a plate thickness range query code and a work time adjustment coefficient determination code in the target execution program are determined; The target execution program is determined according to the thickness range query code and the working time adjustment coefficient determination code corresponding to each target variable, and the first preset variable.
6. The method according to claim 1, It is characterized in that The target-based execution program sequentially analyzes and processes the designed material quantities of the segmented plate blanking to obtain the waiting man-hours for the designed material quantities of the segmented plate blanking, including: For each segmented plate blanking design quantity, traverse the processing codes in the segmented plate blanking design quantity based on the target execution program, determine at least one part code to be cold-processed on the plate, and obtain the number of parts corresponding to the part code; Determine the target plate thickness range of the material to be processed and the corresponding target working time adjustment factor for each part code based on the target execution program; The man-hours to be used for the designed quantity of blanking of the segmented plate are determined based on the target man-hour adjustment coefficient of at least one part code associated with the designed quantity of blanking of the segmented plate, the reference man-hours, and the corresponding number of parts.
7. The method according to claim 1, It is characterized in that The method of determining the target working time for cold working of the plates in each process of the ship to be built based on the working time to be used for the designed material quantity of all the segmented plates corresponding to the ship to be built includes: The target working hours are obtained by accumulating the man-hours to be used for the design material quantities of the blanking of all the segmented plates corresponding to the hull to be built; After obtaining the target working hours, the method further includes: Feedback information is generated based on the target working hours and fed back.
8. A device for determining the quota working hours used in ships, It is characterized in that include: A data receiving module, used for receiving basic hull data of a hull to be built and a designed material quantity of at least one segmented plate blanking; A target execution program determination module is used to retrieve a target quota standard relationship table associated with the hull basic data, and code the contents in the target quota standard relationship table to obtain a target execution program of the target quota standard relationship table; A module for determining the man-hours to be used is used to analyze and process the designed material quantities of the blanking of the segmented plates in sequence based on the target execution program to obtain the man-hours to be used for the designed material quantities of the blanking of each segmented plate; The target working time determination module is used to determine the target working time for cold working of the plates in each process of the ship to be built based on the working time to be used for the design material quantity of all segmented plates corresponding to the ship to be built.
9. An electronic device, It is characterized in that The electronic device comprises: at least one processor; and a memory communicatively connected to the at least one processor; wherein, The memory stores a computer program executable by the at least one processor, and the computer program is executed by the at least one processor so that the at least one processor can execute the method for determining the quota working hours applied in a ship according to any one of claims 1 to 7.
10. A computer-readable storage medium, It is characterized in that The computer-readable storage medium stores computer instructions, and the computer instructions are used to enable a processor to implement the method for determining the quota working hours applied to a ship according to any one of claims 1 to 7 when executed.