Fabricated construction method for inverted circular truncated cone fireproof glass curtain wall
Through the prefabricated construction method of rounded fireproof glass curtain wall, the problem that the existing technology cannot be applied to the rounded fireproof glass curtain wall structure is solved, and the stability, sealing and fire resistance of the curtain wall structure is improved, which significantly shortens the construction cycle.
Patent Information
- Application Number
- CN202411816567.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-11
- Publication Date
- 2025-02-11
AI Technical Summary
The existing curtain wall construction method cannot be suitable for rounded table fireproof glass curtain wall structures, resulting in high construction difficulty and long cycle, and the stability, sealing and fire resistance of the structure cannot meet the requirements.
The prefabricated construction method of rounded fireproof glass curtain wall is adopted. Through fine construction lines, keel assembly and fireproof structure installation, the stability and integrity of the curtain wall structure are ensured, and the combination efficiency of the keel unit is improved through adjustment parts.
The modular and standardized construction of the curtain wall structure has been realized, which significantly shortens the construction cycle, improves the stability and overall performance of the structure, enhances the wind pressure and earthquake resistance of the curtain wall, and improves the sealing and fire resistance.
Smart Images

Figure CN119411828A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of curtain wall construction, and in particular to an assembled construction method for an inverted truncated table fireproof glass curtain wall. Background Art
[0002] With the diversified development of modern architectural design concepts, architects are constantly breaking through the constraints of traditional architectural frameworks with extraordinary creativity, integrating complex roof shapes such as slopes and arcs into architectural design, adding infinite vitality and charm to the city skyline. For example, the inverted truncated glass curtain wall construction structure has a unique shape and is difficult to construct. The inverted truncated fireproof glass curtain wall assembly construction method has shown extremely high innovation and challenges in modern architectural design. The construction difficulties are mainly reflected in the following aspects: First of all, the special shape of the inverted truncated cone requires the skeleton system to have a high degree of stability and precision. The production and marking positioning of the keel unit should be precise to ensure that the skeleton will not deform or become unstable when bearing load.
[0003] Secondly, the processing and installation of fire-resistant glass is also a major difficulty. Due to the complex shape of the frustum, fire-resistant glass needs to be customized, and the installation process needs to ensure a close fit between the glass and the frame, which places high demands on processing accuracy and installation technology.
[0004] In addition, sealing and fire protection are also key links in construction. Appropriate sealing materials and fireproof materials need to be selected to ensure the fire resistance and air tightness of the curtain wall.
[0005] At the same time, safety control during the construction process is also a difficulty that cannot be ignored. High-altitude operations and the construction of complex structures increase safety risks, and strict safety measures and emergency plans need to be taken to ensure the safety of construction workers.
[0006] Based on this, it is necessary to study an assembled construction method for inverted frustum fire-resistant glass curtain wall. Summary of the invention
[0007] In view of this, the purpose of the present invention is to provide an assembled construction method for an inverted frustum fire-resistant glass curtain wall, which effectively solves the problem that the existing curtain wall construction method is not applicable to the inverted frustum fire-resistant glass curtain wall structure, making the construction of the inverted frustum fire-resistant glass curtain wall difficult, the construction period is long, and the stability, sealing and fire resistance between the structures cannot meet the requirements.
[0008] To achieve the above object, the technical solution adopted by the present invention is: an assembled construction method of an inverted truncated cone fireproof glass curtain wall, comprising the following steps; Step 1: Construction layout Take the elevation line and axis of each floor as the reference line, measure the auxiliary axis from the original axis control point and elevation point, and make auxiliary marks on the corresponding level; determine the position of the horizontal post-embedded parts according to the construction drawings and the horizontal elevation line on site, and make embedded plate marks; determine the position of the vertical keel and the horizontal keel according to the curtain wall grid drawing, and make keel marks; Step 2: Determination of curtain wall dividing line and keel line Determine the corner position and construct the corner vertical line. Then divide the grid between the two corner points according to the grid size, connect the upper and lower lines to form an overall control network. According to the distance between the surface line of the drawing and the keel line, the keel line is reversed inwards as the basis for installing the keel. Step 3: Post-embedded plate and adapter construction At the embedded plate mark, a rear embedded plate is constructed, and an adapter is fixed on the rear embedded plate; a long hole is provided at the end of the adapter; Step 4: Keel assembly The curtain wall keel is divided into multiple keel units according to the overall control network, and the keel units are assembled and hoisted to the corresponding points and connected with the adjustment holes of the adapter bolts; adjacent keel units are connected vertically through steel inserts and horizontally through U-shaped connection seats; Step 5: Interlayer fire protection installation A fireproof structure is constructed between the curtain wall keel and the interlayer floor slab. The fireproof structure is supported by fireproof rock wool and galvanized steel plates, and is sealed after construction is completed; Step 6: Glass panel and backing plate installation The backing plate is fixed on the inner side of the keel frame. After the glass panel is manufactured in the factory, it is transported to the construction site. A fireproof rubber pad is placed between the glass panel and the keel frame, and sealant is added to fix the glass panel on the keel frame. Step 7: Install the decorative cover First, waterproof and seal the vertical line laying area, and then buckle the decorative cover onto the glass panel.
[0009] Furthermore, the keel unit includes columns and crossbeams. The columns between adjacent keel units are connected by inserts and expansion joints are reserved. A U-shaped seat is fixed on the side of the column, and the cross keel is fixed in the U-shaped seat by bolts.
[0010] Furthermore, the steel core is arranged on the inner side of the upper column and fixed by bolts; a socket is arranged on the inner side of the lower column, the core is sleeved in the socket and fixed on the rear embedded plate.
[0011] Furthermore, the fire protection structure includes an interlayer fire protection structure and a transverse fire protection structure. The interlayer fire protection structure is arranged between the interlayer floor and the curtain wall body and fixed on the adapter; the transverse fire protection structure is L-shaped, and its two ends are respectively fixed between the curtain wall body and the transverse partition wall.
[0012] Furthermore, the rear embedded plate includes a side embedded plate, a top embedded template and a bottom embedded template.
[0013] Furthermore, it also includes an inner circle curtain wall structure and an outer circle curtain wall structure; the main body of the floor is between the inner circle curtain wall structure and the outer circle curtain wall structure.
[0014] Furthermore, closing structures are provided above and below the inner circle curtain wall structure and the outer circle closing structure, and the closing structure includes a closing piece and a closing seat, one side of the closing seat is fixedly connected to the building body, and the other side is connected to the lower part of the keel unit, and the glass panel is connected to the outer side of the closing seat through the closing piece.
[0015] Furthermore, the crossbeam and the column are connected by an adjusting piece, and the adjusting piece includes a central clamp body, a first clamp seat, a second clamp seat, a limiting track, a limiting slide plate and an adjusting plate; the central clamp body is a U-shaped structure, and the first clamp seat and the second clamp seat are hinged on both sides of its opening, and the first clamp seat and the second clamp seat both have outward U-shaped openings so that the crossbeam can be fixed therein, and the limiting track is arranged on the back side of the first clamp seat and the second clamp seat, and the limiting slide plate is adapted to be mounted therein, and one end of the adjusting plate is hinged to the end of the limiting slide plate, and an adjusting flat hole is arranged on the other side.
[0016] Furthermore, both sides and the back side of the central clamp are provided with connection holes, wherein the connection holes on the back side correspond to the adjustment flat holes, and the central clamp is combined with the column after bolts are applied.
[0017] Furthermore, the main bodies of the first clamping seat and the second clamping seat are both provided with long holes so that the crossbeam can adjust the length thereof.
[0018] The beneficial effects of the above technical solution are: the present invention accurately determines the position of the rear embedded plate and the installation position of the keel through the layout construction, and at the same time combines the corner position and constructs the corner vertical line, and then divides the grid between the two corner points according to the grid size, connects the upper and lower lines to form an overall control network; according to the size of the surface line of the drawing from the keel line, the keel line is reversed inward as the basis for installing the keel, providing a positioning point for the installation of the keel, which is convenient for subsequent construction.
[0019] During construction, the keel units are divided into units and prefabricated in the factory. Adjacent keel units are connected horizontally through U-shaped connecting seats and spliced up and down through steel inserts to achieve the combination and docking of keel units, making structural construction convenient.
[0020] At the same time, the present invention can make the connection angle between the crossbeam and the column adjustable through the adjusting piece, that is, the central clamping body is fixedly assembled on the column, and the first clamping body and the second frame body on both sides thereof can adjust the angle relative to each other, and lock it after the adjustment is completed, so that the structure of the crossbeam and the column can form an arc-shaped curved surface, which is convenient for the assembly of the crossbeam and its angle adjustment, simple to operate, and improves the combination efficiency between the keel units.
[0021] The present invention realizes modular and standardized construction of curtain wall structures through precise construction layout, keel assembly and other steps, reduces the time of on-site processing and debugging, and significantly shortens the construction period; at the same time, by positioning and connecting the keels, the stability and integrity of the curtain wall structures are ensured, and the wind pressure resistance, earthquake resistance and other performances of the curtain wall are improved; further, the adjustment parts are used to improve the combination efficiency of the keels, ensure the smooth transition of the transition points, reduce the construction difficulty, improve the aesthetics of the curtain wall, ensure the close connection and transition between the curtain wall and the main building, and enhance the stability and durability of the overall structure. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 It is a schematic diagram of the implementation structure of the present invention; Figure 2 It is a schematic diagram of the implementation structure of the glass panel and the frame unit; Figure 3 Schematic diagram of the structure for the inner and outer curtain walls; Figure 4 It is a schematic diagram of the closing structure; Figure 5 It is a schematic diagram of the implementation structure of the regulating member; Figure 6 for Figure 5 Schematic diagram of the main structure; Figure 7 for Figure 5 Schematic diagram of the top view structure.
[0023] Figure markings: 1-column, 2-crossbeam, 3-glass panel, 4-decorative cover, 5-steel insert, 6-adapter, 7-rear embedded plate, 8-inter-layer floor, 9-inter-layer fire protection structure, 10-lateral fire protection structure, 11-outer circle curtain wall structure, 12-inner circle curtain wall structure, 13-closing seat, 14-closing piece, 15-center clamp seat, 16-first clamp seat, 17-second clamp seat, 18-limiting track, 19-limiting slide plate, 20-adjusting plate, 21-adjusting flat hole. DETAILED DESCRIPTION
[0024] The present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments: Embodiment 1, this embodiment aims to provide an assembled construction method of an inverted frustum fireproof glass curtain wall, which is mainly used to form the main body of an inverted frustum fireproof glass curtain wall. The current construction method cannot be applied to the inverted frustum fireproof glass curtain wall structure, which makes the construction of the inverted frustum fireproof glass curtain wall difficult and the construction period long. The stability, sealing and fire resistance between the structures cannot meet the requirements. Therefore, this embodiment provides an assembled construction method of an inverted frustum fireproof glass curtain wall.
[0025] Specific as Figure 1-2 As shown in , an assembled construction method of an inverted frustum fireproof glass curtain wall comprises the following steps: Step 1: Construction layout Take the elevation line and axis of each floor as the reference line, measure the auxiliary axis from the original axis control point and elevation point, and make auxiliary marks on the corresponding level; determine the position of horizontal post-embedded parts according to the construction drawings and the horizontal elevation line on site, and make embedded plate marks; determine the position of vertical and horizontal keels according to the curtain wall grid diagram, and make keel marks.
[0026] When positioning and laying out, the four-byte method of exterior curtain wall construction is used for laying out, including: "check", "guide", "measure", and "determine".
[0027] 1. “Check” mainly includes the calibration of instruments before construction and the review of the axis and elevation provided by the general contractor.
[0028] Calibration of instruments: Before entering the construction site to lay out the lines, construction personnel will calibrate instruments such as levels and theodolites to ensure the accuracy of the measurements.
[0029] Axis and elevation verification: After entering the construction site, the construction personnel will verify the axis position, original elevation point and one-meter elevation line or 50 line provided by the general contractor. Appropriate and reasonable allocation of the errors that occur, and after inspection and confirmation, fill in the axis and original elevation point actual measurement record table.
[0030] 2. “Guide” is mainly divided into floor elevation line, axis line and control line.
[0031] Draw floor elevation lines: Pull a ruler upward to measure and set the line to the main floor based on the verified original elevation point, mark the relative elevation of each floor on the column or wall of each floor, and draw points to other facades and mark them based on the elevation point of each floor.
[0032] Lead the axis line and control line: Lead the verified axis line and control line to the four corners and the positive and negative corners of each floor's building structure.
[0033] 3. “Measurement” is mainly divided into measuring the deviation of the main structure and the relationship between the axis, control line and the entry and exit of the curtain wall.
[0034] ① Measure the main structure: measure the deviation of the main structure axis and elevation line and make timely adjustments.
[0035] ② Measure the relationship between the axis line, control line and the entry and exit of the curtain wall: After measuring the axis line and floor height, determine its entry and exit relationship with the finished surface of the curtain wall according to the construction drawings.
[0036] 4. "Positioning" is mainly divided into post-embedded parts positioning and keel positioning.
[0037] ① Determine the position of post-embedded parts: Determine the position of horizontal post-embedded parts according to the construction drawings and the horizontal elevation line on site.
[0038] ② Determine the position of the keel: According to the curtain wall grid diagram, the axis position at the corner can be divided and positioned between the two corner points. First determine the vertical keel, then the horizontal keel. Each vertical keel and horizontal keel of each facade must be marked and marked.
[0039] Step 2: Determination of curtain wall dividing line and keel line Determine the corner position and construct the corner vertical line. Then divide the grid between the two corner points according to the grid size, connect the upper and lower lines to form an overall control network. According to the distance between the surface line of the drawing and the keel line, the keel line is reversed inwards as the basis for installing the keel. Step 3: Post-embedded plate and adapter construction At the buried plate mark, the rear buried plate is constructed and the adapter is fixed on the rear buried plate; the end of the adapter is provided with a long hole; the rear buried plate includes a side buried plate, a top buried template and a bottom buried template. When installing the buried plate, the main steps include measuring and laying out → positioning and drilling → hole cleaning → screw installation → rear buried part fixing → nut tightening.
[0040] Step 4: Keel assembly The curtain wall keel is divided into multiple keel units according to the overall control network, and the keel units are assembled and hoisted to the corresponding points and connected with the adjustment holes of the adapter by bolts. The keel unit includes a column 1 and a crossbeam 2. The columns between adjacent keel units are connected by inserts, and expansion joints are reserved; a U-shaped seat is fixed on the side of the column, and the cross keel is fixed in the U-shaped seat by bolts.
[0041] Adjacent keel units are connected vertically by steel inserts 5 and horizontally by U-shaped connecting seats; the columns are connected to the adapters by bolts, and the adapters are connected to the post-embedded parts by welding; the adapters 6 are provided with long holes in the vertical direction of the curtain wall and long holes in the horizontal direction. After the columns are connected to the adapters 6, the components of the columns and the adapters 6 can be adjusted forward and backward.
[0042] Column 1 is fixed to the channel steel. The upper part of column 1 is connected to the horizontal steel plug opening of steel column 1 for hoisting. The upper horizontal opening is used to hang the curtain wall. The lower part is fixed with plugs. The main force-bearing part is on the upper part of the glass curtain wall. The upper concrete structure beam bears the main force of the glass curtain wall, and the lower part will bear the lateral force of the glass curtain wall. The plug of steel column 1 is welded and fixed to the three sides of the rear embedded parts. According to the axis and elevation of the main beam, the elevation deviation of column 1 is adjusted to no more than 3mm, the front and rear deviation of the axis is adjusted to no more than 2mm, and the left and right deviation is adjusted to no more than 3mm; noise-proof and fire-proof rubber gaskets are fixed between column 1 and channel steel to reduce the noise generated when the curtain wall moves and prevent damage caused by rigid connections.
[0043] The installation of curtain wall column 1 can be carried out after the installation verification of embedded parts is completed, the pull-out test is qualified and the concealed acceptance is carried out. The steel insert is set on the inner side of the upper column 1 and fixed by bolts; a sleeve is set on the inner side of the lower column 1, and the insert is set in the sleeve and fixed on the rear embedded plate. When implementing, first check whether the size of the main beam and the processing hole position are correct according to the construction drawing, and then install the column 1 insert on the inner side of the steel column 1. The column 1 and the steel insert are fixed with M12 stainless steel bolts, the verticality and horizontality of the column 1 are adjusted, and then the insert is welded and fixed to the embedded plate to make the final fixed position.
[0044] The curtain wall columns 1 are connected with each other through inserts, and expansion joints are reserved. All hard contacts are connected with elasticity to improve the anti-seismic performance of the curtain wall and eliminate expansion noise. It is ensured that under the action of temperature, settlement and other external forces, it can expand and contract relatively, absorb deformation, and ensure that the column 1 is not damaged.
[0045] Column 1 is installed in a plug-in manner with the horizontal connection. Both sides of the steel beam are fixed with steel inserts and 3 m8*130 stainless steel bolts. A notch is opened in the front section of the connecting seat to facilitate the fixation of the beam. Then the inserts and the beam are fixed, and the steel inserts are used to extend and retract with column 1.
[0046] Step 5: Interlayer fire protection installation A fireproof structure is constructed between the curtain wall keel and the interlayer floor 8. The fireproof structure is supported by fireproof rock wool and an external galvanized steel plate, and is sealed after construction. The fireproof structure includes an interlayer fireproof structure 9 and a transverse fireproof structure 10. The interlayer fireproof structure is arranged between the interlayer floor and the curtain wall body and fixed on the adapter 6. The transverse fireproof structure is L-shaped, and its two ends are respectively fixed between the curtain wall body and the transverse partition wall.
[0047] Step 6: Glass panel and backing plate installation The backing plate is fixed on the inner side of the keel frame; after the glass panel 3 is manufactured in the factory, it is transported to the construction site, a fireproof rubber pad is placed between the glass panel 3 and the keel frame, and a sealant is added to fix the glass panel 3 on the keel frame; Step 7: Install the decorative cover First, waterproof and seal the vertical line installation area, and then buckle the decorative cover 4 onto the glass panel 3.
[0048] This embodiment has the following characteristics: 1. Improved construction accuracy and efficiency: Through the detailed construction layout steps, including the four links of "checking", "leading", "measuring" and "determining", the accuracy and efficiency of curtain wall construction are ensured. This method not only reduces construction errors, but also shortens the construction period and improves the overall construction efficiency.
[0049] 2. Enhanced the stability of the curtain wall structure: This method ensures the stability and integrity of the curtain wall structure through precise keel positioning and connection, as well as reasonable core and U-shaped connection seat design. This stability not only improves the curtain wall's wind pressure resistance, earthquake resistance and other performance, but also enhances the curtain wall's safety and durability.
[0050] 2. Improved the sealing and fireproofing of the curtain wall: During the interlayer fireproofing installation and glass panel installation, this method uses fireproof rock wool, galvanized steel plate support, fireproof rubber pads and other fireproof materials, and adds sealant to effectively improve the sealing and fireproofing of the curtain wall. This design not only meets the building safety requirements, but also improves the thermal insulation and sound insulation of the curtain wall.
[0051] , Optimized the curtain wall construction process: This method divides curtain wall construction into multiple clear and orderly steps, each of which has clear tasks and operation requirements. This process-based construction method not only facilitates construction management and quality control, but also improves the operating efficiency and skill level of construction personnel.
[0052] , Enhanced the adaptability and flexibility of the curtain wall: This method is particularly suitable for the inverted truncated fireproof glass curtain wall structure, solving the problem that the traditional construction method cannot adapt to such complex structures. At the same time, this method also improves the curtain wall's ability to adapt to external forces such as temperature and settlement by reserving expansion joints and using elastic connections, thereby ensuring the curtain wall's stability and safety.
[0053] In summary, the inverted frustum fireproof glass curtain wall assembly construction method shows remarkable beneficial effects in terms of construction accuracy, structural stability, sealing and fire resistance, construction process, adaptability and flexibility, etc., which provides help for people to implement the inverted frustum fireproof glass curtain wall assembly construction. This method effectively solves the problem that traditional construction methods are not suitable for inverted frustum fireproof glass curtain wall structures through the steps of fine construction layout, determination of curtain wall dividing lines and keel lines, post-construction embedded plates and adapters 6, keel assembly, interlayer fire protection installation, glass panel 3 and backing plate installation, and decorative cover installation. It improves construction efficiency, ensures the stability, sealing and fire resistance of the curtain wall structure, and provides an efficient and reliable solution for the complex curtain wall construction of modern buildings.
[0054] Embodiment 2, this embodiment further includes an inner circle curtain wall structure 11 and an outer circle curtain wall structure 12 .
[0055] like Figure 3 As shown in the figure, the main body of the floor is between the inner curtain wall structure 11 and the outer curtain wall structure 12. The inner curtain wall structure and the outer closing structure are both provided with closing structures above and below, and the closing structures include closing members 14 and closing seats 13. One side of the closing seat 13 is fixedly connected to the main body of the building, and the other side is connected to the lower part of the keel unit. The glass panel 3 is combined and connected to the outer side of the closing seat 13 through the closing member 14.
[0056] This embodiment not only improves the aesthetics of the curtain wall through the closing structure, but also ensures the close connection and transition between the curtain wall and the main body of the building, thereby enhancing the stability and durability of the overall structure.
[0057] Embodiment 3: This embodiment further illustrates the combined structure between the cross beam and the column.
[0058] In this embodiment, Figure 5-7 As shown in the figure, the cross beam 2 is connected to the column 1 through an adjusting member, which includes a central clamp body 15, a first clamp seat 16, a second clamp seat 17, a limiting track 18, a limiting slide plate 19 and an adjusting plate 20; the central clamp body 15 is a U-shaped structure, and the first clamp seat 16 and the second clamp seat 17 are hinged on both sides of its opening, and the first clamp seat 16 and the second clamp seat 17 both have an outward U-shaped opening so that the cross beam can be fixed therein, and the limiting track 18 is arranged on the back side of the first clamp seat 16 and the second clamp seat 17, and the limiting slide plate 19 is adapted to be mounted therein, one end of the adjusting plate 20 is hinged to the end of the limiting slide plate 19, and an adjusting flat hole 21 is arranged on the other side, and the adjusting plate is assembled on the column by bolts, and the limiting slide plate 19 is used to slide and swing so that it can adapt to the angle change of the clamp seat, and the stability of the adjusting plate is used to lock it.
[0059] The central clamp body 15 is provided with connection holes on both sides and the back side, wherein the connection holes on the back side correspond to the adjustment flat holes, and after bolts are applied, the central clamp body 15 is assembled with the column 1. The main bodies of the first clamp seat 16 and the second clamp seat 17 are provided with long holes so that the cross beam can adjust the length thereof.
[0060] The connection angle between the crossbeam and the column 1 can be adjusted by the adjusting piece, that is, the central clamp 15 is fixedly assembled on the column 1, and the first clamp seat 16 and the second clamp seat 17 on both sides thereof can adjust the angle relative to each other and lock them after the adjustment is completed, so that the structure of the crossbeam and the column 1 can form an arc-shaped curved surface, which is convenient for the assembly of the crossbeam and its angle adjustment, simple to operate, and improves the combination efficiency between the keel units.
[0061] The embodiments of the present invention described above do not constitute a limitation on the protection scope of the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the claims of the present invention.
Claims
1. An assembled construction method of an inverted truncated table fireproof glass curtain wall, characterized in that: The method comprises the following steps: Step 1: Construction layout Take the elevation line and axis of each floor as the reference line, measure the auxiliary axis from the original axis control point and elevation point, and make auxiliary marks on the corresponding level; determine the position of the horizontal post-embedded parts according to the construction drawings and the horizontal elevation line on site, and make embedded plate marks; determine the position of the vertical keel and the horizontal keel according to the curtain wall grid drawing, and make keel marks; Step 2: Determination of curtain wall dividing line and keel line Determine the corner position and construct the corner vertical line. Then divide the grid between the two corner points according to the grid size, connect the upper and lower lines to form an overall control network. According to the distance between the surface line of the drawing and the keel line, the keel line is reversed inwards as the basis for installing the keel. Step 3: Post-embedded plate and adapter construction At the embedded plate mark, a rear embedded plate is constructed, and an adapter is fixed on the rear embedded plate; a long hole is provided at the end of the adapter; Step 4: Keel assembly The curtain wall keel is divided into multiple keel units according to the overall control network, and the keel units are assembled and hoisted to the corresponding points and connected with the adjustment holes of the adapter bolts; adjacent keel units are connected vertically through steel inserts and horizontally through U-shaped connection seats; Step 5: Interlayer fire protection installation A fireproof structure is constructed between the curtain wall keel and the interlayer floor slab. The fireproof structure is supported by fireproof rock wool and galvanized steel plates, and is sealed after construction is completed; Step 6: Glass panel and backing plate installation The backing plate is fixed on the inner side of the keel frame. After the glass panel is manufactured in the factory, it is transported to the construction site. A fireproof rubber pad is placed between the glass panel and the keel frame, and sealant is added to fix the glass panel on the keel frame. Step 7: Install the decorative cover First, waterproof and seal the vertical line laying area, and then buckle the decorative cover onto the glass panel.
2. The method for assembling the inverted truncated cone fireproof glass curtain wall according to claim 1 is characterized in that: The keel unit comprises columns and beams. The columns between adjacent keel units are connected by inserts and expansion joints are reserved. A U-shaped seat is fixed on the side of the column, and the transverse keel is fixed in the U-shaped seat by bolts.
3. The method for assembling the inverted truncated cone fireproof glass curtain wall according to claim 1 is characterized in that: The steel insert is arranged on the inner side of the upper column and fixed by bolts; a socket is arranged on the inner side of the lower column, the insert is sleeved in the socket and fixed on the rear embedded plate.
4. The method for assembling the inverted truncated cone fireproof glass curtain wall according to claim 1 is characterized in that: The fire protection structure includes an interlayer fire protection structure and a transverse fire protection structure. The interlayer fire protection structure is arranged between the interlayer floor and the curtain wall body and fixed on the adapter; the transverse fire protection structure is L-shaped, and its two ends are respectively fixed between the curtain wall body and the transverse partition wall.
5. The method for assembling the inverted truncated table fireproof glass curtain wall according to claim 1 is characterized in that: The post-embedded plate comprises a side embedded plate, a top embedded template and a bottom embedded template.
6. The method for assembling the inverted truncated cone fireproof glass curtain wall according to claim 1 is characterized in that: It also includes an inner circle curtain wall structure and an outer circle curtain wall structure; the main body of the floor is between the inner circle curtain wall structure and the outer circle curtain wall structure.
7. The method for assembling the inverted truncated cone fireproof glass curtain wall according to claim 6 is characterized in that: The inner circle curtain wall structure and the outer circle closing structure are both provided with closing structures above and below. The closing structure includes a closing piece and a closing seat. One side of the closing seat is fixedly connected to the building body, and the other side is connected to the lower part of the keel unit. The glass panel is combined and connected to the outer side of the closing seat through the closing piece.
8. The method for assembling the inverted truncated cone fireproof glass curtain wall according to claim 1 is characterized in that: The crossbeam and the column are connected by an adjusting member, and the adjusting member includes a central clamping body, a first clamping seat, a second clamping seat, a limiting track, a limiting slide plate and an adjusting plate; the central clamping body is a U-shaped structure, and the first clamping seat and the second clamping seat are hinged on both sides of its opening, and the first clamping seat and the second clamping seat both have outward U-shaped openings so that the crossbeam can be fixed therein. A limiting track is arranged on the back side of the first clamp seat and the second clamp seat, and the limiting slide plate is adapted to be mounted therein. One end of the adjustment plate is hinged to the end of the limiting slide plate, and an adjustment flat hole is arranged on the other side.
9. The method for assembling the inverted truncated cone fireproof glass curtain wall according to claim 8, characterized in that: Both sides and the back side of the central clamp are provided with connection holes, wherein the connection holes on the back side correspond to the adjustment flat holes, and the central clamp is combined with the column after bolts are applied.
10. The method for assembling the inverted truncated cone fireproof glass curtain wall according to claim 8, characterized in that: The main bodies of the first clamping seat and the second clamping seat are both provided with long holes so that the cross beam can adjust the length thereof.