Cross-station operation method and system of centralized control five-prevention system, equipment and storage medium
By generating cross-site operation task sequences in the five defense system and performing anti-error logic verification, the problem of long cross-site operation processes in the existing technology is solved, and the five defense main stations are issued in one invoice and strictly executed operation items in order. The effect improves operational efficiency.
Patent Information
- Application Number
- CN202310984100.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-08-04
- Publication Date
- 2025-02-14
AI Technical Summary
During cross-site operation, the existing five-defense system cannot achieve cross-site operation in one operation ticket due to the different interfaces of computer keys and locks of each sub-site, and the process is lengthy and inefficient.
A cross-site operation method of the centralized control five-defense system is proposed. By generating a cross-site operation task sequence, the operation items are subject to anti-error logic verification, and when the verification is passed, the centralized control five-defense system is controlled in sequence. Perform action items.
It has achieved the time to issue an operation ticket to meet the cross-site error prevention logic requirements at the five defense main station, and the five defense main station strictly executes the operation items in sequence to ensure the correct execution of cross-site operation items and reduce the review pressure of operation and maintenance personnel. , improve operational efficiency.
Smart Images

Figure CN119448533A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of anti-mislocking of operation tasks, and more specifically, to a cross-station operation method and system, device and storage medium of a centralized control five-protection system. Background Art
[0002] In recent years, with the development of automation technology and the increasing demand for unmanned substations, regional power grids with total step-down transformers and several downstream low-voltage substations in new energy, petrochemical, industrial and mining enterprises usually adopt the method of centralizing the substation monitoring system through the optical fiber ring network to the patrol and maintenance center where the electrical and instrumentation team members are located to meet the needs of centralized monitoring and control of the regional power grid. The five-defense system, as an important part of the monitoring system, also sets up a centralized five-defense master station in the patrol and maintenance center, and uses the industry's unified five-defense protocol to access the five-defense substations of each substation, so as to achieve centralized management, unified invoicing, and unified operation of the five-defense system of the main and substations, and improve labor production efficiency.
[0003] However, in actual operation, due to the different manufacturers of the five-defense systems of each substation and product upgrades, the different computer key and lock interfaces of each substation make it impossible to implement cross-station operations in one operation ticket. When cross-station operations are involved, tickets need to be issued and reviewed separately according to the substations, and the process is lengthy: if the cross-station operation ticket involves inter-station locking, it is necessary to wait for the previous substation to complete the operation and refresh the equipment status before the error-proof logic of the operation ticket of the next substation can be satisfied. Only then can the operation ticket of the next substation be issued, and the efficiency of the entire operation process is very low. Moreover, if an operation task needs to switch back and forth between multiple substations, the operation process will be further prolonged.
[0004] The above information disclosed in the Background section is only for enhancement of understanding of the background of the present application and therefore it may contain information that does not constitute the prior art that is already known to a person of ordinary skill in the art. Summary of the invention
[0005] In order to solve at least one of the above problems, the present application proposes a cross-site operation method and system, device and storage medium of a centralized control five-defense system.
[0006] According to the first aspect of the present application, at least one embodiment of the present application provides a cross-site operation method for a centralized control and five-defense system, the cross-site operation method comprising: generating a cross-site operation task sequence; performing anti-error logic verification on the operation items in the cross-site operation task sequence; and controlling the centralized control and five-defense system to execute the operation items in sequence according to the cross-site operation task sequence when the operation items in the cross-site operation task sequence pass the anti-error logic verification.
[0007] For example, in some embodiments of the present application, the error-proof logic check of the operation items in the cross-site operation task sequence includes: controlling the five-defense master station of the centralized control five-defense system to verify the operation items in the cross-site operation task sequence; controlling each five-defense substation of the centralized control five-defense system to verify the operation items in the cross-site operation task sequence that need to be executed by the five-defense substation.
[0008] For example, in some embodiments of the present application, it also includes: when the operation items in the cross-site operation task sequence pass the anti-error logic check, the operation items that need to be executed by each five-defense substation in the cross-site operation task sequence are classified into operation item sets of each five-defense substation.
[0009] For example, in some embodiments of the present application, controlling each five-defense substation in the centralized control five-defense system to execute the operation items in sequence according to the cross-station operation task sequence includes: each five-defense substation or five-defense main station adopts remote control operation and / or on-site operation to execute the operation items in sequence.
[0010] For example, in some embodiments of the present application, the remote control operation method includes: allowing the monitoring system corresponding to the five-defense substation or the five-defense main station to remotely operate the remotely controllable items in the operation items one by one.
[0011] For example, in some embodiments of the present application, the on-site operation method includes: configuring the operation items that need to be executed by each five-defense substation to the key of the corresponding five-defense substation; or configuring all operation items that need to be executed to the key of the five-defense main station; wherein the key is the execution carrier of the operation items that need to be executed in the cross-station operation task sequence.
[0012] For example, in some embodiments of the present application, the operation items of the cross-site operation task sequence include operation items for the primary equipment and the secondary equipment in each of the five-defense substations.
[0013] According to a third aspect of the present application, at least one embodiment of the present application provides a cross-site operating system for a centralized control five-defense system, characterized in that the cross-site operating system is used to execute the cross-site operation method as described in any one of the first aspects, and the cross-site operating system includes:
[0014] An operation task sequence generation unit is used to generate a cross-site operation task sequence; an anti-error logic verification unit is used to perform an anti-error logic verification on the operation items of the cross-site operation task sequence; and an operation item execution unit is used to control the centralized control five-defense system to execute the operation items in sequence according to the cross-site operation task sequence when the cross-site operation task sequence passes the anti-error logic verification.
[0015] According to a third aspect of the present application, at least one embodiment of the present application provides an electronic device, including:
[0016] one or more processors; and
[0017] A memory for storing one or more programs;
[0018] When the one or more programs are executed by the one or more processors, the one or more processors execute the method as described in any one of the first aspects.
[0019] According to a fourth aspect of the present application, at least one embodiment of the present application provides a computer-readable storage medium having a computer program stored thereon, wherein when the program is executed by a processor, the method described in any one of the first aspects is implemented.
[0020] The cross-station operation method of the centralized control five-defense system provided in this application enables operation and maintenance personnel to issue an operation ticket that meets the cross-station error prevention logic requirements at the five-defense master station at one time when performing cross-station operation tasks, and the five-defense master station controls the operation items to be strictly executed in sequence to ensure the correct execution of the cross-station operation items. At the same time, it avoids issuing and reviewing multiple stations separately, reduces the pressure of process review on operation and maintenance personnel on duty, and improves operation efficiency.
[0021] It should be understood that the foregoing general description and the following detailed description are exemplary only and are not restrictive of the present application. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] By describing in detail exemplary embodiments thereof with reference to the accompanying drawings, the above and other objects, features and advantages of the present application will become more apparent. The accompanying drawings described below are only some embodiments of the present application, and are not intended to limit the present application.
[0023] Figure 1 A flow chart showing a cross-site operation method of a centralized control five-defense system according to an exemplary embodiment;
[0024] Figure 2 A schematic diagram of a centralized control five-defense system is shown according to an exemplary embodiment;
[0025] Figure 3 A schematic diagram showing the cross-site operation method of the centralized control five-defense system in this application;
[0026] Figure 4 A schematic diagram showing the cross-site operation method of the centralized control five-defense system in this application;
[0027] Figure 5 A schematic diagram of a cross-station operating system for a centralized control five-defense system is shown according to an exemplary embodiment;
[0028] Figure 6A structural diagram of an electronic device provided by the present application is shown. DETAILED DESCRIPTION
[0029] Example embodiments will now be described more fully with reference to the accompanying drawings. However, example embodiments can be implemented in many forms and should not be construed as limited to the embodiments set forth herein; rather, these embodiments are provided so that this application will be comprehensive and complete and will fully convey the concepts of the example embodiments to those skilled in the art. The same reference numerals in the figures represent the same or similar parts, and thus their repeated description will be omitted.
[0030] The described features, structures or characteristics may be combined in one or more embodiments in any suitable manner. In the following description, many specific details are provided to provide a full understanding of the embodiments of the present disclosure. However, those skilled in the art will appreciate that the technical solutions of the present disclosure may be practiced without one or more of these specific details, or other modes, components, materials, devices, etc. may be adopted. In these cases, known structures, methods, devices, implementations, materials or operations will not be shown or described in detail.
[0031] The flowcharts shown in the accompanying drawings are only exemplary and do not necessarily include all the contents and operations or steps, nor do they have to be executed in the order described. For example, some operations or steps can be decomposed, and some operations or steps can be combined or partially combined, so the actual execution order may change according to actual conditions.
[0032] The terms "first", "second", etc. in the specification and claims of this application and the above-mentioned drawings are used to distinguish different objects, rather than to describe a specific order. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions. For example, a process, method, system, product or device that includes a series of steps or units is not limited to the listed steps or units, but optionally includes steps or units that are not listed, or optionally includes other steps or units inherent to these processes, methods, products or devices.
[0033] Those skilled in the art will appreciate that the drawings are merely schematic diagrams of example embodiments, and the modules or processes in the drawings are not necessarily necessary for implementing the present application, and therefore cannot be used to limit the scope of protection of the present application.
[0034] Figure 1 A flow chart of a cross-site operation method of a centralized control five-defense system is shown according to an exemplary embodiment.
[0035] like Figure 1 As shown, the cross-site operation method of the centralized control five-defense system includes steps S101 to S103.
[0036] like Figure 2 As shown, the centralized control five-defense system includes a five-defense master station and multiple five-defense substations 1-five-defense substations N. The five-defense master station includes a monitoring system and a five-defense system. The five-defense system includes a five-defense server and an operator station. The five-defense server is connected to the operator station. Each substation includes a five-defense substation, a monitoring system and a key base. Each five-defense substation is connected to the five-defense server.
[0037] In step S101, a cross-site operation task sequence is generated.
[0038] According to an example embodiment, based on the operation and maintenance requirements and the operating specifications of the equipment, the operation and maintenance personnel use the five-defense master station to generate a cross-site operation task sequence, which is stored in the five-defense server as an unreviewed ticket after being generated.
[0039] In step S102, an error-prevention logic check is performed on the operation items in the cross-site operation task sequence.
[0040] According to the example embodiment, after the five-defense server and the five-defense substation of the five-defense master station obtain the cross-station operation task sequence, it is necessary to perform an error prevention logic check to prevent the occurrence of an operation task sequence that violates the error prevention logic.
[0041] The anti-error logic check is verified separately by the five-defense master station and the five-defense substations involved: the five-defense master station of the centralized control five-defense system verifies all operation items in the cross-station operation task sequence, and each five-defense substation of the centralized control five-defense system only verifies the operation items that need to be executed by the equipment within the scope of the five-defense substation. If both are verified and passed, the anti-error logic check is considered to have passed.
[0042] According to the exemplary embodiment, if the verification is passed, the process goes to step S103. If the verification is not passed, the centralized control five-defense system prompts the error type and prohibits the execution of the operation item.
[0043] According to some embodiments, the five-defense server confirms whether each operation item in the cross-site operation task sequence has the operation authority.
[0044] According to some embodiments, the operation items of the cross-site operation task sequence include operation items for the primary equipment and the secondary equipment in each of the five-defense substations.
[0045] In step S103, when the operation items in the cross-site operation task sequence pass the error prevention logic check, the centralized control five-defense system is controlled to execute the operation items in sequence according to the cross-site operation task sequence.
[0046] According to an exemplary embodiment, when the operation items in the cross-station operation task sequence pass the error prevention logic check, each of the five-defense substations is controlled to execute the operation items in sequence according to the order of the cross-station operation task sequence.
[0047] According to some embodiments, when the operation items in the cross-site operation task sequence pass the anti-error logic check, the cross-site operation method also includes classifying the operation items that need to be executed by each five-defense substation in the cross-site operation task sequence into operation item sets of each five-defense substation.
[0048] According to the example embodiment, when the cross-site operation task sequence passes the anti-error logic check, that is, the un-inspected anti-error logic check passes, and after the operation and maintenance personnel review and determine that it has been inspected, the operation items of the cross-site operation task sequence that needs to be executed by each five-defense substation are downloaded to the corresponding five-defense substation through the operator station, or the operation items of the cross-site operation task sequence that needs to be executed by each five-defense substation are saved in the five-defense main station.
[0049] According to some embodiments, when each operation item is executed, the operation and maintenance personnel can switch the execution mode of the operation item to a remote control operation mode or an on-site operation mode according to needs and on-site conditions.
[0050] For example, when the remote control operation mode is adopted, the monitoring system corresponding to the five-defense substation or the five-defense main station is allowed to perform remote control operation item by item to complete the corresponding operation items.
[0051] For another example, when the local operation mode is adopted, the operation items to be executed by each five-defense substation are configured on the key of the corresponding five-defense substation, and the local operation is performed at the five-defense substation. Alternatively, the five-defense master station configures all the operation items to be executed on the key of the five-defense master station, and the local operation is performed at the five-defense master station. Among them, the key is the execution carrier of the operation items to be executed in the cross-station operation task sequence.
[0052] According to some embodiments, when the keys or locks of the five-defense substations have different interfaces, the number of keys of the five-defense main station can be multiple, and they correspond one to one with the keys of the five-defense substations. The corresponding keys are configured according to the operation items that need to be executed by each five-defense substation. If the key unlocking interfaces used for on-site operation of the five-defense substation 1 and the five-defense substation 2 are different, the operation items need to be downloaded to the corresponding two computer keys respectively, but the five-defense main station only allows one of them to operate at the same time.
[0053] For example, the centralized control five-defense system includes two five-defense substations 1 and five-defense substation 2. The cross-station operation task sequence includes 7 operation items, which are five-defense substation 1 executing operation item 1, operation item 2 and operation item 3; five-defense substation 2 executing operation item 4 and operation item 5; and five-defense substation 1 executing operation item 6 and operation item 7. When the five-defense master station sequentially performs anti-error logic check on operation items 1-7 in the cross-station operation task sequence, five-defense substation 1 performs anti-error logic check on operation items 1-3, and five-defense substation 2 performs anti-error logic check on operation items 4 and operation items 5, and then five-defense substation 1 performs anti-error logic check on operation items 6 and operation items 7. After all operation items 1-7 pass the anti-error logic check, the operation item set of five-defense substation 1 is generated, including operation items 1, 2, 3, 6, and 7; and the operation item set of five-defense substation 2 is generated, including operation items 4 and 5.
[0054] like Figure 3 As shown, the operation and maintenance personnel choose to start and execute the operation task at the operator station of the five-defense main station according to their operating habits. After the task is started, it starts from the first operation item, and sequentially completes the operation items 1, 2, and 3 that can be executed by the five-defense substation 1, and then starts to execute the operation items 4 and 5 that can be executed by the five-defense substation 2, and then executes the operation items 6 and 7 that can be executed by the five-defense substation 1, until all the operation items are executed or the operation is ended. Specifically for the operation of the five-defense substation 1 and the five-defense substation 2, you can choose to remotely operate the monitoring system of the five-defense main station according to the equipment status and operating habits, or download the operation items that need to be executed by the five-defense substation 1 and the five-defense substation 2 to the key configured in the five-defense main station for on-site operation.
[0055] According to some embodiments, if the unlocking interfaces of the keys used for on-site operation of the five-defense substation 1 and the five-defense substation 2 are different, the operation items need to be downloaded to two keys respectively, but only one of them is allowed to operate at the same time.
[0056] like Figure 4As shown, the operation and maintenance personnel choose to split the task and send it to the corresponding five-defense substation according to their operation habits and start to execute the operation task. After the task is started, the server of the five-defense main station enables the operation authority of substation 1 where operation item 1 is located. The operation and maintenance personnel go to five-defense substation 1 and start to execute the operation items from five-defense substation 1, and then complete the operation items 2 and 3 that can be executed by five-defense substation 1 in sequence. Then the server of the five-defense main station transfers the operation authority to five-defense substation 2 where the subsequent operation items are located, and the operation and maintenance personnel go to five-defense substation 2 to start to execute five-defense substation 2 operation items 4 and 5. Then the server of the five-defense main station transfers the operation authority to five-defense substation 1 where the subsequent operation items are located, and the operation and maintenance personnel go to five-defense substation 1 to start to execute five-defense substation 1 operation items 6 and 7 until all operation items are executed or the operation is ended. Specifically in the operation of the five-defense substation 1 and the five-defense substation 2, you can choose to remotely operate by the monitoring system of the five-defense substation or download the key to the five-defense substation for on-site operation according to the equipment status and operating habits, that is, the operation items that need to be executed by the five-defense substation 1 are configured to the corresponding key of the five-defense substation 1, and the operation items that need to be executed by the five-defense substation 2 are configured to the corresponding key of the five-defense substation 2.
[0057] The present application provides a method for cross-station operation of a centralized control five-defense system, which enables operation and maintenance personnel to issue an operation ticket that meets the cross-station error prevention logic requirements at the five-defense master station at one time when performing cross-station operation tasks, and the five-defense master station controls the operation items to be strictly executed in sequence to ensure the correct execution of the cross-station operation items. At the same time, it avoids issuing and reviewing multiple stations separately, reduces the pressure of process review on operation and maintenance personnel on duty, and improves operation efficiency.
[0058] Figure 5 A schematic diagram of a cross-site operating system for centralized control of a five-defense system is shown according to an exemplary embodiment.
[0059] like Figure 5 As shown, the cross-site operating system includes an operation task sequence generating unit 501 , an error prevention logic checking unit 502 and an operation item executing unit 503 .
[0060] The operation task sequence generating unit 501 is used to generate a cross-site operation task sequence.
[0061] The error prevention logic checking unit 502 is used to perform error prevention logic checking on the operation items of the cross-site operation task sequence.
[0062] The operation item execution unit 503 is used to execute the operation items in sequence according to the cross-site operation task sequence when the cross-site operation task sequence passes the error prevention logic check.
[0063] According to an exemplary embodiment, the cross-site operating system is used to execute the cross-site operating method as described above, so the operating method of the cross-site operating system will not be described in detail herein.
[0064] Figure 6A structural diagram of an electronic device provided by the present application is shown.
[0065] See also Figure 6 , Figure 6 An electronic device is provided, comprising a processor and a memory. The memory stores computer instructions. When the computer instructions are executed by the processor, the processor executes the computer instructions to achieve the following Figure 1 The method and refinement scheme shown.
[0066] It should be understood that the above-mentioned device embodiments are only illustrative, and the device disclosed in the present application can also be implemented in other ways. For example, the division of units or modules in the above-mentioned embodiments is only a logical function division, and there may be other division methods in actual implementation. For example, multiple units, modules or components can be combined, or can be integrated into another system, or some features can be ignored or not executed.
[0067] In addition, unless otherwise specified, each functional unit or module in each embodiment of the present application may be integrated into one unit or module, or each unit or module may exist physically separately, or two or more units or modules may be integrated together. The above-mentioned integrated unit or module may be implemented in the form of hardware or in the form of a software program module.
[0068] If the integrated unit or module is implemented in the form of hardware, the hardware may be a digital circuit, an analog circuit, etc. The physical implementation of the hardware structure includes but is not limited to transistors, memristors, etc. Unless otherwise specified, the processor or chip may be any appropriate hardware processor, such as CPU, GPU, FPGA, DSP, and ASIC, etc. Unless otherwise specified, the on-chip cache, off-chip memory, and storage may be any appropriate magnetic storage medium or magneto-optical storage medium, such as Resistive Random Access Memory (RRAM), Dynamic Random Access Memory (DRAM), Static Random Access Memory (SRAM), Enhanced Dynamic Random Access Memory (EDRAM), High-Bandwidth Memory (HBM), Hybrid Memory Cube (HMC), etc.
[0069] If the integrated unit or module is implemented in the form of a software program module and sold or used as an independent product, it can be stored in a computer-readable memory. Based on this understanding, the technical solution of the present application, in essence, or the part that contributes to the prior art or all or part of the technical solution can be embodied in the form of a software product, and the computer software product is stored in a memory, including a number of instructions to enable a computer device (which can be a personal computer, server or network device, etc.) to perform all or part of the steps of the various embodiments of the present disclosure. The aforementioned memory includes: U disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), mobile hard disk, disk or optical disk and other media that can store program codes.
[0070] The present application also provides a non-transitory computer storage medium storing a computer program. When the computer program is executed by multiple processors, the processors execute the following Figure 1 The method and refinement scheme shown.
[0071] It should be clearly understood that the present application describes how to form and use specific examples, but the present application is not limited to any details of these examples. On the contrary, based on the teaching of the content disclosed in the present application, these principles can be applied to many other embodiments.
[0072] In addition, it should be noted that the above figures are only schematic illustrations of the processes included in the method according to the exemplary embodiments of the present application, and are not intended to be limiting. It is easy to understand that the processes shown in the above figures do not indicate or limit the time sequence of these processes. In addition, it is also easy to understand that these processes can be performed synchronously or asynchronously, for example, in multiple modules.
[0073] The exemplary embodiments of the present application are specifically shown and described above. It should be understood that the present application is not limited to the detailed structures, configurations or implementations described herein; on the contrary, the present application is intended to cover various modifications and equivalent configurations included in the spirit and scope of the appended claims.
Claims
1. A cross-site operation method for a centralized control five-defense system, characterized in that: The cross-site operation method comprises: Generate cross-site operation task sequences; Performing error-proof logic check on the operation items in the cross-site operation task sequence; When the operation items in the cross-site operation task sequence pass the error prevention logic check, the centralized control five-protection system is controlled to execute the operation items in sequence according to the cross-site operation task sequence.
2. The cross-site operation method according to claim 1, characterized in that: The performing error-proof logic checking on the operation items in the cross-site operation task sequence includes: Controlling the five-defense master station of the centralized control five-defense system to verify the operation items in the cross-station operation task sequence; Control each five-defense substation of the centralized control five-defense system to verify the operation items in the cross-station operation task sequence that need to be executed by the five-defense substation.
3. The cross-site operation method according to claim 1, characterized in that: Also includes: When the operation items in the cross-station operation task sequence pass the error prevention logic check, the operation items that need to be executed by each five-defense substation in the cross-station operation task sequence are respectively classified into operation item sets of each five-defense substation.
4. The cross-site operation method according to claim 1, characterized in that: The controlling the centralized control five-defense system to sequentially execute the operation items according to the cross-site operation task sequence includes: Each five-defense substation or five-defense main station uses a remote control operation mode and / or a local operation mode to execute the operation items in sequence.
5. The cross-site operation method according to claim 4, characterized in that: The remote control operation method includes: The monitoring system corresponding to the five-defense substation or the five-defense main station is allowed to remotely control the remotely controllable items in the operation items one by one.
6. The cross-site operation method according to claim 4, characterized in that: The on-site operation method includes: Assign the operation items that need to be executed by each five-defense substation to the key of the corresponding five-defense substation; or All operations that need to be performed are configured on the key of the five-defense master station; Among them, the key is the execution carrier of the operation items that need to be executed in the cross-site operation task sequence.
7. The cross-site operation method according to claim 1, characterized in that: The operation items of the cross-station operation task sequence include operation items for the primary equipment and the secondary equipment in each five-defense substation.
8. A cross-site operating system for centralized control of five-defense system, characterized in that: The cross-site operating system is used to execute the cross-site operation method according to any one of claims 1 to 7, and the cross-site operating system includes: An operation task sequence generating unit, used for generating a cross-site operation task sequence; an error-proofing logic checking unit, used for performing an error-proofing logic checking on the operation items of the cross-station operation task sequence; and The operation item execution unit is used to control the centralized control five-defense system to execute the operation items in sequence according to the cross-site operation task sequence when the cross-site operation task sequence passes the anti-error logic check.
9. An electronic device, characterized in that: include: one or more processors; as well as A memory for storing one or more programs; When the one or more programs are executed by the one or more processors, the one or more processors execute the method according to any one of claims 1 to 7.
10. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the program is executed by a processor, the method according to any one of claims 1 to 7 is implemented.