Electric power prefabricated cabin capable of being rapidly installed

By using connectors and drainage systems in power prefabricated chambers, the assembly process is simplified and the stability and drainage efficiency is improved, and the problems of long installation and poor stability in the prior art are solved.

CN119275722APending Publication Date: 2025-01-07GANSU CHENJU MODULAR BUILDING TECH CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202411268403.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-11
Publication Date
2025-01-07

AI Technical Summary

Technical Problem

The existing prefabricated power cabin consumes a lot of construction period and manpower during the installation and construction process, and is not stable, resulting in high labor intensity for staff and low drainage efficiency in rainy weather.

Method used

The prefabricated cabin body consists of a base, wall, connector and cabin top. By setting up connections, support plates, fixing grooves, fixing holes and fasteners, the assembly process is simplified and the stability is improved. Set up drainage troughs, runners and drain pipes to speed up drainage efficiency.

Benefits of technology

It greatly improves the assembly efficiency and stability of the power prefabricated cabin, and quickly discharges the liquid on the roof of the cabin in rainy weather, improving waterproof performance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119275722A_ABST
    Figure CN119275722A_ABST
Patent Text Reader

Abstract

The invention discloses a quick-to-install electric power prefabricated cabin, which comprises a prefabricated cabin main body, the prefabricated cabin main body is composed of a base, a wall body, a connecting piece and a cabin roof, the end face of the base is provided with a first fixing groove and a second fixing groove, the connecting piece is vertically fixed in the first fixing groove and the second fixing groove, and the wall body is fixedly connected with the prefabricated cabin main body. The wall bodies are installed at the edge of the top of the base, the two ends of each wall body are clamped into the connecting pieces, first fixing holes are formed in the surfaces of the first fixing grooves and the wall bodies, second fixing holes are formed in the surfaces of the connecting pieces, and the connecting pieces penetrate through the first fixing holes and the second fixing holes through fasteners to be fixed to the base and the wall bodies. Through cooperative use of the connecting pieces, the supporting plates, the first fixing grooves, the second fixing grooves, the first fixing holes, the second fixing holes and the fasteners, the prefabricated cabin body can be conveniently installed, and meanwhile the overall stability of the prefabricated cabin body is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of prefabricated cabins, and in particular to a rapidly installed prefabricated power cabin. Background Art

[0002] With the continuous development of society, power equipment is also developing and improving. With the improvement of people's quality of life, the demand for electricity is also increasing. When installing power equipment, the existing equipment is more labor-intensive, the installation process is relatively long, and the labor intensity of the staff is relatively high. Therefore, a prefabricated power cabin that can be easily installed and fixed is needed.

[0003] The existing patent CN108075370A discloses a prefabricated power cabin, including a cabin, a cabin door is opened on the side of the cabin, two cantilever beams are arranged in parallel along the length direction of the cabin on the top lower surface of the cabin, a plurality of cable brackets are arranged at intervals below the cantilever beams, cables are preset on the cable brackets, a rail transport vehicle is arranged on the cantilever beam, a telescopic mechanism is arranged on the rail transport vehicle, the rail transport vehicle hoists the power equipment from the cabin door into the cabin through the telescopic mechanism, a cable cabin is formed between the power equipment and the cable bracket, and the power equipment is connected to the cable in the cable cabin. The present invention can save time and effort in installing and disassembling equipment in the cabin, and provide more space for maintenance personnel to repair cables, which is convenient for maintenance work.

[0004] Based on the search of the above patents and in combination with the power prefabricated cabin in the prior art, it is found that the above power prefabricated cabin can install and disassemble the equipment in the cabin when in use, which provides convenience for maintenance. However, in actual use, the most time-consuming part is the construction and installation of the power prefabricated cabin, which is more time-consuming and labor-intensive. The above device is not well designed, which results in a longer construction period and labor intensity for the staff when installing and constructing the power prefabricated cabin, and the stability is not high.

[0005] To this end, we proposed a quick-installation prefabricated power cabin to solve the above-mentioned drawbacks. Summary of the invention

[0006] The purpose of the present invention is to solve the shortcomings of the prior art and to propose a quickly installed prefabricated power cabin.

[0007] In order to achieve the above-mentioned purpose, the present invention adopts the following technical scheme: a quick-installation prefabricated power cabin, comprising a prefabricated cabin body, the prefabricated cabin body is composed of a base, a wall, a connecting piece and a cabin top, the end surface of the base is respectively provided with a first fixing groove and a second fixing groove, the connecting piece is vertically fixed inside the first fixing groove and the second fixing groove, the wall is installed at the top edge of the base, and both ends of each wall are snapped into the inside of the connecting piece, the first fixing groove and the wall surface are provided with a first fixing hole, the surface of the connecting piece is provided with a second fixing hole, the connecting piece is fixed to the base and the wall through a fastener passing through the first fixing hole and the second fixing hole, and the connecting piece is provided by setting the connecting piece, the supporting piece and the supporting piece. The coordinated use of the support plate, the first fixing groove, the second fixing groove, the first fixing hole, the second fixing hole and the fasteners facilitates the installation of the prefabricated cabin body and also improves its overall stability. During assembly, the staff first fits the connecting piece with the first fixing groove and the second fixing groove on the end face of the base, and then fixes the connecting piece to the base through the fasteners. Then, the wall is fixed to the base, and then the two ends of the wall are snapped into the inside of the connecting piece, and then the wall and the connecting piece are fixed through the fasteners. Finally, the cabin roof is fixed to complete the assembly of the prefabricated cabin body. This method is simple to operate and greatly improves its assembly efficiency. At the same time, the overall stability is improved through the setting of the connecting piece.

[0008] Preferably, the cabin roof is installed on the top of the wall, and a first drainage groove and a second drainage groove are provided at the edge of the top surface of the cabin roof, and a flow channel is provided on the top surface of the cabin roof, and both ends of the flow channel are respectively connected with the first drainage groove and the second drainage groove, and drainage pipes are provided at both ends of the cabin roof, and the two drainage pipes are respectively connected with the first drainage groove and the second drainage groove. By setting the first drainage groove, the second drainage groove, the flow channel and the drainage pipe, the efficiency of drainage from the cabin roof surface can be accelerated, so that in rainy weather, rainwater falling on the cabin roof will enter the flow channel, and then enter the first drainage groove and the second drainage groove under the drainage of the flow channel, and then the torrent of liquid can be discharged through the drainage pipe. This method is simple to operate, convenient for quickly discharging the liquid inside the cabin roof, and improves its waterproof performance.

[0009] Preferably, a plurality of flow channels are provided, and the plurality of flow channels are opened at equal distances on the top surface of the tank roof. By providing a plurality of flow channels, the outflow of the liquid on the top of the tank roof can be accelerated.

[0010] Preferably, a support plate is provided inside the connecting piece. By providing the support plate, it is convenient to support both ends of the wall, thereby improving the stability of the connection between the connecting piece and the wall.

[0011] Preferably, the cross-section of the first drainage groove and the second drainage groove is a "v"-shaped structure. By making the cross-section of the first drainage groove and the second drainage groove a "v"-shaped structure, it is convenient for the liquid inside the first drainage groove and the second drainage groove to be discharged through the drain pipe.

[0012] Preferably, the cross section of the flow channel is a "V"-shaped structure. By making the cross section of the flow channel a "V"-shaped structure, it is convenient for the liquid inside the flow channel to flow into the first drainage groove and the second drainage groove.

[0013] Preferably, doors and windows are movably installed on the surface of the prefabricated cabin body, and a clearance hole is opened on the surface of the prefabricated cabin body. By setting the clearance hole, it is easy to make way for the power line, so that the electrical components inside the prefabricated cabin can be conveniently connected to the external power supply.

[0014] Compared with the prior art, the beneficial effects of the present invention are:

[0015] (1) The present invention facilitates the installation of the prefabricated cabin body by providing a connecting piece, a support plate, a first fixing groove, a second fixing groove, a first fixing hole, a second fixing hole and a fastener for use in combination, and also improves its overall stability. During assembly, the worker first fits the connecting piece with the first fixing groove and the second fixing groove on the end face of the base, then fixes the connecting piece to the base through the fastener, then fixes the wall to the base, then snaps the two ends of the wall into the inside of the connecting piece, then fixes the wall to the connecting piece through the fastener, and finally fixes the cabin top, thereby completing the assembly. The assembly of the prefabricated cabin body is simple to operate and greatly improves its assembly efficiency. At the same time, the overall stability is improved by setting the connecting parts. By setting the first drainage trough, the second drainage trough, the flow channel and the drain pipe, the drainage efficiency of the cabin roof surface can be accelerated, so that in rainy weather, rainwater falling on the cabin roof will enter the flow channel, and then enter the first drainage trough and the second drainage trough under the drainage of the flow channel. After that, the torrent of liquid can be discharged through the drain pipe. This method is simple to operate and is convenient for quickly discharging the liquid inside the cabin roof, thereby improving its waterproof performance. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required to be used in the embodiments are briefly introduced below.

[0017] Figure 1 This is a schematic diagram of the structure of a quick-installation prefabricated power cabin proposed by the present invention;

[0018] Figure 2 A schematic diagram of a quick-installation prefabricated power cabin base proposed by the present invention;

[0019] Figure 3A schematic diagram of a quick-installation prefabricated power cabin connector proposed by the present invention;

[0020] Figure 4 A schematic diagram of a quick-installed prefabricated power cabin support plate proposed by the present invention;

[0021] Figure 5 A schematic diagram of a first drainage trough of a quick-installed prefabricated power cabin proposed by the present invention;

[0022] Figure 6 A schematic diagram of a flow channel of a quick-installation prefabricated power cabin proposed by the present invention.

[0023] Legend:

[0024] 1. Base; 2. Wall; 3. Window; 4. Connector; 5. Cabin roof; 6. First drainage groove; 7. Flow channel; 8. Second drainage groove; 9. Drain pipe; 10. Make way hole; 11. Fastener; 12. Cabin door; 13. First fixing groove; 14. First fixing hole; 15. Second fixing groove; 16. Support plate; 17. Second fixing hole. DETAILED DESCRIPTION

[0025] In order to make the purpose, technical scheme and advantages of the present invention clearer, the present invention is further described in detail below in conjunction with specific embodiments and with reference to the accompanying drawings. It should be understood that these descriptions are only exemplary and are not intended to limit the scope of the present invention. In addition, in the following description, the description of well-known structures and technologies is omitted to avoid unnecessary confusion of the concept of the present invention.

[0026] Embodiment 1

[0027] See also Figure 1-6A fast-installed prefabricated power cabin includes a prefabricated cabin body, which is composed of a base 1, a wall 2, a connector 4 and a cabin top 5. The end surface of the base 1 is respectively provided with a first fixing groove 13 and a second fixing groove 15, and the connector 4 is vertically fixed inside the first fixing groove 13 and the second fixing groove 15. The wall 2 is installed at the top edge of the base 1, and both ends of each wall 2 are snapped into the inside of the connector 4. The first fixing groove 13 and the surface of the wall 2 are provided with a first fixing hole 14, and the surface of the connector 4 is provided with a second fixing hole 17. The connector 4 is fixed to the base 1 and the wall 2 through a fastener 11 passing through the first fixing hole 14 and the second fixing hole 17. By setting the connector 4, the support plate 16, the first fixing The coordinated use of the groove 13, the second fixing groove 15, the first fixing hole 14, the second fixing hole 17 and the fastener 11 facilitates the installation of the prefabricated cabin body and also improves its overall stability. During assembly, the staff first fits the connecting piece 4 with the first fixing groove 13 and the second fixing groove 15 on the end face of the base 1, and then fixes the connecting piece 4 to the base 1 through the fastener 11, and then fixes the wall 2 to the base 1, and then snaps the two ends of the wall 2 into the inside of the connecting piece 4, and then fixes the wall 2 to the connecting piece 4 through the fastener 11, and finally fixes the cabin roof 5, thereby completing the assembly of the prefabricated cabin body. This method is simple to operate and greatly improves its assembly efficiency. At the same time, through the setting of the connecting piece 4, its overall stability is improved.

[0028] The working principle of a fast-installed prefabricated power cabin provided by the present invention is as follows:

[0029] By setting the connection piece 4, the support plate 16, the first fixing groove 13, the second fixing groove 15, the first fixing hole 14, the second fixing hole 17 and the fastener 11, the installation of the prefabricated cabin body is facilitated, and the overall stability is also improved. When assembling, the staff first fits the connection piece 4 with the first fixing groove 13 and the second fixing groove 15 on the end face of the base 1, and then fixes the connection piece 4 to the base 1 through the fastener 11, and then fixes the wall 2 to the base 1, and then clamps the two ends of the wall 2 into the inside of the connection piece 4, and then fixes the wall 2 to the connection piece 4 through the fastener 11, and finally fixes the cabin top 5. , thereby completing the assembly of the prefabricated cabin body. This method is simple to operate and greatly improves its assembly efficiency. At the same time, through the setting of the connecting piece 4, its overall stability is improved. By setting the first drainage groove 6, the second drainage groove 8, the flow channel 7 and the drainage pipe 9, it is convenient to speed up the drainage efficiency of the cabin roof 5 surface, so that in rainy weather, the rainwater falling on the cabin roof 5 will enter the flow channel 7, and then enter the first drainage groove 6 and the second drainage groove 8 under the drainage of the flow channel 7. After that, the torrent of liquid can be discharged through the drainage pipe 9. This method is simple to operate and is convenient for quickly discharging the liquid inside the cabin roof 5, thereby improving its waterproof performance.

[0030] Compared with the related art, the fast-installed prefabricated power cabin provided by the present invention has the following beneficial effects:

[0031] By setting the connection piece 4, the support plate 16, the first fixing groove 13, the second fixing groove 15, the first fixing hole 14, the second fixing hole 17 and the fastener 11, the installation of the prefabricated cabin body is facilitated, and the overall stability is also improved. When assembling, the staff first fits the connection piece 4 with the first fixing groove 13 and the second fixing groove 15 on the end face of the base 1, and then fixes the connection piece 4 to the base 1 through the fastener 11, and then fixes the wall 2 to the base 1, and then clamps the two ends of the wall 2 into the inside of the connection piece 4, and then fixes the wall 2 to the connection piece 4 through the fastener 11, and finally fixes the cabin top 5. , thereby completing the assembly of the prefabricated cabin body. This method is simple to operate and greatly improves its assembly efficiency. At the same time, through the setting of the connecting piece 4, its overall stability is improved. By setting the first drainage groove 6, the second drainage groove 8, the flow channel 7 and the drainage pipe 9, it is convenient to speed up the drainage efficiency of the cabin roof 5 surface, so that in rainy weather, the rainwater falling on the cabin roof 5 will enter the flow channel 7, and then enter the first drainage groove 6 and the second drainage groove 8 under the drainage of the flow channel 7. After that, the torrent of liquid can be discharged through the drainage pipe 9. This method is simple to operate and is convenient for quickly discharging the liquid inside the cabin roof 5, thereby improving its waterproof performance.

[0032] Embodiment 2

[0033] Based on the first embodiment, refer to Figure 1-6 The cabin roof 5 is installed on the top of the wall 2, and a first drainage groove 6 and a second drainage groove 8 are provided at the edge of the top surface of the cabin roof 5. A flow channel 7 is provided on the top surface of the cabin roof 5, and both ends of the flow channel 7 are respectively connected with the first drainage groove 6 and the second drainage groove 8. Drain pipes 9 are provided at both ends of the cabin roof 5, and the two drainage pipes 9 are respectively connected with the first drainage groove 6 and the second drainage groove 8. By setting the first drainage groove 6, the second drainage groove 8, the flow channel 7 and the drainage pipe 9, the efficiency of drainage on the surface of the cabin roof 5 can be accelerated, so that in rainy weather, rainwater falling on the cabin roof 5 will enter the flow channel 7, and then enter the first drainage groove 6 and the second drainage groove 8 under the drainage of the flow channel 7, and then the torrent of liquid can be discharged through the drainage pipe 9. This method is simple to operate, and is convenient for quickly discharging the liquid inside the cabin roof 5, thereby improving its waterproof performance.

[0034] Based on the first embodiment, refer to Figure 1-6 There are multiple flow channels 7, and the multiple flow channels 7 are opened at equal distances on the top surface of the cabin roof 5. By setting up multiple flow channels 7, it is convenient to speed up the outflow of liquid on the top of the cabin roof 5.

[0035] Based on the first embodiment, refer to Figure 1-6 A support plate 16 is provided inside the connecting member 4. By providing the support plate 16, it is convenient to support both ends of the wall 2, thereby improving the stability of the connection between the connecting member 4 and the wall 2.

[0036] Based on the first embodiment, refer to Figure 1-6 The cross-section of the first drainage groove 6 and the second drainage groove 8 is a "v"-shaped structure. By making the cross-section of the first drainage groove 6 and the second drainage groove 8 a "v"-shaped structure, it is convenient for the liquid inside the first drainage groove 6 and the second drainage groove 8 to be discharged through the drain pipe 9.

[0037] Based on the first embodiment, refer to Figure 1-6 The cross section of the flow channel 7 is a "V"-shaped structure. By making the cross section of the flow channel 7 a "V"-shaped structure, it is convenient for the liquid inside the flow channel 7 to flow into the first drainage groove 6 and the second drainage groove 8.

[0038] Based on the first embodiment, refer to Figure 1-6 The surface of the prefabricated cabin body is movably provided with a door 12 and a window 3, and the surface of the prefabricated cabin body is provided with a clearance hole 10. By setting the clearance hole 10, it is convenient to make way for the power line, so that the electrical components inside the prefabricated cabin can be connected to the external power supply.

[0039] It should be noted that all kinds of components used in this application document are standard parts and can be purchased on the market. The specific connection methods of each part adopt conventional means such as mature bolts, rivets and welding in the existing technology. Machinery, parts and electrical equipment all adopt conventional models in the existing technology. Circuit connections adopt conventional connection methods in the existing technology. Electrical equipment are connected to an external safe power supply, and no specific description is given here.

[0040] It should be understood that the above specific embodiments of the present invention are only used to illustrate or explain the principles of the present invention, and do not constitute a limitation of the present invention. Therefore, any modifications, equivalent substitutions, improvements, etc. made without departing from the spirit and scope of the present invention should be included in the protection scope of the present invention. In addition, the appended claims of the present invention are intended to cover all changes and modifications that fall within the scope and boundaries of the appended claims, or the equivalent forms of such scope and boundaries.

Claims

1. A fast-installed prefabricated power cabin, comprising a prefabricated cabin body, characterized in that: The prefabricated cabin body is composed of a base (1), a wall (2), a connecting piece (4) and a cabin top (5); the end surface of the base (1) is respectively provided with a first fixing groove (13) and a second fixing groove (15); the connecting piece (4) is vertically fixed inside the first fixing groove (13) and the second fixing groove (15); the wall (2) is installed at the top edge of the base (1), and both ends of each wall (2) are snapped into the inside of the connecting piece (4); the first fixing groove (13) and the surface of the wall (2) are provided with a first fixing hole (14); the surface of the connecting piece (4) is provided with a second fixing hole (17); the connecting piece (4) is fixed to the base (1) and the wall (2) by a fastener (11) penetrating the first fixing hole (14) and the second fixing hole (17).

2. A rapidly installed prefabricated power cabin according to claim 1, characterized in that: The cabin roof (5) is installed on the top of the wall (2); a first drainage groove (6) and a second drainage groove (8) are provided at the edge of the top surface of the cabin roof (5); a flow channel (7) is provided on the top surface of the cabin roof (5); two ends of the flow channel (7) are respectively connected to the first drainage groove (6) and the second drainage groove (8); drainage pipes (9) are provided at both ends of the cabin roof (5); the two drainage pipes (9) are respectively connected to the first drainage groove (6) and the second drainage groove (8).

3. A rapidly installed prefabricated power cabin according to claim 2, characterized in that: A plurality of flow channels (7) are provided, and the plurality of flow channels (7) are opened at equal distances on the top surface of the cabin top (5).

4. A rapidly installed prefabricated power cabin according to claim 1, characterized in that: A support plate (16) is arranged inside the connecting piece (4).

5. The fast-installed prefabricated power cabin according to claim 2, characterized in that: The cross-sections of the first drainage groove (6) and the second drainage groove (8) are "V"-shaped structures.

6. The fast-installed prefabricated power cabin according to claim 2, characterized in that: The cross section of the flow channel (7) is a "V" shaped structure.

7. The fast-installed prefabricated power cabin according to claim 1, characterized in that: A door (12) and a window (3) are movably mounted on the surface of the prefabricated cabin body, and a clearance hole (10) is provided on the surface of the prefabricated cabin body.

Citation Information

Patent Citations

  • Power prefabrication cabin

    CN108075370A