Nuclear power overhaul work order combination query management and control system and method

By providing a work order combination query management and control system during the overhaul of the nuclear power plant, the problem of work order statistics relying on manual search is solved, and the rapid, accurate and real-time statistics of work order execution status is achieved, and work efficiency is improved.

CN119226349APending Publication Date: 2024-12-31CNNC NUCLEAR POWER OPERATION MANAGEMENT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411173588.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-26
Publication Date
2024-12-31

AI Technical Summary

Technical Problem

During the overhaul of nuclear power plant, the implementation statistics of work orders in the existing technology rely on manual search, which leads to laborious time, easy human error, unreal-time statistical results, inefficient personnel, and repeated statistics on the completion of work orders for different personnel to obtain work orders. Work.

Method used

Provide a combination query management system and method for nuclear power overhaul work orders, including data acquisition module, query condition setting module and data storage module. By capturing data from EAM work order management system and E-soms isolation system, set and store query Conditions to realize combined query and real-time display of work order tasks.

Benefits of technology

The system facilitates statistics on the execution status of overhaul work orders, reduces the risk of errors due to personal skills, improves the accuracy and real-timeness of statistical results, reduces duplicate work, and improves work efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119226349A_ABST
    Figure CN119226349A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of nuclear power overhaul, and provides a nuclear power overhaul work order combination query management and control system and method, and the system comprises a data obtaining module which is used for obtaining the total work order task number of a certain overhaul and the basic elements of each work order; the query condition setting module is used for presetting or freely combining various query conditions; the data storage module is used for storing combination conditions of free query; the method comprises the steps of setting a query condition, storing and quickly calling the query condition, reading a query result, and pushing the query result. According to the method, the execution condition of the overhaul work order can be conveniently counted, the time is saved, the personnel error risk caused by personal skills is reduced, the accuracy of a statistical result is improved, real-time display is realized, repeated work is reduced, and the working efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of nuclear power overhaul, and in particular to a nuclear power overhaul work order combination query management and control system and method. Background Art

[0002] Nuclear power plant overhaul is carried out through work orders, and the number of work orders for each overhaul is very large, often 6,000 to 7,000 work orders or even more. During the overhaul, the number of work orders issued every day ranges from hundreds to thousands. The statistics of the daily start and completion of so many work orders are very important for the implementation of the overhaul.

[0003] At present, in overhaul, the implementation statistics of daily work orders are realized by the overhaul planning engineer through manual search. For example, to find the work orders that were scheduled to start yesterday: the overhaul planning engineer enters yesterday's date in the EAM work order management system, enters 48 (in progress) as the work order task status, and clicks Search to get the result.

[0004] However, there are many problems in this management and control process. First, there are many points to search every day, which is time-consuming and laborious. Second, it is entirely dependent on the personal skills of the overhaul planning engineer, which is prone to the risk of human error. Third, different statistical time points will cause deviations in the statistical results, and the real-time management and display of work order tasks are poor. Fourth, different personnel want to understand the start and completion statistics of work order tasks, which leads to duplication of work and low personnel efficiency. Summary of the invention

[0005] The purpose of the present invention is to overcome the defects of the prior art and provide a nuclear power overhaul work order combination query management and control system and method, which is convenient for statistics on the execution status of overhaul work orders and saves time, reduces the risk of human errors due to personal skills, improves the accuracy of statistical results and realizes real-time display, reduces duplication of work, and improves work efficiency.

[0006] In order to achieve the above object, the present invention provides the following technical solutions:

[0007] On the one hand, the present invention provides a nuclear power overhaul work order combination query management and control system, comprising:

[0008] The data acquisition module is used to obtain the total number of work order tasks and the basic elements of each work order for a certain overhaul;

[0009] Query condition setting module, used to preset or freely combine various query conditions;

[0010] The data storage module is used to store the combination conditions of free queries.

[0011] In some embodiments, the basic elements include work order task number, work order task status, work order task name, work order planned start time, work order planned completion time, work order actual start time, work order actual completion time, scheduling group, specialty, overhaul number, responsible department, responsible team, name and phone number of the person in charge of the work, isolation name, and isolation code.

[0012] In some embodiments, the query condition setting module classifies and displays the quantity of all work orders during the overhaul implementation period according to a single query condition.

[0013] In some embodiments, the data storage module sends the query results to the email address of the sender, so as to realize the quick retrieval of personalized combined query conditions and the quick sending of query results.

[0014] On the other hand, the present invention provides a nuclear power overhaul work order combination query management and control method, comprising:

[0015] Step 1: Set the query conditions;

[0016] Step 2: Store and quickly call query conditions;

[0017] Step 3: Read the query results and push the query results.

[0018] In some embodiments, step 1 specifically includes:

[0019] Step 1.1: Preset commonly used combination queries;

[0020] Step 1.2: Set the free query combination conditions.

[0021] In some embodiments, in step 1.1, commonly used combination queries include today's planned start work orders, today's planned completion work orders, yesterday's planned completion work orders, yesterday's planned start work orders, tomorrow's planned start work orders, tomorrow's planned completion work orders, yesterday's unplanned start work orders, yesterday's unplanned completion work orders, today's unstarted work orders, and today's uncompleted work orders.

[0022] In some embodiments, in step 1.2, the free query combination conditions include the combination of the work order planned start time, the work order planned completion time, the work order actual start time, the work order actual completion time, the scheduling group, the specialty, the overhaul number, the responsible department, the responsible team, the name and phone number of the work supervisor, the isolation name, and the isolation code.

[0023] In some embodiments, step 2 specifically includes:

[0024] Step 2.1: Store frequently used free combination queries;

[0025] Step 2.2: Call the autonomous named query.

[0026] In some embodiments, step 3 specifically includes:

[0027] Step 3.1: Download the query results;

[0028] Step 3.2: Push query results.

[0029] Compared with the prior art, the overhaul work order combination query system and method provided by the present invention has the following beneficial effects:

[0030] The present invention facilitates statistics on the execution status of overhaul work orders and saves time, reduces the risk of human error due to personal skills, improves the accuracy of statistical results and realizes real-time display, reduces duplication of work, and improves work efficiency.

[0031] Furthermore, the present invention captures the final status of the EAM work order management system and the E-soms isolation system, and screens them through logical conditions to achieve a combined query of work order tasks. It is not limited by the queryer's skill conditions, and is convenient, accurate, fast, and real-time display and push. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] In order to more clearly illustrate the technical solution of the present invention, the following briefly introduces the drawings required for the technical description.

[0033] Figure 1 A schematic diagram of the structure of the nuclear power overhaul work order combination query control system provided by the present invention;

[0034] Figure 2 A flow chart of the combined query and control method for nuclear power overhaul work orders provided by the present invention. DETAILED DESCRIPTION

[0035] The following is further explained in detail through specific implementation methods.

[0036] like Figure 1 As shown, the present invention provides a nuclear power overhaul work order combination query management and control system, including a data acquisition module, a query condition setting module, and a data storage module.

[0037] The data acquisition module is used to capture the total number of work order tasks and basic elements of each work order of a certain overhaul from the EAM system through the overhaul code. These elements include work order task number, work order task status, work order task name, work order planned start time, work order planned completion time, work order actual start time, work order actual completion time, scheduling group, specialty, overhaul number, responsible department, responsible team, name and phone number of the person in charge of the work, isolation name, isolation code, etc.

[0038] As an implementable method, take 123 overhaul as an example. Select the 123 overhaul code, and the data acquisition module will grab all the work order tasks with the 123 overhaul mark, form a number and display all the work orders with the 123 overhaul mark.

[0039] The query condition setting module is used to preset or freely combine various query conditions. These query conditions are based on the data captured by the data acquisition module and are combined according to the query requirements.

[0040] The query condition setting module first classifies and displays the quantity of all work orders during the 123 overhaul implementation period according to a single query condition.

[0041] Example 1: Today's planned start date: The query condition setting module will filter the work orders of the EAM work order management system and the E-soms isolation system whose start date is today and whose operation permission mark is Y, to form data and quantity.

[0042] Example 2: Today we plan to start work on the mechanical engineering specialty: the query condition setting module will filter out the work orders found in Example 1 and those with the attribute MM (mechanical engineering specialty) to form data and quantity, etc.

[0043] The data storage module is used to store the combination conditions of free queries and the email information of the sender of query results, so as to realize the quick retrieval of personalized combination query conditions and quick sending of query results.

[0044] In addition, if Figure 2 As shown, the present invention also provides a nuclear power overhaul work order combination query management and control method, comprising the following steps:

[0045] Step 1: Set the query conditions.

[0046] Step 1.1: Preset commonly used combination queries.

[0047] According to the actual needs of overhaul work, the commonly used combination query requirements and configurations are as follows:

[0048] (1) Today's planned work order

[0049] The query condition is: planned start date = today.

[0050] (2) Today’s planned completed work orders

[0051] The query condition is: planned completion date = today.

[0052] (3) Yesterday’s planned completed work orders

[0053] The query condition is: planned completion date = yesterday.

[0054] (4) Yesterday’s planned work order

[0055] The query condition is: planned start date = yesterday.

[0056] (5) Tomorrow's planned work order

[0057] The query condition is: planned start date = tomorrow.

[0058] (6) Tomorrow's planned completion work order

[0059] The query condition is: planned completion date = tomorrow.

[0060] (7) Work orders were not started as planned yesterday

[0061] The query conditions are: planned start date = yesterday's work order task status = not started.

[0062] (8) Work orders that were not completed as planned yesterday

[0063] The query conditions are: planned completion date = yesterday's work order task status = unfinished.

[0064] (9) No work orders have been started today

[0065] The query conditions are: planned start date = today's work order task status = not started.

[0066] (10) Today’s unfinished work orders

[0067] The query conditions are: planned completion date = today's work order task status = unfinished.

[0068] It should be noted that all the above query conditions must include the "overhaul number = current overhaul number" condition.

[0069] Step 1.2: Set the free query combination conditions.

[0070] The conditions that can be used for free query combinations include: combined work order planned start time, work order planned completion time, work order actual start time, work order actual completion time, scheduling group, specialty, overhaul number, responsible department, responsible team, work supervisor name and phone number, isolation name, isolation code and other conditions to achieve various target work order queries.

[0071] Step 2: Query condition storage and quick call.

[0072] Step 2.1: Store frequently used free combination queries.

[0073] According to the preferences of the query personnel, the self-set combined queries are stored. For example, a mechanical professional can configure the combination condition of "Today" as the planned start date and "Machinery" as the professional to store "Today's planned start work order for machinery".

[0074] Step 2.2: Call the autonomous named query.

[0075] The query personnel select the combination query conditions stored independently and execute the query or slightly modify the query. For example, after executing the query of "Today's planned start date of machinery work order", the "planned start date = today" is adjusted to "planned completion date = today", and the query of today's planned completion of machinery professionals can be completed.

[0076] Step 3: Read and push query results.

[0077] Step 3.1: Download query results.

[0078] When the query personnel complete the target work order query, they can export the list from the system to a data file for use.

[0079] Step 3.2: Push query results.

[0080] When the query personnel complete the target work order query, they can configure the email addresses of the personnel who need to be pushed in the system and push the list directly to the relevant personnel.

[0081] The email addresses of the people who need to be pushed can be configured according to different groups. For example, you can set up a "planning staff group", "management staff group", etc., to achieve batch selection and quick push of personnel.

[0082] The above is only a specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that can be easily thought of by a person skilled in the art within the technical scope disclosed by the present invention should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.

Claims

1. A nuclear power overhaul work order combination query management and control system, characterized in that: include: The data acquisition module is used to obtain the total number of work order tasks and the basic elements of each work order for a certain overhaul; Query condition setting module, used to preset or freely combine various query conditions; The data storage module is used to store the combination conditions of free queries.

2. The nuclear power overhaul work order combined query management and control system according to claim 1 is characterized in that: The basic elements include work order task number, work order task status, work order task name, work order planned start time, work order planned completion time, work order actual start time, work order actual completion time, scheduling group, specialty, overhaul number, responsible department, responsible team, name and phone number of the person in charge of the work, isolation name, and isolation code.

3. The nuclear power overhaul work order combination query management and control system according to claim 1 is characterized in that: The query condition setting module classifies and displays the quantity of all work orders during the overhaul implementation period according to a single query condition.

4. The nuclear power overhaul work order combination query management and control system according to claim 1 is characterized in that: The data storage module sends the query results to the email address of the sender, enabling quick retrieval of personalized combined query conditions and quick delivery of query results.

5. A nuclear power overhaul work order combination query control method, characterized in that: include: Step 1: Set the query conditions; Step 2: Store and quickly call query conditions; Step 3: Read the query results and push the query results.

6. The nuclear power overhaul work order combination query control method according to claim 5 is characterized in that: Step 1 specifically includes: Step 1.1: Preset commonly used combination queries; Step 1.2: Set the free query combination conditions.

7. The nuclear power overhaul work order combination query control method according to claim 6 is characterized in that: In step 1.1, commonly used combination queries include today's planned start work orders, today's planned completion work orders, yesterday's planned completion work orders, yesterday's planned start work orders, tomorrow's planned start work orders, tomorrow's planned completion work orders, yesterday's unplanned start work orders, yesterday's unplanned completion work orders, today's unstarted work orders, and today's uncompleted work orders.

8. The nuclear power overhaul work order combination query control method according to claim 6 is characterized in that: In step 1.2, the free query combination conditions include the combination of the work order planned start time, the work order planned completion time, the work order actual start time, the work order actual completion time, the scheduling group, the specialty, the overhaul number, the responsible department, the responsible team, the name and telephone number of the person in charge of the work, the isolation name, and the isolation code.

9. The nuclear power overhaul work order combination query control method according to claim 5 is characterized in that: Step 2 specifically includes: Step 2.1: Store frequently used free combination queries; Step 2.2: Call the autonomous named query.

10. The nuclear power overhaul work order combination query control method according to claim 5, characterized in that: Step 3 specifically includes: Step 3.1: Download the query results; Step 3.2: Push query results.