Photovoltaic power station inverter active power coordinated optimization control method
By evaluating the communication link status, maximum adjustable capacity and adjustment speed of the photovoltaic power station inverter, a comprehensive adjustment performance function is built, and the inverter is sorted according to priority for power adjustment, the difficulty of adjusting accuracy and speed of the photovoltaic power station inverter is solved. The problem of meeting operating requirements has improved grid stability and inverter life.
Patent Information
- Application Number
- CN202411200233.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-29
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2044-08-29
AI Technical Summary
The adjustment accuracy and speed of existing photovoltaic power station inverters are difficult to meet the operating requirements during power adjustment, resulting in overloading of individual inverters or affecting grid stability, and the regulation plan lacks accuracy.
By evaluating the communication link status of the inverter, the maximum adjustable capacity, the adjustment speed and the adjustment accuracy, a comprehensive adjustment performance function is built, and the inverter is sorted by priority to optimize the power adjustment allocation, ensuring the emergency control and AGC adjustment requirements satisfy.
It effectively avoids the inverter adjustment accuracy or adjustment speed that cannot meet the operating requirements, and improves the stability of the power grid and the life safety of the inverter.
Smart Images

Figure CN119093510A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of active power control of photovoltaic power stations, and in particular to a method for coordinated optimization control of active power of inverters in photovoltaic power stations. Background Art
[0002] In recent years, the domestic photovoltaic power generation industry has developed rapidly and has become one of the world's largest photovoltaic power generation markets, and the production capacity of photovoltaic modules has continued to expand. By the end of 2021, the annual production capacity of photovoltaic modules has exceeded 250GW, accounting for more than 70% of the global total production capacity. Due to the widespread access of photovoltaic power generation units, the impact of photovoltaic grid connection on the voltage and active network loss of the distribution network is increasing, which adds difficulties to the planning and scheduling of the distribution network and ultimately leads to a decrease in the stability of the power grid. In order to protect the overall stable operation of the power grid, it is often necessary to limit or increase the power of photovoltaic power generation sites. In order to reduce the impact of transient processes on the operation of the power grid, there are specific requirements for the adjustment speed, adjustment accuracy, and adjustment capacity when adjusting the power. The current power regulation plan often only calculates the power target value of each area within the site and sends it down to each inverter in the area on average. The regulation plan is rarely accurate to a single inverter. However, different inverters in each area will also have different power generation capabilities due to individual differences. Simply averaging the power target values of each area and then sending them to each inverter may cause individual inverters to overload, thereby affecting the life of the inverter and even affecting the overall safe and stable operation of the power grid. Summary of the invention
[0003] The present invention proposes a method for coordinated optimization control of active power of photovoltaic power station inverters, which evaluates the regulation capabilities of each photovoltaic inverter in scenarios such as emergency control, primary frequency regulation, and AGC, and optimizes power plan allocation on this basis, mainly to solve the problem that the inverter regulation accuracy or regulation speed cannot meet the operating requirements when the photovoltaic inverter is adjusted according to control instructions.
[0004] A photovoltaic power station inverter active power coordinated optimization control method is based on a control system composed of a station control device, an optical fiber ring network, a ring network switch and an inverter. The method is implemented by the following steps:
[0005] Step 1: Use the light attenuation between each inverter i Determine the real-time communication link status. When the optical attenuation exceeds the lower limit d min When the light source power is too high, it may lead to a series of consequences such as high bit error rate and equipment damage; when the light decays i Over the limit d max When the above two situations occur, it is considered that the light attenuation between nodes is too large and the communication quality is reduced; when the above two situations occur, it is considered that the inverter communication is interrupted and the inverter should be moved out of the controllable inverter range.
[0006] Step 2: Predict the maximum adjustable capacity of each inverter. The station is divided into several partitions according to the geographical location of each inverter, and sample inverters are selected from each partition. The sample inverters do not participate in power regulation. The current power P of the sample inverters is sample As the estimated value base value of the maximum power generation of the inverter in this partition, and using the correction coefficient k based on the membership function pi Correct the maximum power generation estimated value base value to obtain the maximum power generation predicted value of each inverter When power needs to be increased, the maximum adjustable capacity of each inverter Where P ci The current power of the inverter. When the power needs to be reduced, the maximum adjustable capacity of each inverter Where P si is the minimum adjustable threshold.
[0007] Step 3: predict the regulation speed performance of each inverter. First, perform a performance test on each inverter to obtain the inverter local regulation response time t pi , single-step adjustment time t set_i , where the inverter local regulation response time t pi It is defined as the time required from the addition of the step quantity to the change of the controlled quantity to 10% of the step quantity in the step experiment. The time required for single-step regulation is the time interval for each change of voltage or current in the MPPT (Maximum Power Point Tracking) algorithm. When power regulation is required, the regulation response time directly adopts the local response time t of the inverter in the performance test. pi The adjustment time should be combined with the adjustment step value δ of each photovoltaic inverter. set_i And the time required for single-step adjustment t set_i calculate The response time t pi And the adjustment time t si Add together to get the time t required for each inverter to adjust i =t pi +t si , thereby evaluating the adjustment speed of each inverter according to the time required for adjustment.
[0008] Step 4: Evaluate the regulation accuracy performance of each inverter based on the historical data of regulation error. i =|P di -P i '| / P Ni Historical data, P di is the target power, Pi ' is the active power of the inverter after entering the regulation dead zone, P Ni is the rated power of the inverter. Construct the regulation error and the current power generation P i 、Ambient temperature T i The relevant pre-calculated table can be used to directly select the corresponding e when power adjustment is required. i Evaluate the regulation accuracy.
[0009] Step 5: Build the maximum adjustable capacity of each inverter Adjustment time t i , adjustment error e i As the regulation performance function of the input parameters, the inverter comprehensive regulation performance Q is obtained. i and send it to control systems at all levels.
[0010] Step six, when power regulation is required, the control system will sort the inverters from high to low according to their comprehensive regulation performance, and use this order as the power regulation priority order to meet the requirements of different scenarios such as emergency control, primary frequency regulation, and AGC (Automatic Generation Control) regulation. When only AGC regulation is required, in order to ensure that there is still adjustable capacity when emergency control and primary frequency regulation are required, a threshold should be set for the regulation performance. For inverters below this threshold, the AGC system will issue target power values for regulation according to the principle of comprehensive regulation performance from high to low.
[0011] The present invention also provides a computer storage medium and an electronic device, wherein a computer program is stored on the computer storage medium, and when the computer program is executed by a processor, the steps of the method are implemented. The electronic device includes a memory and one or more processors, and the memory is used to store one or more programs; when the one or more programs are executed by the one or more processors, the method is implemented.
[0012] Beneficial effects of the present invention: The present invention evaluates the adjustable capacity, adjustment time and adjustment accuracy of the photovoltaic inverter, and sorts the priorities of different inverters in various application scenarios according to the size of the adjustment performance, so as to meet the needs of different scenarios such as emergency control, primary frequency modulation, AGC, etc., and effectively avoids the situation where the adjustment accuracy or adjustment speed of the inverter cannot meet the operation requirements due to the lack of an inverter with adjustment performance that meets the time requirements of emergency control after AGC adjustment. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 Flow chart of the method of the present invention.
[0014] Figure 2This is a diagram of the photovoltaic power station control system architecture in the present invention.
[0015] Figure 3 It is the membership function curve corresponding to the inverter power generation in step 2 of the present invention. DETAILED DESCRIPTION
[0016] The present invention is further described below in conjunction with the accompanying drawings.
[0017] The process of the photovoltaic power station inverter active power coordinated optimization control method of the present invention is as follows: Figure 1 As shown in the figure, the control system architecture of the photovoltaic power station is as follows Figure 2 As shown, it is composed of a station control device, an optical fiber ring network, a ring network switch and an inverter. The method is implemented by the following steps:
[0018] Step 1: Determine the communication link status:
[0019] The present invention uses the optical attenuation between communication devices to evaluate the communication link status. The present invention uses network devices that support SNMP (Simple Network Management Protocol) and configures SNMP agents and SNMP management systems on the control system, thereby identifying and obtaining them through the specific OID (Object Identifier) of SNMP. i Determine the real-time communication link status, count the optical attenuation of each inverter, and evaluate the communication link status of the optical fiber ring network. The optical attenuation data is collected and sent by the terminal or switch. The calculation method of the optical attenuation d between nodes is as follows:
[0020] d=d s -d r
[0021] where d s is the optical attenuation at the transmitting end, d r is the optical attenuation at the receiving end.
[0022] The optical attenuation of optical fiber is usually related to factors such as cable material and cable length, which can be expressed as the following formula:
[0023] d=k d ×
[0024] where k d is the light attenuation coefficient, and l is the cable length.
[0025] Because the optical fiber attenuation coefficient and cable length should be determined when laying, the optical attenuation of the communication link of each inverter is d i The following standards should always be met:
[0026] dmin ≤d i ≤d max
[0027] where d min is the lower limit of strong light attenuation, d max is the upper limit of weak optical attenuation. The range of strong and weak optical attenuation and normal optical attenuation can be calculated based on the attenuation coefficient of the optical fiber and the transmission distance. min ≤d i ≤d max When , it is considered that the node communication is interrupted and the node should be removed from the controllable inverter range.
[0028] Step 2: Maximum power generation prediction:
[0029] Since the maximum power generation of a photovoltaic inverter is mainly related to factors such as light intensity and ambient temperature, photovoltaic inverters in similar geographical locations have similar conditions such as light intensity and ambient temperature. Therefore, the present invention divides the regions according to the geographical locations of each inverter, selects sample inverters in each partition, and the sample inverters do not participate in power regulation. The maximum power generation of the photovoltaic inverters in each partition is predicted with reference to the current power generation of the sample inverters in each partition. Taking into account individual differences such as installation angles, there is still a gap between the power generation of each inverter in the same area and the power generation of the sample inverter. Therefore, it is necessary to use historical data of the same power generation state to correct the predicted maximum power generation of each inverter. The prediction formula is as follows:
[0030]
[0031] in is the predicted value of the maximum power generation of the inverter, k pi is the correction coefficient of each inverter based on the membership function, where the membership is calculated according to the current power of the sample inverter, P sample is the current power generation of the sample inverter.
[0032] The present invention proposes a correction coefficient setting method based on membership function, combining the current power generation of the sample inverter to calculate the corresponding correction coefficient k pi In order to avoid data imbalance and increased complexity caused by too many levels or information loss caused by too few levels, the present invention establishes a power level set based on the inverter, which includes three power levels set in order from low to high, [0,P a ]、[P a ,P b ]、[P b ,P N ], P a , P bare the lower and upper limits corresponding to the intermediate power, P N is the rated power of the sample inverter, and according to the current power generation power P of the sample inverter sample Calculate the membership degree μ of each power level ij , then the final correction coefficient k corresponding to each inverter pi It can be written as follows:
[0033]
[0034] where k pij is the correction coefficient corresponding to the different power levels of each inverter. It is necessary to calculate the power P of each inverter at the same time in the statistical historical data. i With the sample inverter power P sample The ratio between them is calculated, and the average value of the ratio in the corresponding interval is taken as the correction coefficient k of the inverter. pij ,Right now
[0035]
[0036] Where P sample_his_1 ,P sample_his_2 ,…,P sample_his_n is the power sampling data of all the sample inverters in the jth power level in the historical data, n is the number of corresponding sampling points, P i_his_1 ,P i_his_2 ,...,P i_his_n is the sampling data of the power of each inverter at the same time, n is the number of corresponding sampling points, where P sample_his_x =0 or P i_his_x =0 should not be used as sample calculation.
[0037] The membership degree μ of each region ij The Gaussian membership function, that is, the bell-shaped curve, is used for characterization, and the membership of each region is μ ij It can be written as follows:
[0038]
[0039] Where P j is the center point of the corresponding membership function, σ ij is the standard deviation of the membership function. When it is at the center point, the corresponding membership function is the largest, that is, P sample =P j When ij =1, it is recommended to select P1=0, P2=0.5P N , P3=P N , where P N is the rated power of the sample inverter, σ ijSpecifically affects the width of the membership function. j , σ ij The selection should be made based on the specific application of the actual project.
[0040] For example, choose σ i1 =σ i2 =σ i3 =0.1P N , when P i1 =0,P i2 =0.5P N , P i3 =P N When , the final membership function is as follows Figure 2 As shown, when the sample inverter generates power P sample =0.5P N When , the corresponding three power levels are i1 =3.72×10 -6 , μ i2 =1,μ i3 =3.72×10 -6 , then the correction coefficient of the inverter at this moment can be considered as k pi ≈k pi2 .
[0041] When power needs to be increased, the maximum adjustable capacity of the inverter can be expressed as the maximum power generation With the current power P ci The difference is When power reduction is required, the maximum adjustable capacity of the inverter is the current power generation power P ci With the minimum adjustable threshold P si The difference is
[0042] Step 3: Evaluation of photovoltaic inverter regulation speed performance:
[0043] Perform performance tests on each inverter to obtain the local regulation response time t pi , single-step adjustment time t set_i The test was conducted in which the inverter locally adjusted the response time t pi It is defined as the time required from the addition of the step amount to the time the controlled amount changes to 10% of the step amount in the step test, and the time required for single-step adjustment t set_i It is the interval between each change of voltage or current in the MPPT control algorithm.
[0044] When the power is increased, in order to prevent blind and rapid power setting during the climbing process, which is likely to cause the inverter DC voltage to collapse and trip, the current photovoltaic inverter mainly adopts the MPPT control method to avoid this situation. The operating point of the voltage and current is adjusted in real time during the power generation process to achieve the maximum power generation. Therefore, the adjustment time is mainly affected by the adjustment step value of the photovoltaic inverter. Therefore, the present invention uses the adjustment step value to estimate the adjustment time. When the power is increased, the adjustment time t si The calculation formula is as follows:
[0045]
[0046] where δ set_i is the constant value of the adjustment step length, t set_i It is the time required for single-step regulation of the PV inverter.
[0047] The time required for the final adjustment is calculated as follows:
[0048] t i =t pi +t si
[0049] Step 4: Adjustment accuracy performance evaluation:
[0050] The present invention evaluates the regulation accuracy of the inverter through the historical data of the regulation error. Emergency control, primary frequency regulation, and AGC control have different requirements for regulation performance. The regulation error is defined as the difference between the power generation and the target value after each adjustment of the photovoltaic inverter. The calculation formula is as follows:
[0051]
[0052] Where P di is the target value issued, P i ' is the active power of the inverter after entering the regulation dead zone, P Ni is the rated power of the inverter.
[0053] Considering that the adjustment error is mainly affected by the inverter properties and the current power generation and ambient temperature, the present invention establishes a matrix of the adjustment error of each inverter with the power generation and ambient temperature: the information such as power generation and temperature is divided into multiple intervals at equal intervals, and the adjustment error in each interval is counted to calculate the average value, where the power generation is within (P m ,P n ) range, the ambient temperature is (T x ,T y ) The average value of the adjustment error in the interval It can be expressed as
[0054]
[0055] Where: e i1 ,e i2 ,...,e iw is the adjustment error of each inverter in the corresponding interval, and w is the number of adjustments in the corresponding interval. When the performance function needs to calculate the adjustment error, the table lookup method is used to find the average adjustment error in the corresponding interval. As the calculation error e i , thus evaluating the regulation accuracy performance. When power regulation is required, it should be based on the ambient temperature T i And power generation P i Use table lookup to find the corresponding
[0056] Step 5: Construction of comprehensive adjustment performance function:
[0057] The present invention proposes a method for constructing a comprehensive regulation performance function, which normalizes the regulation speed, adjustable capacity, regulation accuracy and other indicators, and then a comprehensive regulation performance function Q can be used. i Represents the required performance indicators, then it can be written as follows
[0058]
[0059] Where: t i is the adjustment time calculated in step 3, k1, k2, k3∈(0,1) are adjustable weight factors, and all inverters should use the same k1, k2, k3 when calculating the performance function. is the maximum adjustable power of the photovoltaic inverter calculated in step 2, P Ni is the rated power of the inverter, e i is the adjustment error obtained from historical data in step 4. In the comprehensive adjustment performance function, 1 / (1+exp(-k1t i )) item indicates the speed adjustment performance. The term represents the maximum adjustable capacity performance, The term represents the regulation accuracy performance. When the inverter performance function Q i The larger the value, the better the regulation performance of the inverter. Different k1, k2, and k3 can be selected to meet different requirements. When the requirements for individual performance are higher, the corresponding weight factor k should be i Higher, assuming that when the adjustment speed requirement is higher, k1>k2, k1>k3 should be made.
[0060] Step 6: Inverter selection:
[0061] When power regulation is required, the inverter that meets the performance requirements of the regulation scenario should be selected first, and the adjustment should be carried out in order from high to low according to the comprehensive regulation performance until the adjustable power of the selected inverter combination meets the power requirements of this regulation. When only AGC regulation is required, in order to ensure that there is still adjustable capacity when emergency control and primary frequency regulation are required, a threshold should be set for the comprehensive regulation performance. The setting of the threshold should ensure that when the power is reduced, the remaining adjustable capacity of the entire station is not less than the rated power P of the entire station. N_set α% of the total power. When the power is increased, the remaining adjustable capacity of the entire station shall not be less than the rated power P of the entire station. N_set β%, α and β can be adjusted by fixed value, it is recommended to be no less than 10% and 6%. For inverters below this threshold, the AGC system will issue target power values for adjustment according to the principle of comprehensive adjustment performance from high to low.
[0062] The technical means disclosed in the scheme of the present invention are not limited to the technical means disclosed in the above-mentioned implementation mode, but also include technical schemes composed of any combination of the above-mentioned technical features. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present invention, and these improvements and modifications are also regarded as the protection scope of the present invention.
Claims
1. A photovoltaic power station inverter active power coordinated optimization control method, characterized in that: Based on the control system composed of station control device, optical fiber ring network, ring network switch and inverter, the following steps are specifically included: Step 1: Use the light attenuation between each inverter i Determine the real-time communication link status. When the optical attenuation exceeds the lower limit d min When the light source power is too high, it may lead to a series of consequences such as high bit error rate and equipment damage; when the light decays i Over the limit d max When the above two situations occur, it is considered that the light attenuation between nodes is too large and the communication quality is reduced; when the above two situations occur, it is considered that the inverter communication is interrupted and the inverter should be moved out of the controllable inverter range; Step 2: divide the inverter into several zones according to the geographical location of each inverter in the station, and select sample inverters in each zone. The sample inverters do not participate in power regulation. sample As the estimated value base value of the maximum power generation of the inverter in this partition, and using the correction coefficient k based on the membership function pi Correct the maximum power generation estimated value base value to obtain the maximum power generation predicted value of each inverter When power needs to be increased, the maximum adjustable capacity of each inverter Where P ci The current power of the inverter. When the power needs to be reduced, the maximum adjustable capacity of each inverter Where P si is the minimum adjustable threshold; Step 3: Perform performance tests on each inverter to obtain the inverter local regulation response time t pi , single-step adjustment time t set_i , where the inverter local regulation response time t pi It is defined as the time required from the addition of the step quantity to the change of the controlled quantity to 10% of the step quantity in the step experiment. The time required for single-step regulation is the time interval for each change of voltage or current in the MPPT algorithm. When power regulation is required, the regulation response time directly adopts the local response time t of the inverter in the performance test. pi The adjustment time should be combined with the adjustment step value δ of each photovoltaic inverter. set_i And the time required for single-step adjustment t set_i calculate The response time t pi And the adjustment time t si Add together to get the time t required for each inverter to adjust i =t pi +t si , thereby evaluating the adjustment speed of each inverter according to the time required for adjustment; Step 4: Count the adjustment errors e of each inverter during the power adjustment process i The historical data of the inverter regulation error e is constructed i With power generation P i 、Ambient temperature T i The relevant pre-calculated table is used to directly select the corresponding adjustment error e when power adjustment is required. i As a performance indicator for evaluating regulation accuracy; Step 5: Build the maximum adjustable capacity of each inverter Adjustment time t i , adjustment error e i As the regulation performance function of the input parameters, the inverter comprehensive regulation performance Q is obtained. i ; Step 6: Based on the comprehensive regulation performance Q of each inverter i Sort from high to low, and use this order as the power adjustment priority order to meet the needs of different scenarios such as emergency control, primary frequency regulation, and AGC regulation.
2. The photovoltaic power station inverter active power coordinated optimization control method according to claim 1, characterized in that: In step 1, all the devices in the system use network devices that support SNMP, and SNMP agent and SNMP management system are configured on the control system, so as to realize the light attenuation monitoring of each inverter through the specific OID of SNMP; i Determine the real-time communication link status, count the optical attenuation of each inverter, and evaluate the communication link status of the optical fiber ring network. i The following criteria should always be met under default communication link conditions: d min ≤d i ≤d max where d min is the lower limit of strong light attenuation, d max It is the upper limit of weak light attenuation.
3. The photovoltaic power station inverter active power coordinated optimization control method according to claim 1, characterized in that: In step 2, the maximum power generation prediction value of each inverter is The calculation formula is as follows: k pi is the correction coefficient of each inverter based on the membership function, where the membership is calculated according to the current power of the sample inverter; a power level set based on the sample inverter is established, which contains low power levels [0,P a ], medium power level [P a ,P b ] and high power levels [P b ,P N ]Three power levels, P a and P b are the lower and upper limits corresponding to the medium power level, P N is the rated power of the sample inverter, and according to the current power generation power P of the sample inverter sample Calculate the membership degree μ of each inverter at each power level ij , combined with the correction coefficient k corresponding to each power level pij Calculate the correction coefficient k of each inverter based on the membership function pi : The correction coefficient k corresponding to each inverter in each power level is pij The power generation power P of each inverter in the power-unrestricted state in the historical data is used i_his At the same time, the sample inverter power generation P samplej_his The average value of the ratio is calculated as follows: Where P sample_his_1 ,P sample_his_2 ,…,P sample_his_n is the power sampling data of all sample inverters corresponding to the jth power level in the historical data, and n is the number of corresponding sampling points; P i_his_1 ,P i_his_2 ,…,P i_his_n is the sampling data of the power of each inverter at the same time, n is the number of corresponding sampling points, where P sample_his_x =0 or P i_his_x = 0 when historical data should not be used as sample calculation; The membership degree μ of each inverter at each power level ij The Gaussian membership function, that is, the bell curve, is used for characterization, and its calculation method is as follows: Where P j is the center point of the membership function, σ ij is the standard deviation of the membership function, P j ,σ ij All are determined based on historical data from actual engineering applications.
4. The photovoltaic power station inverter active power coordinated optimization control method according to claim 1, characterized in that: In step 4, the adjustment accuracy needs to be evaluated through the historical data of the adjustment error. The definition of the adjustment error is as follows: Where: P di is the target value issued, P i 'To press P di The active power of the inverter after adjusting to the target value, P Ni is the inverter rated power; construct the regulation error e i With the current power generation P i 、Ambient temperature T i The relevant pre-calculated table divides the power generation and ambient temperature into multiple intervals at equal intervals. m ,P n ) range, the ambient temperature is (T x ,T y ) The average value of the adjustment error adjusted within the interval Expressed as Where: e i1 ,e i2 ,...,e iw is the adjustment error of each inverter in the corresponding interval, and w is the number of adjustments in the corresponding interval; when power adjustment is required, the corresponding value is directly selected by table lookup method. As the adjustment error e i , so as to evaluate the regulation accuracy of each inverter.
5. The photovoltaic power station inverter active power coordinated optimization control method according to claim 1, characterized in that: In step 5, it is necessary to construct a comprehensive regulation performance function Q for multiple scenarios of emergency control, primary frequency regulation, and AGC of the stability control system. i , taking the regulation speed, adjustable capacity and regulation accuracy as the comprehensive regulation performance function Q i The evaluation criteria are: i The final expression is written as: Where: t i is the time required for regulation calculated in step 3, k1, k2, k3∈(0,1) are adjustable weight factors, and all inverters should use the same k1, k2, k3 when calculating the performance function. is the maximum adjustable power of the photovoltaic inverter calculated in step 2, P Ni is the inverter rated power, e i is the adjustment error obtained from historical data in step 4.
6. The photovoltaic power station inverter active power coordinated optimization control method according to claim 1, characterized in that: In step 6, all inverter priorities should be sorted from high to low according to the comprehensive adjustment performance until the adjustable power of the selected inverter combination meets the power demand required for this adjustment; When only AGC adjustment is required, in order to ensure that there is still adjustable capacity during transient and dynamic adjustment, the inverter performance function threshold should be set. The setting of the threshold should ensure that when the power is reduced, the remaining adjustable capacity of the entire station is not less than the rated power P of the entire station. N_set α% of the total power. When the power is increased, the remaining adjustable capacity of the entire station shall not be less than the rated power P of the entire station. N_set β%, α and β can be adjusted by fixed values. When the reserved capacity is not enough to meet the AGC regulation capacity demand, the reserved inverter part should be opened for regulation.
7. A computer storage medium, characterized in that: A computer program is stored thereon, and when the computer program is executed by a processor, the steps of the method according to any one of claims 1 to 6 are implemented.
8. An electronic device, characterized in that: It comprises a memory and one or more processors, wherein the memory is used to store one or more programs; when the one or more programs are executed by the one or more processors, the method according to any one of claims 1 to 6 is implemented.
Citation Information
Patent Citations
Adjusting performance judgment method of photovoltaic inverter adjusting performance judgment device
CN114915021A
Power regulation and control method and system of photovoltaic power station, electronic equipment and storage medium
CN116231632A
Cited By
Photovoltaic inverter service life prediction method
CN120911315A