Pipe pile cantilever safety platform and installation method thereof
By installing friction self-locking fixtures and steel structure platforms and guardrails with adjustable support rods on the outer wall of the pipe pile, the difficulty of setting up the traditional scaffolding on the slope floor and the foundation of the high-pipe pile is solved, and the installation of photovoltaic modules is realized. Safe and efficient operation.
Patent Information
- Application Number
- CN202411300845.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-18
- Publication Date
- 2025-02-07
AI Technical Summary
On the slope ground and high-management pile foundation, traditional movable scaffolding is difficult to erect, which poses safety risks and cannot meet the needs of photovoltaic module installation operations.
The friction self-locking fixture is used as the fulcrum, and the adjustable support rod is used to install the steel structure platform and guardrail on the outer wall of the pipe pile to form a cantilever safety platform and provide a safe operation platform.
It solves the problem that traditional scaffolding cannot be erected, provides a safe operating platform that is not restricted by terrain, and improves the efficiency and safety of photovoltaic module installation.
Smart Images

Figure CN119392905A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of photovoltaic assembly installation, and in particular to a pipe pile cantilever safety platform and an installation method thereof. Background Art
[0002] Prefabricated pipe piles are one of the most common forms of pile foundations for photovoltaic construction projects and are widely used. For the "tea-photovoltaic complementary" construction project, the height of the prefabricated pipe piles needs to be considered in combination with the safe net height of mechanical tea picking. Generally, the height of the prefabricated pipe piles is above 3.5m. At this height, personnel cannot stand on the ground to perform installation operations, and a safe operating platform needs to be set up to install photovoltaic modules. However, tea gardens are mostly mountainous, with rugged and uneven ground and a certain slope. The erection of movable scaffolding is extremely inconvenient and poses a safety hazard. Therefore, the development of a photovoltaic module installation operation platform suitable for sloping ground and high pipe pile foundation is a technical problem that needs to be solved urgently. Summary of the invention
[0003] In view of the above-mentioned defects in the prior art, the present invention provides a pipe pile cantilever safety platform and an installation method thereof, which utilizes a friction self-locking clamp as a fulcrum and an adjustable support rod as a support, and installs a steel structure platform and a guardrail on the outer wall of the pipe pile, thereby providing a safe operating platform to solve the problem that traditional movable scaffolding cannot be erected and cannot ensure the safety of personnel during component installation.
[0004] To achieve the above-mentioned purpose, on the one hand, the present invention provides a pipe pile cantilever safety platform, characterized in that: upper friction self-locking nodes and lower friction self-locking nodes are distributed on the upper and lower sides of the outer wall of the pipe pile; the upper friction self-locking nodes are evenly connected to a plurality of horizontal support arms toward the outer periphery; a platform is installed on the upper surface of the horizontal support arm; a platform plate is installed on the top surface of the platform, and a guardrail is provided on the outer edge; an adjustable support rod connects the lower friction self-locking node and the horizontal support arm, forming a triangular support structure under the horizontal support arm;
[0005] The upper friction self-locking node and the lower friction self-locking node both include a wedge-shaped slider and a friction self-locking clamp; the inner diameter of the wedge-shaped slider is the same as the outer diameter of the pipe pile, and the whole is circular, adopts a semicircular structure design, and is fixed to the outer wall of the pipe pile by clamping with a hoop; the friction self-locking clamp is two semicircular wedge blocks, whose wedge surfaces are complementary to the wedge surfaces of the wedge-shaped slider, and are fixed to the outer wall of the wedge-shaped slider by clamping with a hoop.
[0006] The safety platform of the present invention uses the friction self-locking device as a fulcrum and the adjustable support rod as a support to detachably and firmly connect the horizontal support arm of the platform with the pipe pile, which can solve the problem that the traditional movable scaffolding cannot be erected. Compared with the traditional clamping method, the friction self-locking device has a higher bearing capacity and a stable and safe structure.
[0007] Furthermore, there are 12 horizontal support arms evenly distributed along the circumference, and the angle between adjacent horizontal support arms is 30°.
[0008] Furthermore, the platform is a modular steel structure platform, which can achieve rapid assembly and disassembly of the steel platform.
[0009] Furthermore, the guardrail adopts a sleeve insertion connection mode, and the base of the sleeve is fixed on the platform. When in use, the shaped railing is inserted into the sleeve at the bottom, and the bolts are tightened. The railing can be removed by loosening the bolts, which is convenient for installation and removal.
[0010] Furthermore, the adjustable support rod is composed of internal threaded sleeves on both sides and a matching screw in the middle, and a nut is fixed in the middle of the screw. The function of adjusting the length of the support rod is achieved by rotating the nut forward and backward.
[0011] Furthermore, ear plates are provided on the outer periphery of the lower friction self-locking node and at positions corresponding to the horizontal support arms; connecting rings are provided at both ends of the adjustable support rod, and the lower friction self-locking node and the horizontal support arm are connected by the ear plates, connecting rings and bolts to form a triangular support structure under the horizontal support arm.
[0012] On the other hand, the present invention provides a method for installing a pipe pile cantilever safety platform, characterized in that the installation of the pipe pile cantilever safety platform as described above comprises the following steps:
[0013] Step S1, confirm the position of the upper friction self-locking node and the lower friction self-locking node according to the height of the installer, and install the upper and lower pairs of wedge-shaped sliders, and fix and clamp them on the outer wall of the pile with the first connecting clamping piece;
[0014] Step S2, installing two pairs of upper and lower friction self-locking clamps, and using a second connecting clamping piece to fix and clamp the outer wall of the wedge-shaped slider;
[0015] Step S3, connecting horizontal supporting arms evenly and dispersedly on the outer circumference of the friction self-locking clamp;
[0016] Step S4, installing an adjustable support rod between the horizontal support arm and the upper friction self-locking node;
[0017] Step S5: installing a platform, a platform board and a guardrail on the horizontal supporting arm.
[0018] Compared with the prior art, the present invention has the following beneficial effects:
[0019] (1) The platform device of the present invention is a pipe pile cantilever structure, which is not affected by the topography and terrain undulations; the pipe pile clamp adopts the friction self-locking working principle, has a larger bearing capacity and is safer.
[0020] (2) The platform device of the present invention has a simple structure, is easy to manufacture, has a low cost, and the installation method requires low operator skills and is easy to use.
[0021] (3) The platform and guardrail of the present invention can be installed in a modular and standardized manner, which can be quickly installed and disassembled, and is extremely convenient for turnover and use. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] The present invention and its features, appearance and advantages will become more apparent by reading the detailed description of non-limiting embodiments with reference to the following drawings. The same reference numerals indicate the same parts in all the drawings. The drawings are not drawn completely to scale, and emphasis is placed on illustrating the subject matter of the present invention.
[0023] Figure 1 This is a general assembly diagram of a pipe pile cantilever safety platform in one embodiment of the present invention;
[0024] Figure 2 for Figure 1 A magnified view of part A;
[0025] Figure 3 It is a plan view of a pipe pile cantilever safety platform in one embodiment of the present invention;
[0026] Figure 4 This is a schematic structural diagram of a detachable guard bar in one embodiment of the present invention;
[0027] Figure 5 This is a schematic diagram of the structure of an adjustable support rod in one embodiment of the present invention;
[0028] Figure 6 This is a flow chart of the installation of a pipe pile cantilever safety platform in one embodiment of the present invention;
[0029] Among them, 1. photovoltaic module; 2. photovoltaic bracket; 3. pipe pile; 4. sloped ground; 5. wedge-shaped slider; 6. friction self-locking clamp; 7. platform; 8. guardrail; 9. adjustable support rod; 10. second connecting clamping piece; 11. platform plate; 12. horizontal support arm; 13. guardrail sleeve; 14. ear plate; 15. first connecting clamping piece; 91. internal threaded sleeve; 92. screw; 93. nut; 94. connecting ring. DETAILED DESCRIPTION
[0030] The exemplary embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. It should be understood that all of these exemplary embodiments described are only partial embodiments and examples of the present invention, rather than all of them. On the contrary, these exemplary embodiments are provided so that those skilled in the art can more thoroughly understand the present disclosure and can more completely convey the technical content of the present disclosure to those skilled in the art.
[0031] In the description of this application, unless otherwise clearly specified and limited, the terms "installation" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; the method can be welding or threaded connection; it can be directly connected or indirectly connected through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0032] Example
[0033] See also Figures 1 to 3 The present embodiment provides a pipe pile cantilever safety platform, wherein upper friction self-locking nodes and lower friction self-locking nodes are distributed on the upper and lower outer walls of the pipe pile 3; the upper friction self-locking nodes are evenly connected to a number of horizontal support arms 12 toward the outer periphery; a platform 7 is installed on the upper surface of the horizontal support arm 12; a platform plate 11 is installed on the top surface of the platform 7, and a guardrail 8 is provided on the outer edge; an adjustable support rod 9 connects the lower friction self-locking node and the horizontal support arm 12 to form a triangular support structure under the horizontal support arm 12; the upper friction self-locking node and the lower friction self-locking node both include a wedge-shaped slider 5 and a friction self-locking clamp 6; the inner diameter of the wedge-shaped slider 5 is the same as the outer diameter of the pipe pile 3, and the whole is circular, adopts a semicircular structure design, and is fixed to the outer wall of the pipe pile 3 by clamping with a hoop; the friction self-locking clamp 6 is two semicircular wedge-shaped blocks, whose wedge surfaces are complementary to the wedge surfaces of the wedge-shaped slider 5, and are fixed to the outer wall of the wedge-shaped slider 5 by clamping with a hoop.
[0034] The technical principle of the safety platform is: the friction self-locking device is used as a fulcrum, and the adjustable support rod is used as a support to detachably and firmly connect the horizontal support arm of the platform to the pipe pile, so as to stably carry the load of the platform. When the friction self-locking clamp of the friction self-locking device is subjected to its own weight and upper load, the friction self-locking clamp moves downward, and maintains a continuous friction and compression state with the wedge-shaped slider during the movement. The friction force is directed upward, and then stable self-locking is achieved, and it is firmly fixed on the pipe pile. Compared with the traditional clamping method, the friction self-locking device has a higher bearing capacity and a stable and safe structure.
[0035] As a preferred technical solution, 12 horizontal support arms 12 are evenly distributed along the circumference, and the angle between adjacent horizontal support arms is 30°. The distribution density of the load-bearing support arms meets the safety requirements for safe operation of personnel.
[0036] As a preferred technical solution, the platform 7 is a modular steel structure platform, which can realize rapid assembly and disassembly of the steel platform.
[0037] As a preferred technical solution, see Figure 4The guardrail 8 adopts a sleeve insertion connection mode, and the base of the sleeve 13 is fixed on the platform 7. When in use, the shaped railing is inserted into the sleeve at the bottom, the bolts are tightened, and the railing can be removed by loosening the bolts, which is convenient for installation and removal.
[0038] As a preferred technical solution, see Figure 5 The adjustable support rod 9 is composed of an internal threaded sleeve 91 on both sides and a matching screw rod 92 in the middle, and a nut 93 is fixed in the middle of the screw rod 92. The function of adjusting the length of the support rod is achieved by rotating the nut forward and backward.
[0039] As a preferred technical solution, see Figure 1 and Figure 5 An ear plate 14 is provided on the outer periphery of the lower friction self-locking node and at a position corresponding to the horizontal support arm 12 to provide a support connection point; connecting rings 94 are provided at both ends of the adjustable support rod 9, and the lower friction self-locking node and the horizontal support arm 12 are connected by the ear plate 14, the connecting ring 94 and bolts to form a triangular support structure under the horizontal support arm 12.
[0040] See also Figure 1 , Figure 2 and Figure 6 The pipe piles 3 of the photovoltaic support 2 are prefabricated on the sloped ground 4, and then the above-mentioned pipe pile cantilever safety platform is installed. The more specific installation method includes the following steps:
[0041] Step S1, according to the height of the installer, confirm the position of the upper friction self-locking node and the upper friction self-locking node, and install the upper and lower pairs of wedge-shaped sliders 5, and fix them on the outer wall of the pipe pile 3 with the first connecting clamping piece 15.
[0042] Step S2, installing two pairs of upper and lower friction self-locking clamps 6, and using the second connecting clamping piece 10 to fix and clamp them on the outer wall of the wedge-shaped slider 5.
[0043] Step S3, evenly distribute and connect the horizontal support arms 12 on the outer circumference of the friction self-locking clamp 6. Figure 2 The preferred connection method is bolt connection.
[0044] Step S4, install the adjustable support rod 9 between the horizontal support arm 12 and the upper friction self-locking node. The adjustable support rod can use a screw with a larger diameter to meet the requirement of providing auxiliary support for the horizontal support arm. Preferably, the adjustable support rod is designed with a "positive and negative thread structure" and a nut is fixed in the middle; when the nut rotates forward and backward, the connection mechanisms on both sides will be extended and retracted, thereby achieving length adjustment.
[0045] Step S5, the platform 7, the platform plate 11 and the guardrail 8 are installed on the horizontal support arm 12. More specifically, a detachable steel structure platform 7 is installed on the horizontal support arm 12, and a platform plate 11 is installed on the top of the platform 7. The platform 7 and the platform plate 11 are fixedly connected to the horizontal support arm structure by bolts. A detachable guardrail sleeve 13 is installed around the detachable platform 7; when in use, the detachable guardrail 8 is inserted into the sleeve at the bottom and the bolts are tightened. When dismantling, first loosen the bottom bolts to remove the guardrail.
[0046] After the safety platform is assembled, construction workers can stand on the platform board 11 to install the photovoltaic bracket 2 and the photovoltaic panel 1.
[0047] From the above construction process, it can be known that the cantilever safety platform of the present invention is suitable for prefabricated pipe pile operations with a high excavation height. It is relatively convenient to manufacture and install, and can be quickly used in a turnover manner. Because it is a cantilever structure, the platform erection is not restricted by terrain and landforms. A photovoltaic composite power generation project undertaken by our company is designed with a total of 100,000 meters of pipe piles, divided into 16 photovoltaic matrices. In the installation process of photovoltaic modules, the present invention is adopted, which greatly improves the installation efficiency of photovoltaic modules, ensures the safety of personnel operations, and achieves the expected effect.
[0048] In summary, the present invention provides a pipe pile cantilever safety platform and an installation method thereof, characterized in that upper friction self-locking nodes and lower friction self-locking nodes are distributed on the upper and lower outer walls of the pipe pile; the upper friction self-locking nodes are evenly connected to a number of horizontal support arms toward the periphery; a platform is installed on the upper surface of the horizontal support arm; a platform plate is installed on the top surface of the platform, and a guardrail is provided on the outer edge; an adjustable support rod connects the lower friction self-locking node and the horizontal support arm to form a triangular support structure under the horizontal support arm; the upper friction self-locking node and the lower friction self-locking node both include a wedge-shaped slider and a friction self-locking clamp. The present invention utilizes the friction self-locking clamp as a fulcrum, cooperates with the adjustable support rod as a support, and installs a steel structure platform and guardrail on the outer wall of the pipe pile, thereby providing a safe operation platform to solve the problem that traditional movable scaffolding cannot be erected.
[0049] The above describes the preferred embodiments of the present invention. It should be understood that the present invention is not limited to the above-mentioned specific embodiments, and the devices and structures that are not described in detail should be understood to be implemented in a common manner in the art; any technician familiar with the art can use the above-disclosed methods and technical contents to make many possible changes and modifications to the technical solutions of the present invention without departing from the scope of the technical solutions of the present invention, or modify them into equivalent embodiments of equivalent changes, which does not affect the essential content of the present invention. Therefore, any simple modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solutions of the present invention are still within the scope of protection of the technical solutions of the present invention.
Claims
1. A pipe pile cantilever safety platform, characterized by: The outer wall of the pipe pile (3) is provided with upper friction self-locking nodes and lower friction self-locking nodes distributed above and below; the upper friction self-locking nodes are evenly connected to a plurality of horizontal support arms (12) toward the outer periphery; a platform (7) is installed on the upper surface of the horizontal support arm (12); a platform plate (11) is installed on the top surface of the platform (7), and a guardrail (8) is provided on the outer edge; an adjustable support rod (9) connects the lower friction self-locking node and the horizontal support arm (12), forming a triangular support structure under the horizontal support arm (12); The upper friction self-locking node and the lower friction self-locking node both comprise a wedge-shaped slider (5) and a friction self-locking clamp (6); the inner diameter of the wedge-shaped slider (5) is the same as the outer diameter of the pipe pile (3), the whole is circular, and adopts a semicircular structure design, and is fixed to the outer wall of the pipe pile (3) by clamping with a clamp; the friction self-locking clamp (6) is two semicircular wedge blocks, the wedge surfaces of which are complementary to the wedge surfaces of the wedge-shaped slider (5), and are fixed to the outer wall of the wedge-shaped slider (5) by clamping with a clamp.
2. The pipe pile cantilever safety platform according to claim 1, characterized in that: There are 12 horizontal supporting arms (12) evenly distributed along the circumference.
3. The pipe pile cantilever safety platform according to claim 1, characterized in that: The platform (7) is a modular steel structure platform.
4. A pipe pile cantilever safety platform according to claim 1 or 3, characterized in that: The guardrail (8) adopts a sleeve insertion connection method, and the base of the guardrail sleeve (13) is fixed on the platform (7).
5. A pipe pile cantilever safety platform according to claim 1 or 3, characterized in that: The adjustable support rod (9) is composed of internal threaded sleeves (91) on both sides and a matching screw rod (92) in the middle, and a nut (93) is fixed in the middle of the screw rod (92).
6. The pipe pile cantilever safety platform according to claim 5, characterized in that: Ear plates (14) are provided at the outer periphery of the lower friction self-locking node and at positions corresponding to the horizontal support arm (12); connecting rings (94) are provided at both ends of the adjustable support rod (9); the lower friction self-locking node and the horizontal support arm (12) are connected by the ear plates (14), the connecting rings (94) and bolts, so as to form a triangular support structure under the horizontal support arm (12).
7. A method for installing a pipe pile cantilever safety platform, characterized in that: The installation of the pipe pile cantilever safety platform according to any one of claims 1 to 6 comprises the following steps: Step S1, confirm the position of the upper friction self-locking node and the lower friction self-locking node according to the height of the installer, and install the upper and lower pairs of wedge-shaped sliders (5), and fix and clamp them on the outer wall of the pipe pile (3) with the first connecting clamping piece (15); Step S2, installing two pairs of upper and lower friction self-locking clamps (6), and using a second connecting clamping piece (10) to fix and clamp the clamps on the outer wall of the wedge-shaped slider (5); Step S3, connecting the horizontal supporting arms (12) evenly and dispersedly on the outer circumference of the friction self-locking clamp (6); Step S4, installing the adjustable support rod (9) between the horizontal support arm (12) and the upper friction self-locking node; Step S5: installing the platform (7), the platform plate (11) and the guardrail (8) on the horizontal supporting arm (12).
Citation Information
Patent Citations
Assembly type expansion self-locking joint and tower platform supporting and connecting structure
CN112302401A
Working platform for offshore photovoltaic frame installation and installation method thereof
CN118563741A
Binding operation platform for construction steel bars
CN214462703U
Suspension type construction platform structure of photovoltaic power station
CN217054266U
Novel self-locking hoop
CN217923124U