Modularized-design-based construction method for secondary structure concrete member of shaped brick mold
Through modular design and BIM software, the design of fixed brick molds is simplified, the construction process of secondary structure concrete components is solved, and the problems of high construction difficulty and poor molding quality in public buildings are achieved, and efficient and high-quality construction results are achieved.
Patent Information
- Application Number
- CN202411423406.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-12
- Publication Date
- 2025-01-07
AI Technical Summary
In public building construction, the construction of secondary structure concrete components is difficult, has a long cycle, has poor appearance quality, and requires a large number of formwork and materials.
Using the construction method of secondary structure concrete components of fixed brick molds based on modular design, the design and simulation layout are carried out through BIM software, and the construction process of fixed brick molds is designed and processed, and the construction process is simplified, and the construction process is replaced by traditional wooden formwork construction, so as to realize the factory processing of molds and Assemble and build.
It improves construction efficiency and molding quality, reduces material use, and achieves efficient and high-quality secondary structure concrete components construction, which is suitable for the construction needs of large public buildings.
Smart Images

Figure CN119266546A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a construction method of a secondary structure concrete component of a fixed brick mold based on modular design. Background Art
[0002] With the rapid development of the national economy and cities, in order to meet the needs of the general public for improved work and life quality, various large venues, hospitals and other public buildings have emerged in large numbers. The mechanical and electrical installation, intelligentization, medical special equipment and pipelines of such public buildings are intricate. In order to realize the use function of the building, higher floor height requirements are required than ordinary building engineering spaces. The corresponding secondary structure masonry and secondary structure concrete components have high construction height and large volume. The traditional construction method is used, which is difficult to construct and has a long construction period. The appearance quality of the concrete components is poor, and a large number of secondary turnover materials such as formwork, wooden squares, and tension screws are required. Summary of the invention
[0003] The present invention is aimed at the above-mentioned problems and specifically designs a construction method for secondary structure concrete components using standardized brick molds based on modular design, so that it can be combined with BIM software to simulate the layout and assembly of secondary structure concrete components, extract the parameters of the unit modules that constitute the secondary structure concrete components, and design and process standardized brick molds.
[0004] To achieve the above object, the present invention provides a method for constructing a secondary structure concrete member using a fixed brick mold based on a modular design, comprising the following steps: Step 1: Based on the general description of the building and structural construction design, structural drawings, architectural drawings, and relevant requirements of the design and construction specifications, use CAD and BIM software to conduct in-depth design and drawing of the secondary structural concrete components of all floors of the building; Step 2: Before the formal construction of the masonry secondary structure, check the position relationship between the main concrete structure and the secondary structure, and review the detailed design drawings based on the actual situation. Adjust the positions where the relevant parameters between the main structure and the secondary structure are significantly different, and ask the design unit to confirm. After verification and confirmation, the number of unit modules of secondary structural concrete components on each floor shall be counted and summarized; Step 3: According to the secondary structure detailed design drawings confirmed by the design unit, select representative walls, and use BIM modeling to simulate the layout and assembly of masonry and fixed brick molds; After the overall layout drawing is completed, the secondary structure concrete components are decomposed into unit modules; Step 4: According to the decomposed unit module parameters, combined with the actual situation on site and the construction progress requirements, adopt BIM modeling to carry out corresponding mold design and processing; Step 5: After the first fixed brick mold is processed, the fixed brick mold is tested and the finished product accuracy and product qualification rate of the fixed brick mold are tested; Step 6. Before the formal construction on site, the finalized brick molds of each wall masonry and secondary structure concrete components are assembled and arranged as a whole, and construction can be carried out after verification and confirmation.
[0005] Furthermore, in the step 2, the axis, elevation, size, and position deviation of the main concrete structure of the building are first reviewed, and the positional relationship between the completed main structure and the secondary structure masonry, ring beam, and structural column is checked.
[0006] Preferably, in step three, the representative wall is a wall having only a ring beam but no structural column, or a wall having both a ring beam and a structural column, or a T-shaped wall, an L-shaped wall, or a cross wall.
[0007] Preferably, in step 4, the precision error of the shaping brick mold does not exceed 2 mm.
[0008] Preferably, in step five, the precision error of the finished brick mold does not exceed 3 mm.
[0009] Furthermore, in the step six, before formal masonry, first clean the base of the masonry wall, check the axis, elevation, position, and size of the wall, erect the skin number rod, and according to the secondary structure construction drawings after in-depth design, refer to the assembly methods of various types of walls and standardized brick molds in the typical wall standardized brick mold layout, and carry out the overall combination layout of wall masonry and standardized brick molds to ensure that the masonry method, mortar joints, and masonry lap length meet the requirements of design and construction specifications before masonry.
[0010] Furthermore, in step six, after the masonry mortar strength reaches the strength required by the design and construction specifications, the secondary structural concrete components are poured. When pouring concrete, each pouring height does not exceed 500mm, and steel bars are used to vibrate and compact it.
[0011] Furthermore, in step six, when building the wall, it is difficult to clean up the garbage at the structural column, and protective measures are taken at the holes of the shaped bricks to prevent mortar debris from falling into the structural column.
[0012] Furthermore, in step four, the shaped brick mold includes a steel plate template, a steel rectangular tube keel, a base, a clamp and a limit plate, the steel plate template is fixedly connected to the base, the steel rectangular tube keel is fixedly connected to the steel plate template, the steel plate template is equipped with the clamp, and the limit plate is fixedly installed between the steel plate template and the base.
[0013] Furthermore, in step five, before the shaped brick mold is cast and manufactured, cold-drawn steel bars are arranged in the mold.
[0014] In summary, the present invention has the following advantages and beneficial technical effects: 1. The present invention conducts a comprehensive and systematic in-depth design of the unit modules of the secondary structure concrete components, adopts prefabricated unit module fixed brick molds for assembly and construction, replaces the traditional secondary structure concrete component wooden formwork reinforcement construction, and simplifies the on-site construction process.
[0015] 2. The dimensions of the brick molds for various secondary structural concrete components in the present invention are standardized, modularized, unified and universalized to facilitate subsequent mold processing and reduce the number of molds. The present invention is suitable for large-scale factory production of brick molds and can meet the progress of on-site production and construction. A systematic solution is provided for different types of secondary structural masonry and walls composed of secondary structural concrete components, such as T-shaped walls, L-shaped walls and cross walls. High-quality and efficient construction of masonry secondary structures is achieved in a manner of fewer specifications and more combinations.
[0016] 3. The present invention uses a fixed brick mold to replace the traditional wooden formwork construction, which is free of formwork support and formwork removal, and has high on-site construction efficiency. The fixed brick mold is processed in a mold factory, and the visual molding quality is good.
[0017] 4. The present invention is easy to operate, simple and easy to learn. The construction process and construction operation points are combined with BIM models and construction animations for technical explanation, so that the construction points can be quickly mastered and it is easy to promote on a large scale. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] The above and / or additional aspects and advantages of the present invention will become apparent and easily understood from the description of the embodiments in conjunction with the following drawings, in which: Figure 1 It is a schematic diagram of a BIM model of a component module in the present invention; Figure 2 It is a schematic diagram of a BIM model of a wall filled with a ring beam but no structural columns in the present invention; Figure 3 It is a schematic diagram of a BIM model of a unit module composed of a wall with a ring beam but no structural columns in the present invention; Figure 4 It is a schematic diagram of a BIM model having both a ring beam and a structural column-filled wall in the present invention; Figure 5 It is a schematic diagram of a BIM model of a unit module composed of both a ring beam and a structural column wall in the present invention; Figure 6 It is a schematic diagram of the BIM model of the T-shaped wall in the present invention; Figure 7 It is a schematic diagram of a BIM model of a T-shaped wall unit module in the present invention; Figure 8 It is a schematic diagram of the BIM model of the L-shaped wall in the present invention; Fig. 9 It is a schematic diagram of a BIM model of an L-shaped wall component unit module in the present invention; Fig.10 It is a schematic diagram of the BIM model of the cross wall in the present invention; Fig.11 It is a schematic diagram of the BIM model of the cross wall component unit module in the present invention; Fig.12 It is a schematic diagram of the mold structure of the unit module H in the present invention; Fig.13 It is a schematic diagram of the mold structure of the unit module G in the present invention.
[0019] The reference numerals in the accompanying drawings are: 1. Steel plate formwork; 2. Steel rectangular tube keel; 3. Base; 4. Clamp; 5. Limit plate; 6. Handle. DETAILED DESCRIPTION
[0020] In order to make the purpose, technical solution and advantages of the implementation of the present invention clearer, the technical solution in the embodiment of the present invention will be described in more detail below in conjunction with the drawings in the embodiment of the present invention. In the drawings, the same or similar reference numerals throughout represent the same or similar elements or elements with the same or similar functions; the described embodiments are part of the embodiments of the present invention, not all of the embodiments; the embodiments and directional terms described below with reference to the drawings are exemplary and intended to be used to explain the present invention, and cannot be understood as limitations on the present invention; based on the embodiments in the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention. The embodiments of the present invention are described in detail below in conjunction with the drawings: The following is combined with Figure 1-Figure 13 The present invention is described in further detail: like Figure 1-Figure 11 As shown, this embodiment discloses a method for constructing a secondary structure concrete component of a fixed brick mold based on modular design, comprising the following steps: Step 1: Deepen the design. According to the general description of the building and structural construction design, structural drawings, architectural drawings, and relevant requirements of the design and construction specifications, use CAD and BIM technology to deepen the design of the secondary structural concrete components of all floors of the building and enter them into the drawings to ensure the accuracy and operability of the deepening documents of the secondary structural concrete components; Step 2: Structural review. Before the formal construction of the secondary masonry structure, first review the axis, elevation, size, and position deviation of the main concrete structure of the building, check the positional relationship between the completed main structure and the secondary structure masonry, ring beam, and structural column to be built, and review the detailed design drawings in combination with the actual situation. For the positions where the relevant parameters between the main structure and the secondary structure are significantly different, timely adjustments should be made, and the design unit should be asked to confirm them. After verification and confirmation, the number of unit modules of secondary structural concrete components on each floor shall be counted and summarized; Step 3: Layout of typical wall fixed brick molds. According to the secondary structure detailed design drawings confirmed by the design unit, select representative walls, preferably: walls with only ring beams but no structural columns, walls with both ring beams and structural columns, T-shaped walls, L-shaped walls, and cross walls. Use BIM modeling to carry out the layout design of masonry and fixed brick mold combination; After the overall layout drawing is completed, the secondary structure concrete components are decomposed into unit modules; Step 4: Mould processing: According to the secondary structure concrete component unit module parameters decomposed from the typical wall brick mould layout, combined with the actual situation on site and the construction progress requirements, BIM modeling technology is used to design and process the mould to ensure the accuracy and reliability of the mould size and size parameters, and the mould precision error does not exceed 2mm; like Figure 12-13 As shown, the molded brick mold includes a steel plate template 1, a steel rectangular tube keel 2, a base 3 and a clamp 4. The steel plate template 1 has multiple groups, which are assembled and welded above the base 3. The inverted mold space formed by the steel plate template 1 matches the ring beam unit module. The steel rectangular tube keel 2 is fixedly welded to the outer wall of the steel plate template 1. After each steel plate template 1 is assembled, it is locked by the clamp 4. The clamp 4 is preferably: a fastening bolt; The fixed brick mold used in the ring beam unit module also includes a limit plate 5 installed between the steel plate template 1 and the base 3 to lock the positions of the steel plate template 1 and the base 3 to resist deformation caused by grouting impact; The standard brick mold used in the structural column unit module also includes a handle 6 installed in the steel plate template 1; Step 5: Making the final brick mold. After the first final brick mold is processed, the final brick mold is tested and the precision and qualified rate of the final brick mold are tested. The precision error of the final brick mold is no more than 3mm. In order to prevent the fixed brick mold from cracking and breaking, before pouring, the fixed brick mold is equipped with 4mm diameter cold-drawn steel bars to increase the crack resistance of the fixed brick mold; Step 6: Wall layout, masonry, and pouring of concrete components. Before formal masonry, first clean the masonry wall base, check the axis, elevation, position, and size of the wall, and set up the skin number pole. According to the secondary structure construction drawings after in-depth design, refer to the assembly methods of various types of walls and standardized brick molds in the typical wall standardized brick mold layout, and carry out the overall combination layout of wall masonry and standardized brick molds to ensure that the masonry method, mortar joints, and masonry overlap length meet the requirements of design and construction specifications. After checking and confirming that they are correct, masonry can be carried out; During the wall construction process, it is difficult to clean up the garbage at the structural column, and protective measures should be taken at the holes of the shaped bricks to prevent mortar debris from falling into the structural column; After the masonry mortar strength reaches the strength required by the design and construction specifications, the secondary structural concrete components can be poured. When pouring concrete, each pouring height shall not exceed 500mm, and steel rods shall be used to vibrate and compact it.
[0021] Finally, it should be pointed out that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit them. Although the present invention has been described in detail with reference to the above embodiments, a person skilled in the art should understand that the technical solutions described in the above embodiments can still be modified, or some of the technical features can be replaced by equivalents; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A method for constructing secondary structural concrete components using a fixed brick mold based on modular design, characterized in that: The following steps are involved: Step 1: Based on the general description of the building and structural construction design, structural drawings, architectural drawings, and relevant requirements of the design and construction specifications, use CAD and BIM software to conduct in-depth design and drawing of the secondary structural concrete components of all floors of the building; Step 2: Before the formal construction of the masonry secondary structure, check the position relationship between the main concrete structure and the secondary structure, and review the detailed design drawings based on the actual situation. Adjust the positions where the relevant parameters between the main structure and the secondary structure are significantly different, and ask the design unit to confirm. After verification and confirmation, the number of unit modules of secondary structural concrete components on each floor shall be counted and summarized; Step 3: According to the secondary structure detailed design drawings confirmed by the design unit, select representative walls, and use BIM modeling to simulate the layout and assembly of masonry and fixed brick molds; After the overall layout drawing is completed, the secondary structure concrete components are decomposed into unit modules; Step 4: According to the decomposed unit module parameters, combined with the actual situation on site and the construction progress requirements, adopt BIM modeling to carry out corresponding mold design and processing; Step 5: After the first fixed brick mold is processed, the fixed brick mold is tested and the finished product accuracy and product qualification rate of the fixed brick mold are tested; Step 6. Before the formal construction on site, the finalized brick molds of each wall masonry and secondary structure concrete components are assembled and arranged as a whole, and construction can be carried out after verification and confirmation.
2. The method for constructing secondary structure concrete components with a fixed brick mold based on modular design according to claim 1 is characterized in that: In the step 2, the axis, elevation, size and position deviation of the main concrete structure of the building are firstly checked, and the positional relationship between the completed main structure and the secondary structure masonry, ring beam and structural column is checked.
3. The method for constructing secondary structure concrete components with a fixed brick mold based on modular design according to claim 2 is characterized in that: In the step 3, a representative wall is a wall having only a ring beam but no structural column, or a wall having both a ring beam and a structural column, or a T-shaped wall, an L-shaped wall, or a cross wall.
4. The method for constructing secondary structure concrete components with a fixed brick mold based on modular design according to claim 3 is characterized in that: In step 4, the precision error of the shaping brick mold does not exceed 2 mm.
5. The method for constructing secondary structure concrete components with a fixed brick mold based on modular design according to claim 4 is characterized in that: In the step 5, the precision error of the finished brick mold does not exceed 3mm.
6. The method for constructing secondary structure concrete components with a fixed brick mold based on modular design according to claim 5 is characterized in that: In the step six, before formal masonry, first clean the base of the masonry wall, check the axis, elevation, position, and size of the wall, and set up the skin number rod. According to the secondary structure construction drawings after in-depth design, refer to the assembly methods of various types of walls and standardized brick molds in the typical wall standardized brick mold layout, and carry out the overall combination layout of wall masonry and standardized brick molds to ensure that the masonry method, mortar joints, and masonry overlap length meet the requirements of design and construction specifications before masonry.
7. The method for constructing secondary structure concrete components with a fixed brick mold based on modular design according to claim 6 is characterized in that: In the step six, after the masonry mortar strength reaches the strength required by the design and construction specifications, the secondary structural concrete components are poured. When pouring concrete, each pouring height does not exceed 500mm, and a steel bar is used to vibrate and compact it.
8. The method for constructing secondary structure concrete components with a fixed brick mold based on modular design according to claim 7 is characterized in that: In the step six, when building the wall, it is difficult to clean up the garbage at the structural column, and protective measures are taken at the holes of the shaped bricks to prevent mortar debris from falling into the structural column.
9. The method for constructing secondary structure concrete components with a fixed brick mold based on modular design according to claim 8 is characterized in that: In the step four, the shaped brick mold includes a steel plate template, a steel rectangular tube keel, a base and a clamp, the steel plate template is fixedly connected to the base, the steel rectangular tube keel is fixedly connected to the steel plate template, and the steel plate template is equipped with the clamp.
10. The method for constructing secondary structure concrete components with a fixed brick mold based on modular design according to claim 9, characterized in that: In the step 5, before the fixed brick mold is cast and manufactured, cold-drawn steel bars are arranged in the mold.