High-temperature and high-pressure dynamic simulation erosion test system

By designing a dynamic simulation erosion test system for high temperature and high pressure, the simulation problem of erosion wear problems in oil and gas fields is solved, and the high simulation and experimental research of complex erosion conditions are achieved, which improves the refinement and scientificity of the research.

CN119413638APending Publication Date: 2025-02-11CNOOC ENERGY TECHNOLOGY & SERVICES LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411525856.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-30
Publication Date
2025-02-11

AI Technical Summary

Technical Problem

There are serious erosion and wear problems in oil and gas fields, resulting in equipment failure and safety hazards. It is difficult for the existing technology to effectively simulate complex erosion conditions.

Method used

A high-temperature and high-pressure dynamic simulation erosion test system is designed, including feeding unit, erosion simulation unit, environmental simulation unit and control unit, which can simulate the erosion of pipes by high-speed fluid carrying solid particles, and has high-temperature and high-pressure, multi-phase fluid simulation capability.

Benefits of technology

Real simulation of oil and gas field equipment in high temperature and high pressure erosion environment is achieved, and the factors affecting erosion can be studied more comprehensively, the refinement and scientificity of the experiments are improved, and the understanding of erosion wear behavior is enhanced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119413638A_ABST
    Figure CN119413638A_ABST
Patent Text Reader

Abstract

The invention provides a high-temperature and high-pressure dynamic simulation erosion test system, and relates to oil and gas field pipe erosion wear experiment research, the system comprises a feeding unit, an erosion simulation unit, an environment simulation unit and a control unit, the feeding unit comprises a main pipeline and a sand adding assembly, the sand adding assembly comprises a sand storage device, a sand mixing mechanism connected with the sand storage device and a sand outlet pipeline connected to the sand mixing mechanism. The erosion simulation unit comprises an erosion chamber and an adjustable spray head, and the spray head is connected with a main pipeline through a hose; the environment simulation unit comprises a clamping device, a pressurizing assembly and a temperature adjusting assembly, the clamping device comprises a kettle body, the temperature adjusting assembly is arranged on the outer side of the kettle body, a middle shaft is arranged in the kettle body, one end of the middle shaft is connected with the pressurizing assembly, the other end of the middle shaft extends into the erosion chamber, and a sample piece to be eroded can be installed at the end of the middle shaft; and the feeding unit, the erosion simulation unit and the environment simulation unit are all in communication connection with the control unit. According to the invention, high simulation of real erosion working conditions can be realized.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of experimental research on erosion and wear of oil and gas field pipes, in particular to a high-temperature and high-pressure dynamic simulation erosion test system. Background Art

[0002] The erosion and wear of gathering and transportation pipes is a surface damage phenomenon caused by the fluid carrying solid particles flowing through the pipe surface. The factors affecting this phenomenon mainly include the metal properties of the pipe itself, such as hardness, ductility, etc.; the viscosity of the fluid and the shape, size, hardness, speed and angle of impact on the metal surface of the solid particles it carries. In addition, studies have shown that the ambient temperature and pH are also important influencing factors.

[0003] More than 70% of oil and gas wells in the western part of the South China Sea have sand production to varying degrees, and the current mechanical sand control methods can only prevent large particles from entering the wellbore. Erosion and wear are still one of the main forms of equipment failure. Various types of downhole tool adapters, elbows, Christmas trees, nozzles, and surface manifolds have many failures caused by erosion and wear. High-speed fluids carrying solid particles will cause a significant decrease in the equipment's carrying capacity, and even worse, it will cause perforation of the pipe wall, causing serious safety hazards in production.

[0004] The erosion and wear of various metal materials of petroleum machinery in oil and gas fields is a complex behavior involving many influencing factors. Due to the nature of the metal materials themselves, it is difficult to come up with a universally applicable theory. Therefore, there is an urgent need for an erosion test system with complete functions that can highly simulate the actual erosion conditions on site, so as to enhance researchers' deeper understanding of erosion and wear behavior through more refined experimental research. Summary of the invention

[0005] The purpose of the present invention is to provide a high temperature and high pressure dynamic simulation erosion test system. The preferred technical solutions among the many technical solutions provided by the present invention can produce many technical effects as described below.

[0006] To achieve the above object, the present invention provides the following technical solutions:

[0007] The present invention provides a high-temperature and high-pressure dynamic simulation erosion test system, comprising a feeding unit, an erosion simulation unit, an environment simulation unit and a control unit, wherein:

[0008] The feeding unit comprises a main pipeline and a sand feeding assembly, wherein the sand feeding assembly comprises a sand storage device, a sand mixing mechanism connected to the sand storage device, and a sand outlet pipeline connected to the sand mixing mechanism, wherein the main pipeline can be connected to an air source, a liquid pump, a horizontal flow pump, and the sand outlet pipeline;

[0009] The erosion simulation unit comprises an erosion chamber and an adjustable nozzle, wherein the nozzle is arranged in the erosion chamber and connected to the main pipeline through a hose;

[0010] The environmental simulation unit includes a holder, a pressurizing component and a temperature regulating component. The holder includes a kettle body. The temperature regulating component is arranged on the outside of the kettle body. A central axis is arranged inside the kettle body. One end of the central axis is connected to the pressurizing component. The other end of the central axis extends into the erosion chamber. The end of the central axis can be used to mount the sample to be etched.

[0011] The feeding unit, the erosion simulation unit, and the environment simulation unit are all in communication connection with the control unit.

[0012] Preferably, the temperature regulating assembly comprises a heating sleeve and a temperature sensor, the heating sleeve is arranged on the outside of the kettle body, the temperature sensor is used to monitor the temperature of the kettle body, and the temperature sensor and the heating sleeve are both electrically connected to the control unit.

[0013] Preferably, the pressurizing component comprises a hydraulic oil storage tank and a hand pump connected to the hydraulic oil storage tank, the hand pump is pressurized by hydraulic oil, and the hand pump is connected to the kettle body through a high-pressure pipeline.

[0014] Preferably, the clamp further comprises a pressure cover, which can be connected to the end of the central axis, the sample to be etched is arranged between the central axis and the pressure cover, a hole structure is arranged at the center of the end face of the pressure cover, and the sample to be etched can be exposed from the hole structure.

[0015] Preferably, a nozzle support is provided in the erosion chamber, and the nozzle support includes an X-axis moving component, a Y-axis moving component and a rotating structure, wherein:

[0016] The X-axis moving assembly is installed at the bottom of the erosion chamber;

[0017] The Y-axis moving assembly is installed on the X-axis moving assembly;

[0018] The nozzle is connected to the rotating structure, and the rotating structure is installed on the Y-axis moving assembly;

[0019] The X-axis moving component, the Y-axis moving component, and the rotating structure are all electrically connected to the control unit.

[0020] Preferably, the sand storage device includes at least a first silo and a second silo that can operate alternately, the first silo and the second silo are both connected to a sand mixing mechanism, the first silo and the second silo are both provided with a variable frequency motor and a paddle rotor connected to the variable frequency motor, and the variable frequency motor is electrically connected to the control unit.

[0021] Preferably, it further comprises a sand collecting box, which is arranged at the bottom of the erosion chamber and is connected to the erosion chamber through a pipeline.

[0022] Preferably, the sand mixing mechanism comprises a sand mixing chamber, a sand mixing assembly and a sand mixing motor, wherein:

[0023] The sand mixing assembly is arranged in the sand mixing chamber, and the sand mixing motor is connected to the sand mixing assembly.

[0024] Preferably, it also includes a gas flow meter and a liquid flow meter, the gas flow meter and the liquid flow meter are used to monitor the gas flow and liquid flow in the main pipeline respectively, and the gas flow meter and the liquid flow meter are both electrically connected to the control unit.

[0025] Preferably, the erosion chamber is a sealed structure, comprising relatively arranged transparent observation windows.

[0026] The high-temperature and high-pressure dynamic simulation erosion test system provided by the present invention cooperates with a feeding unit, an erosion simulation unit, an environment simulation unit and a control unit. By setting the feeding unit to include a main pipeline and a sand adding component, the main pipeline can be connected to a gas source, a liquid pump, a horizontal flow pump and a sand outlet pipeline. It has the ability to simulate experiments on sand carrying volume, sand body type, sand body particle size, and erosion flow rate, and has the ability to conduct gas phase, liquid phase, gas-liquid two-phase, gas-carrying sand, liquid-carrying sand, and gas-liquid-solid three-phase erosion tests. By setting an adjustable nozzle, the system has the ability to simulate the erosion angle and erosion distance. By setting an environmental simulation unit including a clamp, a pressurizing component and a temperature regulating component 33, an erosion sample is installed at the end of the central axis of the clamp. By replacing the erosion sample, the system has the ability to simulate the eroded material. By setting a pressurizing component and a temperature regulating component, the system has the ability to simulate the pressure and temperature of the eroded steel. At the same time, the system has the ability to simulate factors such as the water content of the erosion gas and the erosion time. This high-temperature and high-pressure dynamic simulation erosion test system can meet the high-temperature and high-pressure erosion environment simulation of oil and gas fields, and can achieve a more comprehensive simulation of erosion influencing factors, and can carry out various types of erosion tests to achieve a high degree of simulation of real erosion conditions. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0028] Figure 1It is a structural schematic diagram of an embodiment of a high temperature and high pressure dynamic simulation erosion test system of the present invention;

[0029] Figure 2 yes Figure 1 Schematic diagram of the main structure;

[0030] Figure 3 yes Figure 1 A schematic diagram of the structure from another angle;

[0031] Figure 4 It is a schematic diagram of the structure of the clamp in the high temperature and high pressure dynamic simulation erosion test system of the present invention;

[0032] Figure 5 This is a working principle diagram of the high temperature and high pressure dynamic simulation erosion test system of the present invention;

[0033] Figure 6 It is a schematic structural diagram of another angle of the holder in the high temperature and high pressure dynamic simulation erosion test system of the present invention;

[0034] Figure 7 It is a structural schematic diagram of the sand adding component in the high temperature and high pressure dynamic simulation erosion test system of the present invention.

[0035] In the figure: 1, feeding unit; 10, main pipeline; 101, liquid pump; 102, horizontal flow pump; 11, sand adding assembly; 111, sand storage device; 1111, first silo; 1112, second silo; 112, sand mixing mechanism; 1120, sand mixing chamber; 1121, sand mixing motor; 113, sand outlet pipeline;

[0036] 2. Erosion simulation unit; 20. Erosion chamber; 21. Nozzle; 22. Hose; 23. Nozzle bracket; 231. X-axis moving assembly; 232. Y-axis moving assembly; 233. Rotating structure;

[0037] 3. Environmental simulation unit; 31. Clamp; 310. Kettle body; 311. Central axis; 312. Gland; 32. Pressurizing assembly; 321. Hydraulic oil storage tank; 322. Hand pump; 33. Temperature regulating assembly; 331. Heating jacket; 332. Temperature sensor;

[0038] 4. Control unit;

[0039] 5. Sand collecting box;

[0040] 6. Gas flow meter; 7. Liquid flow meter. DETAILED DESCRIPTION

[0041] To make the purpose, technical solution and advantages of the present invention clearer, the technical solution of the present invention will be described in detail below. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other implementation methods obtained by ordinary technicians in this field without creative work belong to the scope of protection of the present invention.

[0042] In the description of the present invention, it is to be understood that the terms “center”, “lateral”, “length”, “width”, “height”, “up”, “down”, “front”, “back”, “left”, “right”, “vertical”, “horizontal”, “top”, “bottom”, “inside”, “outside”, “side”, etc., indicating orientations or positional relationships are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.

[0043] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to the specific circumstances.

[0044] The present invention provides a high temperature and high pressure dynamic simulation erosion test system. Figure 1 is a schematic diagram of the structure of this embodiment, Figure 2 yes Figure 1 The main structure diagram of Figure 3 yes Figure 1 Another structural diagram from another angle, Figure 1-Figure 3 As shown, the high temperature and high pressure dynamic simulation erosion test system includes a feeding unit 1, an erosion simulation unit 2, an environment simulation unit 3 and a control unit 4.

[0045] Among them, the feeding unit 1 includes a main pipeline 10 and a sand adding component 11, the sand adding component 11 includes a sand storage device 111, a sand mixing mechanism 112 connected to the sand storage device 111, and a sand outlet pipeline 113 connected to the sand mixing mechanism 112. The main pipeline 10 can be connected to the gas source, liquid pump 101, horizontal flow pump 102 and sand outlet pipeline 113; in this embodiment, the horizontal flow pump 102 is connected to the main pipeline 10 to provide power for the high-pressure and high-speed sand-carrying fluid, and the gas phase pressure and liquid phase flow are adjusted according to the experimental requirements to control the erosion intensity. The sand carrying system is designed to have a working pressure of 7MPa and a maximum pressure of 20MPa.

[0046] The erosion simulation unit 2 includes an erosion chamber 20 and an adjustable nozzle 21. The nozzle 21 is arranged in the erosion chamber 20 and connected to the main pipeline 10 through a hose 22. The hose 22 in this embodiment adopts a high-pressure hose with a pressure bearing capacity of not less than 20MPa, which is used to match and connect with the nozzle to meet the test requirements; the nozzle 21 adopts a wear-resistant, direct current nozzle, and the material is selected from existing wear-resistant materials. In actual production and use, the nozzle 21 can be equipped with a variety of different specifications to facilitate replacement according to the erosion needs of different media.

[0047] The environment simulation unit 3 includes a holder 31, a pressurizing component 32 and a temperature regulating component 33. Figure 4 Schematic diagram of the structure of the clamp in this embodiment. Figure 4 As shown, the clamp 31 includes a kettle body 310, a temperature regulating component 33 is arranged on the outside of the kettle body 310, a central axis 311 is arranged in the kettle body 310, one end of the central axis 311 is connected to the pressurizing component 32, and the other end of the central axis 311 extends into the erosion chamber 20, and the end of the central axis 311 can be installed with the sample to be eroded; the clamp 31 adopts a semi-open type, which can realize the temperature and pressure simulation of the erosion and wear environment of metal pipes in oil and gas fields. Specifically, in this embodiment, the temperature can be simulated from room temperature to 200°C through the temperature regulating component 33, and the pressure can be simulated from normal pressure to 20MPa through the pressurizing component 32.

[0048] In this embodiment, the feeding unit 1, the erosion simulation unit 2, and the environmental simulation unit 3 are all communicatively connected to the control unit 4, wherein the control unit 4 includes a PLC for performing intelligent and automatic control of the feeding unit 1, the erosion simulation unit 2, and the environmental simulation unit 3 through the control unit 4.

[0049] As an optional implementation, Figure 5 It is the control principle diagram of this embodiment, such as Figure 5 As shown, the temperature adjustment component 33 includes a heating sleeve 331 and a temperature sensor 332 . The heating sleeve 331 is sleeved on the outside of the kettle body 310 . The temperature sensor 332 is used to monitor the temperature of the kettle body 310 . Both the temperature sensor 332 and the heating sleeve 331 are electrically connected to the control unit 4 .

[0050] As an optional embodiment, the pressurizing component 32 includes a hydraulic oil storage tank 321 and a hand pump 322 connected to the hydraulic oil storage tank 321. The hand pump 322 is pressurized by hydraulic oil, and the hand pump 322 is connected to the kettle body 310 through a high-pressure pipeline.

[0051] in, Figure 6 is a schematic diagram of the structure of the clamp at another angle in this embodiment. Figure 6As shown, the clamp 31 also includes a pressure cover 312, which can be connected to the end of the central axis 311, and the sample to be etched is arranged between the central axis 311 and the pressure cover 312. A hole structure is arranged at the center of the end face of the pressure cover 312, and the sample to be etched can be exposed through the hole structure.

[0052] Optionally, the pressurizing component 32 also includes a pressure sensor. The hand pump 322 is a high-precision hand pump. The high-precision hand pump is connected to the kettle body 310 through a high-pressure pipeline. The hand pump 322 uses hydraulic oil for pressurization. The central axis 311 and the kettle body 310 are sealed.

[0053] When in use, the erosion sample is installed on the end of the central axis 311 through the pressure cover 312, and the hydraulic oil pressurized by the hand pump 322 enters the interior of the kettle 310 to push the central axis 311 to move against the non-open surface of the erosion sample (i.e., the non-eroded surface, simulating the contact between the metal pipe and the formation). The pressure increased by the hand pump 322 is transmitted to the back of the erosion sample through the central axis 311, thereby simulating the pressure difference that the metal pipe is subjected to when being eroded (i.e., the pressure difference between the non-eroded surface and the eroded surface).

[0054] As an optional implementation, Figure 6 As shown, a nozzle support 23 is disposed in the erosion chamber 20 , and the nozzle support 23 includes an X-axis moving component 231 , a Y-axis moving component 232 and a rotating structure 233 .

[0055] The X-axis moving assembly 231 is installed at the bottom of the erosion chamber 20; the Y-axis moving assembly 232 is installed on the X-axis moving assembly 231; the nozzle 21 is connected to the rotating structure 233, and the rotating structure 233 is installed on the Y-axis moving assembly 232;

[0056] The X-axis moving assembly 231 , the Y-axis moving assembly 232 , and the rotating structure 233 are all electrically connected to the control unit 4 .

[0057] In this embodiment, the nozzle bracket 23 is made of stainless steel. By setting the nozzle bracket 23 to include an X-axis moving component 231, a Y-axis moving component 232 and a rotating structure 233, the X-axis moving component 231 can adjust the distance between the nozzle 21 and the erosion sample, the Y-axis moving component 232 can adjust the height of the nozzle 21, and the rotating structure 233 can adjust the angle of the nozzle, that is, by setting the nozzle bracket 23, the angle, height and distance of the nozzle movement can be adjusted. Optionally, the X-axis moving component 231 and the Y-axis moving component 232 in this embodiment are both linear modules.

[0058] Specifically, in this embodiment, the angle adjustment range (pitch angle) of the nozzle is 0-90°, the height adjustment stroke is 50 mm, and the distance adjustment stroke is 150 mm.

[0059] As an optional implementation, Figure 7 Schematic diagram of the structure of the sand adding assembly in this embodiment. Figure 7 As shown, the sand storage device 111 includes at least a first silo 1111 and a second silo 1112 which can operate alternately, the first silo 1111 and the second silo 1112 are both connected to a sand mixing mechanism 112, the first silo 1111 and the second silo 1112 are both provided with a variable frequency motor and a paddle rotor connected to the variable frequency motor (not shown inside the silo), and the variable frequency motor is electrically connected to the control unit 4.

[0060] The first silo 1111 and the second silo 1112 in this embodiment are both existing sand feeder structures, which are equipped with paddle rotors. According to the required amount of sand added, the frequency conversion motor controls the screw to drive the paddle rotor to rotate, and the sand adding rate is adjusted by controlling the rotation speed to add sand quantitatively. In this embodiment, the quantitative sand adding working area is in a pressure balance state, and the working pressure is 7MPa.

[0061] Specifically, in this embodiment, a 10L silo is used to achieve uninterrupted sand replenishment through alternating operation, providing test conditions for long-term erosion tests.

[0062] In this embodiment, the sand mixing mechanism 112 includes a sand mixing chamber 1120, a sand mixing assembly and a sand mixing motor 1121. The sand mixing assembly (not shown in the figure) is arranged in the sand mixing chamber 1120, and the sand mixing motor 1121 is connected to the sand mixing assembly. The sand mixing assembly is driven to rotate by the sand mixing motor 1121 to perform the sand mixing operation. In this embodiment, the sand mixing motor 1121 is electrically connected to the control unit 4 to realize automatic intelligent control.

[0063] As an optional embodiment, the high temperature and high pressure dynamic simulation erosion test system further includes a sand collecting box 5, which is arranged at the bottom of the erosion chamber 20, and the sand collecting box 5 is connected to the erosion chamber 20 through a pipeline. The sand collecting box 5 is arranged to collect the residual sand after the test. Optionally, wheels are arranged at the bottom of the sand collecting box 5 to facilitate cleaning thereof.

[0064] As an optional embodiment, a gas flow meter 6 and a liquid flow meter 7 are also included, and the gas flow meter 6 and the liquid flow meter 7 are respectively used to monitor the gas flow and the liquid flow in the main pipeline 10, and the gas flow meter 6 and the liquid flow meter 7 are electrically connected to the control unit 4. By setting the gas flow meter 6 and the liquid flow meter 7, the flow of fluids in different phases is monitored and collected, providing a basis for the control of sand carrying conditions.

[0065] As an optional embodiment, the erosion chamber 20 is a sealed structure, including relatively arranged transparent observation windows.

[0066] The length, width and height of the erosion chamber 20 in this embodiment are 600 mm, 350 mm and 350 mm respectively, and the front and rear opposite surfaces are made of highly light wear-resistant transparent material, and the rest are made of stainless steel. Under the premise of meeting the strength requirements, it can provide a visual environment and provide a high-speed jet erosion process for observation.

[0067] The above is only a specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any person skilled in the art can easily think of changes or substitutions within the technical scope disclosed by the present invention, which should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.

Claims

1. A high temperature and high pressure dynamic simulation erosion test system, characterized in that: It includes a feeding unit, an erosion simulation unit, an environment simulation unit and a control unit, wherein: The feeding unit comprises a main pipeline and a sand feeding assembly, wherein the sand feeding assembly comprises a sand storage device, a sand mixing mechanism connected to the sand storage device, and a sand outlet pipeline connected to the sand mixing mechanism, wherein the main pipeline can be connected to an air source, a liquid pump, a horizontal flow pump, and the sand outlet pipeline; The erosion simulation unit comprises an erosion chamber and an adjustable nozzle, wherein the nozzle is arranged in the erosion chamber and connected to the main pipeline through a hose; The environmental simulation unit includes a holder, a pressurizing component and a temperature regulating component. The holder includes a kettle body. The temperature regulating component is arranged on the outside of the kettle body. A central axis is arranged inside the kettle body. One end of the central axis is connected to the pressurizing component. The other end of the central axis extends into the erosion chamber. The end of the central axis can be used to mount the sample to be etched. The feeding unit, the erosion simulation unit, and the environment simulation unit are all in communication connection with the control unit.

2. The high temperature and high pressure dynamic simulation erosion test system according to claim 1, characterized in that: The temperature regulating assembly comprises a heating sleeve and a temperature sensor. The heating sleeve is sleeved on the outside of the kettle body. The temperature sensor is used to monitor the temperature of the kettle body. The temperature sensor and the heating sleeve are both electrically connected to the control unit.

3. The high temperature and high pressure dynamic simulation erosion test system according to claim 1, characterized in that: The pressurizing component includes a hydraulic oil storage tank and a hand pump connected to the hydraulic oil storage tank. The hand pump is pressurized by hydraulic oil, and the hand pump is connected to the kettle body through a high-pressure pipeline.

4. The high temperature and high pressure dynamic simulation erosion test system according to any one of claims 1 to 3, characterized in that: The clamp also includes a pressure cover, which can be connected to the end of the central axis. The sample to be etched is arranged between the central axis and the pressure cover. A hole structure is arranged at the center of the end face of the pressure cover, and the sample to be etched can be exposed from the hole structure.

5. The high temperature and high pressure dynamic simulation erosion test system according to any one of claims 1 to 3, characterized in that: The erosion chamber is provided with a nozzle support, and the nozzle support includes an X-axis moving component, a Y-axis moving component and a rotating structure, wherein: The X-axis moving assembly is installed at the bottom of the erosion chamber; The Y-axis moving assembly is installed on the X-axis moving assembly; The nozzle is connected to the rotating structure, and the rotating structure is installed on the Y-axis moving assembly; The X-axis moving component, the Y-axis moving component, and the rotating structure are all electrically connected to the control unit.

6. The high temperature and high pressure dynamic simulation erosion test system according to any one of claims 1 to 3, characterized in that: The sand storage device includes at least a first silo and a second silo that can operate alternately, the first silo and the second silo are both connected to a sand mixing mechanism, the first silo and the second silo are both provided with a variable frequency motor and a paddle rotor connected to the variable frequency motor, and the variable frequency motor is electrically connected to the control unit.

7. The high temperature and high pressure dynamic simulation erosion test system according to any one of claims 1 to 3, characterized in that: It also includes a sand collecting box, which is arranged at the bottom of the erosion chamber and is connected to the erosion chamber through a pipeline.

8. The high temperature and high pressure dynamic simulation erosion test system according to any one of claims 1 to 3, characterized in that: The sand mixing mechanism comprises a sand mixing chamber, a sand mixing assembly and a sand mixing motor, wherein: The sand mixing assembly is arranged in the sand mixing chamber, and the sand mixing motor is connected to the sand mixing assembly.

9. The high temperature and high pressure dynamic simulation erosion test system according to any one of claims 1 to 3, characterized in that: It also includes a gas flow meter and a liquid flow meter, which are used to monitor the gas flow and liquid flow in the main pipeline respectively, and the gas flow meter and the liquid flow meter are both electrically connected to the control unit.

10. The high temperature and high pressure dynamic simulation erosion test system according to any one of claims 1 to 3, characterized in that: The erosion chamber is a sealed structure and includes relatively arranged transparent observation windows.

Citation Information

Cited By

  • High-temperature and high-pressure recyclable gas-liquid-solid multi-phase erosion-corrosion experimental device

    CN121475941A