Leakage-proof device of desulfurizing tower

By designing a leak-proof device for desulfurization tower, a tension between the built-in beam plate and the arc plate is formed by using fastening bolts and nuts to form a tension between the built-in beam plate and the arc plate to clamp the outer wall of the desulfurization tower, the leakage problem caused by the leakage point in the lower area of ​​the desulfurization tower is solved, and the leakage problem is quickly achieved. Effective leakage treatment ensures production and environmental protection indicators.

CN119412497AInactive Publication Date: 2025-02-11HULUNBUIR ANTAI THERMAL POWER CO LTD ZHALANTUN THERMAL POWER PLANT
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411553215.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-01
Publication Date
2025-02-11
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The welds in the lower area of ​​the desulfurization tower often have leakage points, resulting in leakage of ammonium sulfate solution and polluting the environment. The existing technology lacks rapid treatment devices, which affects production progress and may lead to excessive environmental protection indicators.

Method used

A desulfurization tower leakage prevention device is designed, including leakage prevention member and fixing member. The leakage prevention member is composed of an external pressure plate structure and a sealing member. The fixing member is composed of a built-in beam plate and a locking structure, and is built-in by fastening bolts and nuts. A tensile force is formed between the beam plate and the arc plate to clamp the outer wall of the desulfurization tower and block the leakage area.

Benefits of technology

The device can quickly block the leakage area, prevent media leakage, ensure the safe and stable operation of the desulfurization tower, reduce processing time, and avoid exceeding environmental protection indicators.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119412497A_ABST
    Figure CN119412497A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of desulfurizing towers, in particular to a desulfurizing tower leakproof device, which comprises a leakproof component, an outer pressure plate structure and a sealing element arranged at the bottom of the outer pressure plate structure; the fixing component comprises a built-in beam plate and a locking structure arranged on the inner wall of the built-in beam plate, when leakage of leakage holes occurs in the desulfurization tower, the outer pressing plate structure is fixed outside the desulfurization tower, tension is formed through the locking structure, the outer pressing plate structure and the built-in beam plate clamp the outer wall of the desulfurization tower from the inner side and the outer side, and the outer wall of the desulfurization tower is fixed through the locking structure. The outer pressing plate structure tightly covers the leakage position of the outer wall of the desulfurizing tower for leaking stoppage, meanwhile, the sealing piece is fixed between the outer pressing plate structure and the outer wall of the desulfurizing tower, and the sealing piece prevents media in the tower from continuously leaking from a gap between the outer pressing plate structure and the outer wall of the desulfurizing tower. Leakage points can be quickly treated on line through the built-in beam plate and the arc-shaped plate which are machined in advance, and safe and stable operation of the desulfurizing tower is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of desulfurization towers, in particular to a desulfurization tower anti-leakage device. Background Art

[0002] The desulfurization tower is an important device for boiler flue gas treatment. The tower body is generally a steel-lined glass clay flake structure, which is built by welding annular steel plates in circles. Due to defects in the welding quality of the welds in the tower and the anti-corrosion quality of the welds, and the fact that the medium in the tower is an extremely corrosive ammonium sulfate solution, which mainly exists in the lower area of ​​the tower, the welds in the lower area of ​​the desulfurization tower often leak. Due to the strong corrosiveness of the leaked medium, the leakage point will expand rapidly, causing a large amount of medium in the tower to leak along the outer tower wall (the leakage point is generally two or three meters away from the bottom of the tower), polluting the environment.

[0003] Since the existing technology does not have a rapid treatment device for desulfurization tower leakage, when the desulfurization tower leaks, in order to ensure the safety of personnel and equipment, the only way to deal with it is to stop the operation of the desulfurization tower, which seriously affects the production progress. At the same time, the treatment time is too long, which will cause environmental protection indicators to exceed the standard. Summary of the invention

[0004] In view of the problems existing in the prior art, the present invention is proposed.

[0005] In order to solve the above technical problems, the present invention provides the following technical solutions: a desulfurization tower anti-leakage device, comprising:

[0006] a leakage-proof component, comprising an outer pressure plate structure and a sealing member disposed at the bottom of the outer pressure plate structure; and

[0007] The fixing component comprises an internal beam plate and a locking structure arranged on the inner wall of the internal beam plate.

[0008] As a preferred solution of the desulfurization tower anti-leakage device of the present invention, the outer pressure plate structure comprises an arc-shaped plate, and a mounting hole is opened in the middle of the arc-shaped plate.

[0009] As a preferred solution of the desulfurization tower anti-leakage device of the present invention, the sealing member is annular, and the outer diameter of the arc plate is larger than the outer diameter of the sealing member.

[0010] As a preferred solution of the desulfurization tower anti-leakage device of the present invention, an annular groove is provided on the top of the mounting hole, and the annular groove is concentric with the mounting hole.

[0011] As a preferred solution of the desulfurization tower leakage prevention device of the present invention, the locking structure includes a fastening bolt arranged on the inner wall of the mounting hole, and the top outer wall of the fastening bolt is provided with an embedded ring, and the outer diameter of the embedded ring is the same as the inner diameter of the annular groove.

[0012] As a preferred solution of the desulfurization tower anti-leakage device of the present invention, the outer diameter of the fastening bolt is the same as the inner diameter of the mounting hole, and the outer wall of the built-in beam plate is provided with a through hole for the fastening bolt to pass through.

[0013] As a preferred solution of the desulfurization tower anti-leakage device of the present invention, the bottom end of the fastening bolt passes through the built-in beam plate, and the top end of the fastening bolt is located above the arc plate.

[0014] As a preferred solution of the desulfurization tower anti-leakage device of the present invention, a nut is arranged at the bottom of the fastening bolt, a gasket is arranged on the outer wall of the fastening bolt, and the inner diameter of the gasket is the same as the outer diameter of the embedded ring.

[0015] As a preferred solution of the desulfurization tower leakage prevention device described in the present invention, the inner wall of the gasket is provided with a sealing filler, the top of the sealing filler is in contact with the embedded ring, the bottom of the sealing filler is in contact with the annular groove, and the inner wall of the sealing filler is in contact with the fastening bolts.

[0016] As a preferred solution of the desulfurization tower anti-leakage device of the present invention, the sealing filler is an acid- and alkali-resistant sealing material.

[0017] Beneficial effects of the present invention: The device utilizes fastening bolts and nuts to form tension between the built-in beams and the arc-shaped plates. The built-in beams and the arc-shaped plates clamp the outer wall of the desulfurization tower, thereby blocking the leakage area and preventing leakage. The leakage points can be quickly processed online through the built-in beams and arc-shaped plates processed in advance, thereby ensuring the safe and stable operation of the desulfurization tower. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for describing the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work. Among them:

[0019] Figure 1 It is a schematic diagram of the overall structure of the present invention.

[0020] Figure 2 It is an enlarged schematic diagram of the overall structure A in the present invention.

[0021] Figure 3 It is a top view of the overall structure of the present invention. DETAILED DESCRIPTION

[0022] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are described in detail below in conjunction with the accompanying drawings.

[0023] In the following description, many specific details are set forth to facilitate a full understanding of the present invention, but the present invention may also be implemented in other ways different from those described herein, and those skilled in the art may make similar generalizations without violating the connotation of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed below.

[0024] Secondly, the term "one embodiment" or "embodiment" as used herein refers to a specific feature, structure, or characteristic that may be included in at least one implementation of the present invention. The term "in one embodiment" that appears in different places in this specification does not necessarily refer to the same embodiment, nor does it refer to a separate or selective embodiment that is mutually exclusive with other embodiments.

[0025] Example 1, reference Figures 1 to 3 , which is the first embodiment of the present invention, provides a desulfurization tower anti-leakage device, comprising:

[0026] The anti-leakage component 100 includes an outer pressure plate structure 101 and a seal 102 disposed at the bottom of the outer pressure plate structure 101. After leakage occurs, the outer pressure plate structure 101 will be fixed to the leakage hole on the outer wall of the desulfurization tower to block the leakage hole from the outside. Figure 1 As shown, k-1 is the outer wall of the desulfurization tower where leakage occurs, k-2 is the leakage hole, the outer pressure plate structure 101 tightly covers the leakage of the outer wall of the desulfurization tower to stop the leakage, and at the same time, the seal 102 is fixed between the outer pressure plate structure 101 and the outer wall of the desulfurization tower. The seal 102 prevents the medium in the tower from continuing to leak from the gap between the outer pressure plate structure 101 and the outer wall of the desulfurization tower, thereby improving the anti-leakage effect; and

[0027] The fixing member 200 includes an internal beam plate 201 and a locking structure 202 arranged on the inner wall of the internal beam plate 201. The internal beam plate 201 is placed into the desulfurization tower through the leakage hole, and the desulfurization tower is connected to the external pressure plate structure 101 by using the locking structure 202. The internal beam plate 201 is fixed inside the desulfurization tower, and the external pressure plate structure 101 is fixed outside the desulfurization tower. The locking structure 202 forms a tensile force, and the external pressure plate structure 101 and the internal beam plate 201 clamp the outer wall of the desulfurization tower from the inside and outside to plug the leak. The fixing structure is simple, the fixing method is convenient, and the plugging time can be saved.

[0028] Specifically, when a leakage hole appears in the desulfurization tower, the external pressure plate structure 101 is fixed to the outside of the desulfurization tower, and a tensile force is formed by the locking structure 202. The external pressure plate structure 101 and the internal beam plate 201 clamp the outer wall of the desulfurization tower from the inside and outside. The external pressure plate structure 101 tightly covers the leakage on the outer wall of the desulfurization tower to stop the leakage. At the same time, the seal 102 is fixed between the external pressure plate structure 101 and the outer wall of the desulfurization tower. The seal 102 prevents the medium in the tower from continuing to leak from the gap between the external pressure plate structure 101 and the outer wall of the desulfurization tower.

[0029] Example 2, reference Figures 1 to 3 , which is the second embodiment of the present invention. Different from the previous embodiment, the external pressure plate structure 101 includes an arc-shaped plate 101a. The arc of the arc-shaped plate 101a is processed to be close to the arc of the outside of the desulfurization tower, and the arc-shaped plate 101a and the outer wall of the desulfurization tower are fitted as much as possible. A mounting hole 101b is opened in the middle of the arc-shaped plate 101a, and the mounting hole 101b is a through hole.

[0030] Furthermore, the seal 102 is annular, and the outer diameter of the arc plate 101a is larger than the outer diameter of the seal 102. When fixed, the arc plate 101a presses the seal 102 between the arc plate 101a and the outer wall of the desulfurization tower. An annular groove 101c is provided at the top of the mounting hole 101b, and the annular groove 101c is concentric with the mounting hole 101b. The arc plate 101a provides an annular groove 101c at the top of the mounting hole 101b, and the annular groove 101c and the mounting hole 101b together form a step hole.

[0031] Furthermore, the locking structure 202 includes a fastening bolt 202a arranged on the inner wall of the mounting hole 101b, and a ring 202b is arranged on the top outer wall of the fastening bolt 202a. The outer diameter of the ring 202b is the same as the inner diameter of the annular groove 101c, and the outer diameter of the fastening bolt 202a is the same as the inner diameter of the mounting hole 101b. The outer wall of the built-in beam plate 201 is provided with a through hole for the fastening bolt 202a to pass through. The bottom end of the fastening bolt 202a passes through the built-in beam plate 201, and the top end of the fastening bolt 202a is fixed to the inner wall of the built-in beam plate 201. Located above the arc plate 101a, a nut 203 is provided at the bottom of the fastening bolt 202a. Preferably, the nut 203 can be fixed to the bottom of the built-in beam plate 201. The fastening bolt 202a is tightened by the fastening bolt 202a and the nut 203 to form a tension between the built-in beam plate 201 and the arc plate 101a. The built-in beam plate 201 and the arc plate 101a clamp the outer wall of the desulfurization tower. Preferably, the built-in beam plate 201 can be processed in various sizes in advance, and the size of the leakage hole that is suddenly broken has been used.

[0032] Specifically, when a leak occurs in the desulfurization tower, the built-in beam plate 201 is placed into the desulfurization tower through the leakage hole, and the arc plate 101a is placed on the outside of the desulfurization tower at a position corresponding to the built-in beam plate 201. The fastening bolts 202a and nuts 203 are used to tighten the fastening bolts 202a to form a tensile force between the built-in beam plate 201 and the arc plate 101a. The built-in beam plate 201 and the arc plate 101a clamp the outer wall of the desulfurization tower, thereby blocking the leakage area and preventing leakage.

[0033] Example 3, reference Figures 1 to 3 , which is the third embodiment of the present invention. Different from the previous embodiment, a gasket 204 is provided on the outer wall of the fastening bolt 202a. The inner diameter of the gasket 204 is the same as the outer diameter of the embedded ring 202b. A sealing filler 205 is provided on the inner wall of the gasket 204. The top of the sealing filler 205 contacts the embedded ring 202b. The bottom of the sealing filler 205 contacts the annular groove 101c. The inner size of the annular groove 101c is the same as the size of the embedded ring 202b. The outer diameter of the embedded ring 202b is the same as the inner diameter of the gasket 204. When the fastening bolt 202a is locked, the bolt is pressed down to drive the embedded ring 202b into the gasket 204. The bolt continues to be pressed down, and the brim of the bolt top presses the gasket 204. The gasket 204, the embedded ring 202b and the annular groove 101c cooperate to form an accommodating space. The inner wall of the sealing filler 205 contacts the fastening bolt 202a. The sealing filler Material 205 is an acid- and alkali-resistant sealing material. The sealing filler 205 is placed in the accommodating space formed by the gasket 204, the embedded ring 202b and the annular groove 101c. The connection between the arc plate 101a and the fastening bolt 202a is sealed again to prevent the medium in the desulfurization tower from leaking from here. Preferably, the sealing filler 205 can be an acid- and alkali-resistant polymer material to prevent corrosion from the medium inside the desulfurization tower, extend the service life of the device, and further improve the anti-leakage effect. Preferably, the embedded ring 202b is embedded in the gasket 204 to extrude the sealing filler 205 in the annular groove 101c, and the sealing filler 205 is compressed to improve the sealing effect. Since the sealing filler 205 may have errors in the processing size, gaskets 204 of various sizes can be processed in advance to prevent the sealing filler 205 from being too short and the embedded ring 202b from being unable to compress the sealing filler 205.

[0034] Specifically, when tightening the fastening bolt, the downward pressure of the bolt will drive the embedded ring into the gasket. The bolt continues to be pressed downward, and the brim of the bolt top will press the gasket. The gasket, the embedded ring and the annular groove cooperate to form an accommodating space. The sealing filler is placed in the accommodating space formed by the gasket, the embedded ring and the annular groove. The connection between the arc plate and the fastening bolt is sealed again to prevent the medium in the desulfurization tower from leaking from here.

[0035] Importantly, it should be noted that the construction and arrangement of the present application shown in a plurality of different exemplary embodiments are only exemplary. Although only a few embodiments are described in detail in this disclosure, it should be readily understood by those who refer to this disclosure that many modifications are possible (e.g., the size, scale, structure, shape and proportion of various elements, and parameter values ​​(e.g., temperature, pressure, etc.), installation arrangement, use of materials, color, directional changes, etc.) without substantially departing from the novel teachings and advantages of the subject matter described in the application. For example, the element shown as integrally formed can be composed of multiple parts or elements, the position of the element can be inverted or otherwise changed, and the nature or number or position of the discrete element can be changed or changed. Therefore, all such modifications are intended to be included in the scope of the present invention. The order or sequence of any process or method steps can be changed or reordered according to alternative embodiments. In the claims, any "device plus function" clause is intended to cover the structure of performing the function described herein, and is not only structurally equivalent but also equivalent structure. Without departing from the scope of the present invention, other replacements, modifications, changes and omissions can be made in the design, operating conditions and arrangement of the exemplary embodiments. Therefore, the invention is not limited to a specific embodiment, but extends to numerous modifications still falling within the scope of the appended claims.

[0036] Additionally, in order to provide a concise description of exemplary embodiments, all features of an actual embodiment (ie, those features that are not relevant to the best mode presently contemplated for carrying out the invention or those that are not relevant to implementing the invention) may not be described.

[0037] It will be appreciated that in the development of any actual implementation, as in any engineering or design project, numerous implementation-specific decisions may be made. Such a development effort may be complex and time-consuming, but will be a routine task of design, fabrication, and production for those of ordinary skill having the benefit of this disclosure without undue experimentation.

[0038] It should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solutions of the present invention may be modified or replaced by equivalents without departing from the spirit and scope of the technical solutions of the present invention, which should all be included in the scope of the claims of the present invention.

Claims

1. A desulfurization tower anti-leakage device, characterized in that: include, A leakage prevention component (100) comprising an outer pressure plate structure (101) and a sealing member (102) arranged at the bottom of the outer pressure plate structure (101); and The fixing component (200) comprises a built-in beam plate (201) and a locking structure (202) arranged on the inner wall of the built-in beam plate (201).

2. The desulfurization tower anti-leakage device according to claim 1, characterized in that: The outer pressure plate structure (101) comprises an arc-shaped plate (101a), and a mounting hole (101b) is provided in the middle of the arc-shaped plate (101a).

3. The desulfurization tower anti-leakage device according to claim 2, characterized in that: The sealing member (102) is annular, and the outer diameter of the arc-shaped plate (101a) is greater than the outer diameter of the sealing member (102).

4. The desulfurization tower anti-leakage device according to claim 3, characterized in that: An annular groove (101c) is provided at the top of the mounting hole (101b), and the annular groove (101c) is concentric with the mounting hole (101b).

5. The desulfurization tower anti-leakage device according to claim 4, characterized in that: The locking structure (202) comprises a fastening bolt (202a) arranged on the inner wall of the mounting hole (101b), and the top outer wall of the fastening bolt (202a) is provided with an insert ring (202b), and the outer diameter of the insert ring (202b) is the same as the inner diameter of the annular groove (101c).

6. The desulfurization tower anti-leakage device according to claim 5, characterized in that: The outer diameter of the fastening bolt (202a) is the same as the inner diameter of the mounting hole (101b), and a through hole for the fastening bolt (202a) to pass through is provided on the outer wall of the built-in beam plate (201).

7. The desulfurization tower anti-leakage device according to claim 6, characterized in that: The bottom end of the fastening bolt (202a) passes through the built-in beam plate (201), and the top end of the fastening bolt (202a) is located above the arc-shaped plate (101a).

8. The desulfurization tower anti-leakage device according to claim 7, characterized in that: A nut (203) is provided at the bottom of the fastening bolt (202a), and a gasket (204) is provided on the outer wall of the fastening bolt (202a). The inner diameter of the gasket (204) is the same as the outer diameter of the insert ring (202b).

9. The desulfurization tower anti-leakage device according to claim 8, characterized in that: The inner wall of the gasket (204) is provided with a sealing filler (205), the top of the sealing filler (205) is in contact with the insert ring (202b), the bottom of the sealing filler (205) is in contact with the annular groove (101c), and the inner wall of the sealing filler (205) is in contact with the fastening bolt (202a).

10. The desulfurization tower anti-leakage device according to claim 9, characterized in that: The sealing filler (205) is an acid- and alkali-resistant sealing material.

Citation Information

Cited By

  • Online leaking stoppage device for desulfurizing tower

    CN122305225A