Simulation stone outer wall decoration method
By updating the structural level of simulated stone and adopting multi-step construction methods, combining automatic coating equipment and environmentally friendly materials, the existing simulated stone has solved the problems of poor simulation, complex construction and poor durability in exterior wall decoration, and achieved high simulation The simulated stone exterior wall decoration with degree, convenient construction, strong durability and environmental protection meets the needs of modern buildings for high-performance exterior wall decoration.
Patent Information
- Application Number
- CN202411583339.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-07
- Publication Date
- 2025-02-14
AI Technical Summary
Existing simulated stones have problems such as poor simulation, complex construction and poor durability in exterior wall decoration, which is difficult to meet the diversified needs of modern buildings for aesthetics, economy and environmental protection.
By updating the stone structure layer, a multi-step construction method is adopted, including cleaning the base layer, fiber reinforcement layer and environmentally friendly cementing layer, natural stone powder base layer, color adjustment layer and texture simulation layer, weatherproof protection layer and waterproof dust-proof surface layer construction, Combining automatic coating equipment and environmentally friendly materials, it achieves high simulation stone exterior wall decoration with convenient construction, strong durability and environmental protection.
It improves the quality and durability of decoration, improves construction efficiency and environmental friendliness, while maintaining cost-effectiveness, meeting the needs of modern buildings for high-performance exterior wall decoration.
Smart Images

Figure CN119434564A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building decoration materials, and in particular to a simulated stone exterior wall decoration method. Background Art
[0002] With the continuous development of the construction industry, the requirements for building decoration materials are increasing day by day. The application of traditional dry hanging stone in high-rise and home decoration is limited due to its high cost, complex installation and heavy weight. Therefore, simulated stone is widely used in building exterior wall decoration as a substitute for traditional stone.
[0003] There are many problems with simulated stone in the prior art: poor simulation, poor texture and grain; complex construction, high requirements for construction technology; poor durability, easy to age after long-term exposure to harsh environments. In response to such problems, the present invention aims to create a new simulated stone exterior wall decoration method with high simulation, convenient construction, strong durability and environmental protection by updating the stone structure layer, so as to meet the diversified needs of modern buildings for beauty, economy and environmental protection. Summary of the invention
[0004] Based on the existing technical problems, the present invention proposes a simulated stone exterior wall decoration method.
[0005] The present invention provides a method for decorating an exterior wall made of simulated stone, comprising the following steps:
[0006] Step 1: Clean the base construction, remove dust, oil and debris, check the flatness and strength of the base, ensure that the base is dry, select a suitable base treatment material, apply it evenly on the base, and ensure that the base treatment layer is dry and solidified.
[0007] Step 2: Construction of fiber reinforcement layer and environmentally friendly adhesive layer. Select high-quality reinforced fiber mesh cloth anti-cracking material, lay it on the base treatment layer, ensure there are no wrinkles and bubbles, and use environmentally friendly adhesive material to stick it to the base layer.
[0008] Step 3: Construction of natural stone powder base layer: prepare natural stone powder and resin raw materials, mix them evenly according to the matching ratio, lay them on the reinforced fiber layer, and use automatic coating equipment to coat the mixed material on the fiber reinforcement layer and the environmentally friendly bonding layer to form a base layer. Use vibration and pressing technology to ensure that the base layer is dense and free of voids and reaches the required thickness and flatness.
[0009] Step 4: Construction of color adjustment layer and texture simulation layer. Select appropriate inorganic pigments or color pastes for color adjustment according to design requirements, conduct appearance inspection to ensure uniform color, realistic texture, no bubbles and cracks, and perform performance tests. Apply pigments or color pastes evenly on the base layer, or use spray painting or embossing technology to form a texture effect.
[0010] Step 5. Construction of weather-resistant protective layer and waterproof and dustproof surface layer. Select suitable weather-resistant protective material and evenly apply the weather-resistant protective material on the color adjustment and texture simulation layer. Ensure that the protective layer is dry and solidified to play its protective role. Evenly apply the waterproof and dustproof material on the weather-resistant protective layer to form a smooth and impermeable surface layer. Wait for the surface layer to dry and solidify before inspecting and cleaning.
[0011] Preferably, in the step 1 of cleaning the base, a level is used to accurately measure and check the flatness of the base, and the error is controlled within ±3mm. A rebound hammer is used to perform multi-point testing to detect the strength, ensuring that the strength of the base concrete reaches more than 90% of the design standard.
[0012] In the construction of the fiber reinforcement layer and the environmentally friendly bonding layer in step 2, different specifications of reinforced fiber mesh cloth are selected according to the size and stress conditions of the exterior wall.
[0013] Step 4: During the construction of the color adjustment layer and texture simulation layer, a small area sample test is carried out before construction, and the color changes are observed after being exposed to the natural environment for a period of time.
[0014] Preferably, the automatic coating equipment comprises a movable base, a movable wheel group is arranged on the lower surface of the movable base, and a plurality of movable wheel groups are evenly distributed on the lower surface of the movable base.
[0015] A PLC controller is fixedly installed on the upper surface of the mobile base, and a fixed gantry is fixedly connected to the upper surface of the mobile base. A fixed support seat is fixedly connected to the upper surface of the fixed gantry. A load-bearing shaft is fixedly connected to the surface of the fixed support seat, and both ends of the load-bearing shaft penetrate and extend to both side surfaces of the fixed support seat, and both ends of the load-bearing shaft are rotatably connected to load-bearing pulleys through bearings.
[0016] Preferably, a winding support seat is fixedly installed on the upper surface of the mobile base, and the surface of the winding support seat is rotatably connected to a steel cable winding wheel through a bearing. The two winding support seats are symmetrically distributed with the axis of the steel cable winding wheel as the center, and a winding reduction motor electrically connected to the PLC controller through a cable is fixedly installed on the surface of one of the winding support seats, and the reduction output end of the winding reduction motor is fixedly connected to one end of the steel cable winding wheel.
[0017] The surface of the cable reel is wound with two symmetrical lifting cables, which are respectively slidably connected to the surfaces of the two load-bearing pulleys, and one end of the lifting cable passes through the upper surface of the fixed gantry and extends to the inner wall of the fixed gantry.
[0018] Preferably, one end of the lifting steel cable is fixedly connected to a lifting mounting seat, and a plurality of symmetrically distributed guide wheels are fixedly mounted on both side surfaces of the lifting mounting seat, and the plurality of guide wheels are rotatably connected to the two side surfaces of the lifting mounting seat through bearings.
[0019] The inner walls on both sides of the fixed gantry are provided with guide slots matched with the guide wheels, and the surfaces of the guide wheels are slidably connected to the inner walls of the guide slots.
[0020] A load-bearing support beam is fixedly connected to the surface of the lifting mounting seat, and the two load-bearing support beams are symmetrically distributed with the axis of the lifting mounting seat as the center.
[0021] A reinforcing rib is fixedly connected to the upper surface of the load-bearing support beam, one end of the reinforcing rib is fixedly connected to the surface of the lifting mounting seat, and one end of the load-bearing support beam away from the lifting mounting seat is fixedly connected to a reinforcing crossbeam.
[0022] Preferably, the inner wall of the load-bearing support beam is slidably connected to a movable mounting frame, and a plurality of symmetrically distributed support wheels are fixedly mounted on both side surfaces of the movable mounting frame. The inner wall of the load-bearing support beam is provided with a limiting slide groove matched with the support wheel, and the surface of the support wheel is slidably connected to the inner wall of the limiting slide groove.
[0023] A servo electric cylinder electrically connected to the PLC controller via a cable is fixedly mounted on the surface of the lifting mounting seat, and one end of the servo electric cylinder is fixedly connected to the surface of the movable mounting bracket.
[0024] A connecting beam is fixedly connected to the lower surface of the mobile mounting frame, and a plurality of the connecting beams are evenly distributed on the lower surface of the mobile mounting frame. A working beam is fixedly connected to the upper surface of the mobile mounting frame, and two working beams are symmetrically distributed with the axis of the connecting beam as the center.
[0025] Preferably, a mixing box is fixedly connected to the upper surface of the working beam, a pressurizing connecting block is fixedly connected to the surface of the mixing box, a discharge pressurizing frame is fixedly connected to the surface of the pressurizing connecting block, the inner wall of the discharge pressurizing frame is trapezoidal, and a coating frame is fixedly connected to the surface of the discharge pressurizing frame.
[0026] A discharge cavity is opened on the surface of the pressurized connection block, and the inner walls of the plurality of discharge cavities are respectively fixedly connected with the inner wall of the mixing box and the inner wall of the discharge pressurizing frame, and the inner wall of the discharge cavity is circular.
[0027] An extrusion shaft is sleeved on the inner wall of the discharge chamber, and one end of multiple extrusion shafts passes through and extends to one side surface of the mixing box. The surface of the extrusion shaft is rotatably connected to the inner wall of the mixing box through a bearing, and an extrusion spiral piece is fixedly connected to the surface of the extrusion shaft. The surface of the extrusion spiral piece is adapted to be slidably connected to the inner wall of the discharge chamber, and one end of the extrusion spiral piece extends to the interior of the mixing box.
[0028] Preferably, the surface of the extrusion shaft is respectively fixedly mounted with a first transmission sprocket and a second transmission sprocket, and the plurality of extrusion shafts are transmission-connected through the first transmission sprocket and the second transmission sprocket and the chain, and the surface of the mixing box is fixedly mounted with a discharging reduction motor electrically connected to the PLC controller via a cable, and the reduction output end of the discharging reduction motor is fixedly connected to one end of one of the extrusion shafts.
[0029] A sealed extrusion hopper is fixedly connected to the inner wall of one side of the mixing box close to the discharging reduction motor, and the surface of the sealed extrusion hopper is slidably connected to one end of the extrusion spiral sheet.
[0030] Preferably, a vibration pressure plate is fixedly sleeved on the surface of the coating frame, and a rubber sealing strip with a U-shaped surface is fixedly connected to the surface of the vibration pressure plate.
[0031] A vibration motor electrically connected to the PLC controller via a cable is fixedly mounted on a surface of one side of the vibration pressure plate close to the mixing box, and a plurality of the vibration motors are evenly distributed on the surface of the vibration pressure plate.
[0032] Preferably, a vibration pressure auxiliary column is fixedly connected to the surface of one side of the vibration pressure plate close to the mixing box, and the two vibration pressure auxiliary columns are symmetrically distributed with the axis of the vibration pressure plate as the center, one end of the vibration pressure auxiliary column is fixedly connected to a first positioning rod, and the surface of the first positioning rod is sleeved with a support spring with one end fixedly connected to one end of the vibration pressure auxiliary column, the other end of the support spring is fixedly connected to a support column, one end of the support column is fixedly connected to the lower surface of the working beam, and the other end of the support column is fixedly connected to a second positioning rod, and the surface of the second positioning rod is sleeved with the inner wall of the support spring.
[0033] The beneficial effects of the present invention are:
[0034] 1. By setting steps one to five, in the construction of simulated stone exterior wall decoration, not only the quality and durability of the decoration are improved, but also the construction efficiency and environmental friendliness are improved, while maintaining cost-effectiveness, thereby achieving the effect of meeting the needs of modern buildings for high-performance exterior wall decoration.
[0035] 2. By setting up automatic coating equipment, when constructing the natural stone powder base layer, the mixture can be automatically coated on the fiber reinforcement layer and the environmentally friendly bonding layer. During the coating process, the mixed coating is compacted by a vibration motor, and the mixture is automatically smoothed by a vibration plate, so as to achieve a better effect of simulated stone exterior wall decoration construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0036] Figure 1 A schematic diagram of a simulated stone exterior wall decoration method proposed by the present invention;
[0037] Figure 2 A method for decorating an exterior wall of simulated stone provided by the present invention Figure 1 Enlarged view of point A in the middle;
[0038] Figure 3 A three-dimensional diagram of a fixed gantry structure of a simulated stone exterior wall decoration method proposed by the present invention;
[0039] Figure 4 A method for decorating an exterior wall of simulated stone provided by the present invention Figure 3 A magnified view of the structure at B in the middle;
[0040] Figure 5 A three-dimensional diagram of the structure of a mixing material box for a simulated stone exterior wall decoration method proposed by the present invention;
[0041] Figure 6 A three-dimensional diagram of the structure of a mobile mounting frame for a simulated stone exterior wall decoration method proposed by the present invention;
[0042] Figure 7 A three-dimensional diagram of the structure of a discharging reduction motor of a simulated stone exterior wall decoration method proposed by the present invention;
[0043] Figure 8 A three-dimensional diagram of the extrusion shaft structure of a simulated stone exterior wall decoration method proposed by the present invention;
[0044] Fig. 9 This is a front view of a supporting spring structure of a simulated stone exterior wall decoration method proposed by the present invention.
[0045] In the figure: 1. Mobile base; 2. Mobile wheel group; 3. PLC controller; 4. Fixed gantry; 5. Fixed support seat; 6. Load-bearing shaft; 7. Load-bearing pulley; 8. Winding support seat; 9. Cable winding wheel; 10. Winding reduction motor; 11. Lifting cable; 12. Lifting mounting seat; 13. Guide wheel; 14. Guide slide; 15. Load-bearing support beam; 16. Mobile mounting frame; 17. Support wheel; 18. Limit slide; 19. Servo electric cylinder; 20. Connecting beam ; 21. Working beam; 22. Mixing box; 23. Pressurized connecting block; 24. Discharging pressurized frame; 25. Coating frame; 26. Extrusion shaft; 27. Extrusion spiral sheet; 28. First transmission sprocket; 29. Second transmission sprocket; 30. Discharging reduction motor; 31. Sealed extrusion hopper; 32. Vibration pressure plate; 33. Rubber sealing strip; 34. Vibration motor; 35. Vibration pressure auxiliary column; 36. First positioning rod; 37. Support spring; 38. Support column; 39. Second positioning rod. DETAILED DESCRIPTION
[0046] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.
[0047] Reference Figure 1 , a simulated stone exterior wall decoration method, comprising the following steps:
[0048] Step 1: Clean the base construction, remove dust, oil and other debris, check the flatness and strength of the base, ensure that the base is dry, select a suitable base treatment material, apply it evenly on the base, and ensure that the base treatment layer is dry and solidified.
[0049] Specifically, during the construction of the clean base, a level meter is used to accurately measure and check the flatness of the base, and the error is controlled within ±3mm. A rebound hammer is used to perform multi-point tests to test the strength to ensure that the strength of the base concrete reaches more than 90% of the design standard.
[0050] Preferably, after cleaning the base layer, the base layer is lightly polished to increase the adhesion of the base treatment material.
[0051] Furthermore, by testing and processing the base layer, the flatness and strength of the base layer are ensured, which has the effect of improving the adhesion and durability of the final decorative layer.
[0052] Step 2: Construction of fiber reinforcement layer and environmentally friendly adhesive layer. Select high-quality reinforced fiber mesh cloth anti-cracking material, lay it on the base treatment layer, ensure there are no wrinkles and bubbles, and use environmentally friendly adhesive material to stick it to the base layer.
[0053] Specifically, different specifications of reinforced fiber mesh cloth are selected according to the size and stress of the exterior wall. For large-area exterior walls, mesh cloth with larger mesh size (such as 10mm×10mm) and higher strength is selected to improve the overall crack resistance.
[0054] Furthermore, the use of high-quality reinforced fiber mesh cloth and environmentally friendly adhesive materials has the characteristics of providing additional crack resistance and reducing cracks caused by temperature changes or external forces.
[0055] Preferably, before laying the reinforced fiber mesh cloth, it is pre-soaked to better combine with the environmentally friendly adhesive material. The soaking time is controlled to be 5-10 minutes, and the diluent matching the adhesive material is used for soaking.
[0056] Furthermore, when pasting the reinforced fiber mesh cloth, the pasting method is adopted from the middle to both sides to avoid wrinkles. At the same time, a special scraper is used to evenly scrape the environmentally friendly adhesive material on the mesh cloth to ensure that the thickness of the adhesive material is uniform and controlled at 1-2mm.
[0057] Step three, construction of natural stone powder base layer, prepare natural stone powder, resin and other raw materials, mix them evenly according to the matching ratio, lay them on the reinforced fiber layer, and use automatic coating equipment to coat the mixed material on the fiber reinforcement layer and the environmentally friendly bonding layer to form a base layer. Use vibration, pressing and other processes to ensure that the base layer is dense and free of voids and reaches the required thickness and flatness.
[0058] Specifically, when preparing raw materials such as natural stone powder and resin, the natural stone powder is screened to remove large particles of impurities to ensure that the particle size of the stone powder is between 0.1-0.5mm. The resin is quality tested to check its viscosity, curing time and other indicators to ensure that it meets the construction requirements.
[0059] Further, refer to Figure 1-Figure 9 The automatic coating equipment includes a mobile base 1 , a mobile wheel group 2 is arranged on the lower surface of the mobile base 1 , and a plurality of mobile wheel groups 2 are evenly distributed on the lower surface of the mobile base 1 .
[0060] Furthermore, the moving wheel set 2 is composed of a plurality of universal self-locking wheels, and the moving base 1 is supported and locked after movement by the moving wheel set 2 .
[0061] A PLC controller 3 is fixedly installed on the upper surface of the mobile base 1, and a fixed gantry 4 is fixedly connected to the upper surface of the mobile base 1. A fixed support seat 5 is fixedly connected to the upper surface of the fixed gantry 4. A load-bearing shaft 6 is fixedly connected to the surface of the fixed support seat 5. Both ends of the load-bearing shaft 6 penetrate and extend to the two side surfaces of the fixed support seat 5. Both ends of the load-bearing shaft 6 are rotatably connected to load-bearing pulleys 7 through bearings.
[0062] A winding support seat 8 is fixedly installed on the upper surface of the mobile base 1, and the surface of the winding support seat 8 is rotatably connected to a steel cable winding wheel 9 through a bearing. The two winding support seats 8 are symmetrically distributed with the axis of the steel cable winding wheel 9 as the center. A winding reduction motor 10 electrically connected to the PLC controller 3 through a cable is fixedly installed on the surface of one of the winding support seats 8, and the reduction output end of the winding reduction motor 10 is fixedly connected to one end of the steel cable winding wheel 9.
[0063] When in use, the winding reduction motor 10 is a worm gear type self-locking reduction motor. Through the self-locking function of the winding reduction motor 10, the wire rope winding wheel 9 is driven to rotate and locked after the rotation stops.
[0064] Two symmetrical lifting cables 11 are wound on the surface of the cable winding wheel 9, and the two lifting cables 11 are slidingly connected to the surfaces of the two load-bearing pulleys 7 respectively. One end of the lifting cable 11 passes through the upper surface of the fixed gantry 4 and extends to the inner wall of the fixed gantry 4.
[0065] One end of the lifting cable 11 is fixedly connected to a lifting mounting seat 12, and a plurality of symmetrically distributed guide wheels 13 are fixedly installed on both side surfaces of the lifting mounting seat 12. The plurality of guide wheels 13 are rotatably connected to the two side surfaces of the lifting mounting seat 12 through bearings.
[0066] The inner walls on both sides of the fixed gantry 4 are provided with guide slots 14 adapted to the guide wheels 13 , and the surfaces of the guide wheels 13 are slidably connected to the inner walls of the guide slots 14 .
[0067] When in use, the guide slot 14 and the guide wheel 13 cooperate to guide and limit the lifting and lowering of the lifting mounting seat 12 through the lifting cable 11.
[0068] Specifically, when in use, the cable winding wheel 9 is driven to rotate by the winding reduction motor 10, and the lifting cable 11 is wound or unwound by the rotation of the cable winding wheel 9, driving the lifting mounting seat 12 to perform lifting and lowering movements on the inner wall of the fixed gantry 4, and the lifting and lowering mounting seat 12 is guided and limited by the cooperation of the guide wheel 13 and the guide slide groove 14.
[0069] A load-bearing support beam 15 is fixedly connected to the surface of the lifting installation seat 12 , and the two load-bearing support beams 15 are symmetrically distributed with the axis of the lifting installation seat 12 as the center.
[0070] Furthermore, in order to improve the strength of the load-bearing support beam 15, a reinforcing rib is fixedly connected to the upper surface of the load-bearing support beam 15, one end of the reinforcing rib is fixedly connected to the surface of the lifting mounting seat 12, and the end of the load-bearing support beam 15 away from the lifting mounting seat 12 is fixedly connected to a reinforcing cross beam.
[0071] The inner wall of the load-bearing support beam 15 is slidably connected to a movable mounting frame 16, and a plurality of symmetrically distributed support wheels 17 are fixedly mounted on the two side surfaces of the movable mounting frame 16. The inner wall of the load-bearing support beam 15 is provided with a limiting slide groove 18 matched with the support wheel 17, and the surface of the support wheel 17 is slidably connected to the inner wall of the limiting slide groove 18.
[0072] When in use, the support wheel 17 slides on the inner wall of the limiting slide groove 18 to facilitate the movement and limiting of the movable mounting frame 16 and ensure that the movable mounting frame 16 maintains a sliding connection with the load-bearing support beam 15.
[0073] A servo electric cylinder 19 electrically connected to the PLC controller 3 via a cable is fixedly mounted on the surface of the lifting mounting seat 12 , and one end of the servo electric cylinder 19 is fixedly connected to the surface of the movable mounting frame 16 .
[0074] When in use, the servo electric cylinder 19 is provided with electric energy through a drag chain cable, a conductive slot or a battery. When a battery is used to provide electric energy, the battery is installed on the lifting mounting seat 12 .
[0075] Specifically, when in use, the push rod in the servo electric cylinder 19 extends or contracts, driving the movable mounting seat to move linearly along the surface of the load-bearing support beam 15 .
[0076] A connecting beam 20 is fixedly connected to the lower surface of the mobile mounting frame 16, and multiple connecting beams 20 are evenly distributed on the lower surface of the mobile mounting frame 16. A working beam 21 is fixedly connected to the upper surface of the mobile mounting frame 16, and the two working beams 21 are symmetrically distributed with the axis of the connecting beam 20 as the center.
[0077] A mixing box 22 is fixedly connected to the upper surface of the working beam 21, a pressurizing connection block 23 is fixedly connected to the surface of the mixing box 22, a discharge pressurizing frame 24 is fixedly connected to the surface of the pressurizing connection block 23, the inner wall of the discharge pressurizing frame 24 is trapezoidal, and a coating frame 25 is fixedly connected to the surface of the discharge pressurizing frame 24.
[0078] A discharge cavity is formed on the surface of the pressurizing connection block 23 , and inner walls of the plurality of discharge cavities are fixedly connected to the inner wall of the mixing box 22 and the inner wall of the discharge pressurizing frame 24 , respectively, and the inner wall of the discharge cavity is circular.
[0079] An extrusion shaft 26 is sleeved on the inner wall of the discharge chamber, and one end of multiple extrusion shafts 26 penetrates and extends to one side surface of the mixing box 22. The surface of the extrusion shaft 26 is rotatably connected to the inner wall of the mixing box 22 through a bearing. An extrusion spiral piece 27 is fixedly connected to the surface of the extrusion shaft 26. The surface of the extrusion spiral piece 27 is adapted to be slidably connected to the inner wall of the discharge chamber, and one end of the extrusion spiral piece 27 extends to the interior of the mixing box 22.
[0080] When in use, the extrusion shaft 26 rotates, driving the extrusion spiral blade 27 to rotate, squeezing the mixed material inside the mixed material box 22 into the discharge cavity and into the pressurizing frame. The inner wall of the pressurizing frame is trapezoidal, and the entering mixed material is extruded and pressurized.
[0081] The surface of the extrusion shaft 26 is respectively fixedly mounted with a first transmission sprocket 28 and a second transmission sprocket 29, and the multiple extrusion shafts 26 are connected to each other through the first transmission sprocket 28 and the second transmission sprocket 29 and the chain. The surface of the mixing box 22 is fixedly mounted with a discharging reduction motor 30 electrically connected to the PLC controller 3 through a cable, and the reduction output end of the discharging reduction motor 30 is fixedly connected to one end of one of the extrusion shafts 26.
[0082] When in use, an extrusion shaft 26 located at one end of the mixing box 22 is driven to rotate by the discharge reduction motor 30. The rotating extrusion shaft 26 drives multiple other extrusion shafts 26 to rotate simultaneously through the first transmission sprocket 28, the second transmission sprocket 29 and the chain, driving the extrusion spiral blade 27 to rotate, and squeezing the mixed material inside the mixing box 22 into the discharge cavity.
[0083] A sealed extrusion hopper is fixedly connected to the inner wall of one side of the mixing box 22 close to the discharging reduction motor 30 , and the surface of the sealed extrusion hopper 31 is slidably connected to one end of the extrusion spiral blade 27 .
[0084] When in use, the extrusion shaft 26 and the first transmission sprocket 28, the second transmission sprocket 29 and the chain on its surface are sealed by sealing the extrusion hopper 31 to prevent the mixture from contacting the first transmission sprocket 28, the second transmission sprocket 29 and the chain, and the mixing box 22 is ensured to ensure that the mixture inside the mixing box 22 is in contact with the surface of the extrusion spiral blade 27 to the greatest extent, thereby reducing the volume of the bottom of the mixing box 22, thereby achieving a better effect of coating and discharging the mixture.
[0085] A vibration pressure plate 32 is fixedly sleeved on the surface of the coating frame 25 , and a rubber sealing strip 33 with a U-shaped surface is fixedly connected to the surface of the vibration pressure plate 32 .
[0086] A vibration motor 34 electrically connected to the PLC controller 3 via a cable is fixedly mounted on a surface of the vibration plate 32 on one side close to the mixing box 22 , and a plurality of vibration motors 34 are evenly distributed on the surface of the vibration plate 32 .
[0087] A vibration pressure auxiliary column 35 is fixedly connected to the surface of one side of the vibration pressure plate 32 close to the mixing box 22. The two vibration pressure auxiliary columns 35 are symmetrically distributed with the axis of the vibration pressure plate 32 as the center. One end of the vibration pressure auxiliary column 35 is fixedly connected to a first positioning rod 36. The surface of the first positioning rod 36 is sleeved with a support spring 37 with one end fixedly connected to one end of the vibration pressure auxiliary column 35. The other end of the support spring 37 is fixedly connected to a support column 38. One end of the support column 38 is fixedly connected to the lower surface of the working beam 21. The other end of the support column 38 is fixedly connected to a second positioning rod 39. The surface of the second positioning rod 39 is sleeved with the inner wall of the support spring 37.
[0088] Specifically, the automatic coating equipment works as follows during the construction process: first, a mixture of natural stone powder and resin is added to the mixture box 22, and then the PLC controller 3 is programmed according to the wall height to be coated and the amount of the mixture added to the mixture box 22.
[0089] After the PLC controller 3 is programmed, the PLC controller 3 automatically controls the winding reduction motor 10, the servo electric cylinder 19, the discharging reduction motor 30 and the vibration motor 34 to work. During coating, the servo electric cylinder 19 is first controlled by the PLC controller 3 to work, and the push rod in the servo electric cylinder 19 is extended or retracted to drive the mobile mounting seat to move linearly along the surface of the load-bearing support beam 15, drive the mixing box 22 and the coating frame 25 to move, and adjust the distance between the coating frame 25 and the wall.
[0090] After the distance between the coating frame 25 and the wall is adjusted, the PLC controller 3 controls the discharge reduction motor 30 to work, and the reduction output end of the discharge reduction motor 30 drives one of the extrusion shafts 26 to rotate. The extrusion shaft 26 rotates, and drives multiple extrusion shafts 26 to rotate synchronously through the first transmission sprocket 28, the second transmission sprocket 29 and the chain, and drives the extrusion spiral piece 27 to rotate, and the mixed material inside the mixed material box 22 is squeezed into the discharge cavity. The mixed material enters the pressurizing frame through the discharge cavity, and the internal volume of the pressurizing frame is gradually reduced to pressurize the mixed material. The pressurized mixed material enters the coating frame 25, and the coating frame 25 discharges the material and contacts the wall for coating. During the process, the PLC controller 3 synchronizes the winding reduction motor 10 to work, and the winding reduction motor 10 drives the cable winding wheel 9 to rotate. The cable winding wheel 9 synchronously winds up the two lifting cables 11, driving the lifting mounting seat 12 to move upward along the inner wall of the fixed gantry 4, so that the mixture extruded out of the coating frame 25 contacts the wall from bottom to top, and the wall surface is coated with the mixture. During the coating process, the PLC controller 3 controls the vibration motor 34 to work. After the mixture is coated on the wall, the mixture is maintained by the vibration pressure plate 32, and the vibration force generated by the vibration motor 34 is transmitted to the vibration pressure plate 32, and the vibration pressure plate 32 contacts the mixture to compact the mixture.
[0091] By setting up automatic coating equipment, when constructing the natural stone powder base layer, the mixture can be automatically coated on the fiber reinforcement layer and the environmentally friendly bonding layer. During the coating process, the mixed coating is compacted by the vibration motor 34, and the mixture is automatically smoothed by the vibration pressure plate 32, so as to achieve a better effect of simulated stone exterior wall decoration construction.
[0092] Step 4: Construction of color adjustment layer and texture simulation layer. Select appropriate inorganic pigments or color pastes for color adjustment according to design requirements, conduct appearance inspection to ensure uniform color, realistic texture, absence of defects such as bubbles and cracks, and perform performance tests. Apply pigments or color pastes evenly on the base layer, or use spray painting, embossing and other technologies to form a texture effect.
[0093] Specifically, in the construction of the color adjustment layer and the texture simulation layer, when selecting inorganic pigments or color pastes, in addition to considering the color, the light resistance, weather resistance and alkali resistance should also be considered.
[0094] Preferably, a small area sample test is carried out before construction, and the color change is observed after being exposed to the natural environment for a period of time.
[0095] Step 5. Construction of weather-resistant protective layer and waterproof and dustproof surface layer. Select suitable weather-resistant protective material and evenly apply the weather-resistant protective material on the color adjustment and texture simulation layer. Ensure that the protective layer is dry and solidified to play its protective role. Evenly apply the waterproof and dustproof material on the weather-resistant protective layer to form a smooth and impermeable surface layer. Wait for the surface layer to dry and solidify before inspecting and cleaning.
[0096] Specifically, during the construction of the weatherproof protective layer and the waterproof and dustproof surface layer, weatherproof protective materials should be selected according to local climatic conditions. If the local ultraviolet radiation is strong, weatherproof protective materials with high ultraviolet absorption capacity should be selected, such as acrylic materials containing special ultraviolet absorbers. When selecting waterproof and dustproof materials, consider their compatibility with weatherproof protective materials and conduct compatibility tests to ensure that no chemical reaction occurs between the two.
[0097] Furthermore, by setting up a weather-resistant protective layer and a waterproof and dustproof surface layer, and selecting materials with excellent weather resistance and waterproof performance, it is ensured that the exterior wall decoration can maintain a good appearance and performance under various climatic conditions. This has the characteristics of improving the overall durability of the building exterior wall and reducing maintenance costs.
[0098] By setting steps one to five, in the construction of simulated stone exterior wall decoration, not only the quality and durability of the decoration are improved, but also the construction efficiency and environmental friendliness are improved, while maintaining cost-effectiveness, thereby achieving the effect of meeting the needs of modern buildings for high-performance exterior wall decoration.
[0099] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A method for decorating an exterior wall of simulated stone, characterized in that: The following steps are involved: Step 1: Clean the base construction, remove dust, oil and debris, check the flatness and strength of the base, ensure that the base is dry, select a suitable base treatment material, apply it evenly on the base, and ensure that the base treatment layer is dry and solidified; Step 2: Construction of fiber reinforcement layer and environmentally friendly adhesive layer: select high-quality reinforced fiber mesh cloth anti-cracking material, lay it on the base treatment layer, ensure that there are no wrinkles and bubbles, and use environmentally friendly adhesive material to stick it on the base layer; Step 3: Construction of natural stone powder base layer: prepare natural stone powder and resin raw materials, mix them evenly according to the mix ratio, lay them on the reinforced fiber layer, and use automatic coating equipment to coat the mixed materials on the fiber reinforcement layer and the environmentally friendly bonding layer to form a base layer. Use vibration and pressing processes to ensure that the base layer is dense and void-free, and reaches the required thickness and flatness; Step 4: Construction of color adjustment layer and texture simulation layer. Select appropriate inorganic pigments or color pastes for color adjustment according to design requirements, conduct appearance inspection to ensure uniform color, realistic texture, no bubbles and cracks, and conduct performance tests. Apply pigments or color pastes evenly on the base layer, or use spray painting or embossing technology to form texture effects. Step 5. Construction of weather-resistant protective layer and waterproof and dustproof surface layer. Select suitable weather-resistant protective material and evenly apply the weather-resistant protective material on the color adjustment and texture simulation layer. Ensure that the protective layer is dry and solidified to play its protective role. Evenly apply the waterproof and dustproof material on the weather-resistant protective layer to form a smooth and impermeable surface layer. Wait for the surface layer to dry and solidify before inspecting and cleaning.
2. The method for decorating an exterior wall of simulated stone according to claim 1, characterized in that: During the construction of the clean base in step 1, a level is used to accurately measure and check the flatness of the base, and the error is controlled within ±3mm; and a rebound hammer is used to perform multi-point testing to detect the strength to ensure that the strength of the base concrete reaches more than 90% of the design standard; Step 2: During the construction of the fiber reinforcement layer and the environmentally friendly bonding layer, different specifications of reinforced fiber mesh cloth are selected according to the size and stress conditions of the exterior wall; Step 4: During the construction of the color adjustment layer and texture simulation layer, a small area sample test is carried out before construction, and the color changes are observed after being exposed to the natural environment for a period of time.
3. The method for decorating an exterior wall of simulated stone according to claim 1, characterized in that: The automatic coating device comprises a movable base (1), a movable wheel group (2) is arranged on the lower surface of the movable base (1), and a plurality of movable wheel groups (2) are evenly distributed on the lower surface of the movable base (1); A PLC controller (3) is fixedly mounted on the upper surface of the mobile base (1); a fixed gantry (4) is fixedly connected to the upper surface of the mobile base (1); a fixed support seat (5) is fixedly connected to the upper surface of the fixed gantry (4); a load-bearing shaft (6) is fixedly connected to the surface of the fixed support seat (5); two ends of the load-bearing shaft (6) penetrate and extend to the two side surfaces of the fixed support seat (5); and two ends of the load-bearing shaft (6) are rotatably connected to load-bearing pulleys (7) via bearings.
4. A method for decorating an exterior wall of simulated stone according to claim 3, characterized in that: A winding support seat (8) is fixedly mounted on the upper surface of the mobile base (1), and a steel cable winding wheel (9) is rotatably connected to the surface of the winding support seat (8) via a bearing. The two winding support seats (8) are symmetrically distributed with the axis of the steel cable winding wheel (9) as the center, and a winding reduction motor (10) electrically connected to the PLC controller (3) via a cable is fixedly mounted on the surface of one of the winding support seats (8), and a reduction output end of the winding reduction motor (10) is fixedly connected to one end of the steel cable winding wheel (9); The surface of the cable reel (9) is wound with two symmetrical hoisting cables (11), and the two hoisting cables (11) are respectively slidably connected to the surfaces of the two load-bearing pulleys (7), and one end of the hoisting cable (11) passes through the upper surface of the fixed gantry (4) and extends to the inner wall of the fixed gantry (4).
5. The method for decorating an exterior wall of simulated stone according to claim 4, characterized in that: One end of the lifting steel cable (11) is fixedly connected to a lifting mounting seat (12), and a plurality of symmetrically distributed guide wheels (13) are fixedly installed on both side surfaces of the lifting mounting seat (12), and the plurality of guide wheels (13) are rotatably connected to the two side surfaces of the lifting mounting seat (12) via bearings; The inner walls on both sides of the fixed gantry (4) are provided with guide slots (14) adapted to the guide wheels (13), and the surfaces of the guide wheels (13) are slidably connected to the inner walls of the guide slots (14); A load-bearing support beam (15) is fixedly connected to the surface of the lifting installation seat (12), and the two load-bearing support beams (15) are symmetrically distributed with the axis of the lifting installation seat (12) as the center; A reinforcing rib is fixedly connected to the upper surface of the load-bearing support beam (15), one end of the reinforcing rib is fixedly connected to the surface of the lifting mounting seat (12), and one end of the load-bearing support beam (15) away from the lifting mounting seat (12) is fixedly connected to a reinforcing cross beam.
6. The method for decorating an exterior wall of simulated stone according to claim 5, characterized in that: The inner wall of the load-bearing support beam (15) is slidably connected to a movable mounting frame (16), and a plurality of symmetrically distributed supporting wheels (17) are fixedly mounted on both side surfaces of the movable mounting frame (16), and a limiting sliding groove (18) adapted to the supporting wheel (17) is provided on the inner wall of the load-bearing support beam (15), and the surface of the supporting wheel (17) is slidably connected to the inner wall of the limiting sliding groove (18); A servo electric cylinder (19) electrically connected to the PLC controller (3) via a cable is fixedly mounted on the surface of the lifting mounting seat (12), and one end of the servo electric cylinder (19) is fixedly connected to the surface of the movable mounting frame (16); A connecting crossbeam (20) is fixedly connected to the lower surface of the mobile mounting frame (16), and a plurality of the connecting crossbeams (20) are evenly distributed on the lower surface of the mobile mounting frame (16). A working beam (21) is fixedly connected to the upper surface of the mobile mounting frame (16), and two working beams (21) are symmetrically distributed with the axis of the connecting crossbeam (20) as the center.
7. The method for decorating an exterior wall of simulated stone according to claim 6, characterized in that: The upper surface of the working beam (21) is fixedly connected to a mixing box (22), the surface of the mixing box (22) is fixedly connected to a pressurizing connection block (23), the surface of the pressurizing connection block (23) is fixedly connected to a discharge pressurizing frame (24), the inner wall of the discharge pressurizing frame (24) is trapezoidal, and the surface of the discharge pressurizing frame (24) is fixedly connected to a coating frame (25); A discharge cavity is provided on the surface of the pressurizing connection block (23), and the inner walls of the plurality of discharge cavities are respectively fixedly connected to the inner wall of the mixing box (22) and the inner wall of the discharge pressurizing frame (24), and the inner wall of the discharge cavity is circular in shape; The inner wall of the discharge chamber is sleeved with an extrusion shaft (26), one end of each of the extrusion shafts (26) passes through and extends to a side surface of the mixing box (22), the surface of the extrusion shaft (26) is rotatably connected to the inner wall of the mixing box (22) via a bearing, the surface of the extrusion shaft (26) is fixedly connected with an extrusion spiral blade (27), the surface of the extrusion spiral blade (27) is adapted to be slidably connected to the inner wall of the discharge chamber, and one end of the extrusion spiral blade (27) extends to the interior of the mixing box (22).
8. The method for decorating an exterior wall using simulated stone according to claim 7, characterized in that: A first transmission sprocket (28) and a second transmission sprocket (29) are fixedly mounted on the surface of the extrusion shaft (26), and a plurality of the extrusion shafts (26) are connected to each other through the first transmission sprocket (28) and the second transmission sprocket (29) in a chain-coordinated transmission manner. A discharge reduction motor (30) electrically connected to the PLC controller (3) through a cable is fixedly mounted on the surface of the mixing box (22), and a reduction output end of the discharge reduction motor (30) is fixedly connected to one end of one of the extrusion shafts (26); A sealed extrusion hopper is fixedly connected to the inner wall of one side of the mixing box (22) close to the discharge reduction motor (30), and the surface of the sealed extrusion hopper (31) is slidably connected to one end of the extrusion spiral blade (27).
9. The method for decorating an exterior wall of simulated stone according to claim 8, characterized in that: A vibration pressure plate (32) is fixedly sleeved on the surface of the coating frame (25), and a rubber sealing strip (33) with a U-shaped surface is fixedly connected to the surface of the vibration pressure plate (32); A vibration motor (34) electrically connected to the PLC controller (3) via a cable is fixedly mounted on a surface of one side of the vibration plate (32) close to the mixing box (22), and a plurality of the vibration motors (34) are evenly distributed on the surface of the vibration plate (32).
10. The method for decorating an exterior wall of simulated stone according to claim 9, characterized in that: A vibration pressure auxiliary column (35) is fixedly connected to the surface of one side of the vibration pressure plate (32) close to the mixing box (22), and the two vibration pressure auxiliary columns (35) are symmetrically distributed with the axis of the vibration pressure plate (32) as the center. One end of the vibration pressure auxiliary column (35) is fixedly connected to a first positioning rod (36), and the surface of the first positioning rod (36) is sleeved with a support spring (37) with one end fixedly connected to one end of the vibration pressure auxiliary column (35). The other end of the support spring (37) is fixedly connected to a support column (38), one end of the support column (38) is fixedly connected to the lower surface of the working beam (21), and the other end of the support column (38) is fixedly connected to a second positioning rod (39), and the surface of the second positioning rod (39) is sleeved with the inner wall of the support spring (37).