Direct-current power supply intelligent sharing system and method for transformer substation

The DC power intelligent sharing system addresses the challenge of load fluctuations in substations by implementing intelligent load balancing and resource optimization, enhancing stability and reliability.

CN119093314AActive Publication Date: 2024-12-06WUXI GUANGYING ELECTRIC POWER DESIGN CO LTD +1
View PDF 9 Cites 0 Cited by

Patent Information

Application Number
CN202411394497.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-08
Publication Date
2024-12-06
Estimated Expiration
2044-10-08

AI Technical Summary

Technical Problem

Existing substations with multiple independent DC power supplies struggle to handle large load fluctuations, leading to power supply overload, poor stability, and low resource utilization efficiency.

Method used

A DC power intelligent sharing system that includes modules for monitoring data acquisition, load type determination, parallel DC power supply configuration, load distribution node establishment, allocation rule configuration, and parallel DC power supply sharing distribution, enabling intelligent load balancing and resource optimization.

Benefits of technology

Improves resource utilization efficiency and stability by intelligently sharing DC power resources, effectively managing load fluctuations and ensuring reliable power supply.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119093314A_ABST
    Figure CN119093314A_ABST
Patent Text Reader

Abstract

The invention discloses a direct-current power supply intelligent sharing system and method for a transformer substation, and relates to the technical field of transformer substations, and the system comprises the steps: installing a sensor at each load end of the transformer substation, and obtaining monitoring data; determining a load type; configuring a parallel direct-current power supply; establishing a load distribution node according to the load handling capacity and the residual load capacity; configuring an allocation rule based on the load type; distributing the load request quantity, and determining a distribution relationship between the load request quantity and a load distribution node; and sharing and distributing the parallel direct-current power supply. The technical problems of poor stability and reliability and low resource utilization efficiency of the transformer substation due to the fact that a plurality of load ends are provided with independent direct-current power supplies and are difficult to deal with large load fluctuation and the power supply is easy to be overloaded in the direct-current power supply of the existing transformer substation are solved, intelligent sharing of the direct-current power supply is realized, and the service life of the transformer substation is prolonged. The technical effect of improving the resource utilization efficiency and the stability and reliability of the transformer substation is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field related to substations, and in particular to a direct current power intelligent sharing system and method for substations. Background Art

[0002] Therefore, in the current substation DC power supply related technologies, there are technical problems that multiple load ends are equipped with independent DC power supplies, which makes it difficult to cope with large load fluctuations and easily causes power supply overload, thereby leading to poor stability and reliability of the substation and low resource utilization efficiency. Summary of the invention

[0003] The present application provides a DC power intelligent sharing system and method for a substation, thereby solving the technical problem that the DC power supply of an existing substation is equipped with multiple load ends with independent DC power supplies, which makes it difficult to cope with large load fluctuations and easily causes power overload, thereby leading to poor stability and reliability of the substation and low resource utilization efficiency. The application realizes the intelligent sharing of DC power and achieves the technical effect of improving resource utilization efficiency and the stability and reliability of the substation.

[0004] The present application provides a DC power intelligent sharing system for a substation, the system comprising: a monitoring data acquisition module, used to install sensors at each load end of the substation to obtain monitoring data, including monitoring current and power fluctuations; a load type determination module, used to identify load characteristics according to the monitoring data, determine the load type, the load type includes continuous load and intermittent load, and use the load type to generate a type label to identify the load of each load end; a parallel DC power configuration module, used to configure a parallel DC power supply, the parallel DC power supply includes a plurality of DC power supplies, and obtain the load processing capacity and the remaining load of each DC power supply; a load distribution node establishment module, used to identify the load characteristics according to the monitoring data, determine the load type, and generate a type label to identify the load of each load end; a parallel DC power configuration module, used to configure a parallel DC power supply, the parallel DC power supply includes a plurality of DC power supplies, and obtain the load processing capacity and the remaining load of each DC power supply; a load distribution node establishment module, used to identify the load processing capacity and the remaining load of each DC power supply according to the monitoring data ... The load processing capacity and remaining load of each DC power supply are used to establish a load distribution node, wherein the load distribution node corresponds to the parallel position of the DC power supply, and the load of the load distribution node corresponds to the remaining load; an allocation rule configuration module is used to obtain the load request amount of the load end, and configure the allocation rule based on the load type of the load request amount; an allocation relationship determination module is used to allocate the load request amount based on the allocation rule according to the remaining load amount of the load distribution node, and determine the allocation relationship between the load request amount and the load distribution node; a parallel DC power supply sharing allocation module is used to share the parallel DC power supplies according to the allocation relationship.

[0005] In a possible implementation, the load type determination module also performs the following processing: extracting a load data set based on the monitoring data; calculating the mean, variance, peak and frequency characteristics of the load data set; extracting the continuous interval characteristics of the load based on the calculation results of the mean, variance, peak and frequency characteristics, and setting the load type based on the continuous interval characteristics.

[0006] In a possible implementation, the load type determination module also performs the following processing: extracting the core frequency component according to the frequency characteristics; determining the duty cycle of the load signal according to the core frequency component; reconstructing the time domain information by inverse Fourier transform according to the core frequency component to determine the working time and interval time of the load signal within the working cycle; calculating the continuous time mean, continuous time variance, interval time mean, and interval time variance using the mean and variance based on the working time and interval time respectively; identifying the ratio relationship between the continuous time and the interval time based on the continuous time mean, continuous time variance, interval time mean, and interval time variance to determine the load type, wherein the continuous load is a continuous time mean that is greater than the interval time mean, and the variance of the continuous working time and the interval time is small.

[0007] In a possible implementation, the allocation rule configuration module also performs the following processing: configuring the allocation priority according to the load type, wherein the continuous load priority is greater than the intermittent load priority; when the remaining load amount does not meet the load request amount, activating the energy storage system for supplying power to the intermittent load; when the remaining load amount meets the continuous load and there is a surplus, dividing the supply of the intermittent load, wherein a part of the division is supplied through the energy storage system, and a part of the division shares the DC power supply with the continuous load.

[0008] In a possible implementation, the distribution relationship determination module also performs the following processing: setting a load synchronization window according to the remaining load of the load distribution node, and the load synchronization window is used to synchronously satisfy all loads in the window; identifying the load type according to the load request amount, and extracting the load of the continuous load type; traversing the load of the continuous load type using the load synchronization window to determine the synchronization window matching relationship; identifying the window load according to the synchronization window matching relationship, and the window load is the load balance of the synchronization window; splitting the synchronization window based on the window load, and using the split window to perform intermittent load traversal distribution to determine the matching relationship of the split window.

[0009] In a possible implementation, the allocation rule configuration module also performs the following processing: constructing an optimization objective function of the energy storage system by minimizing the operating cost; obtaining the charging and discharging power of the energy storage system to meet the balance constraint condition of the DC power supply capacity; optimizing according to the balance constraint condition and the optimization objective function to determine the energy supply timing chain of the energy storage system; extracting the load timing relationship according to the demand time and interval time of the intermittent load, optimizing the allocation with the goal of minimizing the waiting time of the intermittent load, and determining the load supply demand timing chain; configuring the weight coefficients of the energy supply timing chain and the load supply demand timing chain, wherein the weight coefficient of the energy supply timing chain is greater than the weight coefficient of the load supply demand timing chain; based on the weight coefficients, using the Nash equilibrium algorithm to balance and optimize the energy supply timing chain and the load supply demand timing chain to determine the supply relationship between the energy storage system and the intermittent load.

[0010] In a possible implementation, the allocation rule configuration module further performs the following processing: the optimization objective function expression is: Among them, C e (t) is the operating cost of the energy storage system at time t, P e (t) is the discharge power of the energy storage system at time t, P c (t) is the charging power of the energy storage system at time t, φ is the charging and discharging efficiency of the energy storage system, and T is the total time period.

[0011] The present application also provides a method for intelligent sharing of DC power supplies for a substation, the method comprising: installing sensors at each load end of the substation to obtain monitoring data, including monitoring current and power fluctuations; identifying load characteristics according to the monitoring data to determine the load type, the load type including continuous load and intermittent load, and using the load type to generate a type label to identify the load at each load end; configuring parallel DC power supplies, the parallel DC power supplies including multiple DC power supplies, obtaining the load processing capacity and remaining load of each DC power supply; establishing a load distribution node according to the load processing capacity and remaining load of each DC power supply, the load distribution node corresponding to the parallel position of the DC power supply, and the load of the load distribution node corresponding to the remaining load; obtaining the load request amount of the load end, and configuring a distribution rule based on the load type of the load request amount; according to the remaining load amount of the load distribution node, distributing the load request amount based on the distribution rule, and determining the distribution relationship between the load request amount and the load distribution node; and performing shared distribution of the parallel DC power supplies according to the distribution relationship.

[0012] The intelligent sharing system and method of DC power supply for substation proposed in this application is to install sensors at each load end of the substation to obtain monitoring data; determine the load type; configure parallel DC power supply; establish load distribution nodes according to load processing capacity and remaining load; configure distribution rules based on load type; distribute load request quantity, determine the distribution relationship between load request quantity and load distribution node; and share and distribute parallel DC power supply. It solves the technical problem that multiple load ends of the DC power supply of the existing substation are equipped with independent DC power supplies, which is difficult to cope with large load fluctuations and easily causes power supply overload, thereby leading to poor stability and reliability of the substation and low resource utilization efficiency. It realizes intelligent sharing of DC power supply and achieves the technical effect of improving resource utilization efficiency and stability and reliability of the substation. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] In order to more clearly illustrate the technical solution of the embodiment of the present disclosure, the accompanying drawings of the embodiment of the present disclosure will be briefly introduced below. A flow chart is used in the present application to illustrate the operations performed by the system according to the embodiment of the present application. It should be understood that the preceding or following operations are not necessarily performed accurately in order. On the contrary, various steps can be processed in reverse order or simultaneously as needed. At the same time, other operations can also be added to these processes, or one or more operations can be removed from these processes.

[0014] Figure 1 A schematic diagram of the structure of a DC power intelligent sharing system for a substation provided in an embodiment of the present application;

[0015] Figure 2 A flow chart of a method for intelligent sharing of DC power supply for a substation provided in an embodiment of the present application.

[0016] Explanation of the accompanying drawings: monitoring data acquisition module 10, load type determination module 20, parallel DC power supply configuration module 30, load distribution node establishment module 40, distribution rule configuration module 50, distribution relationship determination module 60, parallel DC power supply sharing distribution module 70. DETAILED DESCRIPTION

[0017] The above description is only an overview of the technical solution of the present application. In order to more clearly understand the technical means of the present application, it can be implemented in accordance with the contents of the specification. In order to make the above and other purposes, features and advantages of the present application more obvious and easy to understand, the specific implementation methods of the present application are listed below.

[0018] In order to make the purpose, technical solutions and advantages of the present application clearer, the present application will be further described in detail below in conjunction with the accompanying drawings. The described embodiments should not be regarded as limiting the present application. All other embodiments obtained by ordinary technicians in the field without making creative work are within the scope of protection of this application.

[0019] In the following description, reference is made to "some embodiments", which describe a subset of all possible embodiments, but it is understood that "some embodiments" may be the same subset or different subsets of all possible embodiments, and may be combined with each other without conflict, and the terms "first\second" involved are merely to distinguish similar objects and do not represent a specific ordering of objects. The terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions, for example, a process, system, product, or server that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or modules that are not clearly listed or inherent to these processes, products, or devices. Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those generally understood by technicians in the technical field of this application. The terms used herein are for the purpose of describing the embodiments of the present application only.

[0020] The present application embodiment provides a DC power intelligent sharing system for a substation, such as Figure 1 As shown, the system comprises:

[0021] The monitoring data acquisition module 10 is used to install sensors at each load end of the substation to obtain monitoring data, including monitoring current and power fluctuations. According to the characteristics and installation conditions of the load, suitable sensors are installed at each load end of the substation to obtain monitoring data, including monitoring current and power fluctuations. Sensors are installed at each load end of the substation to monitor the operating status of each load in real time and obtain key operating data, so as to ensure the stable operation of the substation and the reasonable distribution of power supply. The monitoring data obtained includes monitoring current and power fluctuations. Specifically, current is an important parameter to characterize the working state of the load. The current value of the load is monitored in real time by the sensor to understand the real-time power consumption of the load and whether it is in a normal working state. Among them, for the current measurement of the high-voltage circuit, an insulating clamp is required to be used for measurement to ensure the accuracy and safety of the measurement. The monitored current data can determine the load type of the load, such as continuous load and intermittent load; power fluctuation reflects the dynamic changes of the load during operation. By monitoring the power fluctuation, the stability of the load and the requirements for power quality can be understood. The monitored power fluctuation data can evaluate the stability and reliability of the power supply system, and whether the power supply allocation strategy needs to be adjusted to cope with load changes.

[0022] The load type determination module 20 is used to identify the load characteristics according to the monitoring data, determine the load type, and the load type includes continuous load and intermittent load. The load type is used to generate a type label to identify the load of each load end. Load characteristic identification is to classify the working characteristics of each load end in the substation according to the monitoring data, that is, to determine the load type according to the detection current and power fluctuation. Specifically, based on the collected monitoring data, the characteristics of the load are identified, and the key characteristics such as the current change mode and power fluctuation range of the load are analyzed. According to the results of load characteristic identification, the load is divided into different types, mainly including continuous load and intermittent load. Continuous load refers to a load that works continuously and stably and has small current and power fluctuations, such as some constant production equipment; intermittent load refers to a load that has frequent start and stop during the working process and has large current and power fluctuations, such as some intermittent working equipment; using the identified load type, a corresponding type label is generated for each load end to identify and distinguish the working characteristics of different loads.

[0023] The parallel DC power supply configuration module 30 is used to configure a parallel DC power supply, wherein the parallel DC power supply includes multiple DC power supplies, and obtains the load processing capacity and the remaining load capacity of each DC power supply. A parallel DC power supply refers to connecting the positive and negative poles of multiple DC power supplies together to form an integrated power supply system. By connecting in parallel, the total voltage (when the voltage is the same) or the total current (when the current is the same) can be increased to meet the power supply requirements of more loads. Specifically, when configuring a parallel DC power supply, consider whether the voltage, current, power and other parameters of each DC power supply match. Usually, multiple DC power supplies with the same voltage, similar current and power are selected for parallel connection to ensure the stability and reliability of the power supply system. During the configuration process, the capacity and safety of the power supply system must also be considered to ensure that the system can meet the power supply requirements of various loads. Load processing capacity refers to the load capacity that a DC power supply can handle within a specific time. It is calculated by measuring the output current, voltage and other parameters of the DC power supply and combining them with the power demand of the load. For example, if a DC power supply can handle a load power of 1000W within 1 hour, then its load processing capacity is 1000W / h; the remaining load capacity refers to the load capacity that the DC power supply can still handle within a specific time. It is obtained by subtracting the processed load capacity from the total capacity of the DC power supply. For example, if the total capacity of a DC power supply is 2000W / h and it has handled a load of 1000W / h, then its remaining load capacity is 1000W / h; in a parallel DC power supply system, the output data of each DC power supply can be collected in real time through the monitoring system, and calculated and analyzed according to the preset algorithm, and finally the load processing capacity and remaining load of each DC power supply can be obtained.

[0024] The load distribution node establishment module 40 is used to establish a load distribution node according to the load processing capacity and the remaining load of each DC power supply. The load distribution node corresponds to the parallel position of the DC power supply, and the load of the load distribution node corresponds to the remaining load. The load distribution node is used to distribute the load according to the remaining load of the DC power supply to ensure that the load is evenly distributed among multiple DC power supplies. Specifically, the collected data is analyzed to understand the working status and performance of each DC power supply, and the DC power supply with a large remaining load and the DC power supply with a small remaining load are identified. According to the difference in the remaining load, a load distribution strategy is formulated to achieve a balanced distribution of the load among multiple DC power supplies. At the same time, the remaining load of each DC power supply is fully utilized to establish load distribution nodes. These load distribution nodes correspond to the parallel position of the DC power supply to ensure that the load can be correctly distributed to each DC power supply, that is, according to the load distribution strategy, a corresponding load is set for each load distribution node, and the load should correspond to the remaining load of each DC power supply to ensure the rationality and effectiveness of the load distribution.

[0025] The allocation rule configuration module 50 is used to obtain the load request amount of the load end, and configure the allocation rule based on the load type of the load request amount. The load request amount refers to the amount of electricity that the load end (such as equipment, system or application) needs to process or consume within a specific time. The load current, power and other parameters are collected in real time through sensors or other monitoring devices installed at the load end, and then the load request amount is calculated. According to the characteristics of the load request amount (such as continuity, intermittence, peak value, etc.), the load is divided into different types, such as continuous load, intermittent load, peak load, etc. Different types of loads have different impacts and requirements on the power supply system. According to the load type and the actual situation of the system, the corresponding allocation rules are formulated, that is, the allocation rules are configured. For example, for continuous loads, stable power can be allocated first; for intermittent loads, the power distribution can be dynamically adjusted according to their working cycle and peak value.

[0026] The allocation relationship determination module 60 is used to allocate the load request according to the remaining load of the load distribution node based on the allocation rule, and determine the allocation relationship between the load request and the load distribution node. The remaining load of the load distribution node represents the load that the node can still handle in the current time period. The load request is allocated according to the allocation rule. During the allocation process, the best allocation scheme is determined based on factors such as the type, size and time of the load request, as well as the remaining load and processing capacity of each node. For example, the load is preferentially allocated to nodes with larger remaining load to make full use of system resources; for continuous load, it is preferentially allocated to nodes with higher stability; for intermittent load, it is dynamically allocated according to the processing capacity of the node and the load fluctuation; during the allocation process, one or more target load distribution nodes are determined for each load request, and these nodes will be responsible for processing the load request, that is, the allocation relationship between the load request and the load distribution node is determined.

[0027] The parallel DC power supply sharing distribution module 70 is used to share and distribute the parallel DC power supplies according to the distribution relationship. After the load distribution relationship is determined, the load request amount is distributed to the parallel DC power supplies according to the distribution relationship. Specifically, according to the distribution relationship, the DC power supply to which each load request amount needs to be distributed is determined, and according to the distributed load request amount, the output current or voltage of the target DC power supply is adjusted to ensure that the parameters of the power supply output meet the load requirements. During the load distribution process, the status and load conditions of each power supply are monitored in real time. If it is found that the load of a power supply is too heavy or insufficient, it is optimized by adjusting the distribution relationship or increasing or decreasing the number of parallel power supplies, and finally load balancing is achieved, that is, ensuring that each power supply bears an appropriate amount of load to improve the overall performance and stability of the system.

[0028] The DC power intelligent sharing system for substations according to the embodiment of the present invention is used to solve the problem that multiple load ends of the DC power supply of the existing substation are equipped with independent DC power supplies, which is difficult to cope with large load fluctuations, easily causing power overload, and thus leading to poor stability and reliability of the substation and low resource utilization efficiency. The DC power intelligent sharing system for substations includes: a monitoring data acquisition module 10, a load type determination module 20, a parallel DC power configuration module 30, a load distribution node establishment module 40, a distribution rule configuration module 50, a distribution relationship determination module 60, and a parallel DC power sharing distribution module 70.

[0029] The specific configuration of the load type determination module 20 will be described in detail below. The load type determination module 20 may further include: extracting a load data set based on the monitoring data. Extracting a load data set for analysis from the original monitoring data includes changes in the load over a period of time. It also includes calculating the mean, variance, peak and frequency characteristics based on the load data set. The load data mean is the sum of the load data of each load end divided by the total number of load ends, indicating the overall level of the load; the load data variance is the sum of the squares of the difference between the load data of each load end and the load mean and then divided by the total number of load ends, indicating the discreteness or fluctuation of the load data; the load peak is to find the maximum value of the load data in the load data set, which is used to indicate the maximum processing capacity or demand of the load; the frequency characteristic refers to analyzing the frequency of load changes in the load data set, that is, the speed or frequency of the load switching between different values.

[0030] The load type determination module 20 also includes extracting the continuous interval characteristics of the load according to the calculation results of the mean, variance, peak and frequency characteristics, and setting the load type according to the continuous interval characteristics. According to the previously calculated mean, variance, peak and frequency characteristics, combined with the time series analysis method, the continuous high load or low load intervals in the load data set are identified, and the duration and intervals of these intervals are calculated, that is, the continuous interval characteristics of the load are extracted. According to the extracted continuous interval characteristics, combined with the actual application scenarios and business requirements of the load, appropriate thresholds and conditions are set to determine the load type. For example, if a load maintains a high load state for most of the time, and the intervals between continuous high load intervals are very short, it can be determined as a continuous load; if the load frequently switches between high load and low load, and the switching interval is short, it can be determined as an intermittent load.

[0031] The specific configuration of the load type determination module 20 will be described in detail below. The load type determination module 20 may further include: extracting the core frequency component according to the frequency feature. In the frequency domain, the load signal may contain multiple frequency components, and the core frequency component refers to the frequencies that contribute the most to the signal, that is, the main components of the signal, which are achieved by finding the peaks in the spectrum. It also includes determining the duty cycle of the load signal according to the core frequency component. The reciprocal of the core frequency component is usually equal to the duty cycle. For example, if the core frequency is 1Hz, then the duty cycle is 1 second. The duty cycle refers to the time required for the signal to complete a complete cycle. It also includes reconstructing the time domain information through inverse Fourier transform according to the core frequency component to determine the working time and interval time of the load signal within the duty cycle. The time domain information of the core frequency component is reconstructed by inverse Fourier transform, and the change of the signal in time is analyzed. By detecting the transition point of the signal from low level to high level (or vice versa), the working time and interval time of the load signal can be determined.

[0032] The load type determination module 20 also includes, based on the working time and the interval time, using the mean and variance to calculate the continuous time mean, continuous time variance, interval time mean, and interval time variance. The continuous time mean refers to the average value of all working time periods; the continuous time variance refers to the average value of the square of the deviations of all working time periods from their mean; the interval time mean refers to the average value of all interval time periods; the interval time variance refers to the average value of the square of the deviations of all interval time periods from their mean. It also includes, based on the continuous time mean, continuous time variance, interval time mean, and interval time variance, identifying the ratio relationship between continuous time and interval time, and determining the load type, wherein the continuous load is that the continuous time mean is greater than the interval time mean, and the variance of the continuous working time and the interval time is small. By comparing the continuous time mean and the interval time mean, as well as their variances, the load type can be identified. If the continuous time mean is greater than the interval time mean, and the variance of the continuous working time and the interval time is small, the load can be identified as a continuous load, because the continuous load usually maintains a longer continuous working state when working, while the interval time is relatively short and stable; on the contrary, the intermittent load has a shorter working time and a longer interval time, and the variance of the working time and the interval time is larger.

[0033] The specific configuration of the allocation rule configuration module 50 will be described in detail below. The allocation rule configuration module 50 may further include: configuring the allocation priority according to the load type, wherein the continuous load priority is greater than the intermittent load priority. Since the continuous load generally requires a continuous and stable power supply, its priority is set higher than the intermittent load. The intermittent load may not require power in certain time periods, or its working cycle includes a long idle time. In the case of limited resources, the priority of the intermittent load is relatively low.

[0034] The allocation rule configuration module 50 also includes, when the remaining load does not meet the load request, activating the energy storage system for the intermittent load power supply. Compare the remaining load and the load request to decide how to allocate the power. When the remaining load does not meet the request of all loads (including continuous loads and intermittent loads), the system will give priority to meeting the needs of the continuous load and activate the energy storage system to provide power for the intermittent load to ensure the stable operation of the continuous load while minimizing the impact on the intermittent load. The energy storage system (such as batteries, super capacitors, etc.) is used to provide power during peak power demand or insufficient power supply.

[0035] The allocation rule configuration module 50 also includes, when the remaining load quantity meets the continuous load and there is a surplus, the intermittent load is supplied and divided, wherein a part of the supply is supplied by the energy storage system, and a part of the supply is shared with the continuous load. When the remaining load quantity meets the needs of the continuous load and there is still a surplus, the power supply of the intermittent load is divided, and a part of the power demand of the intermittent load is supplied by the energy storage system, which can reduce the burden of the DC power supply and extend the service life of the energy storage system; the other part of the intermittent load shares the DC power supply with the continuous load, and it is necessary to reasonably allocate the power supply of the DC power supply according to the working characteristics and needs of the intermittent load under the premise of meeting the stable operation of the continuous load.

[0036] The specific configuration of the allocation relationship determination module 60 will be described in detail below. The allocation relationship determination module 60 may further include: setting a load synchronization window according to the remaining load of the load distribution node, and the load synchronization window is used to synchronously meet all loads in the window. The size of the load synchronization window is set according to the remaining load of the load distribution node. The more the remaining load, the larger the synchronization window may be; conversely, the synchronization window may be smaller, wherein the load synchronization window is a window of time or electrical energy, which is used to ensure that all loads in the window can be met within the same time period. It also includes identifying the load type according to the load request amount and extracting the load amount of the continuous load type. According to the working characteristics of the load, identify which loads belong to the continuous load type, and extract the specific load amount of the continuous load type, that is, the electrical energy required by these loads within a period of time.

[0037] The allocation relationship determination module 60 also includes, using the load synchronization window to traverse the load amount of the continuous load type to determine the synchronization window matching relationship. Using the set load synchronization window, the load amount of the continuous load type is traversed to determine which continuous loads can be satisfied in the current synchronization window, that is, the size of the synchronization window matches the load amount of these loads. It also includes, according to the synchronization window matching relationship, identifying the window load amount, and the window load amount is the load balance of the synchronization window. The window load amount refers to the load amount remaining after matching in the synchronization window, that is, the load balance of the synchronization window. This balance may be caused by the synchronization window being greater than the load amount of some continuous loads, or it may be due to the fact that some continuous loads cannot be satisfied in the current synchronization window and remain. It also includes, based on the window load amount, performing intermittent load traversal distribution using the split window, and determining the matching relationship of the split window. According to the identified window load, the original synchronization window is divided into multiple smaller split windows, and these split windows are used to traverse and distribute the intermittent load. Similar to the continuous load, it is determined which intermittent loads can be satisfied within these split windows, and the matching relationship between each split window and the intermittent load is determined, that is, which intermittent loads can be satisfied within which split windows.

[0038] The specific configuration of the allocation rule configuration module 50 will be described in detail below. The allocation rule configuration module 50 may further include: constructing an optimization objective function of the energy storage system with the operation cost minimized. Constructing the optimization objective function, configuring the energy storage system to minimize the overall operation cost of the energy storage system. It also includes obtaining the balance constraint condition that the charge and discharge power of the energy storage system meets the DC power supply capacity. According to the charge and discharge characteristics of the energy storage system and the power supply capacity of the DC power supply, a power balance equation is established, including factors such as the charge and discharge power of the energy storage system, the power supply power of the DC power supply, and the power demand of the load, to obtain the balance constraint condition to ensure that the charge and discharge power of the energy storage system is balanced with the supply capacity of the DC power supply. It also includes searching for the optimal solution according to the balance constraint condition and the optimization objective function to determine the energy supply timing chain of the energy storage coefficient. Using an optimization method (such as linear programming, integer programming, genetic algorithm, etc.) to search for the optimal solution, find the energy storage coefficient and energy supply timing chain that meet the balance constraint condition and optimize the objective function, that is, determine the charge and discharge state, power output, etc. of the energy storage system in different time periods to form a timing chain of energy supply.

[0039] The allocation rule configuration module 50 also includes extracting the load timing relationship according to the demand time and interval time of the intermittent load, optimizing the allocation with the goal of minimizing the waiting time of the intermittent load, and determining the load supply demand timing chain. The specific demand time of each intermittent load is clarified, that is, the start time and end time of the load requiring power supply, and the interval time of the intermittent load is considered, that is, the idle time between two consecutive demand times. Based on these demand times and interval times, the timing relationship of all intermittent loads is extracted to form a demand sequence on the time axis. The optimization goal is to reduce the waiting time of the intermittent load. The waiting time refers to the time difference between the load sending the demand signal and the actual power supply. In order to achieve this goal, the supply of the load is reasonably arranged to ensure that while satisfying the stable supply of the continuous load, the waiting time of the intermittent load is shortened as much as possible. Based on the extracted load timing relationship, an optimization allocation strategy is formulated. For example, intermittent loads with earlier demand times and shorter interval times are given priority to reduce their waiting time. At the same time, the optimization allocation strategy is continuously adjusted according to actual conditions. For example, when the demand for continuous loads suddenly increases, it may be necessary to temporarily reduce the supply to intermittent loads to ensure the stability of the power system. The load supply demand timing chain is ultimately determined, and detailed information such as the demand time, supply time, and corresponding power supply of each intermittent load is recorded, which helps to better understand the load demand situation, ensure the stable operation of the power system, and optimize operating costs.

[0040] The allocation rule configuration module 50 also includes configuring the weight coefficients of the energy supply timing chain and the load supply demand timing chain, wherein the weight coefficient of the energy supply timing chain is greater than the weight coefficient of the load supply demand timing chain. The weight coefficient is used to indicate the relative importance of different factors or indicators in the overall system, and can help determine which timing chains should be given priority in decision-making. The energy supply timing chain represents the entire process from energy production to supply, including energy generation, transmission, storage and distribution, etc. Since the stability and reliability of energy supply are crucial to the operation of the entire system, its weight coefficient is usually set to a higher value, and a higher weight coefficient means that the energy supply timing chain will be given priority in the optimization and decision-making process to ensure a stable supply of energy; the load supply demand timing chain describes the energy demand of the load at different time points. In some cases, such as when the energy supply is tight or the system stability is threatened, it may be necessary to temporarily sacrifice part of the load demand to ensure the overall operation of the system. Therefore, the weight coefficient of the load supply demand timing chain is usually set to a value lower than that of the energy supply timing chain.

[0041] The allocation rule configuration module 50 also includes, based on the weight coefficient, using the Nash equilibrium algorithm to balance and optimize the energy supply timing chain and the load supply demand timing chain, and determine the supply relationship between the energy storage system and the intermittent load. The Nash equilibrium algorithm is used to balance and optimize the energy supply timing chain and the load supply demand timing chain. Specifically, a Nash equilibrium model is constructed. In this model, the energy storage system is a participant, and its goal is to make the best energy allocation decision based on the current energy supply timing chain and the load supply demand timing chain. The strategy of the energy storage system includes deciding when to charge, discharge, and the amount of discharge to meet load demand while optimizing energy use. The benefit function is the benefit obtained by the participant based on the result of the strategy selection, such as energy supply cost, load satisfaction (related to waiting time), system stability and other dimensions. The Nash equilibrium algorithm is used through an iterative method Find a strategy combination under which no participant can increase their benefits by unilaterally changing their strategy. For example, initialize the strategy of the energy storage system (such as the time and amount of charging and discharging). According to the current strategy combination, calculate the benefits of each participant. Participants adjust their strategies according to the benefits to maximize their benefits. Repeat until the Nash equilibrium is reached, that is, no participant can increase their benefits by unilaterally changing their strategies. After reaching the Nash equilibrium, determine the optimal supply relationship between the energy storage system and the intermittent load, including the charging and discharging status of the energy storage system at different time points and the amount of power supplied to the load.

[0042] The specific configuration of the allocation rule configuration module 50 will be described in detail below. The allocation rule configuration module 50 may further include: the optimization objective function expression is: Among them, C e (t) is the operating cost of the energy storage system at time t, P e (t) is the discharge power of the energy storage system at time t, P c (t) is the charging power of the energy storage system at time t, φ is the charging and discharging efficiency of the energy storage system, and T is the total time period.

[0043] In the above, refer to Figure 1 The DC power intelligent sharing system for substations according to an embodiment of the present invention is described in detail. Figure 2 A DC power intelligent sharing method for a substation according to an embodiment of the present invention is described.

[0044] Intelligent sharing method of DC power supply for substations, such as Figure 2As shown, the method includes: installing sensors at each load end of the substation to obtain monitoring data, including monitoring current and power fluctuations; identifying load characteristics according to the monitoring data to determine the load type, the load type including continuous load and intermittent load, and using the load type to generate a type label to identify the load at each load end; configuring a parallel DC power supply, the parallel DC power supply includes multiple DC power supplies, and obtaining the load processing capacity and remaining load of each DC power supply; establishing a load distribution node according to the load processing capacity and remaining load of each DC power supply, the load distribution node corresponds to the parallel position of the DC power supply, and the load of the load distribution node corresponds to the remaining load; obtaining the load request amount of the load end, and configuring a distribution rule based on the load type of the load request amount; according to the remaining load of the load distribution node, distributing the load request amount based on the distribution rule, and determining the distribution relationship between the load request amount and the load distribution node; and performing shared distribution of the parallel DC power supplies according to the distribution relationship.

[0045] In a possible implementation, the method for intelligent sharing of DC power supply for a substation also includes: extracting a load data set based on the monitoring data; calculating the mean, variance, peak and frequency characteristics of the load data set; extracting the continuous interval characteristics of the load based on the calculation results of the mean, variance, peak and frequency characteristics, and setting the load type based on the continuous interval characteristics.

[0046] In a possible implementation, the DC power intelligent sharing method for substations also includes: extracting core frequency components according to the frequency characteristics; determining the working cycle of the load signal according to the core frequency components; reconstructing time domain information through inverse Fourier transform according to the core frequency components to determine the working time and interval time of the load signal within the working cycle; calculating the continuous time mean, continuous time variance, interval time mean, and interval time variance using mean and variance based on the working time and interval time respectively; identifying the ratio relationship between continuous time and interval time based on the continuous time mean, continuous time variance, interval time mean, and interval time variance, and determining the load type, wherein the continuous load is a continuous time mean that is greater than the interval time mean, and the variance of the continuous working time and the interval time is small.

[0047] In one possible implementation, the method for intelligent sharing of DC power supply for a substation also includes: configuring an allocation priority according to the load type, wherein the continuous load priority is greater than the intermittent load priority; when the remaining load amount does not meet the load request amount, activating the energy storage system for supplying power to the intermittent load; when the remaining load amount meets the continuous load and there is a surplus, dividing the supply of the intermittent load, wherein a part of the division is supplied by the energy storage system, and a part of the DC power supply is shared with the continuous load.

[0048] In a possible implementation, the method for intelligent sharing of DC power supply for substation also includes: setting a load synchronization window according to the remaining load of the load distribution node, and the load synchronization window is used to synchronously meet all loads in the window; identifying the load type according to the load request amount, and extracting the load amount of the continuous load type; using the load synchronization window to traverse the load amount of the continuous load type to determine the synchronization window matching relationship; identifying the window load amount according to the synchronization window matching relationship, and the window load amount is the load balance of the synchronization window; splitting the synchronization window based on the window load amount, using the split window to perform intermittent load traversal distribution, and determining the matching relationship of the split window.

[0049] In a possible implementation, the method for intelligent sharing of DC power supply for substations also includes: constructing an optimization objective function of an energy storage system with minimization of operating costs; obtaining a balance constraint condition of the DC power supply capacity to satisfy the charging and discharging power of the energy storage system; optimizing according to the balance constraint condition and the optimization objective function to determine the energy supply timing chain of the energy storage system; extracting the load timing relationship according to the demand time and interval time of the intermittent load, optimizing the allocation with the goal of minimizing the waiting time of the intermittent load, and determining the load supply demand timing chain; configuring the weight coefficients of the energy supply timing chain and the load supply demand timing chain, wherein the weight coefficient of the energy supply timing chain is greater than the weight coefficient of the load supply demand timing chain; based on the weight coefficients, using the Nash equilibrium algorithm to perform balanced optimization on the energy supply timing chain and the load supply demand timing chain to determine the supply relationship between the energy storage system and the intermittent load.

[0050] In a possible implementation, the DC power intelligent sharing method for a substation further includes: the optimization objective function expression is: Among them, C e (t) is the operating cost of the energy storage system at time t, P e (t) is the discharge power of the energy storage system at time t, P c (t) is the charging power of the energy storage system at time t, φ is the charging and discharging efficiency of the energy storage system, and T is the total time period.

[0051] The DC power intelligent sharing system for substations provided by the embodiment of the present invention can execute the DC power intelligent sharing method for substations provided by any embodiment of the present invention, and has functional modules and beneficial effects corresponding to the execution method.

[0052] Although the present application makes various references to certain modules in the system according to the embodiments of the present application, any number of different modules may be used and run on the user terminal and / or server, and the various units and modules included are only divided according to functional logic, but are not limited to the above division, as long as the corresponding functions can be achieved; in addition, the specific names of the functional units are only for the convenience of distinguishing each other, and are not used to limit the scope of protection of the present invention.

[0053] The above specific implementations do not constitute a limitation on the protection scope of this application. It should be understood by those skilled in the art that various modifications, combinations and substitutions can be made according to design requirements and other factors. Any modifications, equivalent substitutions and improvements made within the spirit and principles of this application should be included in the protection scope of this application.

Claims

1. A DC power intelligent sharing system for a substation, characterized in that: The DC power intelligent sharing system for substations comprises: The monitoring data acquisition module is used to install sensors at each load end of the substation to obtain monitoring data, including monitoring current and power fluctuations; A load type determination module, used to identify load characteristics according to the monitoring data, determine the load type, the load type includes continuous load and intermittent load, and use the load type to generate a type label to identify the load of each load end; A parallel DC power supply configuration module, used to configure a parallel DC power supply, wherein the parallel DC power supply includes a plurality of DC power supplies, and obtain a load processing capacity and a remaining load capacity of each DC power supply; A load distribution node establishment module, used to establish a load distribution node according to the load processing capacity and the remaining load of each DC power supply, wherein the load distribution node corresponds to the parallel position of the DC power supply, and the load of the load distribution node corresponds to the remaining load; An allocation rule configuration module, used to obtain the load request amount of the load end, and configure an allocation rule based on the load type of the load request amount; A distribution relationship determination module, configured to distribute the load request according to the remaining load of the load distribution node based on the distribution rule, and determine the distribution relationship between the load request and the load distribution node; The parallel DC power supply sharing distribution module is used to share and distribute the parallel DC power supplies according to the distribution relationship.

2. The DC power intelligent sharing system for substations according to claim 1, characterized in that: The load type determination module performs the following steps: extracting a load data set according to the monitoring data; Calculate the mean, variance, peak value and frequency characteristics according to the load data set; The continuous interval characteristics of the load are extracted according to the calculation results of the mean, variance, peak value and frequency characteristics, and the load type is set according to the continuous interval characteristics.

3. The DC power intelligent sharing system for substations according to claim 2, characterized in that: The load type determination module performs the following steps: Extracting core frequency components according to the frequency characteristics; determining a duty cycle of a load signal according to the core frequency component; Reconstructing time domain information by inverse Fourier transform according to the core frequency component to determine the working time and interval time of the load signal within one working cycle; Based on the working time and the interval time, respectively, the continuous time mean, the continuous time variance, the interval time mean, and the interval time variance are calculated using the mean and the variance; Based on the continuous time mean, continuous time variance, interval time mean, and interval time variance, the ratio relationship between the continuous time and the interval time is identified to determine the load type, wherein the continuous load is a continuous time mean that is greater than the interval time mean, and the variance of the continuous working time and the interval time is small.

4. The DC power intelligent sharing system for substations according to claim 1, characterized in that: The steps performed by the allocation rule configuration module include: According to the load type, configuring a distribution priority, wherein the continuous load priority is greater than the intermittent load priority; When the remaining load amount does not meet the load request amount, activating the energy storage system for supplying electric energy to the intermittent load; When the remaining load quantity satisfies the continuous load and there is a surplus, the intermittent load is supplied and divided, wherein a part of the supply is supplied by the energy storage system, and a part of the supply is shared with the continuous load.

5. The DC power intelligent sharing system for substations according to claim 4, characterized in that: The steps performed by the allocation relationship determination module include: According to the remaining load of the load distribution node, a load synchronization window is set, wherein the load synchronization window is used to synchronously satisfy all loads within the window; Perform load type identification according to the load request amount, and extract the load amount of the continuous load type; Using the load synchronization window to traverse the load amount of the continuous load type, and determine the synchronization window matching relationship; According to the synchronization window matching relationship, identifying the window load, the window load is the load balance of the synchronization window; Synchronous windows are segmented based on the window load, intermittent load traversal distribution is performed using the segmented windows, and a matching relationship between the segmented windows is determined.

6. The DC power intelligent sharing system for substations according to claim 5, characterized in that: The activation energy storage system is used to supply electric energy to the intermittent load, including: The optimization objective function of the energy storage system is constructed by minimizing the operating cost; Obtaining the charging and discharging power of the energy storage system to meet the balance constraint of the DC power supply capacity; Optimize according to the balance constraint condition and the optimization objective function to determine the energy supply timing chain of the energy storage coefficient; Extract the load timing relationship according to the demand time and interval time of the intermittent load, optimize the allocation with the minimum waiting time of the intermittent load as the goal, and determine the load supply demand timing chain; Configure the weight coefficients of the energy supply timing chain and the load supply demand timing chain, wherein the weight coefficient of the energy supply timing chain is greater than the weight coefficient of the load supply demand timing chain; Based on the weight coefficients, the Nash equilibrium algorithm is used to balance and optimize the energy supply timing chain and the load supply demand timing chain to determine the supply relationship between the energy storage system and the intermittent load.

7. The DC power intelligent sharing system for substations according to claim 6, characterized in that: The optimization objective function expression is: Among them, C e (t) is the operating cost of the energy storage system at time t, P e (t) is the discharge power of the energy storage system at time t, P c (t) is the charging power of the energy storage system at time t, φ is the charging and discharging efficiency of the energy storage system, and T is the total time period.

8. A method for intelligently sharing DC power supply for a substation, characterized in that: The method is applied to the DC power intelligent sharing system for substations according to claim 1, and the method comprises: Install sensors at each load end of the substation to obtain monitoring data, including monitoring current and power fluctuations; Perform load feature identification according to the monitoring data to determine the load type, the load type including continuous load and intermittent load, and generate a type label using the load type to identify the load at each load end; Configure a parallel DC power supply, wherein the parallel DC power supply includes a plurality of DC power supplies, and obtain a load processing capacity and a remaining load capacity of each DC power supply; Establishing a load distribution node according to the load processing capacity and the remaining load of each DC power supply, wherein the load distribution node corresponds to the parallel position of the DC power supply, and the load of the load distribution node corresponds to the remaining load; Obtaining a load request amount of the load end, and configuring a distribution rule based on a load type of the load request amount; According to the remaining load of the load distribution node, the load request is distributed based on the distribution rule to determine the distribution relationship between the load request and the load distribution node; The parallel DC power sources are shared and allocated according to the allocation relationship.

Citation Information

Patent Citations

  • Experimental platform of direct-current micro-grid system for wave energy cluster power generation

    CN108376980A

  • Load decomposition method based on electrical appliance physical characteristics and residential electricity consumption behaviors

    CN111563827A

  • Power distribution method and system

    CN112721707A

  • Configuration method for direct-current power supply system of transformer substation

    CN112994223A

  • Intelligent DC power distribution system

    CN114156861A